Analisa Harga Satuan Pekerjaan Persiapan

Diposkan : 31 Mei 2014


Oleh : Endang Kusman

No. URAIAN SATUAN VOLUME A SATUAN


(Rp)

A-01 1 M' Pagar Sementara Dari Kayu Tinggi 2 m


- Dolken Kayu Ø 8-10 / 400 cm Btg 1.25 28,000.00
- Semen Portland Kg 2.5 1,406.00
- Pasir beton M3 0.005 ###
- Koral Beton 2/3 M3 0.009 ###
- Kayu balok terentang M3 0.072 ###
- Paku Biasa 2" - 5" Kg 0.06 23,400.00
- Residu Kg 0.4 8,100.00
- Pekerja Oh 0.4 42,000.00
- Tukang Kayu Oh 0.2 65,000.00
- Kepala Tukang Oh 0.02 75,000.00
- Mandor Oh 0.02 80,000.00
Jumlah
Dibulatkan

A-02 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m


- Dolken Kayu Ø 8-10 / 400 cm Btg 1.25 28,000.00
- Semen Portland Kg 2.5 1,406.00
- Seng Gelombang BJLS-30 Lbr 1.2 62,900.00
- Pasir beton M3 0.005 ###
- Koral Beton 2/3 M3 0.009 ###
- Kayu balok terentang M3 0.072 ###
- Paku Biasa 2" - 5" Kg 0.06 23,400.00
- Meni Besi Kg 0.45 30,400.00
- Pekerja Oh 0.4 42,000.00
- Tukang Kayu Oh 0.2 65,000.00
- Kepala Tukang Oh 0.02 75,000.00
- Mandor Oh 0.02 80,000.00
Jumlah
Dibulatkan

A-03 1 M' Pagar SementaraKawat Duri Tinggi 1,80 m


- Dolken Kayu Ø 8-10 / 400 cm Btg 1 28,000.00
- Semen Portland Kg 2 1,406.00
- Kawat Duri Kg 2.5 63,500.00
- Pasir beton M3 0.005 ###
- Koral Beton 2/3 M3 0.009 ###
- Paku Biasa 2" - 5" Kg 0.06 23,400.00
- Pekerja Oh 0.3 42,000.00
- Tukang Kayu Oh 0.2 65,000.00
- Kepala Tukang Oh 0.02 75,000.00
- Mandor Oh 0.02 80,000.00
Jumlah
Dibulatkan

A-04 1 M2 Pengukuran Dan Pasang Bouwplank


- Kayu kaso 5/7 M3 0.012 ###
- Paku Biasa 2" - 5" Kg 0.02 23,400.00
- Kayu papan albasia M3 0.007 ###
- Pekerja Oh 0.1 42,000.00
- Tukang Kayu Oh 0.1 65,000.00
- Kepala Tukang Oh 0.01 75,000.00
- Mandor Oh 0.005 80,000.00
Jumlah
Dibulatkan

A-05 1 M2 Pembuatan Kantor Sementara dgn Lantai Dip


- Dolken Kayu Ø 8-10 / 400 cm Btg 1.25 28,000.00
- Kayu Balok terentang M3 0.18 ###
- Paku Biasa Kg 0.85 23,400.00
- Besi Strip Kg 1.1 26,800.00
- Semen Portland Kg 35 1,406.00
- Pasir Pasang M3 0.15 ###
- Pasir beton M3 0.1 ###
- Koral Beton2/3 M3 0.15 ###
- Bata Merah Bh 30 775
- Seng Plat m' 0.25 15,815.00
- Kawat harmonika M2 2 35,900.00
- Kaca Polos 3mm M2 0.08 87,400.00
- Kunci Tanam Bh 0.15 94,500.00
- Plywood 120 x 240 x 0,4 cm Lbr 0.06 ###
- Pekerja Oh 2 42,000.00
- Tukang Kayu Oh 2 65,000.00
- Tukang Batu Oh 1 65,000.00
- Kepala Tukang Oh 0.3 75,000.00
- Mandor Oh 0.05 80,000.00
Jumlah
Dibulatkan

A-06 1 M2 Pembuatan Gudang Semen dan Alat-alat


- Dolken Kayu Ø 8-10 / 400 cm Btg 1.7 28,000.00
- Kayu balok terentang M3 0.21 ###
- Paku Biasa Kg 0.3 23,400.00
- Semen Portland Kg 10.5 1,406.00
- Pasir Beton M3 0.03 ###
- Koral Beton 2/3 M3 0.05 ###
- Seng Gelombang BJLS 30 Lbr 1.5 62,900.00
- Pekerja Oh 1 42,000.00
- Tukang Kayu Oh 2 65,000.00
- Kepala Tukang Oh 0.2 75,000.00
- Mandor Oh 0.05 80,000.00
Jumlah
Dibulatkan

A-07 1 M2 Pembuatan Bedeng Buruh


- Dolken Kayu Ø 8-10 / 400 cm Btg 1.25 28,000.00
- Kayu balok terentang M3 0.186 ###
- Paku Biasa Kg 0.3 23,400.00
- Semen Portland Kg 18 1,406.00
- Pasir Beton M3 0.03 ###
- Koral Beton 2/3 M3 0.05 ###
- Seng Gelombang BJLS 30 Lbr 1.5 62,900.00
- Pekerja Oh 1 42,000.00
- Tukang Kayu Oh 2 65,000.00
- Kepala Tukang Oh 0.2 75,000.00
- Mandor Oh 0.05 80,000.00
Jumlah
Dibulatkan

A-08 1 M2 Membersihkan Lapangan dan Perataan


- Pekerja Oh 0.1 42,000.00
- Mandor Oh 0.05 80,000.00
Jumlah
Dibulatkan

A-09 1M2 Pembuatan Jalan Sementara


- Batu Belah 15/20 M3 0.15 ###
- Batu Pecah 5/7 M3 0.09 ###
- Pasir Pasang M3 0.01 ###
- Pekerja Oh 1 42,000.00
- Mandor Oh 0.05 80,000.00
Jumlah
Dibulatkan

A-10 1 M3 Bongkaran Beton Bertulang


- Pekerja Oh 6.667 42,000.00
- Mandor Oh 0.333 80,000.00
Jumlah
Dibulatkan

A-11 1 M3 Bongkaran Dinding Tembok Bata Merah


- Pekerja Oh 6.667 42,000.00
- Mandor Oh 0.033 80,000.00
Jumlah
Dibulatkan

A-12 1 M¹ Pagar beton Pracetak ( 5 x 50 x 213 ) cm


- Panel Beton Pracetak Lbr 0.986 ###
- Kolom Beton Pracetak Btg 0.525 ###
- Pasir Beton M3 0.074 ###
- Koral 2/3 M3 0.146 ###
- Semen abu - abu Kg 45 1,406.00
- Pekerja Oh 0.375 42,000.00
- Tukang Batu Oh 0.125 65,000.00
- Kepala Tukang Oh 0.012 75,000.00
- Mandor Oh 0.019 80,000.00
Jumlah
Dibulatkan

A-13 1 M¹ Pagar kawat ayam tiang besi L50.50.5, tinggi 1 m'


- Kawat ram ayam Lbr 0.434 14,900.00
- Besi siku L 50.50.5 Kg 6.786 18,300.00
- Besi pelat (1,2 x 3) mm Kg 0.0424 18,300.00
- Baut bh 4 600
- Semen Portland Kg 2.5 1,406.00
- Pasir beton M3 0.005 ###
- Koral Beton 2/3 M3 0.009 ###
- Pekerja Oh 0.375 42,000.00
- Tukang Batu Oh 0.125 65,000.00
- Kepala Tukang Oh 0.012 75,000.00
- Mandor Oh 0.019 80,000.00
Jumlah
Dibulatkan

A-14 1 M2 Pagar BRC lengkap dengan tiang


- BRC lengkap dengan tiang Lbr 0.434 ###
- Semen Portland Kg 2 1,406.00
- Kawat Duri Kg 2.5 63,500.00
- Pasir beton M3 0.005 ###
- Koral Beton 2/3 M3 0.009 ###
- Pekerja Oh 0.375 42,000.00
- Tukang Batu Oh 0.125 65,000.00
- Kepala Tukang Oh 0.012 75,000.00
- Mandor Oh 0.019 80,000.00
Jumlah
Dibulatkan

A-15 1 M2 Steiger Werk / perancah dari Bambu


- Bambu Ø 6 - 10 (600) cm btng 1 25,000.00
- Tali ijuk kg 0.25 23,400.00
- Pekerja org 0.25 42,000.00
- Tukang kayu org 0.017 65,000.00
- Kepala tukang org 0.002 75,000.00
- Mandor org 0.013 80,000.00
Jumlah
Dibulatkan
A-16 1 M' Cerucuk Bambu
- Bambu Ø 7 -10 (400) cm btng 1.25 25,000.00
- Pekerja org 0.5 42,000.00
- Mandor org 0.025 80,000.00
Jumlah
Dibulatkan
HARGA
(Rp)

35,000.00
3,515.00
1,277.00
1,899.90
190,080.00
1,404.00
3,240.00
16,800.00
13,000.00
1,500.00
1,600.00
269,315.90
269,316.00

35,000.00
3,515.00
75,480.00
1,277.00
1,899.90
190,080.00
1,404.00
13,680.00
16,800.00
13,000.00
1,500.00
1,600.00
355,235.90
355,236.00

28,000.00
2,812.00
158,750.00
1,277.00
1,899.90
1,404.00
12,600.00
13,000.00
1,500.00
1,600.00
222,842.90
222,843.00

22,446.00
468
14,501.90
4,200.00
6,500.00
750
400
49,265.90
49,266.00

35,000.00
475,200.00
19,890.00
29,480.00
49,210.00
35,010.00
25,540.00
31,665.00
23,250.00
3,953.75
71,800.00
6,992.00
14,175.00
8,400.00
84,000.00
130,000.00
65,000.00
22,500.00
4,000.00
1,135,065.75
1,135,066.00

47,600.00
554,400.00
7,020.00
14,763.00
7,662.00
10,555.00
94,350.00
42,000.00
130,000.00
15,000.00
4,000.00
927,350.00
927,350.00

35,000.00
491,040.00
7,020.00
25,308.00
7,662.00
10,555.00
94,350.00
42,000.00
130,000.00
15,000.00
4,000.00
861,935.00
861,935.00

4,200.00
4,000.00
8,200.00
8,200.00

30,825.00
17,640.00
2,334.00
42,000.00
4,000.00
96,799.00
96,799.00

280,014.00
26,640.00
306,654.00
306,654.00

280,014.00
2,640.00
282,654.00
282,654.00

196,411.20
138,600.00
18,899.60
30,820.60
63,270.00
15,750.00
8,125.00
900
1,520.00
474,296.40
474,296.00

6,466.60
124,183.80
775.92
2,400.00
3,515.00
1,277.00
1,899.90
15,750.00
8,125.00
900
1,520.00
166,813.22
166,813.00

74,344.20
2,812.00
158,750.00
1,277.00
1,899.90
15,750.00
8,125.00
900
1,520.00
265,378.10
265,378.00

25,000.00
5,850.00
10,500.00
1,105.00
150
1,040.00
43,645.00
43,645.00

31,250.00
21,000.00
2,000.00
54,250.00
54,250.00
Analisa Harga Satuan Pekerjaan Tanah
Berkut ini adalah contoh Analisa Harga Satuan (AHS) SNI tahun 2011 untuk pekerjaan tanah yang sering d
B. ANALISA HARGA SATUAN PEKERJAAN TANAH

No. URAIAN SATUAN VOLUME HARGA S HARGA


(Rp) (Rp)
B-01 1 M3 Galian Tanah Biasa sedalam 1 m
- Pekerja Oh 0.4 ### ###
- Mandor Oh 0.04 ### 3,200.00
Jumlah ###
Dibulatkan ###
B-02 1 M3 Galian Tanah Biasa Sedalam 2 m
- Pekerja Oh 0.526 ### ###
- Mandor Oh 0.052 ### 4,160.00
Jumlah ###
Dibulatkan ###
B-03 1 M3 Galian Tanah Biasa Sedalam 3 m
- Pekerja Oh 0.735 ### ###
- Mandor Oh 0.073 ### 5,840.00
Jumlah ###
Dibulatkan ###
B-04 1 M3 Galian Tanah Keras Sedalam 1 m
- Pekerja Oh 0.625 ### ###
- Mandor Oh 0.062 ### 4,960.00
Jumlah ###
Dibulatkan ###
B-05 1 M3 Galian Tanah Lumpur Sedalam 1 m
- Pekerja Oh 0.823 ### ###
- Mandor Oh 0.083 ### 6,640.00
Jumlah ###
Dibulatkan ###
pekerjaan tanah yang sering digunakan untuk pekerjaan bangunan rumah.
Satuan Pekerjaan Pondasi (AHS SNI 2011)
Untuk menghitung biaya pekerjaan pondasi bagunan rumah Anda diperlukan Analisa Harga Satuan Pekerj
C. ANALISA HARGA SATUAN PEKERJAAN PONDASI

No. URAIAN SATUAN VOLUME HARGA S HARGA


(Rp) (Rp)
C-01 1 M3 Pasanag Pondasi batu Kali adk 1pc : 3 ps
- Batu Bela M3 1.1 ### ###
- Semen Por Kg 202 1,406.00 ###
- Pasir Pas M3 0.485 ### ###
- Pekerja Oh 1.5 ### ###
- Tukang Ba Oh 0.6 ### ###
- Kepala Tu Oh 0.06 ### 4,500.00
- Mandor Oh 0.075 ### 6,000.00
Jumlah ###
Dibulatkan ###
C-02 1 M3 Pasang Pondasi Batu kali adk 1pc : 4ps
- Batu Bela M3 1.1 ### ###
- Semen Por Kg 163 1,406.00 ###
- Pasir Pas M3 0.52 ### ###
- Pekerja Oh 1.5 ### ###
- Tukang Ba Oh 0.6 ### ###
- Kepala Tu Oh 0.06 ### 4,500.00
- Mandor Oh 0.075 ### 6,000.00
Jumlah ###
Dibulatkan ###
C-03 1 M3 Pasang Pondasi Batu kali adk 1pc : 5ps
- Batu Bela M3 1.1 ### ###
- Semen Por Kg 136 1,406.00 ###
- Pasir Pas M3 0.544 ### ###
- Pekerja Oh 1.5 ### ###
- Tukang Ba Oh 0.6 ### ###
- Kepala Tu Oh 0.06 ### 4,500.00
- Mandor Oh 0.075 ### 6,000.00
Jumlah ###
Dibulatkan ###
C-04 1 M3 Pasang Pondasi Batu Kosong (aanstamping)
- Batu Bela M3 1.2 ### ###
- Pasir Urug M3 0.3 ### ###
- Pekerja Oh 0.78 ### ###
- Tukang Ba Oh 0.39 ### ###
- Kepala Tu Oh 0.039 ### 2,925.00
- Mandor Oh 0.039 ### 3,120.00
Jumlah ###
Dibulatkan ###
Analisa Harga Satuan Pekerjaaan Pondasi. Berikut adalah contoh analisa pekerjaan pondasi (AHS SNI tahun 2011). Pada dasa
S SNI tahun 2011). Pada dasarnya yang selalu berubah setiap tahun pada analisa harga satuan, adalah harga bahan dan upah,
dalah harga bahan dan upah, sedangkan koefisien (volume pek.) tetap.
Analisa Harga Satuan Pekerjaan Beton
NO URAIAN SAT VOLUMEHRG.SAT
D-17r2 1 M3 Sloof Beton Tulang 15/20 (180 kg besi + bekisting) 4dia. 12 ring 8-15
Kayu papan terentang M3 0.27 ###
Paku Biasa 2" - 5" Kg 2 23,400
Besi Beton Kg 180 16,500
Kawat Beton Kg 3 27,700
Semen Portland Kg 323 1,200
Pasir Beton M3 0.52 225,000
Koral Beton 2/3 M3 0.78 200,000
Pekerja Oh 4.85 55,000
Tukang Batu Oh 0.35 70,000
Tukang Kayu Oh 1.56 70,000
Tukang Besi Oh 1.4 70,000
Kepala Tukang Oh 0.331 80,000
Mandor Oh 0.17 85,000
Jumlah
Dibulatkan

1 M3 Kolom Beton Tulang 15/20 (180 kg besi + bekisting) 4dia.12 8-15


Kayu papan terentang M3 0.4 ###
Paku Biasa 2" - 5" Kg 4 23,400
Minyak Bekisting Ltr 40,500
Besi Beton Kg 180 16,500
Kawat Beton Kg 1.8 27,700
Semen Portland Kg 323 1,200
Pasir Beton M3 0.52 225,000
Koral Beton 2/3 M3 0.78 200,000
Kayu Balok Terentang M3 0.15 ###
Dolken Ø-8-10/4m Btg 20 15,000
Pekerja Oh 7.3 55,000
Tukang Batu Oh 0.35 70,000
Tukang Kayu Oh 3.3 70,000
Tukang Besi Oh 2.1 70,000
Kepala Tukang Oh 0.57 80,000
Mandor Oh 0.25 85,000
Jumlah 6.480.910
Dibulatkan 6.481.000

1 M3 Balok Beton Tulang 15/20 sofi-sofi, ring balk + balok poratl (180 kg besi + bekisting) 4dia.
Kayu papan terentang M3 0.32 ###
Paku Biasa 2" - 5" Kg 3.2 23,400
Besi Beton Kg 180 16,500
Kawat Beton Kg 2.25 27,700
Semen Portland Kg 323 1,200
Pasir Beton M3 0.52 225,000
Koral Beton 2/3 M3 0.78 200,000
Kayu Balok Terentang M3 0.14 ###
Dolken Ø-8-10/4m Btg 16 15,000
Pekerja Oh 5.96 55,000
Tukang Batu Oh 0.35 70,000
Tukang Kayu Oh 2.8 70,000
Tukang Besi Oh 1.4 70,000
Kepala Tukang Oh 0.455 80,000
Mandor Oh 0.208 85,000
Jumlah 6.412.865
Dibulatkan
D-29 1 M3 Tangga Beton Tulang (90 kg besi + bekisting)
Kayu papan terentang M3 0.25 ###
Paku Biasa 2" - 5" Kg 3 23,400
Minyak Bekisting Ltr 1.2 40,500
Besi Beton Kg 90 16,500
Kawat Beton Kg 3 27,700
Semen Portland Kg 323 1,200
Pasir Beton M3 0.52 225,000
Koral Beton 2/3 M3 0.78 200,000
Kayu Balok Terentang M3 0.105 ###
Dolken Ø-8-10/4m Btg 14 15,000
Pekerja Oh 5.6 55,000
Tukang Batu Oh 0.35 70,000
Tukang Kayu Oh 2.3 70,000
Tukang Besi Oh 1.4 70,000
Kepala Tukang Oh 0.405 80,000
Mandor Oh 0.202 85,000
Jumlah
Dibulatkan
3 1 M3 Membuat Plat Lantai Tb. 10 Cm Beton Bertulang ( 90 Kg Besi + Bekisting )
Kayu Terentang M3 0.4 ###
Paku Biasa 2" - 5" Kg 4 23,400
Minyak Bekisting Ltr 2 40,500
Besi Beton Polos Kg 90 16,500
Kawat Beton Kg 3 27,700
Kayu Balok Terentang M3 0.105 151,100
Plywood Tebal 9 mm Lbr 3.5 151,100
Dolken kayu Galam o - 8-10/4 m Btg 60 15,000
Semen Portland Kg 323 1,200
Pasir Beton M3 0.52 225,000
Koral Beton 2/3 M3 0.78 200,000
Pekerja Oh 5.2 55,000
Tukang Batu Oh 0.35 70,000
Tukang Kayu Oh 3.3 70,000
Kepala Tukang Oh 0.365 80,000
Mandor Oh 1.06 85,000
Jumlah
Dibulatkan
JUMLAH

