Anda di halaman 1dari 4

Productivity of MIVAN SHUTTERING in 3days cycle

Labour
Day Description % of Work Time Hours Total
Carp/Fitter Helpers

1st day External 50% area 50%


De-shuttering 50% 4 8 8.30 am 5.30 pm 8 96
Bracket Fixing (Removing & Fixing) 60% 4 8.30 am 1.00 pm 4.5 18
Working Platform (Removing & Fixing) 60% 4 8.30 am 5.30 pm 8 32
Cleaning of Shutters, Wall tie removal 4 2.00 pm 5.30 pm 3.5 14
Lifting & Fixing of Shutters 4 16 5.30 pm 12.30 pm 7 140
C&D flat type
De-shuttering 75% 6 10 8.30 am 1.00 pm 4.5 72
Cleaning of Shutters 8 8.30 am 5.30 pm 8 64
Shifting of Shutters to next Level 6 10 2.00 pm 5.30 pm 3.5 56
Erection of Wall Shutters (Internal) 75% 6 18 5.30 pm 12.30 am 7 168

Staircase & Lobby Area


Deshuttering 50% 2 2 8.30 am 1.00 pm 4.5 18
Cleaning,shifting 50% 2 2.00 pm 4.00 pm 2 4
Erection of Shutters 50% 2 4 2.00 pm 12.30 am 10.5 63

Supervision & Material Maintanence


Supervisor 2 8.30 am 12.30 am 15 30
pins, wedges, tie rods collection 2 8.30 am 12.30 am 15 30

2nd day External area 50%


De-shuttering 50% 4 8 8.30 am 5.30 pm 8 96
Bracket Fixing (Removing & Fixing) 40% 4 8.30 am 1.00 pm 4.5 18
Working Platform (Removing & Fixing) 40% 4 8.30 am 5.30 pm 8 32
Cleaning of Shutters, Wall tie removal 4 2.00 pm 5.30 pm 3.5 14
Lifting & Fixing of Shutters 4 16 5.30 pm 12.30 pm 7 140
C&D flat type
De-shuttering 25% 2 4 8.30 am 1.00 pm 4.5 27
Cleaning of Shutters 4 8.30 am 1.00 pm 4.5 18
Shifting of Shutters to next Level 4 2.00 pm 7.30 pm 5.5 22
Erection of Wall Shutters (Internal) 25% 2 4 2.00 pm 7.30 pm 5.5 33
Productivity of MIVAN SHUTTERING in 3days cycle
Labour
Day Description % of Work Time Hours Total
Carp/Fitter Helpers
A&B flat type
De-shuttering 50% 4 6 8.30 am 1.00 pm 4.5 45
Cleaning of Shutters 4 8.30 am 5.30 pm 8 32
Shifting of Shutters to next Level 4 6 2.00 pm 5.30 pm 3.5 35
Erection of Wall Shutters (Internal) 35% 4 10 5.30 pm 12.30 am 7 98
Staircase & Lobby Area
Deshuttering 50% 2 2 8.30 am 1.00 pm 4.5 18
Cleaning,shifting 50% 2 2.00 pm 4.00 pm 2 4
Erection of Shutters 50% 2 4 2.00 pm 12.30 am 10.5 63
Supervision & Material Maintanence
pins, wedges, tie rods collection 1 8.30 am 12.30 am 15 15
Supervisor 2 8.30 am 12.30 am 15 30
3rd day A&B flat type
De-shuttering 40% 2 6 8.30 am 1.00 pm 4.5 36
Cleaning of Shutters 4 8.30 am 1.00 pm 4.5 18
Shifting of Shutters to next Level 8 8.30 pm 3.30 pm 5.5 44
Erection of Wall Shutters (Internal) 50% 2 6 8.30 pm 3.30 pm 5.5 44
Kicker, Soldier fixing & alignment
Kicker Removing & Lifting to next Level 100% 4 8.30 am 1.00 pm 4.5 18
Kicker Fixing 100% 2 4 8.30 pm 5.30 pm 3.5 21
Soldier Shifting & Fixing 100% 4 8.30 am 5.30 pm 3.5 14
Kicker Bolt Fixing 4 8.30 am 5.30 pm 8 32
Kicker & External Shutter Alignment 100% 2 8 4.30 pm 8.30 pm 4 40
Int. shutter Alignment & Plate Corner Fixing 2 8 8.30 am 8.30 pm 10 100

Supervision & Material Maintanence


Supervisor 2 8.30 am 12.30 am 15 30

Pouring of Concrete 11.00 pm 6.00 am


Carpenters & Helpers during Concrete Casting 1 3 11.00 pm 6.00 am 7 28
1970

Total area of shuttering = 1075 m2

LABOUR PRODUCTIVITY FOR FORMWORK = 1.83 Man-Hr. / Sq.m.


Productivity of MIVAN SHUTTERING in 3days cycle
Labour
Day Description % of Work Time Hours Total
Carp/Fitter Helpers
REINFORCEMENT

Day of Cast Wall reinforcement Lifting & Fixing 25% 9 13 6.30 pm 12.30pm 6 132
Wall reinforcement Lifting & Fixing 60% 7 10 8.30 am 12.30 am 15 255
Day 1 Cutting & Bending for next level 35% 2 3 8.30 am 12.30 am 15 75
Wall reinforcement Fixing 15% 7 10 8.30 am 12.30 pm 4 68
Day 2 Slab reinforcement Shifting,Lifting & Fixing 35% 7 10 2.00 pm 12.30 pm 10 170
Cutting & Bending for next level 35% 2 3 8.30 am 12.30 am 15 75
Slab reinforcement Fixing 65% 7 10 8.30 am 8.30 pm 12 204
Day 3 Cutting & Bending for next level 30% 2 3 8.30 am 12.30 am 15 75
1054
Reinforcement Quantity = 5.5 MT.

LABOUR PRODUCTIVITY FOR REBAR = 191.64 Man-Hr. / MT.


Productivity of MIVAN SHUTTERING in cycle
Labour
Day Description % of Work Time Hours Total
Carp/Fitter Helpers

Anda mungkin juga menyukai