Anda di halaman 1dari 22

Prestress Losses in

Continuous Composite
Bridges
Mohamed H. Soliman
Research Assistant
Department of Civil Engineering
University of Windsor
Windsor, Ontario, Canada

John B. Kennedy
Professor
Department of Civil Engineering
University of Windsor
Windsor, Ontario, Canada

D uring the last 30 years composite con-


struction of concrete slab-on-steel gir-
ders has been widely used to form the
vicinity of the intermediate supports of con-
tinuous bridges as shown in Fig. 2(a). A re-
cent study 2 has shown that such prestressing
superstructure of bridges. Generally, such increases substantially the cracking load in
construction has been applied only to sim- addition to the stiffness of such bridges.
ple spans or to the sagging moment regions For proper design it is essential to esti-
of continuous spans since transverse cracks mate accurately the anticipated losses in the
will inevitably develop in the region of in- prestressing force due to creep, shrinkage
termediate supports. and steel relaxation.'`' The objective of this
Such transverse cracking, caused by the paper is to propose a simple method to-
presence of large negative (hogging) mo- gether with design aids by which these long-
ments, reduces significantly the stiffness of term losses can be reliably estimated. The
the bridge and leads to costly maintenance. results from this simple method are com-
Moreover, even in the case of simple span pared to those from an elaborate method of
bridges, extensive damage to the expansion solution requiring the use of a computer.
joints can occur due to seepage of deicing In this paper it is assumed that prestress-
salt-laden water. Fig. 1 shows an example ing of the concrete deck is carried out on
of such damage in one of the many expan- the composite sections (with the connection
sion joints on the Gardiner Expressway in between the concrete and steel beams re-
Toronto, Canada. alized prior to prestressing). Previous
Several researchers 1-3 have proposed to experience' has shown that the alternative
prestress part of the concrete deck in the scheme of prestressing a free-to-slide con-

84
crete deck can lead to problems not only in
construction but also in bridge mainte- Synopsis
nance. Design aids are developed to esti-
mate the long-term losses in the pres-
tressing force in continuous composite
ANALYTICAL PROCEDURES concrete-on-steel girder bridges. The
prestressed portions of the concrete
Two analytical methods are presented to deck are in the vicinity of the inter-
estimate the losses in the prestressing force mediate supports.
in continuous composite bridges. The first The use of the design aids and ac-
method is an iterative approach requiring counting for the reduced relaxation in
the use of a computer, while the second the prestressing steel are illustrated
method is a one-step explicit solution with with a numerical example. The results
design aids suitable for design office use. are compared to those from an itera-
Both methods are based on well-estab- tive method of solution requiring a
lished principles used by other inves- computer.
tigators3,4.6- s and are dependent on the
following assumptions: plane sections re-
main plane after any change in the stresses;
curvature and axial strain at any cross sec-
tion of the bridge can be related to the ap- in which
plied forces. i, j = time interval number; when
used with time-dependent
parameters they indicate time
Iterative Method at the middle of intervals i, j,
In this method, time is divided into in- respectively
tervals the length of which is assumed to
increase with tine;"" each interval such as
t is subdivided into t '2, t and tj.f1/ 2 , i.e.,
a beginning, middle and end of interval j,
as shown in Fig. 3. Any stress variation is
assumed to take place at the midpoint of the
interval, while the creep and shrinkage
strains as well as the relaxation stress of the
prestressing steel are determined at the be-
ginning and end of the interval.
During any interval j, the incremental
axial strain, AE., and the incremental cur-
vature, AK, , can be expressed, respectively,
.1 4
as :

Deg = —a (1 + 4J *'12J) +
A
1 AN.
E ` (^,+ v2.. – ; ii2.) +
A€ ,, h . (1)
A

.AM
AK = (1 + ^^+u2,,) +

Fig. 1. Damage at one of the expansion


-1 AM
( 4',+v2., – 4;- "2. ) (2)
joints in the Gardiner Expressway in
E .I z Toronto (Courtesy of A. Tork)

PCI JOURNAL/January-February 1986 85


AN,, = change in axial force on the I, = moment of inertia of concrete
concrete, N _ deck about its own neutral axis
D& , hj = incremental axial shrinkage •j+I/2., = creep coefficient at the end of
strain the jth interval for stress ap-
A "= effective area of concrete deck plied at the middle of the ith

Transverse cracks

(a) Composite Concrete deck-on-steel girder


Bridge - Reinforced concrete deck

Non-prestressed Prestressed deck


deck Np ` Np

(b) Composite Concrete deck-on-steel girder


Bridge - Part of deck prestressed

Centroid of
Reinforcing steel
p y =o
Prestressing tendon

Concrete deck

do
J
ys _ _ N.A. of Composite
Sectio
of steel girder

(c) Cross-section

Fig. 2. Geometry of a continuous two-span composite bridge showing a longitudinal


section with (a) cracked reinforced concrete deck, (b) uncracked prestressed concrete
deck and its cross section in (c).

86
N

Time
1-I/2 I 1+1/2 J-1/2 J
+y2

Fig. 3. Definition of the time interval used in the iterative method of solution.

