Excavation Heavy Equipment Site Operatives All excavating equipment to be fitted with reversing
alarm
Soil moving, Controlled/assisted by flag man
Collapse of Daily inspection of excavation works.
excavation, Only employ experienced and trained operators
Overturning of Excavations to be carried out under excavation permit
3 4 12 1 4 4
machines All excavations to be protected by rigid barricades
Regular visual check of slopes
Protective system to be implemented depending on soil
classification, depth of cut, water content of soil,
changes due to weather and climate or other operations
local to the excavation
Excavation Moving excavation Site Operatives Operative all wear high visibility jacket
equipment on site Awareness with operatives and drivers of equipment of
each other workspace
4 4 16 Supervisors to monitor adherence 2 4 8
Equipment to move slow and guided by operative
All equipment to have flashing amber light
Ensure sufficient lighting of the site
Excavation Transport of Site Operatives Respect speed limit on site : 20 km/hr
excavated soil 3 4 12 Use headlights, amber light and back alarm 2 3 6
No overtaking
Excavation Falling of sand Injured, 4 4 16 Banks man and riggers to watch movement of sand 2 4 8
Sides of excavation with a good gradient
Suffocation,
Buried alive
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Rev.: 0
METHOD STATEMENT:
Preparation, Backfilling and Compaction
Date: 02-11-2019 Page: 2 of 2
Excavation Control of dust Surrounding Avoid as much as possible other activities around the
workers 3 4 12 1 4 4
area of ongoing excavation works.
Note: A cubic meter of sand weighted over 1.50 ton, asses the risk
1 -8 Low Risk – Work can commence
9 -12 Medium Risk – Reduce risk further or increase supervision
12 – 25 High Risk – Must be mitigated