Anda di halaman 1dari 6

RENCANA ANGGARAN BIAYA (RAB)

Proyek : Pos Jaga (2 Unit)


Lokasi : Site PT. EFI (Gulo)
Tanggal : 08-Jan-20

No. Uraian Satuan Volume Harga Satuan Total Harga Keterangan


MATERIAL
1 Amplas kasar  Lbr 3                        12,000                        36,000
2 Afur pvc   Bh 2                        15,000                        30,000  Kurasan bak mandi 
3 Bohlam lampu SL 12 watt  Bh 5                        75,000                     375,000
4 Cat minyak warna coklat  Ltr 5                        60,000                     300,000
5 Cat tembok biru muda  Ltr 50                        30,000                  1,500,000
6 Cat tembok biru tua  Ltr 10                        30,000                     300,000
7 Cat tembok putih  Ltr 10                        30,000                     300,000
8 Clamp kabel  Box 2                        25,000                        50,000
9 Clamp pipa conduit  Box 2                        50,000                     100,000
10 Closset jongkok  Bh 2                     300,000                     600,000
11 Daun Jendela Kaca  Set 4                     600,000                  2,400,000 Ukuran sesuai gambar
12 Elbow pvc 3"  Bh 6                        12,000                        72,000
13 Elbow pvc 4"  Bh 2                        26,000                        52,000
14 Elbow pvc 1/2"  Bh 10                          6,000                        60,000
15 Engsel kupu‐kupu 3"  Set 4                        45,000                     180,000 Engsel jendela
16 Engsel kupu‐kupu 4"  Set 3                        65,000                     195,000  Engsel pintu 
17 Fitting lampu tempel  Bh 10                        15,000                     150,000
18 Floor Drain  Bh 2                        25,000                        50,000
19 Hak Angin (jendela)  Bh 4                        17,500                        70,000
20 Isarplas  Roll 2                          6,000                        12,000
21 Isolasi unibel  Roll 2                        15,000                        30,000
22 Kabel NYM 2x1.5 mm  Roll 1                     350,000                     350,000  1 Roll @ 50 m 
23 Kaca Bovenlight  Set 8                        75,000                     600,000 Uk. Sesuai gambar
24 Kayu 10x10x400 cm Btg 20                     172,000                  3,440,000 Ketam
25 Kayu 5x10x400 cm Btg 100                        86,000                  8,600,000 Ketam
26 Kayu Papan 2x20x400 cm  Lbr 250                        68,800                17,200,000 Ketam
27 Koral Beton M3 5                     425,000                  2,125,000
28 Kran air 1/2 "  Bh 2                          1,500                          3,000
29 Kuas cat 3"  Bh 10                        15,000                     150,000
30 Kuas roll & Baki Cat  Set 2                        50,000                     100,000
31 Kunci Tanam   Set 2                        65,000                     130,000  Kunci pintu 
32 Lem Pipa pvc  Box 4                        25,000                     100,000
33 Paku kayu 10 cm  Kg 20                        20,000                     400,000
34 Paku kayu 5 cm  Kg 20                        20,000                     400,000
35 Paku kayu 7 cm  Kg 10                        20,000                     200,000
36 Paku seng   Kg 2                        25,000                        50,000
37 Paku triplek  Kg 2                        25,000                        50,000
38 Pasir Beton M3 10                     225,000                  2,250,000
39 Peralatan dll Ls 1                  5,000,000                  5,000,000
40 Pintu km/wc (pcv) Set 2                     200,000                     400,000
41 Pipa conduit Btg 8                        15,000                     120,000
42 Pipa pvc 1/2 "  Btg 6                        32,000                     192,000
43 Pipa pvc 3"  Btg 4                        45,000                     180,000
44 Pipa pvc 4"  Btg 4                        65,000                     260,000
RENCANA ANGGARAN BIAYA (RAB)
Proyek : Pos Jaga (2 Unit)
Lokasi : Site PT. EFI (Gulo)
Tanggal : 08-Jan-20

No. Uraian Satuan Volume Harga Satuan Total Harga Keterangan


45 Saklar outbow tunggal  Bh 5                        30,000                     150,000
46 Sambungan tandon ke pipa 1/2"  Set 2                        75,000                     150,000
47 Semen Portland Zak 40                        78,000                  3,120,000
48 Seng Datar Lebar 40 cm M 15                        17,000                     255,000 Bubungan seng
49 Seng Gelombang Lbr 80                        65,000                  5,200,000
50 Shockdrat dalam pvc 1/2"  Bh 2                          5,000                        10,000
51 Tandon Air 1000 liter  Bh 2                  3,500,000                  7,000,000  Pinguin  
52 Triplek 4 mm  Lbr 50                        85,000                  4,250,000
53 Thiner  Ltr 4                        50,000                     200,000                                          69,497,000 

UPAH KERJA
1 Pekerja HK 160                     100,000                16,000,000 Hari Kerja (HK)
2 Tukang HK 100                     150,000                15,000,000
3 Upah ketam Ls 1                  8,000,000                  8,000,000                                          39,000,000 

TOTAL                                                                                108,497,000

Note :
 ‐ Pos Mangga tanpa lampu (listrik)