649,279,260.72
JUMLAH 655,769,740.72
PPN 10 % 65,576,974.07
JUMLAH TOTAL 721,346,714.79
DIBULATKAN 721,340,000.00
TERBILANG : Err:511
6,490,480.00
B PEKERJAAN PELAKSANAAN
I PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m 58.62 m3 A.2.3.1.1 62,875.00 3,685,826.81
2 Pengurugan Kembali 14.70 m3 A.2.3.1.9 15,250.00 224,098.75
3,909,925.56
II PEKERJAAN PONDASI
1 Pemasang Batu Kosong/Anstamping 10.85 m3 A.3.2.1.9 452,513.40 4,907,507.82
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 21.09 m3 A.3.2.1.5.1 899,089.00 18,959,539.29
3 Pasang Pondasi Rolag Trashraam BT Mrh 1 Pc : 3 Ps 0.22 m3 A.3.2.1.12 1,207,075.00 267,970.65
4 Urugan Pasir Bawah Pondasi 2.71 m3 A.2.3.1.11 194,484.38 527,295.76
24,662,313.52
III PEKERJAAN PASANGAN DINDING
1 Pasang Din Bt Mrh Kalipucang tbl 1/2 bt 1 SP:8PP Muntilan 336.20 m2 A.4.4.1.12.2 110,750.00 37,234,537.63
37,234,537.63
IV PEKERJAAN PLESTERAN
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan 79.19 m2 A.4.4.2.3 64,000.20 5,068,367.84
2 Pasang Plesteran 1 Pc : 8 Pp tbl 15 mm Ps Muntilan 672.41 m2 A.4.4.2.19 40,516.80 27,243,779.94
3 Pemasangan Acian 672.41 m2 A.4.4.2.27 32,962.50 22,164,215.74
54,476,363.51
V PEKERJAAN BETON
1 Membuat Beton mutu f'c=7,4 Mpa (K100) 0.89 m3 A.4.1.1.1 973,662.43 868,506.89
2 Membuat Foot Plat 100x100
a Membuat Beton mutu MPa (K225) 1.50 m3 A.4.1.1.7 1,106,174.59 1,659,261.88
b Pembesian dg Besi Polos atau Besi Ulir 212.31 kg A.4.1.1.17 13,683.00 2,904,983.39
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 6.00 m2 A.4.1.1.37 99,770.00 598,620.00
3 Membuat Foot Plat 80x80
a Membuat Beton mutu MPa (K225) 0.96 m3 A.4.1.1.7 1,106,174.59 1,061,927.60
b Pembesian dg Besi Polos atau Besi Ulir 103.08 kg A.4.1.1.17 13,683.00 1,410,427.22
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 4.80 m2 A.4.1.1.37 99,770.00 478,896.00
4 Membuat Sloof Beton Bertulang 20x30
a Membuat Beton mutu MPa (K225) 3.98 m3 A.4.1.1.7 1,106,174.59 4,403,681.03
b Pembesian dg Besi Polos atau Besi Ulir 537.08 kg A.4.1.1.17 13,683.00 7,348,933.18
c Memasang Bekisting untuk Sloof 39.81 m2 A.4.1.1.21 137,576.25 5,476,910.51
5 Membuat Kolom Beton Bertulang 30x30
a Membuat Beton mutu MPa (K225) 3.13 m3 A.4.1.1.7 1,106,174.59 3,464,538.81
b Pembesian dg Besi Polos atau Besi Ulir 361.57 kg A.4.1.1.17 13,683.00 4,947,427.77
c Memasang Bekisting untuk Kolom 41.76 m2 A.4.1.1.22 205,045.00 8,562,679.20
6 Membuat Beton bertulang Kolom Praktis 11x11 cm 147.85 m1 A.4.1.1.35 69,841.10 10,326,006.64
7 Membuat Kolom Beton Bertulang 20x20
a Membuat Beton mutu MPa (K225) 1.39 m3 A.4.1.1.7 1,106,174.59 1,539,795.03
b Pembesian dg Besi Polos atau Besi Ulir 201.38 kg A.4.1.1.17 13,683.00 2,755,529.39
c Memasang Bekisting untuk Kolom 26.45 m2 A.4.1.1.22 205,045.00 5,423,030.16
8 Membuat Balok Beton Bertulang 15x30
a Membuat Beton mutu MPa (K225) 0.86 m3 A.4.1.1.7 1,106,174.59 955,734.84
b Pembesian dg Besi Polos atau Besi Ulir 146.21 kg A.4.1.1.17 13,683.00 2,000,566.17
c Memasang Bekisting untuk Kolom 16.51 m2 A.4.1.1.22 205,045.00 3,385,703.04
9 Membuat Balok Beton Bertulang 20x40 (B1)
a Membuat Beton mutu MPa (K225) 2.48 m3 A.4.1.1.7 1,106,174.59 2,743,312.98
b Pembesian dg Besi Polos atau Besi Ulir 428.91 kg A.4.1.1.17 13,683.00 5,868,816.91
c Memasang Bekisting untuk Kolom 29.76 m2 A.4.1.1.23 208,045.00 6,191,419.20
10 Membuat Balok Beton Bertulang 20x30 (B2)
a Membuat Beton mutu MPa (K225) 1.77 m3 A.4.1.1.7 1,106,174.59 1,957,929.02
b Pembesian dg Besi Polos atau Besi Ulir 314.47 kg A.4.1.1.17 13,683.00 4,302,914.27
c Memasang Bekisting untuk Balok 22.42 m2 A.4.1.1.23 208,045.00 4,664,368.90
11 Membuat Balok Beton Bertulang 15x30 (B4)
a Membuat Beton mutu MPa (K225) 3.80 m3 A.4.1.1.7 1,106,174.59 4,206,228.87
b Pembesian dg Besi Polos atau Besi Ulir 652.72 kg A.4.1.1.17 13,683.00 8,931,140.09
c Memasang Bekisting untuk Balok 60.00 m2 A.4.1.1.23 208,045.00 12,481,659.78
12 Membuat Balok Beton Bertulang 15x20 (B3)
a Membuat Beton mutu MPa (K225) 1.65 m3 A.4.1.1.7 1,106,174.59 1,821,869.55
b Pembesian dg Besi Polos atau Besi Ulir 217.94 kg A.4.1.1.17 13,683.00 2,982,007.56
c Memasang Bekisting untuk Balok 18.67 m2 A.4.1.1.23 208,045.00 3,883,367.97
13 Membuat Latiu Balok Beton Bertulang (10 x 15) cm 38.86 m1 A.4.1.1.36 109,298.81 4,247,351.85
14 Membuat Ring Balok Beton Bertulang 15 x 20 cm
a Membuat Beton mutu MPa (K225) 0.60 m3 A.4.1.1.7 1,106,174.59 663,704.75
b Pembesian dg Besi Polos atau Besi Ulir 70.49 kg A.4.1.1.17 13,683.00 964,485.90
c Memasang Bekisting untuk Balok 8.00 m2 A.4.1.1.23 208,045.00 1,664,360.00
15 Membuat Dak Plat Beton tbl 12 cm
a Membuat Beton mutu MPa (K225) 15.37 m3 A.4.1.1.7 1,106,174.59 17,001,682.17
b Pembesian dg Besi Polos atau Besi Ulir 2028.26 kg A.4.1.1.17 13,683.00 27,752,686.23
c Memasang Bekisting untuk Lantai 15.37 m2 A.4.1.1.24 205,645.00 3,160,722.52
185,063,187.25
VI PEKERJAAN TANGGA BETON BERTULANG
1 Membuat Balok Beton Bertulang 15x30 (B4)
a Membuat Beton mutu MPa (K225) 0.78 m3 A.4.1.1.7 1,106,174.59 859,165.80
b Pembesian dg Besi Polos atau Besi Ulir 133.97 kg A.4.1.1.17 13,683.00 1,833,100.09
c Memasang Bekisting untuk Balok 12.25 m2 A.4.1.1.23 208,045.00 2,549,508.26
3 Membuat Plat Tangga
a Membuat Beton mutu MPa (K225) 0.00 m3 A.4.1.1.7 1,106,174.59 -
b Pembesian dg Besi Polos atau Besi Ulir 0.77 kg A.4.1.1.17 13,683.00 10,535.91
c Memasang Bekisting untuk Lantai 0.00 m2 A.4.1.1.21 137,576.25 -
2 Membuat Plat Tangga
a Membuat Beton mutu MPa (K225) 3.24 m3 A.4.1.1.7 1,106,174.59 3,585,664.92
b Pembesian dg Besi Polos atau Besi Ulir 849.82 kg A.4.1.1.17 13,683.00 11,628,151.37
c Memasang Bekisting untuk Lantai 23.89 m2 A.4.1.1.24 205,645.00 4,911,830.83
25,377,957.18
VII PEKERJAAN PENUTUP ATAP
1 Pasang Kasau & Reng Kayu Kruing (SNI) 77.90 m2 A.4.6.1.30 115,419.38 8,991,169.31
80,109,013.39
VIII PEKERJAAN LANGIT - LANGIT
1 Pemasangan 1 m2 rangka besi hollow 1x40.40.0.6 mm, modul 60 x 60 cm, plafon
92.16 m2 A.4.2.1.21 116,945.00 10,777,534.26
2 Memasang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm 92.16 m2 A.4.5.1.7 39,215.00 3,614,015.19
3 List Langit-Langit Kayu Profil 145.18 m1 A.4.5.1.10 20,523.00 2,979,529.14
17,371,078.58
IX PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pemasangan lantai Ubin Granitile Uk. 60 x 60 cm 190.81 m2 A.4.4.3.9 302,949.00 57,807,031.67
2 Pemasangan Lantai Keramik 20 x 20 cm 5.84 m2 A.4.4.3.36 206,645.00 1,206,393.51
3 Pemasangan Dinding Keramik 20x25 cm, 28.19 m2 A.4.4.3.55 225,990.00 6,370,658.10
4 Pemasangan Lantai Keramik 30 x 30 cm warna 2.01 m2 A.4.4.3.35 201,479.00 404,972.79
ng tebal 6 cm5dengan paving mutu K 225 (SNI) 15.68 m2 A.4.4.3.65 170,746.88 2,676,457.27
68,465,513.33
X PEKERJAAN BESI dan ALUMUNIUM
1 Pemasangan Kusen Pintu Allumunium 64.12 m1 A.4.2.1.11 126,524.50 8,112,750.94
2 Pasang Kusen Jendela Alumunium 85.60 m1 A.4.2.1.11 126,524.50 10,830,497.20
3 Pasang Daun Pintu dan Jendela Kaca Alumunium 58.36 m2 A.4.2.1.13 477,020.00 27,836,597.50
4 Pemasangan Pintu Allumunium Strip Lebar 8 cm 1.23 m2 A.4.2.1.12 971,578.00 1,195,040.94
5 Pemasangan Kaca tebal 5 mm 122.45 m2 A.4.6.2.17 149,936.25 18,359,543.88
6 Pemasangan 1 m2 terali besi strip (2 x 3) mm 37.46 m2 A.4.2.1.15 504,106.02 18,881,290.98
85,215,721.44
XI PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex 672.41 m2 A.4.7.1.11.2 42,072.75 28,290,011.61
2 Pengecat 1m2 Waterproof untuk atap dag beton 84.16 m2 A.4.7.1.24 26,438.00 2,225,088.18
3 Pengecat Plafond Baru dengan Mowilex 92.16 m2 A.4.7.1.10.1 26,998.00 2,488,108.68
33,003,208.47
XII PEKERJAAN AKSESORIS
1 Pemasangan Kunci Tanam Biasa 1.00 bh A.4.6.2.2 134,075.00 134,075.00
2 Pemasangan Kunci Kamar Mandi 1.00 bh A.4.6.2.3 102,587.50 102,587.50
3 Pemasangan Engsel Pintu 3.00 bh A.4.6.2.5 44,042.00 132,126.00
4 Pemasangan Engsel Jendela Kupu-kupu 6.00 bh A.4.6.2.6 30,457.50 182,745.00
5 Pemasangan Kait Angin 6.00 bh A.4.6.2.9 25,670.00 154,020.00
705,553.50
XIII PEKERJAAN SANITASI
1 Pemasangan 1 m pipa PVC Ø 25 mm (1") 32.00 m1 A.8.4.1.1.1 31,636.36 1,012,363.64
2 Pemasangan 1 m pipa PVC Ø 50 mm (2") 23.00 m1 A.8.4.1.1 69,255.00 1,592,865.00
3 Pemasangan 1 m pipa PVC Ø 90 mm (4") 18.00 m1 A.8.4.1.3 90,335.00 1,626,030.00
4 Pemasangan Kran Ø ½" atau Ø ¾" 7.00 bh A.5.1.1.19 71,577.50 501,042.50
5 Pemasangan Bak Cuci Piring Stainless stell 1.00 bh A.5.1.1.12 273,525.00 273,525.00
6 Memasang Closet Jongkok Porselen 3.00 bh A.5.1.1.2 413,157.50 1,239,472.50
7 Septiktank Buis Beton 3.00 bh Dihitung 3,892,659.63 11,677,978.89
8 Resapan Air kotor Buis Beton 1.00 bh Dihitung 2,749,434.84 2,749,434.84
9 Tandon Air 1000 L 1.00 bh Taksir 1,500,000.00 1,500,000.00
10 Pemasangan Kran Shower Mandi 2.00 bh Taksir 500,000.00 1,000,000.00
11 Ember Air 3.00 bh Taksir 50,000.00 150,000.00
12 Pemasangan Floor Drain 5.00 bh A.5.1.1.14 35,575.00 177,875.00
13 Pemasangan Pipa PVC tipe AW Ø 3" 17.50 m1 A.5.1.1.31 67,960.00 1,189,300.00
24,689,887.36
XIV PEKERJAAN LISTRIK
1 Pasang Meteran Listrik 2000VA 1.00 bh Taksir 2,000,000.00 2,000,000.00
2 Pasang Instalasi Listrik 43.00 ttk Taksir 80,000.00 3,440,000.00
3 Pasang Lampu LED 15 watt 19.00 bh Taksir 40,000.00 760,000.00
4 Pasang Lampu LED 20 watt 11.00 bh Taksir 60,000.00 660,000.00
5 Pasang Saklar Ganda 11.00 bh Taksir 25,000.00 275,000.00
6 Pasang Stop Kontak 12.00 bh Taksir 30,000.00 360,000.00
7 Pasang Mesin Pompa Air Jet Pump Otomatis 1.00 bh Taksir 1,500,000.00 1,500,000.00
8,995,000.00
TOTAL 655,769,740.72
PPN 10 % 65,576,974.07
JUMLAH TOTAL 721,346,714.79
DIBULATKAN 721,340,000.00
TERBILANG :
Err:511
I PEKERJAAN PERSIAPAN
P L T Q PxLxTxQ total sat
1 Membersihkan Lapangan dan Perataan
8.00 x 10.00 x 1.00 = 80.00
= 80.00 m1
2 Pengukuran dan Pemasangan Bouwplank = 80.00 m1
3 Air Kerja = 1.00 Ls
B PEKERJAAN PELAKSANAAN
I PEKERJAAN TANAH
P L T Q PxLxTxQ unit total sat
1 Menggali Tanah Biasa Sedalam 1 m
a. Mengali foot plat 1.00 x 1.00 x 2.10 x 6.00 = 12.60 1.00 = 12.60
0.80 x 0.80 x 2.10 x 6.00 = 8.06 1.00 = 8.06
b. Mengali pondasi
- Pondasi A 27.00 x 0.90 x 0.70 x 1.00 = 17.01 1.00 = 17.01
x x x = - = -
- Pondasi B 33.25 x 0.90 x 0.70 x 1.00 = 20.95 1.00 = 20.95
= 58.62 m3
2 Pengurugan Kembali = 14.70 m3
footplat - 0.70 x 0.70 x 1.70 x 6.00 = 5.00
0.60 x 0.60 x 1.70 x 6.00 = 3.67
Pondasi - 27.00 x 0.90 x 0.70 x 1.00 = 17.01
33.25 x 0.90 x 0.70 x 1.00 = 20.95
Dikurang 46.63
Pondasi - 21.09
Anstamping - 10.85 = 31.93 -
14.70
II PEKERJAAN PONDASI
P L T Q PxLxTxQ total sat
IV PEKERJAAN PLESTERAN
P L T Q PxLxTxQ total sat
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan
Lantai 1
a. kolom 30x30 2.74 2.30 x 4 = 25.21 = 25.21
b. kolom 15x15 0.30 x 3.7 10.00 = 11.10 = 11.10
0.30 x 2.4 2.00 = 1.44 = 1.44
0.30 x 1.65 1.00 = 0.50 = 0.50
c. kolom 20x20 1.95 1.05 x 4 = 8.19 = 8.19
Lainai 2 =
kolom 15x30 3.00 0.45 3.2 1.00 = 1.44 = 1.44
kolom 15x15 0.3 3.2 20.00 = 19.20 = 19.20
Lantai 3 = - =
kolom 15x15 0.3 3.5 8.00 = 8.40 = 8.40
0.3 2 5.00 = 3.00 = 3.00
0.3 0.6 4.00 = 0.72 = 0.72
79.19 m2
13 Membuat Latiu Balok Beton Bertulang (10 x 15) cm 14.64 x 1.00 = 14.64 = 38.86 m1
21.87 x 1.00 = 21.87
2.35 x 1.00 = 2.35
14 Membuat Ring Balok Beton Bertulang 15 x 20 cm 20.00 x 1.00 = 20.00 1.00 = 20.00 m1
P L T Q PxLxTxQ total sat
Membuat Beton mutu MPa (K225) 20.00 x 0.15 x 0.20 x 1.00 = 0.60 1.00 = 0.60 m3
Pembesian dg Besi Polos atau Besi Ulir P jmlh bj
- tulangan pokok 20.00 x 4.00 x 0.62 x 1.00 = 49.32 1.00 = 49.32
- begel 0.71 x 134 x 0.22 x 1.00 = 21.17 1.00 = 21.17
70.49 kg
Memasang Bekisting untuk Balok 0.40 x 20.00 x 1.00 = 8.00 1.00 = 8.00 m2
92.16
lt. 2 -
lodir room 1.50 x 1.60 - 0.011 = 2.39
tama 5.35 x 4.85 - 3.700 = 22.25
kamar 1 2.60 x 2.85 - = 7.41
kamar 2 3.35 x 2.85 - = 9.55
1.35 x 1.60 - = 2.16
kamar 3 2.35 x 2.85 - x 2.00 = 13.40
balkon 1.35 x 4.75 - = 6.41
-
lt. 3 -
gudang + jemur 7.00 x 8.35 - 4.39 = 54.06
Tangga -
Antrean 0.30 x 1.00 37.00 = 11.10
Optrade 0.20 x 1.00 37.00 = 7.40
Bordes 1.00 x 1.00 2.00 = 2.00
190.81
B PEKERJAAN PELAKSANAAN
I PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m 58.62 m3 A.2.3.1.1 62,875.00 3,685,826.81 0.5621
2 Pengurugan Kembali 14.70 m3 A.2.3.1.9 15,250.00 224,098.75 0.0342
II PEKERJAAN PONDASI
1 Pemasang Batu Kosong/Anstamping 10.85 m3 A.3.2.1.9 452,513.40 4,907,507.82 0.7484
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 21.09 m3 A.3.2.1.5.1 899,089.00 18,959,539.29 2.8912
3 Pasang Pondasi Rolag Trashraam BT Mrh 1 Pc : 3 Ps 0.22 m3 A.3.2.1.12 1,207,075.00 267,970.65 0.0409
4 Urugan Pasir Bawah Pondasi 2.71 m3 A.2.3.1.11 194,484.38 527,295.76 0.0804
IV PEKERJAAN PLESTERAN
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan 79.19 m2 A.4.4.2.3 64,000.20 5,068,367.84 0.7729
2 Pasang Plesteran 1 Pc : 8 Pp tbl 15 mm Ps Muntilan 672.41 m2 A.4.4.2.19 40,516.80 27,243,779.94 4.1545
3 Pemasangan Acian 672.41 m2 A.4.4.2.27 32,962.50 22,164,215.74 3.3799
V PEKERJAAN BETON
1 Membuat Beton mutu f'c=7,4 Mpa (K100) 0.89 m3 A.4.1.1.1 973,662.43 868,506.89 0.1324
2 Membuat Foot Plat 100x100
a Membuat Beton mutu MPa (K225) 1.50 m3 A.4.1.1.7 1,106,174.59 1,659,261.88 0.2530
b Pembesian dg Besi Polos atau Besi Ulir 212.31 kg A.4.1.1.17 13,683.00 2,904,983.39 0.4430
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 6.00 m2 A.4.1.1.37 99,770.00 598,620.00 0.0913
3 Membuat Foot Plat 80x80
a Membuat Beton mutu MPa (K225) 0.96 m3 A.4.1.1.7 1,106,174.59 1,061,927.60 0.1619
b Pembesian dg Besi Polos atau Besi Ulir 103.08 kg A.4.1.1.17 13,683.00 1,410,427.22 0.2151
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 4.80 m2 A.4.1.1.37 99,770.00 478,896.00 0.0730
4 Membuat Sloof Beton Bertulang 20x30
a Membuat Beton mutu MPa (K225) 3.98 m3 A.4.1.1.7 1,106,174.59 4,403,681.03 0.6715
b Pembesian dg Besi Polos atau Besi Ulir 537.08 kg A.4.1.1.17 13,683.00 7,348,933.18 1.1207
c Memasang Bekisting untuk Sloof 39.81 m2 A.4.1.1.21 137,576.25 5,476,910.51 0.8352
5 Membuat Kolom Beton Bertulang 30x30 0.0000
a Membuat Beton mutu MPa (K225) 3.13 m3 A.4.1.1.7 1,106,174.59 3,464,538.81 0.5283
b Pembesian dg Besi Polos atau Besi Ulir 361.57 kg A.4.1.1.17 13,683.00 4,947,427.77 0.7544
c Memasang Bekisting untuk Kolom 41.76 m2 A.4.1.1.22 205,045.00 8,562,679.20 1.3057
6 Membuat Beton bertulang Kolom Praktis 11x11 cm 147.85 m1 A.4.1.1.35 69,841.10 10,326,006.64 1.5746
7 Membuat Kolom Beton Bertulang 20x20
a Membuat Beton mutu MPa (K225) 1.39 m3 A.4.1.1.7 1,106,174.59 1,539,795.03 0.2348
b Pembesian dg Besi Polos atau Besi Ulir 201.38 kg A.4.1.1.17 13,683.00 2,755,529.39 0.4202
c Memasang Bekisting untuk Kolom 26.45 m2 A.4.1.1.22 205,045.00 5,423,030.16 0.8270
8 Membuat Balok Beton Bertulang 15x30
a Membuat Beton mutu MPa (K225) 0.86 m3 A.4.1.1.7 1,106,174.59 955,734.84 0.1457
b Pembesian dg Besi Polos atau Besi Ulir 146.21 kg A.4.1.1.17 13,683.00 2,000,566.17 0.3051
c Memasang Bekisting untuk Kolom 16.51 m2 A.4.1.1.22 205,045.00 3,385,703.04 0.5163
9 Membuat Balok Beton Bertulang 20x40 (B1)
a Membuat Beton mutu MPa (K225) 2.48 m3 A.4.1.1.7 1,106,174.59 2,743,312.98 0.4183
b Pembesian dg Besi Polos atau Besi Ulir 428.91 kg A.4.1.1.17 13,683.00 5,868,816.91 0.8950
c Memasang Bekisting untuk Kolom 29.76 m2 A.4.1.1.23 208,045.00 6,191,419.20 0.9441
10 Membuat Balok Beton Bertulang 20x30 (B2)
a Membuat Beton mutu MPa (K225) 1.77 m3 A.4.1.1.7 1,106,174.59 1,957,929.02 0.2986
b Pembesian dg Besi Polos atau Besi Ulir 314.47 kg A.4.1.1.17 13,683.00 4,302,914.27 0.6562
c Memasang Bekisting untuk Balok 22.42 m2 A.4.1.1.23 208,045.00 4,664,368.90 0.7113
11 Membuat Balok Beton Bertulang 15x30 (B4) 0.0000
a Membuat Beton mutu MPa (K225) 3.80 m3 A.4.1.1.7 1,106,174.59 4,206,228.87 0.6414
b Pembesian dg Besi Polos atau Besi Ulir 652.72 kg A.4.1.1.17 13,683.00 8,931,140.09 1.3619
c Memasang Bekisting untuk Balok 60.00 m2 A.4.1.1.23 208,045.00 12,481,659.78 1.9034
12 Membuat Balok Beton Bertulang 15x20 (B3)
a Membuat Beton mutu MPa (K225) 1.65 m3 A.4.1.1.7 1,106,174.59 1,821,869.55 0.2778
b Pembesian dg Besi Polos atau Besi Ulir 217.94 kg A.4.1.1.17 13,683.00 2,982,007.56 0.4547
c Memasang Bekisting untuk Balok 18.67 m2 A.4.1.1.23 208,045.00 3,883,367.97 0.5922
13 Membuat Latiu Balok Beton Bertulang (10 x 15) cm 38.86 m1 A.4.1.1.36 109,298.81 4,247,351.85 0.6477
14 Membuat Ring Balok Beton Bertulang 15 x 20 cm
a Membuat Beton mutu MPa (K225) 0.60 m3 A.4.1.1.7 1,106,174.59 663,704.75 0.1012
b Pembesian dg Besi Polos atau Besi Ulir 70.49 kg A.4.1.1.17 13,683.00 964,485.90 0.1471
c Memasang Bekisting untuk Balok 8.00 m2 A.4.1.1.23 208,045.00 1,664,360.00 0.2538
15 Membuat Dak Plat Beton tbl 12 cm
a Membuat Beton mutu MPa (K225) 15.37 m3 A.4.1.1.7 1,106,174.59 17,001,682.17 2.5926
b Pembesian dg Besi Polos atau Besi Ulir 2028.26 kg A.4.1.1.17 13,683.00 27,752,686.23 4.2321
c Memasang Bekisting untuk Lantai 15.37 m2 A.4.1.1.24 205,645.00 3,160,722.52 0.4820
2 Pemasangan Atap Genteng Kodok / lokal 77.90 m2 A.4.5.2.2 60,525.00 4,714,897.50 0.7190
3 Pemasangan 1 m2 Dinding Lambriziring dari Papan Kayu Jati 155.80 m2 A.4.6.1.26 419,180.63 65,308,341.38 9.9590
4Pemasangan 1 m2 rangka besi hollow 1x40.40.0.6 mm, modul 60 x 60 cm, plafon
9.36 m3 A.4.2.1.21 116,945.00 1,094,605.20 0.1669
XI PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex 672.41 m2 A.4.7.1.11.2 42,072.75 28,290,011.61 4.3140
2 Pengecat 1m2 Waterproof untuk atap dag beton 84.16 m2 A.4.7.1.24 26,438.00 2,225,088.18 0.3393
3 Pengecat Plafond Baru dengan Mowilex 92.16 m2 A.4.7.1.10.1 26,998.00 2,488,108.68 0.3794
XII PEKERJAAN AKSESORIS
1 Pemasangan Kunci Tanam Biasa 1.00 bh A.4.6.2.2 134,075.00 134,075.00 0.0204
2 Pemasangan Kunci Kamar Mandi 1.00 bh A.4.6.2.3 102,587.50 102,587.50 0.0156
3 Pemasangan Engsel Pintu 3.00 bh A.4.6.2.5 44,042.00 132,126.00 0.0201
4 Pemasangan Engsel Jendela Kupu-kupu 6.00 bh A.4.6.2.6 30,457.50 182,745.00 0.0279
5 Pemasangan Kait Angin 6.00 bh A.4.6.2.9 25,670.00 154,020.00 0.0235
100.00
RENCANA ANGGARAN BIAYA
KEGIATAN
LOGIKA KETERGANTUNGAN
A PEKERJAAN PERSIAPAN
1 Membersihkan Lapangan dan Perataan A1 0
2 Pengukuran dan Pemasangan Bouwplank A2 A1
