Anda di halaman 1dari 81

1

DAFTAR HARGA SATUAN UPAH


DKI JAKARTA TAHUN 2014

Harga Satuan
No Jenis Tenaga Kerja Kode Satuan
( Rp./Hari )
1 2 3 4 5

1. PEKERJA L01 Orang/Hari/jam Rp 102,920.00

2. TUKANG L02 Orang/Hari/jam Rp 121,230.00

3 KEPALA TUKANG L.03 Orang/Hari/jam Rp 139,574.00

4 MANDOR L04 Orang/Hari/jam Rp 157,901.00

5 OPERATOR L05 Orang/Hari/jam Rp 157,901.00

6 PEMBANTU OPERATOR L06 Orang/Hari/jam Rp 121,230.00

7 SUPIR/DRIVER L07 Orang/Hari/jam Rp 157,901.00

8 PEMBANTU SUPIR/DRIVER L08 Orang/Hari/jam Rp 121,230.00

9 MEKANIK L09 Orang/Hari/jam Rp 150,000.00

10 PEMBANTU MEKANIK L10 Orang/Hari/jam Rp 121,230.00


2
FTAR HARGA SATUAN UPAH
DKI JAKARTA TAHUN 2014

Harga Satuan
( Rp./Jam )
6

12,865.00

15,153.75

17,446.75

19,737.63

19,737.63

15,153.75

19,737.63

15,153.75

18,750.00

15,153.75
DAFTAR HARGA SATUAN BAHAN
Provinsi DKI JAKARTA
PERIODE JANUARI 2014

NO. KOMPONEN SATUAN HARGA SATUAN

1 Air bersih liter 100.00


2 Alumunium foil roll 298,000.00
3 Alumunium foil ex.Insol 628 P1mx60 m m2 4,966.67
4 Amplas Lbr 4,000.00
5 Batu alam paras m2 125,000.00
6 Batu alam paras bh 7,812.50
7 Batu Bata bh 611.33
8 Batu kali m3 185,000.00
9 Besi angkur f 8 mm kg 9,282.70
10 Besi beton polos kg 12,026.67
11 Besi beton f 12 mm kg 9,252.34
12 Besi hollow 20x40mm btg 20,000.00
13 Besi hollow 40x40mm btg 24,000.00
14 Beton Readymix K-175 m3 785,000.00
15 Beton Readymix K-250 m3 820,000.00
16 Cat dasar matex kg 20,568.00
17 Cat tembok (dalam) putih & warna isi 20.5 ltr / 28 kg kg 39,668.10
18 Cat melamine liter 54,000.00
19 Cat melamine jadi liter 75,000.00
20 Dolken kayu Æ 8 s/d 10 batang 35,000.00
21 door holder bh 265,000.00
22 Engsel Pintu Ecostyle Selefb 11 pasang 36,000.00
23 Engsel Pintu Ecostyle Selefb 11 bh 18,000.00
24 Engsel Jendela casement 16" pasang 65,000.00
25 Engsel Jendela casement 16" bh 32,500.00
26 Floor Drain stanlesss bh 135,000.00
27 genteng keramik bh 10,700.00
28 nok genteng kanmuri bh 19,400.00
29 Glass block bh 20,000.00
30 Granit ukuran 60x60 cm ex roman, premium m2 245,000.00
31 Granit ukuran 60x60 cm ex roman bh 61,250.00
32 Granit Plint uk 10x60 cm bh 23,000.00
33 Gypsum board 9 mm lbr 68,000.00
34 Hak Angin Biasa pasang 25,000.00
35 Hak Angin Biasa bh 12,500.00
36 Kaca cermin 5mm ex. Asahi Mas m2 145,800.00
37 Kaca 8 mm ex. Asahi Mas m2 155,000.00
38 Kaso klam 4 x 6 m3 5,400,000.00
39 Kaso klam 5 x 7 m3 5,400,000.00
40 Kawat beton Kg 20,000.00
41 Kayu 5/10 m3 5,400,000.00
42 kayu kasau 5/7 Batang 30,000.00
NO. KOMPONEN SATUAN HARGA SATUAN

kayu kelas II m3 4,750,000.00


43 Kayu Kelas III m3 5,500,000.00
44 Keramik ex Roman uk.30x30cm gol D m2 105,000.00
45 Keramik ex Roman uk.30x30cm gol D bh 8,750.00
46 keramik plin 10x30 cm bh 17,000.00
47 keramik dinding 30x60 cm ex.Roman match gol C m2 170,000.00
48 keramik dinding 30x60 cm ex.Roman match gol C bh 28,333.33
49 Kloset duduk bh 2,250,000.00
50 Koral beton m3 264,120.00
51 Kran setara TOTO Type T 23 B 13 bh 175,000.00
52 kran kitchen san Ei bh 155,000.00
53 Kunci silinder bh 130,000.00
54 Kunci slot double bh 125,000.00
55 Lem kayu kg 30,285.00
56 List shadow ine 10x10mm m 10,000.00
57 Listplank GRC m' 20,000.00
58 minyak bekisting liter 24,000.00
59 Main truss C-750 t=0,75 m' 18,150.00
60 Roof buttom/reng R33-0,45 m' 8,400.00
61 Self driiving screw ∅ 6x20mm (trusss screw) bh 650.00
62 Self driiving screw ∅ 4x16mm (bottum trusss screw) bh 525.00
63 Angle clip 50x50cm bh 1,750.00
64 Dinabolt ∅ 12x120mm bh 1,800.00
65 Nok setara Karang Pilang kg
66 Paku 10 cm Kg 16,300.00
67 Paku 5 cm Kg 17,300.00
68 Paku 7 cm Kg 16,500.00
69 Papan cor 2/20 Lembar 32,000.00
70 Papan kayu 3/20 m3 5,000,000.00
71 Papan kayu 3/30 m3 5,000,000.00
72 Pasir beton m3 277,385.00
73 Pasir pasang m3 282,536.00
74 Pasir urug m3 279,224.00
75 Pipa 4 m (PVC) 1/2" m' 3,932.50
76 Pipa 4 m (PVC) 3/4" m' 5,417.50
77 Pipa 4 m (PVC) 1" m' 7,397.50
78 Pipa 4 m (PVC) 1 1/2" m' 12,760.00
79 Pipa 4 m (PVC) 2" m' 16,307.50
80 Pipa 4 m (PVC) 2,5" m' 23,815.00
81 Pipa 4 m (PVC) 3" m' 32,120.00
82 Pipa 4 m (PVC) 4" m' 53,240.00
83 Pipa 4 m (PVC) 6" m' 123,722.50
84 Pintu PVC kamar mandi unit 1,250,000.00
85 Plamir kg 10,600.00
86 Plywood 9 mm Lembar 176,040.00
87 Kusen Profil Aluminium 3" m' 97,000.00
88 Rangka jendela aluminium 3" m' 97,000.00
NO. KOMPONEN SATUAN HARGA SATUAN

89 Roofdrain stainless 3" bh 52,000.00


90 seal tape bh 2,500.00
91 sealant m1 19,608.33
92 sealant /silicone tube 40,000.00
93 Semen Portland tiga roda 50 kg zak 65,185.00
94 Semen Portland Kg 1,303.70
95 Semen warna kg 16,000.00
96 Skrup kg 25,000.00
97 Skrup fisher bh 2,500.00
98 Shower TX 438 S unit 285,800.00
99 Shower kran TX 443 SN unit 652,500.00
100 Wastafel setara TOTO bh 550,000.00
101 waterproofing membrane bitithane 3000 m2 90,000.00
102 zink bh 673,000.00
103 water drain bh 232,000.00
104 Toren air penguin TB 70 / 650 liter unit 950,000.00
NO. KOMPONEN SATUAN HARGA SATUAN

DAFTAR HARGA SATUAN PERALATAN

NO. SATUAN HARGA SATUAN

1 Material Hoist set 285,500


2 Scafolding Set 5,250
3 Concrete Pump Jam 37,500
4 Concrete Vibrator Jam 23,700
5 Stamper Jam 8,700
6 Mesin Las Jam 22,800
7 Genset Jam 35,250
8 Pompa Air Jam 19,000
9 Bar Cutter Jam 13,250
10 Bar Bender Jam 13,250
7

DAFTAR HARGA SEWA PERALATAN


DKI JAKARTA TAHUN 2014

BIAYA SEWA
No. U R A I A N SATUAN
( Rp.)
1 2 3 4
1. MESIN GILING HARI 400,000.00
2. PONTON PANCANG HARI 1,750,000.00
3. PERALATAN PANCANG HARI 475,000.00
4. C RAN E HARI 1,600,000.00
5. JACK SNIPER HARI 225,000.00
6. M E S I N LAS HARI 350,000.00
7. BOR BETON HARI 150,000.00
8. BOR BETON MATA INTAN HARI 275,000.00
9. VIBRO COMPACTOR HARI 1,100,000.00
10. EXAVATOR HARI 1,500,000.00
11. BULDOZER HARI 1,400,000.00
12. S TAM PE R HARI 150,000.00
13. THEODOLITH HARI 75,000.00
14. WATERPASS HARI 45,000.00
15. COMPRESSOR HARI 550,000.00
16. PERANCAH KERJA HARI 275,000.00
17. GRADER HARI 1,400,000.00
DAFTAR ANALISIS HARGA SATUAN PEKERJAAN ( AHSP)
SNI .2014 DPU BIDANG CIPTA KARYA

ANALISA SNI 2014 PU BIDANG CIPTA KARYA


No Sat Kebutuhan Kode Sat Koefisien Harga Satuan Jumlah

A. PEKERJAAN PERSIAPAN
A.2.2.1.4
1 Pengukuran & Pemasangan Bouwplank
1 m' Pekerja L01 Oh 0.100 Rp 102,920 Rp 10,292.00
Tukang Kayu L02 Oh 0.100 Rp 121,230 Rp 12,123.00
Kepala Tukang L03 Oh 0.010 Rp 139,574 Rp 1,395.74
Mandor L04 Oh 0.005 Rp 157,901 Rp 789.51
kayu 5/7 kls III btg 0.012 Rp 30,000 Rp 360.00
Paku biasa 5-7 cm kg 0.020 Rp 16,500 Rp 330.00
Papan kayu 3/20`klas III m3 0.007 Rp 5,000,000 Rp 35,000.00
Jumlah harga Rp 60,290.25
Profit +overhead 10% Rp 6,029.02
Total HSP Rp 66,319.27
Pembulatan Rp 66,320.00
B PEKERJAAN GALIAN DAN URUGAN
1 A.2.3.1.2
Mengali 1 m3 tanah biasa sedalam 2 meter
m3 Pekerja L01 Oh 0.900 Rp 102,920 Rp 92,628.00
Mandor L04 Oh 0.045 Rp 157,901 Rp 7,105.55

