Anda di halaman 1dari 29

BACK UP DATA PEKERJAAN DWEKKER

GALIAN L P T VOLUME
DWEKKER 1 7.5 2.5 2 37.5
DWEKKER 2 5 4.5 2.5 56.25
DWEKKER 3 9 6 2.5 135
DWEKKER 4 0 0 0 0
TOTAL 228.75
LAPORAN MINGGUAN KE I
Monday, September 30, 2019 s/d Sunday, October 06, 2019
Nama Paket : Pembangunan Saluran Buang Desa Waeputeh
Nomor Kontrak : 600/212-611.41/PSDA/BKK/IX/2019
Tanggal Kontrak : 9/27/2019
Tanggal Opname : 1-6/01/2020

KONTRAK KEMAJUAN PEKERJAAN

ORIGINAL KONTRAK MASA PELAKSANAAN


JUMLAH HARGA
No : Item Uraian Pekerjaan Sat. Harga Jumlah Bobot S/D BULAN LALU BULAN INI S/D BULAN INI
Satuan Volume Harga (%) (Rp)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)
(Rupiah) (Rp) (Rupiah)

PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36 -

1 Mobilisasi LS Rp 23,842,000.00 1.00 23,842,000.00 1.54% -


2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras/Sawit) Bh Rp 33,676.00 775.00 26,098,900.00 1.68% -
3 Patok kayu Setiap 50 m Sepanjang Saluran Bh Rp 12,758.00 174.00 2,219,892.00 0.14% -

PEMBUATAN SALURAN 1,223,750,945.43 78.93 -


1 Galian Saluran M3 Rp 17,914.90 62,292 1,115,954,950.80 71.97% -
2 Talud/Dinding Saluran Pasangan Batu (1PC:4PP) M3 Rp 998,649.00 92 91,723,913.35 5.92% -
3 Plesteran Tebal 1 cm (1PC:4PP) M2 Rp 63,523.00 253 16,072,081.28 1.04% -

PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71 -


1 Galian Tanah M3 Rp 17,914.90 285.0 5,105,746.50 0.33% -
2 Urugan Tanah Kembali M3 Rp 34,155.00 84.7 2,892,245.40 0.19% -
3 Beton K-200 untuk Lantai Dekker M3 Rp 908,709.00 16.0 14,539,344.00 0.94% -
4 Beton K-200 untuk Lantai Balok M3 Rp 908,709.00 11.9 10,795,462.92 0.70% -
5 Beton K-100 untuk Bahu Dekker M3 Rp 876,230.00 12.8 11,215,744.00 0.72% -
6 Baja Tulangan U-32 Ulir Untuk Lantai kg Rp 14,969.55 2,340.3 35,033,716.89 2.26% -
7 Baja Tulangan U-24 Polos Untuk Balok kg Rp 20,112.12 998.1 20,074,148.32 1.29% -
8 Baja Tulangan U-32 Ulir Untuk Balok kg Rp 17,697.12 1,363.4 24,128,111.83 1.56% -
9 Pasangan Batu (1PC:4PP) M3 Rp 998,649.00 125.7 125,550,152.28 8.10% -
10 Pasangan Batu Kosong M3 Rp 526,125.00 8.7 4,577,287.50 0.30% -
11 Bekisting Lantai dan Bahu Dekker M2 Rp 58,688.00 163.2 9,577,881.60 0.62% -
12 Bekisting Balok M2 Rp 83,907.00 132.0 11,075,724.00 0.71% -

1,550,477,302.67 100% -

Disetujui Oleh, Diketahui Oleh, Dibuat Oleh :


Pejabat Pelaksana Teknis Kegiatan (PPTK) Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang Dinas Pekerjaan Umum dan Penataan Ruang CV.MATTAMPA KONSULTAN
Kab. Mamuju Tengah Kab. Mamuju Tengah

SUMAILA, S.Pdi NURFADHILA MULYADI ETA, ST SAATIL AULIAH, ST


NIP. 19730304 200901 1 003 NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 1
Periode : Thursday, October 03, 2019 s/d Thursday, October 10, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 0.00% 0.31% 0.31% 4,764,800.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.00 0.00% 0.20 0.31% 0.20 0.31% 4,764,800.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 0.00 0.00% - 0.00% - 0.00% -
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 0.00 0.00% - 0.00% - 0.00% -

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 0.00% 0.00% 0.00% -


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 0.00 0.00% - 0.00% - 0.00% -
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 0.00% 0.31% 0.31% Rp 4,764,800.00

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 2
Periode : Friday, October 11, 2019 s/d Thursday, October 17, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 0.31% 0.52% 0.82% 12,753,900.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.20 0.31% 0.30 0.46% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 0.00 0.00% 25.00 0.05% 25.00 0.05% 841,900.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 0.00 0.00% - 0.00% - 0.00% -

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 0.00% 1.57% 1.57% 24,414,425.72


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 0.00 0.00% 1,362.80 1.57% 1,362.80 1.57% 24,414,425.72
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 0.31% 2.09% 2.40% Rp 37,168,325.72

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 3
Periode : Friday, October 18, 2019 s/d Friday, October 25, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 0.82% 0.07% 0.89% 13,850,960.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 25.00 0.05% 25.00 0.05% 50.00 0.11% 1,683,800.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 0.00 0.00% 20.00 0.02% 20.00 0.02% 255,160.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 1.57% 2.00% 3.58% 55,473,174.34


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 1362.80 1.57% 1,733.68 2.00% 3,096.48 3.58% 55,473,174.34
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 2.40% 2.07% 4.47% Rp 69,324,134.34