3 Air Kerja A3 0 -
B PEKERJAAN PELAKSANAAN
I PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m I1 A2
2 Pengurugan Kembali I2 III 1
II PEKERJAAN PONDASI
1 Pemasang Batu Kosong/Anstamping II 1 II 4
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan II 2 II 3
3 Pasang Pondasi Rolag Trashraam BT Mrh 1 Pc : 3 Ps II 3 II 2
4 Urugan Pasir Bawah Pondasi II 4 I1
IV PEKERJAAN PLESTERAN
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan IV 1 VII 4
2 Pasang Plesteran 1 Pc : 8 Pp tbl 15 mm Ps Muntilan IV 2 IV 1
3 Pemasangan Acian IV 3 IV 1
V PEKERJAAN BETON
1 Membuat Beton mutu f'c=7,4 Mpa (K100) V1 V1
2 Membuat Foot Plat 100x100
a Membuat Beton mutu MPa (K225) V 2A V 2C
b Pembesian dg Besi Polos atau Besi Ulir V 2B II 1
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm V 2C V 2B
3 Membuat Foot Plat 80x80
a Membuat Beton mutu MPa (K225) V 3A V 3C
b Pembesian dg Besi Polos atau Besi Ulir V 3B II 1
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm V 3C V 3B
4 Membuat Sloof Beton Bertulang 20x30
a Membuat Beton mutu MPa (K225) V 4A V 4C
b Pembesian dg Besi Polos atau Besi Ulir V 4B V 4B
c Memasang Bekisting untuk Sloof V 4C V 4B
5 Membuat Kolom Beton Bertulang 30x30
a Membuat Beton mutu MPa (K225) V 5A V 5C
b Pembesian dg Besi Polos atau Besi Ulir V 5B V 4B
c Memasang Bekisting untuk Kolom V 5C V 5B
6 Membuat Beton bertulang Kolom Praktis 11x11 cm V6 III 1
7 Membuat Kolom Beton Bertulang 20x20
a Membuat Beton mutu MPa (K225) V 7A V 7C
b Pembesian dg Besi Polos atau Besi Ulir V 7B V 5B
c Memasang Bekisting untuk Kolom V 7C V 7B
8 Membuat Balok Beton Bertulang 15x30
a Membuat Beton mutu MPa (K225) V 8A V 8A
b Pembesian dg Besi Polos atau Besi Ulir V 8B V 8B
c Memasang Bekisting untuk Kolom V8C V8C
9 Membuat Balok Beton Bertulang 20x40 (B1)
a Membuat Beton mutu MPa (K225) V 9A V 8A
b Pembesian dg Besi Polos atau Besi Ulir V 9B V 9B
c Memasang Bekisting untuk Kolom V 9C V 9C
10 Membuat Balok Beton Bertulang 20x30 (B2)
a Membuat Beton mutu MPa (K225) V 10A V 9A
b Pembesian dg Besi Polos atau Besi Ulir V 10B V 9B
c Memasang Bekisting untuk Balok V 10C V 9C
11 Membuat Balok Beton Bertulang 15x30 (B4)
a Membuat Beton mutu MPa (K225) V 11A V 15A
b Pembesian dg Besi Polos atau Besi Ulir V 11B V 15B
c Memasang Bekisting untuk Balok V 11C V 15C
12 Membuat Balok Beton Bertulang 15x20 (B3)
a Membuat Beton mutu MPa (K225) V 12A V 10A
b Pembesian dg Besi Polos atau Besi Ulir V 12B V 10B
c Memasang Bekisting untuk Balok V 12C V 10C
13 Membuat Latiu Balok Beton Bertulang (10 x 15) cm V 13 V6
14 Membuat Ring Balok Beton Bertulang 15 x 20 cm
a Membuat Beton mutu MPa (K225) V 14A V 14C
b Pembesian dg Besi Polos atau Besi Ulir V 14B III 1
c Memasang Bekisting untuk Balok V 14C V 14B
15 Membuat Dak Plat Beton tbl 12 cm
a Membuat Beton mutu MPa (K225) V 15A V 12A
b Pembesian dg Besi Polos atau Besi Ulir V 15B V 10B
c Memasang Bekisting untuk Lantai V 15C V 10C
XI PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex XI 1 XI 3
2 Pengecat 1m2 Waterproof untuk atap dag beton XI 2 VII 2
3 Pengecat Plafond Baru dengan Mowilex XI 3 XI 1
XII PEKERJAAN AKSESORIS
1 Pemasangan Kunci Tanam Biasa XII 1 XII 1
2 Pemasangan Kunci Kamar Mandi XII 2 XII 4
3 Pemasangan Engsel Pintu XII 3 XII 1
4 Pemasangan Engsel Jendela Kupu-kupu XII 4 XII 2
5 Pemasangan Kait Angin XII 5 XII 3
- 8,995,000.00
655,769,740.72
65,576,974.07
721,346,714.79
721,340,000.00
TERBILANG :
Err:511
Diperiksa Oleh :
DOSEN UNISNU JEPARA
Management Proyek
B PEKERJAAN PELAKSANAAN
I PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m 58.62 m3 A.2.3.1.1 0.75 0.025
2 Pengurugan Kembali 14.70 m3 A.2.3.1.9 0.5000 0.0500
II PEKERJAAN PONDASI
1 Pemasang Batu Kosong/Anstamping 10.85 m3 A.3.2.1.9 0.7800 0.0390 0.0390 0.3900
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 21.09 m3 A.3.2.1.5.1 1.5000 0.0750 0.0750 0.7500
3 Pasang Pondasi Rolag Trashraam BT Mrh 1 Pc : 3 Ps 0.22 m3 A.3.2.1.12 4.5000 0.1500 0.2250 1.5000
4 Urugan Pasir Bawah Pondasi 2.71 m3 A.2.3.1.11 0.3000 0.0100
IV PEKERJAAN PLESTERAN
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan 79.19 m2 A.4.4.2.3 0.3000 0.0150 0.0150 0.1500
2 Pasang Plesteran 1 Pc : 8 Pp tbl 15 mm Ps Muntilan 672.41 m2 A.4.4.2.19 0.1500 0.0080 0.0080 0.0750
3 Pemasangan Acian 672.41 m2 A.4.4.2.27 0.2000 0.0100 0.0100 0.1000
V PEKERJAAN BETON
1 Membuat Beton mutu f'c=7,4 Mpa (K100) 0.89 m3 A.4.1.1.1 1.65 0.028 0.083 0.275
2 Membuat Foot Plat 100x100
a Membuat Beton mutu MPa (K225) 1.50 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 212.31 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 6.00 m2 A.4.1.1.37 0.2 0.05 0.01 0.5
3 Membuat Foot Plat 80x80
a Membuat Beton mutu MPa (K225) 0.96 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 103.08 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 4.80 m2 A.4.1.1.37 0.2 0.05 0.01 0.5
4 Membuat Sloof Beton Bertulang 20x30
a Membuat Beton mutu MPa (K225) 3.98 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 537.08 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Memasang Bekisting untuk Sloof 39.81 m2 A.4.1.1.21 0.52 0.026 0.026 0.26
5 Membuat Kolom Beton Bertulang 30x30
a Membuat Beton mutu MPa (K225) 3.13 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 361.57 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Memasang Bekisting untuk Kolom 41.76 m2 A.4.1.1.22 0.66 0.033 0.033 0.33
6 Membuat Beton bertulang Kolom Praktis 11x11 cm 147.85 m1 A.4.1.1.35 0.18 0.006 0.009 0.02 0.02 0.02
7 Membuat Kolom Beton Bertulang 20x20
a Membuat Beton mutu MPa (K225) 1.39 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 201.38 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Memasang Bekisting untuk Kolom 26.45 m2 A.4.1.1.22 0.66 0.033 0.033 0.33
8 Membuat Balok Beton Bertulang 15x30
a Membuat Beton mutu MPa (K225) 0.86 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 146.21 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Memasang Bekisting untuk Kolom 16.51 m2 A.4.1.1.22 0.66 0.033 0.033 0.33
9 Membuat Balok Beton Bertulang 20x40 (B1)
a Membuat Beton mutu MPa (K225) 2.48 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 428.91 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Memasang Bekisting untuk Balok 29.76 m2 A.4.1.1.23 0.66 0.033 0.033 0.33
10 Membuat Balok Beton Bertulang 20x30 (B2)
a Membuat Beton mutu MPa (K225) 1.77 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 314.47 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Memasang Bekisting untuk Balok 22.42 m2 A.4.1.1.23 0.66 0.033 0.033 0.33
11 Membuat Balok Beton Bertulang 15x30 (B4)
a Membuat Beton mutu MPa (K225) 3.80 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 652.72 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Memasang Bekisting untuk Balok 60.00 m2 A.4.1.1.23 0.66 0.033 0.033 0.33
12 Membuat Balok Beton Bertulang 15x20 (B3)
a Membuat Beton mutu MPa (K225) 1.65 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 217.94 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Memasang Bekisting untuk Balok 18.67 m2 A.4.1.1.23 0.66 0.033 0.033 0.33
13 Membuat Latiu Balok Beton Bertulang (10 x 15) cm 38.86 m1 A.4.1.1.36 0.297 0.01 0.015 0.033 0.033 0.033
14 Membuat Ring Balok Beton Bertulang 15 x 20 cm
a Membuat Beton mutu MPa (K225) 0.60 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 70.49 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Memasang Bekisting untuk Balok 8.00 m2 A.4.1.1.23 0.66 0.033 0.033 0.33
15 Membuat Dak Plat Beton tbl 12 cm
a Membuat Beton mutu MPa (K225) 15.37 m3 A.4.1.1.7 1.65 0.028 0.083 0.275
b Pembesian dg Besi Polos atau Besi Ulir 2028.26 kg A.4.1.1.17 0.07 0.007 0.004 0.07
c Memasang Bekisting untuk Lantai 15.37 m2 A.4.1.1.24 0.66 0.033 0.033 0.33
2 Pemasangan Atap Genteng Kodok / lokal 77.90 m2 A.4.5.2.2 0.15 0.008 0.008 0.075
3 Pemasangan 1 m2 Dinding Lambriziring dari Papan Kayu Jati 155.80 m2 A.4.6.1.26 0.6 0.18 0.03 1.8
4Pemasangan 1 m2 rangka besi hollow 1x40.40.0.6 mm, modul 60 x 60 cm, plafon
9.36 m3 A.4.2.1.21 0.35 0.018 0.018 0.35
XI PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex 672.41 m2 A.4.7.1.11.2 0.028 0.0042 0.003
2 Pengecat 1m2 Waterproof untuk atap dag beton 84.16 m2 A.4.7.1.24 0.02 0.0063 0.003
3 Pengecat Plafond Baru dengan Mowilex 92.16 m2 A.4.7.1.10.1 0.02 0.003 0.003
XII PEKERJAAN AKSESORIS
1 Pemasangan Kunci Tanam Biasa 1.00 bh A.4.6.2.2 0.01 0.05 0.005 0.5
2 Pemasangan Kunci Kamar Mandi 1.00 bh A.4.6.2.3 0.005 0.05 0.0025 0.5
3 Pemasangan Engsel Pintu 3.00 bh A.4.6.2.5 0.015 0.015 0.0008 0.15
4 Pemasangan Engsel Jendela Kupu-kupu 6.00 bh A.4.6.2.6 0.01 0.01 0.0005 0.1
5 Pemasangan Kait Angin 6.00 bh A.4.6.2.9 0.015 0.008 0.008 0.15
TERBILANG :
Err:511
Diperiksa Oleh :
DOSEN UNISNU JEPARA
Management Proyek
43.97 44 - 0 1.47 1 - 0 - 0 - 0 - 0 -
7.35 7 - 0 0.73 1 - 0 - 0 - 0 - 0 -
- 0 - 0 - 0 - 0 - 0 - 0 - 0 -
0.05 0 0.01 0 0.00 0 - 0 - 0 0.05 0 - 0 -
- 0 - 0 - 0 - 0 - 0 - 0 - 0 -
0 - 0 16 12 1.33 1
0 - 0 17 8 2.15 2
0 - 0 0 1 0.00 0
0 - 0 45 15 3.03 3
0 - 0 8 5 1.62 2
0 - 0 14 5 2.71 3
0 - 0 51 7 7.23 7
0 - 0 1 1 1.42 1
0 - 0 1 1 0.84 1
0 - 0 145 20 7.23 7
0 - 0 38 10 3.80 4
0 - 0 162 14 11.58 12
0 - 0 215 10 21.52 22
0 - 0 2 1 1.82 2
0 - 0 3 2 1.53 2
0 - 0 32 3 10.69 11
0 - 0 5 3 1.52 2
0 - 0 2 1 1.95 2
0 - 0 16 3 5.19 5
0 - 0 4 1 3.65 4
0 - 0 8 3 2.70 3
0 - 0 81 7 11.59 12
0 - 0 33 5 6.62 7
0 - 0 6 2 3.19 3
0 - 0 55 4 13.65 14
0 - 0 44 5 8.82 9
0 - 0 38 7 5.39 5
0 - 0 3 1 2.83 3
0 - 0 30 1 30.41 30
0 - 0 28 1 27.93 28
0 - 0 2 1 1.76 2
0 - 0 22 1 22.08 22
0 - 0 17 2 8.72 9
0 - 0 5 1 5.05 5
0 - 0 65 3 21.59 22
0 - 0 31 2 15.71 16
0 - 0 4 2 1.80 2
0 - 0 47 7 6.78 7
0 - 0 24 4 5.92 6
0 - 0 8 3 2.58 3
0 - 0 99 10 9.86 10
0 - 0 63 8 7.92 8
0 - 0 3 2 1.68 2
0 - 0 33 3 10.97 11
0 - 0 20 3 6.57 7
0 - 0 16 3 5.45 5
0 - 0 1 1 1.22 1
0 - 0 11 7 1.52 2
0 - 0 8 4 2.11 2
0 - 0 31 5 6.26 6
0 - 0 306 9 34.03 34
0 - 0 16 7 2.32 2
0 - 0 2 1 1.58 2
0 - 0 20 1 20.23 20
0 - 0 13 1 12.94 13
0 - 0 0 0 #DIV/0! ###
0 - 0 0 0 #DIV/0! ###
0 - 0 0 0 #DIV/0! ###
0 - 0 7 3 2.20 2
0 - 0 128 7 18.33 18
0 - 0 25 4 6.31 6
0 - 0 16 5 3.27 3
0 - 0 19 7 2.68 3
0 - 0 407 10 40.66 41
0 - 0 7 1 6.89 7
0 - 0 68 15 4.52 5
0 - 0 15 7 2.11 2
0 - 0 15 7 2.20 2
0 - 0 77 10 7.65 8
0 - 0 7 1 6.54 7
0 - 0 41 7 5.80 6
0 - 0 2 1 2.25 2
0 - 0 11 5 2.19 2
0 - 0 6 3 1.97 2
0 - 0 8 2 3.95 4
0 - 0 11 5 2.15 2
0 - 0 1 1 1.00 1
0 - 0 22 5 4.43 4
63 - 0 134 13 10.34 10
0 - 0 52 10 5.19 5
0 - 0 8 1 7.77 8
0 - 0 8 1 8.20 8
0 - 0 1 1 0.57 1
0 - 0 1 1 0.56 1
0 - 0 1 1 0.54 1
0 - 0 1 1 0.72 1
0 - 0 1 1 1.09 1
0 1 1 3 1 3.44 3
0 1 1 3 1 2.99 3
0 1 1 3 1 3.04 3
0 - 0 3 1 3.19 3
0 - 0 1 1 1.00 1
0 - 0 8 2 4.22 4
0 - 0 8 2 4.22 4
0 - 0 3 1 2.81 3
0 - 0 3 1 2.81 3
0 - 0 6 1 5.62 6
0 - 0 5 1 5.28 5
0 - 0 1 1 0.63 1
0 - 0 4 1 3.92 4
0 - 0 1 1 0.81 1
0 - 0 35 1 34.83 35
0 - 0 15 1 15.39 15
0 - 0 9 1 8.91 9
0 - 0 9 1 8.91 9
0 - 0 10 1 9.72 10
0 - 0 1 1 0.81 1
0.01465925 0.10787947 0.14535022 0.14535022 0.14535022 0.14535022 0.14535022 0.14535022 0.1453502 0.1997928 0.3263053 0.3263053 0.0685799 0.1402731 0.3752372 0.2831491 0.3479171 0.3908551 0.3104464 0.3104464
0.01465925 0.12253873 0.26788895 0.41323916 0.55858938 0.7039396 0.84928981 0.99464003 1.1399902 1.339783 1.6660883 1.9923936 2.0609735 2.2012466 2.5764838 2.8596329 3.20755 3.5984051 3.9088515 4.2192978
HARGA SATUAN 100 Minggu 1 Minggu 2 Minggu 3
NO URAIAN PEKERJAAN BOBOT cek jumlah sdm hari
Rp 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6
A PEKERJAAN PERSIAPAN
1 Membersihkan Lapangan dan Perataan 13,750.00 0.1677 0.1677418 16 12 0.01397848 0.01397848 0.01397848 0.01397848 0.01397848 0.01397848 0.01397848 0.01397848 0.0139785 0.0139785 0.0139785 0.0139785
2 Pengukuran dan Pemasangan Bouwplank 61,131.00 0.7458 0.7457618 17 8 0.09322022 0.09322022 0.09322022 0.09322022 0.09322022 0.09322022 0.09322022 0.0932202
3 Air Kerja 500,000.00 0.0762 0.0762463 0 1 0.00068077 0.00068077 0.00068077 0.00068077 0.00068077 0.00068077 0.00068077 0.00068077 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808
0 0
B PEKERJAAN PELAKSANAAN 0 0
I PEKERJAAN TANAH 0 0
1 Menggali Tanah Biasa Sedalam 1 m 62,875.00 0.5621 0.5620611 45 15 0.03747074 0.03747074 0.03747074 0.03747074 0.03747074 0.03747074 0.0374707 0.0374707 0.0374707 0.0374707 0.0374707 0.0374707 0.0374707 0.0374707 0.0374707
2 Pengurugan Kembali 15,250.00 0.0342 0.0341734 8 5
0 0
II PEKERJAAN PONDASI 0 0
1 Pemasang Batu Kosong/Anstamping 452,513.40 0.7484 0.7483584 14 5 0.1496717 0.1496717 0.1496717 0.1496717
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 899,089.00 2.8912 2.8911885 51 7
3 Pasang Pondasi Rolag Trashraam BT Mrh 1 Pc : 3 Ps 1,207,075.00 0.0409 0.0408635 1 1 0.0408635
1 90 1
4 Urugan Pasir Bawah Pondasi 194,484.38 0.0804 0.0804087 0.0804087
0 0
III PEKERJAAN PASANGAN DINDING 0 0
1 Pasang Din Bt Mrh Kalipucang tbl 1/2 bt 1 SP:8PP Muntilan 110,750.00 5.6780 5.6779896 145 20
0 0
IV PEKERJAAN PLESTERAN 0 0
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan 64,000.20 0.7729 0.7728883 38 10
2 Pasang Plesteran 1 Pc : 8 Pp tbl 15 mm Ps Muntilan 40,516.80 4.1545 4.1544735 162 14
3 Pemasangan Acian 32,962.50 3.3799 3.3798778 215 10
0 0
V PEKERJAAN BETON 0 0
1 Membuat Beton mutu f'c=7,4 Mpa (K100) 973,662.43 0.1324 0.1324408 2 1 0.1324408
2 Membuat Foot Plat 100x100 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.2530 0.2530251 3 2 0.1265125 0.1265125
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.4430 0.4429883 32 3 0.1476628 0.1476628 0.1476628
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 99,770.00 0.0913 0.0912851 5 3 0.0304284 0.0304284 0.0304284
80
3 Membuat Foot Plat 80x80 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.1619 0.161936 2 1 0.161936
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.2151 0.2150796 16 3 0.0716932 0.0716932 0.0716932
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 99,770.00 0.0730 0.0730281 4 1 0.0730281
4 Membuat Sloof Beton Bertulang 20x30 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.6715 0.6715286 8 3
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 1.1207 1.1206576 81 7 0.1600939 0.1600939 0.1600939 0.1600939
c Memasang Bekisting untuk Sloof 137,576.25 0.8352 0.8351881 33 5
5 Membuat Kolom Beton Bertulang 30x30 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.5283 0.5283164 6 2
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.7544 0.7544459 55 4
c Memasang Bekisting untuk Kolom 205,045.00 1.3057 1.3057448 44 5
6 Membuat Beton bertulang Kolom Praktis 11x11 cm 69,841.10 1.5746 1.5746391 38 7
7 Membuat Kolom Beton Bertulang 20x20 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.2348 0.2348073 3 1
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.4202 0.4201977 30 1
70
c Memasang Bekisting untuk Kolom 205,045.00 0.8270 0.8269717 28 1
8 Membuat Balok Beton Bertulang 15x30 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.1457 0.1457424 2 1
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.3051 0.3050714 22 1
c Memasang Bekisting untuk Kolom 205,045.00 0.5163 0.5162945 17 2
9 Membuat Balok Beton Bertulang 20x40 (B1) 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.4183 0.4183348 5 1
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.8950 0.8949509 65 3
c Memasang Bekisting untuk Kolom 208,045.00 0.9441 0.9441453 31 2
10 Membuat Balok Beton Bertulang 20x30 (B2) 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.2986 0.2985696 4 2
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.6562 0.6561624 47 7
c Memasang Bekisting untuk Balok 208,045.00 0.7113 0.7112815 24 4
11 Membuat Balok Beton Bertulang 15x30 (B4) 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.6414 0.6414186 8 3
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 1.3619 1.2257391 99 10
60
c Memasang Bekisting untuk Balok 208,045.00 1.9034 1.9033601 63 8
12 Membuat Balok Beton Bertulang 15x20 (B3) 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.2778 0.2778215 3 2
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.4547 0.4547339 33 3
c Memasang Bekisting untuk Balok 208,045.00 0.5922 0.5921847 20 3
13 Membuat Latiu Balok Beton Bertulang (10 x 15) cm 109,298.81 0.6477 0.6476895 16 3
14 Membuat Ring Balok Beton Bertulang 15 x 20 cm 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.1012 0.10121 1 1
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.1471 0.1470769 11 7
c Memasang Bekisting untuk Balok 208,045.00 0.2538 0.2538025 8 4
15 Membuat Dak Plat Beton tbl 12 cm 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 2.5926 2.5926299 31 5
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 4.2321 4.2320779 306 9
c Memasang Bekisting untuk Lantai 205,645.00 0.4820 0.4819866 16 7
0 0
VI PEKERJAAN TANGGA BETON BERTULANG 0 0
50
1 Membuat Balok Beton Bertulang 15x30 (B4) 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.1310 0.1310164 2 1
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.2795 0.2795341 20 1
c Memasang Bekisting untuk Balok 208,045.00 0.3888 0.388781 13 1
3 Membuat Plat Tangga 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.0000 0 0 0
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 0.0016 0 0 0
c Memasang Bekisting untuk Lantai 137,576.25 0.0000 0 0 0
2 Membuat Plat Tangga 0 0
a Membuat Beton mutu MPa (K225) 1,106,174.59 0.5468 0.5467872 7 3
b Pembesian dg Besi Polos atau Besi Ulir 13,683.00 1.7732 1.7732065 128 7
c Memasang Bekisting untuk Lantai 205,645.00 0.7490 0.7490176 25 4
0 0
VII PEKERJAAN PENUTUP ATAP 0 0
1 Pasang Kasau & Reng Kayu Kruing (SNI) 115,419.38 1.3711 1.3710863 16 5
0 40 0
2 Pemasangan Atap Genteng Kodok / lokal 60,525.00 0.7190 0.7189867 19 7
3 Pemasangan 1 m2 Dinding Lambriziring dari Papan Kayu Jati 419,180.63 9.9590 9.9590355 407 10
4Pemasangan 1 m2 rangka besi hollow 1x40.40.0.6 mm, modul 60 x 60 cm, plafon 116,945.00 0.1669 0.1669191 7 1
0 0
VIII PEKERJAAN LANGIT - LANGIT 0 0
1 Pemasangan 1 m2 rangka besi hollow 1x40.40.0.6 mm, modul 60 x 60 cm, plafon 0 0
