SUMADHURA NANDANAM DECEMBER 31-12-2019 MPR.

A block 9th floor roof slab concrete work


completed.
A block North side view A block South side view

A block 7th floor block work in progress


A-Block Progress

Toilet CPVC
Electrical Chipping
Pipe wiring
& pipe fixing with Water Proofing Screed Concrete
work
Internal Wall box
Block A Slab Concrete Block work Ceiling Plastering Plastering

Lower Basement Completed NA NA NA NA NA NA NA


Upper Basement Completed NA NA NA NA NA NA NA
Ground Floor Completed - - - - - - -

First Floor Completed - - - - - -

Second Floor Completed - - - - - - -

Third Floor Completed Completed - Completed Completed Completed Under progress -

Fourth Floor Completed Completed - Under progress Completed Under progress - -


Fifth Floor Completed Completed - - Under Progress - - -

Sixth Floor Completed Completed - - - - - -

Seventh Floor Completed Under progress - - - - - -

Eighth Floor Completed - - - - - - -

Ninth Floor Completed - - -- - - - -

Tenth Floor - - - - - - - -

Eleventh Floor - - - - - - - -

Twelfth Floor - - - - - - - -

Thirteenth Floor - - - - - - - -

Fourteenth Floor - - - - -- - - -
B block B block B block
10th floor Internal wall & ceiling 5th floor vitrified flooring tile 8th floor toilet dado work is
1st coat putty work in progress. work is under progress under progress.
B-Block Progress
Electrical
Inernal ceiling Toilets dado
Internal Chipping & Toilet CPVC Pipe Water Vitrified
Screed Concrete & wall 1st coat Tiles
Ceiling Wall External wall pipe fixing with wiring work Proofing Flooring Tiles
Putty
Block B Block work Plastering Plastering Plastering box

Lower
Basement NA NA NA NA NA NA NA NA NA NA NA
Upper
Basement NA NA NA NA NA NA NA NA Na NA NA

Ground Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed - -

First Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Under Progress Under Progress

Second Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Under Progress Under Progress

Third Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Under Progress Under Progress

Fourth Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Under Progress Under Progress

Fifth Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Under Progress Under Progress

Sixth Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Under Progress

Seventh Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Under Progress

Eighth Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed Under Progress

Ninth Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed

Tenth Floor Completed Completed Completed Under progress Completed Completed Completed Completed Under progress

Eleventh Floor Completed Completed Completed Under progress Completed Completed Completed Under progress -

Under
Completed Completed - -
Twelfth Floor Completed Completed Completed Under progress progress
Thirteenth
Completed Under progress Completed Under progress - - -
Floor Completed Completed
Fourteenth
- Under progress - - - - -
Floor Completed -
C block C block C block
10th floor Internal wall & 6th & 7th Vitrified flooring tile 7th floor toilet dado work is under
ceiling 1st coat putty work is work is under progress. progress.
under progress.
C-Block Progress
Electrical
Toilet CPVC Pipe Inrernal ceiling & Vitrified Flooring
Chipping & pipe Water Proofing Screed Concrete Toilets dado tiles
Ceiling Internal Wall External wall wiring work wall 1st coat Putty Tiles
fixing with box
Block C Plastering Plastering Plastering
Lower
Basement NA NA NA NA NA NA NA NA Na NA
Upper
Basement NA NA NA NA NA NA NA NA NA NA

Ground Floor Completed Completed Completed Completed Completed Completed Completed Completed - -

First Floor Completed Completed Completed Completed Completed Completed Completed Completed Under Progress Under Progress

Second Floor Completed Completed Completed Completed Completed Completed Completed Completed Under Progress Under Progress

Third Floor Completed Completed Completed Completed Completed Completed Completed Completed Under Progress Under Progress

Fourth Floor Completed Completed Completed Completed Completed Completed Completed Completed Under Progress Under Progress

Fifth Floor Completed Completed Completed Completed Completed Completed Completed Completed Under Progress Under Progress

Sixth Floor Completed Completed Completed Completed Completed Completed Completed Completed Under progress Under Progress

Under Progress
Completed Completed Completed Completed Completed Under Progress
Seventh Floor Completed Completed Completed -

Eighth Floor Completed Completed Completed Completed Completed Completed Completed Completed - -

Ninth Floor Completed Completed Completed Completed Completed Completed Completed Completed - -

Tenth Floor Completed Completed Under progress Completed Completed Completed Completed Under progress - -

Eleventh Floor Completed Completed Under progress Completed Completed Completed Completed - - -

Twelfth Floor Completed Completed Under progress Completed Completed Under progress - - - -

Thirteenth Floor Completed Completed Under progress Completed Completed - - - - -

Fourteenth
- Under progress - - - - - - -
Floor -
B block & C block
Ground+14th floor Structure work completed.
Ground+14th floor block work completed.
South side podium work in progress.
West side compound wall work in progress. South side compund wall work in progress.