Facility / Site: TATAOUINE Location within Site: TATAOUINE Permit No: Permit Type: Date:
Slips trips and fall Check The Work Area to avoid Slips Eni ERP
1. Electrical work: Trips Fall.
Approach the equipment Torsion /back injury /hernia First aider in the site
(electric, hand tool, cable Two person at least to carry the heavy
Air conditioning unit) to work Hand injury loads First aid kit available
spot (manual handling)
PPE
1. Connected the electrical Electric failure, electric shocks Use all PPE Eni ERP
cable with Air conditioning
unit Injuries wounds Good supervision First aider in the site
Fire and burns First aid kit First aid kit available
2. Commissioning/ Energizing Equipment/ Asset damage Work shall be carried as per PTW Eni ERP
the installed Air conditioning procedure
unit Electric shock/ Electrocution/ Fire First aider in the site
Strictly follow electrical procedure
Hazardous area First aid kit available
Follow Manufacturer instruction.
Incompetent person.
Deploy qualified and competent
electrical person.
Approved By