116,945.00 1.6435 1.6434937 68 15
2 Memasang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm 39,215.00 0.5511 0.5511104 15 7
3 List Langit-Langit Kayu Profil 20,523.00 0.4544 0.454356 15 7
0 0
IX PEKERJAAN PENUTUP LANTAI DAN DINDING 0 0
1 Pemasangan lantai Ubin Granitile Uk. 60 x 60 cm 302,949.00 8.8151 8.8151417 77 10
2 Pemasangan Lantai Keramik 20 x 20 cm 206,645.00 0.1840 0.183966 7 1
3 Pemasangan Dinding Keramik 20x25 cm, 225,990.00 0.9715 0.9714779 41 7
4 Pemasangan Lantai Keramik 30 x 30 cm warna 201,479.00 0.0618 0.0617553 2 1
Blok paving tebal 6 cm5dengan paving mutu K 225 (SNI) 170,746.88 0.4081 0.4081398 11 30 5
0 0
X PEKERJAAN BESI dan ALUMUNIUM 0 0
1 Pemasangan Kusen Pintu Allumunium 126,524.50 1.2371 1.2371341 6 3
2 Pasang Kusen Jendela Alumunium 126,524.50 1.6516 1.6515701 8 2
3 Pasang Daun Pintu dan Jendela Kaca Alumunium 477,020.00 4.2449 4.2448737 11 5
4 Pemasangan Pintu Allumunium Strip Lebar 8 cm 971,578.00 0.1822 0.1822348 1 1
5 Pemasangan Kaca tebal 5 mm 149,936.25 2.7997 2.7996937 22 5
6 Pemasangan 1 m2 terali besi strip (2 x 3) mm 504,106.02 2.8793 2.8792562 134 13
0 0
0 0
XI PEKERJAAN PENGECATAN 0 0
1 Pengecat Tembok Baru dengan Mowilex 42,072.75 4.3140 4.314016 52 10
2 Pengecat 1m2 Waterproof untuk atap dag beton 26,438.00 0.3393 0.3393094 8 1
3 Pengecat Plafond Baru dengan Mowilex 26,998.00 0.3794 0.379418 8 1
0 0
XII PEKERJAAN AKSESORIS 0 20 0
1 Pemasangan Kunci Tanam Biasa 134,075.00 0.0204 0.0204454 1 1
2 Pemasangan Kunci Kamar Mandi 102,587.50 0.0156 0.0156438 1 1
3 Pemasangan Engsel Pintu 44,042.00 0.0201 0.0201482 1 1
4 Pemasangan Engsel Jendela Kupu-kupu 30,457.50 0.0279 0.0278673 1 1
5 Pemasangan Kait Angin 25,670.00 0.0235 0.0234869 1 1
0 0
XIII PEKERJAAN SANITASI 0 0
1 Pemasangan 1 m pipa PVC Ø 25 mm (1") 31,636.36 0.1544 0.1543779 3 1
2 Pemasangan 1 m pipa PVC Ø 50 mm (2") 69,255.00 0.2429 0.2429 3 1
3 Pemasangan 1 m pipa PVC Ø 90 mm (4") 90,335.00 0.2480 0.2479575 3 1
4 Pemasangan Kran Ø ½" atau Ø ¾" 71,577.50 0.0764 0.0764052 3 1
5 Pemasangan Bak Cuci Piring Stainless stell 273,525.00 0.0417 0.0417105 1 1
6 Memasang Closet Jongkok Porselen 413,157.50 0.1890 0.1890103 8 2
7 Septiktank Buis Beton 3,892,659.63 1.7808 1.7808048 8 2
8 Resapan Air kotor Buis Beton 2,749,434.84 0.4193 0.4192683 3 1
9 Tandon Air 1000 L 1,500,000.00 0.2287 0.2287388 3 10 1
10 Pemasangan Kran Shower Mandi 500,000.00 0.1525 0.1524926 6 1
11 Ember Air 50,000.00 0.0229 0.0228739 5 1
12 Pemasangan Floor Drain 35,575.00 0.0271 0.0271246 1 1 7.8
13 Pemasangan Pipa PVC tipe AW Ø 3" 67,960.00 0.1814 0.1813594 4 1
7.0413841422
0 0
XIV PEKERJAAN LISTRIK 0 0 6.0755964564
1 Pasang Meteran Listrik 2000VA 2,000,000.00 0.3050 0.3049851 1 1
5.1098087707
2 Pasang Instalasi Listrik 80,000.00 0.5246 0.5245744 35 1
3 Pasang Lampu LED 15 watt 40,000.00 0.1159 0.1158943 15 1 4.2192978489
3.908851465
4 Pasang Lampu LED 20 watt 60,000.00 0.1006 0.1006451 9 1 3.598405081
3.2075500217
5 Pasang Saklar Ganda 25,000.00 0.0419 0.0419355 9 1 2.8596328957
2.5764838113
6 Pasang Stop Kontak 30,000.00 0.0549 0.0548973 10 1 2.2012466006
2.0609735104
1.9923936347
7 Pasang Mesin Pompa Air Jet Pump Otomatis 1,500,000.00 0.2287 0.2287388 1 1 1.6660883261
1.3397830174
1.1399902465
0 0 0.9946400297
0.8492898129
0.7039395961
100.00 0.5585893793
0.4132391625
0.2678889457
0.1225387289
progres mingguan 0 0.0146592541
0.01465925 0.10787947 0.14535022 0.14535022 0.14535022 0.14535022 0.14535022 0.14535022 0.1453502 0.1997928 0.3263053 0.3263053 0.0685799 0.1402731 0.3752372 0.2831491 0.3479171 0.3908551 0.3104464 0.3104464
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
progres komulatif 0.01465925 0.12253873 0.26788895 0.41323916 0.55858938 0.7039396 0.84928981 0.99464003 1.1399902 1.339783 1.6660883 1.9923936 2.0609735 2.2012466 2.5764838 2.8596329 3.20755 3.5984051 3.9088515 4.2192978
0.8905109 0.9657877 0.9657877 0.8045882 0.8045882 0.862499 0.6386561 0.6822243 0.6822243 0.6822243 0.7214341 0.5328226 0.8276525 0.704778 0.735284 0.5896517 0.5427275 0.6884699 0.7566529 0.7566529 0.5828972 0.5828972 0.7173325 0.5397669 0.5397669 0.5397669 0.4709116 0.588062 0.5192067 0.6335531 0.6335531 0.6335531 0.6013114 0.6701666
5.1098088 6.0755965 7.0413841 7.8459723 8.6505605 9.5130594 10.151716 10.83394 11.516164 12.198389 12.919823 13.452645 14.280298 14.985076 15.72036 16.310011 16.852739 17.541209 18.297862 19.054515 19.637412 20.220309 20.937641 21.477408 22.017175 22.556942 23.027854 23.615916 24.135122 24.768676 25.402229 26.035782 26.637093 27.30726
u3 Minggu 4 Minggu 5 Minggu 6 Minggu 7 Minggu 8
7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5
0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808
0.1496717
0.4130269 0.4130269 0.4130269 0.4130269 0.4130269 0.4130269 0.4130269
0.2838995 0.2838995 0.2838995 0.2838995 0.2838995 0.2838995 0.2838995 0.2838995 0.2838995 0.2838995 0.2838995 0.2838995 0.2838995 0.2838995
0.2641582 0.2641582
0.1886115 0.1886115 0.1886115 0.1886115
0.261149 0.261149 0.261149 0.261149 0.261149
0.2249484 0.2249484 0.2249484 0.2249484 0.2249484 0.2249484 0.2249484
0.2348073
0.4201977
0.8269717
0.1457424
0.3050714
0.2581472 0.2581472
0.4183348
0.298317 0.298317 0.298317
0.4720727 0.4720727
0.1778204 0.1778204
0.1389108 0.1389108
0.151578 0.151578 0.151578
0.1973949 0.1973949 0.1973949
0.2158965
0.518526 0.518526
0.4702309 0.4702309 0.4702309 0.4702309
0.0688552 0.0688552 0.0688552 0.0688552 0.0688552
29.899
29.0884399719
28.2398913636
27.3072598596
26.6370932324
26.0357818391
25.4022287154
24.7686755916
24.1351224678
23.6159157236
23.0278537456
22.5569420981
22.0171752168
21.4774083355
20.9376414542
20.2203089406
19.6374117387
19.0545145368
18.2978616358
17.5412087349
16.8527387964
16.3100113014
15.7203596153
14.9850755904
14.280297637
13.4526451687
12.9198225844
12.1983885309
11.5161642157
10.8339399005
10.1517155853
9.5130594468
8.6505604583
7.8459723002
7.0413841422
6.0755964564
5.1098087707
4.2192978489
8851465
0.8905109 0.9657877 0.9657877 0.8045882 0.8045882 0.862499 0.6386561 0.6822243 0.6822243 0.6822243 0.7214341 0.5328226 0.8276525 0.704778 0.735284 0.5896517 0.5427275 0.6884699 0.7566529 0.7566529 0.5828972 0.5828972 0.7173325 0.5397669 0.5397669 0.5397669 0.4709116 0.588062 0.5192067 0.6335531 0.6335531 0.6335531 0.6013114 0.6701666
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
5.1098088 6.0755965 7.0413841 7.8459723 8.6505605 9.5130594 10.151716 10.83394 11.516164 12.198389 12.919823 13.452645 14.280298 14.985076 15.72036 16.310011 16.852739 17.541209 18.297862 19.054515 19.637412 20.220309 20.937641 21.477408 22.017175 22.556942 23.027854 23.615916 24.135122 24.768676 25.402229 26.035782 26.637093 27.30726
0.9326315 0.8485486 0.8113247 0.8494009 0.6491107 0.6974058 0.6974058 0.9941539 0.7056447 0.9191267 0.871052 1.0868187 1.0868187 1.1788516 1.1159486 0.9796153 0.9289497 0.9289497 1.2224592 1.3287343 1.3148167 1.1968768 1.8135826 2.0018789 1.5714925 1.6364005 1.6364005 1.6364005 1.2497886 1.2497886 1.3098411 1.3098411 1.1305437 1.1305437
28.239891 29.08844 29.899765 30.749166 31.398276 32.095682 32.793088 33.787242 34.492887 35.412013 36.283065 37.369884 38.456703 39.635554 40.751503 41.731118 42.660068 43.589018 44.811477 46.140211 47.455028 48.651905 50.465487 52.467366 54.038859 55.675259 57.31166 58.94806 60.197849 61.447638 62.757479 64.06732 65.197863 66.328407
Minggu 8 Minggu 9 Minggu 10 Minggu 11 Minggu 12 Minggu 13
6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4
0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808
0.0772888 0.0772888 0.0772888 0.0772888 0.0772888 0.0772888 0.0772888 0.0772888 0.0772888 0.0772888
0.2967481 0.2967481 0.2967481 0.2967481 0.2967481 0.2967481 0.2967481 0.2967481 0.2967481 0.2967481 0.2967481
0.3379878 0.3379878 0.3379878 0.3379878 0.3379878 0.3379878 0.3379878
69.35980651
67.8643982372
66.328407228
65.1978634883
64.0673197487
0.1492848 0.1492848
0.0937375 0.0937375 0.0937375 0.0937375 0.0937375 0.0937375 0.0937375 62.7574786249
0.1778204 0.1778204
61.4476375011
0.2138062 0.2138062 0.2138062
0.1361932 0.1361932 0.1361932 0.1361932 0.1361932 0.1361932 0.1361932 0.1361932 0.1361932 60.1978488785
0.23792 0.23792 0.23792 0.23792 0.23792 0.23792 0.23792 0.23792
58.9480602558
57.3116597617
0.2158965 0.2158965
55.6752592676
0.10121
0.021011 0.021011 0.021011 0.021011 0.021011 0.021011 0.021011
0.0634506 0.0634506 0.0634506 0.0634506 54.0388587734
50.4654873765
0.1310164
48.6519047756
0.2795341
0.388781
47.4550279506
46.1402112634
44.8114769301
41.7311183281
40.7515030005
0.2742173 0.2742173 0.2742173 0.2742173 0.2742173
36.2830653315
35.4120133556 0.1095662 0.1095662 0.1095662 0.1095662 0.1095662 0.1095662 0.1095662 0.1095662 0.1095662 0.1095662 0.1095662 0.1095662 0.1095662
0.0787301 0.0787301 0.0787301 0.0787301 0.0787301 0.0787301 0.0787301
34.4928866154 0.064908 0.064908 0.064908 0.064908 0.064908 0.064908 0.064908
33.7872419415
32.7930879977
0.8815142 0.8815142
32.0956821593
31.3982763208
0.1387826 0.1387826 0.1387826 0.1387826
30.7491655792
29.8997647115
29.0884399719
28.2398913636
27.3072598596
26.6370932324
8391
0.9326315 0.8485486 0.8113247 0.8494009 0.6491107 0.6974058 0.6974058 0.9941539 0.7056447 0.9191267 0.871052 1.0868187 1.0868187 1.1788516 1.1159486 0.9796153 0.9289497 0.9289497 1.2224592 1.3287343 1.3148167 1.1968768 1.8135826 2.0018789 1.5714925 1.6364005 1.6364005 1.6364005 1.2497886 1.2497886 1.3098411 1.3098411 1.1305437 1.1305437
53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91
28.239891 29.08844 29.899765 30.749166 31.398276 32.095682 32.793088 33.787242 34.492887 35.412013 36.283065 37.369884 38.456703 39.635554 40.751503 41.731118 42.660068 43.589018 44.811477 46.140211 47.455028 48.651905 50.465487 52.467366 54.038859 55.675259 57.31166 58.94806 60.197849 61.447638 62.757479 64.06732 65.197863 66.328407
1.535991 1.4954083 1.7364647 1.8944303 2.2324181 2.6458251 2.267449 2.3840525 2.0624771 2.2447119 2.0624771 1.4095943 1.2135024 0.992873 0.9190921 0.8293603 0.8509502 1.0817672 0.8910832 0.753994 0.8910832 0.5206804 0.5167819 0.1013259
67.864398 69.359807 71.096271 72.990702 75.22312 77.868945 80.136394 82.520446 84.582923 86.827635 88.890112 90.299707 91.513209 92.506082 93.425174 94.254534 95.105485 96.187252 97.078335 97.832329 98.723412 99.244092 99.760874 99.8622
Minggu 13 Minggu 14 Minggu 15 Minggu 16 99.8622001195
99.7608742662
5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6
99.2440923973 7
98.7234120314
97.832328871
97.0783349035
0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808 0.0006808
96.1872517431
95.1054845836
94.2545343415
93.4251740119
92.5060819504
91.5132089622
90.2997066113
88.8901123608
86.8276352623
82.520446225
80.1363936923
77.8689446624
75.2231195684
72.9907015163
71.0962712419
69.3598065159
67.8643982372
66.328407228
65.1978634883
0673197487
0.1095662 0.1095662
0.4314016 0.4314016 0.4314016 0.4314016 0.4314016 0.4314016 0.4314016 0.4314016 0.4314016 0.4314016
0.3393094
0.379418
0.0204454
0.0156438
0.0201482
0.0278673
0.0234869
0.1543779
0.2429
0.2479575
0.0764052
0.0417105
0.0945052 0.0945052
0.8904024 0.8904024
0.4192683
0.2287388
0.1524926
0.0228739
0.0271246
0.1813594
0.3049851
0.5245744
0.1158943
0.1006451
0.0419355
0.0548973
0.2287388
1.535991 1.4954083 1.7364647 1.8944303 2.2324181 2.6458251 2.267449 2.3840525 2.0624771 2.2447119 2.0624771 1.4095943 1.2135024 0.992873 0.9190921 0.8293603 0.8509502 1.0817672 0.8910832 0.753994 0.8910832 0.5206804 0.5167819 0.1013259
87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112
67.864398 69.359807 71.096271 72.990702 75.22312 77.868945 80.136394 82.520446 84.582923 86.827635 88.890112 90.299707 91.513209 92.506082 93.425174 94.254534 95.105485 96.187252 97.078335 97.832329 98.723412 99.244092 99.760874 99.8622
1
MINGGU 1 MINGGU 2 MINGGU 3
NO URAIAN PEKERJAAN TOTAL HARI KETERANGAN LOGIKA
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
A PEKERJAAN PERSIAPAN
1 Membersihkan Lapangan dan Perataan 16 12.00 A1 0 1 1 1 1 1 1 1 1 2 2 2 2
2 Pengukuran dan Pemasangan Bouwplank 17 8.00 A2 A1 2 2 2 2 2 2 2 3
3 Air Kerja 0 1.00 A3 0
B PEKERJAAN PELAKSANAAN
I PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m 45 15.00 I1 A2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
2 Pengurugan Kembali 8 5.00 I2 VII
II PEKERJAAN PONDASI
1 Pemasang Batu Kosong/Anstamping 14 5.00 II 1 II 4 2 3 3 3 3
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 51 7.00 II 2 II 3 7
3 Pasang Pondasi Rolag Trashraam BT Mrh 1 Pc : 3 Ps 1 1.00 II 3 II 2 1
4 Urugan Pasir Bawah Pondasi 1 1.00 II 4 I1 1
IV PEKERJAAN PLESTERAN
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan 38 10.00 IV 1 VII 4
2 Pasang Plesteran 1 Pc : 8 Pp tbl 15 mm Ps Muntilan 162 14.00 IV 2 IV 1
3 Pemasangan Acian 215 10.00 IV 3 IV 1
V PEKERJAAN BETON
1 Membuat Beton mutu f'c=7,4 Mpa (K100) 2 1.00 V1 V1 2
2 Membuat Foot Plat 100x100
a Membuat Beton mutu MPa (K225) 3 2.00 V 2A V 2C 1 2
b Pembesian dg Besi Polos atau Besi Ulir 32 3.00 V 2B II 1 10 12 10
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 5 3.00 V 2C V 2B 1 2 2
3 Membuat Foot Plat 80x80
a Membuat Beton mutu MPa (K225) 2 1.00 V 3A V 3C 2
b Pembesian dg Besi Polos atau Besi Ulir 16 3.00 V 3B II 1 5 5 6
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 4 1.00 V 3C V 3B 4
4 Membuat Sloof Beton Bertulang 20x30
a Membuat Beton mutu MPa (K225) 8 3.00 V 4A V 4C
b Pembesian dg Besi Polos atau Besi Ulir 81 7.00 V 4B V 4B 11 11 11 11 12
c Memasang Bekisting untuk Sloof 33 5.00 V 4C V 4B 7
5 Membuat Kolom Beton Bertulang 30x30
a Membuat Beton mutu MPa (K225) 6 2.00 V 5A V 5C
b Pembesian dg Besi Polos atau Besi Ulir 55 4.00 V 5B V 4B
c Memasang Bekisting untuk Kolom 44 5.00 V 5C V 5B
6 Membuat Beton bertulang Kolom Praktis 11x11 cm 38 7.00 V6 III 1
7 Membuat Kolom Beton Bertulang 20x20
a Membuat Beton mutu MPa (K225) 3 1.00 V 7A V 7C
b Pembesian dg Besi Polos atau Besi Ulir 30 1.00 V 7B V 5B
c Memasang Bekisting untuk Kolom 28 1.00 V 7C V 7B
8 Membuat Balok Beton Bertulang 15x30
a Membuat Beton mutu MPa (K225) 2 1.00 V 8A V 8A
b Pembesian dg Besi Polos atau Besi Ulir 22 1.00 V 8B V 8B
c Memasang Bekisting untuk Kolom 17 2.00 V8C V8C
9 Membuat Balok Beton Bertulang 20x40 (B1)
a Membuat Beton mutu MPa (K225) 5 1.00 V 9A V 8A
b Pembesian dg Besi Polos atau Besi Ulir 65 3.00 V 9B V 9B
c Memasang Bekisting untuk Balok 31 2.00 V 9C V 9C
10 Membuat Balok Beton Bertulang 20x30 (B2)
a Membuat Beton mutu MPa (K225) 4 2.00 V 10A V 9A
b Pembesian dg Besi Polos atau Besi Ulir 47 7.00 V 10B V 9B
c Memasang Bekisting untuk Balok 24 4.00 V 10C V 9C
11 Membuat Balok Beton Bertulang 15x30 (B4)
a Membuat Beton mutu MPa (K225) 8 3.00 V 11A V 15A
b Pembesian dg Besi Polos atau Besi Ulir 99 10.00 V 11B V 15B
c Memasang Bekisting untuk Balok 63 8.00 V 11C V 15C
12 Membuat Balok Beton Bertulang 15x20 (B3)
a Membuat Beton mutu MPa (K225) 3 2.00 V 12A V 10A
b Pembesian dg Besi Polos atau Besi Ulir 33 3.00 V 12B V 10B
c Memasang Bekisting untuk Balok 20 3.00 V 12C V 10C
13 Membuat Latiu Balok Beton Bertulang (10 x 15) cm 16 3.00 V 13 V6
14 Membuat Ring Balok Beton Bertulang 15 x 20 cm
a Membuat Beton mutu MPa (K225) 1 1.00 V 14A V 14C
b Pembesian dg Besi Polos atau Besi Ulir 11 7.00 V 14B III 1
c Memasang Bekisting untuk Balok 8 4.00 V 14C V 14B
15 Membuat Dak Plat Beton tbl 12 cm
a Membuat Beton mutu MPa (K225) 31 5.00 V 15A V 12A
b Pembesian dg Besi Polos atau Besi Ulir 306 9.00 V 15B V 10B
c Memasang Bekisting untuk Lantai 16 7.00 V 15C V 10C
XI PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex 52 10.00 XI 1 XI 3
2 Pengecat 1m2 Waterproof untuk atap dag beton 8 1.00 XI 2 VII 2
3 Pengecat Plafond Baru dengan Mowilex 8 1.00 XI 3 XI 1
jumlah pekerja 1 3 6 6 6 6 6 6 8 15 18 17 4 10 16 12 16 15 14 14 29
34 78 116
90
80
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 3
MINGGU 4 MINGGU 5 MINGGU 6 MINGGU 7 MINGGU 8
22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56
2 2 2 1 1
7 7 7 7 8 8
8.00 8.00 8.00 7.00 7.00 7.00 7.00 7.00 7.00 8.00 8.00 8.00 8.00 7.00 7.00 7.00
2 3 3
12 13
7 7 6 6
3 3
13 14 14 14
8 9 9 9 9
5 5 5 5 6 6 6
3
30
28
2
22
8 9
5
21 22 22
15 16
6
6 6 6
1 2
11 11 11
7 7 6
6
6 6
34 34 34 34 34 34
2 2 2 3 2 2
31 32 15 16 16 13 29 31 31 27 13 28 38 11 36 15 18 22 23 28 29 27 36 36 36 34 6 9 8 26 26 31 16 49 49
152 179 171 184 205
19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64
MINGGU 9 MINGGU 10 MINGGU 11 MINGGU 12 MINGGU 13
57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91
4 4 4 4 4 4 4 4 3 3
11 11 11 11 11 11 12 12 12 12 12
21 21 21 21 21 22 22
2 2
6 7 7 7 7 7
6
3 3 2
10 9 10 10 10 10 10 10 10 10
7 8 8 8 8 8 8 8
6 4
1
1 1 1 2 2 2 2
2 2 2 2
6 6 7
34 34 34
3
2
20
13
2 2 3
18 18 18 18 19 18 19
6 6 6 7
3 3 3 3 4
2 2 3 3 3 3 3
40 40 40 41 41 41 41 41 41 41
7
4 4 4 4 4 4 4 5 5 5 5 5 5 5 5
2 2 2 2 2 2 3
2 2 2 2 2 2 3
7 7 7 8 8
7
5 6 6 6 6 6 6
2
2 2
10 10 10
55 41 44 16 16 31 15 24 36 53 54 43 35 62 43 40 47 53 70 58 46 82 56 58 58 58 53 51 53 55 59 18 35 33 28
218 307 357 416 281
55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 1
MINGGU 14 MINGGU 15 MINGGU 16
92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112
12 12 12
22 22 22
8 8 8 8 8
2 2 3
2 2
4 4
2 2 2 2 3
1
4 4 4 5 5
10 10 10 10 10 10 11 11 11 11
6 5 5 5 5 5 5 5 5 6
8
8
1
1
1
1
1
3
3
3
3
1
4 4
4 4
3
3
6
5
1
4
1
35
15
9
9
10
1
34 34 59 44 48 21 23 22 8 21 24 18 11 15 17 4 38 4 27 22 9
263 119 121
90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112
DAFTAR ANALISIS HARGA SATUAN PEKERJAAN
(AHSP)
KABUPATEN JEPARA
TAHUN 2019
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
1m2 tebas tebang berupa memotong dan membersihkan lokasi dari tanaman/
8 A.2.2.1.19 tumbuhan diameter < 15cm
A Tenaga
AHSP-SDA Pekerja L.01 OH 0.0750 80,000.00 6,000.00
Mandor L.04 OH 0.0075 115,000.00 862.50
6,862.50
B Bahan
Minyak tanah ltr 0.010 15,000.00 150.00
150.00
C PERALATAN
D Jumlah A + B + C 7,012.50
E Overhead & Profit 12.5% 876.56
