TERBILANG : Satu Milyar Lima Puluh Enam Juta Sembilan Ratus Sembilan Puluh Tiga Ribu Rupiah
RENCANA ANGGARAN BIAYA
I PEKERJAAN PERSIAPAN
1 Papan Nama Kegiatan 1.000 ls 350,000.00 350,000.00
2 Pembongkaran Bangunan Lama 1.000 ls 350,000.00 350,000.00
3 Pengukuran dan Pemasangan Bouwplank 76.500 m' 280,190.00 21,434,535.00
4 Pelaporan dan Dokumentasi 1.000 ls -
22,134,535.00
II PEKERJAAN TANAH
1 Galian Tanah Biasa Pondasi Batu 26.366 m3 63,750.00 1,680,800.63
4 Urugan Kembali 6.591 m3 42,500.00 280,133.44
5 Urugan Tanah Bawah Lantai #REF! m3 42,500.00 #REF!
6 Urugan Pasir Bawah Pondasi #REF! m3 169,500.00 #REF!
7 Urugan Pasir Bawah Lantai 2.222 m3 169,500.00 376,612.05
#REF!
IV PEKERJAAN BETON
B Pekerjaan Sloof, Kolom & Balok
1 Sloof 15/25 cm, Beton K225 + Pembesian - m3 2,522,820.00 -
2 Sloof 15/20 cm, Beton K225 + Pembesian 1.256 m3 5,559,490.00 6,979,939.70
3 Kolom K1 20/25 cm, Beton K225 + Pembesian - m3 3,328,670.00 -
4 Kolom K2 20/25 cm, Beton K225 + Pembesian 1.600 m3 48,460,090.00 77,536,144.00
5 Kolom Praktis 12/20 cm, Beton K225 + Pembesian 0.428 m' 116,990.00 50,118.52
6 Balok 12/20 cm, Beton K225 + Pembesian 0.276 m3 10,191,720.00 2,812,914.72
7 Ring Balk 12/15 cm, Beton K225 + Pembesian 0.369 m' 1,963,890.00 724,675.41
8 Plat Beton Profil Canopy 31.000 m' 164,700.00 5,105,700.00
88,103,792.34
V PEKERJAAN DINDING
1 Pasangan Dinding Bata Merah 1/2 bata 1 PC : 4 PP 135.597 m2 104,520.00 14,172,598.44
2 Plasteran Dinding 1 PC : 4 PP tebal 15 mm 271.194 m2 53,800.00 14,590,237.20
3 Acian (PC) Dinding + Beton 287.194 m2 32,710.00 9,394,115.74
38,156,951.38
IX PEKERJAAN LANTAI
4 Lantai Keramik 40 X 40 cm, Polished 37.712 m2 195,850.00 7,385,934.37
5 Lantai Keramik 40 X 40 cm, Unpolished 3.488 m2 220,250.00 768,232.00
8,154,166.37
XI PEKERJAAN ELEKTRIKAL
2 Lampu TL Twister 24.W 865 E27 + Fitting 12.000 titik 100,850.00 1,210,200.00
3 Lampu TL 12.W + Fitting 3.000 titik 75,650.00 226,950.00
4 Stop Kontak 1P 220 Volt, Wall Type 3.000 bh 30,070.00 90,210.00
6 Saklar Ganda 3.000 bh 40,050.00 120,150.00
7 NYM 3 x 2,5 + Pipa Conduit dia.20 untuk Lampu 93.950 m' 35,200.00 3,307,040.00
8 NYM 3 x 2,5 + Pipa Conduit dia.20 untuk Stop Kontak 43.650 m' 35,200.00 1,536,480.00
6,491,030.00
186,790.00
4,535.83
191,325.83
#REF!
BACK UP PERHITUNGAN VOLUME PEKERJAAN RUMAH MES GURU - 2 RUANG
DIMENSI VOLUME
NO ITEM PEKERJAAN TINGGI QTY REKAPITULASI
PANJANG LEBAR LUAS @
3 Urugan Pasir Bawah Pondasi 41.850 0.700 29.295 0.050 1.465 1.465
4 Urugan Pasir Bawah lantai 44.438 0.050 2.222 2.222
→ Pekerjaan Pondasi
Volume Beton - - - - - - -
Berat Pembesian : P Qty Total P Koef Berat Jumlah Total
Tulangan X Ø 16 - - - - - -
Tulangan Y Ø 16 - - - - - - -
Berat Tulangan per m3 Beton Poer Plat P1, P3, P4 #DIV/0!
2 Poer Plat P2
Volume Beton - - - - - - -
Volume Beton - - - - - - -
4 Poer Plat P6
Volume Beton - - - - - - -
Berat Pembesian : P Qty Total P Koef Berat Jumlah Total
Tulangan X Ø 14 - - - - - -
Tulangan Y Ø 14 - - - - - - -
5 Poer Plat P7
Volume Beton - - - - - - -
Tulangan Y Ø 14 - - - - - - -
Berat Tulangan per m3 Beton Poer Plat P6 #DIV/0!
DIMENSI VOLUME
NO ITEM PEKERJAAN TINGGI QTY REKAPITULASI
PANJANG LEBAR LUAS @
Tulangan 2 D 12 - - - - -
Beugel Ø 8 - 150 - - - - - -
Berat Tulangan per m3 Beton Sloof SL1 -
Volume Beton - - - - - - -
Berat Pembesian : P Qty Total P Koef Berat Jumlah Total
Tulangan 4 D 12 - - - - -
Tulangan 4 D 14 - - - 1.100 -
Beugel Ø 8 - 150 - - - 0.395 - - -
Berat Tulangan per m3 Beton Kolom K1 -
4 Kolom K2 15/25 cm, Beton K225 + Pembesian
Tulangan 2 D 12 - - - 0.880 -
Beugel Ø 8 - 150 0.650 656.000 426.400 0.395 168.428 266.828 2,668.280
Berat Tulangan per m3 Beton Kolom K2 1,667.675
5 Kolom Praktis 12/12 cm, Beton K225 + Pembesian
Volume Beton m' 0.120 0.120 0.014 4.250 0.061 7.000 0.428
Tulangan 4 D 14 - - - 1.100 -
Tulangan 2 D 12 - - - 0.880 -
Beugel Ø 8 - 150 - - - 0.395 - - -
Berat Tulangan per m3 Beton Kolom K3 #DIV/0!