interval deck.
OM, = change in moment M carried 5. Compatibility of strains at the center
by the concrete deck of gravity of the prestressing steel in the
E ,= modulus of elasticity of con- concrete deck.
crete 6. Compatibility of strains at the center
Using Eqs. (1) and (2) at any time j, six of gravity of the nonprestressed reinforcing
equations can be generated relating the fol- steel in the concrete deck.
lowing unknowns:" changes in the normal These six equations were solved for each
force acting on the concrete deck and on the time interval up to time t = 10,000 days
steel girder, AN, and ANq, respectively; (considered to be infinity) yielding the long-
changes in the induced force in the pre- term losses in the prestressing force. A
stressing steel and in the nonprestressed computer program was written to treat two-
reinforcing steel, ON and ON,,, , respec- span and three-span continuous composite
tively; and, changes in the bending mo- bridges. Values for the concrete creep
ments acting on the concrete deck and the coefficient, 4, and shrinkage strain, es,,,
steel girder, OM,. and OMs, respectively. were based on the recommendations of
The six equations are derived from the ACI Committee 209" and CEB-FIB.18
following conditions: Furthermore, the reduction in the stress re-
1. The suns of the changes in the forces laxation in the prestressing steel was con-
at any section is zero for equilibrium. sidered based on the 1975 PCI recommen-
2. The change in the bending moment at dations. 12
any section is equal to that due to the change The main steps in the computer program
in the prestressing force N. for an analysis by the iterative method are
3. Compatibility of curvature and strain as follows:
at the interface between the steel section 1. Read in the following data: Age of con-
and the concrete deck. crete at the beginning, middle and end of
4. Compatibility of strains at the center each time interval; material properties of
of gravity of the steel section in the concrete steels and concrete (including slump, rela-

PCI JOURNAL/January-February 1986 87


tive humidity, water content, curing pe- in which
riod, etc.); section properties; initial E , = concrete elastic modulus at
prestressing force N„0 and long-term mo- age t
ment due to sustained loading. (, r = creep coefficient at time T
2. Initiate sectional forces, N,^, Ns, NP, N with load applied at concrete
M,, M at time of transfer. age t
3. For each time interval: 6 4.O = concrete shrinkage strain at
(a) Determine the creep coefficient 4) time T
as a function of age of concrete at If the stress is continuously varying with
time of loading and of period of time, then the total strain becomes:
loading.
(b) Compute the shrinkage strain and
convert it to an equivalent normal
E T.r = E (I+4),)+
force N ,,, acting on the concrete deck J
when considering the continuity of r, (1 + 4r.r) afr dt' + e ti^^ (4)
at'
the structure.
(c) Compute the relaxation stress in the The difficulty of continually varying
prestressing steel based on the 1975 stress and concrete characteristics with
PCI recommendation 12 with the in- time is surmounted by the use of the creep
itial steel tendon stress f,, given by: relaxation coefficient introduced first
by Trost' 6 and then refined by Bazant. 6 In
effect, this coefficient accounts for the re-
(N,,, — AN„)IA„
duction in creep deformation at time T =
oo due to continuous change in the applied

where AN,, = 0 at the first time interval (i prestressing force caused by the long-term
= 1). losses.
(d) Based on the six conditional equa- Thus, at time T = , Eq. (4) can be writ-
tions mentioned above formulate ten as:
the matrix equation with the six
unknowns AN, AN ,, AN,,, AN,,,,,
Ex r = (1 + 4k,) +
AM and AM,.
(e) Solve the matrix equation to deter-
f' (1 + 'n 4r) + E.,h(:,
mine the unknowns and in partic- A (5)
ular AN .
4. Print the long-term loss in the pre- Two different 9's are possible'° depend-
stressing steel for each time interval. ing on whether the strain is associated with
Results based on the iterative method us- flexure (q ,,,) or with axial force (i ,). Values
ing the computer program were generated; of q ,,, (or ii„) are obtained from Fig. 4 for
they are discussed in connection with the different values of 4) ,,, (or i„ ) given by:'6
illustrative bridge design example pre-
sented later on.
and
One-Step Method = a ,, 4)_.i
The total strain in the concrete of age T where
and loaded at age t with a stress f , when T
cx =
>> t, can be shown to be:'''fi 1+E,I

EI
f,
E T.r — E (1 + 4)T,) + Esh(Tl
(3) and
r

88
Age at Loading = 10 days
Concrete Age = 10,000days
08

N
Age at Loading = 7 days
0.6 Concrete Age =10,000days

F //
0
0.5

0.4

0 3I,
1 I I 1 I i

0 0.5 1.5 2.5 3.5

0m,n
Fig. 4. Relationship between the flexural and thrust relaxation coefficients q
and creep factor b.

1 N
a=/ hex. = A E fix ' +
A E (1 + ^„ ^__,) + A E (6)
in which
A = area of steel girder and
= modulus of elasticity of steel
+ AM"„ (1 + ^,,, ^_.,) (7)
E
girder .
OK
I, = moment of inertia (about =EL
its own centroid) of steel
girder in which
= distance from centroid of steel N, = initial axial force on concrete
ys
girder to centroid of concrete deck
deck AN + A d<Mer
The coefficients a and a reflect the fact mnA, ml,
that creep is influenced by the restraining M^1 = moment at critical section (see
action of the steel girder, '° ignoring that of Fig. 5) due to long-term loads
the nonprestressed steel in the deck which A, = area of composite section
was shown to be relatively small. Dealing I, = moment of inertia of compos-
only with long-term strains by omitting the ite section
elastic strain in Eq. (5), the changes in m = modular ratio
the strain e and curvature K can be written d = distance from neutral axis of
as: composite section to centroid

PC I JOURNAUJanuary-February 1986 89
NP =D.L±0.3L.L.
N ,—WJt
o Po
(a)
T !

