Anda di halaman 1dari 41

RENCANA ANGGARAN BIAYA

PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA


PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEKARNO - HATTA
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
NO. JENIS PEKERJAAN
Rp.

1 PEKERJAAN ELEKTRIKAL
1.1 SISTEM LISTRIK TEGANGAN MENENGAH 41,873,753,600.00
1.1.1 PANEL TEGANGAN MENENGAH 2,811,430,800.00
1.1.2 TRANSFORMERS 1,182,400,000.00
1.1.3 KABEL DAYA TEGANGAN MENENGAH 6,458,380,400.00
1.1.4 PEKERJAAN GENERATOR 3,326,542,400.00
1.1.5 PEKERJAAN PLTS (Panel Listrik Tenaga Surya) 25,215,000,000.00
1.1.6 INTEGRATION SCADA 2,880,000,000.00

1.2 SISTEM LISTRIK TEGANGAN RENDAH 58,343,241,360.00


1.2.1 PANEL LISTRIK TEGANGAN RENDAH 13,139,829,300.00
1.2.2 KABEL BUSDUCT 29,399,152,800.00
1.2.3 KABEL DAYA LISTRIK TEGANGAN RENDAH 10,469,873,160.00
1.2.4 ARMATUR LAMPU PENERANGAN 4,106,547,200.00
1.2.5 SAKLAR & STOP KONTAK 49,532,800.00
1.2.6 KABEL INSTALASI PENERANGAN & STOP KONTAK 1,178,306,100.00

1.3 SISTEM PENTANAHAN 100,450,470.00


1.3.1 BAK KONTROL & GROUNDING 19,920,000.00
1.3.2 GROUNDING TERMINAL BOX (GTB) 642,200.00
1.3.3 KAWAT PENTANAHAN 79,888,270.00

1.4 RAK KABEL ELEKTRIKAL 847,502,849.00

1.5 SISTEM PENANGKAL PETIR 181,598,558.00

1.6 TESTING & TRAINING 609,258,900.00

PENJUMLAHAN DAFTAR NO. 1 101,955,805,737.00

Rekap EL/HAL.1 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
1 PEKERJAAN ELEKTRIKAL
1.1 SISTEM LISTRIK TEGANGAN MENENGAH
1.1.1 PANEL TEGANGAN MENENGAH
Pengadaan, pemasangan dan pengujian Panel Utama Tegangan Menengah
pada sistim 20 kV, 3 fasa, 50 Hz dengan rumah panel yang dilengkapi pintu
berkunci dari bahan plat baja yang diphospatizing treatment ketebalan
minimum 2,0 mm dengan rangka besi serta dilengkapi mimic diagram, type
free standing, busbar dan pentanahan dari tembaga berdaya hantar tinggi,
komponen lengkap (break switches, instrument, alat ukur dan sebagainya)
dipasang sesuai petunjuk pabrik pembuatnya dilengkapi dengan gambar
wiring diagram, buku petunjuk pengoperasian dan alat bantu lainnya sesuai
gambar dan spesifikasi, serta berfungsi dengan baik.

A Panel MVDP-LHU dengan cubicle teridiri dari : 1.00 set 2,811,430,800.00 2,811,430,800.00
2 (dua) Cubicle Incoming
4 (empat) Cubicle Outgoing
1 (satu) Coupler
dengan komponen selengkapnya sesuai gambar dan spesifikasi.

PENJUMLAHAN DAFTAR NO. 1.1.1 2,811,430,800.00

1.1.2 TRANSFORMERS
Pengadaan, pemasangan dan pengujian Transformator termasuk peralatan
bantu trafo, test infra red, terminasi, memasangnya di atas pondasi yang
telah disediakan sesuai petunjuk pabrik pembuat berikut buku petunjuk
pengoperasian, alat bantu pemasangan yang diperlukan sesuai gambar dan
spesifikasi serta berfungsi dengan baik.

A Step down transformer 1 & 2, Kapasitas 2500 kVA Type Cast Resin memasangnya di 2.00 set 591,200,000.00 1,182,400,000.00
atas pondasi yang ditentukan dan melengkapinya dengan alat bantu pemasangan
serta perlengkapan lainnya sesuai gambar dan spesifikasi dan petunjuk pabrik
pembuat.

PENJUMLAHAN DAFTAR NO. 1.1.2 1,182,400,000.00

1.1.3 KABEL DAYA TEGANGAN MENENGAH


Pengadaan, pemasangan dan pengujian Kabel Tegangan Menengah 20 kV,
memenuhi standard VDE/DIN, dengan conductor, insulation, terminasi
sesuai ketentuan dalam gambar dan spesifikasi serta berfungsi dengan baik.

A Dari PS-3 ke MVDP-LHU


NA2XSEYFGBY 3 x 300 mm2 522.00 m 4,105,800.00 2,143,227,600.00
B Dari MVDP-LHU ke MV-HOTEL INTERNASIONAL
NA2XSEYFGBY 3 x 300 mm2 522.00 m 4,105,800.00 2,143,227,600.00
C Dari MVDP-LHU ke MV-HOTEL INTERNASIONAL
NA2XSEYFGBY 3 x 300 mm2 522.00 m 4,105,800.00 2,143,227,600.00
D Dari MVDP-LHU ke TRAFO-1 kap. 2.500 kVA
N2XSY 3 x 95 mm2 18.00 m 880,100.00 15,841,800.00
E Dari MVDP-LHU ke TRAFO-2 kap. 2.500 kVA
N2XSY 3 x 95 mm2 14.00 m 880,100.00 12,321,400.00
KABEL KONTROL

F Dari MVDP-LHU ke TRAFO-1 kap. 2.500 kVA


Kabel Kontrol NYYHY 2 x 2.5 mm2 18.00 m 16,700.00 300,600.00
G Dari MVDP-LHU ke TRAFO-2 kap. 2.500 kVA
Kabel Kontrol NYYHY 2 x 2.5 mm2 14.00 m 16,700.00 233,800.00

PENJUMLAHAN DAFTAR NO. 1.1.3 6,458,380,400.00

1.1.4 PEKERJAAN GENERATOR


Pengadaan Unit Genset kapasitas 1.250 KVA Silent Type lengkap dengan
Silencer, Battery, Engine DC, Exhaust Flexible Pipe, Daily Fuel Tank,
Generator Control Panel, serta alat bantu sesuai gambar dan spesifikasi.

A GENSET 1.250 kVA, Silent type 1.00 set 2,767,550,000.00 2,767,550,000.00


B Penel PKG 1.00 Unit 199,976,800.00 199,976,800.00
C Panel LV-BOX 1.00 Unit 88,723,600.00 88,723,600.00
D Panel ACTS 1.00 Unit 267,620,000.00 267,620,000.00
KABEL KONTROL
Dari Panel PKG ke Panel ACTS
E Kabel Kontrol NYYHY 2 x 2.5 mm2 80.00 m 16,700.00 1,336,000.00
Dari Panel PKG ke Panel LV-BOX
F Kabel Kontrol NYYHY 2 x 2.5 mm2 80.00 m 16,700.00 1,336,000.00

HPS Elektrikal/HAL.2 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
PENJUMLAHAN DAFTAR NO. 1.1.4 3,326,542,400.00

1.1.5 PEKERJAAN PLTS (Panel Listrik Tenaga Surya) 1.00 Lot 25,215,000,000.00 25,215,000,000.00
- PHOTOVOLTAIC ARRAY (1025pcs X @300 WP = 307.500 WP)
- JUCTION BOX
- Panel INVERTER ON-GRID
- Panel AC COMBINER

PENJUMLAHAN DAFTAR NO. 1.1.5 25,215,000,000.00

1.1.6 INTEGRATION SCADA

Pengadaan, pemasangan dan pengujian Integration SCADA terhadap SCADA 1.00 Set 2,880,000,000.00 2,880,000,000.00
Existing, lengkap dengan overview, terminasi, penyangga, penggantung,
klem-klem, pengaman / pelindung sparing lengkap dengan peralatan bantu
serta perlengkapan lainnya sesuai gambar dan spesifikasi dan berfungsu
dengan baik.

- Managed Switch
- Relay
- Hardwired I/O Module
- Modbus RTU / TCP Converter
- Modbus (TCP/IP) Ethernet
- Fiber Optic

PENJUMLAHAN DAFTAR NO. 1.1.6 2,880,000,000.00

1.2 SISTEM LISTRIK TEGANGAN RENDAH


1.2.1 PANEL LISTRIK TEGANGAN RENDAH
Pengadaan, pemasangan dan pengujian Panel Listrik Tegangan Rendah
pada sistem 380/220 volt, 3 fasa, 50 Hz dengan panel yang dilengkapi pintu
berkunci, busbar untuk fasa, neutral dan pentanahan, komponen lengkap
(switches, instrument dan metering) pada lokasi yang ditentukan termasuk
pondasi / penggantung, pengaman / pelindung serta perlengkapan dan alat
bantu lainya sesuai gambar dan spesifikasi serta berfungsi dengan baik.

A Panel LVMDP-LHU 1.00 set 3,389,565,600.00 3,389,565,600.00


Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
B Panel SDP-CHILLER 1.00 set 473,410,100.00 473,410,100.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
C Panel SDP-BHS 1.00 set 32,450,000.00 32,450,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
D Panel SDP-POMPA 1.00 set 82,650,000.00 82,650,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
E Panel SDP-2 1.00 set 212,229,900.00 212,229,900.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
F Panel SDP-1 1.00 set 210,377,700.00 210,377,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
G Panel SDP-G 1.00 set 210,377,700.00 210,377,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
H Panel SDP-EQ 1.00 set 436,513,100.00 436,513,100.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
I Panel SDP-AHU 1.00 set 416,497,500.00 416,497,500.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
J Panel PP-UPS 1.00 set 239,995,100.00 239,995,100.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
K Panel PC-WCCH-1 1.00 set 48,109,700.00 48,109,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
L Panel PC-CHWP-1 1.00 set 48,109,700.00 48,109,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik

HPS Elektrikal/HAL.3 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
M Panel PC-CHWP-3 1.00 set 48,109,700.00 48,109,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
N Panel PC-CWP-1 1.00 set 48,109,700.00 48,109,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
O Panel PP-CT 1.00 set 47,631,900.00 47,631,900.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
P Panel PC-WCCH-2 1.00 set 48,109,700.00 48,109,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
Q Panel PC-WCCH-3 1.00 set 48,109,700.00 48,109,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
R Panel PC-CHWP-2 1.00 set 48,109,700.00 48,109,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
S Panel PC-CWP-2 1.00 set 48,109,700.00 48,109,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
T Panel PC-CWP-3 1.00 set 48,109,700.00 48,109,700.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
U Panel PC-CT-1.1 1.00 set 47,631,900.00 47,631,900.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
V Panel PC-CT-2.1 1.00 set 47,631,900.00 47,631,900.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
W Panel PC-CT-3.1 1.00 set 47,631,900.00 47,631,900.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
X Panel PC-P. MAKE UP 1.00 set 16,950,000.00 16,950,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
Y Panel PC-CT-1.2 1.00 set 47,631,900.00 47,631,900.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
Z Panel PC-CT-2.2 1.00 set 47,631,900.00 47,631,900.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AA Panel PC-CT-3.2 1.00 set 47,631,900.00 47,631,900.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AA Panel PC-P. DOSING 1.00 set 16,950,000.00 16,950,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AB Panel PC-BOSTER 1.00 set 16,950,000.00 16,950,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AC Panel PL-2 A 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AD Panel PL.2 B 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AE Panel PP-LOUNGE 2 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AF Panel PS-2 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AG Panel PL-1 1.00 set 43,525,000.00 43,525,000.00

HPS Elektrikal/HAL.4 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AH Panel PP-COMM 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AI Panel PP-LOUNGE 1 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AJ Panel PL-PLAZA 1 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AK Panel PL-UHL 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AL Panel PS-1 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AM Panel PS-UHL 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AM Panel PL-G 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AN Panel PL-PLAZA G 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AO Panel PL-URH 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AP Panel PP-BS 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AQ Panel PL-BS 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AR Panel PP-G 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AS Panel PP-1 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AT Panel PP-2 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AU Panel PP-BS 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AV Panel PC-ESC-01 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AW Panel PC-ESC-02 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AX Panel PC-P. BBM 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AY Panel PC-ESC-03 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
AZ Panel PC-ESC-04 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BA Panel PC-SWGP-01 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik

HPS Elektrikal/HAL.5 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BB Panel PC-ESC-05 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BC Panel PC-ESC-06 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BD Panel PC-LIFT-P1-01 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BE Panel PC-TRV.01 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BF Panel PC-TRV.02 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BG Panel PC-LIFT-P1-02 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BH Panel PC-LIFT-S3 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BI Panel PC-SUMP P-01 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BJ Panel PC-SUMP P-03 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BK Panel PC-SWGP-B1 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BL Panel PC-SUMP P-02 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BM Panel PC-LIFT-P2-01 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BN Panel PC-LIFT-S2-01 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BO Panel PC-LIFT-P3-01 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BP Panel PC-LIFT-P2-02 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BQ Panel PC-LIFT-S2-02 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BR Panel PC-LIFT-P3-02 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BS Panel PC-LIFT-S2-03 1.00 set 15,375,000.00 15,375,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BT Panel PP-AHU-B 1.00 set 49,974,000.00 49,974,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BU Panel PP-AHU-G2 1.00 set 49,974,000.00 49,974,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BV Panel PP-AHU-1.3 1.00 set 49,974,000.00 49,974,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BW Panel PP-AHU-2.1 1.00 set 49,974,000.00 49,974,000.00

HPS Elektrikal/HAL.6 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BX Panel PP-AHU-2.2 1.00 set 49,974,000.00 49,974,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BY Panel PP-AHU-G.3 1.00 set 49,974,000.00 49,974,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
BZ Panel PP-AHU-G1 1.00 set 49,974,000.00 49,974,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CA Panel PP-AHU-1.2 1.00 set 49,974,000.00 49,974,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CB Panel PP-AHU-1.1 1.00 set 49,974,000.00 49,974,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CC Panel PP-AHU-2.3 1.00 set 49,974,000.00 49,974,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CD Panel SDP-UPS OUT 1.00 set 228,612,000.00 228,612,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CE Panel PL-GE-A 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CF Panel PP-1E 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CG Panel PP-2E 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CH Panel PP-1E-A 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CI Panel PL-2E 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CJ Panel PP-EC 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CK Panel PP-1E-B 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CL Panel PL-GE-B 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CM Panel PL-BS-E 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CN Panel PP-GE 1.00 set 69,525,000.00 69,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CO Panel PS-G 1.00 set 43,525,000.00 43,525,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102
CP MCB-BOX 22.00 set 1,875,000.00 41,250,000.00
Type Test Modullar System mengacu standar IEC 61439 1&2; IEC 61641 ; PUIL 2011
Termasuk on site, instalasi dan commissioning sampai berfungsi dengan baik
dengan komponen selengkapnya sesuai gambar dan spesifikasi. Gambar No. EL-102

UNINTERUPTABLE POWER SUPPLY (UPS)


E UPS kapasitas 200 KVA, min back up 30 minutes, sesuai gambar 2.00 unit 1,870,312,500.00 3,740,625,000.00

PENJUMLAHAN DAFTAR NO. 1.2.1 13,139,829,300.00

HPS Elektrikal/HAL.7 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
1.2.2 KABEL BUSDUCT
Pengadaan, pemasangan dan pengujian kabel busduct lengkap dengan
accessories tegangan rendah dipasang sesuai jalur yang ditentukan lengkap
dengan peralatan bantu serta perlengkapan lainnya sesuai gambar dan
spesifikasi serta berfungsi dengan baik.

