MINGGU KE INSTANSI

1
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN
PEKERJAAN UMUM DAN PENATAAN RUANG
15 AGUSTUS 2017 S/D
21 AGUSTUS 2017

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM KONTRAKTOR PELAKSANA
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
PEKERJAAN : BELANJA PEMBANGUNAN MASJID PULAU SETUNAK KECAMATAN KARIMUN CV. PANUTAN JAYA

NO KONTRAK : 2/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 15 Agustus 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 186.180.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- 1.18 - 1.18

IVII PEKERJAAN TANAH Rp 2,097,895.80 1.24- 1.24 - 1.24-


III PEKERJAAN PONDASI Rp 7,936,173.30 4.67- - - --
IV PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- - - --

VIV PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- - - --


VI PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- - - --
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- - - --
VIII PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- - - --
IX PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- - - -
X PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- - - --
XI PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- - - --
XII PEKERJAAN AKHIR Rp 500,000.00 0.29 - - -

a JUMLAH 169,827,294.47 100.00 2.41 - 2.41


b Realisasi Rencana Minggu Ini 3.73
c Realisasi Tercapai Minggu Ini 2.41
d Deviasi (1.32)

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
MINGGU KE INSTANSI
2
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN
PEKERJAAN UMUM DAN PENATAAN RUANG
22 AGUSTUS 2017 S/D
28 AGUSTUS 2017

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM KONTRAKTOR PELAKSANA
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
CV. PANUTAN JAYA
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- - 1.18 1.18

IVIII PEKERJAAN TANAH Rp 2,097,895.80 1.24- - 1.24 1.24


IV PEKERJAAN PONDASI Rp 7,936,173.30 4.67- 1.05 - 1.05
V PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- - - --
VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- #REF! - #REF!
-
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- - - --
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- - - --
IX PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- - - --
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- - - -
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- - - --
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- - - --
XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR Rp 500,000.00 0.29 - - -

a JUMLAH #NAME? #NAME? #NAME? #NAME?


b Realisasi Rencana Minggu Ini 4.00
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
MINGGU KE INSTANSI
3
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN
PEKERJAAN UMUM DAN PENATAAN RUANG
29 AGUSTUS 2017 S/D
04 SEPTEMBER 2017

KEGIATAN : KONTRAKTOR PELAKSANA


PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
CV. PANUTAN JAYA
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- - 1.18 1.18

IVIII PEKERJAAN TANAH Rp 2,097,895.80 1.24- - 1.24 1.24


IV PEKERJAAN PONDASI Rp 7,936,173.30 4.67- #DIV/0! #DIV/0! #DIV/0!
V PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- 3.49 - 3.49-

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- #REF! - #REF!


-
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- - - --
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- - - --
IX PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- 5.12 - 5.12-
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- - - -
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- - - --
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- - - --
XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR Rp 500,000.00 0.29 - - -

a JUMLAH #NAME? #NAME? #NAME? #NAME?


b Realisasi Rencana Minggu Ini 4.27
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
MINGGU KE INSTANSI
4
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN
PEKERJAAN UMUM DAN PENATAAN RUANG
05 SEPTEMBER 2017 S/D
11 SEPTEMBER 2017

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM KONTRAKTOR PELAKSANA
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
CV. PANUTAN JAYA
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- - 1.18 1.18

IVIII PEKERJAAN TANAH Rp 2,097,895.80 1.24- - 1.24 1.24


IV PEKERJAAN PONDASI Rp 7,936,173.30 4.67- #DIV/0! #DIV/0! #DIV/0!
V PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- - 3.49 3.49-

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- #REF! - #REF!


-
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- - - --
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- - - --
IX PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- - 5.12 5.12-
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- - - -
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- - - --
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- - - --
XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR Rp 500,000.00 0.29 - - -

a JUMLAH #NAME? #NAME? #NAME? #NAME?


b Realisasi Rencana Minggu Ini 34.82
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
MINGGU KE INSTANSI
5
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN
PEKERJAAN UMUM DAN PENATAAN RUANG
12 SEPTEMBER 2017 S/D
18 SEPTEMBER 2017

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM KONTRAKTOR PELAKSANA
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
CV. PANUTAN JAYA
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- - 1.18 1.18