(b)

(c)

ili

(d)

Fig 5. (a) Long-term (It) loading on bridge; bending moment due to


(b) applied prestressing force; (c) w it ; and (d) combined
loading (b) and (c).

of concrete deck AN— = change in axial forces carried


ON- = change in N , at time T = 00 by steel section
N,,, = axial shrinkage force in con- ONE,,, = change in axial forces carried
crete deck assumed to deform by prestressing steel
freely
OM q„ = change in moment carried by
M0 = initial moment resisted by
steel section
concrete deck
AM = change in M,,„ at T = 00 y„ = distance from center of gravity
Results from the iterative solution indi- of prestressing steel to cen-
cated that the effect of nonprestressed steel troid of concrete deck
in the concrete deck is relatively small (less OMet = change in moment at critical
than 0.7 percent) and, therefore, was ig- section (see Fig. 5) due to long-
nored in this analysis in order to arrive at term losses in prestressing
an easy-to-use method of analysis and more force, given by (ON ,, ) k, where
tractable design aids. Thus, applying the A is a continuity factor derived
equilibrium conditions to the changes in the in Appendix A.
forces and in the moments on the composite Such a moment change was ignored in
section yields, respectively: Refs. 7 and 19. It should be remarked that
results from the iterative solution program
ON . +RNs + N = 0.0 (8) showed that the largest prestressing losses
were incurred at the cross sections coincid-
AM , + OM + (AN ,0 )y, (9)
ing with the ends of the prestressed deck(s)
+ (AN ,,) y„ = OMer
due to the presence of a sagging moment.
in which Invoking compatibility of curvature and

90
strains at the interface between the con- from Table 3. The expressions for the factors
crete deck and the steel section, will lead iii, E, C, 'y, p and p., incorporating and
to: ,q ,, , are given in Appendix B.
The numerical values for the factors in
M o
Eq. (13) have been determined for two- and
+ - (1 + i1^, 4 _.^) AM-
EJ three-span continuous composite bridges
(10) having various cross sections (see Tables 1
to 3). For brevity, only a limited number of
N AN
--°(1 + "1„4J) + steel sections were considered. However,
(t, . 7 +
AE values for steel sections not listed in the
AM N
+ N .O, = As tables can be determined by interpolation.
.o,
(11)
E ll s A,E, AsE, The influence of the bending moment car-
ried by the concrete deck (M,.,,) was found
to be relatively insignificant and therefore
11 4_) +
A E fi x•' + A E - (1 + was omitted from Eq. (13).
It should be noted that the results in Ta-
AM .- + N +N (12) bles 1 and 2 are based on a prestressed deck
Ell s ACE, A,,E,, AE of length ranging from 0.21 to 0.351 which
in which is the normal range for this type of construc-
A„ = area of prestressing steel tion, I being the length of one span. For
E , = elastic modulus of prestressing brevity, only the most common concrete deck
steel thicknesses of 8 and 9 in. have been consid-
N „ = prestressing steel relaxation force ered in Tables 1 to 3. However, these re-
at time T =oo sults can be linearly extrapolated for thinner
It should be remarked that the above decks, say 7 in. thick, to give slightly over-
analysis could have been dealt with in terms estimated prestressing losses and, there-
of only two unknowns; however, such a fore, be conservative.
method would perforce require the use of To account for the "reduced" relaxation
one q only since it cannot account for both of the prestressing steel, the value of z, ob-
r) and -q. This would lead to an unneces- tained from Fig. B1, must be reduced by a
sary approximation which was circum- factor a ,. as suggested by Tadros et al` and
vented by the use of the method adopted Dilger. 8 They have shown that a , is a func-
herein. tion of the ratio:
A long-handed solution of Eqs. (8) to (12)
yielded the following explicit expression for H _ Loss due to creep and shrinkage
the long-term losses in the prestressing force Initial prestressing force
at time T = oo:
_ AN,('PIA)
(15)
N,,,,
AN -`i[(1-. - A ) +(I+A)-yp ] N
and the ratio:
°° W(10)3
(13) Initial prestress f
= _ ^ 16
in which Ultimate strength fN,,

N =N , +w (14) Fig. 6 (taken from Ref. 8) gives a , as a


function of fl and (3. Thus, the "reduced" z
to be used in Eq. (13) becomes:
where w = N ,51(fix ) and A zlirN,.
The values of z (without considering the z' = a ,z (17)
"reduced" relaxation of the prestressing steel)
are obtained from Fig. B1 and that for where z is determined from Fig. B1. This

PCI JOURNAUJanuary-February 1986 91


CD
N)

Table 1. Factors to estimate the long-term prestress losses for 8 in. concrete deck.
w x 10" µ
For (A ,/A,m) x 100 =
Relative Section Two Span Three Span
Humidity No. p y (1, 1) (1, 1.21, 1) 0.1 percent 0.2 percent 0.3 percent 0.4 percent 0.5 percent

36 x 300 5.709 1.629 16.009 -3.800 470880. 375732. -118.025 -60.174 -40.891 -31.249 -25.464
36 x 260 5.712 1.735 16.039 -4.411 435395. 346299. -139.457 -71.050 -48.247 -36.846 -30.005
36 x 230 5.798 1.851 16.069 -5.046 405336. 321457. -163.137 -83.052 -56.358 -43.010 -35.002

36 x 210 5.902 1.931 16.101 -5.837 384704. 303237. -187.576 -95.489 -64.794 -49.446 -40.238
36 x 182 5.966 2.099 16.079 -6.759 351480. 276407. -222.873 -113.363 -76.860 -58.609 -47.658
36 x 160 5.999 2.268 16.127 -7.782 322073. 252716. -261.372 -132.868 -90.033 -68.616 -55.766
36 x 135 5.984 2.519 16.150 -9.626 286479. 223890. -324.098 -164.656 -111.509 -84.935 -68.991

33 x 241 5.507 1.802 16.082 -5.121 417091. 330752. -155.180 -79.034 -53.652 -40.961 -33.347
50 percent 33 x 201 5.570 1.985 16.139 -6.249 373631. 295127. -194.372 -98.901 -67.078 -51.166 -41.619

33 x 152 5.748 2.350 16.262 -8.766 311199. 243973. -282.367 -143.498 -97.208 -74.063 -60.176
33 x 130 5.646 2.575 16.222 -10.558 279088. 218144. -337.543 -171.467 -116.108 -88.429 -71.821
33 x 118 5.684 2.760 16.292 -11.940 259688. 202589. -385.312 -195.655 -132.436 -100.826 -81.861