Jumlah harga Rp 99,733.55


Profit +overhead 10% Rp 9,973.35
Total HSP Rp 109,706.90
Pembulatan Rp 109,710.00
2 A.2.3.1.11
Pengurugan 1m 3 dengan pasir
Pekerja L.01 Oh 0.300 Rp 102,920 Rp 30,876.00
M3 Mandor L.04 Oh 0.010 Rp 102,920 Rp 1,029.20
Pasir urug m3 1.200 Rp 279,224 Rp 335,068.80

Jumlah harga Rp 366,974.00


Profit +overhead 10% Rp 36,697.40
Total HSP Rp 403,671.40
Pembulatan Rp 403,670.00
3 A.2.3.1.9.
Pengurugan kembali 1m 3 dengan galian tanah

M3 Pekerja L.01 Oh 0.500 Rp 102,920 Rp 51,460.00


Mandor L.04 Oh 0.050 Rp 102,920 Rp 5,146.00
Jumlah harga Rp 56,606.00
Profit +overhead 10% Rp 5,660.60
Total HSP Rp 62,266.60
Pembulatan Rp 62,270.00
4 A.2.3.1.10.
Pemadatan tanah 1 m3 tanah (per 20 cm)

M3 Pekerja L.01 Oh 0.500 Rp 102,920 Rp 51,460.00


Mandor L.04 Oh 0.050 Rp 102,920 Rp 5,146.00
Jumlah harga Rp 56,606.00
Profit +overhead 10% Rp 5,660.60
Total HSP Rp 62,266.60
Pembulatan Rp 62,270.00
C PEKERJAAN PONDASI
1 A.2.3.1.3.
Pemasangan 1 m3 pondasi batu belah 1 PS:5 PP
M3 Pekerja L.01 Oh 1.500 102,920 Rp 154,380.00
Tukang batu L.02 Oh 0.750 121,230 Rp 90,922.50
Kepala Tukang L.03 Oh 0.075 139,574 Rp 10,468.05
Mandor L.04 Oh 0.075 157,901 Rp 11,842.58
Portland Semen kg 136.00 1,304 Rp 177,303.20
Pasir pasang M3 0.5440 282,536 Rp 153,699.58
batu belah/ batu kali M3 1.200 185,000 Rp 222,000.00
Jumlah harga Rp 820,615.91
Profit +overhead 10% Rp 82,061.59
Total HSP Rp 902,677.50
Pembulatan Rp 902,680.00

D PEKERJAAN KONSTRUKSI BETON


1 A.4.1.1.28.
Membuat 1 m3 pondasi beton bertulang (150kg besi+ bekisting)
Pekerja L.01 Oh 5.300 102,920 Rp 545,476.00
Tukang batu L.02 Oh 0.275 121,230 Rp 33,338.25
Tukang kayu L.02 Oh 1.300 139,574 Rp 181,446.20
Tukang besi L.04 Oh 1.050 157,901 Rp 165,796.05
Kepala Tukang L.03 Oh 0.262 139,574 Rp 36,568.39
Mandor L.04 Oh 0.265 157,901 Rp 41,843.77
Kayu kelas III M3 0.20 5,500,000 Rp 1,100,000.00
Paku 5 cm-12 cm kg 1.50 16,500 Rp 24,750.00
Minyak bekisting liter 0.40 24,000 Rp 9,600.00
besi beton polos kg 157.50 12,027 Rp 1,894,200.53
Kawat beton kg 2.25 20,000 Rp 45,000.00
Portland Semen kg 336.00 1,304 Rp 438,043.20
Pasir Beton M3 0.5400 277,385 Rp 149,787.90
Kerikil Beton (mak 30mm) M3 0.810 264,120 Rp 213,937.20
Jumlah harga Rp 4,879,787.48
Profit +overhead 10% Rp 487,978.75
Total HSP Rp 5,367,766.23
Pembulatan Rp 5,367,770.00

2 A.4.1.1.1.
Membuat lantai kerja 1 m3 beton mutu f'c = 7.4 Mpa (K-100),
M3 Pekerja L.01 Oh 1.650 102,920 Rp 169,818.00
Tukang batu L.02 Oh 0.275 121,230 Rp 33,338.25
Kepala Tukang L.03 Oh 0.028 139,574 Rp 3,908.07
Mandor L.04 Oh 0.083 157,901 Rp 13,105.78
Portland Semen kg 247 1,304 Rp 322,013.90
Pasir Beton M3 0.869 277,385 Rp 241,047.57
Kerikil Beton (mak 30mm) M3 0.999 264,120 Rp 263,855.88
Air Liter 215 100 Rp 21,500.00
Jumlah harga Rp 1,068,587.45
Profit +overhead 10% Rp 106,858.75
Total HSP Rp 1,175,446.20
Pembulatan Rp 1,175,450.00

3 A.4.1.1.35.
Membuat 1 m' kolom praktis beton bertulang (11x11) cm
1m ' Pekerja L.01 Oh 0.180 102,920 Rp 18,525.60
Tukang batu L.02 Oh 0.020 121,230 Rp 2,424.60
Tukang kayu L.02 Oh 0.020 139,574 Rp 2,791.48
Tukang besi L.02 Oh 0.020 157,901 Rp 3,158.02
Kepala Tukang L.03 Oh 0.006 5,500,000 Rp 33,000.00
Mandor L.04 Oh 0.009 17,300 Rp 155.70
kayu kelas III m3 0.002 1,304 Rp 2.61
Paku 5cm-12cm kg 0.010 17,300 Rp 173.00
minyak bekisting liter 1.200 24,000 Rp 28,800.00
besi beton polos kg 3.000 12,027 Rp 36,080.01
kawat beton kg 0.450 20,000 Rp 9,000.00
Semen portland kg 4.000 1,304 Rp 5,214.80
Pasir Beton m3 0.006 277,385 Rp 1,664.31
Kerikil m3 0.009 264,120 Rp 2,377.08
Jumlah harga Rp 143,367.21
Profit +overhead 10% Rp 14,336.72
Total HSP Rp 157,703.93
Pembulatan Rp 157,700.00
E PEKERJAAN ARSITEKTUR
1 PEKERJAAN DINDING PLESTER / ACI
a A.4.4.1.10
Pemasang 1 m2 dinding bata merah tebal 1/2 bata campuran 1 sp: 5 pp
1 m2 Pekerja L.01 Oh 0.300 102,920 Rp 30,876.00
Tukang batu L.02 Oh 0.100 121,230 Rp 12,123.00
Kepala Tukang L.03 Oh 0.010 139,574 Rp 1,395.74
Mandor L.04 Oh 0.015 157,901 Rp 2,368.52
Bata merah m 3
70.000 611 Rp 42,793.10
Semen portland kg 9.680 1,304 Rp 12,619.82
Pasir pasang m 3
0.045 282,536 Rp 12,714.12
Jumlah harga Rp 114,890.29
Profit +overhead 10% Rp 11,489.03
Total HSP Rp 126,379.32
Pembulatan Rp 126,380.00
b A.4.4.2.5
Pemasangan 1 m2 plesteran 1 SP: 5PP, tebal 15 mm
1 m2 Pekerja L.01 Oh 0.300 102,920 Rp 30,876.00
Tukang batu L.02 Oh 0.150 121,230 Rp 18,184.50
Kepala Tukang L.03 Oh 0.015 139,574 Rp 2,093.61
Mandor L.04 Oh 0.015 157,901 Rp 2,368.52
Semen portland (SP) kg 5.184 1,304 Rp 6,758.38
Pasir pasang (PP) m 3
0.026 282,536 Rp 7,345.94
Jumlah harga Rp 67,626.94
Profit +overhead 10% Rp 6,762.69
Total HSP Rp 74,389.64
Pembulatan Rp 74,390.00
c A.4.4.2.27.
Pemasangan 1 m2 acian
1 m2 Pekerja L.01 Oh 0.200 102,920 Rp 20,584.00
Tukang batu L.02 Oh 0.100 121,230 Rp 12,123.00
Kepala Tukang L.03 Oh 0.010 139,574 Rp 1,395.74
Mandor L.04 Oh 0.010 157,901 Rp 1,579.01
Semen portland kg 3.250 1,304 Rp 4,237.03
Jumlah harga Rp 39,918.78
Profit +overhead 10% Rp 3,991.88
Total HSP Rp 43,910.65
Pembulatan Rp 43,910.00
d A.4.4.1.23
Asumsi Pemasangan 1 m2 glass block ukuran 20x20 cm
1 m2 Pekerja L.01 Oh 0.300 102,920 Rp 30,876.00
Tukang batu L.02 Oh 0.100 121,230 Rp 12,123.00
Kepala Tukang L.03 Oh 0.010 139,574 Rp 1,395.74
Mandor L.04 Oh 0.015 157,901 Rp 2,368.52
glass block bh 25.000 20,000 Rp 500,000.00
Semen portland (SP) kg 11.000 1,304
Jumlah harga Rp 546,763.26
Profit +overhead 10% Rp 54,676.33
Total HSP Rp 601,439.58
Pembulatan Rp 601,440.00
2 PEKERJAAN DINDING
a A.4.4.3.54.
Pemasangan 1 m2 dinding keramik ukuran (30x60) cm
1 m2 Pekerja L.01 Oh 0.900 102,920 Rp 92,628.00
Tukang batu L.02 Oh 0.450 121,230 Rp 54,553.50
Kepala Tukang L.03 Oh 0.045 139,574 Rp 6,280.83
Mandor L.04 Oh 0.045 157,901 Rp 7,105.55
keramik dinding Bh 11.550 28,333 Rp 327,250.00
Portland cement kg 9.300 1,304 Rp 12,124.41
Pasir pasang m3 0.018 282,536 Rp 5,085.65
Semen warna kg 1.940 16,000 Rp 31,040.00
Jumlah harga Rp 536,067.93
Profit +overhead 10% Rp 53,606.79
Total HSP Rp 589,674.73
Pembulatan Rp 589,670.00
b A.4.4.3.57.
Pemasangan 1 m2 dinding Batu alam paras
1 m2 Pekerja L.01 Oh 0.700 102,920 Rp 72,044.00
Tukang batu L.02 Oh 0.350 121,230 Rp 42,430.50
Kepala Tukang L.03 Oh 0.035 139,574 Rp 4,885.09
Mandor L.04 Oh 0.035 157,901 Rp 5,526.54
Batu alam paras Bh 1.100 7,813 Rp 8,593.75
Portland cement kg 11.750 1,304 Rp 15,318.48
Pasir pasang m3 0.035 282,536 Rp 9,888.76
Jumlah harga Rp 158,687.11
Profit +overhead 10% Rp 15,868.71
Total HSP Rp 174,555.82
Pembulatan Rp 174,560.00
c A.4.4.2.20 Asumsi.
Pemasangan 1 m' Profil dinding bergaris 3cm + tebal acian ban banan t=2,5cm
1 m' Pekerja L.01 Oh 0.080 102,920 Rp 8,233.60
Tukang batu L.02 Oh 0.400 121,230 Rp 48,492.00
Kepala Tukang L.03 Oh 0.040 139,574 Rp 5,582.96
Mandor L.04 Oh 0.004 157,901 Rp 631.60
Portland cement kg 3.250 1,304 Rp 4,237.03
Pasir pasang m3 0.013 282,536 Rp 3,672.97
Jumlah harga Rp 70,850.16
Profit +overhead 10% Rp 7,085.02
Total HSP Rp 77,935.17
Pembulatan Rp 77,940.00

