Infrastructure Costs
The costs of storage, power consumption and labour required for installation are also taken into account.
Assumptions
1 Active Directory
3 File Server
XenDesktop will support Microsoft Active Directory Server 2003 or higher. Freedom has Windows NT
domain and migration is not part of VDI Implementation
Storage for User Data is not considered, we can use existing file server for user data
We have considered Xenserver as Hypervisor Platfrom for Xendesktop which is part of Xendesktop
License
For a quick TCO overview , please enter the total number of desktops you plan to refresh or virtualize.
Please only change white cells. For customizing the tool to your environment, please edit the VDI and Assumptions tabs first.
Relative TCO Over 6 years Relative Per Desktop Costs Over 1 year
$1,198,828
$1,116,000
$1,200,000
$1,000,000
10
$800,000
8
$600,000
6
$400,000
$200,000 4
$- 2
XenDesktop + Thin Desktop Replacement
Client 0
Desktop Virtualization Licensing Costs
Number of Desktops 1000 being considered for implementation
These are default assumptions - Change (white cells) as per your quoted prices.
Accounting for existing infrastructure could drastically change the assumptions.
1. Citrix XenDesktop
2 Citrix XenDesktop
Replace default costs entered in the chart with quotes you have received from the vendor. Please adjust the licensing option you wish to test in cell F37
Citrix XenDesktop Licensing & Related Cost Units Total
Hardware Costing
Hypervisor Hardware cost $ 9,100 14 $ 127,400
Blade Chasse $ - $ 20,000
$ - 0 $ -
$ - $ -
Total Number of server 14
XenDesktop (Advanced license) $ 195 0 $ - Advanced
Comes with XenApp Integrated (Enterprise) $ 225 1000 $ 225,000 Enterprise
Comes with XenApp Integrated (Platinum) $ 300 0 $ - Platinum
> Solution Selected: (Default is Enterprise) $ 225 1000 $ 225,000
Please note that this calculator does not take the depreciation of capital assets into account. Capital costs are recorded at the time of purchase, rather than as an annual
depreciation cost.
These are default assumptions - Change (white cells) as per your own environment
apital costs are recorded at the time of purchase, rather than as an annual
Time it takes to unpack, image, install apps, deliver to end user desk
Time to diagnose, and perform deskside visit
Time to diagnose and restart a VM or delete and issue new VM
Traditional PC failure rate industry average
Estimates from industry studies
KWHrs * 4 servers
Terabytes of disk required to host VM's for View & Citrix
Price per Gb of SAN disk storage
Assumed
Typical tier 1 desktop with dual core cpu, 2GB memory, 160gb HDD
Price / copy of system management tool one time fee
One time
These costs are based on previously entered assumptions. (Manual changes on this sheet not recommended except Vendor X).
1
Standard Assumptions Year 1 Year 2 Year 3 Total ($)
Standard Assumptions
Number of Desktops 1000 10 10
Price per KWHr $ - $ - $ - /KWHr
Software Assurance annual update rate 20% 23% 26%
2
Desktop Replacement Costs Year 1 Year 2 Year 3 Total ($)
Desktop Replacement
Typical Desktop $ 800,000 $ 8,000 $ 8,000 $ 816,000
System Management Tool / PC Price $ - $ - $ - $ -
Annual Upgrade for Sys Mgt Tools $ - $ - $ - $ -
Desktop Labour
Configuration & Installation $ - $ - $ - $ -
Desktop Related Support & Management $ - $ - $ - $ -
Total Desktop Installation Costs $ 800,000 $ 8,000 $ 8,000 $ 816,000
Destkop Power Consumption
Desktop Device Power Cost per Year $ - $ - $ - $ -
Desktop Air Conditioning Cost $ - $ - $ - $ -
… $ - $ - $ - $ -
… $ - $ - $ - $ -
Total Desktop Power Costs $ - $ - $ - $ -
3
Thin Client Acquisition Costs Year 1 Year 2 Year 3 Total ($)