A Dari TRAFO-1 kap. 2.500 kVA


ke LVMDP-LHU
CU Busduct 4000A 4W 8.00 m 748,831,000.00 5,990,648,000.00
B Dari TRAFO-2 kap. 2.500 kVA
ke Panel LV-BOX
CU Busduct 4000A 4W 7.20 m 748,831,000.00 5,391,583,200.00
C Dari Panel LV-BOX
ke Panel ACTS
CU Busduct 4000A 4W 7.20 m 748,831,000.00 5,391,583,200.00
D Dari Panel ACTS
ke LVMDP-LHU
CU Busduct 4000A 4W 7.20 m 748,831,000.00 5,391,583,200.00
E Dari GENSET 1.250 kVA
ke Panel PKG
CU Busduct 2000A 4W 18.00 m 374,415,500.00 6,739,479,000.00
F Dari SDP-CHILLER
ke Panel PC-WCCH-1
AL BUSDUCT 1250A 4W 20.00 m 6,209,500.00 124,190,000.00
ke Panel PC-WCCH-2
AL BUSDUCT 1250A 4W 26.60 m 6,209,500.00 165,172,700.00
ke Panel PC-WCCH-3
AL BUSDUCT 1250A 4W 33.00 m 6,209,500.00 204,913,500.00

PENJUMLAHAN DAFTAR NO. 1.2.2 29,399,152,800.00

1.2.3 KABEL DAYA LISTRIK TEGANGAN RENDAH


Pengadaan, pemasangan dan pengujian kabel daya listrik tegangan rendah
dipasang pada kabel tray elektrikal sesuai jalur yang ditentukan lengkap
dengan terminasi, cable glands, cable shoes, penyangga, penggantung,
klem-klem, pengaman / pelindung sparing dan peralatan bantu serta
perlengkapan sesuai gambar dan spesifikasi serta berfungsi dengan baik.

A Dari Panel PKG


ke Panel ACTS
NYY 4x 4x 1c x 300 mm2 80.00 m 3,725,700.00 298,056,000.00
B Dari LVMDP-LHU
ke SDP-CHILLER
NYY 9 x 4 x 1c x 300 mm2 + NYA 240 mm2 93.00 m 8,803,200.00 818,697,600.00
ke SDP-CHILLER
NYY 9 x 4 x 1c x 300 mm2 + NYA 240 mm2 93.00 m 8,803,200.00 818,697,600.00
C Dari SDP-CHILLER
ke Panel PC-CHWP-1
NYY 4 x 95 mm2 + NYA 50 mm2 18.00 m 777,100.00 13,987,800.00
ke Panel PC-CHWP-3
NYY 4 x 95 mm2 + NYA 50 mm2 18.00 m 777,100.00 13,987,800.00
ke Panel PC-CWP-1
NYY 4 x 50 mm2 + NYA 25 mm2 24.00 m 402,100.00 9,650,400.00
ke Panel PC-CT
NYY 4 x 1C x 240 mm2 + NYA 120 mm2 32.00 m 1,818,000.00 58,176,000.00
ke Panel PC-CHWP-2
NYY 4 x 95 mm2 + NYA 50 mm2 17.00 m 777,100.00 13,210,700.00
ke Panel PC-CWP-2
NYY 4 x 50 mm2 + NYA 25 mm2 24.00 m 402,100.00 9,650,400.00
ke Panel PC-CWP-3
NYY 4 x 50 mm2 + NYA 25 mm2 25.00 m 402,100.00 10,052,500.00
ke Panel PC-CT
NYY 4 x 1C x 240 mm2 + NYA 120 mm2 32.00 m 1,818,000.00 58,176,000.00
D Dari Panel PP-CT
ke Panel PC-CT-1.1
NYY 4 x 16 mm2 + NYA 16 mm2 55.00 m 153,100.00 8,420,500.00
ke Panel PC-CT-2.1
NYY 4 x 16 mm2 + NYA 16 mm2 53.00 m 153,100.00 8,114,300.00
ke Panel PC-CT-3.1
NYY 4 x 16 mm2 + NYA 16 mm2 51.00 m 153,100.00 7,808,100.00
ke Panel PC-P. MAKE UP
NYY 4 x 4 mm2 + NYA 4 mm2 49.00 m 65,600.00 3,214,400.00
ke Panel PC-CT-1.2
NYY 4 x 16 mm2 + NYA 16 mm2 47.00 m 153,100.00 7,195,700.00
ke Panel PC-CT-2.2
NYY 4 x 16 mm2 + NYA 16 mm2 45.00 m 153,100.00 6,889,500.00
ke Panel PC-CT-3.2
NYY 4 x 16 mm2 + NYA 16 mm2 43.00 m 153,100.00 6,583,300.00
ke Panel PC-P. DOSING
NYY 4 x 4 mm2 + NYA 4 mm2 41.00 m 65,600.00 2,689,600.00
E Dari LVMDP-LHU
ke Panel SDP-BHS
NYY 4 x 120 mm2 + NYA 70 mm2 183.00 m 434,700.00 79,550,100.00
ke Panel SDP-BHS
HPS Elektrikal/HAL.8 DARI 41
RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
NYY 4 x 120 mm2 + NYA 70 mm2 183.00 m 434,700.00 79,550,100.00
F Dari LVMDP-LHU
ke Panel SDP-POMPA
NYY 4 x 70 mm2 + NYA 35 mm2 187.00 m 253,700.00 47,441,900.00
ke Panel SDP-POMPA
NYY 4 x 70 mm2 + NYA 35 mm2 187.00 m 253,700.00 47,441,900.00
G Dari Panel SDP-POMPA
ke PC-BOSTER
NYY 4 x 6 mm2 + NYA 6 mm2 43.00 m 58,200.00 2,502,600.00
H Dari LVMDP-LHU
ke Panel SDP-2
NYY 4 x 2 x 1C x 185 mm2 + NYA 95 mm2 151.00 m 2,985,500.00 450,810,500.00
ke Panel SDP-2
NYY 4 x 2 x 1C x 185 mm2 + NYA 95 mm2 151.00 m 2,985,500.00 450,810,500.00
I Dari Panel SDP-2
ke Panel PL-2 A
NYY 4 x 16 mm2 + NYA 16 mm2 14.20 m 153,100.00 2,174,020.00
ke Panel PL-2 B
NYY 4 x 16 mm2 + NYA 16 mm2 101.00 m 153,100.00 15,463,100.00
ke Panel PL-LOUNGE 2
NYY 4 x 1C x 95 mm2 + NYA 50 mm2 102.00 m 337,300.00 34,404,600.00
ke Panel PS-2
NYY 4 x 16 mm2 + NYA 16 mm2 15.50 m 153,100.00 2,373,050.00
ke Panel PL-2 A
NYY 4 x 16 mm2 + NYA 16 mm2 14.20 m 153,100.00 2,174,020.00
ke Panel PL-2 B
NYY 4 x 16 mm2 + NYA 16 mm2 101.00 m 153,100.00 15,463,100.00
ke Panel PP-LOUNGE 2
NYY 4 x 1C x 95 mm2 + NYA 50 mm2 102.00 m 337,300.00 34,404,600.00
ke Panel PS-2
NYY 4 x 16 mm2 + NYA 16 mm2 15.50 m 153,100.00 2,373,050.00
J Dari Panel PP-LOUNGE 2
ke MCB-BOX COMMERCIAL 01
NYY 4 x 16 mm2 11.00 m 140,100.00 1,541,100.00
ke MCB-BOX COMMERCIAL 02
NYY 4 x 16 mm2 30.00 m 140,100.00 4,203,000.00
ke MCB-BOX COMMERCIAL 03
NYY 4 x 10 mm2 49.00 m 76,100.00 3,728,900.00
ke MCB-BOX COMMERCIAL 04
NYY 4 x 16 mm2 178.00 m 140,100.00 24,937,800.00
ke MCB-BOX COMMERCIAL 05
NYY 4 x 10 mm2 168.00 m 76,100.00 12,784,800.00
ke MCB-BOX COMMERCIAL 06
NYY 4 x 10 mm2 153.00 m 76,100.00 11,643,300.00
K Dari LVMDP-LHU
ke Panel SDP-1
NYY 4 x 4 x 1C x 300 mm2 + NYA 240 mm2 147.00 m 3,915,700.00 575,607,900.00
ke Panel SDP-1
NYY 4 x 4 x 1C x 300 mm2 + NYA 240 mm2 147.00 m 3,915,700.00 575,607,900.00
L Dari Panel SDP-1
ke Panel PL-1
NYY 4 x 16 mm2 + NYA 16 mm2 15.00 m 153,100.00 2,296,500.00
ke Panel PP-COMM
NYY 4 x 2 x (1 x 240 mm2) + NYA 120 mm2 12.00 m 3,630,300.00 43,563,600.00
ke Panel PP-LOUNGE 1
NYY 4 x 1 x 185 mm2 + NYA 95 mm2 143.00 m 1,535,800.00 219,619,400.00
ke Panel PL-PLAZA 1
NYY 4 x 16 mm2 + NYA 16 mm2 87.00 m 153,100.00 13,319,700.00
ke Panel PL-UHL
NYY 4 x 16 mm2 + NYA 16 mm2 69.00 m 153,100.00 10,563,900.00
ke Panel PS-1
NYY 4 x 16 mm2 + NYA 16 mm2 13.00 m 153,100.00 1,990,300.00
ke Panel PS-UHL
NYY 4 x 16 mm2 + NYA 16 mm2 71.00 m 153,100.00 10,870,100.00
ke Panel PL-1
NYY 4 x 16 mm2 + NYA 16 mm2 15.00 m 153,100.00 2,296,500.00
ke Panel PP-COMM
NYY 4 x 2 x (1 x 240 mm2) + NYA 120 mm2 12.00 m 3,630,300.00 43,563,600.00
ke Panel PP-LOUNGE 1
NYY 4 x 1 x 185 mm2 + NYA 95 mm2 143.00 m 1,535,800.00 219,619,400.00
ke Panel PL-PLAZA 1
NYY 4 x 16 mm2 + NYA 16 mm2 87.00 m 153,100.00 13,319,700.00
ke Panel PL-UHL
NYY 4 x 16 mm2 + NYA 16 mm2 69.00 m 153,100.00 10,563,900.00
ke Panel PS-1
NYY 4 x 16 mm2 + NYA 16 mm2 13.00 m 153,100.00 1,990,300.00
ke Panel PS-UHL
NYY 4 x 16 mm2 + NYA 16 mm2 71.00 m 153,100.00 10,870,100.00
M Dari Panel PP-COMM
ke MCB-BOX 01
NYY 4 x 35 mm2 71.00 m 288,200.00 20,462,200.00
ke MCB-BOX 02
NYY 4 x 35 mm2 55.00 m 288,200.00 15,851,000.00
ke MCB-BOX 03
NYY 4 x 35 mm2 43.00 m 288,200.00 12,392,600.00
ke MCB-BOX 04