769,500
46,800
###
83,100
387,600
117,000
156,000
266,750
24,500
109,200
98,000
26,480
14,450
###
###

###
93,600
-
###
49,860
387,600
117,000
156,000
396,000
300,000
401,500
24,500
231,000
147,000
45,600
21,250
6.480.910
6.481.000

(180 kg besi + bekisting) 4dia. 12, 8-15


912,000
74,880
###
62,325
387,600
117,000
156,000
369,600
240,000
327,800
24,500
196,000
98,000
36,400
17,680
6.412.865
###

712,500
70,200
48,600
###
83,100
387,600
117,000
156,000
277,200
210,000
308,000
24,500
161,000
98,000
32,400
17,170
###
###
si + Bekisting )
###
93,600 243
81,000 117
### 80.75
83,100 440.75
15,866 88.15
528,850
900,000
387,600
117,000
156,000
286,000
24,500
231,000
29,200
90,100
###
Analisa Harga Satuan Pekerjaan Dinding (AHS-SNI 2011)
Berikut adalah penggalan analisa harga satuan (AHS-SNI 2011) untuk pekerjaan dinding yang biasa digun
E. ANALISA HARGA SATUAN PEKERJAAN DINDING
No. URAIAN SATUAN VOLUME SATUAN
(Rp)

E-01 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 3ps


- Bata Merah Bh 140 775
- Semen Portland Kg 32.95 1,406.00
- Pasir Pasang M3 0.091 ###
- Pekerja Oh 0.65 ###
- Tukang Batu Oh 0.2 ###
- Kepala Tukang Oh 0.02 ###
- Mandor Oh 0.03 ###
Jumlah
Dibulatkan
E-02 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 4ps
- Bata Merah Bh 140 775
- Semen Portland Kg 26.55 1,406.00
- Pasir Pasang M3 0.093 ###
- Pekerja Oh 0.65 ###
- Tukang Batu Oh 0.2 ###
- Kepala Tukang Oh 0.02 ###
- Mandor Oh 0.03 ###
Jumlah
Dibulatkan
E-03 1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 5ps
- Bata Merah Bh 140 775
- Semen Portland Kg 22.2 1,406.00
- Pasir Pasang M3 0.102 ###
- Pekerja Oh 0.65 ###
- Tukang Batu Oh 0.2 ###
- Kepala Tukang Oh 0.02 ###
- Mandor Oh 0.03 ###
Jumlah
Dibulatkan

E-04 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 3ps


- Bata Merah Bh 70 775
- Semen Portland Kg 14.37 1,406.00
- Pasir Pasang M3 0.04 ###
- Pekerja Oh 0.32 ###
- Tukang Batu Oh 0.1 ###
- Kepala Tukang Oh 0.01 ###
- Mandor Oh 0.015 ###
Jumlah
Dibulatkan

E-05 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 4ps


- Bata Merah Bh 70 775
- Semen Portland Kg 11.5 1,406.00
- Pasir Pasang M3 0.043 ###
- Pekerja Oh 0.32 ###
- Tukang Batu Oh 0.1 ###
- Kepala Tukang Oh 0.01 ###
- Mandor Oh 0.015 ###
Jumlah
Dibulatkan

E-06 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 5ps


- Bata Merah Bh 70 775
- Semen Portland Kg 9.68 1,406.00
- Pasir Pasang M3 0.045 ###
- Pekerja Oh 0.32 ###
- Tukang Batu Oh 0.1 ###
- Kepala Tukang Oh 0.01 ###
- Mandor Oh 0.015 ###
Jumlah
Dibulatkan
AHS-SNI 2011)
jaan dinding yang biasa digunakan untuk menghitung biaya pekerjaan dinding pada rumah tinggal. Keseluruhan analisa pekerj

HARGA
(Rp)

###
###
###
###
###
1,500.00
2,400.00
###
###

###
###
###
###
###
1,500.00
2,400.00
###
###

###
###
###
###
###
1,500.00
2,400.00
###
###

###
###
9,336.00
###
6,500.00
750
1,200.00
###
###

###
###
###
###
6,500.00
750
1,200.00
###
###

###
###
###
###
6,500.00
750
1,200.00
###
###
al. Keseluruhan analisa pekerjaan dinding untuk berbagai ukuran ketebalan dinding dan komposisi adukan pada AHS-SNI ada s
i adukan pada AHS-SNI ada sekitar 40 analisa.
Analisa Harga Satuan Pekerjaan Plesteran (AHS SNI 2011)
Inilah penggalan analisa pekerjaan plesteran yang paling banyak digunakan untuk menghitung biaya bang
F. ANALISA HARGA SATUAN PEKERJAAN PLESTERAN
No. URAIAN SATUAN VOLUME SATUAN HARGA
(Rp) (Rp)
F-01 1 M2 Plesteran adk. 1pc : 2ps Tebal 15 mm
- Semen Portland Kg 8.52 1,406.00 ###
- Pasir Pasang M3 0.017 ### 3,967.80
- Pekerja Oh 0.2 ### 8,400.00
- Tukang Batu Oh 0.15 ### 9,750.00
- Kepala Tukang Oh 0.015 ### 1,125.00
- Mandor Oh 0.01 ### 800
Jumlah ###
Dibulatkan ###
F-02 1 M2 Plesteran adk. 1pc : 3ps Tebal 15 mm
- Semen Portland Kg 6.48 1,406.00 9,110.88
- Pasir Pasang M3 0.019 ### 4,434.60
- Pekerja Oh 0.2 ### 8,400.00
- Tukang Batu Oh 0.15 ### 9,750.00
- Kepala Tukang Oh 0.015 ### 1,125.00
- Mandor Oh 0.01 ### 800
Jumlah ###
Dibulatkan ###
F-03 1 M2 Plesteran adk. 1pc : 4ps Tebal 15 mm
- Semen Portland Kg 5.2 1,406.00 7,311.20
- Pasir Pasang M3 0.02 ### 4,668.00
- Pekerja Oh 0.2 ### 8,400.00
- Tukang Batu Oh 0.15 ### 9,750.00
- Kepala Tukang Oh 0.015 ### 1,125.00
- Mandor Oh 0.01 ### 800
Jumlah ###
Dibulatkan ###
F-04 1 M2 Plesteran adk. 1pc : 3ps Tebal 20 mm
- Semen Portland Kg 10.8 1,406.00 ###
- Pasir Pasang M3 0.026 ### 6,068.40
- Pekerja Oh 0.25 ### ###
- Tukang Batu Oh 0.2 ### ###
- Kepala Tukang Oh 0.02 ### 1,500.00
- Mandor Oh 0.0125 ### 1,000.00
Jumlah ###
Dibulatkan ###
F-05 1 M2 Plesteran adk. 1pc : 4ps Tebal 20 mm
- Semen Portland Kg 8.68 1,406.00 ###
- Pasir Pasang M3 0.028 ### 6,535.20
- Pekerja Oh 0.25 ### ###
- Tukang Batu Oh 0.2 ### ###
- Kepala Tukang Oh 0.02 ### 1,500.00
- Mandor Oh 0.0125 ### 1,000.00
Jumlah ###
Dibulatkan ###
F-06 1 M2 Plesteran adk. 1pc:5ps tebal 20 mm
- Semen Portland Kg 7.29 1,406.00 ###
- Pasir Pasang M3 0.026 ### 6,068.40
- Pekerja Oh 0.25 ### ###
- Tukang Batu Oh 0.2 ### ###
- Kepala Tukang Oh 0.02 ### 1,500.00
- Mandor Oh 0.0125 ### 1,000.00
Jumlah ###
Dibulatkan ###
F-11 1 M2 Acian Plesteran
- Semen Portland Kg 4 1,406.00 5,624.00
- Pekerja Oh 0.143 ### 6,006.00
- Tukang batu Oh 0.107 ### 6,955.00
- Kepala Tukang Oh 0.0105 ### 787.5
- Mandor Oh 0.0105 ### 840
Jumlah ###
Dibulatkan ###
(AHS SNI 2011)
untuk menghitung biaya bangunan rumah tinggal.
Analisa Harga Satuan Penutup Atap (AHS SNI 2011)
Untuk menghitung pekerjaan penutup atap seperti genting plentong, genting morando, genting keramik, g
G. ANALISA HARGA SATUAN PEKERJAAN PENUTUP ATAP
No. URAIAN SATUAN VOLUME

G-01 1 M2 Pasang Atap Genteng Palentong


- Genteng palentong Bh 25
- Pekerja Oh 0.15
- Tukang kayu Oh 0.075
- Kepala tukang Oh 0.008
- Mandor Oh 0.008
Jumlah
Dibulatkan

G-02 1 M2 Pasang Genteng Bubung Palentong


- Genteng bubung palentong Bh 5
- Semen Portland Kg 8
- Pasir pasang M3 0.032
- Pekerja Oh 0.4
- Tukang kayu Oh 0.2
- Kepala tukang Oh 0.02
- Mandor Oh 0.002
Jumlah
Dibulatkan

G-03 1 M2 Pasang Roof Light Fibreglass ( 180 x 90 ) cm


- Roof light fibreglass Lbr 0.6
- Paku biasa ½" - 1" Kg 0.05
- Pekerja Oh 0.14
- Tukang kayu Oh 0.067
- Kepala tukang Oh 0.007
- Mandor Oh 0.007
Jumlah
Dibulatkan

G-04 1 M2 Pasang Atap Asbes Gelombang ( 3,00 x 1,05 m ) x 4


- Asbes gelombang Lbr 0.35
- Paku seng Kg 0.12
- Pekerja Oh 0.14
- Tukang kayu Oh 0.07
- Kepala tukang Oh 0.007
- Mandor Oh 0.007
Jumlah
Dibulatkan

G-05 1 M2 Pasang Atap Asbes Gelombang ( 2,70 x 1,05 m ) x 4 mm


- Asbes gelombang Lbr 0.42
- Paku seng Kg 0.12
- Pekerja Oh 0.14
- Tukang kayu Oh 0.07
- Kepala tukang Oh 0.007
- Mandor Oh 0.007
Jumlah
Dibulatkan

G-06 1 M2 Pasang Atap Asbes Gelombang ( 2,40 x 1,05 m ) x 4


- Asbes gelombang Lbr 0.44
- Paku seng Kg 0.12
- Pekerja Oh 0.14
- Tukang kayu Oh 0.067
- Kepala tukang Oh 0.007
- Mandor Oh 0.007
Jumlah
Dibulatkan
G-07 1 M2 Pasang Atap Asbes Gelombang ( 2,10 x 1,05 m ) x 4 mm
- Asbes gelombang Lbr 0.51
- Paku seng Kg 0.12
- Pekerja Oh 0.14
- Tukang kayu Oh 0.067
- Kepala tukang Oh 0.007
- Mandor Oh 0.007
Jumlah
Dibulatkan

G-08 1 M2 Pasang Atap Asbes Gelombang ( 1,50 x 1,05 m ) x 4


- Asbes gelombang Lbr 0.8
- Paku seng Kg 0.12
- Pekerja Oh 0.14
- Tukang kayu Oh 0.067
- Kepala tukang Oh 0.007
- Mandor Oh 0.007
Jumlah
Dibulatkan

G-09 1 M¹ Pasang Nok Stel Gelombang 1,05 m


- Nok stel gelombang Lbr 2.1
- Paku sekrup 3,5" Bh 6
- Pekerja Oh 0.084
- Tukang kayu Oh 0.125
- Kepala tukang Oh 0.013
- Mandor Oh 0.004
Jumlah
Dibulatkan

G-10 1 M2 Pasang Atap Genteng Beton


- Genteng beton bh 11
- Paku biasa 2" - 5" Kg 0.03
- Pekerja Oh 0.2
- Tukang kayu Oh 0.1
- Kepala tukang Oh 0.01
- Mandor Oh 0.01
Jumlah
Dibulatkan

G-11 1 M2 Pasang Atap Genteng Murando Natural


- Genteng murando natural bh 18
- Pekerja Oh 0.15
- Tukang kayu Oh 0.075
- Kepala tukang Oh 0.008
- Mandor Oh 0.008
Jumlah
Dibulatkan

G-12 1 M2 Pasang Atap Genteng Murando Glazur


- Genteng murando glazur bh 18
- Pekerja Oh 0.15
- Tukang kayu Oh 0.075
- Kepala tukang Oh 0.008
- Mandor Oh 0.008
Jumlah
Dibulatkan
NI 2011)
morando, genting keramik, genting beton dll. diperlukan analisa harga satuan penutup atap. Berikut adalah penggalan AHS SN

SATUAN HARGA
(Rp) (Rp)

1,900.00 ###
### 6,300.00
### 4,875.00
### 600
### 640
###
###

6,000.00 ###
1,406.00 ###
### 7,468.80
### ###
### ###
### 1,500.00
### 160
###
###

### ###
### 1,190.00
### 5,880.00
### 4,355.00
### 525
### 560
###
###

### ###
### 2,856.00
### 5,880.00
### 4,550.00
### 525
### 560
###
###

### ###
### 2,856.00
### 5,880.00
### 4,550.00
### 525
### 560
###
###

### ###
### 2,856.00
### 5,880.00
### 4,355.00
### 525
### 560
###
###

### ###
### 2,856.00
### 5,880.00
### 4,355.00
### 525
### 560
###
###

### ###
### 2,856.00
### 5,880.00
### 4,355.00
### 525
### 560
###
###

### ###
800 4,800.00
### 3,528.00
### 8,125.00
### 975
### 320
###
###

8,500.00 ###
### 702
### 8,400.00
### 6,500.00
### 750
### 800
###
###

2,700.00 ###
### 6,300.00
### 4,875.00
### 600
### 640
###
###

4,000.00 ###
### 6,300.00
### 4,875.00
### 600
### 640
###
###
kut adalah penggalan AHS SNI 2011 penutup atap yang biasa digunakan untuk menghitung RAB Rumah tinggal.
Rumah tinggal.
Analisa Harga Satuan Pekerjaan Penutup Langit-langit (AHS
Berikut ini adalah penggalan Analisa Harga Satuan Pekerjaan untuk menghitung biaya pekerjaan langit-lan

H. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANGIT-LANGIT


No. URAIAN SATUAN VOLUME SATUAN HARGA
(Rp) (Rp)
(Rp) (Rp)

H-01 1 M2 Langit-langit
- Pelat asb m2 1.1 ### ###
- Paku seng Kg 0.01 ### 238
- Pekerja Oh 0.03 ### 1,260.00
- Tukang k Oh 0.07 ### 4,550.00
- Kepala tu Oh 0.007 ### 525
- Mandor Oh 0.0015 ### 120
Jumlah ###
Dibulatkan ###

H-02 1 M2 Langit-langit
- Pelat asb Lbr 1.1 ### ###
- Paku seng Kg 0.01 ### 238
- Pekerja Oh 0.03 ### 1,260.00
- Tukang k Oh 0.07 ### 4,550.00
- Kepala tu Oh 0.007 ### 525
- Mandor Oh 0.0015 ### 120
Jumlah ###
Dibulatkan ###

H-03 1 M2 Langit-langit Akustik (


- Akustik 6 Lbr 1.5 ### ###
- Paku Kg 0.05 ### 1,190.00
- Pekerja Oh 0.06 ### 2,520.00
- Tukang k Oh 0.1 ### 6,500.00
- Kepala tu Oh 0.01 ### 750
- Mandor Oh 0.003 ### 240
Jumlah ###
Dibulatkan ###

H-04 1 M2 Langit-langit Akustik ( 60 x 120 ) cm + Ra


- Profil All M¹ 3.6 ### ###
- Kawat f Kg 0.15 ### 4,230.00
- Ramset / d Bh 1.05 7,200.00 7,560.00
- Akustik 6 Lbr 1.5 ### ###
- Pekerja Oh 0.15 ### 6,300.00
- Tukang k Oh 0.5 ### ###
- Kepala tu Oh 0.05 ### 3,750.00
- Mandor Oh 0.0075 ### 600
Jumlah ###
Dibulatkan ###

H-05 1 M2 Langit-langit teakwood (60 x 120) cm, t = 4 mm + r


- Kayu Balo M3 0.023 ### ###
- Paku biasa Kg 0.06 ### 1,404.00
- Teakwood Lbr 0.39 ### ###
- Pekerja Oh 0.27 ### ###
- Tukang k Oh 0.4 ### ###
- Kepala tu Oh 0.04 ### 3,000.00
- Mandor Oh 0.0135 ### 1,080.00
Jumlah ###
Dibulatkan ###

H-06 1 M2 Langit-langit Teakwood 3 mm + Rangka Ka


- Kayu Balo M3 0.023 ### ###
- Paku biasa Kg 0.06 ### 1,404.00
- Teakwood Lbr 0.39 ### ###
- Pekerja Oh 0.27 ### ###
- Tukang k Oh 0.4 ### ###
- Kepala tu Oh 0.04 ### 3,000.00
- Mandor Oh 0.0135 ### 1,080.00
Jumlah ###
Dibulatkan ###

H-07 1 M2 Langit-langit Triplek 4 mm + Rangka Kayu


- Kayu Balo M3 0.023 ### ###
- Paku biasa Kg 0.06 ### 1,428.00
- Triplek 1 Lbr 0.39 ### ###
- Pekerja Oh 0.27 ### ###
- Tukang k Oh 0.4 ### ###
- Kepala tu Oh 0.04 ### 3,000.00
- Mandor Oh 0.0135 ### 1,080.00
Jumlah ###
Dibulatkan ###