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 4
Periode : Saturday, October 26, 2019 s/d Saturday, November 02, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 0.89% 0.21% 1.11% 17,136,960.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 50.00 0.11% 90.00 0.20% 140.00 0.30% 4,714,640.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 20.00 0.02% 20.00 0.02% 40.00 0.03% 510,320.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 3.58% 4.36% 7.93% 123,018,572.77


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 3,096.48 3.58% 3,770.35 4.36% 6,866.83 7.93% 123,018,572.77
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 4.47% 4.57% 9.04% Rp 140,155,532.77

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN BULANAN KE - 1
Periode : Thursday, October 03, 2019 s/d Saturday, November 02, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 0.00% 1.11% 1.11% 17,136,960.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% - 0.00% 0.50 0.77% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% - 0.00% 140.00 0.30% 140.00 0.30% 4,714,640.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% - 0.00% 40.00 0.03% 40.00 0.03% 510,320.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 0.00% 7.93% 7.93% 123,018,572.77


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% - 0.00% 6,866.83 7.93% 6,866.83 7.93% 123,018,572.77
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% - 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% - 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% - 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% - 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% - 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% - 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% - 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% - 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% - 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% - 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% - 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% - 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% - 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% - 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 0.00% 9.04% 9.04% Rp 140,155,532.77

Disetujui Oleh, Diketahui Oleh, Dibuat Oleh,


Pejabat Pelaksana Teknis Kegiatan (PPTK) Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah Kab. Mamuju Tengah

SUMAILA, S.Pdi NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19730304 200901 1 003 NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 5
Periode : Sunday, November 03, 2019 s/d Sunday, November 10, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 1.11% 0.30% 1.41% 21,863,904.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 140.00 0.30% 129.00 0.28% 269.00 0.58% 9,058,844.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 40.00 0.03% 30.00 0.02% 70.00 0.06% 893,060.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 7.93% 7.25% 15.19% 235,444,441.38


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 6,866.83 7.93% 6,275.55 7.25% 13,142.38 15.19% 235,444,441.38
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 9.04% 7.56% 16.60% Rp 257,308,345.38

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 6
Periode : Monday, November 11, 2019 s/d Sunday, November 17, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 1.41% 0.14% 1.55% 24,012,044.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 269.00 0.58% 60.00 0.13% 329.00 0.71% 11,079,404.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 70.00 0.06% 10.00 0.01% 80.00 0.07% 1,020,640.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 15.19% 7.87% 23.06% 357,541,382.11


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 13,142.38 15.19% 6,815.39 7.87% 19,957.77 23.06% 357,541,382.11
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 16.60% 8.01% 24.61% Rp 381,553,426.11

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 7
Periode : Monday, November 18, 2019 s/d Monday, November 25, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 1.55% 0.21% 1.76% 27,298,044.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 329.00 0.71% 90.00 0.20% 419.00 0.91% 14,110,244.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 80.00 0.07% 20.00 0.02% 100.00 0.08% 1,275,800.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 23.06% 5.81% 28.87% 447,667,369.92


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 19,957.77 23.06% 5,030.78 5.81% 24,988.55 28.87% 447,667,369.92
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 24.61% 6.02% 30.63% Rp 474,965,413.92

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 8
Periode : Tuesday, November 26, 2019 s/d Monday, December 02, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 1.76% 0.25% 2.01% 31,114,700.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 419.00 0.91% 105.00 0.23% 524.00 1.14% 17,646,224.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 100.00 0.08% 22.00 0.02% 122.00 0.10% 1,556,476.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 28.87% 7.09% 35.96% 557,566,055.24


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 24,988.55 28.87% 6,134.49 7.09% 31,123.03 35.96% 557,566,055.24
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 30.63% 7.33% 37.97% Rp 588,680,755.24

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN BULANAN KE - 2
Periode : Sunday, November 03, 2019 s/d Tuesday, December 03, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 1.11% 0.90% 2.01% 31,114,700.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 140.00 0.30% 384.00 0.83% 524.00 1.14% 17,646,224.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 40.00 0.03% 82.00 0.07% 122.00 0.10% 1,556,476.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 7.93% 28.03% 35.96% 557,566,055.24


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 6,866.83 7.93% 24,256.20 28.03% 31,123.03 35.96% 557,566,055.24
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% - 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% - 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% - 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% - 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% - 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% - 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% - 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% - 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% - 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% - 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% - 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% - 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% - 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% - 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 9.04% 28.93% 37.97% Rp 588,680,755.24

Disetujui Oleh, Diketahui Oleh, Dibuat Oleh,


Pejabat Pelaksana Teknis Kegiatan (PPTK) Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah Kab. Mamuju Tengah

SUMAILA, S.Pdi NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19730304 200901 1 003 NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 9
Periode : Tuesday, December 03, 2019 s/d Monday, December 09, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 2.01% 0.17% 2.18% 33,743,500.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 524.00 1.14% 72.00 0.16% 596.00 1.29% 20,070,896.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 122.00 0.10% 16.00 0.01% 138.00 0.11% 1,760,604.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 35.96% 3.40% 39.36% 610,236,550.97


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 31,123.03 35.96% 2,940.04 3.40% 34,063.07 39.36% 610,236,550.97
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 37.97% 3.57% 41.53% Rp 643,980,050.97

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 10
Periode : Tuesday, December 10, 2019 s/d Monday, December 16, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 2.18% 0.16% 2.34% 36,237,596.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 596.00 1.29% 68.00 0.15% 664.00 1.44% 22,360,864.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 138.00 0.11% 16.00 0.01% 154.00 0.13% 1,964,732.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 39.36% 3.18% 42.53% 659,476,504.57


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 34,063.07 39.36% 2,748.55 3.18% 36,811.62 42.53% 659,476,504.57
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 41.53% 3.34% 44.87% Rp 695,714,100.57

