Mrinmay Biswas
Associate Professor of Civil Engineering, and
Director, Transportation and Infrastructure
Research Center
Duke University
Durham, North Carolina
he use of precast concrete for new America in the early seventies and dur-
Tbridge construction and for the reha- ing the last decade the technology
bilitation of deteriorated bridges is eco- gained from the numerous applications
nomically and structurally amenable to of the method has grown enormously.
today's systems engineering con- Spans ranging from 150 to 800 ft (46 to
cepts. 1.2•3 Precast elements can be used 244 m) can be efficiently built using
for pedestrian, highway and railway segmental construction. When com-
bridges. They can be adapted to all bined with a cable-stay system, the eco-
types of structures having short, nomical span can extend to at least 1300
medium and long spans. 11 (396 in).
Precast products can be used for some The evolution of prestressed seg-
or most of the components of a bridge's mental bridge construction throughout
superstructure and/or substructure. the world is well documented'-' 2 This
Durability, ease and speed of construc- wide application has also motivated re-
tion together with reduced need for search and development. Results of
maintenance are all advantages in using some of the tests and a review of specific
precast concrete. design problems have recently been re-
Depending on the span length and ported.' 14
40
This report describes applications of full depth,
precast concrete panels for the rehabilitation of
deteriorated bridge decks and the construction of new
bridges. Emphasis is placed on systems of
construction and the economy derived in using precast
concrete for bridge construction.
The report presents design systems, details of joints
and joint material used for a number of highway and
railway bridges. The advantages and a few of the
difficulties involved in this construction method are
discussed including some pertinent research work.
oped.',15 The current availability of high sections are shown in Fig. 1. These sec-
strength concrete provides further in- tions are suited for short span highway
centive for modifications. In some cases, bridges because of their low cost and
these standard sections can be stretched rapid erection?s-"
to accommodate special long span ap- Solid and voided slabs can be used for
plications.' spans of 35 and 50 ft (11 and 15 m), re-
Precast I girders are used in conjunc- spectively.
tion with cast-in-place deck, stay-in- Channel or multiple stemmed sec-
place metal forms, or stay-in-place pre- tions with cast-in-place decks can be
cast concrete deck panels. Concrete used to span up to about 70 ft (21 m).
stay-in-place deck panels are a signifi- Single-stemmed sections and box
cant precast element in bridge super- beams can be used to span up to about
structures. Concrete deck panels can 120 ft (37 m). The box beams may be
also be used with steel girders or used either as adjacent units or spaced
stringers. In this capacity they are used apart.
for both new bridge construction and Bulb tees, which incorporate features
bridge deck rehabilitation. of the AASHTO-PCI I girders and
The introduction of deck panels fol- single-stemmed sections can be
lowed extensive research both in the designed to span up to about 180 ft
laboratory and in the field. The current (59 m).
AASHTO Bridge Specifications cover the The integral sections, especially the
analysis, design and fabrication of deck single and double box beam and the
panels." The results from research and double-stemmed sections are particu-
successful applications of deck panels are larly suitable for railway applications.
well documented. These sections have been used to re-
Integrally constructed girder cued deck place old timber trestles with speed and
components are another type of impor- economy.
tant precast prestressed concrete ele- Full span, stay-in-place deck forms
ment for bridge construction. Typical are another element with growing ap-
CHANNEL
SINGLE TEE
42
o y^DECK REPLACEMENT
rr
u-
—PROTECTION, REPAIR,
AND MAINTENANCE
Q
U
25%
% OF BRIDGE DECK DETERIORATION
CAST-IN- PLACE
REINFORCED CONCRETE
PRECAST CONCRETE
PANEL
Existing
Stringers
Deteriorated
Existing Deck
deck systems can be economically used level and square. The roadway is on
to replace both deck and stringers sim- both a vertical and horizontal curve. The
ultaneously. For bridges where the deck spans have superelevation and skew.
supporting structure, i.e., the stringers The old stringers may have partial
or girders, are in good condition, only length riveted cover plates. When a pre-
the deck portion may need to be re- cast system is chosen, special fabrication
placed by precast elements. and construction procedures should be
Precast elements can provide an ad- followed to ensure that the precast ele-
ditional advantage of greater durability ments achieve proper fit.
over cast-in-place concrete. Better qual- When an existing structure is com-
ity control of material in a precast plant posite, the replacement structure must
can result in higher strength concrete. also be composite. Even when an exist-
One important point to remember is that ing structure is not composite, because
precast concrete becomes increasingly of greater load carrying capacity re-
economical with repetitive elements. quirements and larger roadway width
However, certain special constraints requirements of many rehabilitation
related to the use of precast concrete projects, the replacement structures are
should be recognized. The example often required to be composite.
below illustrates such a case. Fig. 6 shows the basic load transfer
Fig. 5 shows the plan, elevation and requirements for a composite structure
cross section of a bridge which is not using precast elements. Figs. 6(a) and
44
0.