5
Citrix XenDesktop Costs Year 1 Year 2 Year 3 Total ($)
… $ - $ - $ - $ -
Total Server Costs $ 483,400 $ 33,750 $ 33,750 $ 419,900
Virtualization Storage Hardware
Cost of Storage for VDI $ 76,800 $ 7,680 $ 8,448 $ 92,928
… $ - $ - $ - $ -
Total Storage Costs $ 76,800 $ 7,680 $ 8,448 $ 92,928
Virtualization Infrastruture Power Consumed
Power Consumed by Servers $ - $ - $ - $ -
Server Air Conditioning $ - $ - $ - $ -
Power Consumed by Storage $ - $ - $ - $ -
Storage Air Conditioning $ - $ - $ - $ -
… $ - $ - $ - $ -
… $ - $ - $ - $ -
Total power Costs $ - $ - $ - $ -
Labor Costs
Configuration & Installation $ - $ - $ - $ -
VDI Support & Management $ - $ - $ - $ -
… $ - $ - $ - $ -
… $ - $ - $ - $ -
Total Labor Costs $ - $ - $ - $ -
Common Hardware/Software $ - $ - $ - $ -
Desktop Replacement Costs $ 800,000 $ 8,000 $ 8,000 $ 816,000
Thinclient Acquisition Costs $ 250,000 $ 2,500 $ 2,500 $ 255,000
Citrix XenDesktop costs $ 560,200 $ 41,430 $ 42,198 $ 643,828
Licensing
Application Licensing Costs $ - $ - $ - $ -
Solution Selected: (VDA w/o SA) $ 300,000 $ - $ - $ 300,000
TCO Summary Sheet
After filling in the necessary values, the spreadsheet automically generates two TCO summary graphs. The first graph
illustrates the total difference between the project's direct and indirect costs. The second graph depicts the total direct
and indirect costs per year.
Three Scenarios
Year 1 Year 2 Year 3
Citrix XenDesktop with Thin Client Hardware
Common HW/SW $ - $ - $ -
Thin Client $ 250,000 $ 2,500 $ 2,500
XenDesktop $ 560,200 $ 41,430 $ 42,198
Application Licensing Costs $ - $ - $ -
Solution Selected: (VDA w/o SA) $ 300,000 $ - $ -
Subtotals $ 1,110,200 $ 43,930 $ 44,698
Desktops 1000
Relative Costs
XenDesktop + Thin Client $ 1,198,828 Relative Costs
Desktop Replacement $ 1,116,000
$1,198,828
$1,116,000
$1,200,000
$1,000,000
$800,000
$600,000
$400,000
$200,000
$-
XenDesktop + Desktop
Thin Client Replacement
Storage
HDDCalculation
Required in GB
per user
Hosted
(2GB forVDI Pooled
Page (NotWrite
file+1GB dedicated) (60%) Files+Temp)--->
back Cach+Log 5
Linked Clone
Storage requirement in GB
1000 users
5000 users
7500 users
10000 users
RAM in GB HDD in GB
375 3*72
32 3*72
ation
Users Storage Space in GB
600 3000
400 12000
1000
16000
3200
19200
20
19200
60432
90620
120807
Price in $
Web Interface 2 1000 2000
DDC 2 1000 2000
License Server 1 1000 1000
Hosted Apps 6 1000 6000
XenDesktop License 1000 225 225000
Windows 7 VDA 1000 100 100000
Sl. No.
4
5
10
Effort requirements for VDI Implementation
Description
Prepare Architecture and Design Document
Hypervisor Architecture
Citrix XenApp Architecture
Citrix XenDesktop Architecture
Roll Out:-
Phase 1 roll out--200
Preparation of Master Image for the business unit
Allocation of Desktops
User Data Migration
Fixing users issues Post Production migration
Policy Implementation according to business units
Documentation
Roll Out:-
Phase 2 roll out--200
Preparation of Master Image for the business unit
Allocation of Desktops
User Data Migration
Fixing users issues Post Production migration
Policy Implementation according to business units
Documentation
Roll Out:-
Phase 3 roll out--200
Preparation of Master Image for the business unit
Allocation of Desktops
User Data Migration
Fixing users issues Post Production migration
Policy Implementation according to business units
Documentation
Roll Out:-
Phase 4 roll out--200
Preparation of Master Image for the business unit
Allocation of Desktops
User Data Migration
Fixing users issues Post Production migration
Policy Implementation according to business units
Documentation
10
25 Y
45 Y
20 Y
45 Y
40 Y
40 Y
40 Y
40 Y
30 Y