HPS Elektrikal/HAL.9 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
NYY 4 x 35 mm2 26.00 m 288,200.00 7,493,200.00
ke MCB-BOX 05
NYY 4 x 35 mm2 25.00 m 288,200.00 7,205,000.00
ke MCB-BOX 06
NYY 4 x 35 mm2 90.00 m 288,200.00 25,938,000.00
ke MCB-BOX 07
NYY 4 x 35 mm2 91.00 m 288,200.00 26,226,200.00
ke MCB-BOX 08
NYY 4 x 35 mm2 122.00 m 288,200.00 35,160,400.00
ke MCB-BOX 09
NYY 4 x 35 mm2 143.00 m 288,200.00 41,212,600.00
N Dari Panel PP-LOUNGE 1
ke MCB-BOX COMMERCIAL 01
NYY 4 x 16 mm2 28.00 m 140,100.00 3,922,800.00
ke MCB-BOX COMMERCIAL 02
NYY 4 x 16 mm2 17.50 m 140,100.00 2,451,750.00
ke MCB-BOX COMMERCIAL 03
NYY 4 x 16 mm2 35.00 m 140,100.00 4,903,500.00
ke MCB-BOX COMMERCIAL 04
NYY 4 x 10 mm2 83.00 m 76,100.00 6,316,300.00
ke MCB-BOX COMMERCIAL 05
NYY 4 x 16 mm2 45.00 m 140,100.00 6,304,500.00
ke MCB-BOX COMMERCIAL 06
NYY 4 x 10 mm2 56.00 m 76,100.00 4,261,600.00
ke MCB-BOX COMMERCIAL 07
NYY 4 x 10 mm2 68.00 m 76,100.00 5,174,800.00
O Dari LVMDP-LHU
ke Panel SDP-G
NYY 4 x 2 x 1C x 150 mm2 + NYA 70 mm2 141.00 m 2,061,700.00 290,699,700.00
ke Panel SDP-G
NYY 4 x 2 x 1C x 150 mm2 + NYA 70 mm2 141.00 m 2,061,700.00 290,699,700.00
P Dari Panel SDP-G
ke Panel PL-G
NYY 4 x 16 mm2 + NYA 16 mm2 14.00 m 153,100.00 2,143,400.00
ke Panel PL-PLAZA G
NYY 4 x 16 mm2 + NYA 16 mm2 88.00 m 153,100.00 13,472,800.00
ke Panel PL-URH
NYY 4 x 16 mm2 + NYA 16 mm2 87.00 m 153,100.00 13,319,700.00
ke Panel PP-BS
NYY 4 x 16 mm2 + NYA 16 mm2 91.00 m 153,100.00 13,932,100.00
ke Panel PL-BS
NYY 4 x 16 mm2 + NYA 16 mm2 94.00 m 153,100.00 14,391,400.00
ke Panel PL-G
NYY 4 x 16 mm2 + NYA 16 mm2 14.00 m 153,100.00 2,143,400.00
ke Panel PL-PLAZA G
NYY 4 x 16 mm2 + NYA 16 mm2 88.00 m 153,100.00 13,472,800.00
ke Panel PL-URH
NYY 4 x 16 mm2 + NYA 16 mm2 87.00 m 153,100.00 13,319,700.00
ke Panel PP-BS
NYY 4 x 16 mm2 + NYA 16 mm2 91.00 m 153,100.00 13,932,100.00
ke Panel PL-BS
NYY 4 x 16 mm2 + NYA 16 mm2 94.00 m 153,100.00 14,391,400.00
Q Dari LVMDP-LHU
ke Panel SDP-EQ
NYY 4 x 2 x 1C x 185 mm2 + NYA 120 mm2 140.00 m 3,025,500.00 423,570,000.00
ke Panel SDP-EQ
NYY 4 x 2 x 1C x 185 mm2 + NYA 120 mm2 140.00 m 3,025,500.00 423,570,000.00
R Dari Panel SDP-EQ
ke Panel PP-G
NYY 4 x 70 mm2 + NYA 35 mm2 86.00 m 253,700.00 21,818,200.00
ke Panel PP-1
NYY 4 x 120 mm2 + NYA 70 mm2 102.00 m 434,700.00 44,339,400.00
ke Panel PP-2
NYY 4 x 120 mm2 + NYA 70 mm2 35.00 m 434,700.00 15,214,500.00
ke Panel PP-BS
NYY 4 x 70 mm2 + NYA 35 mm2 90.00 m 253,700.00 22,833,000.00
ke Panel PP-G
NYY 4 x 70 mm2 + NYA 35 mm2 86.00 m 253,700.00 21,818,200.00
ke Panel PP-1
NYY 4 x 120 mm2 + NYA 70 mm2 102.00 m 434,700.00 44,339,400.00
ke Panel PP-2
NYY 4 x 120 mm2 + NYA 70 mm2 35.00 m 434,700.00 15,214,500.00
ke Panel PP-BS
NYY 4 x 70 mm2 + NYA 35 mm2 90.00 m 253,700.00 22,833,000.00
S Dari Panel PP-G
ke Panel PC-ESC-01
NYY 4 x 10 mm2 + NYA 10 mm2 76.00 m 90,800.00 6,900,800.00
ke Panel PC-ESC-02
NYY 4 x 10 mm2 + NYA 10 mm2 74.00 m 90,800.00 6,719,200.00
ke Panel PC-P. BBM
NYY 4 x 6 mm2 + NYA 6 mm2 139.00 m 58,200.00 8,089,800.00
ke Panel PC-ESC-03
NYY 4 x 10 mm2 + NYA 10 mm2 104.00 m 90,800.00 9,443,200.00
ke Panel PC-ESC-04
NYY 4 x 10 mm2 + NYA 10 mm2 106.00 m 90,800.00 9,624,800.00
ke Panel PC-SWGP-01

HPS Elektrikal/HAL.10 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
NYY 4 x 6 mm2 + NYA 6 mm2 115.00 m 58,200.00 6,693,000.00
T Dari Panel PP-1
ke Panel PC-ESC-05
NYY 4 x 10 mm2 + NYA 10 mm2 61.00 m 90,800.00 5,538,800.00
ke Panel PC-ESC-06
NYY 4 x 10 mm2 + NYA 10 mm2 59.00 m 90,800.00 5,357,200.00
ke Panel PC-LIFT-P1-01
NYY 4 x 16 mm2 + NYA 16 mm2 261.00 m 153,100.00 39,959,100.00
ke Panel PC-TRV.01
NYY 4 x 10 mm2 + NYA 10 mm2 241.00 m 90,800.00 21,882,800.00
ke Panel PC-TRV.02
NYY 4 x 10 mm2 + NYA 10 mm2 239.00 m 90,800.00 21,701,200.00
ke Panel PC-LIFT-P1-02
NYY 4 x 10 mm2 + NYA 10 mm2 259.00 m 90,800.00 23,517,200.00
ke Panel PC-LIFT-S3
NYY 4 x 10 mm2 + NYA 10 mm2 32.00 m 90,800.00 2,905,600.00
U Dari Panel PP-2
ke Panel PC-LIFT-P2-01
NYY 4 x 10 mm2 + NYA 10 mm2 106.00 m 90,800.00 9,624,800.00
ke Panel PC-LIFT-S2-01
NYY 4 x 10 mm2 + NYA 10 mm2 73.00 m 90,800.00 6,628,400.00
ke Panel PC-LIFT-P3-01
NYY 4 x 10 mm2 + NYA 10 mm2 161.00 m 90,800.00 14,618,800.00
ke Panel PC-LIFT-P2-02
NYY 4 x 10 mm2 + NYA 10 mm2 105.00 m 90,800.00 9,534,000.00
ke Panel PC-LIFT-S2-02
NYY 4 x 10 mm2 + NYA 10 mm2 72.00 m 90,800.00 6,537,600.00
NYY 4 x 10 mm2 + NYA 10 mm2 164.00 m 90,800.00 14,891,200.00
ke Panel PC-LIFT-S2-03
NYY 4 x 10 mm2 + NYA 10 mm2 174.00 m 90,800.00 15,799,200.00
V Dari Panel PP-BS
ke EF-B.P/03
NYY 4 x 6 mm2 + NYA 6 mm2 64.00 m 58,200.00 3,724,800.00
+ ke Motor NYY 2 x (3 x 6 mm2) + NYA 6 mm2 3.00 m 87,300.00 261,900.00
ke EF-B.P/01
NYY 4 x 6 mm2 + NYA 6 mm2 148.00 m 58,200.00 8,613,600.00
+ ke Motor NYY 2 x (3 x 6 mm2) + NYA 6 mm2 3.00 m 87,300.00 261,900.00
ke EF-B.P/02
NYY 4 x 6 mm2 + NYA 6 mm2 103.00 m 58,200.00 5,994,600.00
+ ke Motor NYY 2 x (3 x 6 mm2) + NYA 6 mm2 3.00 m 87,300.00 261,900.00
ke PC-SUMP P-01
NYY 4 x 4 mm2 + NYA 4 mm2 75.00 m 65,600.00 4,920,000.00
ke PC-SUMP P-03
NYY 4 x 4 mm2 + NYA 4 mm2 115.00 m 65,600.00 7,544,000.00
ke IF-B.P/02
NYY 4 x 10 mm2 + NYA 10 mm2 82.00 m 90,800.00 7,445,600.00
ke IF-B.P/01
NYY 4 x 10 mm2 + NYA 10 mm2 116.00 m 90,800.00 10,532,800.00
ke IF-B.P/03
NYY 4 x 10 mm2 + NYA 10 mm2 71.00 m 90,800.00 6,446,800.00
ke PC-SWGP-B1
NYY 4 x 4 mm2 + NYA 4 mm2 106.00 m 65,600.00 6,953,600.00
ke PC-SUMP P-02
NYY 4 x 4 mm2 + NYA 4 mm2 54.00 m 65,600.00 3,542,400.00
W Dari LVMDP-LHU
ke Panel SDP-AHU
NYY 4 x 2 x 1C x 240 mm2 + NYA 240 mm2 138.00 m 3,919,100.00 540,835,800.00
ke Panel SDP-AHU
NYY 4 x 2 x 1C x 240 mm2 + NYA 240 mm2 138.00 m 3,919,100.00 540,835,800.00
X Dari Panel SDP-AHU
ke Panel PP-AHU-B
NYY 4 x 95 mm2 + NYA 50 mm2 108.00 m 777,100.00 83,926,800.00
ke Panel PP-AHU-G.2
NYY 4 x 95 mm2 + NYA 50 mm2 40.00 m 777,100.00 31,084,000.00
ke Panel PP-AHU-1.3
NYY 4 x 150 mm2 + NYA 70 mm2 64.00 m 519,700.00 33,260,800.00
ke Panel PP-AHU-2.1
NYY 4 x 120 mm2 + NYA 70 mm2 194.00 m 434,700.00 84,331,800.00
ke Panel PP-AHU-2.2
NYY 4 x 150 mm2 + NYA 70 mm2 146.00 m 519,700.00 75,876,200.00
ke Panel PP-AHU-G.3
NYY 4 x 95 mm2 + NYA 50 mm2 74.00 m 777,100.00 57,505,400.00
ke Panel PP-AHU-G.1
NYY 4 x 95 mm2 + NYA 50 mm2 179.00 m 777,100.00 139,100,900.00
ke Panel PP-AHU-1.2
NYY 4 x 150 mm2 + NYA 70 mm2 118.00 m 519,700.00 61,324,600.00
ke Panel PP-AHU-1.1
NYY 4 x 120 mm2 + NYA 70 mm2 232.00 m 434,700.00 100,850,400.00
ke Panel PP-AHU-2.3
NYY 4 x 150 mm2 + NYA 70 mm2 71.00 m 519,700.00 36,898,700.00
Y Dari Panel PP-AHU-B
ke Panel PP-AHU-G.3
NYY 4 x 50 mm2 44.00 m 381,100.00 16,768,400.00
Ke AHU-B.OF/01
NYY 2 (3 x 16 mm2) + NYA 16 mm2 15.00 m 125,700.00 1,885,500.00
Ke AHU-B.OF/02

HPS Elektrikal/HAL.11 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
NYY 2 (3 x 16 mm2) + NYA 16 mm2 11.00 m 125,700.00 1,382,700.00
Z Dari Panel PP-AHU-G2
ke Panel PP-AHU-G.1
NYY 4 x 50 mm2 186.00 m 381,100.00 70,884,600.00
Ke AHU-2.SC/01
NYY 2 (3 x 16 mm2) + NYA 16 mm2 15.00 m 125,700.00 1,885,500.00
Ke AHU-2.SC/02
NYY 2 (3 x 16 mm2) + NYA 16 mm2 11.00 m 125,700.00 1,382,700.00
AA Dari Panel PP-AHU-1.3
ke Panel PP-AHU-1.2
NYY 4 x 95 mm2 139.00 m 739,100.00 102,734,900.00
Ke AHU-1.UH/01
NYY 2 (3 x 16 mm2) + NYA 16 mm2 24.00 m 125,700.00 3,016,800.00
Ke AHU-1.UH/02
NYY 2 (3 x 16 mm2) + NYA 16 mm2 28.00 m 125,700.00 3,519,600.00
Ke AHU-1.CA/01
NYY 2 (3 x 16 mm2) + NYA 16 mm2 19.00 m 125,700.00 2,388,300.00
Ke AHU-1.CAP/01
NYY 2 (3 x 16 mm2) + NYA 16 mm2 14.20 m 125,700.00 1,784,940.00
AB Dari Panel PP-AHU-2.1
ke Panel PP-AHU-1.1
NYY 4 x 50 mm2 20.00 m 381,100.00 7,622,000.00
Ke AHU-2.LG/01
NYY 2 (3 x 16 mm2) + NYA 16 mm2 17.00 m 125,700.00 2,136,900.00
Ke AHU-2.LG/02
NYY 2 (3 x 16 mm2) + NYA 16 mm2 12.80 m 125,700.00 1,608,960.00
AC Dari Panel PP-AHU-2.2
ke Panel PP-AHU-2.3
NYY 4 x 95 mm2 166.00 m 739,100.00 122,690,600.00
Ke AHU-2.IH/01
NYY 2 (3 x 16 mm2) + NYA 16 mm2 13.30 m 125,700.00 1,671,810.00
Ke AHU-2.IH/02
NYY 2 (3 x 16 mm2) + NYA 16 mm2 18.00 m 125,700.00 2,262,600.00
Ke AHU-2.IH/03
NYY 2 (3 x 16 mm2) + NYA 16 mm2 21.70 m 125,700.00 2,727,690.00
AD Dari Panel PP-AHU-G.3
Ke AHU-G.UR/01
NYY 2 (3 x 16 mm2) + NYA 16 mm2 13.00 m 125,700.00 1,634,100.00
AE Dari Panel PP-AHU-G.1
Ke AHU-1.LGP/01
NYY 2 (3 x 16 mm2) + NYA 16 mm2 13.50 m 125,700.00 1,696,950.00
Ke AHU-1.LGP/02
NYY 2 (3 x 16 mm2) + NYA 16 mm2 18.00 m 125,700.00 2,262,600.00
AF Dari Panel PP-AHU-1.2
Ke AHU-1.CAP/02
NYY 2 (3 x 16 mm2) + NYA 16 mm2 14.00 m 125,700.00 1,759,800.00
AG Dari Panel PP-AHU-1.1
Ke AHU-1.LG/03
NYY 2 (3 x 16 mm2) + NYA 16 mm2 19.50 m 125,700.00 2,451,150.00
Ke AHU-1.LG/04
NYY 2 (3 x 16 mm2) + NYA 16 mm2 13.50 m 125,700.00 1,696,950.00
AH Dari Panel PP-AHU-2.3
Ke AHU-2.PCH/01
NYY 2 (3 x 16 mm2) + NYA 16 mm2 17.00 m 125,700.00 2,136,900.00
Ke AHU-2.PCH/02
NYY 2 (3 x 16 mm2) + NYA 16 mm2 12.00 m 125,700.00 1,508,400.00
AI Dari LVMDP-LHU
ke Panel PP-UPS
NYY 4 x 1C x 240 mm2 + NYA 120 mm2 120.00 m 1,818,000.00 218,160,000.00
ke Panel PP-UPS
NYY 4 x 1C x 240 mm2 + NYA 120 mm2 120.00 m 1,818,000.00 218,160,000.00
AJ Dari Panel PP-UPS
ke UPS ONLINE (200 kVA)
NYY 4 x 1C x 240 mm2 + NYA 120 mm2 11.00 m 1,818,000.00 19,998,000.00
ke UPS ONLINE (200 kVA)
NYY 4 x 1C x 240 mm2 + NYA 120 mm2 11.00 m 1,818,000.00 19,998,000.00
AK Dari UPS ONLINE (200 kVA)
ke Panel SDP-UPS.OUT
NYY 4 x 1C x 240 mm2 + NYA 120 mm2 15.10 m 1,818,000.00 27,451,800.00
ke Panel SDP-UPS.OUT
NYY 4 x 1C x 240 mm2 + NYA 120 mm2 13.80 m 1,818,000.00 25,088,400.00
AL Dari Panel SDP-UPS.OUT
ke Panel PL-GE.A
NYY 4 x 50 mm2 + NYA 25 mm2 22.00 m 402,100.00 8,846,200.00
ke Panel PP-1E
NYY 4 x 50 mm2 + NYA 25 mm2 34.00 m 402,100.00 13,671,400.00
ke Panel PP-2E
NYY 4 x 70 mm2 + NYA 35 mm2 41.00 m 253,700.00 10,401,700.00
ke Panel PP-1E-A
NYY 4 x 16 mm2 + NYA 16 mm2 35.00 m 153,100.00 5,358,500.00
ke Panel PL-2E
NYY 4 x 16 mm2 + NYA 16 mm2 43.00 m 153,100.00 6,583,300.00
ke Panel PP-EC
NYY 4 x 50 mm2 + NYA 35 mm2 80.00 m 409,100.00 32,728,000.00
ke Panel PP-1E-B
NYY 4 x 16 mm2 + NYA 16 mm2 109.00 m 153,100.00 16,687,900.00