PLAN
ELEVATION
40 Ft
TRANSVERSE SECTION
6(b) show the vertical load transfer and tactical requirements related to
horizontal shear transfer, respectively, schedule and traffic interference, (2)
at the interface of the deck slab and geometric fitup problems and (3) load
stringer. Figs. 6(c) and 6(d) show the transfer, strength and serviceability re-
horizontal in-plane forces and vertical quirements. The design, of course, must
shear transfer at the interface of adjacent also meet the project's overall economic
deck slab panels. constraints.
A proper design must adequately ad- in modular construction, the per-
dress the following three criteria: (1) formance of joints is especially critical
7L O"(Typ E -6 (Typ J
Cast in Place
,--Precast
LONGITUDINAL SECTION
1/2110 Salt
W 21x
TRANSVERSE SECTION
Curved Viaduct Ramp (Fig. 9); and (2) gained in the applications prior to 1973
the Emil-Schulz Bridge (Fig. 10). These provided the knowledge base for future
were major spans, both built in Ger- developments.
many, using precast decks on steel box
girders, They were both composite.
Epoxy mortar was used as the joint ma- 1973 AND AFTER
terial along with high strength bolts as Significant advances have been made
shear connectors.34 since 1973 with the construction of
The designs used and the experience major bridges, some over 1000 ft (305 m)
48
Varies
LONGITUDINAL SECTION
4 ' l a i
ir
Beni I -. ^s
/B x 6x I 3/41` BOIL
TRANSVERSE SECTION
long. Many of the spans are composite joint. The major emphasis of this report
while some are continuous. A few is in addressing these interface details of
of the designs involved complex geom- bridges completed since 1973.
etries. The details used in a bridge design
The details of the interfaces are the depend mainly on the respective trans-
key to precast slab stringer design. Spe- portation agency and the consulting en-
cifically, there are three locations of in- gineer involved. Such details reflect
terface: (1) the bedding plane at the slab their standard practice, previous experi-
to stringer; (2) the shear connector ence and design philosophy. The fol-
pocket area; and (3) the slab-to-slab lowing information is presented in a
Box Girder
Precast Deck
65
TRANSVERSE SECTION
iIs
-. .. . .-. . III II .
DETAIL AT A
TRANSVERSE SECTION
Shear Studs
and Spirals I! rPrecost Deck opo
000
Box Section
Flange FP I
SFC'TIfN PLAN
DETAIL AT A
top of the steel stringers and at the shear and time consuming task.
pockets. Some of the distinctive features of
Fig. 11 shows the configuration of the each of the NYSTA projects are de-
panel-to-panel joints. An oblong funnel scribed below:
was needed to place flowable epoxy Amsterdam Interchange Bridge
mortar in the joint. The use of adhesive (1973)—Fig. 12 shows a view of the
tape at the bottom opening of the joint two-lane bridge consisting of four sim-
was not effective in containing the ple spans: 33, 59, 66 and 60 ft (1O 18, 20
epoxy mortar. The opening subse- and 18 m) long, respectively. This
quently had to be blocked by additional bridge was designed to carry about 2000
formwork. Existing composite deck and AADT over the mainline Thruway. The
spiral shear connectors had to be re- deteriorated deck of one-half of the 66 ft
moved which proved to he a laborious (20.1 m) span was replaced by using
Joint
Deck Slab II Epoxy Mortar
N G •,
Adhesive Tape
L_/Backed by Lumber
Fig. 11. Transverse joint between precast slabs, New York State Thruway
Authority (NYSTA).
ri
52
0°
41 -
—Oil 21O1 1101
E
7 1I }
YL
Stringer
k
E:±±fiE x A
Temporary I L4
Spring Clip
PLAN
Epoxy Mortar
Deck Slab C5x 9
4. • .. 6 <'
Fig. 13. Plan and section of welded channel shear connection (NYSTA).
in. (203 mm) x 4 x 22 ft (1.2 x 6.7 m). partment personnel without difficulty.