H-08 1 M2 Langit-langit Gypsum Board, tebal 9 mm +


- Hollow 4/ Btg 0.415 ### ###
- Hollow 2/ Btg 0.15 ### 3,390.00
- Gypsum bo Lbr 0.364 ### ###
- Paku gyp kg 0.11 ### 1,925.00
- Ramset / d Bh 4 7,200.00 ###
- Cotton pla Bh 0.072 ### 1,080.00
- Compoun Zak 0.125 ### 9,375.00
- Pekerja Oh 0.1 ### 4,200.00
- Tukang k Oh 0.05 ### 3,250.00
- Kepala tu Oh 0.005 ### 375
- Mandor Oh 0.005 ### 400
Jumlah ###
Dibulatkan ###

H-09 1 M2 Langit-langit GRC t = 4 mm + ran


- Hollow 4/ Btg 0.415 ### ###
- Hollow 2/ Btg 0.15 ### 3,390.00
- GRC ( 120 Lbr 0.364 ### ###
- Paku GRC kg 0.11 ### 3,850.00
- Ramset / d Bh 4 7,200.00 ###
- Cotton pla Bh 0.072 ### 1,080.00
- Compoun Zak 0.125 ### 9,375.00
- Pekerja Oh 0.1 ### 4,200.00
- Tukang k Oh 0.05 ### 3,250.00
- Kepala tu Oh 0.005 ### 375
- Mandor Oh 0.005 ### 400
Jumlah ###
Dibulatkan ###

H-10 1 M2 Langit-langit gypsum t = 9 mm + Rangka


- Kayu Balo M3 0.023 ### ###
- Paku biasa Kg 0.06 ### 1,428.00
- Gypsum bo Lbr 0.39 ### ###
- Paku sekr kg 0.11 ### 1,925.00
- Pekerja Oh 0.27 ### ###
- Tukang k Oh 0.4 ### ###
- Kepala tu Oh 0.04 ### 3,000.00
- Mandor Oh 0.0135 ### 1,080.00
Jumlah ###
Dibulatkan ###

H-11 1 M2 Langit-langit GRC t = 4 mm + Rangka Kay


- Kayu Balo M3 0.023 ### ###
- Paku biasa Kg 0.06 ### 1,428.00
- GRC ( 120 Lbr 0.39 ### ###
- Paku GRC kg 0.11 ### 3,850.00
- Pekerja Oh 0.27 ### ###
- Tukang k Oh 0.4 ### ###
- Kepala tu Oh 0.04 ### 3,000.00
- Mandor Oh 0.0135 ### 1,080.00
Jumlah ###
Dibulatkan ###
H-12 1 M¹ List Langit-lan
- List Kayu p M¹ 1.05 ### ###
- Paku Kg 0.01 ### 238
- Pekerja Oh 0.05 ### 2,100.00
- Tukang k Oh 0.05 ### 3,250.00
- Kepala tu Oh 0.005 ### 375
- Mandor Oh 0.003 ### 240
Jumlah ###
Dibulatkan ###

H-13 1 M¹ List Langit-la


- List gyps M¹ 1.05 8,500.00 8,925.00
- Tepung g Kg 0.15 ### 1,875.00
- Pekerja Oh 0.05 ### 2,100.00
- Tukang k Oh 0.05 ### 3,250.00
- Kepala tu Oh 0.005 ### 375
- Mandor Oh 0.003 ### 240
Jumlah ###
Dibulatkan ###
angit-langit (AHS SNI 2011)
ung biaya pekerjaan langit-langit: asbes, akustik, tekwood, gypsum, dan GRC.
Analisa Harga Satuan Pekerjaan Penutup Lantai dan Dinding
Berikut adalah analisa harga satuan pekerjaan penutup landat dan dinding untuk menghitung biaaya penu
No. URAIAN SATUAN VOLUME

I-01 1 M2 Lantai Ubin Granito ukuran 40 x 4


- Granito 40 x 40 cm m2 1.05
- Semen portland Kg 9.8
- Pasir pasang M3 0.0215
- Semen warna Kg 1.3
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-02 1 M2 Lantai Ubin Granito ukuran 30 x 3


- Granito 30 x 30 cm m2 1.05
- Semen portland Kg 10
- Pasir pasang M3 0.0215
- Semen warna Kg 1.5
- Pekerja Oh 0.26
- Tukang batu Oh 0.125
- Kepala tukang Oh 0.0125
- Mandor Oh 0.013
Jumlah
Dibulatkan

I-03 1 M¹ Plint Ubin Granito ukuran 10 x 40


- Plint granito 10 x 40 cm Bh 2.65
- Semen portland Kg 1.2
- Pasir pasang M3 0.003
- Semen warna Kg 0.1
- Pekerja Oh 0.06
- Tukang batu Oh 0.03
- Kepala tukang Oh 0.003
- Mandor Oh 0.003
Jumlah
Dibulatkan
I-04 1 M¹ Plint Ubin Granito ukuran 10 x 30
- Plint granito 10 x 30 cm Bh 3.33
- Semen portland Kg 1.65
- Pasir pasang M3 0.0032
- Semen warna Kg 0.1
- Pekerja Oh 0.09
- Tukang batu Oh 0.09
- Kepala tukang Oh 0.009
- Mandor Oh 0.0045
Jumlah
Dibulatkan

I-05 1 M2 Lantai Keramik Corak 10 x 20 cm setara Mulia


- Keramik corak 10 x 20 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-06 1 M2 Lantai Keramik corak 20 x 20 cm se


- Keramik corak 20 x 20 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-07 1 M2 Lantai Keramik polos 30 x 30 cm se


- Keramik polos 30 x 30 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-08 1 M2 Lantai Keramik corak 30 x 30 cm Se


- Keramik corak 30 x 30 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-09 1 M2 Lantai Keramik polos 40 x 40 cm Se


- Keramik polos 40 x 40 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-10 1 M2 Lantai Keramik corak 40 x 40 cm Se


- Keramik corak 40 x 40 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan
I-11 1 M2 Lantai Keramik Corak 10 x 20 cm setara Roman
- Keramik corak 10 x 20 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-12 1 M2 Lantai Keramik corak 20 x 20 cm s


- Keramik corak 20 x 20 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-13 1 M2 Lantai Keramik polos 30 x 30 cm s


- Keramik polos 30 x 30 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-14 1 M2 Lantai Keramik corak 30 x 30 cm


- Keramik corak 30 x 30 cm M2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-15 1 M2 Lantai Keramik polos 40 x 40 cm s


- Keramik polos 40 x 40 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-16 1 M2 Lantai Keramik corak 40 x 40 cm


- Keramik corak 40 x 40 cm m2 1
- Semen portland Kg 8
- Pasir pasang M3 0.0215
- Semen warna Kg 0.013
- Pekerja Oh 0.25
- Tukang batu Oh 0.12
- Kepala tukang Oh 0.012
- Mandor Oh 0.0125
Jumlah
Dibulatkan

I-17 1 M2 Lantai Marmer


- Marmer m2 1.06
- Semen portland Kg 8.19
- Pasir pasang M3 0.045
- Semen warna Kg 0.65
- Pekerja Oh 0.7
- Tukang batu Oh 0.35
- Kepala tukang Oh 0.035
- Mandor Oh 0.035
Jumlah
Dibulatkan

I-18 1 M2 Lantai Parquet Jati


- Parquet jati M2 1.05
- Lem vinyl Kg 0.6
- Pekerja Oh 0.65
- Tukang Oh 0.35
- Kepala tukang Oh 0.035
- Mandor Oh 0.0325
Jumlah
Dibulatkan
antai dan Dinding (AHS SNI 2011)
untuk menghitung biaaya penutup lantai per meter persegi, seperti lantai keramik, lantai marmer dll.
HARGA SATUAN HARGA
(Rp) (Rp)

345,000.00 362,250.00
1,406.00 13,778.80
233,400.00 5,018.10
15,700.00 20,410.00
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
421,656.90
421,657.00

322,800.00 338,940.00
1,406.00 14,060.00
233,400.00 5,018.10
15,700.00 23,550.00
42,000.00 10,920.00
65,000.00 8,125.00
75,000.00 937.5
80,000.00 1,040.00
402,590.60
402,591.00

27,600.00 73,140.00
1,406.00 1,687.20
233,400.00 700.2
15,700.00 1,570.00
42,000.00 2,520.00
65,000.00 1,950.00
75,000.00 225
80,000.00 240
82,032.40
82,032.00
25,900.00 86,247.00
1,406.00 2,319.90
233,400.00 746.88
15,700.00 1,570.00
42,000.00 3,780.00
65,000.00 5,850.00
75,000.00 675
80,000.00 360
101,548.78
101,549.00

56,000.00 56,000.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
92,670.20
92,670.00

62,500.00 62,500.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
99,170.20
99,170.00

53,000.00 53,000.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
89,670.20
89,670.00

58,000.00 58,000.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
94,670.20
94,670.00

56,800.00 56,800.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
93,470.20
93,470.00

65,500.00 65,500.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
102,170.20
102,170.00
72,200.00 72,200.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
108,870.20
108,870.00

75,200.00 75,200.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
111,870.20
111,870.00

68,900.00 68,900.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
105,570.20
105,570.00

76,600.00 76,600.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
113,270.20
113,270.00

72,500.00 72,500.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
109,170.20
109,170.00

77,000.00 77,000.00
1,406.00 11,248.00
233,400.00 5,018.10
15,700.00 204.1
42,000.00 10,500.00
65,000.00 7,800.00
75,000.00 900
80,000.00 1,000.00
113,670.20
113,670.00

550,000.00 583,000.00
1,406.00 11,515.14
233,400.00 10,503.00
15,700.00 10,205.00
42,000.00 29,400.00
65,000.00 22,750.00
75,000.00 2,625.00
80,000.00 2,800.00
672,798.14
672,798.00
375,400.00 394,170.00
44,000.00 26,400.00
42,000.00 27,300.00
65,000.00 22,750.00
75,000.00 2,625.00
80,000.00 2,600.00
475,845.00
475,845.00
Analisa Harga Satuan Pekerjaan Kayu - AHS SNI 2011
Berikut adalah penggalan analisa harga satuan pekerjaan kayu, untuk menghitung harga satuan pekerjaan
J. ANALISA HARGA SATUAN PEKERJAAN KAYU
No. URAIAN SATUAN VOLUME

J-01 1 M3 Kusen Pintu & jendela kayu Kamper Samarinda


- Kayu Balok Kamper Samarinda m3 1.2
- Pekerja Oh 6
- Tukang Kayu Oh 18
- Kepala Tukang Oh 2
- Mandor Oh 0.3
Jumlah
Dibulatkan
J-02 1 M3 Kusen Pintu & jendela kayu Kamper Medan/Kruing
- Kayu Balok Kamper Medan M3 1.2
- Pekerja Oh 6
- Tukang Kayu Oh 18
- Kepala Tukang Oh 2
- Mandor Oh 0.3
Jumlah
Dibulatkan
J-03 1 M3 Kusen Pintu & jendela kayu Borneo Super
- Kayu Borneo Balok Super M3 1.2
- Pekerja Oh 6
- Tukang Kayu Oh 18
- Kepala Tukang Oh 2
- Mandor Oh 0.3
Jumlah
Dibulatkan

J-04 1 M2 Pintu Panel Kayu Kamper Samarinda


- Kayu Papan Kamper Samarinda M3 0.04
- Paku Biasa 2" - 5" Kg 0.05
- Pekerja Oh 1
- Tukang Kayu Oh 2.5
- Kepala Tukang Oh 0.25
- Mandor Oh 0.05
Jumlah
Dibulatkan

J-05 1 M2 Pintu Panel Kayu Kamper Medan/Kruing


- Kayu Papan Kamper Medan M3 0.04
- Paku Biasa 2" - 5" Kg 0.05
- Pekerja Oh 1
- Tukang Kayu Oh 2.5
- Kepala Tukang Oh 0.25
- Mandor Oh 0.05
Jumlah
Dibulatkan
J-06 1 M2 Pintu & Jendela Kaca Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.035
- Pekerja Oh 0.8
- Tukang Kayu Oh 2
- Kepala Tukang Oh 0.2
- Mandor Oh 0.04
Jumlah
Dibulatkan
J-07 1 M2 Pintu & Jendela Kaca Kayu Borneo
- Kayu Papan Borneo Super M3 0.035
- Pekerja Oh 0.8
- Tukang Kayu Oh 2
- Kepala Tukang Oh 0.2
- Mandor Oh 0.04
Jumlah
Dibulatkan
J-08 1 M2 Pintu & Jendela Jalusi Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.064
- Pekerja Oh 1
- Tukang Kayu Oh 3
- Kepala Tukang Oh 0.3
- Mandor Oh 0.5
Jumlah
Dibulatkan
J-09 1 M2 Pintu Triplek Rangkap, Rangka Tertutup Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0196
- Paku Biasa ½" - 1" Kg 0.03
- Lem Kayu Ltr 0.3
- Triplek 120 x 240 x 0,4 cm Lbr 1
- Pekerja Oh 0.6
- Tukang Kayu Oh 2
- Kepala Tukang Oh 0.2
- Mandor Oh 0.03
Jumlah
Dibulatkan
J-10 1 M2 Jalusi Mati Kusen Kayu kamper Medan
- Kayu Papan Kamper Medan M3 0.06
- Paku Biasa ½" - 1" Kg 0.15
- Pekerja Oh 0.5
- Tukang Kayu Oh 2
- Kepala Tukang Oh 0.2
- Mandor Oh 0.025
Jumlah
Dibulatkan

J-11 1 M2 Pintu Triplek Rangkap, Rangka Kayu Borneo Super


- Kayu Papan Borneo Super M3 0.0196
- Paku Biasa ½" - 1" Kg 0.03
- Lem Kayu Ltr 0.3
- Triplek 120 x 240 x 0,4 cm Lbr 1
- Pekerja Oh 0.6
- Tukang Kayu Oh 2
- Kepala Tukang Oh 0.2
- Mandor Oh 0.03
Jumlah
Dibulatkan
J-12 1 M2 Pintu Teakwood Rangkap, rangka Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0196
- Paku Biasa ½" - 1" Kg 0.3
- Lem Kayu Ltr 0.3
- Teakwood 4 mm Lbr 1
- Pekerja Oh 0.6
- Tukang Kayu Oh 2
- Kepala Tukang Oh 0.2
- Mandor Oh 0.03
Jumlah
Dibulatkan
J-13 1 M2 Pintu Triplek & Formika, Rangka Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0196
- Paku Biasa ½" - 1" Kg 0.3
- Lem Kayu Ltr 0.8
- Triplek 120 x 240 x 0,4 cm Lbr 1
- Formica 3" x 6" Lbr 0.5
- Pekerja Oh 0.8
- Tukang Kayu Oh 2.5
- Kepala Tukang Oh 0.25
- Mandor Oh 0.04
Jumlah
Dibulatkan
J-14 1 M2 Pintu Teakwood & Formika, Rangka Kayu Kamper Medan (dipolitur)
- Kayu Papan Kamper Medan M3 0.0196
- Paku Biasa ½" - 1" Kg 0.3
- Lem Kayu Ltr 0.8
- Teakwood 120 x 240 x 0,4 cm Lbr 1
- Formica 4" x 8" Lbr 0.5
- Pekerja Oh 0.8
- Tukang Kayu Oh 2.5
- Kepala Tukang Oh 0.25
- Mandor Oh 0.04
Jumlah
Dibulatkan

J-15 1 M3 Kuda-kuda Kayu Kamper Medan


- Kayu Balok Kamper Medan M3 1.1
- Besi Strip Kg 15
- Paku Biasa 2" - 5" Kg 0.8
- Pekerja Oh 4
- Tukang Kayu Oh 12
- Kepala Tukang Oh 1.2
- Mandor Oh 0.2
Jumlah
Dibulatkan
J-16 1 M3 Kuda-kuda Kayu Borneo Super
- Kayu balok Borneo super M3 1.1
- Besi Strip Kg 15
- Paku Biasa 2" - 5" Kg 0.8
- Pekerja Oh 4
- Tukang Kayu Oh 12
- Kepala Tukang Oh 1.2
- Mandor Oh 0.2
Jumlah
Dibulatkan
J-17 1 M2 Kaso + Reng Genteng Plentong Kayu Borneo Super
- Kayu balok Borneo super m3 0.012
- Paku Biasa 2" - 5" Kg 0.15
- Pekerja Oh 0.1
- Tukang Kayu Oh 0.1
- Kepala Tukang Oh 0.01
- Mandor Oh 0.005
Jumlah
Dibulatkan
J-18 1 M2 Kaso + Reng Genteng Beton Kayu Borneo Super
- Kayu balok Borneo super M3 0.014
- Paku Biasa 2" - 5" Kg 0.15
- Pekerja Oh 0.1
- Tukang Kayu Oh 0.1
- Kepala Tukang Oh 0.01
- Mandor Oh 0.005
Jumlah
Dibulatkan
J-19 1 M' Lisplang uk (3x20)cm, Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0072
- Paku Biasa 2" - 5" Kg 0.05
- Pekerja Oh 0.1
- Tukang Kayu Oh 0.2
- Kepala Tukang Oh 0.02
- Mandor Oh 0.005
Jumlah
Dibulatkan

J-20 1 M' Lisplang uk (3x30)cm, Kayu Kamper Medan


- Kayu Papan Kamper Medan M3 0.011
- Paku Biasa 2" - 5" Kg 0.05
- Pekerja Oh 0.11
- Tukang Kayu Oh 0.22
- Kepala Tukang Oh 0.022
- Mandor Oh 0.005
Jumlah
Dibulatkan

J-21 1 M¹ List Plafond + kayu Profil 10 cm


- Kayu Profil 10 cm M' 1.05
- Pekerja Oh 0.021
- Tukang Kayu Oh 0.021
- Kepala Tukang Oh 0.002
- Mandor Oh 0.001
Jumlah
Dibulatkan
SNI 2011
ung harga satuan pekerjaan kayu per m3, seperti pekerjaan kusen dan jendela, pekerjaan plapond, dan pekerjaan atap.

