Bulan: April

Mg Sen Sel
No Jenis Pekerjaan Volume Satuan 7 8 9
1 SoftPile Dia.600mm 91 Titik
L=12M 14 15 16
6
21 22 23

28 29 30

32 Titik
Rab Kam Jum Sab
10 11 12 13
14 12
17 18 19 20

24 25 26 27
Maret'19 April'19
1 2 3 4
No Jenis Pekerjaan Volume Sat '27-31 '01-07 '08-14 '15-21
1 Secant Pile 183 Ttk
2 Capping Beam 6,253.82 Kg
3 Galian THP.1 (-4.40) 6,756.16 M3
4 Cor Pondasi TC 5,263.07 Kg
5 Strutting Beam 25,750 Kg
6 Bobok Borepile Dia.600 mm 183 Ttk
7 Pemancangan 45x45 208 Ttk
8 Galian Final (-8.85) 9,395.29 M3
9 Bobok Tiang Pancang 45x45 208 Ttk
pril'19 Mei'19 Juni'19
5 6 7 8 9 10 11 12 13 14
'22-28 '29-05 '6-12 '13-19 '20-26 '27-02 '03-09 '10-16 '17-23 '24-30