F Harga Satuan Pekerjaan (D+E) 7,889.06
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
NO URAIAN PEKERJAAN TOTAL HARI
minggu 1 minggu 2 minggu 3 minggu 4 minggu 5 minggu 6 minggu 7 minggu 8 minggu 9 minggu 10 minggu 11 minggu 12 minggu 13 minggu 14 minggu 15 minggu 16
A PEKERJAAN PERSIAPAN
1 Membersihkan Lapangan dan Perataan 16 12.00 7 9
2 Pengukuran dan Pemasangan Bouwplank 17 8.00 17
3 Air Kerja 0 1.00
B PEKERJAAN PELAKSANAAN
I PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m 45 15.00 15 21 9
2 Pengurugan Kembali 8 5.00 2 6
II PEKERJAAN PONDASI
1 Pemasang Batu Kosong/Anstamping 14 5.00 14
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 51 7.00 14 37
3 Pasang Pondasi Rolag Trashraam BT Mrh 1 Pc : 3 Ps 1 1.00 1
4 Urugan Pasir Bawah Pondasi 1 1.00 1
IV PEKERJAAN PLESTERAN
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan 38 10.00 12 16 10
2 Pasang Plesteran 1 Pc : 8 Pp tbl 15 mm Ps Muntilan 162 14.00 66 48 12 36
3 Pemasangan Acian 215 10.00 21 42 86 66
V PEKERJAAN BETON
1 Membuat Beton mutu f'c=7,4 Mpa (K100) 2 1.00 2
2 Membuat Foot Plat 100x100
a Membuat Beton mutu MPa (K225) 3 2.00 3
b Pembesian dg Besi Polos atau Besi Ulir 32 3.00 32
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 5 3.00 3 2
3 Membuat Foot Plat 80x80
a Membuat Beton mutu MPa (K225) 2 1.00 2
b Pembesian dg Besi Polos atau Besi Ulir 16 3.00 5 11
c Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 4 1.00 4
4 Membuat Sloof Beton Bertulang 20x30
a Membuat Beton mutu MPa (K225) 8 3.00 8
b Pembesian dg Besi Polos atau Besi Ulir 81 7.00 56 25
c Memasang Bekisting untuk Sloof 33 5.00 7 26
5 Membuat Kolom Beton Bertulang 30x30
a Membuat Beton mutu MPa (K225) 6 2.00 6
b Pembesian dg Besi Polos atau Besi Ulir 55 4.00 55
c Memasang Bekisting untuk Kolom 44 5.00 35 9
6 Membuat Beton bertulang Kolom Praktis 11x11 cm 38 7.00 26 12
7 Membuat Kolom Beton Bertulang 20x20
a Membuat Beton mutu MPa (K225) 3 1.00 3
b Pembesian dg Besi Polos atau Besi Ulir 30 1.00 25 6
c Memasang Bekisting untuk Kolom 28 1.00 22 6
8 Membuat Balok Beton Bertulang 15x30
a Membuat Beton mutu MPa (K225) 2 1.00 2
b Pembesian dg Besi Polos atau Besi Ulir 22 1.00 9 13
c Memasang Bekisting untuk Kolom 17 2.00 17
9 Membuat Balok Beton Bertulang 20x40 (B1)
a Membuat Beton mutu MPa (K225) 5 1.00 5
b Pembesian dg Besi Polos atau Besi Ulir 65 3.00 36 29
c Memasang Bekisting untuk Balok 31 2.00 31
10 Membuat Balok Beton Bertulang 20x30 (B2)
a Membuat Beton mutu MPa (K225) 4 2.00 4
b Pembesian dg Besi Polos atau Besi Ulir 47 7.00 33 14
c Memasang Bekisting untuk Balok 24 4.00 24
11 Membuat Balok Beton Bertulang 15x30 (B4)
a Membuat Beton mutu MPa (K225) 8 3.00 8
b Pembesian dg Besi Polos atau Besi Ulir 99 10.00 49 50
c Memasang Bekisting untuk Balok 63 8.00 63
12 Membuat Balok Beton Bertulang 15x20 (B3)
a Membuat Beton mutu MPa (K225) 3 2.00 3
b Pembesian dg Besi Polos atau Besi Ulir 33 3.00 33
c Memasang Bekisting untuk Balok 20 3.00 20
13 Membuat Latiu Balok Beton Bertulang (10 x 15) cm 16 3.00 6 6 4
14 Membuat Ring Balok Beton Bertulang 15 x 20 cm
a Membuat Beton mutu MPa (K225) 1 1.00 1
b Pembesian dg Besi Polos atau Besi Ulir 11 7.00 1 10
c Memasang Bekisting untuk Balok 8 4.00 8
15 Membuat Dak Plat Beton tbl 12 cm
a Membuat Beton mutu MPa (K225) 31 5.00 15 16
b Pembesian dg Besi Polos atau Besi Ulir 306 9.00 30 121 155
c Memasang Bekisting untuk Lantai 16 7.00 8 2 6
XI PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex 52 10.00 10 36 6
2 Pengecat 1m2 Waterproof untuk atap dag beton 8 1.00 8
3 Pengecat Plafond Baru dengan Mowilex 8 1.00 8
XII PEKERJAAN AKSESORIS
1 Pemasangan Kunci Tanam Biasa 1 1.00 1
2 Pemasangan Kunci Kamar Mandi 1 1.00 1
3 Pemasangan Engsel Pintu 1 1.00 1
4 Pemasangan Engsel Jendela Kupu-kupu 1 1.00 1
5 Pemasangan Kait Angin 1 1.00 1
jumlah pekerja 15 64 123 124 130 114 152 281 453 272 438 368 139 211 157 125
500
450
400
350
300
250
200
150
100
50
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
DAFTAR HARGA SATUAN PEKERJAAN KONSTRUKSI
KABUPATEN JEPARA
TAHUN ANGGARAN 2019
( Harga sudah termasuk bahan,upah tenaga,alat tahun 2019, Overhead & Profit 12.5%)
(Ket :belum termasuk PPN 10%)
Ir. BUDIARTO, MT
Pembina Utama Madya
NIP. 19590410 198603 1 015
Ir. BUDIARTO, MT
Pembina Utama Madya
NIP. 19590410 198603 1 015
200.000,00 - 245.000,00
BACK UP VOLUME
I PEKERJAAN PERSIAPAN
P L T Q PxLxTxQ total sat
1 Pengukuran dan Pemasangan Bouwplank
- kios makanan 36.00 + 6.00 x 1.00 = 42.00
- kioa kerajinan 35.00 + 6.00 x 1.00 = 41.00
= 83.00 m
2 Membersihkan Lapangan dan Perataan
- kios makanan 36.00 x 6.00 x 2.00 = 432.00
- kioa kerajinan 35.00 x 6.00 x 1.00 = 210.00
= 642.00 m2
3 Air Kerja
3 Urugan tanah padas dan dipadatkan 36.00 x 6.00 x 0.20 x 1.00 = 43.20 2.00 86.40 m3
II PEKERJAAN PONDASI
P L T Q PxLxTxQ total sat
1 Pemasang Batu Kosong/Anstamping 36.00 x 0.60 x 0.20 x 2.00 = 8.64 2.00 17.28
6.00 x 0.60 x 0.20 x 7.00 = 5.04 2.00 10.08
36.00 x 0.50 x 0.20 x 0.00 = 0.00 2.00 0.00
= 27.36 m3
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 36.00 x 0.35 x 0.40 x 2.00 = 10.08 2.00 20.16
6.00 x 0.35 x 0.40 x 7.00 = 5.88 2.00 11.76
36.00 x 0.25 x 0.30 x 0.00 = 0.00 2.00 0.00
= 31.92 m3
3 Pasang Pondasi Rolag Trashraam BT Mrh 1 Pc : 3 Ps 36.00 x 0.20 x 0.10 x 1.00 = 0.72 2.00 = 1.44 m3
Membuat Beton mutu MPa (K225) 137.60 x 0.15 x 0.20 x 1.00 = 4.13 4.13 m3
Pembesian dg Besi Polos atau Besi Ulir P jmlh bj
- tulangan pokok 137.60 x 6.00 x 0.62 x 1.00 = 508.98
137.60 x 0.00 x 0.39 x 1.00 = 0.00
- begel 0.75 x 917 x 0.22 x 1.00 = 152.69
661.68 kg
Memasang Bekisting untuk Kolom 0.70 x 137.60 x 1.00 = 96.32 96.32 m2
7 Membuat Ring Balok Beton Bertulang (10 x 15) cm 36.00 x 2.00 = 72.00 2.00 = 144.00 m
1 Pas Rangka Hollow 1x40.40.0,6 mm Modul 60x60 cm 5.85 x 5.85 x 6.00 = 205.34 2.00 = 410.67 m2
2 Pas Langit2 Kalsiboard, Uk 120x240 tbl 3,5 mm = 410.67 m2
3 List Langit-Langit Kayu Profil
- teras 18.00 x 6.00 = 108.00 2.00 = 216.00
- ruang 18.00 x 6.00 = 108.00 2.00 = 216.00
= 432.00 m
VIII PEKERJAAN BESI dan ALUMUNIUM
P L T Q LxT xQ total sat
1 Pemasangan Rolling Door Allumunium 2.75 x 2.10 x 24.00 = 138.60 138.60 m2
2 Pasang Kusen dan Pintu Besi Strip finishing cat 0.90 x 2.10 x 24.00 = 45.36 45.36 m2
3 Pasang Kusen Jendela Alumunium 4.60 x 24.00 = 110.40 110.40 m
4 Pasang Jendela kaca 4.60 x 0.08 x 24.00 = 8.83 8.83 m2
5 Pasang Rangka Kusen Partisi Alumunium 17.40 x 24.00 = = 417.60 m
6 Pasang Kaca Es 5mm
- kaca jendela sleding 0.94 x 1.04 x 24.00 = 23.46
- kaca partisi 0.95 x 0.95 x 144.00 = 129.96
= 153.42 m2
IX PEKERJAAN KUNCI dan AKSESORIS
XI PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex luar ruangan
- dinding baru = 846.42 m2
2 Pengecat Plafond Baru dengan Mowilex = 410.67 m2
I PEKERJAAN TANAH
MT -0,2 P L T Q PxLxT xQ total sat
1 Menggali Tanah Biasa Sedalam 1 m 35.00 x 2.00 = 70.00
6.00 x 8.00 = 48.00
3.00 x 7.00 = 21.00
139.00
139.00 x 0.50 x 0.50 x 1.00 = 34.75 = 34.75 m3
2 Pengurugan Kembali 0.30 x 34.75 = 10.43 m3
3 Urugan tanah padas dan dipadatkan 35.00 x 6.00 x 0.20 x 1.00 = 42.00 = 42.00 m3
4 Pemasangan trucuk bambu Ø 10 cm panjang 6 m (SNI) = 12.00 ttk
II PEKERJAAN PONDASI
P L T Q PxLxT xQ total sat
1 Pemasang Batu Kosong/Anstamping 139.00 x 0.50 x 0.20 x 1.00 = 13.90 = 13.90 m3
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 139.00 x 0.30 x 0.40 x 1.00 = 16.68 = 16.68 m3
3 Pas Pond Rollag Trashraam bt mrh 1PC : 3PS 35.00 x 0.20 x 0.10 x 1.00 = 0.70 0.70 m3
V PEKERJAAN BETON
P L T Q PxLxTxQ total sat
1 Membuat Kolom Beton Bertulang 15x20
Membuat Beton mutu MPa (K225) 2.85 x 0.15 x 0.20 x 24.00 = 2.05 = 2.05 m3
Pembesian dg Besi Polos atau Besi Ulir P jmlh bj
- tulangan pokok 2.85 x 4.00 x 0.62 x 24.00 = 168.67
- begel 0.65 x 19.00 x 0.39 x 24.00 = 116.95
= 285.62 kg
Memasang Bekisting untuk Kolom 2.85 x 0.60 x 24.00 = 41.04 m2
XI PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex luar ruangan = 507.62 m2
- dinding baru
2 Pengecat Plafond Baru dengan Mowilex = 209.72 m2
C KAMAR MANDI / WC
I PEKERJAAN TANAH
P L T Q PxLxT xQ total sat
1 Menggali Tanah Biasa Sedalam 1 m
- Foot Plat 0.90 x 0.90 x 1.60 x 4.00 = 5.18
- Galian Pondasi
vertikal 8.00 x 2.00 = 16.00
3.00 x 3.00 = 9.00
2.50 x 1.00 = 2.50
horisontal 6.00 x 4.00 = 24.00
3.00 x 1.00 = 3.00
54.50
54.50 x 0.60 x 0.60 x 1.00 = 19.62
= 24.80 m3
2 Pengurugan Kembali 0.30 x 24.80 = 7.44 m3
3 Urugan tanah padas dan dipadatkan 9.00 x 6.00 x 0.20 x 1.00 = 10.80 m3
4 Pemasangan trucuk bambu Ø 10 cm panjang 6 m (SNI) = 4.00 ttk
II PEKERJAAN PONDASI
P L T Q PxLxT xQ total sat
1 Pemasang Batu Kosong/Anstamping 54.50 x 0.60 x 0.20 x 1.00 = 6.54 = 6.54 m3
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 54.50 x 0.35 x 0.40 x 1.00 = 7.63 = 7.63 m3
3 Pas Pond Rollag Trashraam bt mrh 1PC : 3PS
V PEKERJAAN BETON
P L T Q PxLxTxQ total sat
1 Membuat Beton mutu f'c=7,4 Mpa (K100) 0.80 x 0.80 x 0.05 x 4.00 = 0.13 m3
2 Membuat Foot Plat 80x80
Membuat Beton mutu MPa (K225) 0.80 x 0.80 x 0.20 x 4.00 = 0.51 m3
Pembesian dg Besi Polos atau Besi Ulir P x jmlh x bj = 68.72 kg
- tulangan atas 1.20 x 12.67 x 0.62 x 4.00 = 37.48
- tulangan bawah 1.00 x 12.67 x 0.62 x 4.00 = 31.24
68.72
Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 3.20 x 0.00 x 0.20 x 4.00 = 2.56 m2
1 Membuat Kolom Beton Bertulang 15x20 3.55 x 4.00 14.20 m
Membuat Beton mutu MPa (K225) 0.20 x 0.15 x 3.55 x 4.00 = 0.43 = 0.43 m3
Pembesian dg Besi Polos atau Besi Ulir P jmlh bj
- tulangan pokok 14.20 x 4.00 x 0.89 = 50.42
14.20 x 2.00 x 0.62 = 17.51
- begel 0.75 x 94.67 x 0.39 = 28.01
= 95.95 kg
Memasang Bekisting untuk Kolom 0.70 x 3.55 x 4.00 = 9.94 m2
2 Membuat Beton Bertulang Kolom Praktis 11x11 cm 3.55 x 9.00 = 31.95 = 62.95 m
umpak 0.50 x 14.00 = 7.00
kolom tepi 3.00 x 8.00 = 24.00
X PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex luar ruangan = 72.09 m2
2 Pengecatan 1 m2 permukaan Besi 3x (SNI)
a. Plat Landas Tebal 8 mm 0.20 x 0.15 x 7.00 = 0.21
b. Pengaku Pipa Galvanis dia 2 " tbl 2,9 mm 0.15 x 1.00 x 14.00 = 0.00
c. Kolom Besi Pipa Galvanis dia 2,5" tbl 3,2 mm 0.19 x 2.75 x 16.00 = 8.46
b. Kuda - Kuda Canal CNP Rangkap 125x50x20x2,3 0.45 x 8.80 x 7.00 = 27.72
c. Gording Besi Canal CNP 125x50x20x2,3 0.22 x 9.50 5.00 = 10.21
f. Mur Baut dia 13 mm
g. Regel Pengaku Besi Pipa Galvanis dia 2" tbl 2,9 mm 0.15 x 8.30 x 4.00 = 4.98
= 51.58
Hitung Septiktank P L T Q
1 Menggali Tanah Biasa Sedalam 1 m 1.20 x 1.50 x 2.00 = 3.60 62,875.00 = 226,350.00
2 Pemasangan Pipa Beton Ø 100 cm 3.00 = 3.00 1,119,528.90 = 3,358,586.70
3 Membuat Beton mutu f'c=7,4 Mpa (K100) 0.79 x 0.05 x 1.00 = 0.04 973,662.43 = 38,216.25
4 Agregat Pecah Kasar 0.79 x 0.70 x 1.00 = 0.55 220,000.00 = 120,890.00
5 Ijuk 0.10 x 1.00 = 0.10 50,000.00 = 5,000.00
6 Plat Beton 0.79 x 0.10 x 2.00 = 0.20 1,106,174.59 = 221,234.92
besi 110 kg/m3 0.20 x 110.00 = 22.00 13,683.00 = 301,026.00
begisting papan randu 0.79 x 2.00 = 1.57 99,770.00 = 156,638.90
7 Pipa PVC DN 25 ( ¾" ) AW 3.00 m 3.00 4,800.00 = 14,400.00
8 Pipa PVC DN 90 ( 3" ) AW 1.00 m 1.00 29,700.00 = 29,700.00
4,472,042.77
Hitung Resapan
1 Menggali Tanah Biasa Sedalam 1 m 1.00 x 0.50 x 1.00 = 0.50 62,875.00 ;= 31,437.50
Pemasangan Pipa Beton Ø 100 cm 1.00 = 1.00 1,119,528.90 ;= 1,119,528.90
Agregat Pecah Kasar 0.79 x 0.70 x 0.00 = 0.00 220,000.00 ;= 0.00
Ijuk 0.10 x 0.05 = 0.01 50,000.00 ;= 250.00
Plat Beton 0.79 x 0.10 x 1.00 = 0.10 1,106,174.59 ;= 110,617.46
besi 110 kg/m3 0.10 x 80.00 = 8.00 13,683.00 ;= 109,464.00
begisting papan randu 0.79 x 1.00 = 0.79 99,770.00 ;= 78,319.45
Pipa PVC DN 25 ( ¾" ) AW
Pipa PVC DN 90 ( 3" ) AW 1,449,617.31
REKAPITULASI
RENCANA ANGGARAN DAN BIAYA
JUMLAH 1,600,185,791.91
PPN 10 % 160,018,579.19
JUMLAH TOTAL 1,760,204,371.10
DIBULATKAN 1,760,200,000.00
TERBILANG : Err:511
Jepara, 2019
PEJABAT PEMBUAT KOMITMEN Konsultan Perencana
DINAS PARIWISATA DAN KEBUDAYAAN CV. ARDIKON CIPTA ARTISTIKA
KABUPATEN JEPARA
14,426,373.00
B LOS KIOS MAKANAN
I PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m 97.44 m3 A.2.3.1.1 62,875.00 6,126,540.00
2 Pengurugan Kembali 29.23 m3 A.2.3.1.9 15,250.00 445,788.00
3 Urugan tanah padas dan dipadatkan 86.40 m3 A.2.3.1.17 118,066.75 10,200,967.17
4 Pemasangan trucuk bambu Ø 10 cm panjang 6 m (SNI) 16.00 ttk A.2.3.1.19 22,884.33 366,149.25
17,139,444.42
II PEKERJAAN PONDASI
1 Pemasang Batu Kosong/Anstamping 27.360 m3 A.3.2.1.9 452,513.40 12,380,766.62
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 31.920 m3 A.3.2.1.5.1 899,089.00 28,698,920.88
3 Pasang Pondasi Rolag Trashraam BT Mrh 1 Pc : 3 Ps 1.440 m3 A.3.2.1.12 1,207,075.00 1,738,188.00
42,817,875.50
III PEKERJAAN PASANGAN DINDING
1 Pasang Din Bt Mrh Kalipucang tbl 1/2 bt 1 SP:8PP Muntilan 336.060 m2 A.4.4.1.12.2 110,750.00 37,218,645.00
37,218,645.00
IV PEKERJAAN PLESTERAN
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan 174.300 m2 A.4.4.2.3 64,000.20 11,155,234.86
2 Pasang Plesteran 1 Pc : 8 Pp tbl 15 mm Ps Muntilan 672.120 m2 A.4.4.2.8 - -
3 Pemasangan Acian 846.420 m2 A.4.4.2.27 32,962.50 27,900,119.25
39,055,354.11
V PEKERJAAN BETON
1 Membuat Beton mutu f'c=7,4 Mpa (K100) 0.512 m3 A.4.1.1.1 973,662.43 498,515.16
Membuat
2 Foot Plat 80x80
a. Membuat Beton mutu MPa (K225) 2.048 m3 A.4.1.1.7 1,106,174.59 2,265,445.55
b. Pembesian dg Besi Polos atau Besi Ulir 274.877 kg A.4.1.1.17 13,683.00 3,761,139.25
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 10.240 m2 A.4.1.1.37 99,770.00 1,021,644.80
3 Membuat Sloof Beton Bertulang 15x25
a. Membuat Beton mutu MPa (K225) 8.550 m3 A.4.1.1.7 1,106,174.59 9,457,792.72
b. Pembesian dg Besi Polos atau Besi Ulir 1570.546 kg A.4.1.1.17 13,683.00 21,489,782.01
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 114.000 m2 A.4.1.1.37 99,770.00 11,373,780.00
4 Membuat Kolom Beton Bertulang 15x20
a. Membuat Beton mutu MPa (K225) 4.128 m3 A.4.1.1.7 1,106,174.59 4,566,288.70
b. Pembesian dg Besi Polos atau Besi Ulir 661.677 kg A.4.1.1.17 13,683.00 9,053,728.03
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 96.320 m2 A.4.1.1.37 99,770.00 9,609,846.40
5 Membuat Beton bertulang Kolom Praktis 11x11 cm 100.800 m1 A.4.1.1.35 69,841.10 7,039,982.88
6 Membuat Balok Beton Bertulang 15x30
a. Membuat Beton mutu MPa (K225) 7.020 m3 A.4.1.1.7 1,106,174.59 7,765,345.60
b. Pembesian dg Besi Polos atau Besi Ulir 1136.510 kg A.4.1.1.17 13,683.00 15,550,871.15
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 117.000 m2 A.4.1.1.37 99,770.00 11,673,090.00
7 Membuat Ring Balok Beton Bertulang (10 x 15) cm 144.000 m1 A.4.1.1.36 109,298.81 15,739,029.00
8 Membuat Ring Balk 15x20
a. Membuat Beton mutu MPa (K225) 4.320 m3 A.4.1.1.7 1,106,174.59 4,778,674.22
b. Pembesian dg Besi Polos atau Besi Ulir 639.483 kg A.4.1.1.17 13,683.00 8,750,047.53
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 79.200 m2 A.4.1.1.37 99,770.00 7,901,784.00
HARGA SATUAN JUMLAH HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME ANALISA
Rp Rp Rp
9 Membuat Meja Dapur Beton tbl 10 cm
a. Membuat Beton mutu MPa (K225) 3.072 m3 A.4.1.1.7 1,106,174.59 3,398,168.33
b. Pembesian dg Besi Polos atau Besi Ulir 457.058 kg A.4.1.1.17 13,683.00 6,253,928.77
c. Memasang Bekisting untuk Lantai 38.400 m2 A.4.1.1.24 205,645.00 7,896,768.00
169,845,652.12
VI PEKERJAAN ATAP
1 Pasang Konstruksi Atap Baja Ringan SNI 606.800 m2 Taksir 185,000.00 112,258,000.00
2 Pemasangan 1 m2 onduline ukuran 95 x 200 621.600 m2 A.4.5.2.41 147,217.50 91,510,398.00
3 Pasang Krepus Onduline 74.000 m1 Taksir 140,000.00 10,360,000.00
214,128,398.00
VII PEKERJAAN LANGIT - LANGIT
1 Pas Rangka Hollow 1x40.40.0,6 mm Modul 60x60 cm 410.670 m2 A.4.2.1.21 116,945.00 48,025,803.15
2 Pas Langit2 Kalsiboard, Uk 120x240 tbl 3,5 mm 410.670 m2 A.4.5.1.8 37,155.38 15,258,597.85
63,284,401.00
VIII PEKERJAAN BESI dan ALUMUNIUM
1 Pemasangan Rolling Door Allumunium 138.600 m2 A.4.2.1.10 630,843.75 87,434,943.75
2 Pasang Kusen dan Pintu Besi Strip finishing cat 45.360 m2 Taksir 350,000.00 15,876,000.00
3 Pasang Kusen Jendela Alumunium 110.400 m1 A.4.2.1.11 126,524.50 13,968,304.80
4 Pasang Jendela kaca 8.832 m2 A.4.2.1.13 477,020.00 4,213,040.64
5 Pasang Rangka Kusen Partisi Alumunium 417.600 m1 A.4.2.1.11 126,524.50 52,836,631.20
6 Pasang Kaca Es 5mm 153.422 m2 A.4.6.2.17 149,936.25 23,003,579.32
197,332,499.71
IX PEKERJAAN KUNCI dan AKSESORIS
1 Pemasangan Kunci Selot 34.000 bh A.4.6.2.11 36,916.88 1,255,173.75
2 Pemasangan Engsel Jendela Kupu-kupu 68.000 bh A.4.6.2.6 30,457.50 2,071,110.00
3 Pemasangan Kait Angin 68.000 bh A.4.6.2.9 25,670.00 1,745,560.00
5,071,843.75
X PEKERJAAN SANITASI
1 Pasang Instalasi Air Bersih 1.000 ls Taksir 1,500,000.00 1,500,000.00
2 Pemasangan Instalasi Air Kotor 1.000 ls Taksir 1,000,000.00 1,000,000.00
3 Resapan Air Kotor 4.000 ls Taksir 1,449,617.31 5,798,469.23
4 Pemasangan Kran Ø ½" atau Ø ¾" 34.000 bh A.5.1.1.19 71,577.50 2,433,635.00
5 Pemasangan Bak Cuci Piring Stainless stell 34.000 bh A.5.1.1.12 273,525.00 9,299,850.00
20,031,954.23
XI PEKERJAAN LISTRIK
1 Pasang Meteran Listrik 2200VA 4.000 bh Taksir 3,000,000.00 12,000,000.00
2 Pasang Instalasi Listrik 48.000 ttk Taksir 110,000.00 5,280,000.00
3 Pasang Lampu SL 15 watt 48.000 bh Taksir 45,000.00 2,160,000.00
4 Pasang Saklar Ganda 24.000 bh Taksir 45,000.00 1,080,000.00
5 Pasang Stop Kontak 24.000 bh Taksir 35,000.00 840,000.00
21,360,000.00
XII PEKERJAAN PENUTUP LANTAI dan DINDING
1 Pemasangan Lantai Keramik 40 x 40 cm warna 416.070 m2 A.4.4.3.35.2 238,410.00 99,195,248.70
99,195,248.70
XII PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex luar ruangan 846.420 m2 A.4.7.1.10.2 42,072.75 35,611,217.06
2 Pengecat Plafond Baru dengan Mowilex 410.670 m2 A.4.7.1.10.1 26,998.00 11,087,268.66
46,698,485.72
C LOS KIOS KERAJINAN
I PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m 34.750 m3 A.2.3.1.1 62,875.00 2,184,906.25
2 Pengurugan Kembali 10.425 m3 A.2.3.1.9 15,250.00 158,981.25
3 Urugan tanah padas dan dipadatkan 42.000 m3 A.2.3.1.17 118,066.75 4,958,803.48
7,302,690.98