7 Kolom K5 15/30 cm, Beton K225 + Pembesian
Volume Beton - - - - - - -
Berat Pembesian : P Qty Total P Koef Berat Jumlah Total
Tulangan 4 D 12 - - - 0.880 -
Tulangan 2 D 10 - - - 0.615 -
Beugel Ø 8 - 150 - - - 0.395 - - -
Berat Tulangan per m3 Beton Kolom K3 #DIV/0!
8 Kolom Praktis 15/20 (m') -
9 Kolom Praktis 15/15 (m') -
DIMENSI VOLUME
NO ITEM PEKERJAAN TINGGI QTY REKAPITULASI
PANJANG LEBAR LUAS @
Tulangan 2 D 12 - - - 0.880 -
Beugel Ø 8 - 150 0.490 188.600 92.414 0.395 36.504 64.794 64.794
Berat Tulangan per m3 Beton Balok 12/20 234.759
Volume Beton per m' 13.808 0.120 1.657 0.120 0.199 0.199
Berat Pembesian : P Qty Total P Koef Berat Jumlah Total
Volume Beton - - - - - - -
Berat Pembesian : P Qty Total P Koef Berat Jumlah Total
Tulangan 6 D 12 - - - - -
Tulangan 6 D 14 - - - - -
Beugel Ø 8 - 150 - - - - - -
Berat Tulangan per m3 Beton Balok B2 #DIV/0!
14 Ring Balk 15/20 -
→ Pekerjaan Dinding
b. Pas. Dinding Bata Merah Depan (jendela) 3.600 9.300 33.480 6.183 27.298 - 27.298
Pas. Dinding Bata Merah Depan (Pintu) - - - - - - -
c. Pas. Dinding Bata Merah Samping 3.600 8.700 31.320 - 31.320 - 31.320
kanan - - - - - -
kiri - - - - - -
d. Pas. Dinding Bata Merah tengah (pintu) 3.600 4.430 15.948 - 15.948 - 15.948
e. Pas. Dinding Bata Merah dalam (WC) 3.000 5.990 17.970 1.620 16.350 - 16.350
Acian Kolom Depan, Sudut, Tengah 4.000 0.400 1.600 - 1.600 10.000 16.000
Acian Kolom Tengah - - - - - - -
→ Pekerjaan Atap
1 Rangka Atap Baja Ringan + Penutup Atap
b. Plafond Selasar - - - - -
c. Plafond Atap - - - -
→ Pekerjaan Lantai
DIMENSI VOLUME
NO ITEM PEKERJAAN PANJANG QTY REKAPITULASI
TINGGI LEBAR LUAS KUSEN
b. Kusen Pintu & jendela (PJ) 0.050 0.120 0.006 10.392 0.062 2.000 0.125
c. Kusen Pintu (P1) 0.050 0.120 0.006 5.020 0.030 2.000 0.060
d. Kusen Pintu (P2) 0.050 0.120 0.006 4.900 0.029 2.000 0.059
e. Kusen ventilasi (V1) 0.050 0.120 0.006 2.200 0.013 2.000 0.026
Volume Kusen Pintu dan Jendela 0.354
5 Daun Pintu Panil Solid & Daun Jendela (PJ) - - 2.972 - - 2.000 5.944
6 Jendela Jalusi - - - - - - -
7 Kaca Polos 5 mm
a. Daun Jendela J1 - - 1.240 2.000 2.480
18.585 2.16
37.17 4.32 2.948 44.438
4 10 40 100
20.5
3.452 4 13.808
4.35 8.7
8.658 34.632
1.458 11.664
7.29 24.4215
7.29 72.9
143.6175
37.7122
6.000
6.000
12.000
UPAH KERJA
DALAM 1 HARI KERJA ( 8 JAM )
UPAH
NO. JENIS PEKERJA / KEAHLIAN 1 HARI 8 JAM
(Rp)
1 Pekerja 85,000.00 60,000.00 41,544.00
2 Tukang 110,000.00 70,000.00 51,930.00
3 Kepala Tukang 0.00 80,000.00 62,317.00
4 Mandor 0.00 90,000.00 72,703.00
5 Operator Alat Berat 100,000.00 90,000.00 72,703.00
6 Pembantu Operator / Mekanik 75,000.00 60,000.00 41,544.00
7 Sopir Truk 90,000.00 80,000.00 62,317.00
8 Kenek Truk 60,000.00 60,000.00 41,544.00
9 Penjaga Malam 70,000.00 70,000.00 51,930.00
Keuntungan Maksimal 0%
PEKERJA 60,000.00
TUKANG BATU/GALI 70,000.00
KEPALA TUKANG BATU 80,000.00
TUKANG KAYU 70,000.00
KEPALA TUKANG KAYU 80,000.00
TUKANG CAT / PELITUR 70,000.00
KEPALA TUKANG CAT / PELITUR 80,000.00
TUKANG BESI BETON 80,000.00
KEPALA TUKANG BESI BETON 80,000.00
TUKANG BESI PROFIL 80,000.00
KEPALA TUKANG BESI PROFIL 80,000.00
MANDOR 90,000.00
DAFTAR HARGA STANDAR BAHAN BANGUNAN
HARGA (Rp)