HARGA SATUAN HARGA

8,633,700.00 10,360,440.00
42,000.00 252,000.00
65,000.00 1,170,000.00
75,000.00 150,000.00
80,000.00 24,000.00
11,956,440.00
11,956,440.00

5,692,600.00 6,831,120.00
42,000.00 252,000.00
65,000.00 1,170,000.00
75,000.00 150,000.00
80,000.00 24,000.00
8,427,120.00
8,427,120.00

5,280,000.00 6,336,000.00
42,000.00 252,000.00
65,000.00 1,170,000.00
75,000.00 150,000.00
80,000.00 24,000.00
7,932,000.00
7,932,000.00

8,633,700.00 345,348.00
23,400.00 1,170.00
42,000.00 42,000.00
65,000.00 162,500.00
75,000.00 18,750.00
80,000.00 4,000.00
573,768.00
573,768.00

5,692,600.00 227,704.00
23,400.00 1,170.00
42,000.00 42,000.00
65,000.00 162,500.00
75,000.00 18,750.00
80,000.00 4,000.00
456,124.00
456,124.00
5,692,600.00 199,241.00
42,000.00 33,600.00
65,000.00 130,000.00
75,000.00 15,000.00
80,000.00 3,200.00
381,041.00
381,041.00

5,595,800.00 195,853.00
42,000.00 33,600.00
65,000.00 130,000.00
75,000.00 15,000.00
80,000.00 3,200.00
377,653.00
377,653.00

5,692,600.00 364,326.40
42,000.00 42,000.00
65,000.00 195,000.00
75,000.00 22,500.00
80,000.00 40,000.00
663,826.40
663,826.00

5,692,600.00 111,574.96
23,800.00 714
23,900.00 7,170.00
64,400.00 64,400.00
42,000.00 25,200.00
65,000.00 130,000.00
75,000.00 15,000.00
80,000.00 2,400.00
356,458.96
356,459.00

5,692,600.00 341,556.00
23,800.00 3,570.00
42,000.00 21,000.00
65,000.00 130,000.00
75,000.00 15,000.00
80,000.00 2,000.00
513,126.00
513,126.00

5,595,800.00 109,677.68
23,800.00 714
23,900.00 7,170.00
64,400.00 64,400.00
42,000.00 25,200.00
65,000.00 130,000.00
75,000.00 15,000.00
80,000.00 2,400.00
354,561.68
354,562.00

5,692,600.00 111,574.96
23,800.00 7,140.00
23,900.00 7,170.00
131,700.00 131,700.00
42,000.00 25,200.00
65,000.00 130,000.00
75,000.00 15,000.00
80,000.00 2,400.00
430,184.96
430,185.00

5,692,600.00 111,574.96
23,800.00 7,140.00
23,900.00 19,120.00
64,400.00 64,400.00
132,900.00 66,450.00
42,000.00 33,600.00
65,000.00 162,500.00
75,000.00 18,750.00
80,000.00 3,200.00
486,734.96
486,735.00

5,692,600.00 111,574.96
23,800.00 7,140.00
23,900.00 19,120.00
131,700.00 131,700.00
238,100.00 119,050.00
42,000.00 33,600.00
65,000.00 162,500.00
75,000.00 18,750.00
80,000.00 3,200.00
606,634.96
606,635.00

5,692,600.00 6,261,860.00
26,800.00 402,000.00
23,800.00 19,040.00
42,000.00 168,000.00
65,000.00 780,000.00
75,000.00 90,000.00
80,000.00 16,000.00
7,736,900.00
7,736,900.00

5,280,000.00 5,808,000.00
26,800.00 402,000.00
23,800.00 19,040.00
42,000.00 168,000.00
65,000.00 780,000.00
75,000.00 90,000.00
80,000.00 16,000.00
7,283,040.00
7,283,040.00

5,280,000.00 63,360.00
23,800.00 3,570.00
42,000.00 4,200.00
65,000.00 6,500.00
75,000.00 750
80,000.00 400
78,780.00
78,780.00

5,280,000.00 73,920.00
23,800.00 3,570.00
42,000.00 4,200.00
65,000.00 6,500.00
75,000.00 750
80,000.00 400
89,340.00
89,340.00

5,823,400.00 41,928.48
23,800.00 1,190.00
42,000.00 4,200.00
65,000.00 13,000.00
75,000.00 1,500.00
80,000.00 400
62,218.48
62,218.00

5,692,600.00 62,618.60
23,800.00 1,190.00
42,000.00 4,620.00
65,000.00 14,300.00
75,000.00 1,650.00
80,000.00 400
84,778.60
84,779.00

29,400.00 30,870.00
42,000.00 882
65,000.00 1,365.00
75,000.00 150
80,000.00 80
33,347.00
33,347.00
pekerjaan atap.
Analisa Harga Satuan Pekerjaan Rangka Atap Baja Ringan
Diposkan : 21 Junii 2014
Oleh : Endang Kusman

Untuk analisa harga satuan pekerjaan rangka atap baja ringan saya belum menemukannya di AH

No. URAIAN SATUAN

1 m2 Pek. Pasangan Baja Ringan (Bersertifikat dan bergaransi 10 tahun)


Mobilisasi Ls
Main truss C-75-75 m'
Roof Bottom/Reng R 33-0.45 m'
Self drilling screw dia 6 x 20 mm (truss Screw) bh
Self drilling screw dia 4 x 16 mm (Roof Bottom Screw) bh
Dynabol dia 12 x 120 mm bh
Tukang oh
Tukang Besi Profil Oh
Kepala Tukang Besi Profil Oh
Alat Bantu (Mesin Bor Listrik)/Genset Ls
Gambar Desain m2
Total
Keuntungan Max 10%
Total Harga
Dibulatkan
ap Baja Ringan

elum menemukannya di AHS-SNI, tapi ini saya menemukan di salah satu blog yang sepertinya memiliki hubungan d

VOLUME (Rp) SATUAN (Rp) HARGA

10 tahun)
1 9,000.00 9,000.00
2.8 14,870.00 41,636.00
5.1 8,500.00 43,350.00
25 375 9,375.00
35 350 12,250.00
1 1,500.00 1,500.00
0.247 45,000.00 11,115.00
0.176 50,000.00 8,800.00
0.117 52,500.00 6,142.50
1 4,500.00 4,500.00
1 2,340.00 2,340.00
150,008.50
15,000.85
165,009.35
165,000.00
inya memiliki hubungan dengan salah satu produsen baja ringan, inilah analisanya:
Analisa Harga Satuan Pekerjaan Penutup Besi dan Aluminium
Analisa Harga Satuan Pekerjaan Penutup Besi dan Aluminium
Diposkan : 01 Juni 2014
Oleh : Endang Kusman

No. URAIAN SAT VOLUMEARGA SAT


(Rp)
K-01 1 Kg Besi profil
- Besi profil WF Kg 1.1 24,000.00
- Meni besi Kg 0.08 30,400.00
- Pekerja Oh 0.06 42,000.00
- Tukang besi Oh 0.006 65,000.00
- Kepala tukang Oh 0.006 75,000.00
- Mandor Oh 0.0003 80,000.00
Jumlah
Dibulatkan
K-02 1 Kg Perakitan baja
- Solar m' 0.01 7,150.00
- Minyak pelumas m' 0.001 55,000.00
- Sewa alat jam 0.008 ###
- Pekerja Oh 0.001 42,000.00
- Tukang besi Oh 0.00001 65,000.00
- Kepala tukang Oh 0.00001 75,000.00
- Mandor Oh 0.00005 80,000.00
Jumlah
Dibulatkan

K-03 1 Cm Pengelasan dengan las listrik


- kawat las kg 0.04 23,600.00
- Solar ltr 0.03 7,150.00
- Minyak pelumas ltr 0.004 55,000.00
- Sewa alat jam 0.017 ###
- Pekerja org 0.004 42,000.00
- Tukang org 0.002 65,000.00
- Kepala Tukang org 0.0002 75,000.00
- Mandor org 0.0002 80,000.00
Jumlah
Dibulatkan

K-04 1 m2 Pintu Rolling Door


- Rolling door M2 1 ###
- Pekerja Oh 1.05 42,000.00
- Tukang besi Oh 1.5 65,000.00
- Kepala tukang Oh 0.105 75,000.00
- Mandor Oh 0.0052 80,000.00
Jumlah
Dibulatkan

K-05 1 m2 Pintu Alluminium Natural


- Pintu alluminium natural m2 1 ###
- Pekerja Oh 1.05 42,000.00
- Tukang besi Oh 1.05 65,000.00
- Kepala tukang Oh 0.105 75,000.00
- Mandor Oh 0.0052 80,000.00
Jumlah
Dibulatkan
K-06 1 m2 Terali Besi
- Besi strip 2 x 3 m' 11.5 5,500.00
- Pekerja Oh 1.2 42,000.00
- Tukang las Oh 1.2 65,000.00
- Kepala tukang Oh 0.012 75,000.00
- Mandor Oh 0.0006 80,000.00
Jumlah
Dibulatkan

K-07 1 m2 Kawat Harmonika 4 cm


- Kawat harmonika M2 1.1 35,900.00
- Paku biasa ½" - 1" kg 0.02 23,800.00
- Papan kayu kamper M2 0.0018 ###
- Pekerja Oh 0.1 42,000.00
- Tukang kayu Oh 0.1 65,000.00
- Kepala tukang Oh 0.01 75,000.00
- Mandor Oh 0.005 80,000.00
Jumlah
Dibulatkan

K-08 1 m' Talang Datar, Seng BJLS 28 lebar 90 cm


- Seng plat 3' x 6' BJLS 30 m' 1.05 20,801.00
- Paku biasa ½" - 1" Kg 0.015 23,800.00
- Kayu papan borneo super M3 0.0096 ###
- Flincote / meni besi Kg 0.25 30,400.00
- Pekerja Oh 0.15 42,000.00
- Tukang kayu Oh 0.4 65,000.00
- Kepala tukang Oh 0.025 75,000.00
- Mandor Oh 0.0013 80,000.00
Jumlah
Dibulatkan

K-09 1 m' Talang Miring, Seng BJLS 28 lebar 90 cm


- Seng plat 3' x 6' BJLS 30 m' 1.05 20,801.00
- Paku biasa ½" - 1" Kg 0.015 23,800.00
- Kayu papan borneo super M3 0.019 ###
- Flincote / meni besi Kg 0.3 30,400.00
- Pekerja Oh 0.2 42,000.00
- Tukang kayu Oh 0.4 65,000.00
- Kepala tukang Oh 0.025 75,000.00
- Mandor Oh 0.0013 80,000.00
Jumlah
Dibulatkan
K-10 1 m' Talang 1/2 lingkaran D-15 cm, seng pelat BJLS 28
- Seng plat 3' x 6' BJLS 30 m' 1.05 20,801.00
- Paku biasa ½" - 1" Kg 0.1 23,800.00
- Kayu papan borneo super kg 0.019 ###
- Besi strip Kg 0.5 26,800.00
- Pekerja Oh 0.15 42,000.00
- Tukang kayu Oh 0.3 65,000.00
- Kepala tukang Oh 0.03 75,000.00
- Mandor Oh 0.008 80,000.00
Jumlah
Dibulatkan

K-11 1 m' Pasang kusen pintu/jendela alluminium natural 4"


- Alumunium profil natural 4" m' 1.1 ###
- Skrup fixer bh 2 250
- Sealant m' 1 7,500.00
- Pekerja Oh 0.043 42,000.00
- Tukang kayu Oh 0.043 65,000.00
- Kepala tukang Oh 0.0043 75,000.00
- Mandor Oh 0.0021 80,000.00
Jumlah
Dibulatkan

K-12 1 m' Pasang kusen pintu/jendela alluminium warna 4"


- Alumunium profil warna 4" m' 1.1 ###
- Skrup fixer bh 2 250
- Sealant m' 1 7,500.00
- Pekerja Oh 0.043 42,000.00
- Tukang kayu Oh 0.043 65,000.00
- Kepala tukang Oh 0.0043 75,000.00
- Mandor Oh 0.0021 80,000.00
Jumlah
Dibulatkan

K-13 1 m' Pasang kusen pintu/jendela alluminium natural 3"


- Alumunium profil natural 3" m' 1.1 81,000.00
- Skrup fixer bh 2 250
- Sealant m' 1 7,500.00
- Pekerja Oh 0.043 42,000.00
- Tukang kayu Oh 0.043 65,000.00
- Kepala tukang Oh 0.0043 75,000.00
- Mandor Oh 0.0021 80,000.00
Jumlah
Dibulatkan

K-14 1 m' Pasang kusen pintu/jendela alluminium warna 3"


- Alumunium profil warna 3" m' 1.1 ###
- Skrup fixer bh 2 250
- Sealant m' 1 7,500.00
- Pekerja Oh 0.043 42,000.00
- Tukang kayu Oh 0.043 65,000.00
- Kepala tukang Oh 0.0043 75,000.00
- Mandor Oh 0.0021 80,000.00
Jumlah
Dibulatkan

K-15 1 m2 Pintu alluminium strip lebar 8 cm


- Alumunium profil 4" natural m' 4.4 ###
- Alumunium strip 6mm m2 1.05 ###
- Pekerja Oh 0.085 42,000.00
- Tukang kayu Oh 0.085 65,000.00
- Kepala tukang Oh 0.0085 75,000.00
- Mandor Oh 0.0042 80,000.00
Jumlah
Dibulatkan

K-16 1 m2 Pintu/jendela kaca rangka alluminium natural 4"


- Alumunium profil natural 4" m' 4.4 ###
- Profil alluminium T m' 4.5 12,200.00
- Sealant tube 0.27 7,500.00
- Pekerja Oh 0.085 42,000.00
- Tukang kayu Oh 0.085 65,000.00
- Kepala tukang Oh 0.0085 75,000.00
- Mandor Oh 0.005 80,000.00
Jumlah
Dibulatkan

K-17 1 m2 Pintu/jendela kaca rangka alluminium warna 4"


- Alumunium profil warna 4" m' 4.4 ###
- Profil alluminium T m' 4.5 12,200.00
- Sealant tube 0.27 7,500.00
- Pekerja Oh 0.085 42,000.00
- Tukang kayu Oh 0.085 65,000.00
- Kepala tukang Oh 0.0085 75,000.00
- Mandor Oh 0.005 80,000.00
Jumlah
Dibulatkan

K-18 1 m2 Jendela nako & teralis (10 klips)


- Jendela nako (rangka + kaca 5 mm m2 1.1 ###
- Paku skrup 1cm - 2,5cm bh 10 250
- Besi strip m' 7 5,500.00
- Pekerja Oh 0.2 42,000.00
- Tukang kayu Oh 0.2 65,000.00
- Kepala tukang Oh 0.02 75,000.00
- Mandor Oh 0.001 80,000.00
Jumlah
Dibulatkan

K-19 1 m2 Pintu pelat baja tebal 2mm rangkap, rangka baja siku
- Besi siku L 30.30.3 Kg 15 24,000.00
- Baja pelat Kg 32.8 24,000.00
- kawat las Kg 0.05 23,600.00
- Pekerja Oh 0.2 42,000.00
- Tukang kayu Oh 0.2 65,000.00
- Kepala tukang Oh 0.02 75,000.00
- Mandor Oh 0.001 80,000.00
Jumlah
Dibulatkan

K-20 1 m2 Rangka jendela besi square tube (5 x 5) cm


- Besi square tube M 4.76 7,300.00
- Besi lis kaca (1 x 1) cm Kg 4.522 24,000.00
- Pengelasan Cm 20 2,464.00
- Pekerja Oh 0.65 42,000.00
- Tukang kayu Oh 0.65 65,000.00
- Kepala tukang Oh 0.065 75,000.00
- Mandor Oh 0.032 80,000.00
Jumlah
Dibulatkan

K-21 1 m2 Pintu lipat (folding door) bahan besi


- Pintu lipat M2 1 ###
- Pekerja Oh 1.05 42,000.00
- Tukang kayu Oh 1.05 65,000.00
- Kepala tukang Oh 0.105 75,000.00
- Mandor Oh 0.0052 80,000.00
Jumlah
Dibulatkan

K-22 1 m2 Tirai (venetions blinds and vertical blinds)


- Tirai M2 1 ###
- Pekerja Oh 0.35 42,000.00
- Tukang kayu Oh 0.35 65,000.00
- Kepala tukang Oh 0.035 75,000.00
- Mandor Oh 0.0018 80,000.00
Jumlah
Dibulatkan
si dan Aluminium
dan Aluminium

HARGA
(Rp)

26,400.00
2,432.00
2,520.00
390
450
24
32,216.00
32,216.00

71.5
55
800
42
0.65
0.75
4
973.9
974

944
214.5
220
1,700.00
168
130
15
16
2,463.50
2,464.00

306,600.00
44,100.00
97,500.00
7,875.00
416
456,491.00
456,491.00

211,800.00
44,100.00
68,250.00
7,875.00
416
332,441.00
332,441.00

63,250.00
50,400.00
78,000.00
900
48
192,598.00
192,598.00

39,490.00
476
10,246.68
4,200.00
6,500.00
750
400
62,062.68
62,063.00

21,841.05
357
53,719.68
7,600.00
6,300.00
26,000.00
1,875.00
104
117,796.73
117,797.00

21,841.05
357
106,320.20
9,120.00
8,400.00
26,000.00
1,875.00
100
174,013.25
174,013.00
21,841.05
2,380.00
106,320.20
13,400.00
6,300.00
19,500.00
2,250.00
640
172,631.25
172,631.00

166,210.00
500
7,500.00
1,806.00
2,795.00
322.5
168
179,301.50
179,302.00

179,300.00
500
7,500.00
1,806.00
2,795.00
322.5
168
192,391.50
192,392.00

89,100.00
500
7,500.00
1,806.00
2,795.00
322.5
168
102,191.50
102,192.00
112,200.00
500
7,500.00
1,806.00
2,795.00
322.5
168
125,291.50
125,292.00

664,840.00
180,390.00
3,570.00
5,525.00
637.5
336
855,298.50
855,299.00

664,840.00
54,900.00
2,025.00
3,570.00
5,525.00
637.5
400
731,897.50
731,898.00

717,200.00
54,900.00
2,025.00
3,570.00
5,525.00
637.5
400
784,257.50
784,258.00

330,000.00
2,500.00
38,500.00
8,400.00
13,000.00
1,500.00
80
393,980.00
393,980.00

360,000.00
787,200.00
1,180.00
8,400.00
13,000.00
1,500.00
80
1,171,360.00
1,171,360.00

34,748.00
108,528.00
49,280.00
27,300.00
42,250.00
4,875.00
2,560.00
269,541.00
269,541.00

501,700.00
44,100.00
68,250.00
7,875.00
416
622,341.00
622,341.00

537,300.00
14,700.00
22,750.00
2,625.00
144
577,519.00
577,519.00
Analisa Harga Satuan Pekerjaan Pengecatan
Diposkan : 05 Juni 2014
Oleh : Endang Kusman