c A.4.2.1.11.
Pemasangan 1 m' kusen alluminium
1 m' Pekerja L.01 Oh 0.043 102,920 Rp 4,425.56
Tukang allumunium L.03 Oh 0.043 121,230 Rp 5,212.89
Kepala Tukang L.03 Oh 0.004 139,574 Rp 600.17
Mandor L.04 Oh 0.002 157,901 Rp 331.59
profil allumunium m' 1.100 97,000 Rp 106,700.00
skrup fixer bh 2.000 2,500 Rp 5,000.00
sealant tube 0.060 40,000 Rp 2,400.00
Jumlah harga Rp 124,670.21
Profit +overhead 10% Rp 12,467.02
Total HSP Rp 137,137.23
Pembulatan Rp 137,140.00
d A.4.6.2.17.
Pemasangan 1 m2 kaca tebal 5mm
1 m2 Pekerja L.01 Oh 0.015 102,920 Rp 1,543.80
Tukang khusus allu L.03 Oh 0.170 121,230 Rp 20,609.10
Kepala Tukang L.03 Oh 0.015 139,574 Rp 2,093.61
Mandor L.04 Oh 0.0008 157,901 Rp 126.32
Kaca tebal 5mm m2 1.100 155,000 Rp 170,500.00
sealant kg 0.050 19,608 Rp 980.42
Jumlah harga Rp 195,853.25
Profit +overhead 10% Rp 19,585.32
Total HSP Rp 215,438.57
Pembulatan Rp 215,440.00
e A.4.6.2.18.
Pemasangan 1 m2 kaca tebal 8mm
1m 2 Pekerja L.01 Oh 0.017 102,920 Rp 1,749.64
Tukang khusus allu L.03 Oh 0.170 121,230 Rp 20,609.10
Kepala Tukang L.03 Oh 0.017 139,574 Rp 2,372.76
Mandor L.04 Oh 0.0009 157,901 Rp 142.11
Kaca tebal 8mm m2 1.100 155,000 Rp 170,500.00
sealant kg 0.070 19,608 Rp 1,372.58
Jumlah harga Rp 196,746.19
Profit +overhead 10% Rp 19,674.62
Total HSP Rp 216,420.81
Pembulatan Rp 216,420.00
3 PEKERJAAN LANTAI
a A.4.4.3.5.
Pemasangan 1 m2 lantai keramik ukuran (30x30) cm
1 m2 Pekerja L.01 Oh 0.260 102,920 Rp 26,759.20
Tukang batu L.02 Oh 0.130 121,230 Rp 15,759.90
Kepala Tukang L.03 Oh 0.013 139,574 Rp 1,814.46
Mandor L.04 Oh 0.013 157,901 Rp 2,052.71
Lantai keramik Bh 11.870 8,750 Rp 103,862.50
Portland cement kg 10.000 1,304 Rp 13,037.00
Pasir pasang m 3
0.045 282,536 Rp 12,714.12
Semen warna kg 1.500 16,000 Rp 24,000.00
Jumlah harga Rp 199,999.90
Profit +overhead 10% Rp 19,999.99
Total HSP Rp 219,999.88
Pembulatan Rp 220,000.00
a A.4.4.3.13.
Pemasangan 1 m2 lantai granite ukuran (60x60) cm
1 m2 Pekerja L.01 Oh 0.240 102,920 Rp 24,700.80
Tukang batu L.02 Oh 0.120 121,230 Rp 14,547.60
Kepala Tukang L.03 Oh 0.012 139,574 Rp 1,674.89
Mandor L.04 Oh 0.012 157,901 Rp 1,894.81
Lantai granite Bh 6.500 61,250 Rp 398,125.00
Portland cement kg 8.190 1,304 Rp 10,677.30
Pasir pasang m 3
0.045 282,536 Rp 12,714.12
Semen warna kg 1.620 16,000 Rp 25,920.00
Jumlah harga Rp 490,254.52
Profit +overhead 10% Rp 49,025.45
Total HSP Rp 539,279.98
Pembulatan Rp 539,280.00
b A.4.4.3.24.
Pemasang 1 m¹ plint ubin granit ukuran(10x60 cm)
1 m' Pekerja L.01 Oh 0.240 102,920 Rp 24,700.80
Tukang batu L.02 Oh 0.120 121,230 Rp 14,547.60
Kepala Tukang L.03 Oh 0.012 139,574 Rp 1,674.89
Mandor L.04 Oh 0.012 157,901 Rp 1,894.81
Lantai granit Bh 6.500 61,250 Rp 398,125.00
Portland cement kg 8.190 1,304 Rp 10,677.30
Pasir pasang m3 0.045 282,536 Rp 12,714.12
Semen warna kg 1.620 16,000 Rp 25,920.00
Jumlah harga Rp 490,254.52
Profit +overhead 10% Rp 49,025.45
Total HSP Rp 539,279.98
Pembulatan Rp 539,280.00
c A.4.4.3.24.
Pemasang 1 m¹ plint ubin granit ukuran(10x60 cm)
1 m' Pekerja L.01 Oh 0.090 102,920 Rp 9,262.80
Tukang batu L.02 Oh 0.090 121,230 Rp 10,910.70
Kepala Tukang L.03 Oh 0.009 139,574 Rp 1,256.17
Mandor L.04 Oh 0.005 157,901 Rp 789.51
plint ubin granit Bh 1.700 23,000 Rp 39,100.00
Semen Portland kg 1.140 1,304 Rp 1,486.22
Pasir pasang m 3
0.003 282,536 Rp 847.61
Semen warna kg 0.100 16,000 Rp 1,600.00
Jumlah harga Rp 65,253.00
Profit +overhead 10% Rp 6,525.30
Total HSP Rp 71,778.30
Pembulatan Rp 71,780.00
d A.4.4.3.25.
Pemasang 1 m¹ plint ubin granit ukuran(10x30 cm)
1 m' Pekerja L.01 Oh 0.090 102,920 Rp 9,262.80
Tukang batu L.02 Oh 0.090 121,230 Rp 10,910.70
Kepala Tukang L.03 Oh 0.009 139,574 Rp 1,256.17
Mandor L.04 Oh 0.005 157,901 Rp 789.51
plint keramik Bh 3.540 17,000 Rp 60,180.00
Semen Portland kg 1.140 1,304 Rp 1,486.22
Pasir pasang m3
0.003 282,536 Rp 847.61
Semen warna kg 0.100 16,000 Rp 1,600.00
Jumlah harga Rp 86,333.00
Profit +overhead 10% Rp 8,633.30
Total HSP Rp 94,966.30
Pembulatan Rp 94,970.00
e ASUMSI
Pelapisan water proofing 1 m2
1 m2 Pekerja L.01 Oh 0.0500 102,920 Rp 5,146.00
Tukang L.03 Oh 0.0750 121,230 Rp 9,092.25
Kepala Tukang L.03 Oh 0.0075 139,574 Rp 1,046.81
Mandor L.04 Oh 0.0025 157,901 Rp 394.75
water proofing coating m2 1.0000 90,000 Rp 90,000.00
( ex.fosroc / sika/ setara) Rp -
Jumlah harga Rp 105,679.81
Profit +overhead 10% Rp 10,567.98
Total HSP Rp 116,247.79
Pembulatan Rp 116,250.00