NO. JENIS BAHAN SAT KETERANGAN
Data 1 Data 2 Rata-Rata
1 2 3 4 5 4 5
K. BAHAN KACA
1 Kaca Polos 2 mm ( ASAHI ) m2 40,000.00 40,000.00 40,000.00
2 Kaca Polos 3 mm ( ASAHI ) m2 51,000.00 51,000.00 51,000.00
3 Kaca Polos 5 mm ( ASAHI ) m2 155,000.00 155,000.00 155,000.00
4 Kaca Rayband 5 mm ( ASAHI ) m2 120,000.00 120,000.00 120,000.00
5 Kaca Rayband 8 mm ( ASAHI ) m2 131,000.00 131,000.00 131,000.00
6 Kaca Rayband 12 mm ( ASAHI ) m2 144,000.00 144,000.00 144,000.00
7 Kaca Patri Lokal Terpasang ( ASAHI ) m2 537,000.00 537,000.00 537,000.00
8 Kaca Patri Ex.Luar Negeri Terpasang m2 3,100,000.00 3,100,000.00 3,100,000.00
9 Glass Block 20 x 20 cm ( Ex. Luar ) bh 38,000.00 38,000.00 38,000.00
10 Glass Block DN 20 x 20 cm ( Kedaung ) bh 24,000.00 24,000.00 24,000.00
M. BAHAN
1 Lempengan Besi Baja Profil Desain Galvanis m 133,333.33 133,333.33 133,333.33 800,000.00 /batang
2 Tiang Penyangga Besi st. 32 Galvanis bh 400,000.00 400,000.00 400,000.00
3 Baja Struktur (15) kg 23,500.00 23,500.00 23,500.00
4 Pipa Baja (Tiang Panjang) kg 9,500,000.00 9,500,000.00 9,500,000.00
5 Besi Pengikat Baja Profil Desain (Blocking) bh 57,500.00 57,500.00 57,500.00
6 Mur Baut Blocking 12 x 25 mm bh 2,600.00 2,600.00 2,600.00
7 Mur Baut Post 16 x 48 mm bh 2,600.00 2,600.00 2,600.00
O. ALAT TUKANG
1 Palu 0.5 kg bh 50,000.00 50,000.00 50,000.00
2 Cangkul bh 45,000.00 45,000.00 45,000.00
3 Singkup bh 55,100.00 55,100.00 55,100.00
4 Sekrop bh 55,100.00 55,100.00 55,100.00
5 Pengki bh 11,000.00 11,000.00 11,000.00
6 Linggis bh 48,000.00 48,000.00 48,000.00
7 Rool Meter 50 meter (Bahan Plastik) bh 80,000.00 80,000.00 80,000.00
8 Rool Meter 5 meter (Bahan Besi) bh 25,000.00 25,000.00 25,000.00
9 Selang Plastik untuk Waterpass dia. 0.5 cm m 1,700.00 1,700.00 1,700.00
10 Waterpass Alumunium 60 cn bh 70,000.00 70,000.00 70,000.00
P. BAHAN PERPIPAAN
1 Besi Pipa Untuk Hydrant BSP dia. 1" bt 230,000.00 230,000.00 230,000.00
2 Besi Pipa Untuk Hydrant BSP dia. 1,25" bt 268,000.00 268,000.00 268,000.00
3 Besi Pipa Untuk Hydrant BSP dia. 1,5" bt 367,000.00 367,000.00 367,000.00
4 Besi Pipa Untuk Hydrant BSP dia. 2" bt 411,000.00 411,000.00 411,000.00
5 Shower Dengan Tiang bh 200,000.00 200,000.00 200,000.00
6 Shower Tanpa Tiang bh 150,000.00 150,000.00 150,000.00
7 Kran Tembok dia 0,5" bh 25,000.00 25,000.00 25,000.00
8 Kran Tembok dia 1" bh 50,000.00 50,000.00 50,000.00
9 Kran Panas Dingin San Ei Standar bh 240,000.00 240,000.00 240,000.00
10 Tempat Sabun Porselin bh 25,000.00 25,000.00 25,000.00
11 Wastafel Lengkap TOTO LW 230 unit 900,000.00 900,000.00 900,000.00
12 Wastafel Lengkap INA unit 650,000.00 650,000.00 650,000.00
13 Closet Jongkok Porselin Warna TOTO unit 115,000.00 115,000.00 115,000.00
14 Closet Jongkok Standar Putih Porselin TOTO unit 95,000.00 95,000.00 95,000.00
15 Wastafel Bulat Warna Standar Lengkap unit 700,000.00 700,000.00 700,000.00
16 Closet Duduk Warna Standar Lengkap INA bh 950,000.00 950,000.00 950,000.00
17 Urinoar Lengkap TOTO Warna Standar Lengkap unit 650,000.00 650,000.00 650,000.00
18 Penyekat Porselin Urinoir TOTO lbr 350,000.00 350,000.00 350,000.00
19 Kitchen Zink Stainless Standar Lokal ( 1 Lobang ) bh 250,000.00 250,000.00 250,000.00
20 Kitchen Zink Stainless Non Standar Franke ( 1 Lobang ) bh 400,000.00 400,000.00 400,000.00
21 Kitchen Zink Stainless Non Standar Franke ( 2 Lobang ) bh 950,000.00 950,000.00 950,000.00
T. BAHAN MEKANIKAL
1 Kabel NYA 1 x 1.5 Prima - - -
2 Kabel NYA 1 x 2.5 Prima - - -
3 Kabel NYM 2 x 1.5 Prima - - -
4 Kabel NYM 3 x 1.5 Prima - - -
5 Kabel NYM 2 x 2.5 Prima - - -
6 Kabel NYM 3 x 2.5 Prima 9,000.00 9,000.00 9,000.00
7 Kabel NYM 4 x 2.5 Prima - - -
8 Kabel NYM 2 x 4 Prima - - -
9 Kabel NYM 3 x 4 Prima - - -
10 Kabel NYM 4 x 4 Prima - - -
11 Kabel NYM 2 x 6 Prima - - -
12 Kabel NYM 3 x 6 Prima - - -
13 Kabel NYM 4 x 6 Prima - - -
14 Kabel NYM 2 x 10 Prima - - -
15 Kabel NYM 3 x 10 Prima - - -
16 Kabel NYM 4 x 10 Prima - - -
17 Kabel NYM 4 x 16 Prima - - -
18 Kabel NYY 2 x 4 Prima - - -
19 Kabel NYY 3 x 4 Prima - - -
20 Kabel NYY 4 x 4 Prima - - -
21 Kabel NYY 2 x 6 Prima - - -
22 Kabel NYY 3 x 6 Prima - - -
23 Kabel NYY 4 x 6 Prima - - -
24 Kabel NYY 2 x 10 Prima - - -
25 Kabel NYY 3 x 10 Prima - - -
26 Kabel NYY 4 x 10 Prima - - -
27 Kabel NYY 4 x 16 Prima - - -
28 NSFB FUJI EA - 100A - - -
29 NSFB FUJI EA - 150A - - -