No. URAIAN SAT VOLUMEARGA SAT HARGA

N-01 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama


- Soda api Kg 0.05 35,600.00 1,780.00
- Pekerja Oh 0.15 42,000.00 6,300.00
- Mandor Oh 0.0025 80,000.00 200
Jumlah 8,280.00
Dibulatkan 8,280.00
N-02 1 M2 Mendempul Dan Menggosok Kayu
- Dempul Kg 0.08 35,800.00 2,864.00
- Minyak cat Kg 0.02 38,400.00 768
- Batu apung Kg 0.01 29,600.00 296
- Pekerja Oh 0.04 42,000.00 1,680.00
- Tukang cat Oh 0.04 65,000.00 2,600.00
- Kepala tukang Oh 0.004 75,000.00 300
- Mandor Oh 0.0025 80,000.00 200
Jumlah 8,708.00
Dibulatkan 8,708.00
N-03 1 M2 Pengecatan Bidang Kayu Lama Setara Sieve
- Plamir Kg 0.15 25,000.00 3,750.00
- Cat dasar Kg 0.17 30,000.00 5,100.00
- Cat penutup setara sieve Kg 0.17 41,700.00 7,089.00
- Pekerja Oh 0.07 42,000.00 2,940.00
- Tukang cat Oh 0.075 65,000.00 4,875.00
- Kepala tukang Oh 0.0075 75,000.00 562.5
- Mandor Oh 0.0025 80,000.00 200
Jumlah 24,516.50
Dibulatkan 24,517.00
N-04 1 M2 Pengecatan Bidang Kayu Baru Setara Sieve
- Cat meni Kg 0.2 30,400.00 6,080.00
- Plamir Kg 0.15 25,000.00 3,750.00
- Cat dasar Kg 0.17 30,000.00 5,100.00
- Cat penutup 3x setara sie Kg 0.35 41,700.00 14,595.00
- Pekerja Oh 0.07 42,000.00 2,940.00
- Tukang cat Oh 0.105 65,000.00 6,825.00
- Kepala tukang Oh 0.004 75,000.00 300
- Mandor Oh 0.0025 80,000.00 200
Jumlah 39,790.00
Dibulatkan 39,790.00

N-05 1 M2 Pelaburan Bidang Kayu dengan Politur


- Politur Ltr 0.15 48,000.00 7,200.00
- Politur jadi Ltr 0.372 ### 41,924.40
- Ampelas Lbr 2 5,000.00 10,000.00
- Tukang cat Oh 0.06 65,000.00 3,900.00
- Kepala tukang Oh 0.016 75,000.00 1,200.00
- Mandor Oh 0.0025 80,000.00 200
Jumlah 64,424.40
Dibulatkan 64,424.00
N-06 1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter
- Residu atau ter Ltr 0.35 8,100.00 2,835.00
- Pekerja Oh 0.1 42,000.00 4,200.00
- Mandor Oh 0.006 80,000.00 480
Jumlah 7,515.00
Dibulatkan 7,515.00

N-07 1 M2 Pengecatan Tembok Baru Setara ICI


- Plamir tembok Kg 0.1 25,000.00 2,500.00
- Cat dasar Kg 0.1 30,000.00 3,000.00
- Cat penutup 2x setara ICI Kg 0.26 75,000.00 19,500.00
- Pekerja Oh 0.02 42,000.00 840
- Tukang cat Oh 0.063 65,000.00 4,095.00
- Kepala tukang Oh 0.0063 75,000.00 472.5
- Mandor Oh 0.0025 80,000.00 200
Jumlah 30,607.50
Dibulatkan 30,608.00
N-08 1 M2 Pengecatan Tembok Lama Setara ICI
- Cat dasar Kg 0.12 30,000.00 3,600.00
- Cat penutup 2 x Kg 0.18 75,000.00 13,500.00
- Pekerja Oh 0.028 42,000.00 1,176.00
- Tukang cat Oh 0.042 65,000.00 2,730.00
- Kepala tukang Oh 0.0042 75,000.00 315
- Mandor Oh 0.0025 80,000.00 200
Jumlah 21,521.00
Dibulatkan 21,521.00
N-09 1 M2 Pengecatan Plafond ( 3x ) Setara ICI
- Cat tembok setara ICI Kg 0.2 75,000.00 15,000.00
- Plamir tembok Kg 0.16 25,000.00 4,000.00
- Rol cat Bh 0.01 32,500.00 325
- Steger werk Ls 1 1,000.00 1,000.00
- Ampelas Lbr 0.5 5,000.00 2,500.00
- Pekerja Oh 0.2 42,000.00 8,400.00
- Tukang cat Oh 0.3 65,000.00 19,500.00
- Kepala tukang Oh 0.03 75,000.00 2,250.00
- Mandor Oh 0.01 80,000.00 800
Jumlah 53,775.00
Dibulatkan 53,775.00
N-10 1 M2 Pengecatan Plafond ( 3x ) Setara Vinilex
- Cat tembok setara Vinilex Kg 0.2 25,000.00 5,000.00
- Plamir tembok Kg 0.16 25,000.00 4,000.00
- Rol cat Bh 0.01 32,500.00 325
- Steger werk Ls 1 1,000.00 1,000.00
- Ampelas Lbr 0.5 5,000.00 2,500.00
- Pekerja Oh 0.2 42,000.00 8,400.00
- Tukang cat Oh 0.3 65,000.00 19,500.00
- Kepala tukang Oh 0.03 75,000.00 2,250.00
- Mandor Oh 0.01 80,000.00 800
Jumlah 43,775.00
Dibulatkan 43,775.00
N-10-r' 1 M2 Pengecatan Plafond ( 2x ) Setara Vinilex
- Cat tembok setara Vinilex Kg 0.13 25,000.00 3,250.00
- Plamir tembok Kg 0.11 25,000.00 2,750.00
- Rol cat Bh 0.1 32,500.00 3,250.00
- Steger werk Ls 0.67 1,000.00 670
- Ampelas Lbr 0.33 5,000.00 1,650.00
- Pekerja Oh 0.13 42,000.00 5,460.00
- Tukang cat Oh 0.2 65,000.00 13,000.00
- Kepala tukang Oh 0.02 75,000.00 1,500.00
- Mandor Oh 0.01 80,000.00 800
Jumlah 32,330.00
Dibulatkan 32,330.00
N-11 1 M2 Memasang Wallpaper
- Wallpaper m2 1.2 55,700.00 66,840.00
- Lem Perekat Kg 0.25 35,700.00 8,925.00
- Pekerja Oh 0.35 42,000.00 14,700.00
- Tukang cat Oh 0.175 65,000.00 11,375.00
- Kepala tukang Oh 0.017 75,000.00 1,275.00
- Mandor Oh 0.0017 80,000.00 136
Jumlah 103,251.00
Dibulatkan 103,251.00
N-12 1 M2 Pengecatan Permukaan Baja dengan Meni Besi
- Meni besi Kg 0.1 30,400.00 3,040.00
- Kuas 3" Bh 0.01 16,000.00 160
- Pekerja Oh 0.02 42,000.00 840
- Tukang cat Oh 0.2 65,000.00 13,000.00
- Kepala tukang Oh 0.02 75,000.00 1,500.00
- Mandor Oh 0.01 80,000.00 800
Jumlah 19,340.00
Dibulatkan 19,340.00

N-13 1 M2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah


- Meni besi Kg 0.1 30,400.00 3,040.00
- Kuas 3" Bh 0.01 16,000.00 160
- Kayu perancah m3 0.002 ### 4,139.60
- Pekerja Oh 0.25 42,000.00 10,500.00
- Tukang cat Oh 0.225 65,000.00 14,625.00
- Kepala tukang Oh 0.0225 75,000.00 1,687.50
- Mandor Oh 0.0075 80,000.00 600
Jumlah 34,752.10
Dibulatkan 34,752.00

N-14 1 M2 Pengecatan Permukaan Baja Lapis seng (galbani) secara manual 1 lps cat 2 um
- Cat besi setara ICI Kg 0.3 67,700.00 20,310.00
- Pekerja Oh 0.006 42,000.00 252
- Tukang cat Oh 0.06 65,000.00 3,900.00
- Kepala tukang Oh 0.012 75,000.00 900
- Mandor Oh 0.006 80,000.00 480
Jumlah 25,842.00
Dibulatkan 25,842.00
N-15 1 M2 Pengecatan Tembok Baru Setara Vinilex (2 x laburan)
- Plamir tembok Kg 0.1 25,000.00 2,500.00
- Cat dasar Kg 0.1 30,000.00 3,000.00
- Cat penutup 2x setara vini Kg 0.26 25,000.00 6,500.00
- Pekerja Oh 0.02 42,000.00 840
- Tukang cat Oh 0.063 65,000.00 4,095.00
- Kepala tukang Oh 0.0063 75,000.00 472.5
- Mandor Oh 0.0025 80,000.00 200
Jumlah 17,607.50
Dibulatkan 17,608.00
N-15r' 1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x laburan)
- Plamir tembok Kg 0.1 25,000.00 2,500.00
- Cat dasar Kg 0.1 30,000.00 3,000.00
- Cat penutup 3x setara vini Kg 0.39 25,000.00 9,750.00
- Pekerja Oh 0.03 42,000.00 1,260.00
- Tukang cat Oh 0.0945 65,000.00 6,142.50
- Kepala tukang Oh 0.0095 75,000.00 712.5
- Mandor Oh 0.0038 80,000.00 304
Jumlah 23,669.00
Dibulatkan 23,669.00
N-16 1 M2 Pengecatan Tembok Lama Setara Vinilex
- Cat dasar Kg 0.12 30,000.00 3,600.00
- Cat penutup 2 x Kg 0.18 25,000.00 4,500.00
- Pekerja Oh 0.028 42,000.00 1,176.00
- Tukang cat Oh 0.042 65,000.00 2,730.00
- Kepala tukang Oh 0.0042 75,000.00 315
- Mandor Oh 0.0025 80,000.00 200
Jumlah 12,521.00
Dibulatkan 12,521.00
Analisa Harga Satuan Pekerjaan Sanitasi
Diposkan : 04 Juni 2014
Oleh : Endang Kusman

No. URAIAN SAT VOLUMEARGA SAT


(Rp)
M-01 1 Buah Closet jongkok Porselen Standar
Closet jongkok bh 1 ###
P.C (50 gk) Kg 6 1,406.00
Pasir pasang m3 0.01 ###
Pekerja org 1 42,000.00
Tukang batu org 1.5 65,000.00
Kepala Tukang org 1.5 75,000.00
Mandor org 0.16 80,000.00
Jumlah
Dibulatkan
M-02 1 Buah Urinoir
Urinoir bh 1 ###
P.C (50 gk) Kg 6 1,406.00
Pasir pasang m3 0.01 ###
Pekerja org 1 42,000.00
Tukang batu org 1 65,000.00
Kepala Tukang org 0.1 75,000.00
Mandor org 0.001 80,000.00
Perlengkapan 30 % harga urinoir lot 0.3 ###
Jumlah
Dibulatkan
M-03 1 Buah Wastafel
wastafel standar unit 1 ###
P.C (50 gk) Kg 6 1,406.00
Pasir pasang m3 0.01 ###
Pekerja org 1.2 42,000.00
Tukang batu org 1.45 65,000.00
Kepala Tukang org 0.15 75,000.00
Mandor org 0.1 80,000.00
Perlengkapan 12 % harga wastafel lot 0.12 ###
Jumlah
Dibulatkan
M-04 1 Buah bak Mandi Fibreglass Volume 0,30 m3
Bak fibreglass 0.60m x 0.60m bh 1 ###
Pekerja org 1.8 42,000.00
Tukang batu org 2.7 65,000.00
Kepala Tukang org 0.54 75,000.00
Mandor org 0.11 80,000.00
Perlengkapan 18 % harga bak lot 0.18 ###
Jumlah
Dibulatkan
M-05 1 M' Saluran Air Limbah Buis beton d = 30 cm - 60 cm
Buis beton Ø 30 cm bh 1.1 61,700.00
Bata merah bh 25 775
P.C (50 gk) Kg 10.3 1,406.00
Pasir pasang m3 0.061 ###
Pasir urug m3 0.069 ###
Pekerja org 0.38 42,000.00
Tukang batu org 0.19 65,000.00
Kepala Tukang org 0.019 75,000.00
Mandor org 0.019 80,000.00
Jumlah
Dibulatkan
M-06 1 Buah Bak Kontrol Pas Bata Merah Uk (60 x 60) cm
Bata merah bh 186 775
P.C (50 gk) Kg 114 1,406.00
Pasir pasang m3 0.184 ###
Batu pecah 2/3 m3 0.033 ###
Besi beton m3 4.85 16,500.00
Pasir beton m3 0.12 ###
Pekerja org 2.16 42,000.00
Tukang batu org 0.72 65,000.00
Kepala Tukang org 0.072 75,000.00
Mandor org 0.108 80,000.00
Tukang gali org 0.1 42,000.00
Jumlah
Dibulatkan
M-07 1 Buah Bak Kontrol Pas Bata Merah Uk (30 x 30) cm
Bata merah bh 53 775
P.C (50 gk) Kg 44 1,406.00
Pasir pasang m3 0.07 ###
Batu pecah 2/3 m3 0.07 ###
Besi beton m3 1.6 16,500.00
Pasir beton m3 0.06 ###
Pekerja org 3.2 42,000.00
Tukang batu org 1.015 65,000.00
Kepala Tukang org 0.0015 75,000.00
Mandor org 0.016 80,000.00
Jumlah
Dibulatkan
M-08 1 M' Pipa PVC Ø 1/2" (AW)
Pipa pvc Ø 1/2" m' 1.2 10,025.00
Pekerja org 0.036 42,000.00
Tukang batu org 0.06 65,000.00
Kepala Tukang org 0.006 75,000.00
Mandor org 0.0018 80,000.00
Perlengkapan 35 % harga pipa lot 0.35 12,030.00
Jumlah
Dibulatkan
M-09 1 M' Pipa PVC Ø 1" (AW)
Pipa pvc Ø 1" m' 1.2 15,800.00
Pekerja org 0.036 42,000.00
Tukang batu org 0.06 65,000.00
Kepala Tukang org 0.006 75,000.00
Mandor org 0.0018 80,000.00
Perlengkapan 35 % harga pipa lot 0.35 18,960.00
Jumlah
Dibulatkan
M-10 1 M' Pipa PVC Ø 11/2" (AW)
Pipa pvc Ø 11/2" m' 1.2 26,475.00
Pekerja org 0.036 42,000.00
Tukang batu org 0.06 65,000.00
Kepala Tukang org 0.006 75,000.00
Mandor org 0.0018 80,000.00
Perlengkapan 35 % harga pipa lot 0.35 31,770.00
Jumlah
Dibulatkan
M-11 1 M' Pipa PVC Ø 2" (AW)
Pipa pvc Ø 2" m' 1.2 27,675.00
Pekerja org 0.036 42,000.00
Tukang batu org 0.06 65,000.00
Kepala Tukang org 0.006 75,000.00
Mandor org 0.0018 80,000.00
Perlengkapan 35 % harga pipa lot 0.35 31,770.00
Jumlah
Dibulatkan
M-12 1 M' Pipa PVC Ø 4" (AW)
Pipa pvc Ø 4" m' 1.2 86,975.00
Pekerja org 0.081 42,000.00
Tukang batu org 0.135 65,000.00
Kepala Tukang org 0.0135 75,000.00
Mandor org 0.0041 80,000.00
Perlengkapan 35 % harga pipa lot 0.35 ###
Jumlah
Dibulatkan
M-13 1 M' Pipa PVC Ø 3/4" (AW)
Pipa pvc Ø 3/4" m' 1.2 13,050.00
Pekerja org 0.081 42,000.00
Tukang batu org 0.135 65,000.00
Kepala Tukang org 0.0135 75,000.00
Mandor org 0.0041 80,000.00
Perlengkapan 35 % harga pipa lot 0.35 15,660.00
Jumlah
Dibulatkan
M-14 1 Buah Bak Cuci piring Stainless steel
Bak cuci stainless steel + asesoris lengkap bh 1 ###
Pekerja org 0.03 42,000.00
Tukang batu org 0.3 65,000.00
Kepala Tukang org 0.03 75,000.00
Mandor org 0.0015 80,000.00
Jumlah
Dibulatkan
M-15 1 Buah Kran Ø 1/2" - 3/4"
Kran air bh 1 40,900.00
Seal tape bh 0.025 4,200.00
Pekerja org 0.01 42,000.00
Tukang batu org 0.1 65,000.00
Kepala Tukang org 0.01 75,000.00
Mandor org 0.005 80,000.00
Jumlah
Dibulatkan
M-16 1 Buah Floor Drain
Floor drain bh 1 66,600.00
Pekerja org 0.01 42,000.00
Tukang batu org 0.1 65,000.00
Kepala Tukang org 0.01 75,000.00
Mandor org 0.005 80,000.00
Jumlah
Dibulatkan

M-17 1 M' Grafel beton U 20 cm -60 cm


Pipa beton U bh 1.1 44,300.00
Bata merah bh 12 775
P.C (50 gk) zak 0.103 1,406.00
Pasir pasang m3 0.0305 ###
Pasir urug m3 0.0345 ###
Pekerja org 0.01 42,000.00
Tukang batu org 0.1 65,000.00
Kepala Tukang org 0.01 75,000.00
Mandor org 0.005 80,000.00
Jumlah
Dibulatkan
M-18 1 M' Pasang Talang Plastik PVC U 15 cm (AW)
Talang plastik PVC m' 1.05 60,000.00
Perlengkapan 35 % harga talang lot 0.35 63,000.00
Pekerja org 0.15 42,000.00
Tukang batu org 0.4 65,000.00
Kepala Tukang org 0.025 75,000.00
Mandor org 0.0013 80,000.00
Jumlah
Dibulatkan

