CDQ – 3 SHUTDOWN ACTIVITIES

DATE ACTIVITIES
31-AUG-14 AT 05:30 HRS COKE CHARGING STOPPED

31-AUG-14 AT 05:00 HRS BOILER ISOLATED FROM TURBINE

BOILER DEPRESSURIZING
(31 AUG 14
TO (DRUM VENT OPENED AT 09:35 HRS {2-SEPT-14}) , (SUPERHEATERS VENT OPENED AT 10:00 HRS {2-
SEPT-14})
2 SEPT-14

ECONOMISER HOPPER MANHOLES(2 NOS) OPENED FOR CHAMBER REFRACTORIES COOLING

03-SEPT-14 SUB ECO BYPASSED

HP LINE MAIN MOV CLOSED MANUALLY

AT 07:37 HRS GAS CIRCULATING BLOWER STOPPED


05-SEPT-14
ALL BOILER MANHOLES WERE OPENED

06-SEPT-14 BOILER TUBES EXTERNALLY CLEANING DONE BY COMPRESSED AIR

DEAERATOR INTERNALS INSPECTION AND NOZZLE INSPECTION DONE


09-SEPT-14
STEAM DRUM INTERNAL INSPECTION DONE

10-SEPT-14 ECO HOPPER DUST CLEANING DONE(1 TRIP)

HYDROTEST DONE SUCCESSFULLY AT 120KG/CM2


12-SEPT-14
SUB ECO MANHOLES OPENED

BOILER TUBES THICKNESS MEASUREMENT WORK STARTED


13-SEPT-14
ECO HOPPER DUST CLEANING DONE(1 TRIP)
DATE ACTIVITIES

15-SEPT-14 HYDROTEST DONE SUCCESSFULLY AT 140KG/CM2 IN PRESENCE OF BOILER INSPECTOR

16-SEPT-14 SUB ECO TUBES EXTERNALLY AIR CLEANING DONE

18-SEPT-14 ECO HOPPER DUST CLEANING DONE(1 TRIP)

21-SEPT-14 ECO HOPPER DUST CLEANING DONE(2 TRIP)

22-SEPT-14 BOILER TUBES THICKNESS MEASUREMENT WORK COMPLETED

23-SEPT-14 SUB ECO TUBES EXTERNALLY AIR CLEANING DONE

24-SEPT-14 MANHOLES CLOSING DONE EXCEPT ECO HOPPER( 2 NOS) MANHOLES

DEAERATOR AND DRUM DRAINING DONE

LP STEAM CHARGED TO DEAERATOR

25-SEPT-14 LP STEAM CHARGED TO STEAM DRUM

BUBBLING PROCESS STARTED

GAS BLOWER STARTED AT 13:00 HRS

27-SEPT-14 HOT BUCKET CHARGED TO CHAMBER AT 12:40 HRS

SUB- ECO TAKEN IN LINE

28-SEPT-14 BOILER CONNECTED TO TURBINE AT 19:30 HRS