30 Rumah Panel 30 x 60 cm (Kosong) - - -
31 Skring Kas 2 Group Biasa - - -
32 Skring Kas 3 Group Biasa - - -
33 Skring Kas 5 Group Biasa - - -
34 MCB 1 PAS - - -
35 MCB 3 PAS - - -
36 Tahanan 50 A Merk FUJI - - -
37 Tahanan 100 A Merk FUJI - - -
38 Saklar Tunggal Standard bh 23,000.00 23,000.00 23,000.00
39 Saklar Seri Standard bh 33,500.00 33,500.00 33,500.00
40 Stop Kontak 1P 220 Volt bh 24,000.00 24,000.00 24,000.00
41 Instalasi Titik Lampu/Stop Kontak titik - - -
42 Lampu Pijar 25 watt s/d 100 watt bh 15,000.00 15,000.00 15,000.00
43 Lampu Neon TL Philip 20 watt bh 30,000.00 30,000.00 30,000.00
X. STANDARD RATA - RATA SEWA ALAT BERAT, KENDARAAN, TRUCK DAN LAINNYA
1 Asphal Finisher jam 122,400.00 122,400.00 122,400.00
2 Asphal Melting Kalte jam n/a n/a #VALUE!
3 Asphal Mixing Plant jam 3,391,400.00 3,391,400.00 3,391,400.00
4 Asphal Sprayer jam 50,000.00 50,000.00 50,000.00
1 2 3 4 5 6 7 8
PEKERJAAN PERSIAPAN
1 1 m' Pagar sementara dari kayu tinggi 2 m
1.250 btg Kayu dolken ø 8 - 10 (cm) panjang 4 m / kiau 22,000.00 27,500.00 27,500.00
5.000 kg Semen PC @ 50 kg 1,450.00 7,250.00 7,250.00
0.005 m³ Pasir ayak untuk beton 160,000.00 800.00 800.00
0.009 m³ Koral Beton 122,000.00 1,098.00 1,098.00
0.072 m³ Kayu 5/7 2,050,000.00 147,600.00 147,600.00
0.060 kg Paku berbagai ukuran (2" - 5") 17,000.00 1,020.00 1,020.00
0.400 ltr Residu 8,000.00 3,200.00 3,200.00
0.400 Oh Pekerja tak terlatih 85,000.00 34,000.00 34,000.00
0.200 Oh Tukang kayu 110,000.00 22,000.00 22,000.00
0.020 Oh Kepala tukang - - -
0.020 Oh Mandor - - -
Jumlah 244,468.00
Keuntungan Maksimal - -
Jumlah 244,468.00
Dibulatkan 244,460.00
4 1 m' Pengukuran dan pemasangan bouwplank
0.007 m³ Kayu papan 3/20 2,050,000.00 14,350.00 14,350.00
0.120 m³ Kayu balok 5/7 2,050,000.00 246,000.00 246,000.00
0.020 kg Paku berbagai ukuran (2" - 5") 17,000.00 340.00 340.00
0.100 Oh Pekerja tak terlatih 85,000.00 8,500.00 8,500.00
0.100 Oh Tukang kayu 110,000.00 11,000.00 11,000.00
0.010 Oh Kepala tukang - - -
0.005 Oh Mandor - - -
Jumlah 280,190.00
Keuntungan Maksimal - -
Jumlah 280,190.00
Dibulatkan 280,190.00
7 1 m² Membersihkan lapangan dan peralatan
0.100 Oh Pekerja tak terlatih 85,000.00 8,500.00 8,500.00
0.050 Oh Mandor - - -
Jumlah 8,500.00
Keuntungan Maksimal - -
Jumlah 8,500.00
Dibulatkan 8,500.00
HARGA
HARGA, JUMLAH HARGA
NO. INDEKS SATUAN KEBUTUHAN
SATUAN (Rp) BAHAN (Rp) UPAH (Rp) (Rp)
1 2 3 4 5 6 7 8
PEKERJAAN TANAH
1 Menggali 1 m3 tanah biasa sedalam 1 meter
0.750 OH Pekerja 85,000.00 63,750.00 63,750.00
0.025 OH Mandor - - -
Jumlah 63,750.00
Keuntungan Maksimal - -
Jumlah 63,750.00
Dibulatkan 63,750.00
2 Menggali 1 m3 tanah biasa sedalam 2 meter
0.900 OH Pekerja 85,000.00 76,500.00 76,500.00
0.045 OH Mandor - - -
Jumlah 76,500.00
Keuntungan Maksimal - -
Jumlah 76,500.00
Dibulatkan 76,500.00
8 Membuang 1 m3 tanah sejauh 150 meter
0.330 OH Pekerja 85,000.00 28,050.00 28,050.00
0.010 OH Mandor - - -
Jumlah 28,050.00
Keuntungan Maksimal - -
Jumlah 28,050.00
Dibulatkan 28,050.00
9 Mengurug kembali 1 m3 galian tanah biasa sedalam 1 meter
0.500 OH Pekerja 85,000.00 42,500.00 42,500.00
0.050 OH Mandor - - -
Jumlah 42,500.00
Keuntungan Maksimal - -
Jumlah 42,500.00
Dibulatkan 42,500.00
15 Memadatkan 1 m3 tanah (per 20 cm)
0.500 OH Pekerja 85,000.00 42,500.00 42,500.00
0.050 OH Mandor - - -
Jumlah 42,500.00
Keuntungan Maksimal - -
Jumlah 42,500.00
Dibulatkan 42,500.00
16 Mengurug 1 m3 pasir urug
1.200 m3 Pasir urug 120,000.00 144,000.00 144,000.00
0.300 OH Pekerja 85,000.00 25,500.00 25,500.00
0.010 OH Mandor - - -
Jumlah 169,500.00
Keuntungan Maksimal - -
Jumlah 169,500.00
Dibulatkan 169,500.00
HARGA
HARGA, JUMLAH HARGA
NO. INDEKS SATUAN KEBUTUHAN
SATUAN (Rp) BAHAN (Rp) UPAH (Rp) (Rp)
1 2 3 4 5 6 7 8
PEKERJAAN PONDASI
1 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 PP
1.200 M3 Batu belah 15 cm/20 cm 195,000.00 234,000.00 234,000.00
202.000 Kg Portland Cement 1,450.00 292,900.00 292,900.00
0.485 M3 Pasir Pasang 115,000.00 55,775.00 55,775.00
1.500 OH Pekerja 85,000.00 127,500.00 127,500.00
0.750 OH Tukang batu 110,000.00 82,500.00 82,500.00
0.075 OH Kepala tukang - - -
0.075 OH Mandor - - -
Jumlah 792,675.00
Keuntungan Maksimal - -
Jumlah 792,675.00
Dibulatkan 792,670.00
2 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP
1.200 M3 Batu belah 15 cm/20 cm 195,000.00 234,000.00 234,000.00