HPS Elektrikal/HAL.12 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
ke Panel PP-GE-B
NYY 4 x 16 mm2 + NYA 16 mm2 80.00 m 153,100.00 12,248,000.00
ke Panel PL-BS-E
NYY 4 x 16 mm2 + NYA 16 mm2 80.00 m 153,100.00 12,248,000.00
ke Panel PP-GE
NYY 4 x 16 mm2 + NYA 16 mm2 22.00 m 153,100.00 3,368,200.00
ke Panel PS-G
NYY 4 x 16 mm2 + NYA 16 mm2 22.60 m 153,100.00 3,460,060.00
ke Panel PL-GE.A
NYY 4 x 50 mm2 + NYA 25 mm2 22.00 m 402,100.00 8,846,200.00
ke Panel PP-1E
NYY 4 x 35 mm2 + NYA 16 mm2 34.00 m 301,200.00 10,240,800.00
ke Panel PP-2E
NYY 4 x 70 mm2 + NYA 35 mm2 41.00 m 253,700.00 10,401,700.00
ke Panel PP-1E-A
NYY 4 x 16 mm2 + NYA 16 mm2 35.00 m 153,100.00 5,358,500.00
ke Panel PL-2E
NYY 4 x 16 mm2 + NYA 16 mm2 43.00 m 153,100.00 6,583,300.00
ke Panel PP-EC
NYY 4 x 50 mm2 + NYA 35 mm2 80.00 m 409,100.00 32,728,000.00
ke Panel PP-1E-B
NYY 4 x 16 mm2 + NYA 16 mm2 109.00 m 153,100.00 16,687,900.00
ke Panel PP-GE-B
NYY 4 x 16 mm2 + NYA 16 mm2 80.00 m 153,100.00 12,248,000.00
ke Panel PL-BS-E
NYY 4 x 16 mm2 + NYA 16 mm2 80.00 m 153,100.00 12,248,000.00
ke Panel PP-GE
NYY 4 x 16 mm2 + NYA 16 mm2 22.00 m 153,100.00 3,368,200.00
ke Panel PS-G
NYY 4 x 16 mm2 + NYA 16 mm2 22.60 m 153,100.00 3,460,060.00

PENJUMLAHAN DAFTAR NO. 1.2.3 10,469,873,160.00

1.2.4 ARMATUR LAMPU PENERANGAN


Pengadaan, pemasangan dan pengujian Armature Lampu, grounding,
pemasangan pada lokasi dan cara yang ditentukan, penyambungan dengan
kabel instalasi final, termasuk terminal, dilengkapi alat bantu dan
perlengkapan sesuai gambar, spesifikasi dan petunjuk pabrik pembuat serta
berfungsi dengan baik.

LANTAI BASEMENT
A LED Panel Recessed 1200 x 300 40 W 138.00 bh 1,349,900.00 186,286,200.00
B LED Triproof 1 x 16 W 217.00 bh 1,171,000.00 254,107,000.00
C Downligth LED 10 W 5000 K 12.00 bh 695,800.00 8,349,600.00
D LAMPU EXIT 4.00 bh 1,352,900.00 5,411,600.00
LANTAI GROUND FLOOR
E LED Triproof 2 x 16 W 345.00 bh 1,686,200.00 581,739,000.00
F LED Triproof 1 x 16 W 318.00 bh 1,171,000.00 372,378,000.00
G Downligth LED 22 W 4000 K 398.00 bh 907,800.00 361,304,400.00
H Downligth LED 10 W 5000 K 40.00 bh 695,800.00 27,832,000.00
I LAMPU EXIT 7.00 bh 1,352,900.00 9,470,300.00
LANTAI 1
J LED Triproof 1 x 16 W 64.00 bh 1,171,000.00 74,944,000.00
K Downligth LED 22 W 4000 K 783.00 bh 907,800.00 710,807,400.00
L Downligth LED 10 W 5000 K 145.00 bh 695,800.00 100,891,000.00
M Downligth LED 40 W 5000 K 287.00 bh 1,719,800.00 493,582,600.00
N LAMPU EXIT 11.00 bh 1,352,900.00 14,881,900.00
LANTAI 2
O LED Panel Recessed 600 x 600 40 W 57.00 bh 1,204,000.00 68,628,000.00
P LED Triproof 1 x 16 W 66.00 bh 1,171,000.00 77,286,000.00
Q Downligth LED 40 W 5000 K 382.00 bh 1,719,800.00 656,963,600.00
R Downligth LED 10 W 5000 K 107.00 bh 695,800.00 74,450,600.00
S Downligth LED 22 W 4000 K 30.00 bh 907,800.00 27,234,000.00

PENJUMLAHAN DAFTAR NO. 1.2.4 4,106,547,200.00

1.2.5 SAKLAR & STOP KONTAK


Pengadaan, pemasangan dan pengujian Saklar & Stop Kontak dari type
flush mounting (kecuali yang ditentukan lain), flush box dari bahan bakely
atau metal, dipasang pada lokasi dan jarak dari lantai sesuai yang
ditentukan, dilengkapi alat bantu dan perlengkapan sesuai gambar dan
spesifikasi serta berfungsi dengan baik.

LANTAI BASEMENT

HPS Elektrikal/HAL.13 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
A Saklar Engkel 11.00 bh 60,900.00 669,900.00
B Stop Kontak Wall Type 10 A 15.00 bh 190,300.00 2,854,500.00
LANTAI GROUND FLOOR
E Saklar Engkel 3.00 bh 60,900.00 182,700.00
F Stop Kontak Wall Type 10 A 44.00 bh 190,300.00 8,373,200.00
LANTAI 1
J Stop Kontak Wall Type 10 A 41.00 bh 190,300.00 7,802,300.00
K Stop Kontak X-Ray 16 A 10.00 bh 380,300.00 3,803,000.00
LANTAI 2
O Stop Kontak Wall Type 10 A 106.00 bh 190,300.00 20,171,800.00
P Stop Kontak X-Ray 16 A 12.00 bh 380,300.00 4,563,600.00
Q Stop Kontak Lantai 1.500 W 6.00 bh 185,300.00 1,111,800.00

PENJUMLAHAN DAFTAR NO. 1.2.5 49,532,800.00

1.2.6 KABEL INSTALASI PENERANGAN & STOP KONTAK


Pengadaan, pemasangan dan pengujian kabel instalasi untuk Penerangan
dan Stop Kontak lengkap dengan pipa pelindung dipasang pada posisinya
pada plat beton atau tertanam didinding, termasuk pembobokan dan
pemelesteran kembali jalur pipa pelindung, serta penyambungan kabel
pada panel dan stop kontak termasuk terminal phasa, neutral dan
grounding dengan alat bantu dan perlengkapan sesuai gambar dan
spesifikasi serta berfungsi dengan baik.

LANTAI BASEMENT
A Kabel NYY 3 x 2,5 mm di dalam HI PVC conduit dia. 20 mm untuk armatur lampu 371.00 ttk 316,500.00 117,421,500.00
B Kabel NYY 3 x 2,5 mm di dalam HI PVC conduit dia. 20 mm untuk stop kontak 15.00 ttk 421,900.00 6,328,500.00
LANTAI GROUND FLOOR
C Kabel NYY 3 x 2,5 mm di dalam HI PVC conduit dia. 20 mm untuk armatur lampu 1,108.00 ttk 316,500.00 350,682,000.00
D Kabel NYY 3 x 2,5 mm di dalam HI PVC conduit dia. 20 mm untuk stop kontak 44.00 ttk 421,900.00 18,563,600.00
LANTAI 1
C Kabel NYY 3 x 2,5 mm di dalam HI PVC conduit dia. 20 mm untuk armatur lampu 1,290.00 ttk 316,500.00 408,285,000.00
D Kabel NYY 3 x 2,5 mm di dalam HI PVC conduit dia. 20 mm untuk stop kontak 51.00 ttk 421,900.00 21,516,900.00
LANTAI 2
C Kabel NYY 3 x 2,5 mm di dalam HI PVC conduit dia. 20 mm untuk armatur lampu 642.00 ttk 316,500.00 203,193,000.00
D Kabel NYY 3 x 2,5 mm di dalam HI PVC conduit dia. 20 mm untuk stop kontak 124.00 ttk 421,900.00 52,315,600.00

PENJUMLAHAN DAFTAR NO. 1.2.6 1,178,306,100.00

1.3 SISTEM PENTANAHAN


1.3.1 BAK KONTROL & GROUNDING
Pengadaan, pemasangan dan pengujian Bak kontrol dan grounding terbuat
dari copper rod diameter 25,4 mm ditanam sedalam minimal 12 m atau
sepanjang yang diperlukan sampai mencapai tahanan tanah maximum 2
Ohm, termasuk copper socket, bronze nut, copper ring, klem-klem dan bak
kontrol 400 x 400 x 500 mm dari pasangan beton bertulang termasuk
penutup dari bahan yang sama dan pengangkatnya serta perlengkapan dan
alat bantu lainnya sesuai gambar dan spesifikasi serta berfungsi dengan
baik.

A Bak Kontrol Grounding lengkap dengan seluruh accessories, serta alat bantu sesuai 5.00 ttk 3,984,000.00 19,920,000.00
gambar dan spesifikasi.
- Grounding Body MVDP & Trafo
- Grounding Body LVMDP
- Grounding Netral Trafo 1
- Grounding Netral Trafo 2
- Grounding Lift

PENJUMLAHAN DAFTAR NO. 1.3.1 19,920,000.00

1.3.2 GROUNDING TERMINAL BOX (GTB)

Pengadaan, pemasangan dan pengujian Grounding Terminal Box (GTB)


lengkap dengan busbar terminal strip (CU) serta peralatan bantu dan
perlengkapan lainnya sesuai gambar dan spesifikasi serta berfungsi dengan
baik.

A Grounding Terminal Box (GTB) lengkap dengan seluruh accessories, serta alat 2.00 ttk 321,100.00 642,200.00
bantu sesuai gambar dan spesifikasi.

PENJUMLAHAN DAFTAR NO. 1.3.2 642,200.00

1.3.3 KAWAT PENTANAHAN


HPS Elektrikal/HAL.14 DARI 41
RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
Pengadaan, pemasangan dan pengujian kawat pentanahan dari bahan Bare
Copper Conductor sesuai jalur yang ditentukan, termasuk alat bantu dan
perlengkapan sesuai gambar dan spesifikasi, serta standard VDE dan PUIL
serta berfungsi dengan baik.