IVIII PEKERJAAN TANAH Rp 2,097,895.80 1.24- - 1.24 1.24


IV PEKERJAAN PONDASI Rp 7,936,173.30 4.67- #DIV/0! #DIV/0! #DIV/0!
V PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- - 3.49 3.49-

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- 6.40 - 6.40-


VII PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- 10.74 - 10.74-
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- 2.00 - 2.00-
IX PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- - 5.12 5.12-
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- 0.75 - 0.75
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- - - --
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- - - --
XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR Rp 500,000.00 0.29 - - -

a JUMLAH #NAME? #NAME? #NAME? #NAME?


b Realisasi Rencana Minggu Ini 79.23
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
MINGGU KE INSTANSI
6
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN
PEKERJAAN UMUM DAN PENATAAN RUANG
19 SEPTEMBER 2017 S/D
25 SEPTEMBER 2017

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM KONTRAKTOR PELAKSANA
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
CV. PANUTAN JAYA
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- - 1.18 1.18

IVIII PEKERJAAN TANAH Rp 2,097,895.80 1.24- - 1.24 1.24


IV PEKERJAAN PONDASI Rp 7,936,173.30 4.67- #DIV/0! #DIV/0! #DIV/0!
V PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- - 3.49 3.49-

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- #REF! 6.40 #REF!


-
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- - 10.74 10.74-
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- - 2.00 2.00-
IX PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- - 5.12 5.12-
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- 0.75 0.75 1.51
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- 9.65 - 9.65-
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- - - --
XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR Rp 500,000.00 0.29 - - -

a JUMLAH #NAME? #NAME? #NAME? #NAME?


b Realisasi Rencana Minggu Ini 81.34
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
MINGGU KE INSTANSI
7
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN
PEKERJAAN UMUM DAN PENATAAN RUANG
26 SEPTEMBER 2017 S/D
02 OKTOBER 2017

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM KONTRAKTOR PELAKSANA
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
CV. PANUTAN JAYA
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- - 1.18 1.18

IVIII PEKERJAAN TANAH Rp 2,097,895.80 1.24- - 1.24 1.24


IV PEKERJAAN PONDASI Rp 7,936,173.30 4.67- #DIV/0! #DIV/0! #DIV/0!
V PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- - 3.49 3.49-

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- #REF! 6.40 #REF!


-
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- - 10.74 10.74-
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- - 2.00 2.00-
IX PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- - 5.12 5.12-
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- - 1.51 1.51
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- - 9.65 9.65-
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- 1.84 - 1.84-
XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR Rp 500,000.00 0.29 - - -

a JUMLAH #NAME? #NAME? #NAME? #NAME?


b Realisasi Rencana Minggu Ini 99.61
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
MINGGU KE INSTANSI
8
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN
PEKERJAAN UMUM DAN PENATAAN RUANG
03 OKTOBER 2017 S/D
09 OKTOBER 2017

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM KONTRAKTOR PELAKSANA
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA
CV. PANUTAN JAYA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- - 1.18 1.18

IVIII PEKERJAAN TANAH Rp 2,097,895.80 1.24- - 1.24 1.24-


IV PEKERJAAN PONDASI Rp 7,936,173.30 4.67- #DIV/0! #DIV/0! #DIV/0!
V PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- - 3.49 3.49-

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- #REF! 6.40 #REF!


-
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- - 10.74 10.74-
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- - 2.00 2.00-
IX PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- - 5.12 5.12-
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- 15.17 1.51 16.68
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- - 9.65 9.65-
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- - 1.84 1.84-
XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR Rp 500,000.00 0.29 0.29 - 0.29

a JUMLAH #NAME? #NAME? #NAME? #NAME?


b Realisasi Rencana Minggu Ini 100.00
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
MINGGU KE INSTANSI
9
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN
PEKERJAAN UMUM DAN PENATAAN RUANG
10 OKTOBER 2017 S/D
16 OKTOBER 2017

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM KONTRAKTOR PELAKSANA
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA
CV. PANUTAN JAYA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- - 1.18 1.18

IVIII PEKERJAAN TANAH Rp 2,097,895.80 1.24- - 1.24 1.24-


IV PEKERJAAN PONDASI Rp 7,936,173.30 4.67- #DIV/0! #DIV/0! #DIV/0!
V PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- - 3.49 3.49-

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- #REF! 6.40 #REF!


