EVALUASI

RENCANA ANGGARAN BIAYA

PROYEK : Perluasan Area Wudhu


LOKASI : Area Wudhu Masjid Agung Al-Azhar
: Kebayoran Baru, Jakarta Selatan
TANGGAL : 12 FEBRUARI 2019

MANAJEMEN KONSTRU
NO. Uraian Pekerjaan SAT
VOLUME

PEKERJAAN MEKANIKAL, ELECTRIKAL & PLUMBING

I PEKERJAAN ELEKTRIKAL

LED Downlight 13 Watt incl. Armature (OUT Dia. 8" Ex. Phillips Bh 49.00
LED Spotlightt 7 Watt incl. Armature (OUTB Dia. 5" Ex. Phillips Bh 11.00
Saklar Single Ex. Clipsal type Pieno + Bh 4.00
Saklar Double Ex. Clipsal type Pieno + Bh 8.00
Stop Kontak Ex. Clipsal type Pieno + Bh 18.00

NYM 3x2,5 mm ex.


Eterna/setara + sparing
Instalasi Titik lampu Ttk 60.00
PVC/setara (high
impact) + T dus + Clamp

NYM 3x2,5 mm ex.


Eterna/setara + sparing
Instalasi Stop Kontak Ttk 30.00
PVC /setara (high
impact) + T dus + Clamp

Ex. Schneider 12 Group Unit 2.00


Box Skring Model Transparan (Tertanam) +
(Jumlah sesuai diagram
MCB ex Schneider
wiring)
Kabel Toevoer dari KWH ke Box Skring NYM 4 x 10 mm + pipa PV M1 10.00
Maksimum 2 Ohm, kabel
BC 6 mm2 ex. Eterna +
Arde Pentanahan Lot 1.00
pipa PVC Ø 3/4" Tipe
AW ex. Wavin
NYY 3x2,5 mm ex.
Instalasi Lampu Taman + LED Spotlightt 7 Eterna + sparing PVC Ttk 10.00
Watt (Tipe Tanam - Waterproof) /setara (high impact) + T
dus
a KABEL TEGANGAN RENDAH
Dari SDP Eksisting menuju Panel Utama P-U area wudlu Al Azhar m 100.00
Dari Panel Utama P-U menuju Panel Sumpit SP-1, NYY 4x6 mm2 m 18.00
Dari Panel Utama P-U menuju Panel Sewage pit SWP-1, NYY 4x6 m 20.00
Dari Panel Utama P-U menuju Panel Pompa Booster BP-1, NYFGB m 22.00
Dari Panel Utama P-U menuju Panel Pompa Booster BP-2, NYFGB m 37.00
Dari Panel Utama P-U menuju Panel STP-1, NYFGBY 3x4 mm2 m 28.00

Dari Panel Sumpit SP-1 menuju Pompa Sumpit 1, NYY 4x4 mm2 m 11.00
Dari Panel Sumpit SP-1 menuju Pompa Sumpit 2, NYY 4x4 mm2 m 11.00
Dari Panel Sewage pit SWP-1 menuju Pompa Sewage 1, NYY 4x4 m 8.00
Dari Panel Sewage pit SWP-1 menuju Pompa Sewage 2, NYY 4x4 m 8.00
Dari Panel Pompa Booster BP-1 menuju Pompa Booster 1, NYY 4x m 10.00
Dari Panel Pompa Booster BP-1 menuju Pompa Booster 2, NYY 4x m 10.00
Dari Panel Pompa Booster BP-2 menuju Pompa Booster 1, NYY 4x m 10.00
Dari Panel Pompa Booster BP-2 menuju Pompa Booster 2, NYY 4x m 10.00

b PANEL - PANEL
Termasuk suport serta material pendukungnya.
- Panel Utama P-U Unit 1.00
- Panel Sumpit SP-1 Unit 1.00
- Panel Sewage pit SWP-1 Unit 1.00
- Panel Pompa Booster BP-1 Unit 1.00
- Panel Pompa Booster BP-2 Unit 1.00
- Panel P-STP.1 Unit 1.00
- KWH Meter 3 phase Unit 1.00

c KABEL TRAY (Elektrikal)


Termasuk suport, hanger serta material pendukungnya.
W = 200, H = 100 m 14.00
Material bantu + Accessories ls 1.00

d INSTALASI LAMPU PENERANGAN DAN STOP KONTAK

1. DownLight Ceiling mounted 2x15W tipe 30517 bh 16.00


2. Lampu LED T5 8W warm white bh 26.00
3. Lampu LED T8 16W warm white bh 38.00
4. Lampu Striplight waterproof 4,8W/meter warm white m 55.00
5. Lampu LED Value Stick 75 10W bh 4.00

7. Saklar Tunggal bh 4.00


8. Saklar Ganda bh 7.00

9. Stop Kontak dinding 1 phase 13 A, 200 W bh 11.00


10. Instalasi penerangan, kabel NYM 3 x 2,5 mm2 ttk 85.00
+ pipa hight impact conduit ø20 mm2
11. Instalasi stop kontak, kabel NYM 3 x 2,5 mm2 ttk 11.00
+ pipa hight impact conduit ø20 mm2
SUB TOTAL PEKERJAAN ELEKTRIKAL

II PEKERJAAN TATA UDARA

Peralatan Fan
Pengadaan dan pemasangan unit Fan lengkap terpasang dengan material pendukung
lainnya
Fan buangan udara + instalasi Ex. Panasonic Unit

1. EF-1 & EF-2 Unit 2.00


Type : Industrial fan
Kapasitas : 350 CFM
Power : 75W / 220 V / 1 Ph / 50 Hz

2. EF-3 & EF-4 Unit 2.00


Type : Industrial fan
Kapasitas : 350 CFM
Power : 75W / 220 V / 1 Ph / 50 Hz

3. FF-1 & FF-2 Unit 2.00


Type : Fan gantung
Kapasitas : 750 CFM
Power : 125W / 220 V / 1 Ph / 50 Hz

4. FF-3 & FF-4 Unit 2.00


Type : Fan gantung
Kapasitas : 750 CFM
Power : 125W / 220 V / 1 Ph / 50 Hz

5. Pengkabelan listrik ls 1.00


SUB TOTAL PEKERJAAN TATA UDARA

III PEKERJAAN PLUMBING

A Peralatan Utama
Jet Pump ex. Shimizu PC-503 BIT P Bh
Pendorong Pompa Air Booster ex. Shimizu ZPS159140 Bh
1. Pompa Sumur bor unit 1.00
Model : Centrifugal End Suction
Jumlah : 1 unit
Kapasitas : 150 lpm
Head : 40 m
Power : 600 kW / 220 V / 3 Ph / 50 Hz

2. Pompa Booster BP-1.1, BP-1.2 unit 2.00


Model : Centrifugal End Suction
Jumlah : 2 unit
Kapasitas : 250 lpm
Head : 25 m
Power : 2,2 kW / 220 V / 3 Ph / 50 Hz
Operasi : Automatic Parallel Alternate
Lengkap dengan komponen :
- Pressure Tank
- Control Panel
- Gate Valve
- Check Valve
- Header Pipe
- Accessories

3. Pompa Booster BP-2.1, BP-2.2 unit 2.00


Model : Centrifugal End Suction
Jumlah : 2 unit
Kapasitas : 150 lpm
Head : 25 m
Power : 1,5 kW / 220 V / 3 Ph / 50 Hz
Operasi : Automatic Parallel Alternate
Lengkap dengan komponen :
- Pressure Tank
- Control Panel
- Gate Valve
- Check Valve
- Header Pipe
- Accessories

4. Pompa Sumpit SP-1 unit 2.00


Model : Submersible
Jumlah : 2 unit
Kapasitas : 200 lpm
Head : 25 m
Power : 2,2 kW / 220 V / 3 Ph / 50 Hz
Operasi : Automatic Parallel Alternate
Lengkap dengan komponen :
- QDC
- Control Panel
- Accessories
5. Pompa Sewage pit SWP-1 unit 2.00
Model : Submersible non clog
Jumlah : 2 unit
Kapasitas : 150 lpm
Head : 25 m
Power : 1,5 kW / 220 V / 3 Ph / 50 Hz
Operasi : Automatic Parallel Alternate
Lengkap dengan komponen :
- QDC
- Control Panel
- Accessories

6. Sand Filter set 1.00


Pengadaan dan Pemasangan & Accessories
Kapasitas : 12 m3/jam

7. STP + Pompa Submersible set 1.00


Pengadaan dan Pemasangan & Accessories
Jenis : jenis tabung Fiber menggunakan sistem aerob anaeob bio media
Kapasitas : 4.000 liter/hari

8. GWT-1 (ground water tank) set 1.00


Jenis : concrete
Kapasitas : 25 m3

9. GWT-2 (ground water tank) set 1.00


Jenis : concrete
Kapasitas : 25 m3

10. Sumpit set 1.00


Jenis : concrete
dimensi : 2mx1mx1,5m

10. Sewage pit set 1.00


Jenis : concrete
dimensi : 2mx1mx1,5m

B Pekerjaan Instalasi Air Bersih

Pengadaan dan pemasangan Instalasi Air Bersih termasuk material bantu sesuai
gambar perencanaan dan spesifikasi teknis dan Accesories pendukungnya.

Ø 20 mm Ex. Westpex
Instalasi Air Bersih (Blue Water Expose M1
Pipe)
Ø 16 mm Ex. Westpex
Instalasi Air Bersih (Blue Water Expose M1
Pipe)

1. Pipa Air Bersih PPR 10


- Pipa diameter 65 m 41.80
- Pipa diameter 50 m 154.00
- Pipa diameter 40 m 35.90
- Pipa diameter 32 m 242.30
- Pipa diameter 25 m 80.50
- Pipa diameter 20 m 87.00
- Pipa diameter 15 m 59.40
2. Gate Valve
- dia.65 bh 2.00
- dia.50 bh 6.00
- dia 40 bh 11.00
- dia.32 bh 21.00
- dia 25 bh 2.00
3. Fitting pipa , hanger, support, dll ls 1.00

4. Sprinkler Taman bh 4.00

C Pekerjaan Instalasi Air Kotor, Air Bekas, Ventilasi

Pengadaan dan pemasangan Instalasi Air Kotor, Air Bekas, Ventilasi


termasuk material bantu sesuai gambar perencanaan dan spesifikasi teknis
dan Accesories pendukungnya.

Instalasi Air Bekas u/Floordrain PVC 4" Type AW Ex. Wavi M1


Instalasi Air Kotor dari Toilet (WC) ke Septict PVC 4" Type AW Ex. Wavi M1
Instalasi Air Hujan (Incl. Batas Pagar Ke Riol PVC 4" Type D Ex. Wavin M1
PVC 3" Type D Ex.
Instalasi Air Hujan dari Roof Drain Wavin + Penggantung M1
Pipa
Pipa dari septictank ke ril kota PVC 4" Type AW Ex. Wa M1

1. Pipa air kotor, pipa PVC class 10 kg/cm2 (AW)


- Pipa diameter 100 m 63.00
- Pipa diameter 80 m 42.00
- Pipa diameter 65 m 10.00
- Pipa diameter 50 m 4.00
2. Fitting pipa , hanger, support, dll ls 1.00
3. Pipa air bekas, pipa PVC class 10 kg/cm2 (AW)
- Pipa diameter 100 m 59.00
- Pipa diameter 80 m 90.20
- Pipa diameter 65 m 77.00
- Pipa diameter 50 m 30.80
4. Fitting pipa , hanger, support, dll ls 1.00
5. Pipa ventilasi, pipa PVC class 10 kg/cm2 (AW)
- Pipa diameter 65 m 7.00
- Pipa diameter 50 m 52.80
- Pipa diameter 40 m 12.00
- Pipa diameter 32 m 4.00
6. Fitting pipa , hanger, support, dll ls 1.00
7. Clean Out diameter 100 mm bh 6.00
8. Floor Drain diameter 50 mm ex. Toto type TX 1 C bh 87.00

SUB TOTAL PEKERJAAN PLUMBING


MANAJEMEN KONSTRUKSI

HARGA JUMLAH
SATUAN HARGA
m aerob anaeob bio media

by stucture

by stucture

by stucture

by stucture
RENCANA ANGGARAN BIAYA
PROYEK :

NO URAIAN PEKERJAAN

I PEKERJAAN ELEKTRIKAL

II PEKERJAAN TATA UDARA

III PEKERJAAN PLUMBING

TOTAL
PEMBULATAN
AN BIAYA

TOTAL (Rp)

Rp 450,000,000.00