30 x 211 5.161 1.938 16.043 -6.518 385082. 304188. -185.016 -94.163 -63.879 -48.737 -39.651
30 x 173 5.198 2.159 16.260 -8.082 339014. 266855. -236.216 -120.120 -81.422 -62.073 -50.463

30 x 132 5.264 2.551 16.306 -11.447 282341. 220564. -337.703 -171.564 -116.184 -88.494 -71.880
30 x 116 5.287 2.786 16.407 -13.293 256927. 200352. -397.529 -201.856 -136.632 -104.019 -84.452
30 x 99 5.259 3.125 16.441 -16.269 227306. 176804. - 487.100 - 247.207 -167.243 - 127.260 - 103.271

Note: 1. For any section not listed above and falling between any two listed sections (such as WF36 >
factors may be estimated by averaging (e.g., p = (5.709 + 5.712)/2 = 5.7105 for WF36 x 2
2. The values listed are valid only for prestressed deck of length (0.2 to 0.35)1.
Table 1 (cont.) Factors to estimate the long-term prestress losses for 8 in. concrete deck.
w x 10 µ
Relative Section Two Span Three Span
For (k /Am) x 100 =
No. p 0.1 percent 0.2 percent 0.3 percent 0.4 percent 0.5 percent
Humidity 5 y (1, 1) (1, 1.21, 1)

36 x 3(H) 5.599 1.692 14.302 -3.800 427244. 414107. -112.192 -57.133 -38.780 -29.603 -24.098
36 x 260 5.569 1.803 14.332 -4.411 395047. 381667. -132.414 -67.386 -45.711 -34.873 -28.370
36 x 230 5.706 1.938 14,362 -5.046 367774. 354289. - 156.403 -79.526 -53.901 -41.088 -33.400

36 x 210 5.746 2.015 14.393 -5.837 349054. 334208. -178.802 -90.920 -61.626 -46.979 -38.191
36 x 182 5.758 2.183 14.437 -6.759 318909. 304638. -211.763 -107.609 -72.891 -55.532 -45.116
36 x 160 5.721 2.350 14.486 -7.782 292227. 278527. -246.402 -125.157 -84.742 -64.535 -52.411
36 x 135 5.656 2.616 14.405 -9.626 259931. 246756. -303.512 -154.076 -104.264 -79.358 -64.414

33 x 241 5.364 1.875 14.375 -5.121 378439. 364533. -147.556 -75.067 -50.904 -38.823 -31.574
70 percent
33 x 201 5.418 2.073 14.432 -6.249 339007. 325269. -185.270 -94.166 -63.798 -48.614 -39.504

33 x 152 5.410 2.435 14.442 -8.766 282360. 268891. -263.002 -133.551 -90.401 -68.826 -55.881
33 x 130 5.336 2.675 14.477 -10.558 253225. 240425. -316.252 -160.525 -108.616 -82.661 -67.088
33 x 118 5.345 2.869 14.492 -11.940 235623. 223281. -359.635 -182.476 -123.423 -93.896 -76.180

30 x 211 5.062 2.035 14.467 -6.518 349397. 335256. -177.737 -90.359 -61.232 -46.669 -37.931
30 x 173 4.957 2.249 14.440 -8.082 307597. 294110. -221.946 -112.756 -76.359 -58.161 -47.242

30 x 132 4.995 2.649 14.617 -11.447 256176. 243091. -317.727 -161.287 -109.140 -83.067 -67.423
30 x 116 4.972 2.897 14.607 -13.293 233118. 220815. -371.219 -188.351 -127.394 -96.916 -78.630
30 x 99 4.981 :3.255 14.771 -16.269 206241. 194861. -458.917 -232.729 -157.333 -119.635 -97.016

Note: 1. For any section not listed above and falling between any two listed sections (such as WF36 x 280 falls between WF36 x 3(X) and WF36 x 260), the appropriate
factors may be estimated by averaging (e.g., p = (5.709 + 5.712)/2 = 5.7105 for WF36 x 280).
2. The values listed are valid only for prestressed deck of length (0.2 to 0.35)!.

cD
w
Table 2. Factors to estimate the long-term prestress losses for 9 in. concrete deck.
w x 10" µ
Section Two Span Three Span For (A /A,m) x 100
Relative
Humidity No. p y (l, 1) (1, 1.21, 1) 0.1 percent 0.2 percent 0.3 percent 0.4 percent 0.5 percent

36 x 3(X) 4.782 1.838 9.916 -3.885 553092. 482647. -79.408 -40.430 -27.437 -20.940 -17.043
36 x 260 4.787 1.978 9.945 -4.511 507078. 441358. -94.050 -47.8,51 -32.451 -24.751 -20.131
36 x 230 4.834 2.127 9.976 -5.161 468703. 407013. -109.857 -55.857 -37.857 -28.857 -23.457
36 x 210 4.920 2.233 10.007 -5.968 442565. 382201. - 126.716 -64.423 -43.658 -33.276 -'27.047
36 x 182 4.896 2.439 9.971 -6.912 101226. 345928. -148.768 -75.586 -51.192 -38.995 -31.677
:36 x 160 4.924 2.661 10.020 -7.959 :365159. 314326. -174.609 -88.667 -60.020 -45.697 -37.103
36 x 135 4.874 2.966 10.108 -9.847 :322125. 276422. -215.517 -109.398 -74.025 -56.338 -45.726

33 x 241 4.594 2.062 9.989 -5.243 483608. 419840. -104.625 -53.217 -36.081 -27.513 -22.372
50 percent
33 x 201 4.558 2.289 9.966 -6.399 428790. 371122. -129.161 -65.648 - 44.477 -33.891 - 27.540