HARGA SATUAN JUMLAH HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME ANALISA
Rp Rp Rp
II PEKERJAAN PONDASI
1 Pemasang Batu Kosong/Anstamping 13.900 m3 A.3.2.1.9 452,513.40 6,289,936.26
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 16.680 m3 A.3.2.1.5.1 899,089.00 14,996,804.52
3 Pas Pond Rollag Trashraam bt mrh 1PC : 3PS 0.700 m3 A.3.2.1.12 1,207,075.00 844,952.50
22,131,693.28
III PEKERJAAN PASANGAN DINDING
1 Pasang Din Bt Mrh Kalipucang tbl 1/2 bt 1 SP:8PP Muntilan 226.860 m2 A.4.4.1.12.2 110,750.00 25,124,745.00
25,124,745.00
IV PEKERJAAN PLESTERAN
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan 53.900 m2 A.4.4.2.3 64,000.20 3,449,610.78
2 Pasang Plesteran 1 Pc : 8 Pp tbl 15 mm Ps Muntilan 453.720 m2 A.4.4.2.8 - -
3 Pemasangan Acian 507.620 m2 A.4.4.2.27 32,962.50 16,732,424.25
20,182,035.03
V PEKERJAAN BETON
1 Membuat Kolom Beton Bertulang 15x20
a. Membuat Beton mutu MPa (K225) 2.052 m3 A.4.1.1.7 1,106,174.59 2,269,870.25
b. Pembesian dg Besi Polos atau Besi Ulir 285.622 kg A.4.1.1.17 13,683.00 3,908,165.61
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 41.040 m2 A.4.1.1.37 99,770.00 4,094,560.80
2 Membuat Sloof Beton Bertulang 15x20
a. Membuat Beton mutu MPa (K225) 5.220 m3 A.4.1.1.7 1,106,174.59 5,774,231.35
b. Pembesian dg Besi Polos atau Besi Ulir 938.540 kg A.4.1.1.17 13,683.00 12,842,041.07
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 69.600 m2 A.4.1.1.37 99,770.00 6,943,992.00
3 Membuat Beton Bertulang Kolom Praktis 11x11 cm 59.850 m1 A.4.1.1.35 69,841.10 4,179,989.84
4 Membuat Ring Balok Beton Bertulang (10 x 15) cm 161.000 m1 A.4.1.1.36 109,298.81 17,597,108.81
5 Membuat Ring Balk Beton Bertulang 15x30
a. Membuat Beton mutu MPa (K225) 3.735 m3 A.4.1.1.7 1,106,174.59 4,131,562.08
b. Pembesian dg Besi Polos atau Besi Ulir 513.742 kg A.4.1.1.17 13,683.00 7,029,528.78
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 62.250 m2 A.4.1.1.37 99,770.00 6,210,682.50
74,981,733.08
VI PEKERJAAN ATAP
1 Pasang Konstruksi Atap Baja Ringan SNI 295.200 m2 Taksir 185,000.00 54,612,000.00
2 Pemasangan 1 m2 onduline ukuran 95 x 200 302.400 m2 A.4.5.2.41 147,217.50 44,518,572.00
3 Pasang Krepus Onduline 36.000 m1 Taksir 140,000.00 5,040,000.00
104,170,572.00
VII PEKERJAAN LANGIT - LANGIT
1 Pas Rangka Hollow 1x40.40.0,6 mm Modul 60x60 cm 209.723 m2 A.4.2.1.21 116,945.00 24,525,997.76
2 Pas Langit2 Kalsiboard, Uk 120x240 tbl 3,5 mm 209.723 m2 A.4.5.1.8 37,155.38 7,792,318.13
32,318,315.90
VIII PEKERJAAN BESI dan ALUMUNIUM
1 Pemasangan Rolling Door Allumunium 66.150 m2 A.4.2.1.10 630,843.75 41,730,314.06
2 Pasang Kusen dan Pintu Besi Strip finishing cat 26.460 m2 Taksir 350,000.00 9,261,000.00
3 Pasang Kusen Jendela Alumunium 61.600 m1 A.4.2.1.11 126,524.50 7,793,909.20
4 Pasang Jendela kaca 4.928 m2 A.4.2.1.13 477,020.00 2,350,754.56
5 Pasang Rangka Kusen Partisi Alumunium 243.600 m1 A.4.2.1.11 126,524.50 30,821,368.20
6 Pasang Kaca Es 5mm 26.321 m2 A.4.6.2.17 149,936.25 3,946,532.01
95,903,878.03
IX PEKERJAAN KUNCI dan AKSESORIS
1 Pemasangan Kunci Selot 14.000 bh A.4.6.2.11 36,916.88 516,836.25
2 Pemasangan Engsel Jendela Kupu-kupu 28.000 bh A.4.6.2.6 30,457.50 852,810.00
3 Pemasangan Kait Angin 28.000 bh A.4.6.2.9 25,670.00 718,760.00
2,088,406.25
X PEKERJAAN LISTRIK
1 Pasang Meteran Listrik 1300VA 3.000 bh Taksir 2,000,000.00 6,000,000.00
2 Pasang Instalasi Listrik 28.000 ttk Taksir 110,000.00 3,080,000.00
3 Pasang Lampu SL 15 watt 28.000 bh Taksir 45,000.00 1,260,000.00
4 Pasang Saklar Ganda 14.000 bh Taksir 45,000.00 630,000.00
5 Pasang Stop Kontak 14.000 bh Taksir 35,000.00 490,000.00
11,460,000.00
HARGA SATUAN JUMLAH HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME ANALISA
Rp Rp Rp
XI PEKERJAAN PENUTUP LANTAI dan DINDING
1 Pemasangan Lantai Keramik 40 x 40 cm warna 198.765 m2 A.4.4.3.35.2 238,410.00 47,387,563.65
2 Pemasangan Dinding Keramik 20x25 cm,
3 Pemasangan Paving Grees Block
47,387,563.65
XII PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex luar ruangan 507.620 m2 A.4.7.1.10.2 42,072.75 21,356,969.36
2 Pengecat Plafond Baru dengan Mowilex 209.723 m2 A.4.7.1.10.1 26,998.00 5,662,088.06
27,019,057.41
D KAMAR MANDI / WC
I PEKERJAAN TANAH
1 Menggali Tanah Biasa Sedalam 1 m 24.804 m3 A.2.3.1.1 62,875.00 1,559,551.50
2 Pengurugan Kembali 7.441 m3 A.2.3.1.9 15,250.00 113,478.30
3 Urugan tanah padas dan dipadatkan 10.800 m3 A.2.3.1.17 118,066.75 1,275,120.90
4 Pemasangan trucuk bambu Ø 10 cm panjang 6 m (SNI) 4.000 ttk A.2.3.1.19 22,884.33 91,537.31
3,039,688.01
II PEKERJAAN PONDASI
1 Pemasang Batu Kosong/Anstamping 6.540 m3 A.3.2.1.9 452,513.40 2,959,437.64
2 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan 7.630 m3 A.3.2.1.5.1 899,089.00 6,860,049.07
3 Pas Pond Rollag Trashraam bt mrh 1PC : 3PS
9,819,486.71
III PEKERJAAN PASANGAN DINDING
1 Pasang Din Bt Mrh Kalipucang tbl 1/2 bt 1 SP:8PP Muntilan 52.725 m2 A.4.4.1.12.2 110,750.00 5,839,293.75
5,839,293.75
IV PEKERJAAN PLESTERAN
1 Pasang Plesteran 1 Pc : 3 Pp tbl 15 mm Ps Muntilan 72.085 m2 A.4.4.2.8 - -
2 Pemasangan Acian 72.085 m2 A.4.4.2.27 32,962.50 2,376,101.81
2,376,101.81
V PEKERJAAN BETON
1 Membuat Beton mutu f'c=7,4 Mpa (K100) Foot Plat 80x80 0.128 m3 A.4.1.1.1 973,662.43 124,628.79
a. Membuat Beton mutu MPa (K225) 0.512 m3 A.4.1.1.7 1,106,174.59 566,361.39
b. Pembesian dg Besi Polos atau Besi Ulir 68.719 kg A.4.1.1.17 13,683.00 940,284.81
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 2.560 m2 A.4.1.1.37 99,770.00 255,411.20
1 Membuat Kolom Beton Bertulang 15x20
a. Membuat Beton mutu MPa (K225) 0.426 m3 A.4.1.1.7 1,106,174.59 471,230.37
b. Pembesian dg Besi Polos atau Besi Ulir 95.947 kg A.4.1.1.17 13,683.00 1,312,844.55
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 9.940 m2 A.4.1.1.37 99,770.00 991,713.80
2 Membuat Beton Bertulang Kolom Praktis 11x11 cm 62.950 m1 A.4.1.1.35 69,841.10 4,396,497.25
3 Membuat Ring Balk Beton Bertulang 15x30
a. Membuat Beton mutu MPa (K225) 0.540 m3 A.4.1.1.7 1,106,174.59 597,334.28
b. Pembesian dg Besi Polos atau Besi Ulir 93.905 kg A.4.1.1.17 13,683.00 1,284,905.95
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 9.000 m2 A.4.1.1.37 99,770.00 897,930.00
4 Membuat Ring Balk Beton Bertulang 15/20
a. Membuat Beton mutu MPa (K225) 0.735 m3 A.4.1.1.7 1,106,174.59 813,038.32
b. Pembesian dg Besi Polos atau Besi Ulir 138.959 kg A.4.1.1.17 13,683.00 1,901,377.37
c. Pasang Bekisting Beton dg Kayu Randu tbl 2 cm 13.475 m2 A.4.1.1.37 99,770.00 1,344,400.75
5 Membuat Dak Plat Beton Tebal 12 cm
a. Membuat Beton mutu MPa (K225) 1.080 m3 A.4.1.1.7 1,106,174.59 1,194,668.55
b. Pembesian dg Besi Polos atau Besi Ulir 147.960 kg A.4.1.1.17 13,683.00 2,024,536.68
c. Memasang Bekisting untuk Lantai 9.000 m2 A.4.1.1.24 205,645.00 1,850,805.00
20,967,969.06
VI PEKERJAAN ATAP
1 Pekerjaan Besi Konstruksi Atap
a. Plat Landas Tebal 8 mm 13.545 kg A.4.2.1.1 39,280.50 532,054.37
b. Kuda - Kuda Canal CNP Rangkap 125x50x20x2,3 587.202 kg A.4.2.1.1 39,280.50 23,065,588.16
c. Gording Besi Canal CNP 125x50x20x2,3 214.225 kg A.4.2.1.1 39,280.50 8,414,865.11
2 Pemasangan 1 m2 onduline ukuran 95 x 200 85.500 m2 A.4.5.2.41 147,217.50 12,587,096.25
3 Pasang List Plank Grc L 20 cm 37.000 m1 Taksir 80,000.00 2,960,000.00
4 Pasang Krepus Onduline 9.500 m1 Taksir 140,000.00 1,330,000.00
48,889,603.90
HARGA SATUAN JUMLAH HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME ANALISA
Rp Rp Rp
VII PEKERJAAN BESI dan ALUMUNIUM
1 Pasang Kosen + Pintu PVC ber Motif 4.000 bh Taksir 750,000.00 3,000,000.00
2 Pemasangan Kaca tebal 5 mm 1.200 m2 A.4.2.1.13 477,020.00 572,424.00
3,572,424.00
VIII PEKERJAAN SANITASI
1 Memasang Closet Jongkok Porselen 4.000 bh A.5.1.1.2 413,157.50 1,652,630.00
2 Pemasangan Floor Drain 8.000 bh A.5.1.1.14 35,575.00 284,600.00
3 Pemasangan Kran Ø ½" atau Ø ¾" 4.000 bh A.5.1.1.19 71,577.50 286,310.00
4 Pemasangan Kran Shower Mandi 4.000 bh Taksir 300,000.00 1,200,000.00
5 Tandon Air 550 ltr 4.000 bh Taksir 1,200,000.00 4,800,000.00
6 Ember Air 4.000 bh Taksir 40,000.00 160,000.00
7 Pasang Instalasi Air Bersih 1.000 ls Taksir 1,500,000.00 1,500,000.00
8 Pemasangan Instalasi Air Kotor 1.000 ls Taksir 1,000,000.00 1,000,000.00
9 Resapan Air Kotor 1.000 bh Taksir 1,449,617.31 1,449,617.31
10 Septiktank 1.000 bh Taksir 4,472,042.77 4,472,042.77
16,805,200.08
IX PEKERJAAN PENUTUP LANTAI dan DINDING
1 Pemasangan Lantai Keramik 30 x 30 cm warna 39.500 m2 A.4.4.3.35 201,479.00 7,958,420.50
2 Pemasangan Lantai Keramik 20 x 20 cm 13.000 m2 A.4.4.3.36 206,645.00 2,686,385.00
3 Pemasangan Dinding Keramik 20x25 cm, 26.000 m2 A.4.4.3.55 225,990.00 5,875,740.00
4 Pemasangan Dinding Batu Paras / Batu Tempel Hitam 9.000 m2 A.4.4.3.58 278,057.81 2,502,520.31
5 Pasang Batu Paras Motif Ukir 2.000 m2 Taksir 1,200,000.00 2,400,000.00
21,423,065.81
X PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru dengan Mowilex luar ruangan 72.085 m2 A.4.7.1.10.2 42,072.75 3,032,814.18
2 Pengecatan 1 m2 permukaan Besi 3x (SNI) 51.585 m2 A.4.7.1.22 41,160.94 2,123,278.73
5,156,092.91
XI PEKERJAAN LISTRIK
1 Pasang Meteran Listrik 1300VA 1.000 bh Taksir 2,000,000.00 2,000,000.00
2 Pasang Instalasi Listrik 8.000 ttk Taksir 110,000.00 880,000.00
3 Pasang Lampu SL 15 watt 8.000 bh Taksir 45,000.00 360,000.00
4 Pasang Saklar Ganda 4.000 bh Taksir 45,000.00 180,000.00
5 Pasang Stop Kontak 2.000 bh Taksir 35,000.00 70,000.00
6 Pasang Mesin Pompa Air Otomatis 1.000 bh Taksir 1,130,000.00 1,130,000.00
4,620,000.00
TOTAL 1,600,185,791.91
PPN 10 % 160,018,579.19
JUMLAH TOTAL 1,760,204,371.10
DIBULATKAN 1,760,200,000.00
TERBILANG :
Err:511
Jepara, 2019
PEJABAT PEMBUAT KOMITMEN Konsultan Perencana
DINAS PARIWISATA DAN KEBUDAYAAN CV. ARDIKON CIPTA ARTISTIKA
KABUPATEN JEPARA
HARGA
NO. PERALATAN SATUAN SEWA ALAT KET.
(Rp)
18 Molen hr 250,000
Ir. BUDIARTO, MT
Pembina Utama Madya
NIP. 19590410 198603 1 015
DAFTAR UPAH TENAGA KERJA
KABUPATEN JEPARA TAHUN 2019
2 Mandor Hr 115,000
23 Operator Hr 100,000
26 Supir Hr 100,000
28 Mekanik Hr 100,000
Ir. BUDIARTO, MT
Pembina Utama Madya
NIP. 19590410 198603 1 015
DAFTAR HARGA SATUAN BAHAN BANGUNAN
KABUPATEN JEPARA TAHUN 2018
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
I. B A H A N DASAR
1 BATU KALI
Pecah 15/20 m3 243,720
Pecah 5/7 m3 275,000
Pecah 3/5 m3 275,000
2 KERIKIL Timbun/Sirtu m3 125,000
Beton/Ciping 0,5/1 m3 215,000
Beton ,1/2 m3 217,100
Beton ,2/3 m3 215,900
Abu batu m3 190,000
AGREGAT (ANALISA SARINGAN)
Agregat Pecah Kasar M3 220,000
Agg. Halus LP A M3 220,000
Lolos screen1 ukuran ( 0 - 5) / aggr. 3 -5 m3 275,000
Lolos screen2 ukuran ( 0 - 5) / abu batu m3 190,000
Lolos screen2 ukuran ( 5 - 9,5) / chipping m3 275,000
Lolos screen2 ukuran ( 9.5 - 19,0) / aggr. 1 - 2 m3 275,000
3 BATU BATA Kudus bh 900
Kalipucang/Clering bh 560
4 BATA RINGAN Uk. 60x20x7,5 cm bh 10,000
Uk. 60x20x10 cm bh 12,000
5 PASIR Urug m3 115,450
Pasang lokal m3 195,750
Beton/Muntilan m3 450,000
6 TANAH Padas m3 60,600
Liat/tanah merah m3 54,000
7 KAPUR Pasang m3 402,800
Semen Merah m3 172,500
8 PORTLAND CEMENT
Semen PC kg 1,450
Semen Putih kg 2,180
Semen warna kg 12,000
9 SEMEN MORTAR Mortar Perekat kg 2,125
Mortar Plesteran kg 1,380
Mortar Acian kg 2,125
4 ASBES PLAT
. 100cm X 100 cm X 4 mm bh 25,700
60 x 60 cm bh 55,800
V.BAHAN CETAK
1 BUIS BETON
Ø 20 cm - 100 cm bh 78,700
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
Ø 30 cm - 100 cm bh 102,900
Ø 60 cm - 100 cm bh 227,400
Ø 80 cm - 100 cm bh 387,300
Ø 100 cm - 100 cm bh 486,700
U 15 cm - 100 cm bh 38,700
U 20 cm - 100 cm bh 46,200
U 30 cm - 100 cm bh 76,200
VI . B A H A N B E S I
1 BESI BETON besi beton polos/Ulir kg 9,500
besi beton prestress kg 16,000
VII . B A H A N P I P A
1 Pipa PVC AW
Pipa PVC DN 20 ( ½" ) AW m' 6,625
Pipa PVC DN 25 ( ¾" ) AW m' 7,750
Pipa PVC DN 32 ( 1" ) AW m' 9,625
Pipa PVC DN 40 ( 1½" ) AW m' 11,250
Pipa PVC DN 63 ( 2" ) AW m' 13,125
Pipa PVC DN 90 ( 3" ) AW m' 27,500
Pipa PVC DN 110 ( 4" ) AW m' 36,250
Pipa PVC DN 160 ( 6" ) AW m' 43,750
Pipa PVC DN 200 ( 8" ) AW m' 52,500
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
Pipa PVC DN 250 ( 10" ) AW m' 87,500
VIII . B A H A N L A N G I T - L A N G I T
1 List Kayu Profil Mahoni m' 11,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 65,000
List Gypsum m' 25,000
3 PLY WOOD
Teak wood
. 90 X 210 X 4 mm lbr 80,000
Tripleks
. 120 X 240 X 3 mm lbr 50,000
. 120 X 240 X 4 mm lbr 58,000
. 120 X 240 X 6 mm lbr 71,300
. 120 X 240 X 9 mm lbr 125,000
Multipleks
. 120 X 240 X 9 mm lbr 102,000
4 KalsiBoard
. 120 X 240 X 3,5 mm lbr 48,000
. 120 X 240 X 4,5 mm lbr 55,000
5 Formika ukuran pintu lbr 58,000
IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 35,000
Dempul plamur kg 32,800
Ambril/amplas lbr 6,500
Cat dasar kg 33,500
cat kayu kg 52,500
Kuas bh 13,200
Sirlak ons 16,900
Spiritus ltr 12,000
Vernish ltr 27,900
2 TEMBOK
Kalkarium kg 6,900
Kapur sirih kg 6,600
Plamur kg 16,000
Undercoat/cat dasar kg 19,000
Cat Tembok Decolite kg 48,000
Mowilex Dalam Ruangan kg 56,000
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
Mowilex Luar Ruangan kg 96,000
Cat Waterproof sekualitas No Drop kg 50,000
3 BESI
Menie kg 30,600
Cat besi kg 65,000
Minyak cat/Afduner ltr 20,000
Residu (teer/aspal) drum 68,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 855,700
kapasitas 1100 liter. bh 1,506,400
Lem Aica Aibon kg 35,000
8 LAIN - LAIN
Kran Air bh 25,700
Seal tape bh 4,100
Floor drain bh 23,100
Water drain bh 60,000
XIV . ALAT PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 5" kg 12,800
2 PAKU - sekrup kg 13,000
3 PAKU - sekrup fizzer bh 1,600
4 PAKU - sumbat / kait kg 7,500
5 MUR BAUT (kuda-kuda) kg 16,000
6 ANGKUR BAUT bh 14,000
7 LEM KAYU bh 12,800
8 Tali Ijuk kg 25,000
X V . PAVING BLOCK
1 Blok pafing tebal 6 cm lokal m2 55,300
2 Blok pafing tebal 8 cm lokal m2 75,000
3 Blok pafing warna tebal 6 cm lokal m2 51,000
4 Blok pafing warna tebal 8 cm lokal m2 57,500
5 Blok pafing blok tebal 6 cm K.225 Holand m2 89,900
Blok pafing blok tebal 6 cm K.225 Hexagonal m2 89,900
6 Blok pafing blok tebal 8 cm K.300 Holland m2 142,400
Blok pafing blok tebal 8 cm K.300 Unipave/Hexagonal m2 142,400
Blok pafing blok tebal 8 cm K.300 Grassblock m2 140,000
7 Blok pafing blok tebal 8 cm K.400 Holland m2 165,000
Blok pafing blok tebal 8 cm K.400 Unipave/Hexagonal m2 165,000
8 KANSTEEN 15/20x30x50 bh 50,000
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
9 BATACO bh 4,500
10 Glass blox bh 22,600
XVI. L A I N - L A I N
1 Rel Pintu dorong bh 216,200
2 Naco per Daun bh 11,500
3 Rolling door Besi m2 350,000
4 Rolling door Almunium m2 364,000
5 Awning Almunium m2 190,000
6 Profil Alumunium m' 103,200
7 Alumunium strip m' 34,300
8 Besi Hollow 40x40x2 m' 11,300
9 ASPAL.
Aspal Ex Pertamina kg 10,000
10 K A C A
Cermin tebal 5 mm m2 170,000
Ir. BUDIARTO, MT
Pembina Utama Madya
NIP. 19590410 198603 1 015
DAFTAR HARGA SATUAN BAHAN BANGUNAN
KABUPATEN JEPARA TAHUN 2019
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
I. B A H A N DASAR
1 BATU KALI
Pecah 15/20 m3 243,720
Pecah 5/7 m3 275,000
Pecah 3/5 m3 275,000
2 KERIKIL Timbun/Sirtu m3 125,000
Beton/Ciping 0,5/1 m3 215,000
Beton ,1/2 m3 217,100
Beton ,2/3 m3 215,900
Abu batu m3 190,000
AGREGAT (ANALISA SARINGAN)
Agregat Pecah Kasar M3 220,000
Agg. Halus LP A M3 220,000
Lolos screen1 ukuran ( 0 - 5) / aggr. 3 -5 m3 275,000
Lolos screen2 ukuran ( 0 - 5) / abu batu m3 190,000
Lolos screen2 ukuran ( 5 - 9,5) / chipping m3 275,000
Lolos screen2 ukuran ( 9.5 - 19,0) / aggr. 1 - 2 m3 275,000
3 BATU BATA Kudus bh 900
Kalipucang/Clering bh 560
4 BATA RINGAN Uk. 60x20x7,5 cm bh 10,000
Uk. 60x20x10 cm bh 12,000
5 PASIR Urug m3 115,450
Pasang lokal m3 195,750
Beton/Muntilan m3 450,000
6 TANAH Padas m3 60,600
Liat/tanah merah m3 54,000
7 KAPUR Pasang m3 402,800
Semen Merah m3 172,500
8 PORTLAND CEMENT
Semen PC kg 1,450
Semen Putih kg 2,180
Semen warna kg 12,000
9 SEMEN MORTAR Mortar Perekat kg 2,125
Mortar Plesteran kg 1,380
Mortar Acian kg 2,125
4 ASBES PLAT
. 100cm X 100 cm X 4 mm bh 25,700
60 x 60 cm bh 55,800
V.BAHAN CETAK
1 BUIS BETON
Ø 20 cm - 100 cm bh 78,700
Ø 30 cm - 100 cm bh 102,900
Ø 60 cm - 100 cm bh 227,400
Ø 80 cm - 100 cm bh 387,300
Ø 100 cm - 100 cm bh 486,700
U 15 cm - 100 cm bh 38,700
U 20 cm - 100 cm bh 46,200
U 30 cm - 100 cm bh 76,200
VII . B A H A N PIPA
1 Pipa PVC AW
Pipa PVC DN 20 ( ½" ) AW m' 3,600
Pipa PVC DN 25 ( ¾" ) AW m' 4,800
Pipa PVC DN 32 ( 1" ) AW m' 6,600
Pipa PVC DN 40 ( 1½" ) AW m' 11,300
Pipa PVC DN 63 ( 2" ) AW m' 14,500
Pipa PVC DN 90 ( 3" ) AW m' 29,700
Pipa PVC DN 110 ( 4" ) AW m' 49,100
Pipa PVC DN 160 ( 6" ) AW m' 109,150
Pipa PVC DN 200 ( 8" ) AW m' 183,150
Pipa PVC DN 250 ( 10" ) AW m' 283,150
IX . B A H A N FINISHING
1 KAYU
Menie kg 35,000
Dempul plamur kg 32,800
Ambril/amplas lbr 6,500
Cat dasar kg 33,500
cat kayu kg 52,500
Kuas bh 13,200
Sirlak ons 16,900
Spiritus ltr 12,000
Vernish ltr 27,900
2 TEMBOK
Kalkarium kg 6,900
Kapur sirih kg 6,600
Plamur kg 16,000
Undercoat/cat dasar kg 19,000
Cat Tembok Decolite kg 48,000
Mowilex Dalam Ruangan kg 56,000
Mowilex Luar Ruangan kg 96,000
Cat Waterproof sekualitas No Drop kg 50,000
Wallpaper peuntup dinding m2 70,000
3 BESI
Menie kg 30,600
Cat besi kg 65,000
Minyak cat/Afduner ltr 20,000
Residu (teer/aspal) drum 68,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 855,700
kapasitas 1100 liter. bh 1,506,400
Lem Aica Aibon kg 35,000
X.BAHAN KACA
1 POLOS 3 mm m2 85,000
5 mm m2 120,000
8 mm m2 135,000
2 KACA HITAM 3 mm m2 135,000
5 mm m2 150,000
8 mm m2 200,000
8 LAIN - LAIN
Kran Air bh 25,700
Seal tape bh 4,100
Floor drain bh 23,100
Water drain bh 60,000
XIV . ALAT PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 5" kg 12,800
2 PAKU - sekrup kg 13,000
3 PAKU - sekrup fizzer bh 1,600
4 PAKU - sumbat / kait kg 7,500
5 MUR BAUT (kuda-kuda) kg 16,000
6 ANGKUR BAUT bh 14,000
7 LEM KAYU bh 12,800
8 Tali Ijuk kg 25,000
X V . PAVING BLOCK
1 Blok pafing tebal 6 cm lokal m2 55,300
2 Blok pafing tebal 8 cm lokal m2 75,000
HARGA
NO. J E N I S B A H A N SATUAN BAHAN KETERANGAN
(Rp)
