Anda di halaman 1dari 3

REPUBLIC OF THE PH, represented by the NAPOCOR v.

 Sought:
HEIRS OF SATURNINO Q. BORBON and CA o Dismissal of the complaint
GR No. 165354 12 January 2015 o Payment of P1K/sq. m. & attorney’s fees
By Kylie Dado o To be allowed to nominate their representative to the
panel of commissioners to be appointed by the trial court
FACTS:
PRE-TRIAL was conducted and the parties stipulated on the location,
NAPOCOR entered a property in Brgy. San Isidro, Batangas number of heirs, names of the person upon whom title to the property
 In order to construct and maintain transmission lines for the 230 was issued, and the ownership & possession of the property.
KV Mahabang ParangPinamucan Power Transmission Project  RTC directed the parties to submit names of their nominees to sit
o The heirs owned the propery (14, 257 sq. m.) in the panel of commissions within 10 days from the date of pre-
trial
NAPOCOR filed a COMPLAINT in the RTC-Batangas
 Seeking - acquisition of an easement of right of way over a RTC constituted the panel of 3 commissioners.
portion of the property involving an area of only 6,326 square  2 commissioners submitted a joint report, and found:
meters, more or less o property was classified industrial land located within the
 Allegation: Industrial 2 Zone
o It had negotiated w/ the respondents but they failed to o although it is used to be an agricultural land, it was
reach any agreement reclassified to industrial for appraisal/taxation purposes
o It was willing to deposit P9,790.00 representing the o Reclassification was made on the basis of a certification
assessed value of the portion sought to be expropriated issued by the Zoning Administrator
 Prayer:  2 commissioners appraised the value @ P550/sq. m.
o Issuance of a writ of possession upon deposit to enable it  3rd commissioner filed a separate report
to: o Recommended the payment of easement fee of at least
1. Enter and take possession and control of the 10% of the assessed value indicated in the tax
affected portion of the property declaration + damages + improvements affected + tower
2. Demolish all improvements existing occupancy
3. Commence construction of the transmission line
project Parties submitted their OBJECTIONS:
4. Appointment of 3 commissioners to determine just  HEIRS - NAPOCOR should compensate them for the entire
compensation property at the rate of P550.00/ sq. m. because the the property
was already classified as industrial land at the time NAPOCOR
Heirs’ ANSWER: entered it
 NAPOCOR had not negotiated with them before entering the  NAPOCOR – insisted that the property was classified as
property (Entry w/o consent), destroying some fruit trees without agricultural land at the time of its taking, and only seeking an
payment, and installing 5 woodpoles for its project easement of right of way over a portion of the property, not the
 Area being expropriated only covered the portion directly entire area so, it should only pay 10% of the assessed value of
affected by the transmission lines the portion
 Remaining portion of the property was also affected because the
transmission line passed through the center of the land, thereby RTC DECISION:
dividing the land into 3 lots  Price to be paid – value at the time of taking, which is the date of
 Presence of the high tension transmission line had rendered the entry to the property or the date of the filing of the complaint
entire property inutile for any future use and capabilities o There is no evidence as to when NAPOCOR entered so the
 NONETHELESS, they tendered no objection provided it would pay reference point should be the date of filing – May 5, 1995
just compensation not only for the portion sought to be  Gave more weight to the Joint Report of the 2 commissioners
expropriated but for the entire property whose potential was o NOTE: the 2 commissioners who submitted the Joint
greatly diminished, if not totally lost, due to the project; Report are gov’t EE, while the one who has a separate
 Their property is an industrial land report is a private lawyer representing the plaintif
 Ordered NAPOCOR to pay:  It is notable in that case that it was made subject to several
1. Just compen for the whole area (14K sq. m.) @ the rate of conditions in order to address the dispossession of the
P550/sqm defendants of their land, and the inconvenience, annoyance and
2. Legal rate of interest from May 5 until full payment damages suffered by the defendants on account of the
3. Costs of suit proceedings. Accordingly, the Court remanded the case to the
trial court for the issuance of a writ of possession ordering
CA DECISION: Affirmed but modified the area to be covered – 6,326 sqm Metropolitan Water District to immediately return possession of
NAPOCOR appealed. the land to the defendants, and for the determination of
