PRESUPUESTO

PRESUPUESTO : "REFACCIÓN Y ACONDICIONAMIENTO COMPLEJO ARAPA - CASA N° 12, N° 13, N° 14, N° 15, N° 16, N°
18 y SALA DE CAPACITACIÓN"
CLIENTE: COMPAÑÍA MINERA VOLCAN - UNIDAD DE SAN CRISTOBAL
LUGAR : JUNIN - YAULI - YAULI
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14

LINEA BASE - VALOR


PLANEADO SEMANAL $ 0 14,577 22,388 28,433 30,574 45,512 46,253 50,226 51,224 47,239 45,787 39,625 33,286 31,245 25,786

ACUMULADO VALOR
PLANEADO $ 0 14,577 36,966 65,399 95,973 141,485 187,738 237,964 289,188 336,427 382,214 421,839 455,125 486,369 512,156

VALOR GANADO SEMANAL


PV $ 0 11,662 17,911 17,060 19,620 18,145 38,751 48,748 98,547 56.46%

ACUMULADO EV $
0 11,662 29,572 46,632 66,252 84,397 123,148 171,896 270,443 52.80%

COSTO REAL AC $
0 8,746 13,433 17,060 18,344 13,654 37,003 40,181 40,979 3.66%
ACUMULADO COSTO REAL
AC $ 0 8,746 22,179 39,239 57,584 71,237 108,240 148,421 189,400

SPI
0 0.80 0.80 0.71 0.69 0.60 0.66 0.72 0.94 36.98%

CPI
0 1.33 1.33 1.19 1.15 1.18 1.14 1.16 1.43

CURVA S
COSTO ACUMULADO $ & SEMANAS
0.60
Millones

0.50 EV: 52.80%


PV:56.46%

0.40
COSTO ACUMULADOS $

0.30

0.20 AC:36.98%

PV-VALOR PLANEADO

0.10
EV - VALOR EJECUTADO-FISICO

AC-COSTO REAL
0.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

SEMANAS