4 PEKERJAAN PLAFON
a A.4.2.1.21.
Pemasangan 1 m2 Plafond rangka besi hollow
1 m2 Pekerja L.01 Oh 0.100 102,920 Rp 10,292.00
Tukang Kayu L.02 Oh 0.050 121,230 Rp 6,061.50
Kepala Tukang L.03 Oh 0.005 139,574 Rp 697.87
Mandor L.04 Oh 0.005 157,901 Rp 789.51
Gypsum board lbr 0.364 68,000 Rp 24,752.00
Hollow 40x40 btg 1.000 24,000 Rp 24,000.00
Hollow 20x40 btg 1.000 20,000 Rp 20,000.00
Paku skrup kg 0.110 25,000 Rp 2,750.00
Jumlah harga Rp 89,342.88
Profit +overhead 10% Rp 8,934.29
Total HSP Rp 98,277.16
Pembulatan Rp 98,280.00
b A.4.5.1.9.
Pemasangan 1 m' list shadowline 10x10mm
1 m' Pekerja L.01 Oh 0.050 102,920 Rp 5,146.00
Tukang Kayu L.02 Oh 0.050 121,230 Rp 6,061.50
Kepala Tukang L.03 Oh 0.005 139,574 Rp 697.87
Mandor L.04 Oh 0.003 157,901 Rp 473.70
list shadow line 10x10mm m 1.050 10,000 Rp 10,500.00
skrup kg 0.010 25,000 Rp 250.00
Jumlah harga Rp 23,129.07
Profit +overhead 10% Rp 2,312.91
Total HSP Rp 25,441.98
Pembulatan Rp 25,440.00
c A.4.6.1.22.
Pemasangan 1 m' list plank kalsiboard
1 m' Pekerja L.01 Oh 0.100 102,920 Rp 10,292.00
Tukang Kayu L.02 Oh 0.200 121,230 Rp 24,246.00
Kepala Tukang L.03 Oh 0.020 139,574 Rp 2,791.48
Mandor L.04 Oh 0.005 157,901 Rp 789.51
papan kalsiboard/GRC m 1.050 20,000 Rp 21,000.00
skrup kg 0.050 25,000 Rp 1,250.00
Jumlah harga Rp 60,368.99
Profit +overhead 10% Rp 6,036.90
Total HSP Rp 66,405.88
Pembulatan Rp 66,410.00
5 PEKERJAAN PENGECATAN
a A.4.7.1.10.
Pengecatan 1 m2 tembok baru
1 m2 Pekerja L.01 Oh 0.020 102,920 Rp 2,058.40
Tukang khusus allu L.03 Oh 0.063 121,230 Rp 7,637.49
Kepala Tukang L.03 Oh 0.0063 139,574 Rp 879.32
Mandor L.04 Oh 0.0030 157,901 Rp 473.70
plamuur kg 0.100 10,600 Rp 1,060.00
cat dasar kg 0.100 20,568 Rp 2,056.80
cat penutup kg 0.260 39,668 Rp 10,313.70
Jumlah harga Rp 24,479.41
Profit +overhead 10% Rp 2,447.94
Total HSP Rp 26,927.36
Pembulatan Rp 26,930.00
b A.4.7.1.10.
Pengecatan 1 m2 dinding luar
1 m2 Pekerja L.01 Oh 0.020 102,920 Rp 2,058.40
Tukang khusus allu L.03 Oh 0.063 121,230 Rp 7,637.49
Kepala Tukang L.03 Oh
0.0063 139,574 Rp 879.32
Mandor L.04 Oh
0.0030 157,901 Rp 473.70
plamuur kg 0.100 10,600 Rp 1,060.00
cat dasar kg 0.100 20,568 Rp 2,056.80
cat penutup kg 0.260 39,668 Rp 10,313.70
Jumlah harga Rp 24,479.41
Profit +overhead 10% Rp 2,447.94
Total HSP Rp 26,927.36
Pembulatan Rp 26,930.00
6 PEKERJAAN KUSEN, PINTU & JENDELA
a A.4.2.1.11.
Pemasangan 1 m' kusen alluminium
1 m' Pekerja L.01 Oh 0.043 102,920 Rp 4,425.56
Tukang allumunium L.03 Oh 0.043 121,230 Rp 5,212.89
Kepala Tukang L.03 Oh 0.004 139,574 Rp 600.17
Mandor L.04 Oh 0.002 157,901 Rp 331.59
profil allumunium m' 1.100 97,000 Rp 106,700.00
skrup fixer bh 2.000 2,500 Rp 5,000.00
sealant tube 0.060 40,000 Rp 2,400.00
Jumlah harga Rp 124,670.21
Profit +overhead 10% Rp 12,467.02
Total HSP Rp 137,137.23
Pembulatan Rp 137,140.00
b A.4.6.1.5.
Pembuatan & pemasangan 1 m2 daun pintu panel, kayu kelas I & II
1 m2 Pekerja L.01 Oh 1.000 102,920 Rp 102,920.00
Tukang kayu L.03 Oh 3.000 121,230 Rp 363,690.00
Kepala Tukang L.03 Oh 0.300 139,574 Rp 41,872.20
Mandor L.04 Oh 0.050 157,901 Rp 7,895.05
Papan kayu m3 0.040 5,000,000 Rp 200,000.00
lem kayu kg 0.500 30,285 Rp 15,142.50
Jumlah harga Rp 731,519.75
Profit +overhead 10% Rp 73,151.98
Total HSP Rp 804,671.73
Pembulatan Rp 804,670.00
c A.4.7.1.7.
Pelaburan 1 m2 bidang kayu dengan politur
1 m2 Pekerja L.01 Oh 0.040 102,920 Rp 4,116.80
Tukang kayu L.03 Oh 0.060 121,230 Rp 7,273.80
Kepala Tukang L.03 Oh 0.016 139,574 Rp 2,233.18
Mandor L.04 Oh 0.003 157,901 Rp 473.70
Politur / melamine Liter 0.150 54,000 Rp 8,100.00
Politur / melamine jadi liter 0.372 75,000 Rp 27,900.00
amplas lbr 2.000 30,285 Rp 60,570.00
Jumlah harga Rp 110,667.49
Profit +overhead 10% Rp 11,066.75
Total HSP Rp 121,734.24
Pembulatan Rp 121,730.00
d Asumsi
pemasangan 1 bh daun pintu PVC
1 bh Pekerja L.01 Oh 0.043 102,920 Rp 4,425.56
Tukang khusus allu L.03 Oh 0.043 121,230 Rp 5,212.89
Kepala Tukang L.03 Oh 0.004 139,574 Rp 600.17
Mandor L.04 Oh 0.002 157,901 Rp 331.59
pintu pvc unit 1.000 1,250,000 Rp 1,250,000.00
Sekrup fisher bh 5.000 2,500 Rp 12,500.00
Jumlah harga Rp 1,273,070.21
Profit +overhead 10% Rp 127,307.02
Total HSP Rp 1,400,377.23
Pembulatan Rp 1,400,380.00
e Asumsi
pemasangan 1 bh daun pintu PVC
1 bh Pekerja L.01 Oh 0.043 102,920 Rp 4,425.56
Tukang khusus allu L.03 Oh 0.043 121,230 Rp 5,212.89
Kepala Tukang L.03 Oh 0.004 139,574 Rp 600.17
Mandor L.04 Oh 0.002 157,901 Rp 331.59
pintu pvc unit 1.000 1,250,000 Rp 1,250,000.00
Sekrup fisher bh 5.000 2,500 Rp 12,500.00
Jumlah harga Rp 1,273,070.21
Profit +overhead 10% Rp 127,307.02
Total HSP Rp 1,400,377.23
Pembulatan Rp 1,400,380.00
f A.4.6.2.5.
Pemasangan 1 buah engsel pintu
1bh Pekerja L.01 Oh 0.015 102,920 Rp 1,543.80
Tukang L.03 Oh 0.150 121,230 Rp 18,184.50
Kepala Tukang L.03 Oh 0.015 139,574 Rp 2,093.61
Mandor L.04 Oh 0.0008 157,901 Rp 126.32
Engsel pintu bh 1.000 18,000 Rp 18,000.00
Rp -
Jumlah harga Rp 39,948.23
Profit +overhead 10% Rp 3,994.82
Total HSP Rp 43,943.05
Pembulatan Rp 43,940.00
g A.4.6.2.6.
Pemasangan 1 buah engsel jendela
1 bh Pekerja L.01 Oh 0.010 102,920 Rp 1,029.20
Tukang L.03 Oh 0.100 121,230 Rp 12,123.00
Kepala Tukang L.03 Oh 0.010 139,574 Rp 1,395.74
Mandor L.04 Oh 0.0005 157,901 Rp 78.95
Engsel jendela bh 1.000 32,500 Rp 32,500.00
Rp -
Jumlah harga Rp 47,126.89
Profit +overhead 10% Rp 4,712.69
Total HSP Rp 51,839.58
Pembulatan Rp 51,840.00
h A.4.6.2.9.
Pemasangan 1 buah kait angin
1 bh Pekerja L.01 Oh 0.015 102,920 Rp 1,543.80
Tukang L.03 Oh 0.150 121,230 Rp 18,184.50
Kepala Tukang L.03 Oh 0.015 139,574 Rp 2,093.61
Mandor L.04 Oh 0.0008 157,901 Rp 126.32
kait angin bh 1.000 12,500 Rp 12,500.00
Rp -
Jumlah harga Rp 34,448.23
Profit +overhead 10% Rp 3,444.82
Total HSP Rp 37,893.05
Pembulatan Rp 37,890.00
i A.4.6.2.4.
Pemasangan 1 buah kunci silinder
1 bh Pekerja L.01 Oh 0.005 102,920 Rp 514.60
Tukang L.03 Oh 0.500 121,230 Rp 60,615.00
Kepala Tukang L.03 Oh 0.050 139,574 Rp 6,978.70
Mandor L.04 Oh 0.0030 157,901 Rp 473.70
kunci silinder bh 1.000 130,000 Rp 130,000.00
Rp -
Jumlah harga Rp 198,582.00
Profit +overhead 10% Rp 19,858.20
Total HSP Rp 218,440.20
Pembulatan Rp 218,440.00

j A.4.6.2.11.
Pemasangan 1 buah kunci slot
1 bh Pekerja L.01 Oh 0.020 102,920 Rp 2,058.40
Tukang L.03 Oh 0.200 121,230 Rp 24,246.00
Kepala Tukang L.03 Oh 0.020 139,574 Rp 2,791.48
Mandor L.04 Oh 0.0010 157,901 Rp 157.90
kunci slot double bh 1.000 125,000 Rp 125,000.00

Jumlah harga Rp 154,253.78


Profit +overhead 10% Rp 15,425.38
Total HSP Rp 169,679.16
Pembulatan Rp 169,680.00
k A.4.6.2.12.
Pemasangan 1 buah doorholder / pegangan pintu
1 bh Pekerja L.01 Oh 0.050 102,920 Rp 5,146.00
Tukang L.03 Oh 0.500 121,230 Rp 60,615.00
Kepala Tukang L.03 Oh 0.050 139,574 Rp 6,978.70
Mandor L.04 Oh 0.0030 157,901 Rp 473.70
door holder bh 1.000 265,000 Rp 265,000.00