M-19 1 M' Saluran Air Limbah Buis Beton Ø 60 cm


Buis beton Ø 60 cm bh 1.1 ###
Bata merah bh 25 775
P.C (50 gk) zak 0.206 1,406.00
Pasir pasang m3 0.061 ###
Pasir urug m3 0.069 ###
Pekerja org 0.38 42,000.00
Tukang batu org 0.19 65,000.00
Kepala Tukang org 0.019 75,000.00
Mandor org 0.019 80,000.00
Jumlah
Dibulatkan
M-20 1 M' Pasang Talang Seng Datar
Seng pelat 3" x 6" lbr 0.5 20,801.00
Paku kg 0.015 23,400.00
Kayu kelas II m3 0.0096 ###
Meni besi kg 0.25 30,400.00
Pekerja org 0.15 42,000.00
Tukang batu org 0.4 65,000.00
Kepala Tukang org 0.025 75,000.00
Mandor org 0.0013 80,000.00
Jumlah
Dibulatkan
M-21 1 Buah Closet Duduk
Closet duduk bh 1 ###
Pekerja org 3.3 42,000.00
Tukang batu org 1.1 65,000.00
Kepala Tukang org 0.001 75,000.00
Mandor org 0.16 80,000.00
Perlengkapan 6 % harga closet lot 0.06 ###
Jumlah
Dibulatkan
M-22 1 Buah Tangki Air fibreglass Volume 1 m3
Bak fibreglass kapasitas 1 m3 bh 1 ###
Pekerja org 3.3 42,000.00
Tukang batu org 1.1 65,000.00
Kepala Tukang org 0.001 75,000.00
Mandor org 0.16 80,000.00
Perlengkapan 6 % harga bak lot 0.06 ###
Jumlah
Dibulatkan
M-23 1 Unit Septictank 2x1,50x1,50 m + Rembesan
Galian tanah m3 4.5 26,252.00
Pasir urug m3 0.214 ###
lantai kerja m3 2.25 ###
Pas bata adk 1pc : 3ps m2 15 ###
Pelat beton K-225 m3 0.3 ###
Plesteran adk 1pc : 3ps m2 15 41,301.82
Pipa PVC 4" jenis AW m' 5.4 ###
Pipa GIP 1 1/2" m' 5 46,750.00
Galian tanah untuk rembesan m3 3.375 20,000.00
Pas ijuk kg 5.4 23,400.00
Urugan kerikil 3/5 m3 1.05 ###
Pipa PVC 4" berlubang jenis AW m' 9 36,700.00
Urugan dan perataan tanah m3 1.125 34,584.00
Jumlah
Dibulatkan
M-24 1 Unit Septictank 1x1,50x1,50 m + Rembesan
Galian tanah m3 2.25 20,000.00
Pasir urug m3 0.107 ###
lantai kerja m3 1.125 ###
Pas bata adk 1pc : 3ps m2 7.5 ###
Pelat beton K-225 m3 0.15 ###
Plesteran adk 1pc : 3ps m2 7.5 41,301.82
Pipa PVC 4" jenis AW m' 9 ###
Pipa GIP 1 1/2" m' 2.5 46,750.00
Galian tanah untuk rembesan m3 1.688 20,000.00
Pas ijuk kg 2.7 23,400.00
Urugan kerikil 3/5 m3 0.525 ###
Pipa PVC 4" berlubang jenis AW m' 9 36,700.00
Urugan dan perataan tanah m3 0.563 34,584.00
Jumlah
Dibulatkan
HARGA
(Rp)

###
8,436.00
2,334.00
42,000.00
97,500.00
###
12,800.00
###
###

###
8,436.00
2,334.00
42,000.00
65,000.00
7,500.00
80
###
###
###

###
8,436.00
2,334.00
50,400.00
94,250.00
11,250.00
8,000.00
###
###
###

###
75,600.00
###
40,500.00
8,800.00
45,954.00
###
###

67,870.00
19,375.00
14,481.80
14,237.40
12,095.70
15,960.00
12,350.00
1,425.00
1,520.00
###
###

###
###
42,945.60
6,966.30
80,025.00
30,648.00
90,720.00
46,800.00
5,400.00
8,640.00
4,200.00
###
###

41,075.00
61,864.00
16,338.00
14,777.00
26,400.00
15,324.00
###
65,975.00
112.5
1,280.00
###
###

12,030.00
1,512.00
3,900.00
450
144
4,210.50
22,246.50
22,247.00

18,960.00
1,512.00
3,900.00
450
144
6,636.00
31,602.00
31,602.00
31,770.00
1,512.00
3,900.00
450
144
11,119.50
48,895.50
48,896.00

33,210.00
1,512.00
3,900.00
450
144
11,119.50
50,335.50
50,336.00

###
3,402.00
8,775.00
1,012.50
328
36,529.50
###
###

15,660.00
3,402.00
8,775.00
1,012.50
328
5,481.00
34,658.50
34,659.00

###
1,260.00
19,500.00
2,250.00
120
###
###

40,900.00
105
420
6,500.00
750
400
49,075.00
49,075.00
66,600.00
420
6,500.00
750
400
74,670.00
74,670.00

48,730.00
9,300.00
144.82
7,118.70
6,047.85
420
6,500.00
750
400
79,411.37
79,411.00

63,000.00
22,050.00
6,300.00
26,000.00
1,875.00
100
###
###

###
19,375.00
289.64
14,237.40
12,095.70
15,960.00
12,350.00
1,425.00
1,520.00
###
###

10,400.50
351
27,360.00
7,600.00
6,300.00
26,000.00
1,875.00
100
79,986.50
79,987.00

###
###
71,500.00
75
12,800.00
###
###
###

###
###
71,500.00
75
12,800.00
78,984.00
###
###

###
37,514.20
###
###
###
###
###
###
67,500.00
###
###
###
38,907.00
###
###

45,000.00
18,757.10
###
###
###
###
###
###
33,760.00
63,180.00
###
###
19,470.79
###
###
Analisa Harga Satuan Pekerjaan Penanaman Pohon
Diposkan : o6 Juni2014
Oleh : Endang Kusman

NO. URAIAN KOEF SAT. SAT. (Rp) RGA (Rp)


O-01 1 Lubang (70x70x70) cm, tanam pohon pelindung tinggi 2m
Pupuk kandang 0.08 krg 25,000.00 2,000.00
Furadan 0.001 kg 24,000.00 24
Pohon pelindung 1 btng 25,000.00 25,000.00
Pekerja 0.025 org 42,000.00 1,050.00
Mandor 0.0025 org 80,000.00 200
Jumlah 28,274.00
Dibulatkan 28,274.00
O-02 1 Lubang (70x70x70) cm, tanam bambu krisik/jepang
Pupuk kandang 0.08 krg 25,000.00 2,000.00
Furadan 0.001 kg 24,000.00 24
Bambu krisik/jepang 1 btng 50,000.00 50,000.00
Pekerja 0.025 org 42,000.00 1,050.00
Mandor 0.0025 org 80,000.00 200
Jumlah 53,274.00
Dibulatkan 53,274.00
O-03 1 Lubang (40x40x40) cm, tanam pohon perdu (polibag)
Pupuk kandang 0.04 krg 25,000.00 1,000.00
Furadan 0.001 kg 24,000.00 24
Pohon perdu 1 btng 10,000.00 10,000.00
Pekerja 0.02 org 42,000.00 840
Mandor 0.002 org 80,000.00 160
Jumlah 12,024.00
Dibulatkan 12,024.00
O-04 1 M2 Tanam rumput gajah (silang papan catur)
Pupuk kandang 0.04 krg 25,000.00 1,000.00
Rumput gajah mini 0.5 m2 15,000.00 7,500.00
Pekerja 0.04 org 42,000.00 1,680.00
Mandor 0.004 org 80,000.00 320
Jumlah 10,500.00
Dibulatkan 10,500.00
n Pohon
Harga Satuan Bahan Bangunan - AHS 2011

NO MATERIAL SAT HARGA (Rp)

A. AGREGAT KASAR,BAHAN PEREKAT & BAHAN JADINYA

1 Pasir Urug m3 175,300.00


2 Tanah Urug Pilihan m3 89,200.00
3 Sirtu m3 203,500.00
4 Pasir Teras m3 174,200.00
5 Pasir Pasang Kali m3 233,400.00
6 Pasir Beton m3 255,400.00
7 Abu Batu m3 259,000.00
8 Batu Gosok ( Apung ) kg 29,600.00
9 Batu Pecah Mesin 1/2 m3 223,600.00
10 Batu Pecah Mesin 2/3 m3 211,100.00
11 Batu Pecah Mesin 3/5 m3 205,000.00
12 Batu Pecah Mesin 5/7 m3 196,000.00
13 Batu Belah Pondasi m3 205,500.00
14 Batu Bronjol ( Untuk Bronjong ) m3 180,800.00
15 Batu Koral Beton Kali m3 172,600.00
16 Batu Tempel Hitam m3 96,600.00
17 Batu Pinggir Beton 10 x 20 x 35 bh 14,100.00
18 Batu Pinggir Beton 15 x 35 x 50 ( K-225 bh 73,700.00
19 Batu Telor m3 97,800.00
20 Batako Kecil 8 x 10 x 20 bh 2,000.00
21 Batako Besar 8 x 20 x 30 bh 2,400.00
22 Con Blok 8 x 20 x 40 bh 5,400.00
23 Bata Merah Bakar kelas I bh 775
24 Bata Merah Bakar kelas II bh 675
25 Bata Merah Oven ( Klingker ) bh 1,800.00
26 Roster Beton 20 x 20 bh 14,800.00
27 Roster Beton 30 x 30 bh 15,500.00
28 Grass Blok 20 x 20 bh 9,700.00
29 Grass Blok 30 x 30 bh 22,500.00
30 Paving Blok Natural 8 cm m2 81,100.00
31 Paving Blok Warna 8 cm m2 108,600.00
32 Paving Blok Natural 6 cm m2 76,000.00
33 Paving Blok Warna 6 cm m2 86,000.00
34 Canstin Paving Blok m1 34,900.00
35 Semen PC /50 kg zak 70,300.00
1,406.00
36 Semen Putih zak 92,700.00
37 Kanstin Jalan Ukuran Besar ( Bina Mar bh 58,900.00
38 Readymix Beton K500, Tanpa Pompa ( m3 1,105,000.00
39 Readymix Beton K400, Tanpa Pompa ( m3 903,500.00
40 Readymix Beton K350, Tanpa Pompa ( m3 877,500.00
41 Readymix Beton K300, Tanpa Pompa ( m3 925,000.00
42 Readymix Beton K225, Tanpa Pompa ( m3 850,000.00
43 Readymix Beton K175, Tanpa Pompa ( m3 825,000.00
44 Kapur Pasang / Kapur Tembok m3 353,300.00
45 Kapur Sirih kg 18,300.00
46 Semen Warna kg 15,700.00
47 Tanah liat m3 31,300.00
48 Air ltr 3
49 Formite/spacer bh 2,500.00
50 Hollow/Con Blok 8 x 20 x 40 bh 5,000.00
51 Hollow/Con Blok 8 x 15 x 40 bh 4,000.00
52 Hollow/Con Blok 8 x 10 x 40 bh 3,000.00

B LABURAN,PENGISI DAN ALATNYA


1 Plamir Tembok kg 25,000.00
2 Cat Tembok ICI Eksterior ( Beton ) lt 120,000.00
3 Cat Tembok ICI Interior ( Plafon Dan Din lt 75,000.00
4 Cat Tembok Vinilex kg 25,000.00
5 Cat Dasar ICI untuk Interior ( 2 Pelapis lt 75,000.00
6 Cat Tembok Sanlek kg 20,000.00
7 Cat Dasar kg 30,000.00
8 Cat Tahan Asam lt 40,000.00
9 Pelapis Alkali ICI ( Cat Dasar Beton Ekte kg 90,000.00
10 Cat Marka / Spotlight kg 185,000.00
11 Water Profing Emulsion ml 70,000.00
12 Water Profing Membrance bh 62,500.00
13 Rool Cat Tembok bh 32,500.00
14 Kape Tembok bh 8,500.00
15 Kape Kayu 5 lt 10,000.00
16 Soligneum 1 Blek kg 25,000.00
17 Plincote m3 29,000.00
18 Penawetan Kayu m3 382,600.00
19 Pegopenan Kayu bh 370,000.00
20 Kwas 3" bh 16,000.00
21 Oker bks 22,000.00
22 Oyan bks 5,200.00
23 Oten ( Pewarna Plitur ) lt 5,500.00
24 Spirtus kg 15,000.00
25 Bahan Pelitur Kripik ( Sirlak India ) kg 110,000.00
26 Dempul Lilin kg 34,200.00
27 Dempul Plitur kg 37,700.00
28 Dempul Halus / Imfra ( Wood Filler ) lt 37,700.00
29 Dempul Jadi kg 35,800.00
30 Politur lt 48,000.00
31 Politur Jadi lt 112,700.00
32 Terpentin kg 19,500.00
33 Tiner A kg 23,900.00
34 Tiner B kg 21,400.00
35 Kumpon lbr 30,800.00
36 Melamik kg 52,500.00
37 Dempul Plastik kg 39,200.00
38 Dempul Duco kg 35,800.00
39 Ampelas lbr 5,000.00
40 Dempul Kayu Cap Kucing kg 24,400.00
41 Meni Kayu / Besi kg 30,400.00
42 Sincromat kg 40,900.00
43 Cat Kayu Sieve lt 41,700.00
44 Cat Besi lt 44,000.00
45 Cat Besi Duco Danaglos / ICI bh 76,300.00
46 Cat Bron kg 67,700.00
47 Karet lis bh 3,300.00
48 Minyak cat kg 38,400.00
49 Glass beet kg 50,100.00
50 Residu lt 8,100.00

C BAHAN KAYU BERIKUT BAHAN JADINYA


1 Bambu 5 s.d 7 bt 17,700.00
2 Bambu 7 s.d 10 bt 25,000.00
3 Bambu Gombong bt 37,200.00
4 Kayu Kamper Singkil / Kapur ( Kayu Sama m3 7,094,450.00
5 Kayu Balok Borneo Super m3 5,280,000.00
6 Kayu Papan Borneo Super m3 5,595,800.00
7 Kayu Balok Kamper Medan (Kruing ) m3 5,692,600.00
8 Kayu Papan Kamper Medan (Kruing ) m3 5,823,400.00
9 Kayu Balok Kamper Banjar m3 6,363,600.00
10 Kayu Papan Kamper Banjar m3 6,645,300.00
11 Kayu Balok Kamper Samarinda m3 8,633,700.00
12 Kayu Papan Kamper Samarinda m3 8,724,300.00
13 Kayu Balok Rasamala m3 2,658,000.00
14 Kayu Jati Jatim Tua dia. 40 cm m3 20,772,000.00
15 Kayu Jati Jateng Tua dia. 40 cm m3 22,188,400.00
16 Kayu Jati Jabar Tua dia. 40 cm m3 13,625,400.00
17 Kayu Jati Jabar Tua dia. 40 cm kebawa m3 12,736,100.00
18 Kayu Hutan Kelas I ( Segeng,Mahoni, L m3 2,069,800.00
19 Kayu Balok Albasia m3 1,870,500.00
20 Kayu Papan Albasia m3 2,071,700.00
21 Dolken 5 s/d 7 bt 22,600.00
22 Dolken 7 s/d 10 bt 28,000.00
23 List Profil Kamper 1 cm m1 8,900.00
24 List Profil Kamper 2 cm m1 10,000.00
25 List Profil Kamper 4 cm m1 14,300.00
26 List Profil Kamper 5 cm m1 17,200.00
27 List Profil Kamper 10 cm m1 29,400.00
28 Pegangan Tangga Profil Jati m1 160,100.00
29 Pegangan Tangga Profil Kamper m1 122,500.00
30 Kayu Kaso 4/6 m3 2,772,000.00
31 Kayu Kaso 5/7 Kamper Medan m3 3,356,800.00
32 Kayu Reng 2/3 Borneo Super m1 2,500.00
33 Kayu Reng 2/3 Kamper Banjar m1 3,300.00
34 Kayu Reng 3/4 Kamper Medan m3 4,000.00
35 Kayu Papan Terentang m3 2,850,000.00
36 Kayu Balok Terentang m3 2,640,000.00
37 Batang Kelapa bt 139,500.00
38 Tali Ijuk kg 23,400.00
39 lapisan Ijuk tebal 10 cm m2 22,000.00
40 Venetion Blind m2 537,300.00
41 Vertikal Blind m2 351,200.00

D BAHAN PENUTUP RANGKA PLAFOND


1 Plafond Enternit 4 mm m2 17,400.00
2 Plafond hardpleks 5 mm 120 x 240 lbr 62,400.00
3 Plafond Asbes Semen 5 mm m2 22,500.00
4 Plafond Asbes Semen 3,5 mm m2 19,500.00
5 Gypsum 120 x 240 t= 9 mm ex DN lbr 79,800.00
6 Gypsum 120 x 240 t= 9 mm ex Luar lbr 83,800.00
7 Tepung gypsum kg 12,500.00
8 Acustik Amstrong 60 x 120 lbr 132,800.00
9 Cotton Plester bh 15,000.00
10 GRC (120 x 240) cm, t = 4 mm lbr 67,500.00
11 Cornice Coumpound zak 75,000.00
12 List gypsum m' 8,500.00

E BAHAN KAYU LAPIS


1 Triplek 3 mm 120 x 240 lbr 61,700.00
2 Triplek 4 mm 120 x 240 lbr 64,400.00
3 Triplek 4 mm ukuran Pintu lbr 56,200.00
4 Triplek 6 mm 120 x 240 lbr 92,000.00
5 Triplek 9 mm 120 x 240 lbr 166,600.00
6 Jabar Wood 4 mm lbr 119,000.00
7 Bilik Bambu ( tanpa kulit ) m2 19,800.00
8 Bilik Bambu ( dengan kulit ) m2 22,700.00
9 Bilik Bambu Hitam Variasi m2 34,200.00
10 Wall paper m2 55,700.00
11 MultiPlek 9 mm 120 x 240 lbr 151,100.00
12 MultiPlek 12 mm 120 x 240 lbr 195,000.00
13 MultiPlek 18 mm 120 x 240 lbr 255,400.00
14 Ply Wood 18 mm 120 x 240 lbr 323,900.00
15 Ply Wood 9 mm 120 x 240 lbr 235,000.00
16 Ply Wood 4 mm 120 x 240 lbr 140,000.00
17 Teak Wood 3 mm 120 x 240 lbr 129,100.00
18 Teak Wood 4 mm 120 x 240 lbr 131,700.00
19 Teak Wood 3 mm 120 x 240 ukuran Pin lbr 127,200.00
20 Teak Wood ukuran Pintu 4 mm lbr 114,700.00
21 Tacon ( Tahan Bakar ) m2 128,200.00
22 Supercon m2 57,900.00
23 Melamin 4 mm 120 x 240 lbr 89,200.00
24 Melamin TOK 4 mm lbr 133,400.00
25 Formika 120 x 240 lbr 170,000.00
26 Formika ukuran Pintu lbr 132,900.00
27 Formika Warna 4" x 8" lbr 238,100.00

