Anda di halaman 1dari 2

PROGRES PEKERJAAN

PEMBANGUNAN DAN REHABILITASI RUMAH SAKIT PKU MUHAMMADIYAH


BOBOTSARI - PURBALINGGA

BOBOT
BOBOT NILAI PRESTASI NILAI PELAKSANAAN
No. PEKERJAAN PEKERJAAN ( Rp. )
(%) ( Rp. )
(%)
1 2 3 4 5 6

A. PEKERJAAN STRUKTUR
1 PEKERJAAN PERSIAPAN 0.67 61,236,050.00 0.67 61,236,050.00
2 PEKERJAAN TANAH 0.61 56,224,100.00 0.61 56,224,100.00
3 PEKERJAAN BETON 20.88 1,910,883,130.00 20.88 1,910,883,130.00
4 PEKERJAAN BETON DENGAN STEEL DECK 120 MM 0.58 52,751,300.00 0.58 52,751,300.00
5 PEKERJAAN ATAP DROP OFF 0.70 64,000,000.00 0.60 54,906,906.92

Jml. Biaya Sub Pekerjaan Struktur 23.44 2,145,094,580.00 22.74 2,136,001,486.92

B. PEKERJAAN ARSITEKTURE
1 LANTAI 1 7.83 716,954,582.88 7.83 716,954,582.88
2 LANTAI 2 5.91 541,153,039.50 5.91 541,153,039.50
3 LANTAI ATAP 0.32 29,396,174.60 0.32 29,396,174.60

Jml. Biaya Sub Pekerjaan Arsitekture 14.07 1,287,503,796.98 14.07 1,287,503,796.98

C. MEKANIKAL-ELEKTRIKAL-PLUMBING
1 MEKANIKAL ELEKTRIKAL LANTAI 1 16.40 1,500,852,170.15 15.90 1,455,033,033.26
2 MEKANIKAL ELEKTRIKAL LANTAI 2 10.79 987,445,201.44 10.20 933,417,417.56
3 MEKANIKAL ELEKTRIKAL LANTAI ATAP 0.87 79,737,483.75 0.87 79,615,015.03
4 PENYALUR PETIR 0.22 20,098,750.00 0.22 20,132,532.54
5 ELEVATOR 3.17 290,500,000.00 -
6 CODE RED & CODE BLUE 0.36 32,599,941.75 0.36 32,944,144.15
7 SISTEM ANTRIAN 0.59 53,998,800.00 -
8 INSTALASI NURSE CALL 1.91 174,806,656.00 1.91 174,786,987.01
9 TEST SISTEM ME 0.11 10,500,000.00 0.11 10,066,266.27
10 MEP INFRASTRUKTUR 26.56 2,568,013,772.50 20.25 1,957,917,127.00

Jml. Biaya Sub Pekerjaan Mekanikal Elektrikal Plumbing 60.99 5,718,552,775.59 49.82 4,663,912,522.82

JUMLAH 100.00 9,151,151,152.57 86.63 8,087,417,806.71


REALISASI PELAKSANAAN

Bobotsari, 20 JULI 2019


SITE MANAGER

.............................
PROYEK :PKU MUHAMMADIYAH PURBALINGGA
BOBOTSARI, PURBALINGGA TIME SCHEDULLE
NOVEMBER DESEMBER JANUARI FEBRUARI MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER
NO JENIS PEKERJAAN BOBOT %
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1

A PEKERJAAN STRUKTUR

1PEKERJAAN PERSIAPAN 0.67 0.17 0.17 0.17 0.17

2PEKERJAAN TANAH 0.61 0.15 0.15 0.15 0.15

3PEKERJAAN BETON 20.88 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58

4PEKERJAAN BETON DENGAN STEEL DECK 120 MM 0.58 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06

5PEKERJAAN ATAP DROP OFF 0.70

B PEKERJAAN ARSITEKTURE

1PEKERJAAN ARSITEKTURE LANTAI GROUND 7.83 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65

2PEKERJAAN ARSITEKTURE LANTAI 1 5.91 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49

3PEKERJAAN ARSITEKTURE LANTAI 2 0.32 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04

C PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING

1MEKANIKAL ELEKTRIKAL BASEMENT 16.40 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03 1.03

2MEKANIKAL ELEKTRIKAL LANTAI 1 10.79 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90

3MEKANIKAL ELEKTRIKAL LANTAI 2 0.87 0.22

5PENYALUR PETIR 0.22

6ELEVATOR 3.17

7CODE RED & CODE BLUE 0.36

8SISTEM ANTRIAN 0.59

9INSTALASI NURSE CALL 1.91

10TEST SISTEM ME 0.11

11MEP INFRASTRUKTUR 28.06 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44 0.44

PROGRES TOTAL 100.00 0.17 0.17 0.17 0.17 0.15 0.15 0.15 0.15 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 1.23 1.23 1.23 1.23 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.07 1.07 1.07 1.07 2.04 2.04 2.04 2.04 2.08 2.08 2.08 2.08 2.98 2.98 2.98 2.98 2.43 2.43 2.43 2.43 1.40 1.40 1.40 1.40 0.72

PROGRES RENCANA 0.00 0.17 0.33 0.50 0.67 0.82 0.98 1.13 1.28 1.86 2.44 3.02 3.60 4.18 4.76 5.34 5.92 7.16 8.39 9.62 10.86 12.58 14.31 16.03 17.76 19.48 21.21 22.94 24.66 25.73 26.81 27.88 28.95 31.00 33.04 35.08 37.13 39.21 41.29 43.38 45.46 48.44 51.43 54.41 57.39 59.82 62.25 64.67 67.10 68.50 69.90 71.30 72.71 73.43

PROGRES REALISASI 0.00 0.15 0.30 0.40 0.62 0.75 0.95 1.08 1.18 1.63 2.20 2.87 3.38 3.98 4.46 4.87 5.34 6.43 7.64 8.39 9.62 10.86 12.58 14.31 16.03 19.02 22.21 25.89 28.54 32.08 35.78 37.36 39.09 41.04 43.12 45.34 46.87 48.89 50.39 51.89 53.39 54.89 56.39 57.89 59.39 61.03 63.34 65.67 68.50 69.90 71.30 72.71 73.43 74.08

PROGRES DEVIASI 0.00 -0.02 -0.03 -0.10 -0.05 -0.07 -0.03 -0.05 -0.10 -0.23 -0.24 -0.15 -0.22 -0.20 -0.30 -0.47 -0.58 -0.73 -0.75 -1.23 -1.23 -1.73 -1.73 -1.73 -1.73 -0.46 1.00 2.95 3.88 6.35 8.97 9.48 10.14 10.04 10.08 10.26 9.74 9.68 9.10 8.51 7.93 6.45 4.96 3.48 2.00 1.21 1.09 1.00 1.40 1.40 1.40 1.40 0.72 0.66

Anda mungkin juga menyukai