33 x 152 4.648 2.746 10.088 -8.978 351931. 302775. -186.503 -94.696 -64.093 -48.792 -39.611
33 x 130 4.605 3.038 10.180 -10.815 313277. 268938. -224.940 -114.170 -77.246 -58.785 -47.708
33 x 118 4.636 3.277 10.250 -12.233 290194. 248779. -257.009 -130.399 -88.195 -67.093 -54.432
30 x 211 4.265 2.229 10.001 -6.686 443091. 383455. -124.378 -63.230 -42.847 -32.656 -26.541
30 x 173 4.263 2.518 10.086 -8.293 385896, 333125. -157.754 -80.135 -54.262 -41.326 -33.564

30 x 132 4.300 3.007 10.264 -11.746 317124. 272125. -225.960 -114.696 -77.608 -59.064 -47.937
30 x 116 4.285 3.311 10.285 -13.643 286893. 245924. -264.064 -133.976 -90.613 -68.932 -55.923
30 x 99 4.210 3.716 10.370 -16.701 252079. 215750. -320.486 -162.550 -109.905 -83.582 -67.788

Note: 1. For any section not listed above and falling between any two listed sections
Factors may be estimated by averaging (e.g., p = (5.709 + 5.712)/2 = 5.7101
2. The values listed are valid only for prestressed deck of length (0.2 to 0.35)/.
Table 2 (cont.). Factors to estimate the long-term prestress losses for 9 in. concrete deck.
w x 10:1 µ
For (A /A,m) x 100 =
Relative Section Ts C) Span Three Span
No. p ! (1, 1 (1, 1.21, 1) 0.1 percent 0.2 percent 0.3 percent 0. 1 percent 0.5 percent
[lwnidity ry

36 x :300 4.582 1.904 8.822 -3.885 503939. 439754. -74.582 -37.936 -25.720 - 19.612 -15.948
:36 x 260 4.583 2.055 8.851 -4.511 462014. 402134. -88.473 -44.970 -30.469 -23.219 - 18.868
36 x 230 4.578 2.207 8.848 -5.161 427050. 370842. -102,589 -52.116 -35.292 -26.879 -21.832

36 x 210 4.633 2.313 8.879 -5.968 403234. 348235. -118.003 -59.944 -40.590 -30.914 -25.108
36 x 182 4.594 2.514 8.923 -6.912 365569. 315185. -138.512 -70.329 -47.601 -36.237 -29.419
36 x 160 4.629 2.765 8.903 -7.959 332708. 286392. -162.827 -82.621 -55.885 -42.518 -34.497
36 x 135 4.581 3.090 8.991 -9.847 293497. 251857. -201.310 -102.107 -69.040 -52.506 -42.585

33 x 241 4.427 2.157 8.861 -5.243 440630. 382529. -98.984 -50.292 -34.062 -25.947 -21.078
(1 percent 8.918 -6.399 390684. 338141. -121.306 -61.605 -41.705 -31.755 -25.785
33 x 201 4.328 2.37:3
33 x 152 4.369 2.856 8.972 -8.978 320655. 275868. -174.044 -88.301 -59.720 -45.430 -36.856
33 x 130 4.294 3.166 8.995 -10.815 285437. 245037. -208.582 -105.785 -71.520 -54.387 -44.107
33 x 118 4.318 3.417 9.066 -12.233 264405. 226670. -238.320 -120.825 -81.661 -62.078 -50.329

30 x 211 4.018 2.309 8.884 -6.686 403713. 349378. -115.885 -58.865 -39.858 -30.354 -24.652
30 x 173 4.011 2.615 8.970 -8.293 351601. 303520. -147.183 -74.706 -50.547 -38.467 -31.220

30 x 132 4.010 :3.132 9.079 - 11.746 288941. 247942. -209,604 -106.311 -71.880 -54.664 -44.335
30 x 116 3.980 :3.426 9.181 - 13.643 261397. 224069. -244.597 -124.022 -83.831 -63.735 -51.678
3.955 3.883 9.277 -16.701 229677. 196576. -300.329 -152.212 -102.840 -78.154 -63.342
30 x 99

Note: 1. For any section not listed above and falling between any two listed sections (such as WF36 x 280 falls between WF36 x 300 and WF36 x 260), the appropriate
factors may be estimated by averaging (e.g., p = (5.709 + 5.712)/2 = 5.7105 for WF36 x 280).
2. The values listed are valid only for prestressed deck of length (0.2 to 0.35) 1.

(D
01
Table 3. Values for k, under different rel- the loading are also given in Fig. 7.
ative humidity (RH) and slab thickness t. The applied prestressing force, N = 880
kips per composite beam. The length of the
Deck Ill
prestressed deck is 0.251. The width of the
Thickness, ==5 RH = 60 RH = 70 bridge is 32 ft with five equally spaced WF33
t percent percent x 221 steel beams.
8 in. 70.04 65.37 60.10 The total dead load = 1.45 kips per ft.
9 in. 54.02 50.86 46.61 The total sustained (long-term) load, w, , =
dead load + (0.3) live load = 1.75 kips per
ft. From structural analysis the bending mo-
procedure in addition to the use of Tables ment, due to w,,, is shown in Fig. 5(c); and
1 to 3 as design aids are illustrated in the that due to the prestressing force is shown
following example. in Fig. 5(b). By superposition, the net
bending moment diagram is shown in Fig.
5(d) where the largest positive moment M„
DESIGN EXAMPLE = 301 kip-ft at sections coinciding with the
It is required to estimate, at a relative ends of the prestressed concrete deck.
humidity of 50 percent, the prestress losses The appropriate values for the various pa-
in a continuous two-span composite con- rameters in Eq. (13) are determined from
crete-steel girder bridge with a portion of Tables 1 and 3. It should be noted that since
its deck prestressed as shown in Fig. 7. The the chosen section of WF33 X 221 is not
geometric and material properties as well as listed in Table 1, interpolation is used. Thus,

1.0

W
0
0.8
V

Z
0 0.6
I-
V
D \80
Q
c 0.4
Z
0
I-
X 0.2
W
Q'

0 0.1 0.2 0.3 0.4 0.5


JL
Fig. 6. Relaxation reduction factor a, as a function of parameter (1 for
different values of (3 (from Ref. 8).