F BAHAN LANTAI DAN PELAPIS DINDING


1 Tegel PC 20 x 20 bh 3,400.00
2 Plin Tegel PC 10 x 20 bh 2,400.00
3 Tegel PC 30 x 30 bh 3,400.00
4 Plin Tegel PC 15 x 30 bh 2,800.00
5 Tegel Warna 20 x 20 bh 3,600.00
6 Plin Tegel Warna 10 x 20 bh 3,400.00
7 Tegel Warna 30 x 30 bh 5,700.00
8 Plin Tegel Warna 15 x 30 bh 6,300.00
9 Tegel Wafel PC 20 x 20 bh 3,200.00
10 Tegel Wafel Warna 20 x 20 bh 2,500.00
11 Tegel Badak PC 30 x 30 bh 4,100.00
12 Poslin 11 x 11 Warna Standar DN m2 63,300.00
13 Poslin 11 x 11 Warna khusus DN m2 67,300.00
14 Keramik 10 x 20 dan 20 x 20 KW I DN Pu m2 54,500.00
15 Keramik 10 x 20 KW I DN Corak/Warna/A m2 56,000.00
16 Keramik 20 x 20 (KM) KW I DN Corak/Wa m2 62,500.00
17 Keramik 20 x 20 (KM) KW I DN Putih Po m2 54,500.00
18 Keramik 20 x 25 Dinding KM KW I DN C m2 62,500.00
19 Keramik 30 x 30 KWI DN Putih Polos Mu m2 53,000.00
20 Keramik 30 x 30 KWI DN Warna/Corak ( m2 58,000.00
21 Keramik 40 x 40 KWI DN Putih Polos Mu m2 56,800.00
22 Keramik 40 x 40 KWI DN Warna/Corak ( m2 65,500.00
23 Keramik 10 x 20 dan 20 x 20 KW I DN P m2 64,400.00
24 Keramik 10 x 20 KW I DN Corak/Warna/ m2 72,200.00
25 Keramik 20 x 20 (KM) KW I DN Corak/W m2 75,200.00
26 Keramik 20 x 20 (KM) KW I DN Putih P m2 72,900.00
27 Keramik 20 x 25 Dinding KM KW I DN m2 75,200.00
28 Keramik 20 x 25 KW I DN Putih Polos m2 72,900.00
29 Keramik 30 x 30 KW I DN Polos Roman m2 68,900.00
30 Keramik 30 x 30 KW I DN Warna/Corak m2 76,600.00
31 Keramik 40 x 40 KW I DN Polos Roman m2 72,500.00
32 Keramik 40 x 40 KW I DN Warna/Corak m2 77,000.00
33 Vinyl Lantai Standar m2 56,000.00
34 Karpet Kelas Baik LN m2 1,025,500.00
35 Karpet Kelas Sedang LN m2 353,500.00
36 Parquet Jati m2 375,400.00
37 Stairnosing Keramik 10/20 bh 13,700.00
38 Stairnosing Fiber m 25,000.00
39 Taraso Kerang 30 x 30 m2 31,800.00
40 Plin Taraso 10 x 30 bh 13,500.00
41 Granit Alam LN Ukuran Besar m2 1,848,400.00
42 Granit Alam LN Ukuran Kecil m2 1,612,900.00
43 Granit Alam DN Ukuran Besar m2 1,331,100.00
44 Granit Alam DN Ukuran Kecil m2 1,299,400.00
45 Granito Tile Essenza Ukuran 40 x 40 Po m2 345,000.00
46 Granito Tile Essenza Ukuran 30 x 30 m2 322,800.00
47 Granito Tile Essenza Ukuran 40 x 40 Un m2 204,900.00
48 Marmer m2 550,000.00
49 Marmer Alam Lampung Ukuran Besar m2 550,200.00
50 Marmer Alam Lampung Ukuran kecil m2 345,700.00
51 Marmer Alam Citatah Ukuran Besar m2 340,800.00
52 Marmer Alam Citatah Ukuran Kecil m2 237,600.00
53 Marmer Sintetis m2 157,900.00
54 Granito Tile Essenza 60 x 60 Polis m2 358,100.00
55 Granito Tile Essenza 60 x 60 UnPolis m2 231,800.00
56 Batu Tempel Hitam m2 96,500.00
57 Bata Karawang bh 600
58 Campuran untuk Kedap Air ( AM ) ltr 37,600.00
59 Plint keramik 10 x 20 bh 3,000.00
60 Plint keramik 10 x 25 bh 3,250.00
61 Plint keramik 10 x 30 bh 3,500.00
62 Plint keramik 10 x 40 bh 4,000.00
63 Plint keramik 15 x 30 bh 4,500.00
64 Plint keramik 15 x 40 bh 5,250.00
65 Plint granito 10 x 30 bh 25,900.00
66 Plint granito 10 x 40 bh 27,600.00
67 Plint granito 15 x 30 bh 31,100.00
68 Plint granito 15 x 40 bh 41,300.00

G BAHAN SALURAN AIR KOTOR / BERSIH


1 Grafel U 20 cm' m1 44,300.00
2 Grafel U 30 cm' m1 56,400.00
3 Grafel U 40 cm' m1 74,200.00
4 Buis Beton 20 cm ( 1 M' ) m1 49,200.00
5 Buis Beton 30 cm ( 1 M' ) m1 61,700.00
6 Buis Beton 40 cm ( 1 M' ) m1 80,900.00
7 Buis Beton 50 cm ( 1 M' ) stk 94,300.00
8 Buis Beton 60 cm ( 1 M' ) stk 130,900.00
9 Buis Beton 100 cm ( 0.50 M' ) stk 299,800.00
10 Buis Beton 80 cm ( 0.50 M' ) stk 298,500.00
11 BuisTanah 10 cm ( 0.50 M' ) stk 9,600.00
12 BuisTanah 15 cm ( 0.50 M' ) stk 12,700.00
13 BuisTanah 20 cm ( 0.50 M' ) stk 16,800.00
14 BuisTanah 25 cm ( 0.50 M' ) stk 22,800.00
15 Injuk kg 17,400.00

H BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Beton U-24 Rata-rata kg 16,500.00
2 Besi Beton U-39 / U-32 Rata-rata kg 20,700.00
3 Pagar BRC lengkap tiang ( Tanpa Ponda m2 171,300.00
4 Bondek m2 185,000.00
5 Besi WF Ex DN SII kg 24,000.00
6 Besi WF Ex Jepang kg 23,900.00
7 Besi Profil DN SII kg 18,300.00
8 Besi Profil Ex LN kg 21,600.00
9 Besi C Lip Chanel kg 19,200.00
10 Ongkos Galfanis Besi kg 10,600.00
11 Kawat Beton kg 27,700.00
12 Kawat Duri kg 63,500.00
13 Kawat Pengikat m1 1,000.00
14 Kawat Bronjong 4 mm kg 28,200.00
15 Kawat Tembaga kg 41,400.00
16 Ram Nyamuk Hijau m2 13,400.00
17 Ram Kawat 1 x 1 cm m2 15,300.00
18 Ram Ayam m2 14,900.00
19 Kawat Kasa 1 x 1 ( Putih ) m2 32,100.00
20 Kawat Harmonika 4 cm m2 35,900.00
21 Kawat Harmonika 2 cm m2 28,600.00
22 Kawat Las Listrik kg 23,600.00
23 Wiremesh M8 m2 51,900.00
24 Wiremesh M6 m2 38,700.00
25 Timah kg 46,300.00
26 Timah Hitam kg 43,300.00
27 Ram nyamuk Alumunium m2 32,400.00
28 Plat Srip Ø 2 x 30 mm ( 6 m1 ) bt 33,000.00
29 Plat Srip Ø 3 x 30 mm ( 6 m1 ) bt 33,100.00
30 Plat Strip bt 18,200.00
31 Besi Strip kg 26,800.00
32 Plat Alumunium 0.2 mm m2 89,800.00
33 Plat Alumunium 0.3 mm m2 110,500.00
34 Plat Alumunium 0.4 mm m2 141,400.00
35 Plat Alumunium 0.5 mm m2 143,100.00
36 Plat Alumunium 0.6 mm m2 171,800.00
37 Plat Alumunium 0.1 mm m2 56,300.00
38 Kusen Alumunium Natural 1.3 mm t= 1,3 m1 151,100.00
39 Kusen Alumunium Warna 1.3 mm t= 1,3 m1 163,000.00
40 Kusen Alumunium Natural 1.3 mm t= 1,3 m1 81,000.00
41 Kusen Alumunium Warna 1.3 mm t= 1,3 m1 102,000.00
42 Daun Jendela Alumunium Natural ( tanp m2 98,800.00
43 Daun Jendela Alumunium Warna ( tanpa m2 148,800.00
44 Daun Pintu Alumunium Natural ( tanpa k m2 211,800.00
45 Daun Pintu Alumunium Warna ( tanpa ka m2 207,500.00
46 Handle Alumunium ( Tarikan Pintu Alum bh 345,200.00
47 Kait Angin Alumunium ps 104,500.00
48 Karet Asisoris Kusen / Pintu Alumunium m1 7,500.00
49 Jalusi Alluminium m' 35,000.00
50 Sunscreen Almunium m2 380,200.00
51 Seng Plat BJLS 30 60 cm ( 100 m1 ) roll 1,581,500.00
52 Seng Plat BJLS 30 90 cm ( 100 m1 ) roll 2,080,100.00
53 Plat Besi Tipis 1 mm kg 16,800.00
54 Plat Besi Tipis 0.5 mm kg 17,700.00
55 Plat Besi 2 mm s/d 5 mm kg 14,100.00
56 Plat Besi 6 mms/d 10 mm kg 14,100.00
57 Plat Besi 10 mm keatas kg 14,700.00
58 Kabel presstressed polos kg 26,700.00
59 Jaring Kawat Baja kg 28,900.00
60 Lem Kuning ( Aibond ) kg 35,700.00
61 Lem Fox kg 23,900.00
62 Lem Vinyl kg 44,000.00
63 Besi Strip Kaca Nako kg 11,000.00
64 Profil alumunium "T" m1 12,200.00
65 Besi Hallow ( 2 x 4 x 4) cm (400cm) btg 22,600.00
66 Besi Hallow ( 4 x 4) cm (400 cm) btg 29,200.00
67 Besi Rail Pengamanan kg 459,300.00
68 Jendela Besi m2 390,200.00
69 Jendela Besi tahan api m2 501,700.00
70 Pintu gulung besi m2 501,700.00
71 Pintu Roliing Door m2 306,600.00
72 Jendela nako kaca ryben + tralis 6 klips set 170,000.00
73 Jendela nako kaca ryben + tralis 7 klips set 200,000.00
74 Jendela nako kaca ryben + tralis 8 klips set 230,000.00
75 Jendela nako kaca ryben + tralis 10 klip set 290,000.00
76 Jendela nako kaca bening + tralis 4 klip set 120,000.00
77 Jendela nako kaca bening + tralis 5 klip set 140,000.00
78 Jendela nako kaca bening + tralis 6 klip set 170,000.00
79 Jendela nako kaca bening + tralis 7 klip set 210,000.00
80 Jendela nako kaca bening + tralis 8 klip set 230,000.00
81 Jendela nako kaca bening + tralis 10 kli set 300,000.00

I BAHAN KACA
1 Kaca Polos 2 mm ( ASAHI ) m2 69,000.00
2 Kaca Polos 3 mm ( ASAHI ) m2 87,400.00
3 Kaca Polos 5 mm ( ASAHI ) m2 111,000.00
4 Kaca Polos 8 mm ( ASAHI ) m2 183,100.00
5 Kaca Rayband 5 mm ( ASAHI ) m2 148,700.00
6 Kaca Rayband 8 mm ( ASAHI ) m2 323,400.00
7 Kaca Rayband 12 mm ( ASAHI ) m2 627,000.00
8 Kaca cermin 5 mm m2 150,500.00
9 Kaca cermin 6 mm m2 186,400.00
10 Kaca cermin 8 mm m2 234,300.00
11 Kaca Patri Lokal Terpasang ( ASAHI ) m2 1,621,100.00
12 Kaca Patri Ex Luar Negeri Terpasang m2 3,425,700.00
13 Kaca 6 mm Gravver m2 1,263,900.00
14 Glass Block DN 20 x 20 ( Kedawung ) bh 22,000.00
15 Glass Block DN 20 x 20 Ex LN bh 125,700.00
16 Sealant kg 211,800.00
17 Jendela Nako bh 109,200.00

J BAHAN PAKU DAN MUR BAUT


1 Paku 1/2" s/d 2" kg 23,800.00
2 Paku 2" s/d 5" kg 23,400.00
3 Paku 8 cm s/d 15 cm kg 20,000.00
4 Paku Beton 2 cm s/d 5 cm bh 1,600.00
5 Paku Kait Lengkap bh 900
6 Paku Cacing kg 57,100.00
7 Besi Beugel Kuda - Kuda kg 21,700.00
8 Duk Angker bh 7,500.00
9 Angker Mur Baut dia. 19 / Panjang 60 bh 71,800.00
10 Mur Baut HTB dia. 19 s/d 16 ( 5 cm ) bh 15,900.00
11 Mur Baut Biasa dia. 19 s/d 16 ( 5 cm ) bh 9,300.00
12 Piser dia.12 s/d 20 cm bh 5,300.00
13 Paku skrup 3" bh 800
14 Ramset / Dinabolt bh 7,200.00
15 Baut Besar bh 600
16 Baut Kecil bh 300
17 Paku GRC kg 35,000.00
18 Paku gypsum kg 17,500.00
19 Sekrup fixer bh 250

K BAHAN PERPIPAAN
1 Besi Pipa Untuk Hydrant BSP 1" bt 166,700.00
2 Besi Pipa Untuk Hydrant BSP 1.25" bt 210,200.00
3 Besi Pipa Untuk Hydrant BSP 1.5" bt 298,000.00
4 Besi Pipa Untuk Hydrant BSP 2" bt 351,800.00
5 Besi Pipa Untuk Hydrant BSP 2.5" bt 439,300.00
6 Besi Pipa Untuk Hydrant BSP 3" bt 595,000.00
7 Besi Pipa Untuk Hydrant BSP 4" bt 869,600.00
8 Besi Pipa Untuk Hydrant BSP 6" bt 1,423,400.00
9 Besi Pipa Hitam 1" t = 2 mm bt 172,300.00
10 Besi Pipa Hitam 2" t = 2 mm bt 227,900.00
11 Besi Pipa Hitam 3" t = 2mm bt 365,800.00
12 Besi Pipa Hitam 4" t = 2 mm bt 573,100.00
13 Besi Pipa Hitam 6" t = 2 mm bt 772,400.00
14 Pipa GIP Medium A 1/2" ( 6 m1 ) bt 109,100.00
15 Pipa GIP Medium A 3/4" ( 6 m1 ) bt 159,400.00
16 Pipa GIP Medium A 1" ( 6 m1 ) bt 181,500.00
17 Pipa GIP Medium A 1 1/4" ( 6 m1 ) bt 259,300.00
18 Pipa GIP Medium A 1 1/2" ( 6 m1 ) bt 280,500.00
19 Pipa GIP Medium A 1 3/4" ( 6 m1 ) bt 326,400.00
20 Pipa GIP Medium A 2" ( 6 m1 ) bt 467,400.00
21 Pipa GIP Medium A 2 1/2" ( 6 m1 ) bt 672,100.00
22 Pipa GIP Medium A 3" ( 6 m1 ) bt 849,900.00
23 Pipa GIP Medium A 4" ( 6 m1 ) bt 920,300.00
24 Macam2 Sambungan GIP 1/2" bh 6,300.00
25 Macam2 Sambungan GIP 3/4" bh 8,600.00
26 Macam2 Sambungan GIP 1" bh 16,700.00
27 Macam2 Sambungan GIP 1 1/4" bh 19,800.00
28 Macam2 Sambungan GIP 1 1/2" bh 20,700.00
29 Macam2 Sambungan GIP 1 3/4" bh 22,700.00
30 Macam2 Sambungan GIP 2" bh 51,200.00
31 Macam2 Sambungan GIP 2 1/2" bh 60,400.00
32 Macam2 Sambungan GIP 3" bh 75,900.00
33 Macam2 Sambungan GIP 4" bh 118,600.00
34 Pipa PVC RUCIKA type AW 1/2" bt 40,100.00
35 Pipa PVC RUCIKA type AW 3/4" bt 52,200.00
36 Pipa PVC RUCIKA type AW 1" bt 63,200.00
37 Pipa PVC RUCIKA type AW 1 1/4" bt 79,900.00
38 Pipa PVC RUCIKA type AW 1 1/2" bt 105,900.00
39 Pipa PVC RUCIKA type AW 2" bt 110,700.00
40 Pipa PVC RUCIKA type AW 2 1/2" bt 167,100.00
41 Pipa PVC RUCIKA type AW 3" bt 205,100.00
42 Pipa PVC RUCIKA type AW 4" bt 347,900.00
43 Pipa PVC RUCIKA type AW 6" bt 640,000.00
44 Pipa PVC RUCIKA type AW 8" bt 818,300.00
45 Pipa PVC MASPION ABU ( AW ) 1/2" bt 22,500.00
46 Pipa PVC MASPION ABU ( AW ) 3/4" bt 27,800.00
47 Pipa PVC MASPION ABU ( AW ) 1" bt 40,500.00
48 Pipa PVC MASPION ABU ( AW ) 1 1/4" bt 58,500.00
49 Pipa PVC MASPION ABU ( AW ) 1 1/2" bt 60,200.00
50 Pipa PVC MASPION ABU ( AW ) 2" bt 75,800.00
51 Pipa PVC MASPION ABU ( AW ) 2 1/2" bt 126,300.00
52 Pipa PVC MASPION ABU ( AW ) 3" bt 145,700.00
53 Pipa PVC MASPION ABU ( AW ) 4" bt 256,800.00
54 Macam2 Sambungan Paralon 1/2" bh 4,400.00
55 Macam2 Sambungan Paralon 3/4" bh 4,700.00
56 Macam2 Sambungan Paralon 1" bh 4,900.00
57 Macam2 Sambungan Paralon 1 1/4" bh 7,200.00
58 Macam2 Sambungan Paralon 1 1/2" bh 9,500.00
59 Macam2 Sambungan Paralon 1 3/4" bh 13,500.00
60 Macam2 Sambungan Paralon 2" bh 15,800.00
61 Macam2 Sambungan Paralon 2 1/2" bh 26,400.00
62 Macam2 Sambungan Paralon 3" bh 29,700.00
63 Macam2 Sambungan Paralon 4" bh 34,000.00
64 Sambungan Pipa PVC Jenis AW 4" TY bh 89,900.00
65 Lem Paralon tb 10,100.00
66 Solatip Ledeng gl 4,200.00
67 Pipa PVC 4" Berlobang Jenis AW m1 36,700.00
68 PVC Waterstop lebar 150 m1 53,500.00
69 PVC Waterstop lebar 200 m1 57,900.00
70 PVC Waterstop lebar 230 m1 65,700.00
71 PVC Waterstop lebar 250 m1 74,700.00
72 PVC Waterstop lebar 300 m1 83,600.00
73 PVC Waterstop lebar 320 m1 92,500.00