163.000 Kg Portland Cement 1,450.00 236,350.00 236,350.00
0.520 M3 Pasir Pasang 115,000.00 59,800.00 59,800.00
1.500 OH Pekerja 85,000.00 127,500.00 127,500.00
0.750 OH Tukang batu 110,000.00 82,500.00 82,500.00
0.075 OH Kepala tukang - - -
0.075 OH Mandor - - -
Jumlah 740,150.00
Keuntungan Maksimal - -
Jumlah 740,150.00
Dibulatkan 740,150.00
9 Memasang 1 m3 batu kosong (anstamping)
1.200 m3 Batu belah 15 cm/20 cm 195,000.00 234,000.00 234,000.00
0.432 m3 Pasir urug 120,000.00 51,840.00 51,840.00
0.780 OH Pekerja 85,000.00 66,300.00 66,300.00
0.390 OH Tukang batu 110,000.00 42,900.00 42,900.00
0.039 OH Kepala tukang - - -
0.039 OH Mandor - - -
Jumlah 395,040.00
Keuntungan Maksimal - -
Jumlah 395,040.00
Dibulatkan 395,040.00
HARGA
HARGA, JUMLAH HARGA
NO. INDEKS SATUAN KEBUTUHAN
SATUAN (Rp) BAHAN (Rp) UPAH (Rp) (Rp)
1 2 3 4 5 6 7 8
PEKERJAAN BETON
2 Membuat 1 m3 beton mutu f'c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
276.000 kg Portland Cement 1,450.00 400,200.00 400,200.00
0.621 m3 Pasir Beton 160,000.00 99,360.00 99,360.00
0.740 m3 Kerikil (maksimum 30 mm) 250,000.00 185,000.00 185,000.00
215.000 Liter Air 10.00 2,150.00 2,150.00
1.650 OH Pekerja 85,000.00 140,250.00 140,250.00
0.275 OH Tukang batu 110,000.00 30,250.00 30,250.00
0.028 OH Kepala tukang - - -
0.083 OH Mandor - - -
Jumlah 857,210.00
Keuntungan Maksimal - -
Jumlah 857,210.00
Dibulatkan 857,210.00
5 Membuat 1 m3 beton mutu f'c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
326.000 kg Portland Cement 1,450.00 472,700.00 472,700.00
0.543 m3 Pasir Beton 160,000.00 86,864.00 86,864.00
0.762 m3 Kerikil (maksimum 30 mm) 250,000.00 190,550.00 190,550.00
215.000 Liter Air 10.00 2,150.00 2,150.00
1.650 OH Pekerja 85,000.00 140,250.00 140,250.00
0.275 OH Tukang batu 110,000.00 30,250.00 30,250.00
0.028 OH Kepala tukang - - -
0.083 OH Mandor - - -
Jumlah 922,764.00
Keuntungan Maksimal - -
Jumlah 922,764.00
Dibulatkan 922,760.00
7 Membuat 1 m3 beton mutu f'c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
371.000 kg Portland Cement 1,450.00 537,950.00 537,950.00
0.499 m3 Pasir Beton 160,000.00 79,776.00 79,776.00
0.776 m3 Kerikil (maksimum 30 mm) 250,000.00 193,900.00 193,900.00
215.000 Liter Air 10.00 2,150.00 2,150.00
1.650 OH Pekerja 85,000.00 140,250.00 140,250.00
0.275 OH Tukang batu 110,000.00 30,250.00 30,250.00
0.028 OH Kepala tukang - - -
0.083 OH Mandor - - -
Jumlah 984,276.00
Keuntungan Maksimal - -
Jumlah 984,276.00
Dibulatkan 984,270.00
17 Pembesian 1 kg dengan besi polos atau besi ulir
1.050 kg Besi beton (polos/ulir) 9,500.00 9,975.00 9,975.00
0.150 kg Kawat beton 25,000.00 3,750.00 3,750.00
0.070 OH Pekerja 85,000.00 5,950.00 5,950.00
0.070 OH Tukang besi 110,000.00 7,700.00 7,700.00
0.007 OH Kepala tukang - - -
0.004 OH Mandor - - -
Jumlah 27,375.00
Keuntungan Maksimal - -
Jumlah 27,375.00
Dibulatkan 27,370.00
20 Memasang 1 m2 bekisting untuk pondasi
0.040 m3 Kayu kelas III 2,050,000.00 82,000.00 82,000.00
0.300 kg Paku 5 cm - 10 cm 17,000.00 5,100.00 5,100.00
0.100 Liter Minyak bekisting 8,000.00 800.00 800.00
0.520 OH Pekerja 85,000.00 44,200.00 44,200.00
0.260 OH Tukang kayu 110,000.00 28,600.00 28,600.00
0.026 OH Kepala tukang - - -
0.026 OH Mandor - - -
Jumlah 160,700.00
Keuntungan Maksimal - -
Jumlah 160,700.00
Dibulatkan 160,700.00
21 Memasang 1 m2 bekisting untuk sloof
0.045 m3 Kayu kelas III 2,050,000.00 92,250.00 92,250.00
0.300 kg Paku 5 cm - 10 cm 17,000.00 5,100.00 5,100.00
0.100 Liter Minyak bekisting 8,000.00 800.00 800.00
0.520 OH Pekerja 85,000.00 44,200.00 44,200.00
0.260 OH Tukang kayu 110,000.00 28,600.00 28,600.00
0.026 OH Kepala tukang - - -
0.026 OH Mandor - - -
Jumlah 170,950.00
Keuntungan Maksimal - -
Jumlah 170,950.00
Dibulatkan 170,950.00
22 Memasang 1 m2 bekisting untuk kolom
0.040 m3 Kayu kelas III 2,050,000.00 82,000.00 82,000.00
0.400 kg Paku 5 cm-12 cm 17,000.00 6,800.00 6,800.00
0.200 Liter Minyak bekisting 8,000.00 1,600.00 1,600.00
0.015 m3 Balok kayu kelas II 1,500,000.00 22,500.00 22,500.00
0.350 Lbr Multipleks tebal 9 mm 125,000.00 43,750.00 43,750.00
2.000 Batang Dolken kayu galam, <j) (8-10) cm, pjg 4 m 22,000.00 44,000.00 44,000.00
0.660 OH Pekerja 85,000.00 56,100.00 56,100.00
0.330 OH Tukang kayu 110,000.00 36,300.00 36,300.00
0.033 OH Kepala tukang - - -
0.033 OH Mandor - - -
Jumlah 293,050.00
Keuntungan Maksimal - -
Jumlah 293,050.00