96
17.5
No

Longitudinal Section of Bridge

4..
.8 . 8 8

c NA
-- - ys
Y
Non Prestressed
Steel J 33.93

4-WF 33x221 Prestressing


tendons
Cross-Section

Loadings
Concrete weight = 145 lb/ft3
Surfacing weight = 60 lb/ft2
Girder weight = 200 lb/ft
U. D. L. L. =1000lb/ft

Material Properties
Ec =3.9x10 3 ksi; E s = 29x10 3 ksi ; m=7.44;
fpy =230 ksi; fc = 8.0 ksi; fpu=270ksi

Geometric Properties
Ac =768in 2 ; A t =168.3in 2 ; Ap=4.65in 2 ; dc=8.lin; yp=0;
ys =20.98in; y=29.85in; S= 757in 3 ; I t =30885in4;
OT vo = 2.95; A p /mA t -0.37'6 ; Anp=6.00 in2

Fig. 7. Data for estimating the loss in prestressing force in a continuous two-span
composite bridge cited in the design example.

for N in Eq. (14): for sections 33 X 241 and 33 x 201 in Table


A . = 768 in. 2; Nr„ = 880 kips; rn = 7.44; 1.
A, = 168.3 in.'; M,, = (301) (12) kip-in.; d^
Thus-
= 8.1 in.; 1, = 30885 in. ;; (w x 10) for a
steel section 33 x 221 and an 8 in. concrete x
(W103) 417091 + 373631
= = 395361
deck is estimated by averaging the values 2

PCI JOURNAL/January-February 1986 97


from which w = 395.4 kips. N = N + w
Using the definition of N,,,, given by Eq.
= 637.8 + 395.4
(7):
= 1033.2 kips
A^Nu^ AdM
N =--+ Now A = z/(tiN ,), in which z = 97 X 10'
mA, ml
from Fig. B1; and = 70.036 from Table
_ (768)(880) 3. Thus, A = 1.345.
For Eq. (13): Averaging the values for
(7.44) (168.3) +
sections 33 X 241 and 33 X 201 in Table 1
(768) (8.1) (301) (12) yields: p = 5.539; = 1.89; = 16.11; -y
(7.44) (30885) _ - 5.685; and µ = -50.35.
Thus, using Eq. (13) and without ac-
= 637.8 kips
counting for the "reduced" relaxation in the
Thus, from Eq. (14): prestressing steel:

_ 70.036[(1 - 1.89 - 1.89x 1.345)16. 11 + (1 + 1.345)(5.539)(- 5.685)](1033.2)


^Nv (-50.35) (10:')
= 185.8 kips

Hence, the percentage long-term losses steel, respectively.


in the prestressing force is (185.8/880)(100) To account for the "reduced" relaxation,
or 21 percent. The corresponding percent- a reduced value of z and hence A must be
age losses estimated by the iterative method used in Eq. (13). First, the loss in prestress-
using the computer solution program were ing force due to creep and shrinkage only is
20.7 and 20.0 percent without and with al- estimated from Eq. (13) by putting A = 0
lowing for the nonprestressed reinforcing (since z will be zero). Thus:

70.036[(1-1.89)16.11 + (5.539)(-5.685)]1033.2
_ (-50.35)(10)
= 65.9 kips

Hence, from Eq. (15):


65.9 Thus, with fl = 0.075 and 13 = 0.70, Fig.
6 gives a, = 0.8, and hence z' = 0.8z and
H = 880 = 0.075
the factor A in Eq. (13) will be reduced by
and 13 from Eq. (16) is:
the same factor a = 0.8; using Eq. (13)
R
f (880/4.65)
= 0.70 again:
= fF 270

_ 70.036[{1-1.89-1.89(1.345)(0.8)116.11+11+(1.345)(0.8)1(5.539)(-5.685)1(1033.2)
NN W (-50.35)(10)
= 161.4 kips

yielding a percentage of (161.4/880)(100) or duced" relaxation of the prestressing steel


18.3 percent. the percentage long-term losses in the pre-
Thus, by taking into account the "re- stressing steel is reduced by approximately

98
C-)
C-
0
C
X
z
C
v
C
Losses estimated using the one step
T
<U
20.0 rmethod t'= ca
C-
C
v

OD
15.0
W
Q) a
Notation RH A in 2 An in2
C 10.0 Excluding Steel Relaxation
----- 507. 4.65 0.00
a)
--- 50 7 4.65 6.00
a) --- 70 4.65 0.00
a. 5.0
--- 5090 5.00 0.00
50' 4.65 0.00
0.0
0 1200 2400 3600 4800 6000

Time in days
Fig. 8. Percent losses in prestressing force with time under various conditions.
Table 4. Comparison of results for various composite bridges.
Percent Losses
Number of Span Length, 1, and
M^^ and Npo by
Spans Steel Section Iterative One-Step
Method Method
f = 50 ft; WF36 M,, = 116.5 kip -ft 15.5 17.6
x 182 N,0 = 490 kips
f = 60 ft; WF36 M, = 232.5 kip -ft 16.8 18.3
Two Equal x 135 Noo = 700 kips
Spans e = 70 ft; WF33 M1t = 301 kip -ft 16.5 18.3
X 221 N, = 880 kips 20.7* 21.1*
e = 80 ft; WF36 M1, = 463 kip-ft 16.5 18.1
x 300 N,,,= 1115 kips
f = 50 ft; WF33 M1, = 111 kip-ft 15.4 16.9
Three Spans x 118 N, = 445 kips
(1, 1.21, l) C = 60 ft; WF36 M,, = 188 kip-ft 15.7 17.3
x 160 N,, = 560 kips
C = 70 ft; WF36 M,, = 294 kip-ft 16.1 18.6
x 210 N^ = 725 kips
C = 80 ft; WF36 M,, = 515 kip-ft 16.4 18.4
x 260 Npo = 920 kips

Note: In all cases: t = 8 in.; w = 96 in.; u.d. Dead load = 1.45 kips per ft; u.d. Live load = 1
kip per ft. *Losses without accounting for reduced relaxation of steel.