L BAHAN SANITAIR
1 Stop Kran 3/4" KIT bh 103,900.00
2 Stop Kran 1" KIT bh 124,200.00
3 Stop Kran 1 1/2" KIT bh 208,000.00
4 Stop Kran 2" KIT bh 267,900.00
5 Stop Kran 2 1/2" KIT bh 713,200.00
6 Stop Kran 3" KIT bh 830,300.00
7 Check Valve 1/2" bh 86,400.00
8 Double Neple 1/2" bh 32,400.00
9 Water Mur 1/2" bh 40,200.00
10 Gate walve 1/2" bh 55,500.00
11 Saringan Air Lt. KM Stainless Steel bh 66,600.00
12 Apooer Bath Tube bh 267,800.00
13 Kran Stainless Lokal Kait bh 46,100.00
14 Shower Dengan Tiang bh 221,000.00
15 Shower Tanpa Tiang bh 134,800.00
16 Kran Tembok Sun Eui dia. 1/2" bh 86,900.00
17 Kran Tembok ITAP dia. 1/2" bh 40,900.00
18 Kran Bebek Sun Eui 1/2" bh 144,600.00
19 Kran Bebek ITAP 1/2" bh 51,500.00
20 Kran Panas Dingin San Eui Standard bh 228,400.00
21 Bath Cape Washteren unit 2,098,700.00
22 Tempat Sabun Poslin bh 46,300.00
23 Wastafel Lengkap TOTO LW 230 unit 1,012,700.00
24 Wastafel Lengkap INA unit 699,900.00
25 Closet Jongkok Poslin Warna TOTO unit 205,600.00
26 Closet Jongkok Standard Putih Poslin unit 188,200.00
27 Closet Jongkok Lengkap Sistem Jet T unit 2,032,900.00
28 Closet Duduk Warna Standard TOTO C unit 1,724,700.00
29 Wastafel Bulat Warna Standard Lengka unit 910,800.00
30 Closet Duduk Warna Standard INA Len bh 1,272,100.00
31 Urinoir Lengkap TOTO Warna Standard unit 1,773,400.00
32 Penyekat Poslin Urinoar TOTO lbr 495,900.00
33 Kitchen Zink Stainless Standard Lokal ( bh 397,800.00
34 Kitchen Zink Stainless Non Standard Fr bh 1,272,300.00
35 Kitchen Zink Stainless Non Standard Fr bh 1,650,200.00
36 Talang PVC U - 15 cm btng 60,000.00

M BAHAN PENUTUP ATAP


1 Atap Plastik Gelombang 80 x 180 lbr 33,100.00
2 Atap Fiber Glass Tipis 80 x 180 ( Gelo lbr 47,100.00
3 Atap Fiber Glass Tebal 80 x 180 ( Gelo lbr 100,000.00
4 Atap Alumunium Natural USR 26 ( JAIN m2 140,600.00
5 Atap Alumunium Warna USR 26 ( JAIN m2 164,700.00
6 Atap Asbes Gel. Kecil 80 x 180 x 4 mm lbr 77,200.00
7 Atap Asbes Gel. Besar 80 x 180 x 5 mm lbr 111,100.00
8 Atap Seng Gelombang 80 cm x 180 cm lbr 62,900.00
9 Atap Seng Gelombang 80 cm x 180 cm lbr 83,100.00
10 Atap Seng Gelombang 270 cm x 105 c lbr 73,300.00
11 Atap Seng Gelombang 240 cm x 105 c lbr 65,900.00
12 Atap Seng Gelombang 210 cm x 105 c lbr 58,500.00
13 Atap Seng Gelombang 150 cm x 105 c lbr 42,300.00
14 Atap Seng Gelombang 150 cm x 102 c lbr 78,500.00
15 Atap Seng Gelombang 180 cm x 102 c lbr 97,200.00
16 Atap Asbes Gelombang 300 cm x 105 lbr 80,000.00
17 Atap Tegola Kubota, lengkap m2 487,100.00
18 Atap Tegola Kwalitas Sedang m2 283,600.00
19 Alumunium Foile m2 19,600.00
20 Atap Genteng Plentong pres Bakar KW bh 1,900.00
21 Atap Genteng Plentong pres Molen Ov bh 2,700.00
22 Atap Genteng Flam pres Molen Oven Ja bh 2,300.00
23 Bubung Genteng pres Bulat Ex Jatiwan bh 7,500.00
24 Genteng Bubungan Ex Jatiwangi Segi T bh 4,800.00
25 Genteng Bubungan Beton bh 10,500.00
26 Genteng Metal ( Rainbow Roof ) m2 203,100.00
27 Genteng Metal Hana m2 172,700.00
28 Nok Atas Metal ( Rainbow Roof ) lbr 138,500.00
29 Nok Atas Metal Hana lbr 80,900.00
30 Nok Pingir Metal ( Rainbow Roof ) lbr 105,300.00
31 Nok Pingir Metal Hana lbr 100,800.00
32 Wall Flasing ( Rainbow Roof ) lbr 83,900.00
33 Wall Flasing Hana lbr 88,700.00
34 Atap Genteng Beton Warna 14.5/m2 m2 96,700.00
35 Genteng Beton Natural bh 8,500.00
36 Sirap Kelas I ( 80 / m2 ) m2 26,400.00
37 Genteng Keramik Natural Intan 14.5 / m2 112,400.00
38 Genteng Keramik Glasur Standard 14.5 m2 142,200.00
39 Genteng Keramik Glasur Special 14.5 m2 139,300.00
40 Genteng Keramik Glasur Premium 14.5 m2 145,100.00
41 Genteng Murando Natural 1m2 = 18 bh bh 2,700.00
42 Genteng Murando Glasur 1m2 = 18 bh bh 4,000.00
43 Bubung Murando Natural bh 7,500.00
44 Bubung Murando Glasur bh 10,700.00
45 Bubungan Genteng Keramik bh 10,000.00
46 Atap Genteng Kodok bh 3,000.00
47 Bubungan Genteng Kodok bh 4,500.00
48 Bubungan Genteng Plentong bh 6,000.00
49 Bubungan Stel Gelombang bh 7,500.00
50 Nok Stel Gelombang lbr 38,100.00
51 Nok Atap Seng lbr 37,500.00
52 Nok standar 40 cm 18, SWG 22 m2 75,000.00
53 Pelat Asbes tebal 4 mm lbr 21,000.00
54 Pelat Asbes tebal 3.5 mm lbr 16,400.00
55 Trusses ZAM-75 t=0.8 Rangka Utama m1 34,500.00
56 Trusses ZAM-75 t=0.5 Rangka Utama m1 22,000.00
57 Reng 16-DB Roof Battens t=0.48 mm m1 11,000.00
58 Foot Plate t= 1.22 mm m1 7,200.00
59 PLD - Diafragma Plate bh 2,200.00
60 WIND Bracing m1 1,700.00
61 Tensioner ( Pengaku Tali angin ) bh 7,200.00

N BAHAN MEKANIKAL
1 Jockey Pump kap. 80 gln/menit 100 m1 unit 71,396,400.00
2 Electrical Pump kap. 750 gln/menit 120 unit 216,358,900.00
3 Diesel Pump kap. 750 gln/menit 120 m1 unit 591,647,100.00
4 Presure Tank kap. 500 liter lengkap unit 36,997,300.00
5 Hydran Box dlm Gedung ( Lengkap ) unit 6,854,400.00
6 Fire House 1.5 x 30 m + nose unit 4,866,100.00
7 Exhose Fan H 360 W 60 x 60 cm unit 6,862,900.00
8 Exhose Fan H 380 W CFM 55 x 55 cm unit 5,491,100.00
9 Exhose Fan H 100 W 40 x 40 cm unit 1,092,600.00
10 AC Split 3 PK Setara TOSHIBA unit 30,791,800.00
11 AC Split 2 PK Setara TOSHIBA unit 21,926,500.00
12 AC Split 1 PK Setara TOSHIBA unit 5,174,100.00
13 Mesin AC Split DAIKIN ( Indoor / Outdoo 1 BTU 4,200,000.00

O BAHAN ELEKTRIKAL
1 Kabel NYA 1 x 1.5 Prima ( 1 rol = 50 m' ROLL 102,700.00
2 Kabel NYA 1 x 2.5 Prima ( 1 rol = 50 m' ROLL 151,700.00
3 Kabel NYM 2 x 1.5 Prima ( 1 rol = 50 m' m' 6,600.00
4 Kabel NYM 3 x 1.5 Prima ( 1 rol = 50 m' m' 7,600.00
5 Kabel NYM 2 x 2.5 Prima ( 1 rol = 50 m' m' 4,900.00
6 Kabel NYM 3 x 2.5 Prima ( 1 rol = 50 m' m' 10,900.00
7 Kabel NYM 4 x 2.5 Prima ( 1 rol = 50 m' m' 7,600.00
8 Kabel NYM 2 x 4 Prima ( 1 rol = 50 m' ) m' 6,300.00
9 Kabel NYM 3 x 4 Prima ( 1 rol = 50 m' ) m' 15,400.00
10 Kabel NYM 4 x 4 Prima ( 1 rol = 50 m' ) m' 20,700.00
11 Kabel NYM 2 x 6 Supreme ( 1 rol = 50 m m' 11,800.00
12 Kabel NYM 3 x 6 Supreme ( 1 rol = 50 m m' 13,700.00
13 Kabel NYM 4 x 6 Supreme ( 1 rol = 50 m m' 18,600.00
14 Kabel NYM 2 x 10 Supreme ( 1 rol = 50 m' 17,600.00
15 Kabel NYM 3 x 10 Supreme ( 1 rol = 50 m' 119,700.00
16 Kabel NYM 4 x 10 Supreme ( 1 rol = 50 m' 26,500.00
17 Kabel NYM 4 x 16 Supreme ( 1 rol = 50 m' 29,700.00
18 Kabel NYY 2 x 4 Supreme ( 1 rol = 50 m' m' 12,000.00
19 Kabel NYY 3 x 4 Supreme ( 1 rol = 50 m' m' 19,300.00
20 Kabel NYY 4 x 4 Supreme ( 1 rol = 50 m' m' 23,800.00
21 Kabel NYY 2 x 6 Supreme ( 1 rol = 50 m' m' 14,500.00
22 Kabel NYY 3 x 6 Supreme ( 1 rol = 50 m' m' 19,200.00
23 Kabel NYY 4 x 6 Supreme ( 1 rol = 50 m' m' 18,500.00
24 Kabel NYY 2 x 10 Supreme ( 1 rol = 50 m' 20,400.00
25 Kabel NYY 3 x 10 Supreme ( 1 rol = 50 m' 25,800.00
26 Kabel NYY 4 x 10 Supreme ( 1 rol = 50 m' 35,500.00
27 Kabel NYY 4 x 16 Supreme ( 1 rol = 50 m' 41,900.00
28 NSFB FUJI EA - 100 A bh 841,900.00
29 NSFB FUJI EA - 150 A bh 2,182,600.00
30 Rumah Panel 30 x 60 cm ( Kosong ) unt 153,500.00
31 Skring Kas 2 grop Biasa unt 204,800.00
32 Skring Kas 3 grop Biasa unt 222,600.00
33 Skring Kas 5 grop Biasa unt 468,800.00
34 MCB 1 PAS bh 55,100.00
35 MCB 3 PAS bh 106,000.00
36 Tahanan 50 A Merk Fuji bh 521,100.00
37 Saklar Broko Tunggal Standard ( 1 Phas bh 23,800.00
38 Saklar Broko Seri Standard ( 1 Phase ) bh 26,300.00
39 Stop Kontak Broko Standard ( 1 Phase bh 23,800.00
40 Stop Kontak Broko 3 Phase (Out Bow) bh 87,700.00
41 Stop Kontak Broko 3 Phase ( In Bow) bh 144,900.00
42 Stop Kontak Handle 3 Phase bh 87,800.00
43 Instalas Titik Lampu / Stop Kontak (Upa ttk 179,600.00
44 Lampu pijar 25 Watt s/d 100 Watt bh 61,200.00
45 Lampu Neon Phillips 20 Watt bh 29,700.00
46 Lampu Neon Phillips 40 Watt bh 35,200.00
47 Trapo TL 20 W (Phillips) bh 41,800.00
48 Trapo TL 40 W (Phillips) bh 37,900.00
49 Trapo TL 20 W (Sinar) bh 40,600.00
50 Trapo TL 40 W (sinar) bh 41,300.00
51 Stater Neon Phillips bh 8,300.00
52 Stater Neon Biasa bh 6,500.00
53 Rumah TL In Bow / Out Bow 2 x 20 W ( bh 144,000.00
54 Down Light + SL 25 W bh 306,900.00
55 Lampu SL Philip 25 W bh 306,900.00
56 Lampu Sirkel TL 20 W Lengkap bh 67,900.00
57 Lampu Mercuri 80 W bh 147,400.00
58 Lampu Taman + Tiang + Lampu 1 Buah bh 307,600.00
59 Lampu Baret 30 cm + Neon bh 221,700.00
60 Lampu Neon Arcrilik 2 x 40 W Lengkap bh 738,000.00
61 Jarum Penangkal Petir 16 bh 101,500.00
62 Kawat BC ( Tembaga ) kg 65,100.00
63 Pentanahan Penangkal Petir ttk 423,700.00
64 Pentanahan Panel ttk 296,100.00

P BAHAN ALAT PENGANTUNG DAN KUNCI


1 Kunci Silinder ALFA untuk Pintu Al bh 410,900.00
2 Tarikan Pintu Alumunium bh 408,600.00
3 Kunci 2 Slaag ROYAL bh 126,500.00
4 Rel Henderson Lengkap bh 864,300.00
5 Rel maraton I Pintu unt 193,100.00
6 Kunci 2 Slaag Silinder SEIS Asli typ bh 335,900.00
7 Kunci 2 Slaag Ancor Asli bh 165,300.00
8 Kunci 2 Slaag ISO bh 207,300.00
9 Kunci KM Bulat Kualitas Biasa bh 54,400.00
10 Kunci kM Bulat ALFA bh 102,700.00
11 Kunci 2 Slaag Silinder Utama Stand bh 586,600.00
12 Kunci Gembok Besar bh 85,200.00
13 Kunci 2 Slaag Kuda Terbang bh 94,500.00
14 Kunci Lemari bh 46,800.00
15 Espangolet ps 51,600.00
16 Grendel 15 cm bh 49,800.00
17 Grendel 5 cm bh 5,500.00
18 Hak Angin Kait Jendela Biasa ps 7,100.00
19 Hak Angin Jendela Antik ps 29,000.00
20 Hak Angin Sendok Stainless / Kunin bh 32,200.00
21 Sloot Pintu Berikut Rantai bh 31,500.00
22 Sloot Jendela Tunggal bh 33,000.00
23 Engsel Pintu Unilon Standard ps 21,000.00
24 Engsel Jendela Unilon ps 15,000.00
25 Engsel Patrun ps 13,700.00
26 Engsel Harmonika m1 9,100.00
27 Door Closer Kelas Standard ( Kelas unt 420,000.00
28 Door Closer Kelas Standard ( Kelas unt 597,500.00
29 Door Closer Kelas Rendah unt 200,000.00
30 Door Holder unt 205,400.00
31 Door Stoper unt 255,500.00
32 Tarikan Almari Rata-rata bh 19,500.00
33 Seng BJLS 30 Lebar 60 cm ( 1 rol 50 m1 43,500.00
34 Seng BJLS 30 Lebar 90 cm ( 1 rol 50 m1 53,500.00
35 Seng BJLS 30 / 3 x 0.3 mm lbr 86,900.00
36 Seng Plat lbr 50,100.00
37 Waterstop Lebar 200 mm m1 57,900.00

Q BAHAN PENGIKAT UNTUK KONSTRUKSI JALAN


1 Aspal Bitumen kg 12,459.00
2 Aspal Emulsi kg 12,459.00
3 Aspal Curah kg 10,890.00
4 Aspal Concrete / Laston( AC -WC) ton 1,348,300.00
5 Aspal Threated Base ( ATB ) ton 1,200,200.00
6 Lataston /Hot Rolls Sheet ( HRS ) ton 1,666,900.00

R BAHAN PENGISAP AIR SUMUR DALAM


1 Pompa Kodok unit 172,600.00
2 Pompa Dragon Tegal unit 243,800.00
3 Pompa Dragon Asli unit 718,500.00
4 Mesin Pompa Air 100 W - Sanyo unit 1,100,200.00
5 Mesin Pompa Air 150 W - Sanyo unit 1,890,700.00
6 Pompa Zet Pump 250 W - Sanyo unit 4,961,500.00
7 Pompa Zet Pump 450 W - Sanyo unit 7,878,000.00
8 Pompa Submersible kap. 150 liter / unit 27,151,200.00
9 Gear Pump Kap. 60 liter / menit unit 15,702,700.00
10 Deep Well dengan kelengkapannya kapunit 172,052,500.00
11 Hand Oil Pump unit 5,195,300.00

S BAHAN PENAMPUNG AIR


1 Tangki Air Fiber Glass 0.5 m3 ( Excel bh 1,172,500.00
2 Tangki Air Fiber Glass 1 m3 ( Excel ) bh 1,316,400.00
3 Tangki Air Fiber Glass 2 m3 ( Excel ) bh 1,954,200.00
4 Bak KM Fiber 60 x 60 bh 255,300.00
5 Bak Taraso WC 40 x 40 bh 118,500.00
6 Bak KM Taraso 60 x 60 bh 161,100.00
T ALAT TUKANG
1 Palu 0.5 kg bh 39,300.00
2 Cangkul bh 24,500.00
3 Singkup bh 41,400.00
4 Sekrop bh 50,100.00
5 Pengki bh 12,300.00
6 Linggis bh 41,700.00
7 Rool Meter 30 meter ( Bahan Plastik bh 101,000.00
8 Rool Meter 5 meter ( Bahan Besi ) bh 37,800.00
9 Selang Plastik untuk Water Pas dia. m 1,600.00
10 Water Pas Alumunium 60 cm bh 88,200.00

U BAHAN BAKAR DAN PELUMAS


1 Minyak Tanah lt 18,000.00
2 Kayu Bakar dari Kayu Karet m3 151,100.00
3 Bahan Bakar Residu lt 28,435.00
4 Minyak Solar lt 7,150.00
5 Bensin Premium lt 7,800.00
6 Plus Oil lt 3,300.00
7 Oil Mesran 40 SAE lt 55,000.00
8 Elpiji / botol 15 kg 104,600.00
9 Asitilin / Botol 15.1 kg btl 88,900.00
10 Angin ( O2 ) / botol btl 66,400.00
11 Karbit kg 19,400.00
12 Minyak Bekisting ltr 40,500.00
13 Rapidrant Gln 15,700.00
14 Soda Api kg 35,600.00
15 Sabun kg 2,400.00
16 Arang Kayu kg 11,100.00
17 Kawat Las bh 1,400.00

V BAHAN PAGAR
1 Panel Beton Pracetak lbr 199,200.00
2 Kolom Beton Pracetak btg 264,000.00

B. BIDANG PERTAMANAN
1 Aglonema batang 50,000.00
2 Bambu krisik/jepang batang 50,000.00
3 Furadan kg 24,000.00
4 Kompos/pupuk kandang karung 25,000.00
5 M atoa (2 m) batang 40,000.00
6 Palm (botol, ekor tupai, putri, dll) ti batang 100,000.00
7 Philo batang 75,000.00
8 Pohon pelindung (angsana, mahoni, batang 25,000.00
9 Pohon perdu (kaca piring, puring, maw batang 10,000.00
10 Rumput gajah mini m2 15,000.00