Dari Netral Trafo 1 ke GTB


A Kabel BC 120 mm² 46.30 m 124,600.00 5,768,980.00
Dari Body Trafo 1 ke GTB
B Kabel NYA 240 mm2 31.80 m 433,200.00 13,775,760.00
Dari Netral Trafo 2 ke GTB
C Kabel NYA 120 mm2 17.30 m 214,200.00 3,705,660.00
Dari Body Trafo 2 ke GTB
D Kabel NYA 240 mm2 33.69 m 433,200.00 14,594,508.00
Dari MVDP-LHU ke GTB
E Kabel BC 120 mm² 9.38 m 124,600.00 1,168,748.00
Dari LVMDP-LHU ke GTB
F Kabel BC 120 mm² 21.79 m 124,600.00 2,715,034.00
Dari GTB ke BKG 1
G Kabel NYA 120 mm2 29.30 m 214,200.00 6,276,060.00
Dari GTB ke BKG 2
H Kabel NYA 240 mm2 25.80 m 433,200.00 11,176,560.00
Dari GTB ke BKG 3
I Kabel NYA 240 mm2 22.00 m 433,200.00 9,530,400.00
Dari GTB ke BKG 4
I Kabel NYA 240 mm2 25.80 m 433,200.00 11,176,560.00

PENJUMLAHAN DAFTAR NO. 1.3.3 79,888,270.00

1.4 RAK KABEL ELEKTRIKAL


Pengadaan, pemasangan dan pengujian Rak Kabel terbuat dari bahan
perforated steel palte hot dip galvanized dengan tebal minimum 2 mm
dalam bentuk, ukuran dan lay out yang ditentukan, klem kabel dari
aluminium dan mur baut stainless steel termasuk gantungan besi plat atau
besi siku (dicat zinchromat) ke plat beton atap atau dinding dengan ikatan
ramset (fisher plug) lengkap dengan percabangan, elbow, peralatan bantu
dan perlengkapan sesuai gambar dan spesifikasi serta berfungsi dengan
baik.

LANTAI BASEMENT
A Kabel tray 300 x 100 43.86 m 424,300.00 18,609,798.00
B Kabel tray 200 x 100 147.07 m 324,600.00 47,738,922.00
C Kabel tray 150 x 100 144.09 m 304,800.00 43,918,632.00
LANTAI GROUND FLOOR
D Kabel Ladder 1000 x 100 mm 346.02 m 492,800.00 170,518,656.00
E Kabel tray 300 x 100 89.17 m 424,300.00 37,834,831.00
F Kabel tray 200 x 100 188.08 m 324,600.00 61,050,768.00
G Kabel Ladder 800 x 100 mm 64.40 m 436,100.00 28,084,840.00
LANTAI 1
H Kabel tray 600 x 100 77.67 m 537,900.00 41,778,693.00
I Kabel tray 400 x 100 83.21 m 503,700.00 41,912,877.00
J Kabel tray 300 x 100 122.26 m 424,300.00 51,874,918.00
K Kabel tray 200 x 100 169.68 m 324,600.00 55,078,128.00
L Kabel tray 150 x 100 178.33 m 304,800.00 54,354,984.00
M TC 150 x 40 32.94 m 8,100.00 266,814.00
N TC 80 x 40 11.14 m 7,100.00 79,094.00
LANTAI 2
M Kabel tray 300 x 100 115.32 m 424,300.00 48,930,276.00
N Kabel tray 200 x 100 242.90 m 324,600.00 78,845,340.00
O Kabel tray 150 x 100 163.10 m 304,800.00 49,712,880.00
P TC 80 x 40 82.08 m 7,100.00 582,768.00
Q TC 100 x 40 48.72 m 7,600.00 370,272.00
R TC 200 x 40 40.13 m 8,600.00 345,118.00
RUANG MAIN POWER HOUSE
M Kabel tray 300 x 100 36.80 m 424,300.00 15,614,240.00
PENJUMLAHAN DAFTAR NO. 1.4 847,502,849.00

1.5 SISTEM PENANGKAL PETIR

HPS Elektrikal/HAL.15 DARI 41


RENCANA ANGGARAN BIAYA
PROYEK : PERLUASAN TERMINAL SOEKARNO - HATTA
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEK
LOKASI : JL.P2, PANJANG, BENDA, KOTA TANGGERANG, BANTEN
UNIT PEKERJAAN : ELEKTRIKAL

JUMLAH HARGA
H. SATUAN
NO. JENIS PEKERJAAN VOLUME SAT
Rp. Rp.
Pengadaan, pemasangan dan pengujian Sistem Penangkal Petir meliputi Air
Terminal yang di pasang pada lokasi yang ditentukan, kabel penghantar
penangkal petir dan elektroda pentanahan, lengkap dengan alat bantu dan
perlengkapan sesuai gambar dan spesifikasi serta berfungsi dengan baik.

A Air Terminal Pole 500 mm 14.00 bh 1,200,000.00 16,800,000.00


B Air Terminal Pole 1000 mm 9.00 bh 2,400,000.00 21,600,000.00
C Air Terminal 23.00 bh 412,500.00 9,487,500.00
D BC 50 mm 2,018.06 m 44,300.00 89,400,058.00
L Clamp For BC 2,018.00 bh 7,500.00 15,135,000.00
N Polymer Inspection Pit 20.00 bh 656,300.00 13,126,000.00
O Driving Stud By Furse 20.00 bh 52,500.00 1,050,000.00
P Bare Copper 25 x 3 mmsq 20.00 bh 262,500.00 5,250,000.00
Q Earth Copper Rod By Furse 40.00 bh 112,500.00 4,500,000.00
R Wire To Earth Rod Clamp Suitable For Size 25 x 3 mmsq 20.00 bh 262,500.00 5,250,000.00

PENJUMLAHAN DAFTAR NO. 1.5 181,598,558.00

1.6 TESTING & TRAINING


A TOTAL KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING 1.00 Lot 609,258,900.00 609,258,900.00
( FAT ) PEKERJAAN ELEKTRIKAL

PENJUMLAHAN DAFTAR NO. 1.6 609,258,900.00

HPS Elektrikal/HAL.16 DARI 41


ANALISA HARGA SATUAN

HARGA BAHAN ALAT BANTU UPAH SUB TOTAL JASA PEMB. TOTAL DIBULATKAN
NO Item Pekerjaan SAT

( Rp ) ( Rp ) ( Rp ) ( Rp ) ( Rp ) ( Rp )

PERALATAN ELEKTRIKAL

PANEL TM

1 Panel MVDP-LHU set 2,810,005,851 Termasuk 1,425,000 2,811,430,851 2,811,430,800

TRANSFORMATOR

1 Step down transformer 1 & 2, Kapasitas 2500 kVA Type Cast set 590,000,000 Termasuk 1,200,000 591,200,000 591,200,000
Resin memasangnya di atas pondasi yang ditentukan dan
melengkapinya dengan alat bantu pemasangan serta
perlengkapan lainnya sesuai gambar dan spesifikasi dan
petunjuk pabrik pembuat.

KABEL TM

1 NA2XSEYFGBY 3 x 300 mm2 m 4,087,125 Termasuk 18,750 4,105,875 4,105,800

2 N2XSY 3 x 95 mm2 m 861,420 Termasuk 18,750 880,170 880,100

KABEL KONTROL

1 Kabel Kontrol NYYHY 2 x 2.5 mm2 m 11,000 Termasuk 5,750 16,750 16,700

GENSET

1 Pengadaan Unit Genset kapasitas 1.250 KVA Silent Type set 2,750,000,000 Termasuk Termasuk 2,750,000,000 2,750,000,000
lengkap dengan Silencer, Battery, Engine DC, Exhaust
Flexible Pipe, Daily Fuel Tank, Generator Control Panel, serta
alat bantu sesuai gambar dan spesifikasi.

Biaya Pemasangan Genset kapasitas 2.000 KVA penurunan lot 15,150,000 Termasuk 2,400,000 17,550,000 17,550,000
dari atas truk dan menaikkan ke atas pondasi yang
disediakan (handling) lengkap dengan Panel PKG sesiai
gambar EL-101A, termasuk pengkabelan lainnya. Panel
kontrol synchronizing dengan sistem genset existing dan
seluruh instalasi pengkabelan, pemipaan, katup-katup,
assessories, serta alat bantu sesuai gambar dan spesifikasi.

2 Penel PKG set 199,501,800 Termasuk 475,000 199,976,800 199,976,800


3 Panel LV-BOX Unit 88,248,600 Termasuk 475,000 88,723,600 88,723,600
4 Panel ACTS Unit 267,145,000 Termasuk 475,000 267,620,000 267,620,000

PANEL TR
1 Panel LVMDP-LHU set 3,388,615,650 Termasuk 950,000 3,389,565,650 3,389,565,600
2 Panel SDP-CHILLER set 472,460,100 Termasuk 950,000 473,410,100 473,410,100
3 Panel SDP-BHS set 31,500,000 Termasuk 950,000 32,450,000 32,450,000
4 Panel SDP-POMPA set 81,700,000 Termasuk 950,000 82,650,000 82,650,000
5 Panel SDP-2 set 211,279,950 Termasuk 950,000 212,229,950 212,229,900
6 Panel SDP-1 set 209,427,750 Termasuk 950,000 210,377,750 210,377,700
7 Panel SDP-G set 209,427,750 Termasuk 950,000 210,377,750 210,377,700
8 Panel SDP-EQ set 435,563,100 Termasuk 950,000 436,513,100 436,513,100
9 Panel SDP-AHU set 415,547,500 Termasuk 950,000 416,497,500 416,497,500
10 Panel PP-UPS set 239,045,100 Termasuk 950,000 239,995,100 239,995,100
11 Panel PC-WCCH-1 set 47,159,700 Termasuk 950,000 48,109,700 48,109,700
12 Panel PC-CHWP-1 set 47,159,700 Termasuk 950,000 48,109,700 48,109,700
13 Panel PC-CHWP-3 set 47,159,700 Termasuk 950,000 48,109,700 48,109,700
14 Panel PC-CWP-1 set 47,159,700 Termasuk 950,000 48,109,700 48,109,700
15 Panel PP-CT set 46,681,950 Termasuk 950,000 47,631,950 47,631,900
16 Panel PC-WCCH-2 set 47,159,700 Termasuk 950,000 48,109,700 48,109,700
17 Panel PC-WCCH-3 set 47,159,700 Termasuk 950,000 48,109,700 48,109,700
18 Panel PC-CHWP-2 set 47,159,700 Termasuk 950,000 48,109,700 48,109,700
19 Panel PC-CWP-2 set 47,159,700 Termasuk 950,000 48,109,700 48,109,700
20 Panel PC-CWP-3 set 47,159,700 Termasuk 950,000 48,109,700 48,109,700
21 Panel PC-CT-1.1 set 46,681,950 Termasuk 950,000 47,631,950 47,631,900
22 Panel PC-CT-2.1 set 46,681,950 Termasuk 950,000 47,631,950 47,631,900
23 Panel PC-CT-3.1 set 46,681,950 Termasuk 950,000 47,631,950 47,631,900
24 Panel PC-P. MAKE UP set 16,575,000 Termasuk 375,000 16,950,000 16,950,000
25 Panel PC-CT-1.2 set 46,681,950 Termasuk 950,000 47,631,950 47,631,900
26 Panel PC-CT-2.2 set 46,681,950 Termasuk 950,000 47,631,950 47,631,900
27 Panel PC-CT-3.2 set 46,681,950 Termasuk 950,000 47,631,950 47,631,900
28 Panel PC-P. DOSING set 16,575,000 Termasuk 375,000 16,950,000 16,950,000
29 Panel PC-BOSTER set 16,575,000 Termasuk 375,000 16,950,000 16,950,000
30 Panel PL-2 A set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
31 Panel PL.2 B set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
32 Panel PP-LOUNGE 2 set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
33 Panel PS-2 set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
34 Panel PL-1 set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
35 Panel PP-COMM set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
36 Panel PP-LOUNGE 1 set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
37 Panel PL-PLAZA 1 set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
38 Panel PL-UHL set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
39 Panel PS-1 set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
40 Panel PS-UHL set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
41 Panel PL-G set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
42 Panel PL-PLAZA G set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
43 Panel PL-URH set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
44 Panel PP-BS set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
45 Panel PL-BS set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
46 Panel PP-G set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
47 Panel PP-1 set 68,575,000 Termasuk 950,000 69,525,000 69,525,000

Rekap AHS EL/HAL.17 DARI 41


HARGA BAHAN ALAT BANTU UPAH SUB TOTAL JASA PEMB. TOTAL DIBULATKAN
NO Item Pekerjaan SAT

( Rp ) ( Rp ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
48 Panel PP-2 set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
49 Panel PP-BS set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
50 Panel PC-ESC-01 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
51 Panel PC-ESC-02 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
52 Panel PC-P. BBM set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
53 Panel PC-ESC-03 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
54 Panel PC-ESC-04 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
55 Panel PC-SWGP-01 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
56 Panel PC-ESC-05 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
57 Panel PC-ESC-06 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
58 Panel PC-LIFT-P1-01 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
59 Panel PC-TRV.01 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
60 Panel PC-TRV.02 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
61 Panel PC-LIFT-P1-02 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
62 Panel PC-LIFT-S3 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
63 Panel PC-SUMP P-01 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
64 Panel PC-SUMP P-03 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
65 Panel PC-SWGP-B1 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
66 Panel PC-SUMP P-02 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
67 Panel PC-LIFT-P2-01 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
68 Panel PC-LIFT-S2-01 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
69 Panel PC-LIFT-P3-01 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
70 Panel PC-LIFT-P2-02 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
71 Panel PC-LIFT-S2-02 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
72 Panel PC-LIFT-P3-02 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
73 Panel PC-LIFT-S2-03 set 15,000,000 Termasuk 375,000 15,375,000 15,375,000
74 Panel PP-AHU-B set 49,024,000 Termasuk 950,000 49,974,000 49,974,000
75 Panel PP-AHU-G2 set 49,024,000 Termasuk 950,000 49,974,000 49,974,000
76 Panel PP-AHU-1.3 set 49,024,000 Termasuk 950,000 49,974,000 49,974,000
77 Panel PP-AHU-2.1 set 49,024,000 Termasuk 950,000 49,974,000 49,974,000
78 Panel PP-AHU-2.2 set 49,024,000 Termasuk 950,000 49,974,000 49,974,000
79 Panel PP-AHU-G.3 set 49,024,000 Termasuk 950,000 49,974,000 49,974,000
80 Panel PP-AHU-G1 set 49,024,000 Termasuk 950,000 49,974,000 49,974,000
81 Panel PP-AHU-1.2 set 49,024,000 Termasuk 950,000 49,974,000 49,974,000
82 Panel PP-AHU-1.1 set 49,024,000 Termasuk 950,000 49,974,000 49,974,000
83 Panel PP-AHU-2.3 set 49,024,000 Termasuk 950,000 49,974,000 49,974,000
84 Panel SDP-UPS OUT set 227,662,000 Termasuk 950,000 228,612,000 228,612,000
85 Panel PL-GE-A set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
86 Panel PP-1E set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
87 Panel PP-2E set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
88 Panel PP-1E-A set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
89 Panel PL-2E set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
90 Panel PP-EC set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
91 Panel PP-1E-B set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
92 Panel PL-GE-B set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
93 Panel PL-BS-E set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
94 Panel PP-GE set 68,575,000 Termasuk 950,000 69,525,000 69,525,000
95 Panel PS-G set 42,575,000 Termasuk 950,000 43,525,000 43,525,000
96 MCB-BOX set 1,500,000 Termasuk 375,000 1,875,000 1,875,000