3 Blok pafing warna tebal 6 cm lokal m2 51,000
4 Blok pafing warna tebal 8 cm lokal m2 57,500
5 Blok pafing blok tebal 6 cm K.225 Holand m2 90,000
Blok pafing blok tebal 6 cm K.225 Hexagonal m2 104,000
6 Blok pafing blok tebal 8 cm K.300 Holland m2 140,000
Blok pafing blok tebal 8 cm K.300 Unipave/Hexagonal m2 145,000
Blok pafing blok tebal 8 cm K.300 Grassblock m2 150,000
7 Blok pafing blok tebal 8 cm K.400 Holland m2 155,000
Blok pafing blok tebal 8 cm K.400 Unipave/Hexagonal m2 160,000
8 KANSTEEN 15/20x30x50 bh 50,000
9 BATACO bh 4,500
10 Glass blox bh 22,600
XVI. L A I N - L A I N
1 Rel Pintu dorong bh 216,200
2 Naco per Daun bh 11,500
3 Rolling door Besi m2 350,000
4 Rolling door Almunium m2 364,000
5 Awning Almunium m2 190,000
6 Profil Alumunium m' 103,200
7 Alumunium strip m' 34,300
8 Besi Hollow 40x40x0.6 mm m' 11,300
9 ASPAL.
Aspal Ex Pertamina kg 10,000
10 KACA
Cermin tebal 5 mm m2 170,000
Ir. BUDIARTO, MT
Pembina Utama Madya
NIP. 19590410 198603 1 015
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF JUMLAH HARGA
SATUAN
Rp Rp
6 A.4.1.1.7 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58
A Tenaga
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.000 100,000.00 -
Kepala Tukang L.03 OH 0.000 110,000.00 -
Mandor L.04 OH 0.000 115,000.00 -
132,000.00
B Bahan
Portland Semen Kg 371.000 72,157.50 26,770,432.50
Pasir Beton Kg 698.000 20,000.00 13,960,000.00
Kerikil (maksimum 30 mm) Kg 1047.000 15,000.00 15,705,000.00
Air ltr 215.000 20.00 4,300.00
56,439,732.50
C PERALATAN
D Jumlah A + B + C 56,571,732.50
E Overhead & Profit 12.5% 7,071,466.56
F Harga Satuan Pekerjaan (D+E) 63,643,199.06
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF JUMLAH HARGA
SATUAN
Rp Rp
7 A.4.1.1.8 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56
A Tenaga
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.000 100,000.00 -
Kepala Tukang L.03 OH 0.000 110,000.00 -
Mandor L.04 OH 0.000 115,000.00 -
132,000.00
B Bahan
Portland Semen Kg 384.000 72,157.50 27,708,480.00
Pasir Beton Kg 692.000 20,000.00 13,840,000.00
Kerikil (maksimum 30 mm) Kg 1039.000 15,000.00 15,585,000.00
Air ltr 215.000 20.00 4,300.00
57,137,780.00
C PERALATAN
D Jumlah A + B + C 57,269,780.00
E Overhead & Profit 12.5% 7,158,722.50
F Harga Satuan Pekerjaan (D+E) 64,428,502.50
8 A.4.1.1.9 Membuat Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53
A Tenaga
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.000 100,000.00 -
Kepala Tukang L.03 OH 0.000 110,000.00 -
Mandor L.04 OH 0.000 115,000.00 -
132,000.00
B Bahan
Portland Semen Kg 406.000 72,157.50 29,295,945.00
Pasir Beton kg 684.000 20,000.00 13,680,000.00
Kerikil (maksimum 30 mm) kg 1026.000 15,000.00 15,390,000.00
Air ltr 215.000 20.00 4,300.00
58,370,245.00
C PERALATAN
D Jumlah A + B + C 58,502,245.00
E Overhead & Profit 12.5% 7,312,780.63
F Harga Satuan Pekerjaan (D+E) 65,815,025.63
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF JUMLAH HARGA
SATUAN
Rp Rp
9 A.4.1.1.10 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52
A Tenaga
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.000 100,000.00 -
Kepala Tukang L.03 OH 0.000 110,000.00 -
Mandor L.04 OH 0.000 115,000.00 -
132,000.00
B Bahan
Portland Semen Kg 413.000 72,157.50 29,801,047.50
Pasir Beton Kg 681.000 20,000.00 13,620,000.00
Kerikil (maksimum 30 mm) Kg 1021.000 15,000.00 15,315,000.00
Air ltr 215.000 20.00 4,300.00
58,740,347.50
C PERALATAN
D Jumlah A + B + C 58,872,347.50
E Overhead & Profit 12.5% 7,359,043.44
F Harga Satuan Pekerjaan (D+E) 66,231,390.94
D Jumlah A + B + C 192,645.00
E Overhead & Profit 12.5% 24,080.63
F Harga Satuan Pekerjaan (D+E) 216,725.63
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF JUMLAH HARGA
SATUAN
Rp Rp
19 A.4.1.1.26 Memasang Bekisting untuk Tangga
A Tenaga
Pekerja L.01 OH 0.660 80,000.00 52,800.00
Tukang Kayu L.02 OH 0.330 100,000.00 33,000.00
Kepala Tukang L.03 OH 0.033 110,000.00 3,630.00
Mandor L.04 OH 0.033 115,000.00 3,795.00
93,225.00
B Bahan
Kayu Klas III (Randu) m3 0.030 1,000,000.00 30,000.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
Minyak Bekisting Ltr 0.150 0.00 -
Balok Kayu m3 0.015 1,000,000.00 15,000.00
Triplek 4 mm Lbr 0.350 58,000.00 20,300.00
Bambu Btg 2.000 8,000.00 16,000.00
86,420.00
C PERALATAN
D Jumlah A + B + C 179,645.00
E Overhead & Profit 12.5% 22,455.63
F Harga Satuan Pekerjaan (D+E) 202,100.63
22 A.4.1.1.37 1 m² bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm
A Tenaga
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang Kayu L.02 OH 0.500 100,000.00 50,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.010 115,000.00 1,150.00
72,650.00
B Bahan
kayu randu tebal 2 cm m3 0.022 1,000,000.00 22,000.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
27,120.00
C PERALATAN
D Jumlah A + B + C 99,770.00
E Overhead & Profit 12.5% 12,471.25
F Harga Satuan Pekerjaan (D+E) 112,241.25
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
SNI A PERALATAN
7,759.00
B BAHAN
72,720.00
C PERALATAN
18,000.00
D Jumlah A + B + C 98,479.00
SNI A PERALATAN
11,437.50
B BAHAN
8,904.13
C PERALATAN
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
D Jumlah A + B + C 20,341.63
Rp
IV A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
1 A.4.4.1.2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 140 900.00
Portland Semen (PC) Kg 32.95 1,450.00
Pasir Muntilan m3 0.091 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
2 A.4.4.1.3 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 140 900.00
Portland Semen (PC) Kg 26.55 1,450.00
Pasir Muntilan m3 0.093 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
3 A.4.4.1.4 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 140 900.00
Portland Semen (PC) Kg 22.2 1,450.00
Pasir Muntilan m3 0.102 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
4 A.4.4.1.5 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 140 900.00
Portland Semen (PC) Kg 18.5 1,450.00
Pasir Muntilan m3 0.122 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
5 A.4.4.1.8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 900.00
Portland Semen Kg 14.37 1,450.00
Pasir Muntilan m3 0.04 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
6 A.4.4.1.9 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 900.00
Portland Semen Kg 11.50 1,450.00
Pasir Muntilan m3 0.043 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
7 A.4.4.1.10 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 900.00
Portland Semen Kg 9.68 1,450.00
Pasir Muntilan m3 0.045 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
8 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 900.00
Portland Semen Kg 8.32 1,450.00
Pasir Muntilan m3 0.049 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
9 A.4.4.1.12 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 900.00
Portland Semen Kg 6.50 1,450.00
Pasir Muntilan m3 0.05 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
10 A.4.4.1.23 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Terawang / Roster Buah 30 3,800.00
Portland Semen kg 11 1,450.00
Pasir Muntilan m3 0.035 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
11 A.4.4.1.2.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 140 900.00
Portland Semen (PC) Kg 32.95 1,450.00
Pasir Pasang lokal m3 0.091 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
12 A.4.4.1.3.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 140 900.00
Portland Semen (PC) Kg 26.55 1,450.00
Pasir Pasang lokal m3 0.093 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
13 A.4.4.1.4.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 140 900.00
Portland Semen (PC) Kg 22.2 1,450.00
Pasir Pasang lokal m3 0.102 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
14 A.4.4.1.5.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 140 900.00
Portland Semen (PC) Kg 18.5 1,450.00
Pasir Pasang lokal m3 0.122 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
15 A.4.4.1.8.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 900.00
Portland Semen Kg 14.37 1,450.00
Pasir Pasang lokal m3 0.04 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
16 A.4.4.1.9.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 900.00
Portland Semen Kg 11.50 1,450.00
Pasir Pasang lokal m3 0.043 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
17A.4.4.1.10.1Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 900.00
Portland Semen Kg 9.68 1,450.00
Pasir Pasang lokal m3 0.045 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
18A.4.4.1.11.1Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 900.00
Portland Semen Kg 8.32 1,450.00
Pasir Pasang lokal m3 0.049 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
19A.4.4.1.12.1Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 900.00
Portland Semen Kg 6.50 1,450.00
Pasir Pasang lokal m3 0.05 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Terawang / Roster Buah 30 3,800.00
Portland Semen kg 11 1,450.00
Pasir Pasang lokal m3 0.035 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
21 A.4.4.1.2.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 150 560.00
Portland Semen (PC) Kg 32.95 1,450.00
Pasir Muntilan m3 0.091 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
22 A.4.4.1.3.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 150 560.00
Portland Semen (PC) Kg 26.55 1,450.00
Pasir Muntilan m3 0.093 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
23 A.4.4.1.4.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 150 560.00
Portland Semen (PC) Kg 22.2 1,450.00
Pasir Muntilan m3 0.102 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
24 A.4.4.1.5.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 150 560.00
Portland Semen (PC) Kg 18.5 1,450.00
Pasir Muntilan m3 0.122 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
25 A.4.4.1.8.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah Buah 75 560.00
Portland Semen Kg 14.37 1,450.00
Pasir Muntilan m3 0.04 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
26 A.4.4.1.9.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah Buah 75 560.00
Portland Semen Kg 11.50 1,450.00
Pasir Muntilan m3 0.043 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
27A.4.4.1.10.2Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah Buah 75 560.00
Portland Semen Kg 9.68 1,450.00
Pasir Muntilan m3 0.045 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
28A.4.4.1.11.2Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah Buah 75 560.00
Portland Semen Kg 8.32 1,450.00
Pasir Muntilan m3 0.049 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
29A.4.4.1.12.2Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah Buah 75 560.00
Portland Semen Kg 6.50 1,450.00
Pasir Muntilan m3 0.05 450,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 0.0%
F Harga Satuan Pekerjaan (D+E)
30 A.4.4.1.2.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 150 560.00
Portland Semen (PC) Kg 32.95 1,450.00
Pasir Pasang Lokal m3 0.091 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
31 A.4.4.1.3.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 150 560.00
Portland Semen (PC) Kg 26.55 1,450.00
Pasir Pasang Lokal m3 0.093 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
32 A.4.4.1.4.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 150 560.00
Portland Semen (PC) Kg 22.2 1,450.00
Pasir Pasang Lokal m3 0.102 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
33 A.4.4.1.5.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 80,000.00
Tukang Batu L.02 OH 0.2 100,000.00
Kepala Tukang Batu L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.03 115,000.00
B Bahan
Bata Merah Buah 150 560.00
Portland Semen (PC) Kg 18.5 1,450.00
Pasir Pasang Lokal m3 0.122 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
34 A.4.4.1.8.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah Buah 75 560.00
Portland Semen Kg 14.37 1,450.00
Pasir Pasang Lokal m3 0.04 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
35 A.4.4.1.9.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah Buah 75 560.00
Portland Semen Kg 11.50 1,450.00
Pasir Pasang Lokal m3 0.043 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
36A.4.4.1.10.3Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah Buah 75 560.00
Portland Semen Kg 9.68 1,450.00
Pasir Pasang Lokal m3 0.045 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
37A.4.4.1.11.3Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah Buah 75 560.00
Portland Semen Kg 8.32 1,450.00
Pasir Pasang Lokal m3 0.049 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
38A.4.4.1.12.3Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 80,000.00
Tukang Batu L.02 OH 0.1 100,000.00
Kepala Tukang L.03 OH 0.01 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Bata Merah Buah 75 560.00
Portland Semen Kg 6.50 1,450.00
Pasir Pasang Lokal m3 0.05 195,750.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
39 A.4.4.1.20 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP Muntilan
A Tenaga
Pekerja L.01 OH 0.300 80,000.00
Tukang Batu L.02 OH 0.100 100,000.00
Kepala Tukang L.03 OH 0.010 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Batako buah 15.000 4,500.00
PC kg 15.160 1,450.00
Pasir Pasang muntilan m3 0.364 450,000.00
Besi Angkur Ø 8 mm kg 0.280 11,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Batako buah 15.000 4,500.00
PC kg 15.160 1,450.00
Pasir Pasang lokal m3 0.364 195,750.00
Besi Angkur Ø 8 mm kg 0.280 11,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
41 A.4.4.1.21 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP Muntilan
A Tenaga
Pekerja L.01 OH 0.300 80,000.00
Tukang Batu L.02 OH 0.100 100,000.00
Kepala Tukang L.03 OH 0.010 110,000.00
Mandor L.04 OH 0.015 115,000.00
B Bahan
Batako buah 15.000 4,500.00
PC kg 12.130 1,450.00
Pasir Pasang muntilan m3 0.388 450,000.00
Besi Angkur Ø 8 mm kg 0.280 11,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Batako buah 15.000 4,500.00
PC kg 12.130 1,450.00
Pasir Pasang lokal m3 0.388 195,750.00
Besi Angkur Ø 8 mm kg 0.280 11,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
B Bahan
Bata Ringan bh 8.500 10,000.00
Mortar Perekat kg 3.000 2,125.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Bata Ringan bh 8.500 12,000.00
Mortar Perekat kg 4.000 2,125.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
JUMLAH
HARGA
Rp
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
126,000.00
47,777.50
40,950.00
214,727.50
288,377.50
36,047.19
324,424.69
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
126,000.00
38,497.50
41,850.00
206,347.50
279,997.50
34,999.69
314,997.19
JUMLAH
HARGA
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
126,000.00
32,190.00
45,900.00
204,090.00
277,740.00
34,717.50
312,457.50
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
126,000.00
26,825.00
54,900.00
207,725.00
281,375.00
35,171.88
316,546.88
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
63,000.00
20,836.50
18,000.00
101,836.50
138,661.50
17,332.69
155,994.19
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
63,000.00
16,675.00
19,350.00
99,025.00
135,850.00
16,981.25
152,831.25
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
63,000.00
14,036.00
20,250.00
97,286.00
134,111.00
16,763.88
150,874.88
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
63,000.00
12,064.00
22,050.00
97,114.00
133,939.00
16,742.38
150,681.38
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
63,000.00
9,425.00
22,500.00
94,925.00
131,750.00
16,468.75
148,218.75
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
114,000.00
15,950.00
15,750.00
145,700.00
182,525.00
22,815.63
205,340.63
JUMLAH
HARGA
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
126,000.00
47,777.50
17,813.25
191,590.75
265,240.75
33,155.09
298,395.84
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
126,000.00
38,497.50
18,204.75
182,702.25
256,352.25
32,044.03
288,396.28
JUMLAH
HARGA
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
126,000.00
32,190.00
19,966.50
178,156.50
251,806.50
31,475.81
283,282.31
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
126,000.00
26,825.00
23,881.50
176,706.50
250,356.50
31,294.56
281,651.06
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
63,000.00
20,836.50
7,830.00
91,666.50
128,491.50
16,061.44
144,552.94
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
63,000.00
16,675.00
8,417.25
88,092.25
124,917.25
15,614.66
140,531.91
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
63,000.00
14,036.00
8,808.75
85,844.75
122,669.75
15,333.72
138,003.47
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
63,000.00
12,064.00
9,591.75
84,655.75
121,480.75
15,185.09
136,665.84
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
63,000.00
9,425.00
9,787.50
82,212.50
119,037.50
14,879.69
133,917.19
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
114,000.00
15,950.00
6,851.25
136,801.25
173,626.25
21,703.28
195,329.53
JUMLAH
HARGA
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
84,000.00
47,777.50
40,950.00
172,727.50
246,377.50
30,797.19
277,174.69
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
84,000.00
38,497.50
41,850.00
164,347.50
237,997.50
29,749.69
267,747.19
JUMLAH
HARGA
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
84,000.00
32,190.00
45,900.00
162,090.00
235,740.00
29,467.50
283,740.00
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
84,000.00
26,825.00
54,900.00
165,725.00
239,375.00
29,921.88
269,296.88
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
42,000.00
20,836.50
18,000.00
80,836.50
117,661.50
14,707.69
132,369.19
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
42,000.00
16,675.00
19,350.00
78,025.00
114,850.00
14,356.25
129,206.25
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
42,000.00
14,036.00
20,250.00
76,286.00
113,111.00
14,138.88
127,249.88
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
42,000.00
12,064.00
22,050.00
76,114.00
112,939.00
14,117.38
127,056.38
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
42,000.00
9,425.00
22,500.00
73,925.00
110,750.00
-
110,750.00
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
84,000.00
47,777.50
17,813.25
149,590.75
223,240.75
27,905.09
251,145.84
JUMLAH
HARGA
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
84,000.00
38,497.50
18,204.75
140,702.25
214,352.25
26,794.03
241,146.28
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
84,000.00
32,190.00
19,966.50
136,156.50
209,806.50
26,225.81
257,806.50
JUMLAH
HARGA
48,000.00
20,000.00
2,200.00
3,450.00
73,650.00
84,000.00
26,825.00
23,881.50
134,706.50
208,356.50
26,044.56
234,401.06
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
42,000.00
20,836.50
7,830.00
70,666.50
107,491.50
13,436.44
120,927.94
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
42,000.00
16,675.00
8,417.25
67,092.25
103,917.25
12,989.66
116,906.91
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
42,000.00
14,036.00
8,808.75
64,844.75
101,669.75
12,708.72
114,378.47
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
42,000.00
12,064.00
9,591.75
63,655.75
100,480.75
12,560.09
113,040.84
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
42,000.00
9,425.00
9,787.50
61,212.50
98,037.50
12,254.69
110,292.19
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
67,500.00
21,982.00
163,800.00
3,220.00
256,502.00
293,327.00
36,665.88
329,992.88
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
67,500.00
21,982.00
71,253.00
3,220.00
163,955.00
200,780.00
25,097.50
225,877.50
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
67,500.00
17,588.50
174,600.00
3,220.00
262,908.50
299,733.50
37,466.69
337,200.19
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
67,500.00
17,588.50
75,951.00
3,220.00
164,259.50
201,084.50
25,135.56
226,220.06
JUMLAH
HARGA
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
85,000.00
6,375.00
91,375.00
128,200.00
16,025.00
144,225.00
24,000.00
10,000.00
1,100.00
1,725.00
36,825.00
102,000.00
8,500.00
110,500.00
147,325.00
18,415.63
165,740.63
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
V A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp muntilan Tebal 15 mm
A Tenaga
Pekerja L.01 OH 0.3000 80,000.00 24,000.00
Tukang batu L.02 OH 0.1500 100,000.00 15,000.00
Kepala Tukang L.03 OH 0.0150 110,000.00 1,650.00
Mandor L.04 OH 0.0150 115,000.00 1,725.00
42,375.00
B Bahan
Portland Semen Kg 7.7760 1,450.00 11,275.20
Pasir Muntilan m3 0.0230 450,000.00 10,350.00
21,625.20
C PERALATAN
D Jumlah A + B + C 64,000.20
E Overhead & Profit 0.0% -
F Harga Satuan Pekerjaan (D+E) 64,000.20
19 A.4.4.2.24 Pemasangan Finishing Siar Pasangan Dinding Bata Merah (=20 m')
A Tenaga
Pekerja L.01 OH 0.1500 80,000.00 12,000.00
Tukang batu L.02 OH 0.0750 100,000.00 7,500.00
Kepala Tukang L.03 OH 0.0080 110,000.00 880.00
Mandor L.04 OH 0.0080 115,000.00 920.00
21,300.00
B Bahan
Portland Semen Kg 3.1080 1,450.00 4,506.60
4,506.60
C PERALATAN
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
D Jumlah A + B + C 25,806.60
E Overhead & Profit 12.5% 3,225.83
F Harga Satuan Pekerjaan (D+E) 29,032.43
20 A.4.4.2.26 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2PP Muntilan
A Tenaga
Pekerja L.01 OH 0.3000 80,000.00 24,000.00
Tukang batu L.02 OH 0.1500 100,000.00 15,000.00
Kepala Tukang L.03 OH 0.0150 110,000.00 1,650.00
Mandor L.04 OH 0.0150 115,000.00 1,725.00
42,375.00
B Bahan
Pc Kg 6.3400 1,450.00 9,193.00
PP Muntilan m3 0.0120 450,000.00 5,400.00
14,593.00
C PERALATAN
D Jumlah A + B + C 56,968.00
