Design building envelope systems to provide for deflections, displacements and other movements
within the building envelope system, and between the building envelope system and the base
building (including fire stop and smoke flashing connections). Include movements caused by
ambient temperature changes, wind loads, dead loads, live loads, seismic loads and shrinkage.
The Contractor’s design shall include moveable joints to accommodate the full range of
movement requirements including manufacturing tolerances, site tolerances, thermal
movement, lateral movement, floor sag, beam sag, live load deflection and column settlement.
Allowance for movement shall be in addition to allowance for building tolerances.
Joints shall accommodate the worst possible combination of effects to prevent loads of any kind
being transferred from the building into the building envelope system, excessive movements of
any joints or failure of weather seals.
Prepare and submit full analysis and complete details of proposed design movement allowances
based on the base structure information contained in the Specifications.
Indicate movement limits and required clearances on shop drawings.
Accommodate movements within the design movement allowances indicated on the accepted
shop drawings, silently and without failure of the system, permanent deformation, reduction of
performance, visible movement at any joint, or other detrimental effects including:
o Application of stresses or induced loads to any component or system, including structural
elements, fixings, glass or face panels.
o Damage to any component or system, including structural elements, fixings, glass or face
panels.
o Failure of joint seals.
Design movement joint and select sealant products to accommodate all required expansion and
contraction within joint tolerances indicated on the accepted shop drawings and within the
sealant manufacturer under loaded and unloaded conditions.
All movements allowance shall be consistent and applied across all junctions and / or components
for each expansion joint system or assembly.
The contractor shall regularly assess and take into consideration the effect of ongoing base
building movements on building envelope set-out.
The building envelope shall be designed to accommodate the primary structure construction
tolerances.
Unless otherwise noted elsewhere, the maximum construction tolerances shall be taken as
follows:
o Plan position of the building edge: +/- 25 mm
o Level of slab surface and slab soffit: +/- 25 mm
o Deviation in plan over 20M height < 50 mm
Setting Block
Safety
a) First aid appliances including adequate supply of sterilized dressings and cotton wool shall be kept
in a reality accessible place.
b) An injured person shall be taken to a public/ private hospital without loss of time, in case where
the injury necessitates hospitalization.
c) Suitable and strong scaffolds should be provided for workmen for all works that cannot safely be
done from ground.
d) No portable single ladder shall be over 8 meters in length. The width between the side rails shall
not be less than 30 cm. (clear) and the distance between two adjacent rungs shall not be more
than 30 cm. When a ladder is used an extra mason shall be engaged for holding the ladder.
e) The excavated material shall not be placed within 1.5 meters of the edge of the trench or half of
the depths of trench whichever is more. All trenches and excavations shall be provided with
necessary fencing and lighting.
f) Every opening in the floor of a building or a working platform shall be provided with suitable
means to prevent the fall of persons or materials by providing suitable fencing or railing whose
minimum height shall be one meter.
g) No floor, roof or other part of the structure shall be so overloaded with debris or materials as to
render it unsafe.
h) Those engage in welding works shall be provided with welder’s protective eye-shields and gloves.
i) Fire Extinguisher minimum 2 numbers to be provided by contractor at period of execution of the
site.
j) No paint containing lead or lead products shall be used except in the form of paste or readymade
paint. Suitable facemasks shall be supplied for use to the workers when the paint is applied in the
form of spray or surface having lead paint dry rubbed and scrapped.
k) The Contractor to the painters shall supply overalls and adequate facilities shall be provided to
enable the working painters to wash during the periods of cessation of work.
l) Hoisting machines and tackle used in the works, including their attachments, anchorage and
supports shall be in perfect condition.
m) The ropes used in hoisting or lowering materials or as a means of suspension shall be of durable
quality and adequate strength and free from defects.
n) Those engaged in working at heights shall use safety belts.
o) Provide fully toughened glass on the inner side of the IGU if glass is abutting with floor.
Sealant Application