Jumlah harga Rp 338,213.40


Profit +overhead 10% Rp 33,821.34
Total HSP Rp 372,034.74
Pembulatan Rp 372,030.00
F PEKERJAAN SANITAIR
1 A.5.1.1.1.
Pemasangan 1 buah closet duduk
1 bh Pekerja L.01 Oh 3.300 102,920 Rp 339,636.00
Tukang L.03 Oh 1.100 121,230 Rp 133,353.00
Kepala Tukang L.03 Oh 0.010 139,574 Rp 1,395.74
Mandor L.04 Oh 0.1600 157,901 Rp 25,264.16
kloset duduk setara toto unit 1.000 2,250,000 Rp 2,250,000.00
perlengkapan Ls 6%xcloset 135,000 135,000
Jumlah harga Rp 2,884,648.90
Profit +overhead 10% Rp 288,464.89
Total HSP Rp 3,173,113.79
Pembulatan Rp 3,173,110.00
2 A.5.1.1.19.
Pemasangan 1 buah kran diameter 1/2'' & 3/4 "
1 bh Pekerja L.01 Oh 0.010 102,920 Rp 1,029.20
Tukang L.03 Oh 0.400 121,230 Rp 48,492.00
Kepala Tukang L.03 Oh 0.040 139,574 Rp 5,582.96
Mandor L.04 Oh 0.0050 157,901 Rp 789.51
kran air bh 1.000 175,000 Rp 175,000.00
seal tape bh 0.025 2,500 Rp 62.50
Jumlah harga Rp 230,956.17
Profit +overhead 10% Rp 23,095.62
Total HSP Rp 254,051.78
Pembulatan Rp 254,050.00
3 Asumsi .
Asumsi .Pemasangan 1 buah shower + headset
1 bh Pekerja L.01 Oh 0.010 102,920 Rp 1,029.20
Tukang L.03 Oh 0.400 121,230 Rp 48,492.00
Kepala Tukang L.03 Oh 0.040 139,574 Rp 5,582.96
Mandor L.04 Oh 0.0050 157,901 Rp 789.51
Shower TX 438 S bh 1.000 285,800 Rp 285,800.00
Shower kran TX 443 SN bh 1.000 652,500 Rp 652,500.00
seal tape bh 0.025 2,500 Rp 62.50
Jumlah harga Rp 994,256.17
Profit +overhead 10% Rp 99,425.62
Total HSP Rp 1,093,681.78
Pembulatan Rp 1,093,680.00
4 A.5.1.1.14.
Pemasangan 1 buah floor drain
1 bh Pekerja L.01 Oh 0.010 102,920 Rp 1,029.20
Tukang L.03 Oh 0.100 121,230 Rp 12,123.00
Kepala Tukang L.03 Oh 0.010 139,574 Rp 1,395.74
Mandor L.04 Oh 0.0050 157,901 Rp 789.51
floor drain bh 1.000 135,000 Rp 135,000.00
Jumlah harga Rp 150,337.45
Profit +overhead 10% Rp 15,033.74
Total HSP Rp 165,371.19
Pembulatan Rp 165,370.00
5 Asumsi.
Pemasangan 1 buah kran area kitchen zink
1 bh Pekerja L.01 Oh 0.010 102,920 Rp 1,029.20
Tukang L.03 Oh 0.400 121,230 Rp 48,492.00
Kepala Tukang L.03 Oh 0.040 139,574 Rp 5,582.96
Mandor L.04 Oh 0.0050 157,901 Rp 789.51
kran kitchen bh 1.000 155,000 Rp 155,000.00
seal tape bh 0.025 2,500 Rp 62.50
Jumlah harga Rp 210,956.17
Profit 10% Rp 21,095.62
Total HSP Rp 232,051.78
Pembulatan Rp 232,050.00
6 A.5.1.1.5.
Pemasangan 1 buah wastafel
1 bh Pekerja L.01 Oh 1.200 102,920 Rp 123,504.00
Tukang batu L.02 Oh 1.450 121,230 Rp 175,783.50
Kepala Tukang L.03 Oh 0.150 139,574 Rp 20,936.10
Mandor L.04 Oh 0.060 157,901 Rp 9,474.06
wastafel unit 3.250 550,000 Rp 1,787,500.00
Portland cement kg 3.250 1,304 Rp 4,237.03
Pasir pasang m3 0.013 282,536 Rp 3,672.97
perlengkapan % 12.000 66,000 Rp 792,000.00
Jumlah harga Rp 2,917,107.65
Profit +overhead 10% Rp 291,710.77
Total HSP Rp 3,208,818.42
Pembulatan Rp 3,208,820.00
7 A.5.1.1.12.
Pemasangan 1 buah bak cuci piring stainlessteel
1 bh Pekerja L.01 Oh 0.030 102,920 Rp 3,087.60
Tukang batu L.02 Oh 0.300 121,230 Rp 36,369.00
Kepala Tukang L.03 Oh 0.030 139,574 Rp 4,187.22
Mandor L.04 Oh 0.015 157,901 Rp 2,368.52
Bak cuci piring unit 1.000 673,000 Rp 673,000.00
waterdrain bh 1.000 232,000 Rp 232,000.00
Jumlah harga Rp 951,012.34
Profit +overhead 10% Rp 95,101.23
Total HSP Rp 1,046,113.57
Pembulatan Rp 1,046,110.00
8 Asumsi.
Pemasangan 1 buah Roof drain
1 bh Pekerja L.01 Oh 0.010 102,920 Rp 1,029.20
Tukang L.03 Oh 0.100 121,230 Rp 12,123.00
Kepala Tukang L.03 Oh 0.010 139,574 Rp 1,395.74
Mandor L.04 Oh 0.0050 157,901 Rp 789.51
roof drain bh 1.000 52,000 Rp 52,000.00
Jumlah harga Rp 67,337.45
Profit +overhead 10% Rp 6,733.74
Total HSP Rp 67,337.45
Pembulatan Rp 67,340.00
G PEKERJAAN LISTRIK & AIR
1 A.5.1.1.27.
Pemasangan 1 m' pipa PVC tipe AW diameter 1''
1 m' Pekerja L.01 Oh 0.036 102,920 Rp 3,705.12
Tukang L.03 Oh 0.060 121,230 Rp 7,273.80
Kepala Tukang L.03 Oh 0.006 139,574 Rp 837.44
Mandor L.04 Oh 0.0020 157,901 Rp 315.80
pipa pvc 1'' m' 1.200 7,398 Rp 8,877.00
perlengkapan % 0.350 7,398 533
Rp -
Jumlah harga Rp 21,541.79
Profit +overhead 10% Rp 2,154.18
Total HSP Rp 23,695.96
Pembulatan Rp 23,700.00
2 A.5.1.1.31.
Pemasangan 1 m' pipa PVC tipe AW diameter 3''
1 m' Pekerja L.01 Oh 0.081 102,920 Rp 8,336.52
Tukang L.03 Oh 0.135 121,230 Rp 16,366.05
Kepala Tukang L.03 Oh 0.0135 139,574 Rp 1,884.25
Mandor L.04 Oh 0.0040 157,901 Rp 631.60
pipa pvc 3'' m' 1.200 32,120 Rp 38,544.00
perlengkapan % 0.350 32,120 Rp 11,242.00
Jumlah harga Rp 77,004.42
Profit +overhead 10% Rp 7,700.44
Total HSP Rp 84,704.87
Pembulatan Rp 84,700.00
3 A.5.1.1.32.
Pemasangan 1 m' pipa PVC tipe AW diameter 4''
1 m' Pekerja L.01 Oh 0.081 102,920 Rp 8,336.52
Tukang L.03 Oh 0.135 121,230 Rp 16,366.05
Kepala Tukang L.03 Oh 0.0135 139,574 Rp 1,884.25
Mandor L.04 Oh 0.0040 157,901 Rp 631.60
pipa pvc 4'' m' 1.200 53,240 Rp 63,888.00
perlengkapan % 0.350 53,240 Rp 18,634.00
Jumlah harga Rp 109,740.42
Profit +overhead 10% Rp 10,974.04
Total HSP Rp 120,714.47
Pembulatan Rp 120,710.00
3 A.5.1.1.16.
Pemasangan 1 buah bak kontrol pasangan bata 45cmx45 cm tinggi 50 cm
1 bh Pekerja L.01 Oh 3.200 102,920 Rp 329,344.00
Tukang batu L.02 Oh 1.150 121,230 Rp 139,414.50
Kepala Tukang L.03 Oh 0.011 139,574 Rp 1,535.31
Mandor L.04 Oh 0.016 157,901 Rp 2,526.42
bata merah bh 70.000 611 Rp 42,793.10
Portland cement kg 77.000 1,304 Rp 100,384.90
Pasir pasang m3
0.130 282,536 Rp 36,729.68
Pasir beton m3 0.090 277,385 Rp 24,964.65
kerikil m3
0.020 264,120 Rp 5,282.40
besi tulangan kg 2.600 12,027 Rp 31,269.34
Jumlah harga Rp 714,244.30
Profit +overhead 10% Rp 71,424.43
Total HSP Rp 785,668.73
Pembulatan Rp 785,670.00
3 ASUMSI.
Pemasangan 1 buah titik lampu
1 bh Pekerja L.01 Oh 0.400 102,920 Rp 41,168.00
Tukang listrik L.02 Oh 0.250 121,230 Rp 30,307.50
Kepala Tukang L.03 Oh 0.025 139,574 Rp 3,489.35
Mandor L.04 Oh 0.003 157,901 Rp 394.75
lampu bh 1.000 611 Rp 611.33
fivting bh 1.000 1,304 Rp 1,303.70
isolasi rool 0.001 282,536 Rp 282.54
kabel m1 0.090 277,385 Rp 24,964.65
Jumlah harga Rp 102,521.82
Profit +overhead 10% Rp 10,252.18
Total HSP Rp 112,774.00
Pembulatan Rp 112,770.00

H PEKERJAAN ATAP
1 ASUMSI.
Pemasangan 1 M2 rangka atap baja ringan
1 m2 Pekerja L.01 Oh 0.247 102,920 Rp 25,421.24
Tukang kayu L.02 Oh 0.176 121,230 Rp 21,336.48
Kepala Tukang L.03 Oh 0.017 139,574 Rp 2,372.76
Mandor L.04 Oh 0.006 157,901 Rp 947.41
Main truss C-750 t=0,75 m' 2.800 18,150 Rp 50,820.00
Roof buttom/reng R33-0,45 m' 5.100 8,400 Rp 42,840.00
Self driiving screw ∅ 6x20mm bh 25.000 650 Rp 16,250.00
(trusss screw)
Self driiving screw ∅ 4x16mm bh 35.000 525 Rp 18,375.00
(bottum trusss screw)
Angle clip 50x50cm bh 1.000 1,750 Rp 1,750.00
Dinabolt ∅ 12x120mm bh 1.000 1,800 Rp 1,800.00
Jumlah harga Rp 181,912.88
Profit +overhead 10% Rp 18,191.29
Total HSP Rp 200,104.17
Pembulatan Rp 200,100.00
2 A.4.5.2.42.
Pemasangan 1 m2 alumunium foil
1 m2 Pekerja L.01 Oh 0.150 102,920 Rp 15,438.00
Tukang batu L.02 Oh 0.050 121,230 Rp 6,061.50
Kepala Tukang L.03 Oh 0.005 139,574 Rp 697.87
Mandor L.04 Oh 0.008 157,901 Rp 1,263.21
Alumunium foil m2 1.050 4,967 Rp 5,215.00
Jumlah harga Rp 28,675.58
Profit +overhead 10% Rp 2,867.56
Total HSP Rp 31,543.14
Pembulatan Rp 31,540.00
3 A.4.5.2.3.
Pemasangan 1 m2 genteng keramik / pelentong besar super
1 m2 Pekerja L.01 Oh 0.150 102,920 Rp 15,438.00
Tukang batu L.02 Oh 0.075 121,230 Rp 9,092.25
Kepala Tukang L.03 Oh 0.008 139,574 Rp 1,116.59
Mandor L.04 Oh 0.008 157,901 Rp 1,263.21
genteng beton bh 12.000 10,700 Rp 128,400.00
Jumlah harga Rp 155,310.05
Profit +overhead 10% Rp 15,531.01
Total HSP Rp 170,841.06
Pembulatan Rp 170,840.00
4 A.4.5.2.4.
Pemasangan 1 m' bubungan genteng pelentong
1 m' Pekerja L.01 Oh 0.400 102,920 Rp 41,168.00
Tukang batu L.02 Oh 0.200 121,230 Rp 24,246.00
Kepala Tukang L.03 Oh 0.020 139,574 Rp 2,791.48
Mandor L.04 Oh 0.002 157,901 Rp 315.80
genteng bubung bh 5.000 19,400 Rp 97,000.00
Portland cement kg 8.000 1,304 Rp 10,429.60
Pasir pasang m3 0.032 282,536 Rp 9,041.15
Jumlah harga Rp 184,992.03
Profit +overhead 10% Rp 18,499.20
Total HSP Rp 203,491.24
Pembulatan Rp 203,490.00
5 ASUMSI.
Pemasangan 1 buah toren air
1 bh Pekerja L.01 Oh 0.400 102,920 Rp 41,168.00
Tukang batu L.02 Oh 0.200 121,230 Rp 24,246.00
Kepala Tukang L.03 Oh 0.020 139,574 Rp 2,791.48
Mandor L.04 Oh 0.002 157,901 Rp 315.80
toren ex penguin unit 1.000 950,000 Rp 950,000.00
Jumlah harga Rp 1,018,521.28
Profit +overhead 10% Rp 101,852.13
Total HSP Rp 1,120,373.41
Pembulatan Rp 1,120,370.00
REKAPITULASI RENCANA ANGGARAN BIAYA
BERDASARKAN SNI / DPU BIDANG CIPTA KARYA
PERUMAHAN GADING RESIDENCE
TYPE 85 KAV. 9X10 M
JL.Hankam, Puspitek, Serpong, Tangerang Selatan