They were designed to cover one-half A "dry" system detail using long high
the width of the bridge, strength bolts was also used on a few
Cast-in-place concrete was used down panels on the same span. Field applica-
the centerline of the bridge which has a tion of torque for these large high
6 ft (1.8 m) wide flush median mall. Figs. strength bolts was difficult. Plan and
13 and 14 show the details of the bed- section diagrams of these bolted con-
ding area and the shear pockets. Fig. 15 nections are shown in Figs. 16 arid 17.
shows the casting of epoxy mortar in the The gap between the bottom of the pre-
shear pockets. Field welded standard cast slab and the top of the stringer re-
channel sections were used as shear quired shims. Achievement of full ten-
connectors. These were installed by de- sion in the bolts could not be fully
S.
IF
J/ IK ^ b
C Stringer
SECTION B-B
54
ascertained, Possible breakage of slabs was highly supervised by professional
because of excessive motion due to ten- and management level personnel from
sioning was also feared. For these rea- the NYSTA, the consulting engineers
sons, bolted connections were not used and the epoxy supplier. The bridge has
in subsequent NYSTA projects. performed very well over the period
NYSTA protective system of a sheet since rehabilitation. Close field inspec-
membrane overlaid with asphalt con- tion resulting in better quality control
crete was applied on the rehabilitated may be credited as an important ingre-
deck. dient for this success.
Because of the attached importance of Krum Kill Road Bridge (1977)—This
the Amsterdam Interchange Bridge re- is a 50 ft (15 m) long single span, six-lane
habilitation scheme, the construction mainline throughway bridge carrying
^a
3/4 ' l 9
H.S.B4
ringer
Tempe
Spring r LP4 N
nark Clrth
Strir sher
fired
Deck Slab —
-_I E.S.
iitr^ adtt!IP,
Epoxy Mortar
Levelling Grout
Shim Washer
Field Drilled Holes As Required
For 3/a" H.S. Bolts
(Interference—Body)
Q Stringer
SECTION B-B
Asphalt Wear ds
Waterproof Mere
56
AADT 22000 over Krum Kill Road near slightly skewed but level. There are two
Albany. Figs. 18 and 19 show the plan structurally separate spans supported on
and section details of the joints. These common abutments. Each structure car-
details are similar to the Amsterdam ries two active traffic lanes and one in-
Interchange Bridge, except that stan- active lane for future use. The latter was
dard welded shear studs were used in- used effectively to detour traffic during
stead of channel sections. construction.
The precast slab panel work including Precast panels, 7V2 in. (190 mm) thick
delivery and installation, was con- and 5 ft 2 in. (1.6 m) long, of two differ-
tracted. The balance of the work was ent widths were used. For each struc-
completed by the NYSTA. The spans are ture, 42 ft (13 in) wide panels were
ringer
PLAN
Epoxy Mortar
Deck Slob
* - - i .i:
-
f is
5w
lie K 6" Stud
Epoxy Mortar
SECTION A-A
Fig. 21, Placement of 21 It (6 m) wide panel, and longitudinal joint, Krum Kill Road
Bridge.
58
Fig. 22. Harriman Interchange Ramp Bridge, NYSTA.
placed over six stringers and 21 ft (6.5 m) ramp carrying AADT 9000. Each span is
wide panels were placed over three 75 ft (23 m) long. The roadway is on an
stringers. A 3 11 (0.91 m) wide longitudi- 800 ft (244 m) radius horizontal curve.
nal joint at the crown line was cast in The roadway is also on a vertical curve
place over continuity reinforcing bars and is superelevated. Individual spans
extending from two adjacent panels. are markedly skewed. Fig. 22 shows a
Fig. 20 shows the placement of 42 II (13 view of the bridge. The NYSTA let a
m) wide panels. Fig. 21 shows the contract on the complete rehabilitation
placement of 21 ft (6.4 m) wide panels of this bridge. The connection details of
and the longitudinal joint. this structure are similar to those shown
During construction, cracks over the in Figs. 18 and 19.
reinforcing bars were detected in the Based on available drawings of the
precast panels. The cracks were treated existing structure and an actual field
with a penetrating epoxy sealer. Dur- survey, a computer program was writ-
ability of the deck has not been affected ten to generate numerical tables of each
any further 3 7 The performance of the precast concrete slab panel and plot
bridge has been satisfactory although out their geometries for verification.
several joints have shown signs of leak- This information was incorporated in
age where construction debris was the contract drawings and the slab
found in the keyway. This problem in- panels were fabricated accordingly.
dicates the need for a thorough inspec- Full width panels, 8 in. (203 mm)
tion of all joints prior to placing epoxy thick by 4 x 54 ft (1.2 x 16.5 m) covered
mortar. about 9000 sq ft (840 m l ) of deck area.