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 11
Periode : Tuesday, December 17, 2019 s/d Tuesday, December 24, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 2.34% 0.17% 2.51% 38,864,324.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 664.00 1.44% 78.00 0.17% 742.00 1.61% 24,987,592.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 154.00 0.13% - 0.00% 154.00 0.13% 1,964,732.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 42.53% 5.58% 48.11% 745,999,201.36


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 36,811.62 42.53% 4,829.65 5.58% 41,641.27 48.11% 745,999,201.36
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.00% 0.00% -
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% - 0.00% - 0.00% -
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% - 0.00% - 0.00% -

REALISASI PROGRES 1,550,477,302.67 100% 44.87% 5.75% 50.62% Rp 784,863,525.36

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN MINGGUAN KE - 12
Periode : Wednesday, December 25, 2019 s/d Tuesday, December 31, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 2.51% 0.09% 2.59% 40,230,792.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 742.00 1.61% 33.00 0.07% 775.00 1.68% 26,098,900.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 154.00 0.13% 20.00 0.02% 174.00 0.14% 2,219,892.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 48.11% 3.96% 52.08% 807,418,801.27


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 41,641.27 48.11% 3,428.41 3.96% 45,069.68 52.08% 807,418,801.27
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% 0.00 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% 0.00 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.34% 0.34% 5,205,605.78
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% 0.00 0.00% 228.75 0.26% 228.75 0.26% 4,098,033.38
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% 0.00 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% 0.00 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% 0.00 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% 0.00 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% 0.00 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% 0.00 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% 0.00 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% 0.00 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% 0.00 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% 0.00 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% 0.00 0.00% 13.20 0.07% 13.20 0.07% 1,107,572.40

REALISASI PROGRES 1,550,477,302.67 100% 50.62% 4.05% 55.01% Rp 852,855,199.05

Diketahui Oleh, Dibuat Oleh,


Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah

NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19860531 201504 2 001 Site Engineer
LAPORAN BULANAN KE - 3
Periode : Wednesday, December 04, 2019 s/d Tuesday, December 31, 2019

Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)


No. Kontrak : 600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Tgl. Kontrak : Friday, September 27, 2019

ORIGINAL KONTRAK MASA PELAKSANAAN

NO. URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA BOBOT SD/ MINGGU LALU MINGGU INI SD MINGGU INI JUMLAH HARGA
SAT VOLUME
(Rp) (Rp) (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) (Rp)
1 2 3 4 5 6=4X5 7 8 9=8/4 X 7 10 11=10/4 X 7 12 13=12/4 X 7

I. PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36% 2.01% 0.59% 2.59% 40,230,792.00
1 Mobilisasi LS 1.0 Rp 23,824,000.00 23,824,000.00 1.54% 0.50 0.77% - 0.00% 0.50 0.77% 11,912,000.00
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) bh 775.0 Rp 33,676.00 26,098,900.00 1.68% 524.00 1.14% 251.00 0.55% 775.00 1.68% 26,098,900.00
3 Patok Kayu Setiap 50 m Sepanjang Saluran bh 174.0 Rp 12,758.00 2,219,892.00 0.14% 122.00 0.10% 52.00 0.04% 174.00 0.14% 2,219,892.00

II. PEMBUATAN SALURAN 1,223,750,945.43 78.93% 35.96% 16.11% 52.08% 807,418,801.27


1 Galian Saluran m³ 62,292.0 Rp 17,914.90 1,115,954,950.80 71.97% 31,123.03 35.96% 13,946.64 16.11% 45,069.68 52.08% 807,418,801.27
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) m³ 92.0 Rp 998,649.00 91,723,913.35 5.92% - 0.00% - 0.00% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) m³ 253.0 Rp 63,523.00 16,072,081.28 1.04% - 0.00% - 0.00% - 0.00% -

III PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71% 0.00% 0.34% 0.34% 5,205,605.78
1 Galian Tanah (Pembongkaran Badan Jalan) m³ 285.00 Rp 17,914.90 5,105,746.50 0.33% - 0.00% 228.75 0.26% 228.75 0.26% 4,098,033.38
2 Urugan Tanah Kembali ( Manual) m³ 84.68 Rp 34,155.00 2,892,245.40 0.19% - 0.00% - 0.00% - 0.00% -
3 Beton K-200 untuk Lantai Dekker m³ 16.00 Rp 908,709.00 14,539,344.00 0.94% - 0.00% - 0.00% - 0.00% -
4 Beton K-200 untuk Lantai Balok m³ 11.88 Rp 908,709.00 10,795,462.92 0.70% - 0.00% - 0.00% - 0.00% -
5 Beton K-100 untuk Bahu Dekker m³ 12.80 Rp 876,230.00 11,215,744.00 0.72% - 0.00% - 0.00% - 0.00% -
6 Baja Tulangan U32 Ulir untuk Lantai Kg 2,340.33 Rp 14,969.55 35,033,716.89 2.26% - 0.00% - 0.00% - 0.00% -
7 Baja Tulangan U24 Polos untuk Balok Kg 998.11 Rp 20,112.12 20,074,148.32 1.29% - 0.00% - 0.00% - 0.00% -
8 Baja Tulangan U32 Ulir untuk Balok Kg 1,363.39 Rp 17,697.12 24,128,111.83 1.56% - 0.00% - 0.00% - 0.00% -
9 Pasangan Batu (1PC : 4PP) m³ 125.72 Rp 998,649.00 125,550,152.28 8.10% - 0.00% - 0.00% - 0.00% -
10 Pasangan Batu Kosong m³ 8.70 Rp 526,125.00 4,577,287.50 0.30% - 0.00% - 0.00% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker m² 163.20 Rp 58,688.00 9,577,881.60 0.62% - 0.00% - 0.00% - 0.00% -
12 Bekisting Balok m² 132.00 Rp 83,907.00 11,075,724.00 0.71% - 0.00% 13.20 0.07% 13.20 0.07% 1,107,572.40