Dibulatkan 293,050.00
23 Memasang 1 m2 bekisting untuk balok
0.040 m3 Kayu kelas III 2,050,000.00 82,000.00 82,000.00
0.400 kg Paku 5 cm-12 cm 17,000.00 6,800.00 6,800.00
0.200 Liter Minyak bekisting 8,000.00 1,600.00 1,600.00
0.018 m3 Balok kayu kelas II 1,500,000.00 27,000.00 27,000.00
0.350 Lbr Multipleks tebal 9 mm 125,000.00 43,750.00 43,750.00
2.000 Batang Dolken kayu galam, <f> (8-10) cm, pjg 4 m 22,000.00 44,000.00 44,000.00
0.660 OH Pekerja 85,000.00 56,100.00 56,100.00
0.330 OH Tukang kayu 110,000.00 36,300.00 36,300.00
0.033 OH Kepala tukang - - -
0.033 OH Mandor - - -
Jumlah 297,550.00
Keuntungan Maksimal - -
Jumlah 297,550.00
Dibulatkan 297,550.00
24 Memasang 1 m bekisting untuk plat lantai
2
1 2 3 4 5 6 7 8
PEKERJAAN DINDING
1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 2 PP
140.000 Buah Bata merah 600.00 84,000.00 84,000.00
43.500 kg Portland Cement 1,450.00 63,075.00 63,075.00
0.080 m3 Pasir pasang 115,000.00 9,200.00 9,200.00
0.600 OH Pekerja 85,000.00 51,000.00 51,000.00
0.200 OH Tukang batu 110,000.00 22,000.00 22,000.00
0.020 OH Kepala tukang - - -
0.030 OH Mandor - - -
Jumlah 229,275.00
Keuntungan Maksimal - -
Jumlah 229,275.00
Dibulatkan 229,270.00
2 Memasang 1 m dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 PP
2
1 2 3 4 5 6 7 8
PEKERJAAN PLESTERAN
3 Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm
7.776 Kg Portland Cement 1,450.00 11,275.20 11,275.20
0.023 M3 Pasir Pasang 115,000.00 2,645.00 2,645.00
0.300 OH Pekerja 85,000.00 25,500.00 25,500.00
0.150 OH Tukang batu 110,000.00 16,500.00 16,500.00
0.015 OH Kepala tukang - - -
0.015 OH Mandor - - -
Jumlah 55,920.20
Keuntungan Maksimal - -
Jumlah 55,920.20
Dibulatkan 55,920.00
4 Membuat 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm
6.240 Kg Portland Cement 1,450.00 9,048.00 9,048.00
0.024 M3 Pasir Pasang 115,000.00 2,760.00 2,760.00
0.300 OH Pekerja 85,000.00 25,500.00 25,500.00
0.150 OH Tukang batu 110,000.00 16,500.00 16,500.00
0.015 OH Kepala tukang - - -
0.015 OH Mandor - - -
Jumlah 53,808.00
Keuntungan Maksimal - -
Jumlah 53,808.00
Dibulatkan 53,800.00
20 Membuat 1 m' Plesteran Benangan Sudut 1 PC : 2 PP.
0.500 kg Portland Cement 1,450.00 725.00 725.00
0.013 m 3
Pasir Pasang 115,000.00 1,495.00 1,495.00
0.080 OH Pekerja 85,000.00 6,800.00 6,800.00
0.400 OH Tukang batu 110,000.00 44,000.00 44,000.00
0.040 OH Kepala tukang - - -
0.004 OH Mandor - - -
Jumlah 53,020.00
Keuntungan Maksimal - -
Jumlah 53,020.00
Dibulatkan 53,020.00
27 Membuat 1 m2 acian
3.250 kg Portland Cement 1,450.00 4,712.50 4,712.50
0.200 OH Pekerja 85,000.00 17,000.00 17,000.00
0.100 OH Tukang batu 110,000.00 11,000.00 11,000.00
0.010 OH Kepala tukang - - -
0.010 OH Mandor - - -
Jumlah 32,712.50
Keuntungan Maksimal - -
Jumlah 32,712.50
Dibulatkan 32,710.00
HARGA
HARGA, JUMLAH HARGA
NO. INDEKS SATUAN KEBUTUHAN
SATUAN (Rp) BAHAN (Rp) UPAH (Rp) (Rp)
1 2 3 4 5 6 7 8
PEKERJAAN LANTAI
32 Memasang 1 m2 lantai keramik ukuran (40 x 40) cm
6.100 Buah Keramik 40 X 40 Warna Unpolished 10,000.00 61,000.00 61,000.00
11.500 kg Portland Cement 1,450.00 16,675.00 16,675.00
0.045 m3 Pasir pasang 115,000.00 5,175.00 5,175.00
1.500 kg Semen warna 10,000.00 15,000.00 15,000.00
0.700 OH Pekerja 85,000.00 59,500.00 59,500.00
0.350 OH Tukang batu 110,000.00 38,500.00 38,500.00
0.035 OH Kepala tukang - - -
0.035 OH Mandor - - -
Jumlah 195,850.00
Keuntungan Maksimal - -
Jumlah 195,850.00
Dibulatkan 195,850.00
36 Memasang 1 m2 lantai keramik warna ukuran (20 x 20) cm
26.500 Buah Keramik 20 X 20 Warna / Anti Slip 3,360.00 89,040.00 89,040.00
10.400 kg Portland Cement 1,450.00 15,080.00 15,080.00
0.045 m3 Pasir pasang 115,000.00 5,175.00 5,175.00
1.620 kg Semen warna 10,000.00 16,200.00 16,200.00
0.700 OH Pekerja 85,000.00 59,500.00 59,500.00
0.350 OH Tukang batu 110,000.00 38,500.00 38,500.00
0.035 OH Kepala tukang - - -
0.035 OH Mandor - - -
Jumlah 223,495.00
Keuntungan Maksimal - -
Jumlah 223,495.00
Dibulatkan 223,490.00
54 Memasang 1 m2 dinding keramik warna ukuran (20 x 25) cm
20.500 Buah Keramik Dinding 20 X 25 3,700.00 75,850.00 75,850.00
9.300 kg Portland Cement 1,450.00 13,485.00 13,485.00
0.018 m3 Pasir pasang 115,000.00 2,070.00 2,070.00
1.940 kg Semen warna 10,000.00 19,400.00 19,400.00
0.900 OH Pekerja 85,000.00 76,500.00 76,500.00
0.450 OH Tukang batu 110,000.00 49,500.00 49,500.00