Harga Satuan
No Uraian Pekerjaan Sat Volume
Rp.

A. PEKERJAAN PERSIAPAN
1 Bouwplank & pengukuran m1 45.00 66,320.00

Jumlah I
B. PEKERJAAN GALIAN DAN URUGAN
1 Galian Pondasi Foot plat M3 3.69 109,710.00
2 Galian Sloof M3 2.10 109,710.00
3 Urugan Tanah Kembali M3 1.40 62,270.00
4 Pemadatan Tanah + Urugan Pasir t = 10 cm M3 8.63 465,940.00
Jumlah II
C. PEKERJAAN PONDASI
1 Pondasi Beton setempat / foot plat M3 2.29 5,367,770.00
2 Sloof M3 2.10 5,367,770.00
3 Pondasi Bata kali 1 SP: 5 PP m' 7.90 902,680.00
Jumlah III
D. PEKERJAAN KONSTRUKSI BETON
LANTAI 1
1 Lantai kerja 1:3: 5 tebal 5 cm ( Pondasi Plat Setempat ) M3 0.30 1,175,450.00
2 Konstruksi Kolom M3 2.28 5,367,770.00
3 Konstruksi balok M3 2.35 5,367,770.00
4 Konstruksi Plat M3 4.24 5,367,770.00
5 Konstruksi Tangga M3 1.84 5,367,770.00
6 Konstruksi Canopy M3 0.49 5,367,770.00
7 Kolom/balok Praktis M3 0.91 143,000.00
LANTAI 2
1 Konstruksi Kolom M3 0.82 5,367,770.00
2 Konstruksi Ring Balk M3 1.09 5,367,770.00
3 Konstruksi Plat ( Dudukan Toren ) M3 0.24 5,367,770.00
4 Konstruksi Canopy M3 0.04 5,367,770.00
5 Kolom/balok Praktis M3 0.62 143,000.00

Jumlah IV
E PEKERJAAN ARSITEKTUR
E.1 PEKERJAAN DINDING PLESTER/ACI
LANTAI I
1 Pas. Dinding bata tebal 1/2 bata M2 159.00 126,380
2 Plester Dinding M2 320.50 74,390
3 Acian Dinding M2 320.50 43,910
LANTAI II
1 Pas. Dinding bata tebal 1/2 bata M2 154.00 126,380
2 Plester Dinding M2 273.50 74,390
3 Acian Dinding M2 273.50 43,910
4 Pek.GlassBlock M2 1.31 601,440
Jumlah V
E.2 PEKERJAAN DINDING
LANTAI I
Pasangan Dinding Keramik 30x60 ex.Roman + 10x30
1 M2 19.56 589,670
ex.Roman
2 Pasangan + Finish Batu Alam M2 7.20 174,560
Pek. Profil dinding bergaris 3cm + tebal acian ban
3 M2 5.25 77,940
banan t=2,5cm

LANTAI II
Pasangan Dinding Keramik 30x60 ex.Roman + 10x30
1 M2 20.64 589,670
ex.Roman
2 Pek. Penebalan Plesteran/ Ban-banan t=2,5cm M2 9.10 77,940
3 Pek.Kaca Mati + Alumunium + Sealant M2 18.00 325,500

Jumlah VI
E.3 PEKERJAAN FINISH LANTAI
LANTAI I
Pasangan granite lantai utama + Keramik Tangga 60 x
1 M2 39.40 539,410
60 ex Roman
2 Pasangan keramik KM 30x30 ex.Roman M2 3.00 220,000
Pasangan keramik Teras Depan dan Belakang 30x30
3 M2 6.93 220,000
ex.Roman
4 Carport beton rabat M2 12.60 110,000
5 Lapisan Water Proofing Canopy Beton (Atap Lantai 1) M2 5.30 116,250
6 Plint Keramik uk. 10x60 cm m1 53.50 71,780
LANTAI II
Pasangan keramik lantai utama 60 x 60 ex Granit
1 M2 35.00 539,410
Roman
2 Pasangan keramik KM 30 x 30 ex Roman M2 4.00 220,000
3 Lapisan Water Proofing Plat Dak Toren M2 2.00 116,250.00
4 Plint Keramik uk. 10x60 cm m1 40.00 71,780

Jumlah VII
E.4 PEKERJAAN PLAFOND
LANTAI I
1 Pekerjaan Plafond ex.Jayaboard M2 34.00 98,280.00
2 Tali air shadowline 10x10mm m1 44.50 25,440.00
LANTAI II
1 Pekerjaan Plafond ex.Elephant M2 67.20 98,280.00
2 Tali air shadowline 10x10mm m1 101.00 25,440.00
3 Pekerjaan List Plank ex.kalsiboard 6/30 cm m1 18.00 66,410.00
Jumlah VIII

E.5 PEKERJAAN PENGECATAN


LANTAI I
1 Pekerjaan Dinding Dalam ex.Vinilex,Catylac M2 172.60 26,930.00
2 Pekerjaan Dinding Luar ex.Vinilex,Catylac M2 103.40 26,930.00
3 Pekerjaan Plafond ex.Vinilex M2 34.00 26,930.00
LANTAI II
1 Pekerjaan Dinding Dalam ex.Vinilex,Catylac M2 133.00 26,930.00
2 Pekerjaan Dinding Luar ex.Vinilex,Catylac M2 95.00 26,930.00
3 Pekerjaan Plafond ex.Vinilex M2 67.20 26,930.00
4 Pekerjaan List Plank ex.Vinilex M2 5.40 26,930.00
Jumlah IX
E.6 PEKERJAAN KUSEN, PINTU & JENDELA :
LANTAI I
P1 (Kusen Alumunium 3'' & Daun Pintu Panel ex.kayu
1 bh 1.00 2,655,000.00
Kamper finish melamix)
P2 (Kusen Alumunium 3'' & Daun Pintu Panel
2 bh 2.00 1,352,000.00
ex.KNOX 502)
3 P3 ( Pintu toilet PVC ex.Kristal Minimalis ) bh 1.00 1,400,380.00
4 P1A ( Pintu Geser kayu kamper + Kaca t=5mm ) bh 1.00 3,100,000.00
J1 ( Kusen + Daun Jendela Alumunium + Kaca
5 bh 4.00 1,150,000.00
t=5mm )
J2 ( Kusen + Daun Jendela Alumunium + Kaca Mati
6 bh 3.00 1,150,000.00
t=5mm )
J3 ( Kusen + Daun Jendela Alumunium KM + Kaca
7 bh 1.00 425,500.00
t=5mm )
8 Kunci double sloog ( Pintu Depan ) bh 1.00 218,890.00
9 Kunci Pintu bagian dalam, Pintu Belakang bh 3.00 169,860.00
10 Engsel Pintu @ 3 Buah bh 9.00 44,080.00
11 Engsel Jendela bh 8.00 51,930.00
12 Hak Angin m1 8.00 38,030.00
LANTAI II
P2 (Kusen Alumunium 3'' & Daun Pintu Panel
1 bh 2.00 1,352,000.00
ex.KNOX 502)
2 P3 ( Pintu toilet PVC ex.Kristal Minimalis ) bh 1.00 1,400,380.00
J1 ( Kusen + Daun Jendela Alumunium + Kaca
3 bh 3.00 1,150,000.00
t=5mm )
J3 ( Kusen + Daun Jendela Alumunium KM + Kaca
4 bh 1.00 425,500.00
t=5mm )
5 Kunci Pintu bagian dalam, Pintu Belakang dan Dapur bh 2.00 169,680.00
6 Engsel Pintu @ 3 Buah bh 6.00 43,940.00
7 Engsel Jendela bh 6.00 51,930.00
8 Hak Angin bh 6.00 38,030.00

Jumlah X
F PEKERJAAN SANITAIR
LANTAI I
1 Kloset Duduk Ex.Toto Bh 1.00 3,173,110.00
2 Kran Air KM,Taman depan dan belakang ,ex.Toto Bh 3.00 254,050.00
3 Shower + Headset dinding ex.Toto Bh 1.00 1,093,680.00
4 Floor Drain Stainless Bh 1.00 165,370.00
5 Kran Kitchen Zink Bh 1.00 232,050.00
6 Washtafel Lengkap + Acc. Ex.Toto Set 1.00 3,208,820.00
7 Kitchen Zink 1 lobang Meiwa Unit 1.00 1,046,110.00
LANTAI II
1 Kloset Duduk ex.Toto Bh 1.00 3,173,110.00
2 Kran KM ex Toto Bh 1.00 254,050.00
3 Shower + Headset dinding ex.Toto Bh 1.00 1,093,680.00
4 Washtafel Lengkap + Acc. Ex.Toto Bh 1.00 3,208,820.00
5 Floor Drain Stainless Bh 1.00 165,370.00
6 Roof Drain Stainless BH 1.00 67,420.00