REALISASI PROGRES 1,550,477,302.67 100% 37.97% 16.70% 55.01% Rp 852,855,199.05

Disetujui Oleh, Diketahui Oleh, Dibuat Oleh,


Pejabat Pelaksana Teknis Kegiatan (PPTK) Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah Kab. Mamuju Tengah

SUMAILA, S.Pdi NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19730304 200901 1 003 NIP. 19860531 201504 2 001 Site Engineer
TIME SCHEDULE

SKPD : Dinas Pekerjaan Umum dan Penataan Ruang Kabupaten Mamuju Tengah
No. Paket Kontrak : -600/031/057-611.41/SPK/BKK/PSDA/IX/2019
Nama Paket : Pengawasan Pembangunan Saluran Buang Desa Waeputeh (BKK)
Prop / Kab / Kodya : Kab. Mamuju Tengah

Jumlah Harga BULAN - 1 BULAN - 2 BULAN - 3


BOBOT
NO. URAIAN PEKERJAAN Pekerjaan Ket.
(%)
(Rupiah) Mg 1 Mg 2 Mg 3 Mg 4 Mg 5 Mg 6 Mg 7 Mg 8 Mg 9 Mg 10 Mg 11 Mg 12
1 s/d 7 8 s/d 15 16 s/d 23 24 s/d 30 29 s/d 35 36 s/d 42 43 s/d 50 43 s/d 50 29 s/d 35 36 s/d 42 43 s/d 50 43 s/d 50

I. PEKERJAAN PERSIAPAN DAN LAINNYA Rp 52,160,792.00 0.26%


1 Mobilisasi Rp 23,824,000 1.54% 0.26% 0.26% 0.26% 0.26% 0.26% 100%
2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras / Sawit) Rp 26,098,900 1.68% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24%
3 Patok Kayu Setiap 50 m Sepanjang Saluran Rp 2,219,892 0.14% 0.03% 0.03% 0.03% 0.03% 0.03%

II. PEMBUATAN SALURAN Rp 1,223,750,945.43


1 Galian Saluran Rp 1,115,954,951 71.97% 8.00% 8.00% 8.00% 8.00% 8.00% 8.00% 8.00% 8.00% 8.00%
2 Talud / Dinding Saluran Pasangan Batu (1PC : 4PP) Rp 91,723,913 5.92% 1.48% 1.48% RENCANA
1.48% 1.48%
3 Plesteran Tebal 1 cm (1PC:4PP) Rp 16,072,081 1.04% 0.35% 0.35% 0.35%

III PEMBANGUNAN PLAT DEKKER 4 UNIT Rp 274,565,565.24


1 Galian Tanah (Pembongkaran Badan Jalan) Rp 5,105,747 0.33% 0.11% 0.11% 0.11%
50%
2 Urugan Tanah Kembali ( Manual) Rp 2,892,245 0.19% 0.09% 0.09%
3 Beton K-200 untuk Lantai Dekker Rp 14,539,344 0.94% 0.31% 0.31% 0.31%
4 Beton K-200 untuk Lantai Balok Rp 10,795,463 0.70% 0.17% 0.17% 0.17% 0.17%
5 Beton K-100 untuk Bahu Dekker Rp 11,215,744 0.72% 0.24% 0.24% 0.24%
6 Baja Tulangan U32 Ulir untuk Lantai Rp 35,033,717 2.26% 0.56% 0.56% 0.56% REALISASI
0.56%
7 Baja Tulangan U24 Polos untuk Balok Rp 20,074,148 1.29% 0.32% 0.32% 0.32% 0.32%
8 Baja Tulangan U32 Ulir untuk Balok Rp 24,128,112 1.56% 0.39% 0.39% 0.39% 0.39%
9 Pasangan Batu (1PC : 4PP) Rp 125,550,152 8.10% 1.62% 1.62% 1.62% 1.62% 1.62%
10 Pasangan Batu Kosong Rp 4,577,288 0.30% 0.15% 0.15%
11 Bekisting Lantai dan Bahu Dekker Rp 9,577,882 0.62% 0.31% 0.31%
12 Bekisting Balok Rp 11,075,724 0.71% 0.24% 0.24% 0.24% 0%

(A) Jumlah Harga Pekerjaan (termasuk biaya umum dan keuntungan) Rp 1,550,477,302.67
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) Rp 155,047,730.27
100.00% 90 (SEMBILAN PULUH) HARI KALENDER
(C) Jumlah Total Harga Pekerjaan = (A) + (B) Rp 1,705,525,032.94
(D) Jumlah Total Harga Pekerjaan (Dibulatkan) Rp 1,705,525,000.00
BOBOT REALISASI (%) 0.31% 2.09% 2.07% 4.57% 7.56% 8.01% 6.02% 7.33% 3.57% 3.34% 5.75% 4.05%
BOBOT KOMULATIF REALISASI (%) 0 0.31% 2.40% 4.47% 9.04% 16.60% 24.61% 30.63% 37.97% 41.53% 44.87% 50.62% 54.67%
BOBOT RENCANA (%) 0.53% 1.95% 9.95% 12.39% 12.60% 11.39% 11.47% 11.80% 9.77% 9.51% 8.39% 0.26%
BOBOT KOMULATIF RENCANA (%) 0 0.53% 2.48% 12.42% 24.81% 37.41% 48.80% 60.27% 72.07% 81.84% 91.36% 99.74% 100.00%
DEVIASI (%) 0 -0.22% -0.08% -7.95% -15.77% -20.82% -24.19% -29.64% -34.11% -40.31% -46.49% -49.12% -45.33%