3 percent. The corresponding losses by the stressing stress to yield stress (f, ,,/f,,) de-
iterative method using the computer pro- creases, thus effecting a reduction in the
gram are 16.5 and 15.9 percent without and losses due to the relaxation of the prestress-
with allowing for the nonprestressed rein- ing steel (see Fig. B1).
forcing steel, respectively. Fig. 8 also shows that, unlike the situa-
tion in concrete-concrete bridges, the influ-
ence of nonprestressed steel in the concrete
DISCUSSION deck on the losses is relatively small here.
The percentage loss in the prestressing This is due to the fact that the area of non-
force versus time was studied under various prestressed steel in the concrete deck is
conditions by means of the iterative method. usually a small proportion of the steel girder
Fig. 8 shows the variations in these losses area which provides the major restraining
with relative humidity, area of prestressing force.
steel, and area of nonprestressed steel in It can be also observed that the result
the concrete deck, according to the ACI based on the one-step method is in fair
Code." The reduction in the relaxation in agreement with that estimated by the iter-
the prestressing steel was taken into ac- ative method. Comparison of results on
count in calculating these losses. prestress losses based on the CEB Code,1e
The comparison of results shows that the for brevity given elsewhere, 13 shows that such
losses become smaller as the relative hu- losses are only slightly higher than those
midity increases, as expected. Under the based on the ACI Code."
same applied prestressing force, an increase Glodowski and Lorenzetti 1 ° indicated that
in the area of the prestressed steel tends to steel relaxation has an important influence
reduce the prestress losses. The reason for on the prestress losses in prestressed con-
this is that the stress ratio of initial pre- crete structures. Fig. 8 also shows this in-

100
fluence for the composite concrete deck-on- ily estimated by means of a simple easy-to-
steel girder structure used in the design ex- use method.
ample treated earlier. Here it is observed 2. The long-term losses are significantly
that the losses due to steel relaxation are a influenced by the relaxation of the pre-
major component of the total losses. stressing steel; smaller losses can be ex-
To demonstrate the adequacy of the one- pected where low relaxation prestressing
step method and use of the design aids in steel is used. Furthermore, it appears that
estimating the prestress losses, results based these losses are not much influenced by the
on both methods were obtained for two- and presence of nonprestressed steel in the con-
three-span continuous bridges with differ- crete deck.
ent spans and cross sections. From a com- 3. The use of the CEB charts and ACI
parison of the results given in Table 4, it is recommendations for the estimation of creep
evident that the one-step method and the coefficients and shrinkage strain leads to al-
developed design aids can be reliably used most identical values for the long-term
to estimate conservatively the prestress losses prestressing losses.
in composite concrete-steel girder bridges
with portions of the concrete deck pre-
stressed in the vicinity of the piers. ACKNOWLEDGMENT
From this study it can be concluded that:
1. The long-term prestress losses in con- This research work was supported by the
tinuous composite concrete-steel girder Natural Sciences and Engineering Research
bridges with prestressed decks can be read- Council of Canada under Grant No. 1896.

NOTE: Discussion of this paper is invited. Please submit your


comments to PCI Headquarters by September 1, 1986.

PCI JOURNAL/January-February 1986 101


REFERENCES

1. Johnson, R. P., and Buckby, R. J., Compos- ommendations for Estimating Prestress
ite Structures of Steel and Concrete, Vol. 2, Losses," PCI JOURNAL, V. 20, No. 4, 1975,
Granada Publishing Ltd., 1979. 43-75; and discussion in V. 21, No, 2, 1976,
2. Kennedy, J.B., and Grace, N. F., "Pre- pp. 108-126.
stressed Decks in Continuous Composite 13. Soliman, Mohamed H., "Long-Term Losses
Bridges," Journal of the Structural Division. in Prestressed and Thermal Effect in Com-
ASCE, V. 108, No. 11, 1982. posite Steel Concrete Structures with Pre-
3. Roik, K., "Methods of Prestressing Contin- stressed Concrete Decks," MASc Thesis,
uous Composite Girders," Proceedings, University of Windsor, Windsor, Ontario,
Conference on Steel, June 1968, BSSA, Lon- Canada, 1985.
don, 1969. 14. Tadros, M. K., Ghali, A., and Dilger, W.,
4. Tadros, M. K., Ghali, A., and Dilger, W., "Time Dependent Analysis of Composite
"Time Dependent Prestress Losses and De- Frames," Journal of the Structural Division,
flection in Prestressed Concrete Members," ASCE, ST4, April 1977.
PCI JOURNAL, V. 20, No. 3, May-June 1975, 15. Tadros, M. K., Ghali, A., and Dilger, W.,
pp. 86-98. "Effect of Non-Prestressed Steel on Prestress
5. Dorton, R. A., Holowka, M., and King, J. Loss and Deflection," PCI JOURNAL, V. 22,
P. C., "The Conestogo River Bridge — De- No. 2, March-April 1977, pp. 50-63.
sign and Testing," Canadian Journal of Civil
16. Trost, H., "Implications of the Superposition
Engineering, V. 4, 1977. Principle and Creep and Relaxation Prob-
6. Bazant, Z. P., "Prediction of Concrete Creep lems for Concrete and Prestressed Concrete"
Effect Using Age-Adjusted Effective Modu-
(in German) Beton - and Stahlbetonbau,
lus," ACI Journal, V. 69, No. 4, 1972. Berlin - Wilmersdorf, V. 62, No. 10, 1967.
7. Dilger, W., and Neville, A.M., "Effect of
17. ACI Subcommittee 209, "Prediction of Creep,
Creep and Shrinkage in Composite Mem-
Shrinkage and Temperature Effect, 2," ACI
bers," Proceedings, Second Australian Con-
Report 209 R-82, Detroit, Michigan, October
ference on Mechanics of Structures and
1982.
Materials, Adelaide, Australia, 1969.
18. CEB-FIP, "International Recommendations
8. Dilger, W., "Creep Analysis of Prestressed
for Design and Construction of Concrete
Concrete Structures Using Creep Trans-
Structure — Principles and Recommenda-
formed Section Properties," PCI JOURNAL,
tions," Comit6 Europeen du Beton — Fed-
V. 27, No. 1, 1982, pp. 98-118.
eration International de la Pre-Contrainte, FIP
9. Ghali, A., Sisodiya, R. G., and Tadros, G.
S., "Displacements and Losses in Multistage 6th Congress, Prague, June 1970, Cement &
Concrete Association, London, England.
Prestressed Members," Journal of the Struc-
tural Division, ASCE, V. 100, No. ST11, No- 19. Ghali, A., and Tadros, M. K., "Partially Pre-
vember 1974. stressed Concrete Structure," Journal of
10. Knowles, P. R., Composite Steel Concrete Structural Engineering, ASCE, V. 111, No.
Construction, John Wiley and Sons, New 8, August 1985.
York, N.Y., 1973. 20. Glodowski, R. J., and Lorenzetti, J. J., "A
11. Neville, A. M., and Dilger, W., Creep of Method for Predicting Prestress Losses in a
Concrete: Plain, Reinforced and Prestressed, Prestressed Concrete Structure," PCI
North Holland Publishing Co., 1970. JOURNAL, V. 17, No. 2, March-April 1972,
12. PCI Committee on Prestress Losses, "Rec- pp. 17-31.