0.045 OH Kepala tukang - - -
0.045 OH Mandor - - -
Jumlah 236,805.00
Keuntungan Maksimal - -
Jumlah 236,805.00
Dibulatkan 236,800.00
55 Memasang 1 m2 lantai keramik ukuran (40 x 40) cm
6.100 Buah Keramik 40 X 40 Warna Polished 14,000.00 85,400.00 85,400.00
11.500 kg Portland Cement 1,450.00 16,675.00 16,675.00
0.045 m3 Pasir pasang 115,000.00 5,175.00 5,175.00
1.500 kg Semen warna 10,000.00 15,000.00 15,000.00
0.700 OH Pekerja 85,000.00 59,500.00 59,500.00
0.350 OH Tukang batu 110,000.00 38,500.00 38,500.00
0.035 OH Kepala tukang - - -
0.035 OH Mandor - - -
Jumlah 220,250.00
Keuntungan Maksimal - -
Jumlah 220,250.00
Dibulatkan 220,250.00
HARGA
HARGA, JUMLAH HARGA
NO INDEKS SATUAN KEBUTUHAN
SATUAN (Rp) BAHAN (Rp) UPAH (Rp) (Rp)
1 2 3 4 5 6 7 8
Jumlah 1,488,692.24
Keuntungan Maksimal - -
Jumlah 1,488,692.24
Dibulatkan 1,488,690.00
8 1 Unit Pekerjaan Jendela Type J1 + 3 Daun Jendela Bouvenlis RKB 3 Ruang
0.055 m3 Kusen Jendela Kayu Kelas II 6,065,250.00 332,982.23 332,982.23
3.723 m2 Daun Jendela Kaca Kayu Kelas II 438,450.00 1,632,437.04 1,632,437.04
- m2 Daun Jendela Kaca Kayu Kelas II (Bouvenlis) 438,450.00 - -
2.480 m 2
Kaca Polos Tebal 5 mm 188,270.00 466,909.60 466,909.60
5.000 pasang Engsel Jendela 36,850.00 184,250.00 184,250.00
5.000 pasang Kait Angin 31,850.00 159,250.00 159,250.00
2.000 pasang Kunci Selot Jendela 5 cm 26,850.00 53,700.00 53,700.00
3.000 pasang Kunci Selot Jendela Bouvenlis 26,850.00 80,550.00 80,550.00
Jumlah 2,910,078.87
Keuntungan Maksimal - -
Jumlah 2,910,078.87
Dibulatkan 2,910,070.00
9 1 Unit Pekerjaan Jendela Type J2 + 3 Daun Jendela Bouvenlis RKB 3 Ruang
0.062 m3 Kusen Jendela Kayu Kelas II 6,065,250.00 378,180.47 378,180.47
0.437 m 2
Daun Jendela Kaca Kayu Kelas II 438,450.00 191,514.96 191,514.96
- m2 Daun Jendela Kaca Kayu Kelas II (Bouvenlis) 438,450.00 - -
0.299 m2 Kaca Polos Tebal 5 mm 188,270.00 56,330.38 56,330.38
5.000 pasang Engsel Jendela 36,850.00 184,250.00 184,250.00
5.000 pasang Kait Angin 31,850.00 159,250.00 159,250.00
2.000 pasang Kunci Selot Jendela 5 cm 26,850.00 53,700.00 53,700.00
3.000 pasang Kunci Selot Jendela Bouvenlis 26,850.00 80,550.00 80,550.00
Jumlah 1,103,775.81
Keuntungan Maksimal - -
Jumlah 1,103,775.81
Dibulatkan 1,103,770.00
10 Membuat dan memasang 1 m pintu dan jendela jalusi kayu kelas II
2
626,025.81
HARGA
HARGA, JUMLAH HARGA
NO. INDEKS SATUAN KEBUTUHAN
SATUAN (Rp) BAHAN (Rp) UPAH (Rp) (Rp)
1 2 3 4 5 6 7 8
1 2 3 4 5 6 7 8
PEKERJAAN LANGIT-LANGIT
11 Memasang 1 m2 langit-langit Gypsum ukuran (120 x 240) cm, tebal 9 mm
0.364 Lembar Gypsum board 80,000.00 29,120.00 29,120.00
0.110 kg Paku Skrup 350.00 38.50 38.50
0.100 OH Pekerja 85,000.00 8,500.00 8,500.00
0.050 OH Tukang kayu 110,000.00 5,500.00 5,500.00
0.005 OH Kepala tukang - - -
0.005 OH Mandor - - -
Jumlah 43,158.50
Keuntungan Maksimal - -
Jumlah 43,158.50
Dibulatkan 43,150.00
12 Memasang 1 m2 Rangka langit-langit Hollow Alluminium Frame
3.300 m' Hollow Efektif 3.6 X 3.6 7,000.00 23,100.00 23,100.00
2.200 m' Hollow Efektif 1.6 X 3.6 5,500.00 12,100.00 12,100.00
0.110 kg Paku Sekrup 350.00 38.50 38.50
2.000 m' Rod (besi penggantung) 4,500.00 9,000.00 9,000.00
0.120 OH Pekerja 85,000.00 10,200.00 10,200.00
0.060 OH Tukang besi 110,000.00 6,600.00 6,600.00
0.006 OH Kepala tukang - - -
0.006 OH Mandor - - -
Jumlah 61,038.50
Keuntungan Maksimal - -
Jumlah 61,038.50
Dibulatkan 61,030.00
Gypsum Lembar 0.364 2.88
1 2 3 4 5 6 7 8
1 2 3 4 5 6 7 8
PEKERJAAN FINISHING
1 1 m2 Pengecatan Tembok Baru Exterior Weather shield 2X Cat Penutup
0.100 Kg Plamir 13,500.00 1,350.00 1,350.00
0.100 Kg Cat Dasar 24,000.00 2,400.00 2,400.00
0.260 Kg Cat Penutup Exterior Weather shield 2X 44,600.00 11,596.00 11,596.00
0.020 Oh Pekerja 85,000.00 1,700.00 1,700.00
0.063 Oh Tukang kayu 110,000.00 6,930.00 6,930.00
0.006 Oh Kepala tukang - - -
0.025 Oh Mandor - - -
Jumlah 23,976.00
Keuntungan Maksimal - -
Jumlah 23,976.00
Dibulatkan 23,970.00
2 1 m2 Pengecatan Tembok Baru Interior 2X Cat Penutup
0.100 Kg Plamir 13,500.00 1,350.00 1,350.00
0.100 Kg Cat Dasar 24,000.00 2,400.00 2,400.00
0.260 Kg Cat Penutup Interior 35,000.00 9,100.00 9,100.00
0.020 Oh Pekerja 85,000.00 1,700.00 1,700.00
0.063 Oh Tukang kayu 110,000.00 6,930.00 6,930.00
0.006 Oh Kepala tukang - - -
0.025 Oh Mandor - - -
Jumlah 21,480.00
Keuntungan Maksimal - -
Jumlah 21,480.00
Dibulatkan 21,480.00