Disetujui Oleh, Diketahui Oleh, Dibuat Oleh,


Pejabat Pelaksana Teknis Kegiatan (PPTK) Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang Dinas Pekerjaan Umum dan Penataan Ruang CV. MATTAMPA KONSULTAN
Kab. Mamuju Tengah Kab. Mamuju Tengah

SUMAILA, S. Pd. I NURFADILLA M. ETA, ST SAATIL AUNIAH, ST


NIP. 19730304 200903 1 003 NIP. 19860531 201504 2 001 Site Manager
DAFTAR QUANTITAS DAN HARGA

Nama Paket : Pembangunan Saluran Buang Desa Waeputeh


Nomor Kontrak : 600/212-611.41/PSDA/BKK/IX/2019
Tanggal Kontrak : 9/27/2019
Tanggal Opname : 1-6/01/2020

KONTRAK KEMAJUAN PEKERJAAN

ORIGINAL KONTRAK MASA PELAKSANAAN


JUMLAH HARGA
S/D BULAN
No : Item Uraian Pekerjaan Sat. Harga Jumlah Bobot BULAN INI S/D BULAN INI
LALU
Satuan Volume Harga (%) Bobot Bobot (Rp)
Volume Volume Volume Bobot (%)
(Rupiah) (Rp) (%) (%) (Rupiah)

PEKERJAAN PERSIAPAN DAN LAINNYA 52,160,792.00 3.36 2.60% 40,239,792.00

1 Mobilisasi LS Rp 23,842,000.00 1.00 23,842,000.00 1.54% 0.50 0.77% 11,921,000.00


2 Pembersihan Lahan (Cabut 1 Tunggul Pohon Keras/Sawit) Bh Rp 33,676.00 775.00 26,098,900.00 1.68% 775.00 1.68% 26,098,900.00
3 Patok kayu Setiap 50 m Sepanjang Saluran Bh Rp 12,758.00 174.00 2,219,892.00 0.14% 174.00 0.14% 2,219,892.00

PEMBUATAN SALURAN 1,223,750,945.43 78.93 52.08% 807,418,801.27


1 Galian Saluran M3 Rp 17,914.90 62,292 1,115,954,950.80 71.97% 45,069.68 52.08% 807,418,801.27
2 Talud/Dinding Saluran Pasangan Batu (1PC:4PP) M3 Rp 998,649.00 92 91,723,913.35 5.92% - 0.00% -
3 Plesteran Tebal 1 cm (1PC:4PP) M2 Rp 63,523.00 253 16,072,081.28 1.04% - 0.00% -

PEMBANGUNAN PLAT DEKKER 4 UNIT 274,565,565.24 17.71 0.34% 5,205,605.78


1 Galian Tanah M3 Rp 17,914.90 285.0 5,105,746.50 0.33% 228.75 0.26% 4,098,033.38
2 Urugan Tanah Kembali M3 Rp 34,155.00 84.7 2,892,245.40 0.19% - 0.00% -
3 Beton K-200 untuk Lantai Dekker M3 Rp 908,709.00 16.0 14,539,344.00 0.94% - 0.00% -
4 Beton K-200 untuk Lantai Balok M3 Rp 908,709.00 11.9 10,795,462.92 0.70% - 0.00% -
5 Beton K-100 untuk Bahu Dekker M3 Rp 876,230.00 12.8 11,215,744.00 0.72% - 0.00% -
6 Baja Tulangan U-32 Ulir Untuk Lantai kg Rp 14,969.55 2,340.3 35,033,716.89 2.26% - 0.00% -
7 Baja Tulangan U-24 Polos Untuk Balok kg Rp 20,112.12 998.1 20,074,148.32 1.29% - 0.00% -
8 Baja Tulangan U-32 Ulir Untuk Balok kg Rp 17,697.12 1,363.4 24,128,111.83 1.56% - 0.00% -
9 Pasangan Batu (1PC:4PP) M3 Rp 998,649.00 125.7 125,550,152.28 8.10% - 0.00% -
10 Pasangan Batu Kosong M3 Rp 526,125.00 8.7 4,577,287.50 0.30% - 0.00% -
11 Bekisting Lantai dan Bahu Dekker M2 Rp 58,688.00 163.2 9,577,881.60 0.62% - 0.00% -
12 Bekisting Balok M2 Rp 83,907.00 132.0 11,075,724.00 0.71% 13.20 0.07% 1,107,572.40

1,550,477,302.67 100% 55.01% 852,864,199.05

Disetujui Oleh, Diketahui Oleh, Diperiksa Oleh :


Pejabat Pelaksana Teknis Kegiatan (PPTK) Koordinator Kec. Topoyo Konsultan Pengawas
Dinas Pekerjaan Umum dan Penataan Ruang Dinas Pekerjaan Umum dan Penataan Ruang CV.MATTAMPA KONSULTAN
Kab. Mamuju Tengah Kab. Mamuju Tengah
SUMAILA, S.Pdi NURFADHILA MULYADI ETA, ST SAATIL AULIAH, ST
NIP. 19730304 200901 1 003 NIP. 19860531 201504 2 001 Site Engineer
BACK UP DATA
PEKERJAAN GALIAN SALURAN