Jumlah XI
G INSTALASI LISTRIK & AIR
LANTAI I
1 Instalasi Air Bersih 1" Wavin AW M1 11.00 23,700.00
2 Instalasi Air Bekas 3" Wavin AW M1 8.00 84,700.00
3 Instalasi Air Kotor 4" Wavin AW M1 9.00 120,710.00
4 Bak kontrol Unit 1.00 785,670.00
5 Septicktank & Rembesan ( 1m x 1m x 1,5m ) Unit 1.00 2,755,000.00
7 Instalasi Titik Lampu Ttk 7.00 210,500.00
8 Instalasi Titik Taman Ttk 1.00 210,500.00
9 Saklar Single ex clipsal Bh 1.00 40,000.00
10 Saklar Double ex clipsal Bh 3.00 40,000.00
11 Stop Kontak ex clipsal Ttk 3.00 210,500.00
12 Box Panel Unit 1.00 550,000.00
13 MCB 10A Bh 1.00 115,000.00
14 Pemasangan Lampu Down Lite-PLC D4'' dan KM D3'' Ttk 7.00 180,000.00
15 Kabel Toevoer/ 3x4 mm M1 3.00 125,000.00
16 Arde Pertanahan Unit 1.00 100,000.00
LANTAI II
1 Instalasi Air Bersih 1" Wavin AW M1 10.00 23,700.00
2 Instalasi Air Bekas 3" Wavin AW M1 10.00 84,700.00
3 Instalasi Air Kotor 4" Wavin AW M1 10.00 120,710.00
4 Instalasi Titik Lampu Ttk 6.00 220,500.00
5 Saklar Single ex clipsal Bh 2.00 43,000.00
6 Saklar Double ex clipsal Bh 2.00 43,000.00
7 Stop Kontak ex clipsal Ttk 3.00 220,500.00
8 Box Panel Unit 1.00 575,000.00
9 MCB 10A Ttk 1.00 65,000.00
10 Pemasangan Lampu Down Lite-PLC D4'' dan KM D3'' Ttk 6.00 180,000.00
Jumlah XII
H PEKERJAAN ATAP
1 Pek. Rangka atap baja ringan ex.Taso/Tangguh m2 82.00 200,100.00
2 Alumunium Foil m2 82.00 31,540.00
Pek. Penutup atap genteng keramik SNI + Nok
3 m2 82.00 170,840.00
Genteng keramik

Jumlah XIII

I PEKERJAAN LAIN-LAIN
1 Pemasangan Toren 650 Liter TB 70 + Acc ex.Pinguin bh 1.00 1,120,370.00
Pekerjaan Sumur Pantek,pompa + Acc ex Jetpump
2 unit 1.00 4,150,000.00
Standart

Jumlah XIV
GRAND TOTAL
Jumlah
Rp.

2,984,400.00

2,984,400.00

404,336.21
230,391.00
87,146.87
4,021,062.20
4,742,936.27

12,270,722.22
11,272,317.00
7,131,172.00
30,674,211.22
357,042.94
12,238,515.60
12,604,275.45
22,737,873.72
9,876,696.80
2,632,354.41
129,729.60

4,400,068.42
5,862,893.10
1,288,264.80
214,710.80
88,133.76

72,430,559.40

20,094,420.00
23,841,995.00
14,073,155.00

19,462,520.00
20,345,665.00
12,009,385.00
787,886.40
110,615,026.40

11,533,945.20
1,256,832.00
409,185.00

12,170,788.80
709,254.00
5,859,000.00

31,939,005.00

21,252,754.00
660,000.00
1,523,500.00
1,386,000.00
616,125.00
3,840,230.00

18,879,350.00
880,000.00
232,500.00
2,871,200.00

52,141,659.00

3,341,520.00
1,132,080.00

6,604,416.00
2,569,440.00
1,195,380.00
14,842,836.00

4,648,118.00
2,784,562.00
915,620.00
3,581,690.00
2,558,350.00
1,809,696.00
145,422.00
16,443,458.00

2,655,000.00

2,704,000.00
1,400,380.00
3,100,000.00
4,600,000.00

3,450,000.00

425,500.00
218,890.00
509,580.00
396,720.00
415,440.00
304,240.00
2,704,000.00
1,400,380.00
3,450,000.00

425,500.00
339,360.00
263,640.00
311,580.00
228,180.00

29,302,390.00

3,173,110.00
762,150.00
1,093,680.00
165,370.00
232,050.00
3,208,820.00
1,046,110.00

3,173,110.00
254,050.00
1,093,680.00
3,208,820.00
165,370.00
67,420.00

17,643,740.00

260,700.00
677,600.00
1,086,390.00
785,670.00
2,755,000.00
1,473,500.00
210,500.00
40,000.00
120,000.00
631,500.00
550,000.00
115,000.00
1,260,000.00
375,000.00
100,000.00

237,000.00
847,000.00
1,207,100.00
1,323,000.00
86,000.00
86,000.00
661,500.00
575,000.00
65,000.00
1,080,000.00
16,608,460.00

16,408,200.00
2,586,280.00
14,008,880.00

33,003,360.00

1,120,370.00
4,150,000.00

5,270,370.00
438,642,411.29
Asumsi
Membuat 1 m3 kolom praktis beton bertulang
1m ' Pekerja L.01 Oh 0.180 102,920 Rp 18,525.60
Tukang batu L.02 Oh 0.020 121,230 Rp 2,424.60
Tukang kayu L.02 Oh 0.020 139,574 Rp 2,791.48
Tukang besi L.02 Oh 0.020 157,901 Rp 3,158.02
Kepala Tukang L.03 Oh 0.005 5,500,000 Rp 27,500.00
Mandor L.04 Oh 0.065 17,300 Rp 1,124.50
kayu kelas III m3 0.002 1,304 Rp 2.61
Paku 5cm-12cm kg 0.010 17,300 Rp 173.00
minyak bekisting liter 1.200 24,000 Rp 28,800.00
besi beton polos kg 3.000 12,027 Rp 36,080.01
kawat beton kg 0.200 20,000 Rp 4,000.00
Semen portland kg 2.000 1,304 Rp 2,607.40
Pasir Beton m3 0.002 277,385 Rp 554.77
Kerikil m3 0.006 264,120 Rp 1,584.72
Jumlah harga Rp 129,326.71
Profit +overhead 10% Rp 12,932.67
Total HSP Rp 142,259.38
Pembulatan Rp 143,000.00

Asumsi
Membuat 1 m2 COR Rabat beton
1m ' Pekerja L.01 Oh 0.200 102,920 Rp 20,584.00
Tukang batu L.02 Oh 0.020 121,230 Rp 2,424.60
Tukang kayu L.02 Oh 0.020 139,574 Rp 2,791.48
Tukang besi L.02 Oh 0.020 157,901 Rp 3,158.02
Kepala Tukang L.03 Oh 0.005 5,500,000 Rp 27,500.00
Mandor L.04 Oh 0.065 17,300 Rp 1,124.50
kayu kelas III m3 0.001 1,304 Rp 1.30
Paku 5cm-12cm kg 0.010 17,300 Rp 173.00
besi beton polos kg 2.000 12,027 Rp 24,053.34
kawat beton kg 0.250 20,000 Rp 5,000.00
Semen portland kg 2.000 1,304 Rp 2,607.40
Pasir Beton m3 0.003 277,385 Rp 832.16
Kerikil m3 0.007 264,120 Rp 1,848.84
Jumlah harga Rp 92,098.64
Profit +overhead 10% Rp 9,209.86
Total HSP Rp 101,308.50
Pembulatan Rp 110,000.00
0.0005
ANALISA PEKERJAAN KUSEN ,PINTU,JENDELA

NO URAIAN VOL SAT

900
1 Kusen 3" 4.9 m' Rp 97,000
lem silicone 4.9 m' Rp 19,608
2000

P1 pembuatan & pemasangan 1 unit Rp 1,850,000

finishing pintu melamin 1.8 m2 Rp 121,730

jumlah

900
Kusen 3" 4.9 m' Rp 97,000
P2 lem silicone 4.9 m' Rp 19,608
2000

daunpintu panel 1 unit Rp 1,850,000

jumlah

1.45
P1A Kusen 3" 5.65 m' Rp 97,000
lem silicone 4.9 m' Rp 19,608
Kaca 5mm 3.045 m2 Rp 145,800
2.1

acsesories 1 Rp 700,000
upah tenaga 1 ls Rp 1,250,000

jumlah

700
j1 Kusen 3" 5.6 m' Rp 97,000
lem silicone 5.6 m' Rp 19,608
Jendela kaca 1 bh 1 unit Rp 495,000
Lem Silicone
2.1
700
J3 Kusen 3" 2.2 m' Rp 97,000
lem silicone 5.6 m' Rp 19,608
400

Jendela kaca 1 bh 1 unit Rp 102,000


HARGA JUMLAH
SATUAN UNIT HARGA

Rp 475,300
Rp 96,081
Rp 1,850,000

Rp 219,114

Rp 2,640,495 1 Rp 2,640,495
Rp 2,655,000

Rp 475,300
Rp 96,081
Rp 780,000

Rp 1,351,381 1 Rp 1,351,381
Rp 1,352,000

Rp 548,050
Rp 96,081
Rp 443,961
Rp 700,000
Rp 1,250,000

Rp 3,038,092 1 Rp 3,038,092
Rp 3,100,000

Rp 543,200
Rp 109,807
Rp 495,000

Rp 1,148,007 1 Rp 1,148,007
Rp 1,150,000
Rp 213,400
Rp 109,807
Rp 102,000

Rp 425,207 1 Rp 425,207
Rp 425,500
ANALISA RESAPAN
Sumur Resepan unit Galian tanah 3.375 m3
Ijuk 3.900 kg
Urugan pasir t=20 cm 0.600 m3
Batu koral t=20 cm 4.500 m3
urugan tanah kembali 1.500 m3
plesteran 3.000 m2
Pas. Bata 3.000 m2

HARGA PEKERJAAN LISTRIK


SNI PU CIPTA KARYA
1 Instalasi Titik Lampu Ttk 1.00
2 Instalasi Titik Taman Ttk 1.00
2 Saklar Single ex clipsal Bh 1.00
3 Saklar Double ex clipsal Bh 1.00
3 Stop Kontak ex clipsal Ttk 1.00
4 Box Panel Unit 1.00
4 MCB 10A Bh 1.00
Pemasangan Lampu Down Lite-
5 Ttk 1.00
PLC D4'' dan KM D3''
5 Kabel Toevoer/ 3x4 mm M1 1.00
6 Arde Pertanahan Unit 1.00
Instalasi Titik Lampu Ttk 1.00
7 Saklar Single ex clipsal Bh 1.00
8 Saklar Double ex clipsal Bh 1.00
8 Stop Kontak ex clipsal Ttk 1.00
9 Box Panel Unit 1.00
9 MCB 10A Ttk 1.00
Pemasangan Lampu Down Lite-
10 Ttk 1.00
PLC D4'' dan KM D3''
Rp 109,710.00 Rp 370,271.25
Rp 55,000.00 Rp 214,500.00
Rp 403,670.00 Rp 242,202.00
Rp 264,120.00 Rp 1,188,540.00
Rp 62,266.60 Rp 93,399.90
Rp 74,390.00 Rp 223,170.00
Rp 126,380.00 Rp 379,140.00 Rp 2,711,223.15
2,755,000.00