E Overhead & Profit 12.5% 7,121.00
F Harga Satuan Pekerjaan (D+E) 64,089.00
2 A.4.6.1.2 Pembuatan & Pemasangan 1 m3 Kosen Pintu & Jendela Kayu kamfer
A Tenaga
Pekerja L.01 OH 6.0000 80,000.00 480,000.00
Tukang Kayu L.02 OH 18.0000 100,000.00 1,800,000.00
Kepala Tukang L.03 OH 1.8000 110,000.00 198,000.00
Mandor L.04 OH 0.3000 115,000.00 34,500.00
2,512,500.00
B Bahan
Kayu kamfer m3 1.2000 9,000,000.00 10,800,000.00
Paku Biasa 2" - 5 " kg 1.2500 12,800.00 16,000.00
Lem Kayu kg 1.0000 12,800.00 12,800.00
###
C PERALATAN
D Jumlah A + B + C ###
E Overhead & Profit 12.5% 1,667,662.50
F Harga Satuan Pekerjaan (D+E) ###
5 A.4.6.1.6 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu Jati
A Tenaga
Pekerja L.01 OH 0.8000 80,000.00 64,000.00
Tukang Kayu L.02 OH 2.4000 100,000.00 240,000.00
Kepala Tukang L.03 OH 0.2400 110,000.00 26,400.00
Mandor L.04 OH 0.0400 115,000.00 4,600.00
335,000.00
B Bahan
Kayu jati, papan m3 0.0240 16,875,000.00 405,000.00
Lem Kayu kg 0.3000 12,800.00 3,840.00
408,840.00
C PERALATAN
D Jumlah A + B + C 743,840.00
E Overhead & Profit 12.5% 92,980.00
F Harga Satuan Pekerjaan (D+E) 836,820.00
6 A.4.6.1.6.1 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu kamfer
A Tenaga
Pekerja L.01 OH 0.8000 80,000.00 64,000.00
Tukang Kayu L.02 OH 2.4000 100,000.00 240,000.00
Kepala Tukang L.03 OH 0.2400 110,000.00 26,400.00
Mandor L.04 OH 0.0400 115,000.00 4,600.00
335,000.00
B Bahan
Kayu kamfer m3 0.0240 9,000,000.00 216,000.00
Lem Kayu kg 0.3000 12,800.00 3,840.00
219,840.00
C PERALATAN
D Jumlah A + B + C 554,840.00
E Overhead & Profit 12.5% 69,355.00
F Harga Satuan Pekerjaan (D+E) 624,195.00
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
7 A.4.6.1.8 Pembuatan&Pemasangan 1 m2 Pintu kayu lapis (Plywood) Rangkap rangka Kayu Kamfer
A Tenaga
Pekerja L.01 OH 0.7000 80,000.00 56,000.00
Tukang Kayu L.02 OH 2.1000 100,000.00 210,000.00
Kepala Tukang L.03 OH 0.2100 110,000.00 23,100.00
Mandor L.04 OH 0.0350 115,000.00 4,025.00
293,125.00
B Bahan
Kayu Kamfer m3 0.0250 9,000,000.00 225,000.00
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu Ltr 0.5000 12,800.00 6,400.00
Plywood tebal 4 mm uk.90x220cm Lbr 1.0000 80,000.00 80,000.00
311,784.00
C PERALATAN
D Jumlah A + B + C 604,909.00
E Overhead & Profit 12.5% 75,613.63
F Harga Satuan Pekerjaan (D+E) 680,522.63
11 A.4.6.1.12 Pembuatan&Pemasangan 1 m2 Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Kam
A Tenaga
Pekerja L.01 OH 0.8500 80,000.00 68,000.00
Tukang Kayu L.02 OH 2.5500 100,000.00 255,000.00
Kepala Tukang L.03 OH 0.2550 110,000.00 28,050.00
Mandor L.04 OH 0.0430 115,000.00 4,945.00
355,995.00
B Bahan
Kayu Kamfer m3 0.0250 9,000,000.00 225,000.00
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu kg 0.0800 12,800.00 1,024.00
Teakwood (90 x 220) cm x 4 mm Lbr 1.0000 80,000.00 80,000.00
Formika Lbr 0.5000 58,000.00 29,000.00
335,408.00
C PERALATAN
D Jumlah A + B + C 691,403.00
E Overhead & Profit 12.5% 86,425.38
F Harga Satuan Pekerjaan (D+E) 777,828.38
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
12 A.4.6.1.13 Pembuatan&Memasang 1 m3 Konstruksi Kuda-kuda Konvensional Kayu Bengkirai
A Tenaga
Pekerja L.01 OH 4.0000 80,000.00 320,000.00
Tukang Kayu L.02 OH 12.0000 100,000.00 1,200,000.00
Kepala Tukang L.03 OH 1.2000 110,000.00 132,000.00
Mandor L.04 OH 0.2000 115,000.00 23,000.00
1,675,000.00
B Bahan
Kayu Bengkirai m3 1.1000 9,500,000.00 10,450,000.00
Besi Strip Kg 15.0000 20,200.00 303,000.00
Paku Biasa 2" - 5" Kg 5.6000 12,800.00 71,680.00
###
C PERALATAN
D Jumlah A + B + C ###
E Overhead & Profit 12.5% 1,562,460.00
F Harga Satuan Pekerjaan (D+E) ###
4 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66
A Tenaga
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 115,000.00 9,545.00
172,125.00
B Bahan
Portland Semen Kg 326.000 1,450.00 472,700.00
Pasir Beton Kg 760.000 321.43 244,285.71
Kerikil (maksimum 30 mm) Kg 1029.000 159.93 164,563.78
Air ltr 215.000 20.00 4,300.00
885,849.49
C PERALATAN
D Jumlah A + B + C 1,057,974.49
E Overhead & Profit 12.5% 132,246.81
F Harga Satuan Pekerjaan (D+E) 1,190,221.30
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF JUMLAH HARGA
SATUAN
Rp Rp
5 A.4.1.1.6 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61
A Tenaga
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 115,000.00 9,545.00
172,125.00
B Bahan
Portland Semen Kg 352.000 1,450.00 510,400.00
Pasir Beton Kg 731.000 321.43 234,964.29
Kerikil (maksimum 30 mm) Kg 1031.000 159.93 164,883.63
Air ltr 215.000 20.00 4,300.00
914,547.92
C PERALATAN
D Jumlah A + B + C 1,086,672.92
E Overhead & Profit 12.5% 135,834.11
F Harga Satuan Pekerjaan (D+E) 1,222,507.03
6 A.4.1.1.7 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58
A Tenaga
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 115,000.00 9,545.00
172,125.00
B Bahan
Portland Semen Kg 371.000 1,450.00 537,950.00
Pasir Beton Kg 698.000 321.43 224,357.14
Kerikil (maksimum 30 mm) Kg 1047.000 159.93 167,442.44
Air ltr 215.000 20.00 4,300.00
934,049.59
C PERALATAN
D Jumlah A + B + C 1,106,174.59
E Overhead & Profit 0.0% -
F Harga Satuan Pekerjaan (D+E) 1,106,174.59
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF JUMLAH HARGA
SATUAN
Rp Rp
7 A.4.1.1.8 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56
A Tenaga
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 115,000.00 9,545.00
172,125.00
B Bahan
Portland Semen Kg 384.000 1,450.00 556,800.00
Pasir Beton Kg 692.000 321.43 222,428.57
Kerikil (maksimum 30 mm) Kg 1039.000 159.93 166,163.04
Air ltr 215.000 20.00 4,300.00
949,691.61
C PERALATAN
D Jumlah A + B + C 1,121,816.61
E Overhead & Profit 12.5% 140,227.08
F Harga Satuan Pekerjaan (D+E) 1,262,043.68
8 A.4.1.1.9 Membuat Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53
A Tenaga
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 115,000.00 9,545.00
172,125.00
B Bahan
Portland Semen Kg 406.000 1,450.00 588,700.00
Pasir Beton kg 684.000 321.43 219,857.14
Kerikil (maksimum 30 mm) kg 1026.000 159.93 164,084.00
Air ltr 215.000 20.00 4,300.00
976,941.14
C PERALATAN
D Jumlah A + B + C 1,149,066.14
E Overhead & Profit 12.5% 143,633.27
F Harga Satuan Pekerjaan (D+E) 1,292,699.41
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF JUMLAH HARGA
SATUAN
Rp Rp
9 A.4.1.1.10 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52
A Tenaga
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 100,000.00 27,500.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 115,000.00 9,545.00
172,125.00
B Bahan
Portland Semen Kg 413.000 1,450.00 598,850.00
Pasir Beton Kg 681.000 321.43 218,892.86
Kerikil (maksimum 30 mm) Kg 1021.000 159.93 163,284.37
Air ltr 215.000 20.00 4,300.00
985,327.23
C PERALATAN
D Jumlah A + B + C 1,157,452.23
E Overhead & Profit 12.5% 144,681.53
F Harga Satuan Pekerjaan (D+E) 1,302,133.76
D Jumlah A + B + C 192,645.00
E Overhead & Profit 12.5% 24,080.63
F Harga Satuan Pekerjaan (D+E) 216,725.63
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF JUMLAH HARGA
SATUAN
Rp Rp
19 A.4.1.1.26 Memasang Bekisting untuk Tangga
A Tenaga
Pekerja L.01 OH 0.660 80,000.00 52,800.00
Tukang Kayu L.02 OH 0.330 100,000.00 33,000.00
Kepala Tukang L.03 OH 0.033 110,000.00 3,630.00
Mandor L.04 OH 0.033 115,000.00 3,795.00
93,225.00
B Bahan
Kayu Klas III (Randu) m3 0.030 1,000,000.00 30,000.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
Minyak Bekisting Ltr 0.150 0.00 -
Balok Kayu m3 0.015 1,000,000.00 15,000.00
Triplek 4 mm Lbr 0.350 58,000.00 20,300.00
Bambu Btg 2.000 8,000.00 16,000.00
86,420.00
C PERALATAN
D Jumlah A + B + C 179,645.00
E Overhead & Profit 12.5% 22,455.63
F Harga Satuan Pekerjaan (D+E) 202,100.63
22 A.4.1.1.37 1 m² bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm
A Tenaga
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang Kayu L.02 OH 0.500 100,000.00 50,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.010 115,000.00 1,150.00
72,650.00
B Bahan
kayu randu tebal 2 cm m3 0.022 1,000,000.00 22,000.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
27,120.00
C PERALATAN
D Jumlah A + B + C 99,770.00
E Overhead & Profit 0.0% -
F Harga Satuan Pekerjaan (D+E) 99,770.00
HARGA JUMLAH
SATUAN HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
D Jumlah A + B + C 49,915.00
E Overhead & Profit 12.5% 6,239.38
F Harga Satuan Pekerjaan (D+E) 56,154.38
D Jumlah A + B + C 134,810.00
E Overhead & Profit 12.5% 16,851.25
F Harga Satuan Pekerjaan (D+E) 151,661.25
HARGA JUMLAH
SATUAN HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
13 A.4.5.2.33 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai
A TENAGA
Pekerja L.01 OH 0.20 80,000.00 16,000.00
Tukang kayu L.03 OH 0.10 100,000.00 10,000.00
Kepala tukang L.11 OH 0.01 110,000.00 1,100.00
Mandor L.15 OH 0.01 115,000.00 1,150.00
28,250.00
B BAHAN
Genteng metal buah 2.00 80,000.00 160,000.00
Paku biasa ½”-1” Kg 0.20 12,800.00 2,560.00
162,560.00
C PERALATAN
D Jumlah A + B + C 190,810.00
E Overhead & Profit 12.5% 23,851.25
F Harga Satuan Pekerjaan (D+E) 214,661.25
D Jumlah A + B + C 206,510.00
E Overhead & Profit 12.5% 25,813.75
F Harga Satuan Pekerjaan (D+E) 232,323.75
HARGA JUMLAH
SATUAN HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
15 A.4.5.2.34 Pemasangan Nok Genteng Beton
A Tenaga
Pekerja L.01 OH 0.4000 80,000.00 32,000.00
Tukang Kayu L.02 OH 0.2000 100,000.00 20,000.00
Kepala Tukang L.03 OH 0.0200 110,000.00 2,200.00
Mandor L.04 OH 0.0200 115,000.00 2,300.00
56,500.00
B Bahan
Nok Genteng Beton Buah 3.5000 13,500.00 47,250.00
Paku Biasa 2" - 5" Kg 0.0500 12,800.00 640.00
Portland Semen Kg 10.8000 1,450.00 15,660.00
Pasir Pasang m3 0.0320 195,750.00 6,264.00
Semen Warna Kg 1.0000 12,000.00 12,000.00
81,814.00
C PERALATAN
D Jumlah A + B + C 138,314.00
E Overhead & Profit 12.5% 17,289.25
F Harga Satuan Pekerjaan (D+E) 155,603.25
D Jumlah A + B + C 130,860.00
E Overhead & Profit 12.5% 16,357.50
F Harga Satuan Pekerjaan (D+E) 147,217.50
D Jumlah A + B + C 185,200.00
E Overhead & Profit 0.0% -
F Harga Satuan Pekerjaan (D+E) 185,200.00
HARGA JUMLAH
SATUAN HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
D Jumlah A + B + C 151,100.00
E Overhead & Profit 0.0% -
F Harga Satuan Pekerjaan (D+E) 151,100.00
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
A Tenaga
Pekerja L.01 OH 0.0600 80,000.00 4,800.00
Tukang Besi L.02 OH 0.0600 100,000.00 6,000.00
Kepala Tukang L.03 OH 0.0060 110,000.00 660.00
A Tenaga
Pekerja L.01 OH 0.0600 80,000.00 4,800.00
Tukang Besi L.02 OH 0.0600 100,000.00 6,000.00
Kepala Tukang L.03 OH 0.0060 110,000.00 660.00
B Bahan
Besi Baja IWF kg 1.1500 18,500.00 21,275.00
21,275.00
C PERALATAN
D Jumlah A + B + C 33,080.00
E Overhead & Profit 12.5% 4,135.00
F Harga Satuan Pekerjaan (D+E) 37,215.00
3 A.4.2.1.4 Pembuatan 1 m2 pintu besi pelat baja tebal 2 mm rangkap, rangka baja siku
A TENAGA
Pekerja L.01 OH 1.05 80,000.00 84,000.00
Tukang las biasa L.03 OH 1.05 100,000.00 105,000.00
Kepala tukang L.03 OH 0.11 110,000.00 11,550.00
Mandor L.04 OH 0.05 115,000.00 5,980.00
206,530.00
B BAHAN
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
Besi siku L 30.30.3 Kg 15.00 35,800.00 537,000.00
Besi pelat baja Kg 32.80 20,200.00 662,560.00
Kawat las Kg 0.05 900.00 45.00
1,199,605.00
C PERALATAN
D Jumlah A + B + C 1,406,135.00
E Overhead & Profit 12.5% 175,766.88
F Harga Satuan Pekerjaan (D+E) 1,581,901.88
D Jumlah A + B + C 16,680.00
E Overhead & Profit 12.5% 2,085.00
F Harga Satuan Pekerjaan (D+E) 18,765.00
B Bahan
Pintu Gulung Besi m2 1.0000 350,000.00 350,000.00
350,000.00
C PERALATAN
D Jumlah A + B + C 579,890.00
E Overhead & Profit 12.5% 72,486.25
F Harga Satuan Pekerjaan (D+E) 652,376.25
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
A Tenaga
Pekerja L.01 OH 1.0000 80,000.00 80,000.00
B Bahan
Rolling Allumunium m2 1.0000 364,000.00 364,000.00
364,000.00
C PERALATAN
D Jumlah A + B + C 560,750.00
E Overhead & Profit 12.5% 70,093.75
F Harga Satuan Pekerjaan (D+E) 630,843.75
B Bahan
Profil Allumunium m' 1.1000 103,200.00 113,520.00
Skrup Fixer buah 2.0000 1,600.00 3,200.00
Sealant Tube 0.0600 22,500.00 1,350.00
118,070.00
C PERALATAN
D Jumlah A + B + C 126,524.50
E Overhead & Profit -
F Harga Satuan Pekerjaan (D+E) 126,524.50
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
D Jumlah A + B + C 971,578.00
E Overhead & Profit -
F Harga Satuan Pekerjaan (D+E) 971,578.00
16,865.00
B Bahan
Pintu Allumunium m' 4.4000 103,200.00 454,080.00
Sealant tube 0.2700 22,500.00 6,075.00
460,155.00
C PERALATAN
D Jumlah A + B + C 477,020.00
E Overhead & Profit -
A Tenaga
Pekerja L.01 OH 0.2000 80,000.00 16,000.00
Tukang Kayu L.02 OH 0.2000 100,000.00 20,000.00
Kepala Tukang L.03 OH 0.0200 110,000.00 2,200.00
D Jumlah A + B + C 188,072.00
E Overhead & Profit 12.5% 23,509.00
F Harga Satuan Pekerjaan (D+E) 211,581.00
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
13 A.4.2.1.19 Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm
A Tenaga
Pekerja L.01 OH 0.1500 80,000.00 12,000.00
Tukang Kayu L.02 OH 0.3000 100,000.00 30,000.00
C PERALATAN
D Jumlah A + B + C 77,763.00
E Overhead & Profit 12.5% 9,720.38
F Harga Satuan Pekerjaan (D+E) 87,483.38
14 A.4.2.1.20 Pemasangan 1 m2 rangka besi hollow 1x40.40.0,6 mm, modul 60 x 120 cm, untuk partisi
A TENAGA
Pekerja L.01 OH 0.25 80,000.00 20,000.00
Tukang besi L.02 OH 0.25 100,000.00 25,000.00
Kepala tukang L.03 OH 0.03 110,000.00 2,750.00
Mandor L.04 OH 0.01 115,000.00 1,495.00
49,245.00
B BAHAN
hollow 40.40.2 mm M1 3.50 11,300.00 39,550.00
Assesoris
(perkuatan, las dll) Ls 1.00 11,300.00 11,300.00
50,850.00
C PERALATAN
D Jumlah A + B + C 100,095.00
E Overhead & Profit 12.5% 12,511.88
F Harga Satuan Pekerjaan (D+E) 112,606.88
15 A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.0,6 mm, modul 60 x 60 cm, plafon
A Tenaga
Pekerja L.01 OH 0.3500 80,000.00 28,000.00
B Bahan
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
Rangka metal hollow 40.40.0.6 mm M1 4.0000 11,300.00 45,200.00
B Bahan
Kunci Tanam Biasa Buah 1.0000 77,200.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit
2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi
A Tenaga
Pekerja L.01 OH 0.0050 80,000.00
Tukang Kayu L.02 OH 0.5000 100,000.00
Kepala Tukang L.03 OH 0.0500 110,000.00
Mandor L.04 OH 0.0025 115,000.00
B Bahan
Kunci Tanam Kamar Mandi Buah 1.0000 46,400.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
3 A.4.6.2.4 Pemasangan Kunci Selinder
A Tenaga
Pekerja L.01 OH 0.0050 80,000.00
Tukang Kayu L.02 OH 0.5000 100,000.00
Kepala Tukang L.03 OH 0.0500 110,000.00
Mandor L.04 OH 0.0025 115,000.00
B Bahan
Kunci Selinder Buah 1.0000 77,200.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B Bahan
Engsel pintu Buah 1.0000 26,100.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu
A Tenaga
Pekerja L.01 OH 0.0100 80,000.00
Tukang Kayu L.02 OH 0.1000 100,000.00
Kepala Tukang L.03 OH 0.0100 110,000.00
Mandor L.04 OH 0.0005 115,000.00
B Bahan
Engsel Jendela Buah 1.0000 18,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B Bahan
Engsel Angin Buah 1.0000 19,800.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
7 A.4.6.2.9 Pemasangan Kait Angin
A Tenaga
Pekerja L.01 OH 0.0150 80,000.00
Tukang Kayu L.02 OH 0.1500 100,000.00
Kepala Tukang L.03 OH 0.0150 110,000.00
Mandor L.04 OH 0.0080 115,000.00
B Bahan
Kait Angin Buah 1.0000 6,900.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B Bahan
Door Closer Buah 1.0000 118,400.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
9 A.4.6.2.11 Pemasangan Kunci Selot
A Tenaga
Pekerja L.01 OH 0.0200 80,000.00
Tukang Kayu L.02 OH 0.2000 100,000.00
Kepala Tukang L.03 OH 0.0200 110,000.00
Mandor L.04 OH 0.0010 115,000.00
B Bahan
Kunci Selot Buah 1.0000 8,900.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Door Stop Buah 1.0000 35,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
11 A.4.6.2.14 Pemasangan Rel Pintu Dorong
A Tenaga
Pekerja L.01 OH 0.0600 80,000.00
Tukang Kayu L.02 OH 0.6000 100,000.00
Kepala Tukang L.03 OH 0.0600 110,000.00
Mandor L.04 OH 0.0030 115,000.00
B Bahan
Rel Pintu Dorong Buah 1.0000 216,200.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Kaca tebal 3mm m2 1.1000 85,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
13 A.4.6.2.17 Pemasangan Kaca tebal 5 mm
A Tenaga
Pekerja L.01 OH 0.0150 80,000.00
Tukang Kayu L.02 OH 0.1500 100,000.00
Kepala Tukang L.03 OH 0.0150 110,000.00
Mandor L.04 OH 0.0008 115,000.00
B Bahan
Kaca tebal 5mm m2 1.1000 120,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B Bahan
Kaca Cermin m2 1.1000 170,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
15 A.4.6.2.22 Pemasangan 1 m2 kaca wireglassed tebal 5 mm
A TENAGA
Pekerja L.01 OH 0.02 80,000.00
Tukang kayu L.02 OH 0.15 100,000.00
Kepala tukang L.03 OH 0.02 110,000.00
Mandor L.04 OH 0.01 115,000.00
B BAHAN
Kaca wireglassed 5
mm m2 1.10 900,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Kaca patri 5mm m2 1.10 ###
Sealant Kg 0.05 22,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
JUMLAH
HARGA
Rp
800.00
50,000.00
5,500.00
575.00
56,875.00
77,200.00
77,200.00
134,075.00
-
134,075.00
400.00
50,000.00
5,500.00
287.50
56,187.50
46,400.00
46,400.00
102,587.50
-
102,587.50
JUMLAH
HARGA
Rp
400.00
50,000.00
5,500.00
287.50
56,187.50
77,200.00
77,200.00
133,387.50
-
133,387.50
1,200.00
15,000.00
1,650.00
92.00
17,942.00
26,100.00
26,100.00
44,042.00
-
44,042.00
JUMLAH
HARGA
Rp
800.00
10,000.00
1,100.00
57.50
11,957.50
18,500.00
18,500.00
30,457.50
-
30,457.50
8,000.00
20,000.00
2,200.00
57.50
30,257.50
19,800.00
19,800.00
50,057.50
6,257.19
56,314.69
JUMLAH
HARGA
Rp
1,200.00
15,000.00
1,650.00
920.00
18,770.00
6,900.00
6,900.00
25,670.00
-
25,670.00
4,000.00
50,000.00
5,500.00
287.50
59,787.50
118,400.00
118,400.00
178,187.50
22,273.44
200,460.94
JUMLAH
HARGA
Rp
1,600.00
20,000.00
2,200.00
115.00
23,915.00
8,900.00
8,900.00
32,815.00
4,101.88
36,916.88
800.00
10,000.00
1,100.00
57.50
11,957.50
35,000.00
35,000.00
46,957.50
5,869.69
52,827.19
JUMLAH
HARGA
Rp
4,800.00
60,000.00
6,600.00
345.00
71,745.00
216,200.00
216,200.00
287,945.00
35,993.13
323,938.13
1,200.00
15,000.00
1,650.00
86.25
17,936.25
93,500.00
93,500.00
111,436.25
13,929.53
125,365.78
JUMLAH
HARGA
Rp
1,200.00
15,000.00
1,650.00
86.25
17,936.25
132,000.00
132,000.00
149,936.25
-
149,936.25
1,200.00
15,000.00
1,650.00
86.25
17,936.25
187,000.00
187,000.00
204,936.25
25,617.03
230,553.28
JUMLAH
HARGA
Rp
1,200.00
15,000.00
1,650.00
920.00
18,770.00
990,000.00
1,008,770.00
1,027,540.00
128,442.50
1,155,982.50
6,000.00
15,000.00
1,650.00
460.00
23,110.00
1,573,000.00
1,125.00
1,574,125.00
1,597,235.00
199,654.38
1,796,889.38
JUMLAH
HARGA
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 89,443.50
E Overhead & Profit 12.5% 11,180.44
F Harga Satuan Pekerjaan (D+E) 100,623.94
D Jumlah A + B + C 115,507.50
E Overhead & Profit 12.5% 14,438.44
F Harga Satuan Pekerjaan (D+E) 129,945.94
JUMLAH
HARGA
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 145,155.00
E Overhead & Profit 12.5% 18,144.38
F Harga Satuan Pekerjaan (D+E) 163,299.38
D Jumlah A + B + C 196,305.00
E Overhead & Profit 12.5% 24,538.13
F Harga Satuan Pekerjaan (D+E) 220,843.13
JUMLAH
HARGA
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
SNI A Tenaga
Pekerja L.01 OH 0.7000 80,000.00 56,000.00
Tukang Batu L.02 OH 0.3500 100,000.00 35,000.00
Kepala Tukang L.03 OH 0.0350 110,000.00 3,850.00
Mandor L.04 OH 0.0350 115,000.00 4,025.00
98,875.00
B Bahan
Ubin Keramik 40 x 40 cm putih Buah 6.6300 9,000.00 59,670.00
Portland Semen Kg 9.8000 1,450.00 14,210.00
Semen Warna Kg 1.3000 12,000.00 15,600.00
Pasir Beton/Muntilan m3 0.0450 450,000.00 20,250.00
109,730.00
C PERALATAN
D Jumlah A + B + C 208,605.00
E Overhead & Profit 12.5% 26,075.63
F Harga Satuan Pekerjaan (D+E) 234,680.63
33,505.00
B BAHAN
Karpet tb 6 mm ex.Atrium m2 1.05 150,000.00 157,500.00
173,250.00
C PERALATAN
D Jumlah A + B + C 206,755.00
E Overhead & Profit 0.0% -
F Harga Satuan Pekerjaan (D+E) 206,755.00
23,610.00
B BAHAN
Underlayer m2 1.05 6,000.00 6,300.00
22,050.00
C PERALATAN
D Jumlah A + B + C 45,660.00
E Overhead & Profit 0.0% -
F Harga Satuan Pekerjaan (D+E) 45,660.00
JUMLAH
HARGA
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
A Tenaga
Pekerja L.01 OH 0.1500 80,000.00
B Bahan
C PERALATAN
D Jumlah A + B + C
A Tenaga
B Bahan
C PERALATAN
D Jumlah A + B + C
B Bahan
Sabun Kg 0.0500 8,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
4 A.4.7.1.4 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup)
A Tenaga
Pekerja L.01 OH 0.0700 80,000.00
Tukang Cat L.02 OH 0.0090 100,000.00
Kepala Tukang L.03 OH 0.0060 110,000.00
Mandor L.04 OH 0.0030 115,000.00
B Bahan
Cat Menie kg 0.2000 35,000.00
Plamuur kg 0.1500 32,800.00
Cat Dasar kg 0.1700 33,500.00
Cat Penutup kg 0.2600 52,500.00
Kuas bh 0.0100 13,200.00
Pengencer kg 0.0300 20,000.00
Amplas lbr 0.2000 6,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
5 A.4.7.1.5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup)
A Tenaga
Pekerja L.01 OH 0.0700 80,000.00
Tukang Cat L.02 OH 0.1050 100,000.00
Kepala Tukang L.03 OH 0.0040 110,000.00
Mandor L.04 OH 0.0030 115,000.00
B Bahan
Cat Menie kg 0.2000 35,000.00
Plamuur kg 0.1500 32,800.00
Cat Dasar kg 0.1700 33,500.00
Cat Penutup kg 0.3500 52,500.00
Kuas bh 0.0100 13,200.00
Pengencer kg 0.0300 20,000.00
Amplas lbr 0.2000 6,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil
A Tenaga
Pekerja L.01 OH 0.0400 80,000.00
Tukang Cat L.02 OH 0.0630 100,000.00
Kepala Tukang L.03 OH 0.0630 110,000.00
Mandor L.04 OH 0.0030 115,000.00
B Bahan