HASIL GALIAN SISI KIRI


SEGMEN 1
STA L T1 T2 LUAS VOLUME
- 3.5 0.83 0.83 2.905
50 4 0.8 0.8 3.2 152.63
100 3.5 0.75 0.73 2.59 144.75
150 3.65 0.82 0.82 2.993 139.58
200 3.5 0.87 0.87 3.045 150.95
250 3.85 0.73 0.73 2.8105 146.39
300 1 0.8 0.8 0.8 90.26
350 3.3 0.85 0.85 2.805 90.13
400 3.5 0.8 0.8 2.8 140.13
450 3.5 0.92 0.92 3.22 150.50
500 3.5 0.88 0.88 3.08 157.50 1,362.80
550 4 1.05 1.05 4.2 182.00
600 3.5 0.9 0.9 3.15 183.75
650 3.5 0.75 0.75 2.625 144.38
700 3.5 1.02 1.02 3.57 154.88
750 3.5 0.75 0.75 2.625 154.88
800 3.5 0.78 0.78 2.73 133.88
850 3.5 0.75 0.75 2.625 133.88
900 3.5 0.8 0.8 2.8 135.63
950 3.5 0.75 0.8 2.7125 137.81
1,000 3.5 0.75 0.75 2.625 133.44
1,050 3.5 0.75 0.75 2.625 131.25
1,091 3.3 0.75 0.85 2.64 107.93 1,733.68
TOTAL 3,096.48 TOTAL POHON 50 POHON

SEGMEN 2
STA L T1 T2 LUAS VOLUME
- 3.5 1 0.8 3.15
50 3.7 1 0.9 3.515 166.63
100 3.6 0.75 0.75 2.7 155.38
150 3.5 0.8 0.8 2.8 137.50
200 3.5 0.85 0.86 2.9925 144.81
250 3.5 0.78 0.75 2.6775 141.75
300 3.5 0.8 0.75 2.7125 134.75
350 3.6 0.8 0.75 2.79 137.56
400 3.5 0.8 0.8 2.8 139.75
450 3.5 0.95 0.95 3.325 153.13
500 3.5 0.85 0.9 3.0625 159.69
550 3.6 0.75 0.75 2.7 144.06
600 3.5 0.75 0.75 2.625 133.13
650 3.8 1.06 1.06 4.028 166.33
700 3.3 0.8 0.8 2.64 166.70
750 3.2 0.8 0.8 2.56 130.00
800 3.3 0.85 0.85 2.805 134.13
850 3.3 0.87 0.88 2.8875 142.31
900 3.6 0.95 0.95 3.42 157.69
950 3.5 0.85 0.9 3.0625 162.06
1,000 3.7 1.5 1.5 5.55 215.31
1,050 3.5 0.85 0.86 2.9925 213.56
1,100 3.4 0.95 0.95 3.23 155.56
1,150 3.5 0.95 0.95 3.325 163.88
1,200 3.5 1.07 1.07 3.745 176.75
1,250 3.3 0.9 0.88 2.937 167.05
1,300 3.3 0.8 0.8 2.64 139.43
1,350 3.3 0.8 0.8 2.64 132.00
1,400 3.5 0.8 0.85 2.8875 138.19
1,450 3.5 0.8 0.85 2.8875 144.38
1,500 3.5 0.85 0.88 3.0275 147.88
1,550 3.7 0.8 0.8 2.96 149.69
1,575 3.5 0.8 0.8 2.8 72.00 TOTAL POHON 74 POHON
TOTAL 4,823.00

SEGMEN 3
STA L T1 T2 LUAS VOLUME
- 3.8 0.75 0.7 2.755
50 4 0.9 0.8 3.4 153.88
100 3.8 0.8 0.75 2.945 158.63
150 4 0.75 0.8 3.1 151.13
193 3.5 0.8 0.7 2.625 123.09
TOTAL 586.71 TOTAL POHON 25 POHON

SEGMEN 4
STA L T1 T2 LUAS VOLUME
- 4 0.85 0.9 3.5
50 4.3 0.75 0.8 3.3325 170.81
100 4.5 0.78 0.8 3.555 172.19
150 4.5 0.76 0.83 3.5775 178.31
200 4.4 0.85 0.88 3.806 184.59
243 4.2 0.85 0.88 3.633 159.94
TOTAL 865.84 TOTAL POHON 30 POHON

SEGMEN 5
STA L T1 T2 LUAS VOLUME
- 5 0.8 0.85 4.125
100 4 1 1 4 406.25
150 4 0.85 0.85 3.4 185.00
200 4.3 1 1 4.3 192.50
250 4.4 0.9 0.9 3.96 206.50
300 4.8 0.85 0.85 4.08 201.00
350 4.9 1 1 4.9 224.50
400 4.5 1 1 4.5 235.00
450 5 1 1 5 237.50
500 4.5 0.85 0.85 3.825 220.63
550 5.3 1.1 1.1 5.83 241.38
600 5.2 0.9 0.9 4.68 262.75
650 5 1 1 5 242.00
700 4.8 1.1 1.1 5.28 257.00
750 4 1.1 1.1 4.4 242.00
800 4 1 1 4 210.00
850 4.5 0.9 0.85 3.9375 198.44
900 4 0.85 0.9 3.5 185.94
950 4.5 0.9 0.85 3.9375 185.94
1,000 4 0.85 0.8 3.3 180.94
1,050 0.8 0.85 0.8 0.66 99.00
1,083 3.5 0.85 0.8 2.8875 58.53
TOTAL 4,472.78 TOTAL POHON 65 POHON
SEGMEN 6
STA L T1 T2 LUAS VOLUME
- 5 1 1 5
124 4 1 1 4 558.00
TOTAL 558.00 TOTAL POHON 25 POHON

SEGMEN 7
STA L T1 T2 LUAS VOLUME
- 4.5 1 1 4.5
100 4.3 0.8 0.8 3.44 397.00
120 4.8 0.8 0.8 3.84 72.80
TOTAL 469.80 TOTAL POHON 20 POHON