102
APPENDIX A - DETERMINATION OF
CONTINUITY FACTOR
This continuity factor A is found using uous condition, the final long-term bending
the unit load method. 13 Let AM be the moment may be expressed as:
change in the bending moment with the in-
AM,, = AMo + AM,X
termediate support(s) assumed removed and
the structure made simply supported; and At the ends of the prestressed deck (see
AM, be the redundant bending moment with Fig. 5) this becomes:
the intermediate support(s) replaced by a
AM,, = AM o + AM,X, f3'
unit force X,. Thus, with the structure as-
sumed to he brought to its original contin- where

( AN ,0 d„ . AM, dl
J AM"AM ' dl —
EI J EI
=
X J (AM`)2 dl f (AM ' )2 dl
EI EI

and 13'1 is the length of the unprestressed deck in one span (see Fig. 5). Thus:

d OM,

AM, = AN , • d, — ON,,,, dl AM . R'


(OM )2
EI

This may be rewritten as:

d`AM' dl
El
AM,, = AN„,, d , R']
J (AM,)'
dl AM
El

Or:

AMet = AN ,,,, - A

in which A is the continuity factor.

PCI JOURNAL/January-February 1986 103


APPENDIX B - FACTORS FOR DETERMINING
EQ. (13)

The explicit expressions for determining 1 + (1 + I „ ^,, 7)


the factors in Eq. (13) are as follows: [Ej, ELI

= ^a,7
EA ys

ry= EI,

+ (1 + i„ 4..7)
_ EA _ Y, ( 1 + "1 ^x.7) A
(1 + T l,, -,7)
P (1 + r l„-,7) I,

1 (1 + -,7) 1 (1 + I, ^x,7)

_ 1 + ii _ G A .= + E,A,, ) \E A,, + E ft,

EA 1 + T I,. 4 7

LL ErA
( 1(1 + ^1 4 7) l( /.,

x \E SI .9 + ELI, / + \ESIa

J ' (1 + ^h ^m7) (E,,A,, + (1+


x (1 +” 1L 4)-,7) E,I
E,1, + (1 + 11, x7)
EA,_

Note that the expression for the factor z is given in Fig, B1.

Z _ 0_lfpo log t
o ( fpo -0.551
Ep io \ f py /
0.8
t.= 240,000 hours

0.7

O6
.2 4 6 8 10(x10")
z
Fig. B1. Values for the coefficient z defining the factor A in Eq. (13).

104
APPENDIX C — NOTATION

A = area of section rameters they indicate time at


E = modulus of elasticity middle of intervals i, j, re-
f = stress spectively
I = moment of intertia i — V2 = beginning of interval i, j
M = moment acting on section i + V2 = end of interval i, j
N = normal force acting on section m, n = flexural and axial, respectively
w = uniformly distributed load r = steel relaxation reduction
z = factor defined in Fig. B1 T, t = age of concrete and time of load-
a = reduction factor ing, respectively
A = increment p = prestressing steel
E = strain It = long term
= creep coefficient np = nonprestressing steel
= thrust relaxation coefficient sh = shrinkage
X = continuity factor o = initial
K = curvature of beam under loading 00 = very long period
13 = ratio between initial and ulti-
mate prestressing stress in the
tendons
(3'l = length of unprestressed deck in
one span Metric (SI) Conversion
fl = ratio given in Refs. 4 and 8 Factors
,, i;, ^, -y, p, p, are factors defined in Ap-
pendix B. 1 in. = 25.4 mm
1 in.z = 645.2 mm2
1 in. 4 = 416231 mm4
Subscripts
1 kip = 4.448 kN
C = concrete 1 psi = 6.895 kPa
s = steel 1 kip-ft = 1356 N.m
t = time 1 kip/ft = 14.58 kN/m
t' = variable time t - t' T 1 ft = 0.305 m
i, j = time interval numbers, when
used with time dependent pa-

PCI JOURNAL/January-February 1986 105

Anda mungkin juga menyukai