Harriman Interchange Ramp Traffic was maintained using a detour
(1979)—This is a three-span, two-lane ramp.
Fig. 24. Placement of new precast panel deck and deteriorated condition of old deck
(Clark Summit Bridge).
60
Pennsylvania Turnpike scribed next.
Commission Quakertown Interchange Bridge
(1981)—Fig. 26 shows the two-lane di-
Clark Summit Bridge (1980)—This vided interchange overpass and Fig. 27
1627 ft (496 in) long bridge consists of (top) shows a schematic elevation of the
two parallel structures carrying two structure. This is a suspended cantilever
lanes each way.35 -40 Its peak point is system with composite deck in the sus-
about 140 ft (43 m) high. pended span and noncomposite deck in
Fig. 23 shows a view of the bridge. the cantilever span.
Fig. 24 shows placement of panels at Precast panels, 6'/a in. (165 mm) thick
one of the structures while two-way with varying haunch thickness, are 7 ft
traffic was maintained using the parallel 71/4 in. (2.3 rn) long and 17 ft 6 in. (5.3 m)
structure. The figure also shows the se- wide (see Fig. 27 (bottom) I and cover
verely deteriorated condition of the one-half the width of the structure. A
deck at the time of rehabilitation_ cast-in-place concrete median barrier
Typically, 6% in. (171 mm) thick slab was installed between two half-width
panels were 7 ft (2.1 m) long with a full precast panels. Figs. 27 (bottom) and 28
roadway width of 29 ft (8.8 m) weighing show the slab panel sizes and connec-
18,000 Ibs (8165 kg) each. tion detail, respectively.
Elastomeric strips and epoxy mortar Existing bulb angle shear connectors
grout were used for bedding over exist- were left in place as the old slab was
ing stringers. Non-shrink cement grout removed. The slab panels with shear
was placed at the transverse joints and pockets were cast with sufficient preci-
nominal longitudinal post-tensioning sion that the precast slab fitted well
was used. Fig. 25 shows manual longi- when set in place. EIastomeric strips
tudinal tensioning. The deck structure were glued to the top of the flanges to
was noncomposite. contain the epoxy mortar which pro-
Similar details were used in the re- vided uniform bedding of the precast
decking of another bridge which is de- panels.
1nfl
99-O
SCHEMATIC ELEVATI
Bridge
F.-
_____ 17'-6"
Fig. 27. Schematic elevation and panel dimensions, Quakertown Interchange Bridge.
62
Latex Concrete Grout —^
Existing Bulb Angle
7 Conduit For
Longifudino Post Tension
Latex Concrete
Overlay
Latex Concret(
1 X 1 3/8 Elastomer
Cover Plate
HOLD DOWN DETAIL
Eastbound Westbound
4-0"
64
bilitation of the east bound roadway was pretensioned and longitudinally post-
completed and opened to traffic before tensioned. To reduce the dead load,
the target date. The west hound road- lightweight aggregate concrete [115 lb/
way was completed in 1982. ft (1842 kg/m') ] withf, = 5000 psi (34.5
The precast slabs were transversely MPa) was used for the precast concrete
+ftt
ti - runve rC• U' :9
5-270 K Strands
for Pre Tension 1' 5- '-I ½ 8'-1 1/2 !=8
(!2 Total)---- I
f II
11
a Threaded
t Sncket far
Oblong Holes for Conduit for Post' Stringer (Typ) Leveling
Shear Studs Tension (t9 Total)
PLAN OF TYPICAL PRECAST
PRESTRESSED LIGHTWEIGHT CONCRETE SLAB PANEL
Waterproof Membrane
Bituminous Overlay rNor—Shrink Grout
\ J..:
0
U,
. w.
U
I-
C) I/2 3/4
0
En
ti
01
u
C)
a-
Fig. 31. Typical panel dimensions and transverse joint detail, Connecticut River Bridge.
4- Existing Stringer
'ead
O
V
U,
Fig. 32. Slab and stringer connection details, Connecticut River Bridge.
Fig. 33. Bridge No. 1 over Rondout Creek, New York State Department of Transportation
(NYSDOT).
66