SEGMEN 8
STA L T1 T2 LUAS VOLUME
- 4.5 0.8 0.9 3.825
95 4.6 0.85 0.9 4.025 372.88
TOTAL 372.88 TOTAL POHON 15 POHON

SEGMEN 9
STA L T1 T2 LUAS VOLUME
- 4 0.85 0.85 3.4
80 5.2 0.9 0.85 4.55 318.00
100 8 0.8 0.8 6.4 109.50
147 0
200 4.5 0.8 0.8 3.6 500.00
300 5 0.9 0.95 4.625 411.25
355 4 0.8 0.9 3.4 220.69
TOTAL 1,559.44 TOTAL POHON 25 POHON

SEGMEN 10
STA L T1 T2 LUAS VOLUME
- 0
100 0 -
200 0 -
264 0 -
TOTAL - TOTAL POHON 0 POHON

SEGMEN 11
STA L T1 T2 LUAS VOLUME
- 5.2 1.02 1 5.252
101 4 1.2 1.5 5.4 537.93
TOTAL 537.93 TOTAL POHON 12 POHON

SEGMEN 12
STA L T1 T2 LUAS VOLUME
-
100
200 5 0.9 0.85 4.375
268
300 7.5 0.9 0.95 6.9375 565.63
360
400 4.5 0.9 0.9 4.05 549.38
TOTAL 1,115.00 TOTAL POHON 35 POHON

SEGMEN 13
STA L T1 T2 LUAS VOLUME
- 4.2 0.9 0.9 3.78
91 4 0.85 0.8 3.3 322.14
TOTAL 322.14 TOTAL POHON 15 POHON

SEGMEN 14
STA L T1 T2 LUAS VOLUME
- 4.5 0.85 0.8 3.7125
100 5.3 1.5 0.9 6.36 503.63
200 5 1.6 1.75 8.375 736.75
288 5 0.9 0.9 4.5 566.50
TOTAL 1,806.88 TOTAL POHON 15 POHON

SEGMEN 15
STA L T1 T2 LUAS VOLUME
- 4 0.8 0.85 3.3
100 6.5 0.9 0.95 6.0125 465.63
200 6 0.95 0.9 5.55 578.13
253 5.6 0.9 0.9 5.04 280.64
TOTAL 1,324.39 TOTAL POHON 20 POHON

SEGMEN 16
STA L T1 T2 LUAS VOLUME
- 5.5 0.95 0.95 5.225
50 5.5 0.95 0.95 5.225 261.25
105
TOTAL 261.25 TOTAL POHON 8 POHON

TOTAL PANJANG SISI KIRI 6,381.00 M


TOTAL VOLUME SISI KIRI 22,172.51 M3 22,172.51
TOTAL PENEBANGAN POHON 434 POHON

TOTAL SISI KANAN + SISI KIRI


VOLUME
ITEM SATUAN SELISIH
RELISASI RAB
GALIAN SALURAN M3 45,069.68 62,292 17,222.32
PENEBANGAN POHON PHN 775 775 -
PATOK BH 174 174 -
TALUD M3 0 92 91.85
2
PLESTERAN TALUD M 0 253 253.01
DWEKKER UNIT 0 4 4.00
BACK UP DATA
PEKERJAAN GALIAN SALURAN

HASIL GALIAN SISI KANAN


SEGMEN 1

STA L T1 T2 LUAS VOLUME


- 4.40 0.75 0.75 3.30
50 2.80 0.85 0.80 2.31 140.25
100 3.20 0.77 0.70 2.35 116.55
150 4.50 0.80 0.75 3.49 145.99
200 4.90 0.85 0.70 3.80 182.13
250 6.80 0.85 0.70 5.27 226.69
300 2.80 0.85 0.70 2.17 186.00
350 3.90 0.60 0.80 2.73 122.50
400 3.50 0.70 0.75 2.54 131.69
450 3.80 0.70 0.65 2.57 127.56
500 4.50 0.75 0.65 3.15 142.88
550 4.70 0.75 0.60 3.17 158.06
600 5.00 0.88 0.80 4.20 184.31
650 4.50 0.80 0.80 3.60 195.00
700 5.30 0.83 0.50 3.52 178.11
750 4.80 0.50 0.80 3.12 166.11
800 4.30 0.80 0.80 3.44 164.00
850 5.50 0.80 0.80 4.40 196.00
900 6.00 0.80 1.30 6.30 267.50
950 4.00 0.80 0.80 3.20 237.50
1,000 4.20 0.90 0.80 3.57 169.25
1,050 4.20 0.70 1.10 3.78 183.75
1,091 4.20 1.00 0.65 3.47 148.52
TOTAL 3,770.35

SEGMEN 2
STA L T1 T2 LUAS VOLUME
- 6.7 0.75 0.5 4.1875
50 5.1 0.95 0.55 3.825 200.3125
100 4 0.9 0.65 3.1 173.125
150 4 0.85 0.7 3.1 155
200 4.5 0.95 0.55 3.375 161.875
250 4 0.9 0.65 3.1 161.875
300 4.5 0.65 0.6 2.8125 147.8125
350 4.5 0.9 0.7 3.6 160.3125
400 5.9 0.71 0.6 3.8645 186.6125
450 6.3 0.55 0.68 3.8745 193.475
500 7.5 0.9 0.6 5.625 237.4875
550 4 0.65 0.7 2.7 208.125
600 5 0.75 1 4.375 176.875
650 3.8 0.75 0.9 3.135 187.75
700 4 0.85 0.6 2.9 150.875
750 5 0.75 0.85 4 172.5
800 5 0.55 0.75 3.25 181.25
850 4 0.75 1.1 3.7 173.75
900 5.3 0.65 0.75 3.71 185.25
950 4.6 0.5 0.7 2.76 161.75
1,000 4 0.75 0.7 2.9 141.5
1,050 4.3 0.7 0.8 3.225 153.125
1,100 4.5 0.6 0.8 3.15 159.375
1,150 4 0.85 1.3 4.3 186.25
1,200 4.2 0.85 1.2 4.305 215.125
1,250 4.5 0.75 0.75 3.375 192
1,300 4.7 0.77 0.8 3.6895 176.6125
1,350 4.2 0.6 0.8 2.94 165.7375
1,400 4 0.65 0.85 3 148.5
1,450 4 0.65 0.75 2.8 145
1,500 4.1 0.65 0.8 2.9725 144.3125
1,550 4 0.65 1.1 3.5 161.8125
1,575 4.2 4.3 0.8 10.71 177.625
TOTAL 5,542.99