210,500.00
210,500.00
40,000.00
40,000.00
210,500.00
550,000.00
115,000.00
180,000.00
125,000.00
100,000.00
220,500.00
43,000.00
43,000.00
220,500.00
575,000.00
65,000.00

180,000.00
REKAPITULASI RENCANA ANGGARAN BIAYA
BERDASARKAN SNI / DPU BIDANG CIPTA KARYA
PERUMAHAN GADING RESIDENCE
TYPE 85 KAV. 9X10 M
JL.Hankam, Puspitek, Serpong, Tangerang Selatan

No Uraian Pekerjaan Sat Volume

A. PEKERJAAN PERSIAPAN
1 Bouwplank & pengukuran m1 45.00

B. PEKERJAAN GALIAN DAN URUGAN


1 Galian Pondasi Foot plat M3 3.69
2 Galian Sloof M3 2.10
3 Urugan Tanah Kembali M3 1.40
4 Pemadatan Tanah + Urugan Pasir t = 10 cm M3 8.63

C. PEKERJAAN PONDASI
1 Pondasi Beton setempat / foot plat M3 2.29
2 Sloof M3 2.10
3 Pondasi Bata kali 1 SP: 5 PP m' 7.90
Jumlah III
D. PEKERJAAN KONSTRUKSI BETON
LANTAI 1
1 Lantai kerja 1:3: 5 tebal 5 cm ( Pondasi Plat Setempat ) M3 0.30
2 Konstruksi Kolom M3 2.28
3 Konstruksi balok M3 2.35
4 Konstruksi Plat M3 4.24
5 Konstruksi Tangga M3 1.84
6 Konstruksi Canopy M3 0.49
7 Kolom/balok Praktis M3 0.91
LANTAI 2
1 Konstruksi Kolom M3 0.82
2 Konstruksi Ring Balk M3 1.09
3 Konstruksi Plat ( Dudukan Toren ) M3 0.24
4 Konstruksi Canopy M3 0.04
5 Kolom/balok Praktis M3 0.62

Jumlah IV
E PEKERJAAN ARSITEKTUR
E.1 PEKERJAAN DINDING PLESTER/ACI
LANTAI I
1 Pas. Dinding bata tebal 1/2 bata M2 159.00
2 Plester Dinding M2 320.50
3 Acian Dinding M2 320.50
LANTAI II
1 Pas. Dinding bata tebal 1/2 bata M2 154.00
2 Plester Dinding M2 273.50
3 Acian Dinding M2 273.50
4 Pek.GlassBlock M2 1.31
Jumlah V
E.2 PEKERJAAN DINDING
LANTAI I
Pasangan Dinding Keramik 30x60 ex.Roman + 10x30
1 M2 19.56
ex.Roman
2 Pasangan + Finish Batu Alam M2 7.20
Pek. Profil dinding bergaris 3cm + tebal acian ban
3 M2 5.25
banan t=2,5cm

LANTAI II
Pasangan Dinding Keramik 30x60 ex.Roman + 10x30
1 M2 20.64
ex.Roman
2 Pek. Penebalan Plesteran/ Ban-banan t=2,5cm M2 9.10
3 Pek.Kaca Mati + Alumunium + Sealant M2 18.00

Jumlah VI
E.3 PEKERJAAN FINISH LANTAI
LANTAI I
Pasangan granite lantai utama + Keramik Tangga 60 x
1 M2 39.40
60 ex Roman
2 Pasangan keramik KM 30x30 ex.Roman M2 3.00
Pasangan keramik Teras Depan dan Belakang 30x30
3 M2 6.93
ex.Roman
4 Carport beton rabat M2 12.60
5 Lapisan Water Proofing Canopy Beton (Atap Lantai 1) M2 5.30
6 Plint Keramik uk. 10x60 cm m1 53.50
LANTAI II
Pasangan keramik lantai utama 60 x 60 ex Granit
1 M2 35.00
Roman
2 Pasangan keramik KM 30 x 30 ex Roman M2 4.00
3 Lapisan Water Proofing Plat Dak Toren M2 2.00
4 Plint Keramik uk. 10x60 cm m1 40.00

Jumlah VII
E.4 PEKERJAAN PLAFOND
LANTAI I
1 Pekerjaan Plafond ex.Jayaboard M2 34.00
2 Tali air shadowline 10x10mm m1 44.50
LANTAI II
1 Pekerjaan Plafond ex.Elephant M2 67.20
2 Tali air shadowline 10x10mm m1 101.00
3 Pekerjaan List Plank ex.kalsiboard 6/30 cm m1 18.00
Jumlah VIII

E.5 PEKERJAAN PENGECATAN


LANTAI I
1 Pekerjaan Dinding Dalam ex.Vinilex,Catylac M2 172.60
2 Pekerjaan Dinding Luar ex.Vinilex,Catylac M2 103.40
3 Pekerjaan Plafond ex.Vinilex M2 34.00
LANTAI II
1 Pekerjaan Dinding Dalam ex.Vinilex,Catylac M2 133.00
2 Pekerjaan Dinding Luar ex.Vinilex,Catylac M2 95.00
3 Pekerjaan Plafond ex.Vinilex M2 67.20
4 Pekerjaan List Plank ex.Vinilex M2 5.40
Jumlah IX
E.6 PEKERJAAN KUSEN, PINTU & JENDELA :
LANTAI I
P1 (Kusen Alumunium 3'' & Daun Pintu Panel ex.kayu
1 bh 1.00
Kamper finish melamix)
P2 (Kusen Alumunium 3'' & Daun Pintu Panel
2 bh 2.00
ex.KNOX 502)
3 P3 ( Pintu toilet PVC ex.Kristal Minimalis ) bh 1.00
4 P1A ( Pintu Geser kayu kamper + Kaca t=5mm ) bh 1.00
J1 ( Kusen + Daun Jendela Alumunium + Kaca
5 bh 4.00
t=5mm )
J2 ( Kusen + Daun Jendela Alumunium + Kaca Mati
6 bh 3.00
t=5mm )
J3 ( Kusen + Daun Jendela Alumunium KM + Kaca
7 bh 1.00
t=5mm )
8 Kunci double sloog ( Pintu Depan ) bh 1.00
9 Kunci Pintu bagian dalam, Pintu Belakang bh 3.00
10 Engsel Pintu @ 3 Buah bh 9.00
11 Engsel Jendela bh 8.00
12 Hak Angin m1 8.00
LANTAI II
P2 (Kusen Alumunium 3'' & Daun Pintu Panel
1 bh 2.00
ex.KNOX 502)
2 P3 ( Pintu toilet PVC ex.Kristal Minimalis ) bh 1.00
J1 ( Kusen + Daun Jendela Alumunium + Kaca
3 bh 3.00
t=5mm )
J3 ( Kusen + Daun Jendela Alumunium KM + Kaca
4 bh 1.00
t=5mm )
5 Kunci Pintu bagian dalam, Pintu Belakang dan Dapur bh 2.00
6 Engsel Pintu @ 3 Buah bh 6.00
7 Engsel Jendela bh 6.00
8 Hak Angin bh 6.00

Jumlah X
F PEKERJAAN SANITAIR
LANTAI I
1 Kloset Duduk Ex.Toto Bh 1.00
2 Kran Air KM,Taman depan dan belakang ,ex.Toto Bh 3.00
3 Shower + Headset dinding ex.Toto Bh 1.00
4 Floor Drain Stainless Bh 1.00
5 Kran Kitchen Zink Bh 1.00
6 Washtafel Lengkap + Acc. Ex.Toto Set 1.00
7 Kitchen Zink 1 lobang Meiwa Unit 1.00
LANTAI II
1 Kloset Duduk ex.Toto Bh 1.00
2 Kran KM ex Toto Bh 1.00
3 Shower + Headset dinding ex.Toto Bh 1.00
4 Washtafel Lengkap + Acc. Ex.Toto Bh 1.00
5 Floor Drain Stainless Bh 1.00
6 Roof Drain Stainless BH 1.00

Jumlah XI
G INSTALASI LISTRIK & AIR
LANTAI I
1 Instalasi Air Bersih 1" Wavin AW M1 11.00
2 Instalasi Air Bekas 3" Wavin AW M1 8.00
3 Instalasi Air Kotor 4" Wavin AW M1 9.00
4 Bak kontrol Unit 1.00
5 Septicktank & Rembesan ( 1m x 1m x 1,5m ) Unit 1.00
7 Instalasi Titik Lampu Ttk 7.00
8 Instalasi Titik Taman Ttk 1.00
9 Saklar Single ex clipsal Bh 1.00
10 Saklar Double ex clipsal Bh 3.00
11 Stop Kontak ex clipsal Ttk 3.00
12 Box Panel Unit 1.00
13 MCB 10A Bh 1.00
14 Pemasangan Lampu Down Lite-PLC D4'' dan KM D3'' Ttk 7.00
15 Kabel Toevoer/ 3x4 mm M1 3.00
16 Arde Pertanahan Unit 1.00
LANTAI II
1 Instalasi Air Bersih 1" Wavin AW M1 10.00
2 Instalasi Air Bekas 3" Wavin AW M1 10.00
3 Instalasi Air Kotor 4" Wavin AW M1 10.00
4 Instalasi Titik Lampu Ttk 6.00
5 Saklar Single ex clipsal Bh 2.00
6 Saklar Double ex clipsal Bh 2.00
7 Stop Kontak ex clipsal Ttk 3.00
8 Box Panel Unit 1.00
9 MCB 10A Ttk 1.00
10 Pemasangan Lampu Down Lite-PLC D4'' dan KM D3'' Ttk 6.00
Jumlah XII
H PEKERJAAN ATAP
1 Pek. Rangka atap baja ringan ex.Taso/Tangguh m2 82.00
2 Alumunium Foil m2 82.00
Pek. Penutup atap genteng keramik SNI + Nok
3 m2 82.00
Genteng keramik

Jumlah XIII

I PEKERJAAN LAIN-LAIN
1 Pemasangan Toren 650 Liter TB 70 + Acc ex.Pinguin bh 1.00
Pekerjaan Sumur Pantek,pompa + Acc ex Jetpump
2 unit 1.00
Standart

Jumlah XIV
GRAND TOTAL
-

Anda mungkin juga menyukai