Teak Oil Ltr 0.3600 42,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Politur Ltr 0.1500 16,900.00
Spiritus Ltr 0.3720 12,000.00
Ampelas Lbr 2.0000 6,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter
A Tenaga
Pekerja L.01 OH 0.1000 80,000.00
Mandor L.04 OH 0.0060 115,000.00
B Bahan
Residu atau Ter Ltr 0.3500 3,400.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Vernis Ltr 0.1500 27,900.00
Dempul Ltr 0.0500 32,800.00
Ampelas Lbr 0.1000 6,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
10 A.4.7.1.10 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Decolite
A Tenaga
Pekerja L.01 OH 0.0200 80,000.00
Tukang Cat L.02 OH 0.0630 100,000.00
Kepala Tukang L.03 OH 0.0063 110,000.00
Mandor L.04 OH 0.0030 115,000.00
B Bahan
Plamir Kg 0.1000 16,000.00
Cat Dasar Kg 0.1000 19,000.00
Cat Penutup 2 kali Kg 0.2600 48,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
11 A.4.7.1.10.1Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Mowilex da
A Tenaga
Pekerja L.01 OH 0.0200 80,000.00
Tukang Cat L.02 OH 0.0630 100,000.00
Kepala Tukang L.03 OH 0.0063 110,000.00
Mandor L.04 OH 0.0030 115,000.00
B Bahan
Plamir Kg 0.1000 16,000.00
Cat Dasar Kg 0.1000 19,000.00
Cat Penutup 2 kali Kg 0.2600 56,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
12 A.4.7.1.10.2Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Mowilex lua
A Tenaga
Pekerja L.01 OH 0.0200 80,000.00
Tukang Cat L.02 OH 0.0630 100,000.00
Kepala Tukang L.03 OH 0.0063 110,000.00
Mandor L.04 OH 0.0030 115,000.00
B Bahan
Plamir Kg 0.1000 16,000.00
Cat Dasar Kg 0.1000 19,000.00
Cat Penutup 2 kali Kg 0.2600 96,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Cat Dasar Kg 0.1200 19,000.00
Cat Penutup 2 kali Kg 0.1800 48,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
14A.4.7.1.11.1Pengecatan Tembok Lama dengan Mowilex dalam ruangan
A Tenaga
Pekerja L.01 OH 0.0280 80,000.00
Tukang Cat L.02 OH 0.0420 100,000.00
Kepala Tukang L.03 OH 0.0042 110,000.00
Mandor L.04 OH 0.0030 115,000.00
B Bahan
Cat Dasar Kg 0.1200 19,000.00
Cat Penutup 2 kali Kg 0.1800 56,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Cat Dasar Kg 0.1200 19,000.00
Cat Penutup 2 kali Kg 0.1800 96,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
16 A.4.7.1.15 Pemasangan 1 m2 wallpaper
A TENAGA
Pekerja L.01 OH 0.02 80,000.00
B BAHAN
Wall paper m2 1.20 70,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 0.0%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Meni Besi Kg 0.1000 30,600.00
Perekat / Lem Kg 0.0100 35,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp
18 A.4.7.1.22 Pengecatan 1 m2 permukaan Besi 3x
SNI A Tenaga
Pekerja L.01 OH 0.0500 80,000.00
Tukang Cat L.02 OH 0.0750 100,000.00
Kepala Tukang L.03 OH 0.0075 110,000.00
Mandor L.04 OH 0.0025 115,000.00
B Bahan
Cat Kg 0.2600 65,000.00
Pengencer L 0.1740 20,000.00
Meni Kg 0.0750 30,600.00
Amplas Bh 0.2000 6,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Cat Kg 0.2600 65,000.00
Pengencer L 0.1740 20,000.00
Amplas Bh 0.2000 6,500.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit 12.5%
F Harga Satuan Pekerjaan (D+E)
B Bahan
Cat Waterproof sekualitas No Drop Kg 0.3500 50,000.00
C PERALATAN
D Jumlah A + B + C
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
JUMLAH
HARGA
Rp
12,000.00
345.00
12,345.00
1,160.00
1,160.00
13,505.00
1,688.13
15,193.13
12,000.00
345.00
12,345.00
400.00
400.00
12,745.00
1,593.13
14,338.13
12,000.00
920.00
12,920.00
400.00
400.00
13,320.00
1,665.00
14,985.00
JUMLAH
HARGA
Rp
ayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup)
5,600.00
900.00
660.00
345.00
7,505.00
7,000.00
4,920.00
5,695.00
13,650.00
132.00
600.00
1,300.00
33,297.00
40,802.00
5,100.25
45,902.25
5,600.00
10,500.00
440.00
345.00
16,885.00
7,000.00
4,920.00
5,695.00
18,375.00
132.00
600.00
1,300.00
38,022.00
54,907.00
6,863.38
61,770.38
JUMLAH
HARGA
Rp
3,200.00
6,300.00
6,930.00
345.00
16,775.00
15,120.00
15,120.00
31,895.00
3,986.88
35,881.88
3,200.00
6,000.00
1,760.00
345.00
11,305.00
2,535.00
4,464.00
13,000.00
19,999.00
31,304.00
3,913.00
35,217.00
JUMLAH
HARGA
Rp
8,000.00
690.00
8,690.00
1,190.00
1,190.00
9,880.00
1,235.00
11,115.00
12,800.00
16,000.00
1,760.00
345.00
30,905.00
4,185.00
1,640.00
650.00
6,475.00
37,380.00
4,672.50
42,052.50
JUMLAH
HARGA
Rp
u (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Decolite
1,600.00
6,300.00
693.00
345.00
8,938.00
1,600.00
1,900.00
12,480.00
15,980.00
24,918.00
3,114.75
28,032.75
u (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Mowilex dalam ruangan
1,600.00
6,300.00
693.00
345.00
8,938.00
1,600.00
1,900.00
14,560.00
18,060.00
26,998.00
-
26,998.00
JUMLAH
HARGA
Rp
u (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Mowilex luar ruangan
1,600.00
6,300.00
693.00
345.00
8,938.00
1,600.00
1,900.00
24,960.00
28,460.00
37,398.00
4,674.75
42,072.75
2,240.00
4,200.00
462.00
345.00
7,247.00
2,280.00
8,640.00
10,920.00
18,167.00
2,270.88
20,437.88
JUMLAH
HARGA
Rp
2,240.00
4,200.00
462.00
345.00
7,247.00
2,280.00
10,080.00
12,360.00
19,607.00
2,450.88
22,057.88
2,240.00
4,200.00
462.00
345.00
7,247.00
2,280.00
17,280.00
19,560.00
26,807.00
-
26,807.00
JUMLAH
HARGA
Rp
1,600.00
20,000.00
2,200.00
287.50
24,087.50
84,000.00
9,000.00
93,000.00
117,087.50
-
117,087.50
1,600.00
20,000.00
2,200.00
287.50
24,087.50
3,060.00
350.00
3,410.00
27,497.50
3,437.19
30,934.69
JUMLAH
HARGA
Rp
4,000.00
7,500.00
825.00
287.50
12,612.50
16,900.00
3,480.00
2,295.00
1,300.00
23,975.00
36,587.50
4,573.44
41,160.94
4,000.00
7,500.00
825.00
287.50
12,612.50
16,900.00
3,480.00
1,300.00
21,680.00
34,292.50
4,286.56
38,579.06
1,600.00
6,300.00
693.00
345.00
8,938.00
17,500.00
17,500.00
26,438.00
-
26,438.00
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
XV A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA
1 A.8.4.1.1 Pemasangan 1 m pipa PVC Ø 50 mm (2")
A TENAGA
Pekerja L.01 OH 0.081 75,000.00 6,075.00
Tukang pipa L.02 OH 0.041 100,000.00 4,100.00
Mandor L.04 OH 0.008 110,000.00 880.00
11,055.00
B BAHAN
Pipa PVC Ø 50 mm m 1.000 58,200.00 58,200.00
58,200.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.006 -
-
D Jumlah A + B + C 69,255.00
E Overhead & Profit -
F Harga Satuan Pekerjaan (D+E) 69,255.00
9 A.8.4.1.80 Biaya 1 m' pemasangan pipa PVC Ø 25 mm (galian 0,25m x 0,3m + Bahan)
Galian tanah keras m3 0.075 94,140.00 7,060.50
Urugan tanah kembali m3 0.065 15,250.00 991.25
Buangan sisa galian m3 0.010 30,993.75 309.94
Pemasangan Pipa 1.000 31,636.36 31,636.36
Harga Satuan Pekerjaan 39,998.05
10 A.8.4.1.81 Biaya 1 m' pemasangan pipa PVC Ø 40 mm (galian 0,25m x 0,4m + Bahan)
Galian tanah keras m3 0.100 94,140.00 9,414.00
Urugan tanah kembali m3 0.080 15,250.00 1,220.00
Buangan sisa galian m3 0.020 30,993.75 619.88
Pemasangan Pipa 1.000 44,156.25 44,156.25
Harga Satuan Pekerjaan 55,410.13
11 A.8.4.1.82 Biaya 1 m' pemasangan pipa PVC Ø 50 mm (galian 0,25m x 0,5m + Bahan)
Galian tanah keras m3 0.125 94,140.00 11,767.50
Urugan tanah kembali m3 0.095 15,250.00 1,448.75
Buangan sisa galian m3 0.030 30,993.75 929.81
Pemasangan Pipa 1.000 69,255.00 69,255.00
Harga Satuan Pekerjaan 83,401.06
12 A.8.4.1.83 Biaya 1 m' pemasangan pipa PVC Ø 75 mm (galian 0,25m x 0,6m + Bahan)
Galian tanah keras m3 0.150 94,140.00 14,121.00
HARGA JUMLAH
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN HARGA
Rp Rp
Urugan tanah kembali m3 0.120 15,250.00 1,830.00
Buangan sisa galian m3 0.030 30,993.75 929.81
Pemasangan Pipa 1.000 72,157.50 72,157.50
Harga Satuan Pekerjaan 89,038.31
13 A.8.4.1.84 Biaya 1 m' pemasangan pipa PVC Ø 100 mm (galian 0,30m x 1,00m + Bahan)
Galian tanah keras m3 0.300 94,140.00 28,242.00
Urugan tanah kembali m3 0.265 15,250.00 4,041.25
Buangan sisa galian m3 0.035 30,993.75 1,084.78
Pemasangan Pipa 1.000 90,335.00 90,335.00
Harga Satuan Pekerjaan 123,703.03
14 A.8.4.1.85 Biaya 1 m' pemasangan pipa HDPE OD 63 mm (galian 0,25m x 0,5m + Bahan)
Galian tanah keras m3 0.125 94,140.00 11,767.50
Urugan tanah kembali m3 0.095 15,250.00 1,448.75
Buangan sisa galian m3 0.030 30,993.75 929.81
Pemasangan Pipa 1.000 61,543.13 61,543.13
Harga Satuan Pekerjaan 75,689.19
15 A.8.4.1.86 Biaya 1 m' pemasangan pipa HDPE OD 75 mm (galian 0,25m x 0,6m + Bahan)
Galian tanah keras m3 0.150 94,140.00 14,121.00
Urugan tanah kembali m3 0.120 15,250.00 1,830.00
Buangan sisa galian m3 0.030 30,993.75 929.81
Pemasangan Pipa 1.000 84,398.06 84,398.06
Harga Satuan Pekerjaan 101,278.88
16 A.8.4.1.87 Biaya 1 m' pemasangan pipa HDPE OD 90 mm (galian 0,25m x 0,70m + Bahan)
Galian tanah keras m3 0.175 94,140.00 16,474.50
Urugan tanah kembali m3 0.140 15,250.00 2,135.00
Buangan sisa galian m3 0.035 30,993.75 1,084.78
Pemasangan Pipa 1.000 120,082.50 120,082.50
Harga Satuan Pekerjaan 139,776.78
I UPAH
1
Site manager Hari 1.00 x 1.00 75,000.00
2
Operator pemboran Hari 1.00 x 1.00 50,000.00
3
Crew pengeboran Hari 4.00 x 1.00 50,000.00
4
Pengemudi Hari 2.00 x 2.00 40,000.00
II. PERALATAN
1 Sewa kendaraan Hari 2.00 x 2.00 250,000.00
angkut ( truk )
JUMLAH
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 70.00 x 1.00 5,900.00
2 Olie mesin Ltr 5.00 x 1.00 35,300.00
3 Veet Kg 2.00 x 1.00 33,100.00
4 Bentonite Kg 40.00 x 1.00 11,400.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 400,000.00
JUMLAH
1 HARI RATA-RATA 10 M' ----> JADI PER METER
An.3 Jenis pekerjaan :Pemboran pilot hole diameter 6", 50 -- 100 m
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 75.00 x 1.00 5,900.00
2 Olie mesin Ltr 5.00 x 1.00 35,300.00
3 Veet Kg 2.00 x 1.00 33,100.00
4 Bentonite Kg 50.00 x 1.00 11,400.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00
JUMLAH
1 HARI RATA-RATA 10 M' ----> JADI PER METER
An.4 Jenis pekerjaan :Pemboran pilot hole diameter 6", 100 -- 150 m
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 85.00 x 1.00 5,900.00
2 Olie mesin Ltr 6.00 x 1.00 35,300.00
3 Veet Kg 3.00 x 1.00 33,100.00
4 Bentonite Kg 60.00 x 1.00 11,400.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00
JUMLAH
1 HARI RATA-RATA 10 M' ----> JADI PER METER
An.5 Jenis pekerjaan : Pekerjaan reaming, 0 -- 65 m
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 60.00 x 1.00 5,900.00
2 Olie mesin Ltr 4.00 x 1.00 35,300.00
3 Veet Kg 2.00 x 1.00 33,100.00
4 Bentonite Kg 40.00 x 1.00 11,400.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00
JUMLAH
1 HARI RATA-RATA 10 M' ----> JADI PER METER
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 75.00 x 1.00 5,900.00
2 Olie mesin Ltr 6.00 x 1.00 35,300.00
3 Veet Kg 3.00 x 1.00 33,100.00
4 Bentonite Kg 55.00 x 1.00 11,400.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00
JUMLAH
1 HARI RATA-RATA 10 M' ----> JADI PER METER
An.7 Jenis pekerjaan : Electric logging
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00
3 Operator pemboran Hari 1.00 x 1.00 50,000.00
4 Crew pengeboran Hari 2.00 x 1.00 50,000.00
II. PERALATAN
1 Recorder paper Unit 1.00 x 1.00 20,000.00
2 Alat tulis Unit 1.00 x 1.00 15,000.00
III. PERALATAN
Mesin peralatan logging Unit 1.00 x 1.00 700,000.00
Tranportasi peralatan logging Unit 1.00 x 1.00 150,000.00
JUMLAH
1 HARI RATA-RATA 50 M' ----> JADI PER METER
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 120.00 x 1.00 5,900.00
2 Olie mesin Ltr 3.00 x 1.00 35,300.00
3 Veet Kg 2.00 x 1.00 33,100.00
4 Kawat las Btg 120.00 x 1.00 900.00
Pipa jambang diameter 8" Mtr 60.00 x 440,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00
JUMLAH
1 HARI RATA-RATA 60 M' ----> JADI PER METER
DIBULATKAN
An.9 Jenis pekerjaan : Pengadaan dan pemasangan pipa buta diametr 6
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 5,900.00
2 Olie mesin Ltr 1.00 x 35,300.00
3 Veet Kg 0.60 x 33,100.00
4 Kawat las Btg 60.00 x 900.00
5 Pipa buta diameter 6" Mtr 30.00 x 310,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00
JUMLAH
1 HARI RATA-RATA 30 M' ----> JADI PER METER
DIBULATKAN
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 5,900.00
2 Olie mesin Ltr 1.00 x 35,300.00
3 Veet Kg 0.60 x 33,100.00
4 Kawat las Btg 60.00 x 900.00
5 Screen stainless steel dia 6 : Mtr 30.00 x 1,955,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00
JUMLAH
1 HARI RATA-RATA 30 M' ----> JADI PER METER
DIBULATKAN
An.8' Jenis pekerjaan : Pengadaan dan pemasangan pipa jambang diam
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 120.00 x 1.00 5,900.00
2 Olie mesin Ltr 3.00 x 1.00 35,300.00
3 Veet Kg 2.00 x 1.00 33,100.00
4 Kawat las Btg 120.00 x 1.00 900.00
5 Pipa jambang diameter 6" Mtr 60.00 x 302,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00
JUMLAH
1 HARI RATA-RATA 60 M' ----> JADI PER METER
DIBULATKAN
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 5,900.00
2 Olie mesin Ltr 1.00 x 35,300.00
3 Veet Kg 0.60 x 33,100.00
4 Kawat las Btg 60.00 x 900.00
5 Pipa buta diameter 4" Mtr 30.00 x 198,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00
JUMLAH
1 HARI RATA-RATA 30 M' ----> JADI PER METER
DIBULATKAN
An.10' Jenis pekerjaan : Pengad. dan pemasangan screen stainless steel
I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 5,900.00
2 Olie mesin Ltr 1.00 x 35,300.00
3 Veet Kg 0.60 x 33,100.00
4 Kawat las Btg 60.00 x 900.00
5 Screen stainless steel dia 4" : Mtr 30.00 x 1,335,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00
JUMLAH
1 HARI RATA-RATA 30 M' ----> JADI PER METER
DIBULATKAN
EMBUATAN SUMUR PRODUKSI
JUML. HARGA
75,000.00
50,000.00
200,000.00
160,000.00
1,000,000.00
1,485,000.00
JUML. HARGA
75,000.00
60,000.00
50,000.00
50,000.00
50,000.00
60,000.00
100,000.00
80,000.00
413,000.00
176,500.00
66,200.00
456,000.00
400,000.00
2,036,700.00
203,670.00
emboran pilot hole diameter 6", 50 -- 100 m
JUML. HARGA
75,000.00
60,000.00
50,000.00
50,000.00
50,000.00
60,000.00
100,000.00
80,000.00
442,500.00
176,500.00
66,200.00
570,000.00
375,000.00
2,155,200.00
215,520.00
JUML. HARGA
75,000.00
60,000.00
50,000.00
50,000.00
50,000.00
60,000.00
100,000.00
80,000.00
501,500.00
211,800.00
99,300.00
684,000.00
375,000.00
2,396,600.00
239,660.00
JUML. HARGA
75,000.00
60,000.00
50,000.00
50,000.00
50,000.00
60,000.00
100,000.00
80,000.00
354,000.00
141,200.00
66,200.00
456,000.00
375,000.00
1,917,400.00
191,740.00
JUML. HARGA
75,000.00
60,000.00
50,000.00
50,000.00
50,000.00
60,000.00
100,000.00
80,000.00
442,500.00
211,800.00
99,300.00
627,000.00
375,000.00
2,280,600.00
228,060.00
JUML. HARGA
75,000.00
60,000.00
50,000.00
100,000.00
20,000.00
15,000.00
700,000.00
150,000.00
1,170,000.00
23,400.00
JUML. HARGA
75,000.00
50,000.00
60,000.00
150,000.00
80,000.00
708,000.00
105,900.00
66,200.00
108,000.00
26,400,000.00
375,000.00
50,000.00
28,228,100.00
470,468.33
470,000.00
Pengadaan dan pemasangan pipa buta diametr 6"
JUML. HARGA
75,000.00
50,000.00
60,000.00
150,000.00
80,000.00
236,000.00
35,300.00
19,860.00
54,000.00
9,300,000.00
375,000.00
50,000.00
10,485,160.00
349,505.33
349,000.00
JUML. HARGA
75,000.00
50,000.00
60,000.00
150,000.00
80,000.00
236,000.00
35,300.00
19,860.00
54,000.00
58,650,000.00
375,000.00
50,000.00
59,835,160.00
1,994,505.33
1,994,000.00
Pengadaan dan pemasangan pipa jambang diametr 6" (GIP)
JUML. HARGA
75,000.00
50,000.00
60,000.00
150,000.00
80,000.00
708,000.00
105,900.00
66,200.00
108,000.00
18,120,000.00
375,000.00
50,000.00
19,948,100.00
332,468.33
332,000.00
JUML. HARGA
75,000.00
50,000.00
60,000.00
150,000.00
80,000.00
236,000.00
35,300.00
19,860.00
54,000.00
5,940,000.00
375,000.00
50,000.00
7,125,160.00
237,505.33
237,000.00
Pengad. dan pemasangan screen stainless steel diametr 4"
JUML. HARGA
75,000.00
50,000.00
60,000.00
150,000.00
80,000.00
236,000.00
35,300.00
19,860.00
54,000.00
40,050,000.00
375,000.00
50,000.00
41,235,160.00
1,374,505.33
1,374,000.00
Analisa EI-421
NAMA KEGIATAN : 0
NAMA PEKERJAAN : 0
VOLUME : 0
LOKASI : 0
ITEM PEMBAYARAN N: 4.2.(1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A PERKIRAAN VOL. PEK. 1.00
SATUAN PEMBAYAR : M3 TOTAL HARGA (Rp.) 625,093.21
% THD. BIAYA PROYEK 0.38
PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
NAMA KEGIATAN : 0
NAMA PEKERJAAN : 0
VOLUME : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 4.2.(2a) PERKIRAAN VOL. PEK. : 1.00
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas B TOTAL HARGA (Rp.) : 346,299.96
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.38
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. 4.2.(5) PERKIRAAN VOL. PEK. : 1.00
JENIS PEKERJAAN Agregat Penutup BURTU TOTAL HARGA (Rp.) : 7,373.98
SATUAN PEMBAYARAN M2 % THD. BIAYA PROYEK : 0.01
A. TENAGA
B. BAHAN
C. PERALATAN
NAMA KEGIATAN : 0
NAMA PEKERJAAN : 0
VOLUME : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 4.2.(2b)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas S PERKIRAAN VOL. PEK. : 1.00
SATUAN PEMBAYARAN : M3 TOTAL HARGA : 327,356.21
% THD. BIAYA PROYEK : 0.37
A. TENAGA
B. BAHAN
C. PERALATAN
0 : #REF!
0 : #REF!
0 : #REF!
0 : #REF!
ITEM PEMBAYARAN NO. : 0
JENIS PEKERJAAN : 0 PERKIRAAN VOL. PEK. :
SATUAN PEMBAYARAN : 0 TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader E15 Jam 0.0096
2. AMP E01 Jam 0.0201
3. Genset E12 Jam 0.0201
4. Dump Truck E08 Jam 0.7054
5. Asp. Finisher E02 Jam 0.0137
6. Tandem Roller E17 Jam 0.0135
7 P. Tyre Roller E18 Jam 0.0058
8 Alat Bantu Ls 1.0000
Nama Terang
Jabatan
Analisa EI-633a
NAMA KEGIATAN : 0
NAMA PEKERJAAN : 0
VOLUME : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 6.3(3a)
JENIS PEKERJAAN : Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang)
SATUAN PEMBAYARAN : Ton PERKIRAAN VOL. PEK. : 1.00
TOTAL HARGA (Rp.) : 1,532,654.81
% THD. BIAYA PROYEK : 1.09
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader E15 Jam 0.0096 580,949.9995 5,560.49
2. AMP E01 Jam 0.0201 7,030,434.9213 141,173.39
3. Genset E12 Jam 0.0201 370,057.9099 7,430.88
4. Dump Truck E08 Jam 0.7054 252,961.9405 178,428.51
5. Asphalt Finisher E02 Jam 0.0185 1,158,786.1739 21,411.36
6. Tandem Roller E17 Jam 0.0152 461,149.7912 6,997.48
7 P. Tyre Roller E18 Jam 0.0042 519,195.3015 2,168.84
8 Alat Bantu Ls 1.0000 0.0000 0.00
0 : 0
0 : 0
0 : 0
0 : 0
ITEM PEMBAYARAN NO. : 0
JENIS PEKERJAAN : 0 PERKIRAAN VOL. PEK. : 0.00
SATUAN PEMBAYARAN : 0 TOTAL HARGA (Rp.) : 0.00
% THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader E15 Jam 0.0096 580,949.9995 5,560.49
2. AMP E01 Jam 0.0201 7,030,434.9213 141,173.39
3. Genset E12 Jam 0.0201 370,057.9099 7,430.88
4. Dump Truck E08 Jam 0.7054 252,961.9405 178,428.51
5. Asp. Finisher E02 Jam 0.0137 1,158,786.1739 15,920.09
6. Tandem Roller E17 Jam 0.0135 461,149.7912 6,236.55
7 P. Tyre Roller E18 Jam 0.0058 519,195.3015 3,012.60
8 Alat Bantu Ls 1.0000 0.0000 0.00
NAMA KEGIATAN : 0
NAMA PEKERJAAN : 0
VOLUME : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 8.1 (5).b
JENIS PEKERJAAN : Camp. Aspal Panas Lapis Aus Latasir Semi Mekanik PERKIRAAN VOL. PEK. :
Utk.Pek.Minor TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN
1 Dump Truck E09 Jam 0.7157 321,027.17 229,747.15
2 Pedestrian Roller E24 Jam 0.2008 36,905.57 7,410.76
6. Alat Bantu Ls 1.0000 0.00 0.00
NAMA KEGIATAN : 0
NAMA PEKERJAAN : 0
VOLUME : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 8.1 (7) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Penetrasi Macadam Utk. Pek. Minor TOTAL HARGA :
SATUAN PEMBAYARAN : M3 (Perata) % THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN
NAMA KEGIATAN : 0
NAMA PEKERJAAN : 0
VOLUME : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 8.1 (5) PERKIRAAN VOL. PEK. : 1.00
JENIS PEKERJAAN : Camp. Aspal Panas Utk.Pek.Minor TOTAL HARGA (Rp.) : 3,047,499.57
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 2.16
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader E15 Jam 0.0301 580,950.00 17,512.22
2. AMP E01 Jam 0.0554 7,030,434.92 389,638.56
3. Genset E12 Jam 0.0554 370,057.91 20,509.23
4. Dump Truck E09 Jam 0.7482 473,713.22 354,428.80
5. Pedestrian Roller E24 Jam 0.1975 85,087.04 16,805.66
6. Alat Bantu Ls 1.0000 0.00 0.00
NAMA KEGIATAN : 0
NAMA PEKERJAAN : 0
VOLUME : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 8.1 (4) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Waterbound Macadam Utk. Pek. Minor TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN
NAMA KEGIATAN :
NAMA PEKERJAAN :
VOLUME :
LOKASI :
ITEM PEMBAYARAN NO. : 0
JENIS PEKERJAAN : Saluran U - ditch ukuran 60 * 70
SATUAN PEMBAYARAN : M' PERKIRAAN VOL. PEK. :
TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN
NAMA KEGIATAN :
NAMA PEKERJAAN :
VOLUME :
LOKASI :
ITEM PEMBAYARAN NO. : 0
JENIS PEKERJAAN : Saluran U - ditch ukuran 60 * 80
SATUAN PEMBAYARAN : M' PERKIRAAN VOL. PEK. :
TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN
NAMA KEGIATAN :
NAMA PEKERJAAN :
VOLUME :
LOKASI :
ITEM PEMBAYARAN NO. : 0
JENIS PEKERJAAN : Saluran U - ditch ukuran 80 * 100
SATUAN PEMBAYARAN : M' PERKIRAAN VOL. PEK. :
TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN
NAMA KEGIATAN :
NAMA PEKERJAAN :
VOLUME :
LOKASI :
ITEM PEMBAYARAN NO. : 0
JENIS PEKERJAAN : Saluran U - ditch ukuran 100 * 100
SATUAN PEMBAYARAN : M' PERKIRAAN VOL. PEK. :
TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN
NAMA KEGIATAN :
NAMA PEKERJAAN :
VOLUME :
LOKASI :
ITEM PEMBAYARAN NO. : 0
JENIS PEKERJAAN : Saluran U - ditch ukuran 60 * 60
SATUAN PEMBAYARAN : M' PERKIRAAN VOL. PEK. :
TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN
NAMA KEGIATAN :
NAMA PEKERJAAN :
VOLUME :
LOKASI :
ITEM PEMBAYARAN NO. : 8.6.(6)
JENIS PEKERJAAN : Cover Saluran U - ditch ukuran 80
SATUAN PEMBAYARAN : M' PERKIRAAN VOL. PEK. :
TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :
A. TENAGA
B. BAHAN
C. PERALATAN