SEGMEN 3
STA L T1 T2 LUAS VOLUME
- 3.5 0.7 0.65 2.3625
50 4 0.9 0.7 3.2 139.0625
100 3.8 0.75 0.75 2.85 151.25
150 4 0.6 0.7 2.6 136.25
193 3.5 0.65 0.7 2.3625 106.69375
TOTAL 533.25625

SEGMEN 4
STA L T1 T2 LUAS VOLUME
- 4 0.8 0.9 3.4
50 3.9 0.7 0.8 2.925 158.125
100 4 0.7 0.75 2.9 145.625
150 4 0.7 0.8 3 147.5
200 3.7 0.8 0.85 3.0525 151.3125
243 4 0.8 0.85 3.3 136.57875
TOTAL 739.14125

SEGMEN 5
STA L T1 T2 LUAS VOLUME
- 0 0 0 0
64 4.8 0.75 0.8 3.72 119.04
100 4.8 0.75 0.8 3.72 133.92
150 5.3 1.4 1.1 6.625 258.625
200 5.7 1.3 1.1 6.84 336.625
250 6.5 1.1 0.9 6.5 333.5
300 5.2 1.3 0.9 5.72 305.5
350 5.5 1.3 0.95 6.1875 297.6875
400 5 0.95 0.8 4.375 264.0625
450 5.3 0.9 0.8 4.505 222
500 5.3 0.95 0.65 4.24 218.625
550 5.5 0.75 0.7 3.9875 205.6875
600 6 1.6 0.75 7.05 275.9375
650 6.3 1.3 0.75 6.4575 337.6875
700 6.8 1.3 0.75 6.97 335.6875
750 4.7 1.5 0.75 5.2875 306.4375
800 4.8 1.2 0.8 4.8 252.1875
850 4.7 1.2 1.1 5.405 255.125
900 4.7 2.2 0.9 7.285 317.25
950 4.4 1.3 0.75 4.51 294.875
979 5.4 1 0.65 4.455 129.9925
1,050 4.3 0.85 0.9 3.7625 291.72125
1,083 4.8 0.85 0.7 3.72 123.46125
TOTAL 5615.635

SEGMEN 6
STA L T1 T2 LUAS VOLUME
- 6.3 0.75 0.9 5.1975
100 4.5 0.9 0.75 3.7125 445.5
124 4 0.65 0.55 2.4 73.35
TOTAL 518.85

SEGMEN 7
STA L T1 T2 LUAS VOLUME
- 4.5 0.75 0.8 3.4875
100 5.5 0.75 0.75 4.125 380.625
120 4.1 0.7 0.7 2.87 69.95
TOTAL 450.575

SEGMEN 8
STA L T1 T2 LUAS VOLUME
- 3.5 0.75 0.9 2.8875
95 5 0.9 1 4.75 362.78125
TOTAL 362.78125

SEGMEN 9
STA L T1 T2 LUAS VOLUME
- 4.7 0.85 0.75 3.76
80
100 4.3 0.75 1.3 4.4075 408.375
147 4 0.9 0.7 3.2 178.77625
200
300
355
TOTAL 587.15125

SEGMEN 10
STA L T1 T2 LUAS VOLUME
- 5.1 0.75 0.77 3.876
100 5 1.15 0.85 5 443.8
200 7.9 0.85 0.75 6.32 566
264 5 0.75 0.95 4.25 338.24
TOTAL 1348.04

SEGMEN 11
STA L T1 T2 LUAS VOLUME
- 0
101 0 0
TOTAL 0

SEGMEN 12
STA L T1 T2 LUAS VOLUME
- 4.65 1.27 1.1 5.51025
100 6.3 1.5 1 7.875 669.2625
200 5.3 0.85 1.05 5.035 645.5
268 5.4 0.85 1 4.995 341.02
300 0
360 4.3 0.7 0.7 3.01 368.23
400
TOTAL 2024.0125

SEGMEN 13
STA L T1 T2 LUAS VOLUME
- 4.5 0.55 0.8 3.0375
91 5 0.8 1 4.5 342.95625
TOTAL 342.95625

SEGMEN 14
STA L T1 T2 LUAS VOLUME
- 0
100 0 0
200 0 0
288 0 0
TOTAL 0

SEGMEN 15
STA L T1 T2 LUAS VOLUME
- 6.3 0.65 0.75 4.41
100 4.4 0.6 0.75 2.97 369
200 4 0.8 0.7 3 298.5
253 4 0.8 0.7 3 159
TOTAL 826.5

SEGMEN 16
STA L T1 T2 LUAS VOLUME
- 0 0 0 0
26 4.3 0.8 0.9 3.655 47.515
50 0
105 4.2 0.8 0.9 3.57 187.425
TOTAL 234.94

TOTAL PANJANG SISI KANAN 6,381.00 M


TOTAL VOLUME SISI KANAN 22,897.17 M3 22,897.17
TOTAL PENEBANGAN POHON 341 POHON