3 1 m2 Pengecatan Plafond 2X Cat Penutup
0.110 Kg Plamir 13,500.00 1,485.00 1,485.00
0.100 Kg Cat Dasar 24,000.00 2,400.00 2,400.00
0.130 Kg Cat Penutup Interior 35,000.00 4,550.00 4,550.00
1.000 Ls Steger Werk 1,000.00 1,000.00 1,000.00
0.130 Oh Pekerja 85,000.00 11,050.00 11,050.00
0.260 Oh Tukang Cat 110,000.00 28,600.00 28,600.00
0.020 Oh Kepala tukang - - -
0.010 Oh Mandor - - -
Jumlah 49,085.00
Keuntungan Maksimal - -
Jumlah 49,085.00
Dibulatkan 49,080.00
5 Melabur 1 m² bidang kayu dengan politur
0.150 Ltr Politur 55,000.00 8,250.00 8,250.00
0.372 Ltr Politur Jadi 125,000.00 46,500.00 46,500.00
2.000 Lbr Ampelas 10,600.00 21,200.00 21,200.00
0.020 Oh Pekerja 85,000.00 1,700.00 1,700.00
0.060 Oh Tukang kayu 110,000.00 6,600.00 6,600.00
0.016 Oh Kepala tukang - - -
0.003 Oh Mandor - - -
Jumlah 84,250.00
Keuntungan Maksimal - -
Jumlah 84,250.00
Dibulatkan 84,250.00
HARGA
HARGA, JUMLAH HARGA
NO INDEKS SATUAN KEBUTUHAN
SATUAN (Rp) BAHAN (Rp) UPAH (Rp) (Rp)
1 2 3 4 5 6 7 8
PEKERJAAN ELEKTRIKAL
1 Memasang Lampu TL Twister 24.W + Fitting
1.000 bh Lampu TL Twister 24.W 78,000.00 78,000.00 78,000.00
1.000 bh Fittings 17,000.00 17,000.00 17,000.00
5.000 % Perlengkapan - - 3,900.00
0.010 Oh Pembantuk tukang listrik 85,000.00 850.00 850.00
0.010 Oh Tukang listrik 110,000.00 1,100.00 1,100.00
0.001 Oh Kepala tukang listrik - - -
0.001 Oh Mandor - - -
Jumlah 100,850.00
Keuntungan Maksimal - -
Jumlah 100,850.00
Dibulatkan 100,850.00
2 Memasang Lampu TL Twister 24.W + Fitting
1.000 bh Lampu TL Twister 12.W 54,000.00 54,000.00 54,000.00
1.000 bh Fittings 17,000.00 17,000.00 17,000.00
5.000 % Perlengkapan - - 2,700.00
0.010 Oh Pembantuk tukang listrik 85,000.00 850.00 850.00
0.010 Oh Tukang listrik 110,000.00 1,100.00 1,100.00
0.001 Oh Kepala tukang listrik - - -
0.001 Oh Mandor - - -
Jumlah 75,650.00
Keuntungan Maksimal - -
Jumlah 75,650.00
Dibulatkan 75,650.00
3 Memasang Stop Kontak 1P 220 Volt, Wall Type
1.000 bh Stop Kontak 1P 220 Volt 24,000.00 24,000.00 24,000.00
5.000 % Perlengkapan - - 1,200.00
0.025 Oh Pembantuk tukang listrik 85,000.00 2,125.00 2,125.00
0.025 Oh Tukang listrik 110,000.00 2,750.00 2,750.00
0.017 Oh Kepala tukang listrik - - -
0.014 Oh Mandor - - -
Jumlah 30,075.00
Keuntungan Maksimal - -
Jumlah 30,075.00
Dibulatkan 30,070.00
4 Memasang Saklar Tunggal
1.000 bh Saklar Tunggal 23,000.00 23,000.00 23,000.00
5.000 % Perlengkapan - - 1,150.00
0.025 Oh Pembantuk tukang listrik 85,000.00 2,125.00 2,125.00
0.025 Oh Tukang listrik 110,000.00 2,750.00 2,750.00
0.017 Oh Kepala tukang listrik - - -
0.014 Oh Mandor - - -
Jumlah 29,025.00
Keuntungan Maksimal - -
Jumlah 29,025.00
Dibulatkan 29,020.00
5 Memasang Saklar Ganda
1.000 bh Saklar Ganda 33,500.00 33,500.00 33,500.00
5.000 % Perlengkapan - - 1,675.00
0.025 Oh Pembantuk tukang listrik 85,000.00 2,125.00 2,125.00
0.025 Oh Tukang listrik 110,000.00 2,750.00 2,750.00
0.017 Oh Kepala tukang listrik - - -
0.014 Oh Mandor - - -
Jumlah 40,050.00
Keuntungan Maksimal - -
Jumlah 40,050.00
Dibulatkan 40,050.00
6 Memasang Instalasi Titik Lampu
1.100 m' Kabel NYM 3 X 2,5 9,000.00 9,900.00 9,900.00
1.050 m' Pipa Conduite dia 20 mm 6,700.00 7,035.00 7,035.00
5.000 % Perlengkapan - - 495.00
0.015 Oh Pembantuk tukang listrik 85,000.00 1,275.00 1,275.00
0.150 Oh Tukang listrik 110,000.00 16,500.00 16,500.00
0.018 Oh Kepala tukang listrik - - -
0.015 Oh Mandor - - -
Jumlah 35,205.00
Keuntungan Maksimal - -
Jumlah 35,205.00
Dibulatkan 35,200.00
6 Memasang Instalasi Stop Kontak
1.100 m' Kabel NYM 3 X 2,5 9,000.00 9,900.00 9,900.00
1.050 m' Pipa Conduite dia 20 mm 6,700.00 7,035.00 7,035.00
5.000 % Perlengkapan - - 495.00
0.015 Oh Pembantuk tukang listrik 85,000.00 1,275.00 1,275.00
0.150 Oh Tukang listrik 110,000.00 16,500.00 16,500.00
0.018 Oh Kepala tukang listrik - - -
0.015 Oh Mandor - - -
Jumlah 35,205.00
Keuntungan Maksimal - -
Jumlah 35,205.00
Dibulatkan 35,200.00
HARGA
HARGA, JUMLAH HARGA
NO. INDEKS SATUAN KEBUTUHAN
SATUAN (Rp) BAHAN (Rp) UPAH (Rp) (Rp)
1 2 3 4 5 6 7 8
Diameter nominal
No. Penamaan Luas penampang Nominal (L) (cm2)
(d) (mm)
1 P.6 6 0.2827
2 P.8 8 0.5027
3 P.10 10 0.7854
4 P.12 12 1.131
5 P.14 14 1.539
6 P.16 16 2.011
7 P.19 19 2.835
8 P.22 22 3.801
9 P.25 25 4.909
10 P.28 28 6.158
11 P.32 32 8.042
SNI 07-2052-2002 Baja Tulangan Beton
0.222
0.395
0.617
0.888
1.12
1.58
2.23
2.98
3.85
4.83
6.31