damages in favor of the defendants, the claims for which must
During the pendency of the appeal, NAPOCOR filed a Motion to Defer be presented within 30 days from the return of the record to the
Proceedings stating that the negotiations were going on with a view of court of origin and notice thereof.
amicable settlement.
 HOWEVER, a year after, NAPOCOR filed a Manifestation and In this case, NAPOCOR seeks to discontinue the expropriation
Motion to DISCONTINUE Expropriation Proceedings as: proceedings on the ground that the transmission lines constructed on
o they failed to reach an agreement the respondents’ property had already been retired.
o property is no longer necessary for public purpose Verily, the retirement of the transmission lines necessarily
because of the intervening retirement of the transmission stripped the expropriation proceedings of the element of public
lines installed on the heirs’ property use. To continue with the expropriation proceedings despite the definite
o public purpose ceased to exist cessation of the public purpose of the project would result in the
o prayed that the compensation be reduced by the rendition of an invalid judgment in favor of the expropriator due to the
equivalent of the benefit they received from the land absence of the essential element of public use.
during the time of its occupation
o Basis in dismissing the proceedings: Metropolitan Water No board resolution to discontinue the proceedings
District vs. De Los Angeles, land sought to be Despite the lack of the board resolution, therefore, the Court now
expropriated was no longer “indispensably necessary” in considers the documents (such as the Memorandum &Certificate of
the maintenance and operation of petitioner’s Inspection/Accomplishment) attached to NAPOCOR’s Manifestation and
waterworks system Motion to Discontinue Expropriation Proceedings to be sufficient to
establish that the expropriation sought is no longer for some public
ISSUE: W/N THE EXPROPRIATTION PROCEEDINGS SHOULD BE purpose.
DISCONTINUED/DISMISSED PENDING APPEAL
NAPOCOR’s entry without the owner’s consent
SC: YES NAPOCOR entered the property without the owners’ consent and
without paying just compensation to the respondents. Neither did it
Public use is the fundamental basis for the action for expropriation; deposit any amount as required by law prior to its entry.
hence, NAPOCOR’s motion to discontinue the proceedings is warranted  It would be unfair for NAPOCOR not to be made liable to the
and should be granted. respondents for the disturbance of their property rights from the
time of entry until the time of restoration of the possession of
the property
As discussed in the case of Metropolitan Water District vs. De Los
Reyes:
Liability of NAPOCOR; Reckoning Point
The fundamental basis then of all actions brought for the expropriation
There is sufficient showing that NAPOCOR entered into and took
of lands, under the power of eminent domain, is public use. That being
possession of the property as early as in March 1993 without the benefit
true, the very moment that it appears at any stage of the
of first filing a petition for eminent domain.
proceedings that the expropriation is not for a public use, the
action must necessarily fail and should be dismissed, for the  For all intents and purposes, therefore, March 1993 is the
reason that the action cannot be maintained at all except when reckoning point of NAPOCOR’s taking of the property, instead of
the expropriation is for some public use. That must be true May 5, 1995, the time NAPOCOR filed the petition for
even during the pendency of the appeal or at any other stage of expropriation. (Basis: Ansaldo vs. Tantuico)
the proceedings.
No just compensation, only damages
In view of the discontinuance of the proceedings and the eventual Basis of damages
return of the property to the respondents, there is no need to pay “just Basis would be the actual lost as a result and by reason of their
compensation” to them because their property would not be taken by dispossession of the property and of its use, including the value of the
NAPOCOR. fruit trees, plants and crops destroyed by NAPOCOR’s construction of
 Instead of full market value, NAPOCOR should compensate the the transmission lines
respondents for the disturbance of their property rights from the
time of entry in March 1993 until the time of restoration of the Conversion of the proceedings: Expropriation Proceedings  Action for
possession by paying to them actual or other compensatory Damages
damages. (Basis: MactanCebu International Airport Authority v. Court remands the case to the court of origin for further proceedings,
Lozada, Sr.) with instruction to enable the parties to fully litigate the action for
damages.

Anda mungkin juga menyukai