-
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- - 10.74 10.74-
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- - 2.00 2.00-
IX PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- - 5.12 5.12-
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- 15.17 16.68 31.85
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- - 9.65 9.65-
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- - 1.84 1.84-
XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR Rp 500,000.00 0.29 0.29 0.29 0.59

a JUMLAH #NAME? #NAME? #NAME? #NAME?


b Realisasi Rencana Minggu Ini -
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
MINGGU KE INSTANSI
10
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN
PEKERJAAN UMUM DAN PENATAAN RUANG
17 OKTOBER 2017 S/D
23 OKTOBER 2017

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM KONTRAKTOR PELAKSANA
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA
CV. PANUTAN JAYA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- - 1.18 1.18

IVIII PEKERJAAN TANAH Rp 2,097,895.80 1.24- - 1.24 1.24-


IV PEKERJAAN PONDASI Rp 7,936,173.30 4.67- #DIV/0! #DIV/0! #DIV/0!
V PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- - 3.49 3.49-

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- #REF! 6.40 #REF!


-
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- - 10.74 10.74-
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- - 2.00 2.00-
IX PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- - 5.12 5.12-
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- 15.17 31.85 47.02
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- - 9.65 9.65-
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- - 1.84 1.84-
XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR Rp 500,000.00 0.29 0.29 0.59 0.88

a JUMLAH #NAME? #NAME? #NAME? #NAME?


b Realisasi Rencana Minggu Ini -
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
MINGGU KE INSTANSI
11
REKAPITULASI MINGGUAN
TANGGAL PEMERINTAH KABUPATEN KARIMUN DINAS
KEMAJUAN PROGRES PEKERJAAN PEKERJAAN UMUM DAN PENATAAN RUANG
24 OKTOBER 2017 S/D
30 OKTOBER 2017

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM KONTRAKTOR PELAKSANA
BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL,
MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA
CV. PANUTAN JAYA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

MINGGU S/D MINGGU


MINGGU LALU
NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT INI INI

BOBOT BOBOT BOBOT


I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 1.18- - 1.18 1.18

IVIII PEKERJAAN TANAH Rp 2,097,895.80 1.24- - 1.24 1.24-


IV PEKERJAAN PONDASI Rp 7,936,173.30 4.67- #DIV/0! #DIV/0! #DIV/0!
V PEKERJAAN STRUKTUR Rp 48,512,404.20 28.57- - 3.49 3.49-

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 6.40- #REF! 6.40 #REF!


-
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 10.74- - 10.74 10.74-
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 11.28- - 2.00 2.00-
IX PEKERJAAN PLAFOND Rp 8,693,916.00 5.12- - 5.12 5.12-
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 18.63- 15.17 47.02 62.19
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 9.65- - 9.65 9.65-
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 2.24- - 1.84 1.84-
XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR Rp 500,000.00 0.29 0.29 0.88 1.18

a JUMLAH #NAME? #NAME? #NAME? #NAME?


b Realisasi Rencana Minggu Ini -
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
LAPORAN PROGRESS MINGGUAN
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG INTANSI MINGGU KE
WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING
PEKERJAAN : BELANJA PEMBANGUNAN MASJID PULAU SETUNAK KECAMATAN KARIMUN PEMERINTAH KABUPATEN KARIMUN DINAS 1
NO KONTRAK : 2/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017 PEKERJAAN UMUM DAN PENATAAN RUANG TANGGAL
TANGGAL KONTRAK : 15 Agustus 2017 S/D 15-Aug-17
NILAI KONTRAK : Rp. 186.180.000- KONTRAKTOR PELAKSANA TANGGAL 21-Aug-17
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) BULAN KE
CV. SIDAN JAYA
1 ( SATU )

BOBOT MINGGU INI MINGGU LALU S/D MINGGU INI


NO URAIAN PEKERJAAN
VOLUME SATUAN TOTAL HARGA % VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT

I PEKERJAAN PENDAHULUAN
1 Pekerjaan pas.papan proyek 1.000 Ls Rp 200,000.00 0.12 1.00 0.12 - 1.00 0.12
2 Pekerjaan pembersihan lokasi dan pemasangan bouwplank 1.000 Ls Rp 1,800,000.00 1.06 1.00 1.06 - 1.00 1.06
JUMLAH PEKERJAAN SUB TOTAL I Rp 2,000,000.00 1.18 1.18 - 1.18
II PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi 10.24 m3 Rp 441,548.80 0.26 10.24 0.26 - 10.24 0.26
2 Pek.pemadatan tanah t=52,0.37 & 0.22cm 30.73 m3 Rp 1,656,347.00 0.98 30.73 0.98 - 30.73 0.98
JUMLAH PEKERJAAN SUB TOTAL III Rp 2,097,895.80 1.24 1.24 - 1.24
III PEKERJAAN PONDASI
1 Pondasi Tapak 1 (PT.1)
1 Pek. Urugan Pasir 0.13 m3 Rp 34,720.40 0.02 - - - -
2 Pek. Beton Lantai Kerja 0.13 m3 Rp 158,291.39 0.09 - - - -
3 Pek. Pondasi Tapak
a. Beton 0.260 m3 Rp 380,314.72 0.22
b. Besi 73.09 kg Rp 887,082.37 0.52 - - - -
c. Bekesting 4.72 m2 Rp 691,262.88 0.41 - - - -
4 Pek. Urugan Tanah Kembali 0.50 m3 Rp 10,334.50 0.01 - - - -

2 Pondasi Tapak 2 (PT.2)


1 Pek. Urugan Pasir 0.38 m3 Rp 101,490.40 0.06 - - - -
2 Pek. Beton Lantai Kerja 0.38 m3 Rp 462,697.91 0.27 - - - -
3 Pek. Pondasi Tapak
a. Beton 0.77 m3 Rp 1,126,316.67 0.66 - - - -
b. Besi 211.53 kg Rp 2,567,307.88 1.51 - - - -
c. Bekesting 10.08 m2 Rp 1,476,256.32 0.87 - - - -
4 Pek. Urugan Tanah Kembali 1.940 m3 Rp 40,097.86 0.02 - - - -
JUMLAH PEKERJAAN SUB TOTAL III Rp 7,936,173.30 4.67 - - -
IV PEKERJAAN STRUKTUR
1 Sloof (15x 20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03 - - - -
- Pembesian 205.600 kg Rp 2,495,336.36 1.47 - - - -
- Bekesting 16.000 m2 Rp 1,789,392.00 1.05 - - - -
2 Kolom K1 (25 X 25)
- Beton 0.940 m3 Rp 1,374,983.98 0.81 - - - -
- Pembesian 143.110 kg Rp 1,736,904.60 1.02 - - - -
- Bekesting 7.540 m2 Rp 963,845.74 0.57 - - - -
3 Kolom K2 (15 X 15)
- Beton 1.020 m3 Rp 1,492,003.90 0.88 - - - -
- Pembesian 268.270 kg Rp 3,255,952.75 1.92 - - - -
- Bekesting 9.050 m2 Rp 1,156,870.55 0.68 - - - -
4 Balok (20x25)
- Beton 0.270 m3 Rp 394,942.21 0.23 - - - -
- Pembesian 39.470 kg Rp 479,041.47 0.28 - - - -
- Bekesting 3.710 m2 Rp 1,531,272.82 0.90 - - - -
5 Balok B1 (15x20)
- Beton 1.350 m3 Rp 1,974,711.04 1.16 - - - -
- Pembesian 231.300 kg Rp 2,807,253.41 1.65 - - - -
- Bekesting 6.190 m2 Rp 2,554,872.98 1.50 - - - -
6 RB.1 (15x20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03 - - - -
- Pembesian 205.600 kg Rp 2,495,336.36 1.47 - - - -
- Bekesting 11.000 m2 Rp 4,540,162.00 2.67 - - - -
7 Ringbalok (15x20)
- beton 0.220 m3 Rp 321,804.76 0.19 - - - -
- Pembesian 37.010 kg Rp 449,184.82 0.26 - - - -
- Bekesting 1.320 m2 Rp 544,819.44 0.32 - - - -
8 Dak beton teras
- beton 2.720 m3 Rp 3,978,677.06 2.34 - - - -
- Pembesian 225.230 kg Rp 2,733,582.73 1.61 - - - -
- