NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH

I CLUSTER RUELLIA 0
INFRASTRUKTUR PERKERASAN JALAN
1 Cut badan jalan 47.25 m3 25,000 1,181,250
2 Geogrid & geotekstile ex Tensar 135.00 m2 54,500 7,357,500
3 Lapisan Makadam 30 cm padat alat 135.00 m2 94,500 12,757,500
4 Lapisan Basecourse 5 cm padat alat 135.00 m2 23,750 3,206,250
24,502,500
PEKERJAAN HOTMIX CLUSTER
1 Prime Coat 135.00 m2 10,000 1,350,000
2 Laston Lapis aus (AC WC) tebal 4 cm padat terpasang 135.00 m2 110,000 14,850,000
16,200,000
PEKERJAAN LAIN-LAIN
1 Bongkar pasang kanstin 270.00 m' 114,500 30,915,000
2 Cor tutup saluran K-175 tul.Wiremesh M-6 17.28 m3 2,600,000 44,928,000
75,843,000
II CLUSTER IRIS
INFRASTRUKTUR PERKERASAN JALAN
1 Cut badan jalan 71.35 m3 25,000 1,783,779
2 Geogrid & geotekstile ex Tensar 203.86 m2 54,500 11,110,392
3 Lapisan Makadam 30 cm padat alat 203.86 m2 94,500 19,264,808
4 Lapisan Basecourse 5 cm padat alat 203.86 m2 23,750 4,841,685
37,000,663
PEKERJAAN HOTMIX CLUSTER
1 Prime Coat 203.86 m2 10,000 2,038,604
2 Laston Lapis aus (AC WC) tebal 4 cm padat terpasang 203.86 m2 110,000 22,424,644
24,463,248
III CLUSTER SALVIA
INFRASTRUKTUR PERKERASAN JALAN
1 Cut badan jalan 87.10 m3 25,000 2,177,438
2 Geogrid & geotekstile ex Tensar 248.85 m2 54,500 13,562,325
3 Lapisan Makadam 30 cm padat alat 248.85 m2 94,500 23,516,325
4 Lapisan Basecourse 5 cm padat alat 248.85 m2 23,750 5,910,188
45,166,275
PEKERJAAN HOTMIX CLUSTER
1 Prime Coat 248.85 m2 10,000 2,488,500
2 Laston Lapis aus (AC WC) tebal 4 cm padat terpasang 248.85 m2 110,000 27,373,500
29,862,000
PEKERJAAN LAIN-LAIN
1 Bongkar pasang kanstin 497.70 m' 114,500 56,986,650
2 Cor tutup saluran K-175 tul.Wiremesh M-6 31.85 m3 2,600,000 82,817,280
139,803,930
Total Rp 392,841,616

Cibitung, 4 Februari 2020


Dihitung oleh,

,,,,,,,,,,,,,,,,,,,,,,,,
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN

1 Pemasangan pondasi tapak 7.00 titik 1,450,000


2 Kolom K4 K 225 uk. 15x20 (tul. 4 Ø 10 ; sk. Ø 6 - 150) 0.74 m3 3,700,000
3 Perapihan dingding (Acian + Plesteran) 2.40 m2 90,000
4 Ring Balk 15 x 15 panjang 3 m 0.07 m3 3,700,000
5 Bongkar pasang keramik Dapur K. Tidur + wirem 22.70 m2 430,000
6 Bongkar pasang kramik Kamar Mandi 1.83 m2 430,000
7 Perbaikan Talang beton dengan sika coat 3.60 m2 80,000
8 Bongkar Pasang plafond gypsum ( Incld List) 25.50 m2 170,000
9 Pengecatan Plafond 25.50 m2 35,000
10 Pengecatan Interior 124.88 m2 35,000
Plesteran dan acian
11 Perapihan,Pembersihan dan Buang puing 1.00 ls 1,200,000
Total
JUMLAH

10,150,000
2,719,500
216,000
249,750
9,761,000
786,900
288,000
4,335,000
892,500
4,370,800

1,200,000
Rp 34,969,450
PROSES DAN EVALUASI TENDER

PROYEK : METLAND CIBITUNG

HARGA PENAWARAN (Rp.)


NO KONTRAKTOR PESERTA JENIS PEKERJAAN UNIT HARGA AKHIR KETERANGAN
AWAL SETELAH KLARIFIKASI NEGOSIASI

1 SLAMET 33,389,050 33,389,050 30,000,000 30,000,000 Pelaksana


PERBAIKAN RUMAH BLOK N14.NO 15 AREA
TAHAP 1
1
2 PT. FAJARPUTERA DINASTI 392,841,616 392,841,616 392,841,616 392,841,616

Catatan :
- Harga total / akhir sudah termasuk jasa konstruksi dan PPh yang berlaku dan belum termasuk PPn 10%
- Diusulkan Sebagai Pemenang Tender : SLAMET
- Dengan Nilai Kontrak adalah : Rp30,000,000
- Waktu Pelaksanaan : 30 hari
- Sistem Pembayaran
1. Progres 100% dibayar 95%
2. Retensi 5% (100 hari)

Cibitung, 4 Februari 2020


Note :
QCC mengikuti proses tender dan menghadiri final negosiasi Menyetujui, Mengetahui, Disusun oleh,
QCC tidak mengikuti proses tender dan menghadiri final negosiasi
QCC mengikuti proses tender dan tidak menghadiri final negosiasi
QCC tidak mengikuti proses tender dan tidak menghadiri final negosiasi

Kontraktor telah diundang proses tender Nitik Hening MR Ingewati S Ikwandani Kukilo Tranggono Ian Orri Deny Yudanto Cahya Ardian
Kontraktor masuk daftar rekanan dengan nilai pekerjaan < 10 M Finance Manager Technical Manager Quantity Surveyor
Director Operational General Manager QCC General Manager
QCC diundang dalam proses tender Project Project Project

Anda mungkin juga menyukai