KABEL TR
1 NYY 2 x (3 x 6 mm2) + NYA 6 mm2 m 81,640 Termasuk 5,750 87,390 87,300
2 NYY 2 (3 x 16 mm2) + NYA 16 mm2 m 120,000 Termasuk 5,750 125,750 125,700
3 NYY 4 x 1 x 185 mm2 + NYA 95 mm2 m 1,530,063 Termasuk 5,750 1,535,813 1,535,800
4 NYY 4 x 10 mm2 m 70,350 Termasuk 5,750 76,100 76,100
5 NYY 4 x 10 mm2 + NYA 10 mm2 m 85,050 Termasuk 5,750 90,800 90,800
6 NYY 4 x 120 mm2 + NYA 70 mm2 m 429,000 Termasuk 5,750 434,750 434,700
7 NYY 4 x 150 mm2 + NYA 70 mm2 m 514,000 Termasuk 5,750 519,750 519,700
8 NYY 4 x 16 mm2 m 134,400 Termasuk 5,750 140,150 140,100
9 NYY 4 x 16 mm2 + NYA 16 mm2 m 147,400 Termasuk 5,750 153,150 153,100
10 NYY 4 x 1C x 240 mm2 + NYA 120 mm2 m 1,812,300 Termasuk 5,750 1,818,050 1,818,000
11 NYY 4 x 1C x 95 mm2 + NYA 50 mm2 m 331,550 Termasuk 5,750 337,300 337,300
12 NYY 4 x 2 x (1 x 240 mm2) + NYA 120 mm2 m 3,624,600 Termasuk 5,750 3,630,350 3,630,300
13 NYY 4 x 2 x 1C x 150 mm2 + NYA 70 mm2 m 2,056,000 Termasuk 5,750 2,061,750 2,061,700
14 NYY 4 x 2 x 1C x 185 mm2 + NYA 120 mm2 m 3,019,750 Termasuk 5,750 3,025,500 3,025,500
15 NYY 4 x 2 x 1C x 185 mm2 + NYA 95 mm2 m 2,979,750 Termasuk 5,750 2,985,500 2,985,500
16 NYY 4 x 2 x 1C x 240 mm2 + NYA 240 mm2 m 3,913,420 Termasuk 5,750 3,919,170 3,919,100
17 NYY 4 x 35 mm2 m 282,450 Termasuk 5,750 288,200 288,200
18 NYY 4 x 35 mm2 + NYA 16 mm2 m 295,450 Termasuk 5,750 301,200 301,200
19 NYY 4 x 4 mm2 + NYA 4 mm2 m 59,850 Termasuk 5,750 65,600 65,600
20 NYY 4 x 4 x 1C x 300 mm2 + NYA 240 mm2 m 3,910,000 Termasuk 5,750 3,915,750 3,915,700
21 NYY 4 x 50 mm2 m 375,375 Termasuk 5,750 381,125 381,100
22 NYY 4 x 50 mm2 + NYA 25 mm2 m 396,375 Termasuk 5,750 402,125 402,100
23 NYY 4 x 50 mm2 + NYA 35 mm2 m 403,375 Termasuk 5,750 409,125 409,100
24 NYY 4 x 6 mm2 + NYA 6 mm2 m 52,500 Termasuk 5,750 58,250 58,200
25 NYY 4 x 70 mm2 + NYA 35 mm2 m 248,000 Termasuk 5,750 253,750 253,700
26 NYY 4 x 95 mm2 m 733,425 Termasuk 5,750 739,175 739,100
27 NYY 4 x 95 mm2 + NYA 50 mm2 m 771,425 Termasuk 5,750 777,175 777,100
28 NYY 4 x 4 x 1c x 300 mm2 m 3,720,000 Termasuk 5,750 3,725,750 3,725,700
29 NYY 9 x 4 x 1c x 300 mm2 + NYA 240 mm2 m 8,797,500 Termasuk 5,750 8,803,250 8,803,200

KAWAT PENTANAHAN
1 Kabel BC 120 mm² m 118,860 Termasuk 5,750 124,610 124,600
2 Kabel NYA 120 mm2 m 208,500 Termasuk 5,750 214,250 214,200
3 Kabel NYA 240 mm2 m 427,500 Termasuk 5,750 433,250 433,200

ARMATURE LAMPU PENERANGAN


1 Downligth LED 10 W 5000 K bh 600,000 Termasuk 95,825 695,825 695,800
2 Downligth LED 22 W 4000 K bh 812,000 Termasuk 95,825 907,825 907,800
3 Downligth LED 40 W 5000 K bh 1,624,000 Termasuk 95,825 1,719,825 1,719,800

Rekap AHS EL/HAL.18 DARI 41


HARGA BAHAN ALAT BANTU UPAH SUB TOTAL JASA PEMB. TOTAL DIBULATKAN
NO Item Pekerjaan SAT

( Rp ) ( Rp ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
4 LAMPU EXIT bh 1,257,143 Termasuk 95,825 1,352,968 1,352,900
5 LED Panel Recessed 1200 x 300 40 W bh 1,254,167 Termasuk 95,825 1,349,992 1,349,900
6 LED Panel Recessed 600 x 600 40 W bh 1,108,200 Termasuk 95,825 1,204,025 1,204,000
7 LED Triproof 1 x 16 W bh 1,075,200 Termasuk 95,825 1,171,025 1,171,000
8 LED Triproof 2 x 16 W bh 1,590,400 Termasuk 95,825 1,686,225 1,686,200

SAKLAR & STOP KONTAK


1 Saklar Engkel bh 45,600 Termasuk 15,300 60,900 60,900
2 Stop Kontak Lantai 1.500 W bh 162,500 Termasuk 22,800 185,300 185,300
3 Stop Kontak Wall Type 10 A bh 175,000 Termasuk 15,300 190,300 190,300
4 Stop Kontak X-Ray 16 A bh 357,500 Termasuk 22,800 380,300 380,300

GROUNDING
1 Bak Kontrol, Pengadaan, pemasangan dan pengujian Bak bh 3,916,500 Termasuk 67,565 3,984,065 3,984,000
kontrol dan grounding terbuat dari copper rod diameter 25,4
mm ditanam sedalam minimal 12 m atau sepanjang yang
diperlukan sampai mencapai tahanan tanah maximum 2
Ohm, termasuk copper socket, bronze nut, copper ring,
klem-klem dan bak kontrol 400 x 400 x 500 mm dari
pasangan beton bertulang termasuk penutup dari bahan
yang sama dan pengangkatnya serta perlengkapan dan alat
bantu lainnya sesuai gambar dan spesifikasi.

2 Pengadaan, pemasangan dan pengujian Grounding Terminal bh 301,140 Termasuk 20,000 321,140 321,100
Box (GTB) lengkap dengan busbar terminal strip (CU) serta
peralatan bantu dan perlengkapan lainnya sesuai gambar
dan spesifikasi.

KABEL TRAY
1 Kabel Ladder 1000 x 100 mm m 441,500 Termasuk 51,250 492,750 492,800
2 Kabel Ladder 800 x 100 mm m 384,833 Termasuk 51,250 436,083 436,100
3 Kabel tray 150 x 100 m 253,500 Termasuk 51,250 304,750 304,800
4 Kabel tray 200 x 100 m 273,390 Termasuk 51,250 324,640 324,600
5 Kabel tray 300 x 100 m 373,000 Termasuk 51,250 424,250 424,300
6 Kabel tray 400 x 100 m 452,400 Termasuk 51,250 503,650 503,700
7 Kabel tray 600 x 100 m 486,660 Termasuk 51,250 537,910 537,900
8 Kabel Tray 100 x 50 mm m 142,133 Termasuk 51,250 193,383 193,400
9 TC 100 x 40 m 7,000 Termasuk 550 7,550 7,600
10 TC 150 x 40 m 7,500 Termasuk 550 8,050 8,100
11 TC 200 x 40 m 8,000 Termasuk 550 8,550 8,600
12 TC 80 x 40 m 6,500 Termasuk 550 7,050 7,100

SISTEM PENANGKAL PETIR


1 Air Terminal Pole 500 mm bh 1,200,000 Termasuk Termasuk 1,200,000 1,200,000
2 Air Terminal Pole 1000 mm bh 2,400,000 Termasuk Termasuk 2,400,000 2,400,000
3 Air Terminal bh 412,500 Termasuk Termasuk 412,500 412,500
4 BC 50 mm m 38,535 Termasuk 5,750 44,285 44,300
5 Clamp For BC bh 7,500 Termasuk Termasuk 7,500 7,500
6 Polymer Inspection Pit bh 656,250 Termasuk Termasuk 656,250 656,300
7 Driving Stud By Furse bh 52,500 Termasuk Termasuk 52,500 52,500
8 Bare Copper 25 x 3 mmsq bh 262,500 Termasuk Termasuk 262,500 262,500
9 Earth Copper Rod By Furse bh 112,500 Termasuk Termasuk 112,500 112,500
10 Wire To Earth Rod Clamp Suitable For Size 25 x 3 mmsq bh 262,500 Termasuk Termasuk 262,500 262,500

PEKERJAAN PLTS (Panel Listrik Tenaga Surya)


1 Solar panel @ 300 WP pcs 1,025
2 Watt Peak WP 307,500
3 Efektifitas rata - rata sinar matahari jam 5
4 Estimasi Harga PLTS Watt 82,000
TOTAL 25,215,000,000

Rekap AHS EL/HAL.19 DARI 41


ANALISA HARGA SATUAN Sat Qty Harga Satuan (Rp) Harga Total (Rp)

PEKERJAAN KABEL DENGAN CONDUIT

INSTALASI PENERANGAN

1 NYY 3 x 2,5 mm² dalam HI PVC conduit dia. 20 mm


untuk armatur lampu per titik

- Kabel NYY 3 x 2,5 mm² m 15 15,750 236,250


- PVC conduit diameter 20 mm m 15 3,000 45,000
- Alat bantu Ls 1 14,100 14,100
- Upah pasang Ls 1 21,100 21,100

Sub Total 316,450

Jasa Pemborong

Total 316,500

INSTALASI STOP KONTAK

2 NYY 3 x 2,5 mm² dalam HI PVC conduit dia. 20 mm


untuk stop kontak per titik

- Kabel NYY 3 x 2,5 mm² m 20 15,750 315,000


- PVC conduit diameter 20 mm m 20 3,000 60,000
- Alat bantu Ls 1 18,800 18,800
- Upah pasang Ls 1 28,100 28,100

Sub Total 421,900

Jasa Pemborong

Total 421,900

BUSDUCT
1 AL Busduct 1250A 4W
untuk kabel busduct per meter

- 3200A CU Busduct Straight Length m 1 4,415,625 4,415,625


- Accessories Ls 1 1,103,906 1,103,906
- Alat bantu Ls 1 276,000 276,000
- Upah pasang Ls 1 414,000 414,000

Sub Total 6,209,531

Jasa Pemborong

Total 6,209,500

2 CU Busduct 4000A 4W
untuk kabel busduct per meter

- 4000A CU Busduct Straight Length m 1 532,502,000 532,502,000


- Flang end
- Accessories Ls 1 133,125,500 133,125,500
- Alat bantu Ls 1 33,281,400 33,281,400
- Upah pasang Ls 1 49,922,100 49,922,100

Sub Total 748,831,000

Jasa Pemborong

Total 748,831,000

3 CU Busduct 2000A 4W
untuk kabel busduct per meter

- 2000A CU Busduct Straight Length m 1 266,251,000 266,251,000


- Flang end
- Accessories Ls 1 66,562,750 66,562,750
- Alat bantu Ls 1 16,640,700 16,640,700
- Upah pasang Ls 1 24,961,000 24,961,000

Sub Total 374,415,450

Jasa Pemborong

Total 374,415,500

AHS EL Kabel Conduit/HAL.20 DARI 41


ANALISA HARGA SATUAN KEGIATAN ACCEPTANCE TEST, COMMISSION

PEKERJAAN ELEKTRIKAL

PROYEK : Perluasan Bandara Soekarno Hatta


LOKASI : Tanggerang, Banten
PEKERJAAN : PERLUASAN TERMINAL UMROH DAN HAJI SERTA PENAMBAHAN AREA CHECK-IN D
Sub Pekerjaan : -
TAHUN : 2019

VI.1.8 KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( F.A.T )

A Factory Acceptance Test - Transformator Daya Listrik ( Dalam Negeri )


Diikuti oleh 2 ( Dua ) orang dari Kantor Cabang dan 2 ( Dua ) orang Kantor Pusat selama 3 ( tiga
1) Peserta Kantor Cabang ;
a. Tiket = 2 orang x 1
b. Hotel / Penginapan = 2 orang x 3
c. Uang Saku = 2 orang x 3
d. Uang Bantuan Makan = 2 orang x 3
e. Bantuan Uang Laundry = 2 orang x 3
f. Bantuan Uang Taksi Lokal = 2 orang x 1

2) Peserta Kantor Pusat ;


a. Bantuan Uang Makan = 2 orang x 3

Jumlah Factory Acceptance Test - Transformator Daya Listrik

B Factory Acceptance Test - LVMDP ( Dalam Negeri )


Diikuti oleh 2 ( Dua ) orang dari Kantor Cabang dan 2 ( Dua ) orang Kantor Pusat selama 3 ( tiga
1) Peserta Kantor Cabang ;
a. Tiket = 2 orang x 1
b. Hotel / Penginapan = 2 orang x 3
c. Uang Saku = 2 orang x 3
d. Uang Bantuan Makan = 2 orang x 3
e. Bantuan Uang Laundry = 2 orang x 3
f. Bantuan Uang Taksi Lokal = 2 orang x 1

2) Peserta Kantor Pusat ;

ANALISA FAT - ELEKTRIKAL


Hal : 21 of 41
460217693.xlsx
VI.1.8 KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( F.A.T )
a. Bantuan Uang Makan = 2 orang x 3

Jumlah Factory Acceptance Test - LVMDP

C Factory Acceptance Test - Panel Tegangan Menengah ( Dalam Negeri )


Diikuti oleh 2 ( Dua ) orang dari Kantor Cabang dan 2 ( Dua ) orang Kantor Pusat selama 3 ( tiga
1) Peserta Kantor Cabang ;
a. Tiket = 2 orang x 1
b. Hotel / Penginapan = 2 orang x 3
c. Uang Saku = 2 orang x 3
d. Uang Bantuan Makan = 2 orang x 3
e. Bantuan Uang Laundry = 2 orang x 3
f. Bantuan Uang Taksi Lokal = 2 orang x 1

2) Peserta Kantor Pusat ;


a. Bantuan Uang Makan = 2 orang x 3

Jumlah Factory Acceptance Test - Panel Tegangan Menengah

ANALISA FAT - ELEKTRIKAL


Hal : 22 of 41
460217693.xlsx
VI.1.8 KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( F.A.T )

D Factory Acceptance Test - Kabel ( Dalam Negeri )


Diikuti oleh 2 ( Dua ) orang dari Kantor Cabang dan 2 ( Dua ) orang Kantor Pusat selama 3 ( tiga
1) Peserta Kantor Cabang ;
a. Tiket = 2 orang x 1
b. Hotel / Penginapan = 2 orang x 3
c. Uang Saku = 2 orang x 3
d. Uang Bantuan Makan = 2 orang x 3
e. Bantuan Uang Laundry = 2 orang x 3
f. Bantuan Uang Taksi Lokal = 2 orang x 1

2) Peserta Kantor Pusat ;


a. Bantuan Uang Makan = 2 orang x 3

Jumlah Factory Acceptance Test - Kabel

E Factory Acceptance Test - BUSDUCT ( Dalam Negeri )


Diikuti oleh 2 ( Dua ) orang dari Kantor Cabang dan 2 ( Dua ) orang Kantor Pusat selama 3 ( tiga
1) Peserta Kantor Cabang ;
a. Tiket = 2 orang x 1
b. Hotel / Penginapan = 2 orang x 3
c. Uang Saku = 2 orang x 3
d. Uang Bantuan Makan = 2 orang x 3
e. Bantuan Uang Laundry = 2 orang x 3
f. Bantuan Uang Taksi Lokal = 2 orang x 1

2) Peserta Kantor Pusat ;


a. Bantuan Uang Makan = 2 orang x 3

Jumlah Factory Acceptance Test - BUSDUCT

F Factory Acceptance Test - Genset di Pabrik pembuat ( Luar Negeri )


Diikuti oleh 1 ( Satu ) orang dari Kantor Cabang dan 1 ( Satu ) orang Kantor Pusat selama 5 ( Lim
Pembuat ( Luar Negeri )

ANALISA FAT - ELEKTRIKAL


Hal : 23 of 41
460217693.xlsx
VI.1.8 KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( F.A.T )
1) Peserta Kantor Cabang :
a. Biaya Pengurusan Paspor dan Visa
- Biaya Paspor + Visa = 2 orang x 1
b. Tiket = 2 orang x 1
c. Tiket Jakarta - Factory - Jakarta = 2 orang x 1
d. Hotel / Penginapan = 2 orang x 3
e. Uang Harian = 2 orang x 5
f. Bantuan Uang Taxi Lokal = 2 orang x 5
g. Bantuan Uang Laundry = 2 orang x 3

2) Peserta Kantor Pusat :


a. Biaya pengurusan Paspor dan Visa
- Biaya Paspor + Visa = 1 orang x 1
b. Tiket Jakarta - Factory - Jakarta = 1 orang x 1
c. Hotel / Penginapan = 1 orang x 3
d. Uang Harian = 1 orang x 5
e. Bantuan Uang Taxi Lokal = 1 orang x 5
f. Bantuan Uang Laundry = 1 orang x 3
*1 USD = Rp 13,500

Jumlah Factory Acceptance Test - Genset di Pabrik pembua

ANALISA FAT - ELEKTRIKAL


Hal : 24 of 41
460217693.xlsx
VI.1.8 KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( F.A.T )

G Factory Training - Genset di Pabrik Pembuat ( Luar Negeri )

Diikuti oleh 1 ( Satu ) orang Kantor Cabang selama 5 ( Lima ) hari - ( termasuk perjalanan 2 hari

1) Peserta Kantor Cabang :


a. Biaya Pengurusan Paspor dan Visa
- Biaya Paspor + Visa = orang x 1
b. Tiket = orang x 1
c. Tiket Jakarta - Factory - Jakarta = orang x 1
d. Hotel / Penginapan = orang x 3
e. Uang Harian = orang x 5
f. Bantuan Uang Taxi Lokal = orang x 5
g. Bantuan Uang Laundry = orang x 3
*1 USD = Rp 13,500

Jumlah Factory Training - Genset di Pabrik Pembua

H Factory Acceptance Test - UPS di Pabrik pembuat ( Luar Negeri )


Diikuti oleh 1 ( Satu ) orang dari Kantor Cabang dan 1 ( Satu ) orang Kantor Pusat selama 5 ( Lim
Pembuat ( Luar Negeri )
1) Peserta Kantor Cabang :
a. Biaya Pengurusan Paspor dan Visa
- Biaya Paspor + Visa = 1 orang x 1
b. Tiket = 1 orang x 1
c. Tiket Jakarta - Factory - Jakarta = 1 orang x 1
d. Hotel / Penginapan = 1 orang x 3
e. Uang Harian = 1 orang x 5
f. Bantuan Uang Taxi Lokal = 1 orang x 5
g. Bantuan Uang Laundry = 1 orang x 3

2) Peserta Kantor Pusat :


a. Biaya pengurusan Paspor dan Visa
- Biaya Paspor + Visa = 1 orang x 1
b. Tiket Jakarta - Factory - Jakarta = 1 orang x 1
c. Hotel / Penginapan = 1 orang x 3
d. Uang Harian = 1 orang x 5

ANALISA FAT - ELEKTRIKAL


Hal : 25 of 41
460217693.xlsx
VI.1.8 KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( F.A.T )
e. Bantuan Uang Taxi Lokal = 1 orang x 5
f. Bantuan Uang Laundry = 1 orang x 3
*1 USD = Rp 13,500

Jumlah Factory Acceptance Test - UPS di Pabrik pembua

I Factory Training - UPS di Pabrik Pembuat ( Luar Negeri )

Diikuti oleh 1 ( Satu ) orang Kantor Cabang selama 5 ( Lima ) hari - ( termasuk perjalanan 2 hari

1) Peserta Kantor Cabang :


a. Biaya Pengurusan Paspor dan Visa
- Biaya Paspor + Visa = orang x 1
b. Tiket = orang x 1
c. Tiket Jakarta - Factory - Jakarta = orang x 1
d. Hotel / Penginapan = orang x 3
e. Uang Harian = orang x 5
f. Bantuan Uang Taxi Lokal = orang x 5
g. Bantuan Uang Laundry = orang x 3
*1 USD = Rp 13,500

Jumlah Factory Training - UPS di Pabrik Pembua

ANALISA FAT - ELEKTRIKAL


Hal : 26 of 41
460217693.xlsx
VI.1.8 KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( F.A.T )

J Site Acceptance Test dan Commissioning Sistem Terpasang


1 Transformator Daya Listrik
Diikuti oleh 2 ( Dua ) orang dari Kantor Pusat dan 15 ( Lima Belas ) orang Kantor Cabang selama
( 2 orang dari Airport Equiment Readiness Group - Kantor Pusat dan 15 orang dari Kantor Cabang )
a) Peserta Kantor Pusat :
- Tiket = 2 orang x 1
- Hotel / Penginapan = 2 orang x 2
- Uang Saku = 2 orang x 2
- Uang Bantuan Makan = 2 orang x 2
- Bantuan Uang Laundry = 2 orang x 2
- Bantuan Uang Taksi Lokal = 2 orang x 2

b) Peserta Kantor Cabang :


- Uang Bantuan Makan = 15 orang x 2

2 LVMDP
Diikuti oleh 2 ( Dua ) orang dari Kantor Pusat dan 15 ( Lima Belas ) orang Kantor Cabang selama
( 2 orang dari Airport Equiment Readiness Group - Kantor Pusat dan 15 orang dari Kantor Cabang )
a) Peserta Kantor Pusat :
- Tiket Manado - Jakarta - Manado = 2 orang x 1
- Hotel / Penginapan = 2 orang x 2
- Uang Saku = 2 orang x 2
- Uang Bantuan Makan = 2 orang x 2
- Bantuan Uang Laundry = 2 orang x 2
- Bantuan Uang Taksi Lokal = 2 orang x 2

b) Peserta Kantor Cabang :


- Uang Bantuan Makan = 15 orang x 2

ANALISA FAT - ELEKTRIKAL


Hal : 27 of 41
460217693.xlsx
VI.1.8 KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( F.A.T )

3 Panel Tegangan Menengah


Diikuti oleh 2 ( Dua ) orang dari Kantor Pusat dan 15 ( Lima Belas ) orang Kantor Cabang selama
( 2 orang dari Airport Equiment Readiness Group - Kantor Pusat dan 15 orang dari Kantor Cabang )
a) Peserta Kantor Pusat :
- Tiket = 2 orang x 1
- Hotel / Penginapan = 2 orang x 2
- Uang Saku = 2 orang x 2
- Uang Bantuan Makan = 2 orang x 2
- Bantuan Uang Laundry = 2 orang x 2
- Bantuan Uang Taksi Lokal = 2 orang x 2

b) Peserta Kantor Cabang :


- Uang Bantuan Makan = 15 orang x 2

ANALISA FAT - ELEKTRIKAL


Hal : 28 of 41
460217693.xlsx
VI.1.8 KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( F.A.T )

4 Genset
Diikuti oleh 2 ( Dua ) orang dari Kantor Pusat dan 15 ( Lima Belas ) orang Kantor Cabang selama
( 2 orang dari Airport Equiment Readiness Group - Kantor Pusat dan 15 orang dari Kantor Cabang )
a) Peserta Kantor Pusat :
- Tiket Manado - Jakarta - Manado = 2 orang x 1
- Hotel / Penginapan = 2 orang x 2
- Uang Saku = 2 orang x 2
- Uang Bantuan Makan = 2 orang x 2
- Bantuan Uang Laundry = 2 orang x 2
- Bantuan Uang Taksi Lokal = 2 orang x 2

b) Peserta Kantor Cabang :


- Uang Bantuan Makan = 15 orang x 2

5 UPS
Diikuti oleh 2 ( Dua ) orang dari Kantor Pusat dan 15 ( Lima Belas ) orang Kantor Cabang selama
( 2 orang dari Airport Equiment Readiness Group - Kantor Pusat dan 15 orang dari Kantor Cabang )
a) Peserta Kantor Pusat :
- Tiket = 2 orang x 1
- Hotel / Penginapan = 2 orang x 2
- Uang Saku = 2 orang x 2
- Uang Bantuan Makan = 2 orang x 2
- Bantuan Uang Laundry = 2 orang x 2
- Bantuan Uang Taksi Lokal = 2 orang x 2

b) Peserta Kantor Cabang :


- Uang Bantuan Makan = 15 orang x 2

6 Test Sistem Penerangan


Diikuti oleh 2 ( Dua ) orang dari Kantor Pusat dan 15 ( Lima Belas ) orang Kantor Cabang selama

ANALISA FAT - ELEKTRIKAL


Hal : 29 of 41
460217693.xlsx
VI.1.8 KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( F.A.T )
( 2 orang dari Airport Equiment Readiness Group - Kantor Pusat dan 15 orang dari Kantor Cabang )
a) Peserta Kantor Pusat :
- Tiket = 2 orang x 1
- Hotel / Penginapan = 2 orang x 2
- Uang Saku = 2 orang x 2
- Uang Bantuan Makan = 2 orang x 2
- Bantuan Uang Laundry = 2 orang x 2
- Bantuan Uang Taksi Lokal = 2 orang x 2

b) Peserta Kantor Cabang :


- Uang Bantuan Makan = 15 orang x 2

Jumlah - Site Acceptance Test dan Commissioning Sist

TOTAL KEGIATAN ACCEPTANCE TEST, COMMISSIONING SERTA TRAINING ( FAT


ELEKTRIKAL

ANALISA FAT - ELEKTRIKAL


Hal : 30 of 41
460217693.xlsx
E TEST, COMMISSIONING SERTA TRAINING ( F.A.T )

ELEKTRIKAL

BAHAN AREA CHECK-IN DI TERMINAL 3 BANDARA SOEKARNO - HATTA

pekerjaan FAT - elektrikal

A TRAINING ( F.A.T ) - PEKERJAAN ELEKTRIKAL

Dalam Negeri )
ntor Pusat selama 3 ( tiga ) hari di Pabrik Pembuat Dalam Negeri .

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 7,800,000.00
hari x Rp 225,000.00 = Rp 1,350,000.00
hari x Rp 150,000.00 = Rp 900,000.00
hari x Rp 125,000.00 = Rp 750,000.00
Lot x Rp 400,000.00 = Rp 800,000.00
Jumlah - I = Rp 26,267,180.00

hari x Rp 150,000.00 = Rp 900,000.00


Jumlah - II = Rp 900,000.00

sformator Daya Listrik ( Dalam Negeri ) = Rp 27,167,180

ntor Pusat selama 3 ( tiga ) hari di Pabrik Pembuat Dalam Negeri .

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 7,800,000.00
hari x Rp 225,000.00 = Rp 1,350,000.00
hari x Rp 150,000.00 = Rp 900,000.00
hari x Rp 125,000.00 = Rp 750,000.00
Lot x Rp 400,000.00 = Rp 800,000.00
Jumlah - I = Rp 26,267,180.00

ANALISA FAT - ELEKTRIKAL


Hal : 31 of 41
460217693.xlsx
pekerjaan FAT - elektrikal

A TRAINING ( F.A.T ) - PEKERJAAN ELEKTRIKAL


hari x Rp 150,000.00 = Rp 900,000.00
Jumlah - II = Rp 900,000.00

eptance Test - LVMDP ( Dalam Negeri ) = Rp 27,167,180

( Dalam Negeri )
ntor Pusat selama 3 ( tiga ) hari di Pabrik Pembuat Dalam Negeri .

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 7,800,000.00
hari x Rp 225,000.00 = Rp 1,350,000.00
hari x Rp 150,000.00 = Rp 900,000.00
hari x Rp 125,000.00 = Rp 750,000.00
Lot x Rp 400,000.00 = Rp 800,000.00
Jumlah - I = Rp 26,267,180.00

hari x Rp 150,000.00 = Rp 900,000.00


Jumlah - II = Rp 900,000.00

l Tegangan Menengah ( Dalam Negeri ) = Rp 27,167,180

ANALISA FAT - ELEKTRIKAL


Hal : 32 of 41
460217693.xlsx
pekerjaan FAT - elektrikal

A TRAINING ( F.A.T ) - PEKERJAAN ELEKTRIKAL

ntor Pusat selama 3 ( tiga ) hari di Pabrik Pembuat Dalam Negeri .

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 7,800,000.00
hari x Rp 225,000.00 = Rp 1,350,000.00
hari x Rp 150,000.00 = Rp 900,000.00
hari x Rp 125,000.00 = Rp 750,000.00
Lot x Rp 400,000.00 = Rp 800,000.00
Jumlah - I = Rp 26,267,180.00

hari x Rp 150,000.00 = Rp 900,000.00


Jumlah - II = Rp 900,000.00

ceptance Test - Kabel ( Dalam Negeri ) = Rp 27,167,180

ntor Pusat selama 3 ( tiga ) hari di Pabrik Pembuat Dalam Negeri .

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 7,800,000.00
hari x Rp 225,000.00 = Rp 1,350,000.00
hari x Rp 150,000.00 = Rp 900,000.00
hari x Rp 125,000.00 = Rp 750,000.00
Lot x Rp 400,000.00 = Rp 800,000.00
Jumlah - I = Rp 26,267,180.00

hari x Rp 150,000.00 = Rp 900,000.00


Jumlah - II = Rp 900,000.00

tance Test - BUSDUCT ( Dalam Negeri ) = Rp 27,167,180

Luar Negeri )
antor Pusat selama 5 ( Lima ) hari - ( termasuk perjalanan 2 hari ) di Pabrik

ANALISA FAT - ELEKTRIKAL


Hal : 33 of 41
460217693.xlsx
pekerjaan FAT - elektrikal

A TRAINING ( F.A.T ) - PEKERJAAN ELEKTRIKAL

ls x Rp 2,403,800 = Rp 4,807,600.00
tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00
tiket PP x Rp 34,542,530.00 = Rp 69,085,060.00
hari x $ 150.00 = Rp 12,150,000.00
hari x $ 100.00 = Rp 13,500,000.00
hari x $ 50.00 = Rp 6,750,000
hari x $ 25.00 = Rp 2,025,000
Jumlah - I = Rp 122,984,840.00

ls x Rp 2,403,800 = Rp 2,403,800.00
tiket PP x Rp 34,542,530.00 = Rp 34,542,530.00
hari x Rp 150.00 = Rp 12,150,000.00
hari x $ 100.00 = Rp 13,500,000.00
hari x $ 50.00 = Rp 3,375,000.00
hari x $ 25.00 = Rp 1,012,500.00
Jumlah - II = Rp 66,983,830.00

nset di Pabrik pembuat ( Luar Negeri ) = Rp 189,968,670

ANALISA FAT - ELEKTRIKAL


Hal : 34 of 41
460217693.xlsx
pekerjaan FAT - elektrikal

A TRAINING ( F.A.T ) - PEKERJAAN ELEKTRIKAL

ermasuk perjalanan 2 hari ) di Pabrik Pembuat ( Luar Negeri )

ls x Rp 2,403,800 = Rp -
tiket PP x Rp 7,333,590.00 = Rp -
tiket PP x Rp 34,542,530.00 = Rp -
hari x $ 150.00 = Rp -
hari x $ 100.00 = Rp -
hari x $ 50.00 = Rp -
hari x $ 25.00 = Rp -
Jumlah - 1 = Rp -

nset di Pabrik Pembuat ( Luar Negeri ) = Rp -

r Negeri )
antor Pusat selama 5 ( Lima ) hari - ( termasuk perjalanan 2 hari ) di Pabrik

ls x Rp 2,403,800 = Rp 2,403,800.00
tiket PP x Rp 7,333,590.00 = Rp 7,333,590.00
tiket PP x Rp 34,542,530.00 = Rp 34,542,530.00
hari x $ 150.00 = Rp 6,075,000.00
hari x $ 100.00 = Rp 6,750,000.00
hari x $ 50.00 = Rp 3,375,000
hari x $ 25.00 = Rp 1,012,500
Jumlah - I = Rp 61,492,420.00

ls x Rp 2,403,800 = Rp 2,403,800.00
tiket PP x Rp 34,542,530.00 = Rp 34,542,530.00
hari x Rp 150.00 = Rp 6,075,000.00
hari x $ 100.00 = Rp 6,750,000.00

ANALISA FAT - ELEKTRIKAL


Hal : 35 of 41
460217693.xlsx
pekerjaan FAT - elektrikal

A TRAINING ( F.A.T ) - PEKERJAAN ELEKTRIKAL


hari x $ 50.00 = Rp 3,375,000.00
hari x $ 25.00 = Rp 1,012,500.00
Jumlah - II = Rp 54,158,830.00

UPS di Pabrik pembuat ( Luar Negeri ) = Rp 115,651,250

ermasuk perjalanan 2 hari ) di Pabrik Pembuat ( Luar Negeri )

ls x Rp 2,403,800 = Rp -
tiket PP x Rp 7,333,590.00 = Rp -
tiket PP x Rp 34,542,530.00 = Rp -
hari x $ 150.00 = Rp -
hari x $ 100.00 = Rp -
hari x $ 50.00 = Rp -
hari x $ 25.00 = Rp -
Jumlah - 1 = Rp -

UPS di Pabrik Pembuat ( Luar Negeri ) = Rp -

ANALISA FAT - ELEKTRIKAL


Hal : 36 of 41
460217693.xlsx
pekerjaan FAT - elektrikal

A TRAINING ( F.A.T ) - PEKERJAAN ELEKTRIKAL

ang Kantor Cabang selama 2 ( Dua ) hari di Bandara Juanda - Manado


ang dari Kantor Cabang )

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 5,200,000.00
hari x Rp 225,000.00 = Rp 900,000.00
hari x Rp 150,000.00 = Rp 600,000.00
hari x Rp 125,000.00 = Rp 500,000.00
Hari x Rp 400,000.00 = Rp 1,600,000.00
Jumlah - I = Rp 23,467,180.00

hari x Rp 150,000.00 = Rp 4,500,000.00


Jumlah - II = Rp 4,500,000.00

sub - Transformator Daya Listrik = Rp 27,967,180.00

ang Kantor Cabang selama 2 ( Dua ) hari di Bandara Juanda - Manado


ang dari Kantor Cabang )

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 5,200,000.00
hari x Rp 225,000.00 = Rp 900,000.00
hari x Rp 150,000.00 = Rp 600,000.00
hari x Rp 125,000.00 = Rp 500,000.00
Hari x Rp 400,000.00 = Rp 1,600,000.00
Jumlah - I = Rp 23,467,180.00

hari x Rp 150,000.00 = Rp 4,500,000.00


Jumlah - II = Rp 4,500,000.00

sub - LVMDP = Rp 27,967,180.00

ANALISA FAT - ELEKTRIKAL


Hal : 37 of 41
460217693.xlsx
pekerjaan FAT - elektrikal

A TRAINING ( F.A.T ) - PEKERJAAN ELEKTRIKAL

ang Kantor Cabang selama 2 ( Dua ) hari di Bandara Juanda - Manado


ang dari Kantor Cabang )

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 5,200,000.00
hari x Rp 225,000.00 = Rp 900,000.00
hari x Rp 150,000.00 = Rp 600,000.00
hari x Rp 125,000.00 = Rp 500,000.00
Hari x Rp 400,000.00 = Rp 1,600,000.00
Jumlah - I = Rp 23,467,180.00

hari x Rp 150,000.00 = Rp 4,500,000.00


Jumlah - II = Rp 4,500,000.00

sub - Panel Tegangan Menengah = Rp 27,967,180.00

ANALISA FAT - ELEKTRIKAL


Hal : 38 of 41
460217693.xlsx
pekerjaan FAT - elektrikal

A TRAINING ( F.A.T ) - PEKERJAAN ELEKTRIKAL

ang Kantor Cabang selama 2 ( Dua ) hari di Bandara Juanda - Manado


ang dari Kantor Cabang )

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 5,200,000.00
hari x Rp 225,000.00 = Rp 900,000.00
hari x Rp 150,000.00 = Rp 600,000.00
hari x Rp 125,000.00 = Rp 500,000.00
Hari x Rp 400,000.00 = Rp 1,600,000.00
Jumlah - I = Rp 23,467,180.00

hari x Rp 150,000.00 = Rp 4,500,000.00


Jumlah - II = Rp 4,500,000.00

sub - Genset = Rp 27,967,180.00

ang Kantor Cabang selama 2 ( Dua ) hari di Bandara Juanda - Manado


ang dari Kantor Cabang )

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 5,200,000.00
hari x Rp 225,000.00 = Rp 900,000.00
hari x Rp 150,000.00 = Rp 600,000.00
hari x Rp 125,000.00 = Rp 500,000.00
Hari x Rp 400,000.00 = Rp 1,600,000.00
Jumlah - I = Rp 23,467,180.00

hari x Rp 150,000.00 = Rp 4,500,000.00


Jumlah - II = Rp 4,500,000.00

sub - UPS = Rp 27,967,180.00

ang Kantor Cabang selama 2 ( Dua ) hari di Bandara Juanda - Manado

ANALISA FAT - ELEKTRIKAL


Hal : 39 of 41
460217693.xlsx
pekerjaan FAT - elektrikal

A TRAINING ( F.A.T ) - PEKERJAAN ELEKTRIKAL


ang dari Kantor Cabang )

tiket PP x Rp 7,333,590.00 = Rp 14,667,180.00


hari x Rp 1,300,000.00 = Rp 5,200,000.00
hari x Rp 225,000.00 = Rp 900,000.00
hari x Rp 150,000.00 = Rp 600,000.00
hari x Rp 125,000.00 = Rp 500,000.00
Hari x Rp 400,000.00 = Rp 1,600,000.00
Jumlah - I = Rp 23,467,180.00

hari x Rp 150,000.00 = Rp 4,500,000.00


Jumlah - II = Rp 4,500,000.00

sub - Test Sistem Penerangan = Rp 27,967,180.00

an Commissioning Sistem Terpasang = Rp 167,803,080

RTA TRAINING ( FAT ) PEKERJAAN = Rp 609,258,900.00

ANALISA FAT - ELEKTRIKAL


Hal : 40 of 41
460217693.xlsx
ANALISA HARGA SATUAN (AHS) GALIAN & URUGAN

No. Jenis Koef Sat Harga (Rp) Jumlah (Rp) Total (Rp)

Analisa harga Galian untuk pemasangan kabel listrik tegangan menengah


sedalam 200 cm dibawah permukaan tanah per meter.

A Bahan -
- Galian untuk kabel TM 1.000 m³ - -

B Alat Bantu 6,250


- Cangkul 0.063 hari 100,000 6,250

C Upah - 113,333
- Mandor 0.025 oh 177,300 4,433
- Kepala Tukang / Pelaksana 0.000 oh 157,300 -
- Tukang 0.750 oh 145,200 108,900
- Pembantu Tukang 0.000 oh 121,000 -

Jumlah 119,583
Jasa Pemborong 0.000 -
Harga Satuan Pekerjaan (HSP) 119,500

Analisa harga Urugan untuk pemasangan kabel listrik tegangan menengah


sedalam 200 cm dibawah permukaan tanah per meter.

A Bahan 26,000
- Pasir Urug 0.100 m³ 260,000 26,000

B Alat Bantu 6,250


- Cangkul 0.063 hari 100,000 6,250

C Upah - 45,333
- Mandor 0.010 oh 177,300 1,773
- Kepala Tukang / Pelaksana 0.000 oh 157,300 -
- Tukang 0.300 oh 145,200 43,560
- Pembantu Tukang 0.000 oh 121,000 -

Jumlah 77,583
Jasa Pemborong 0.000 -
Harga Satuan Pekerjaan (HSP) 77,500

Total Pekerjaan Galian dan Urugan 197,000

Anda mungkin juga menyukai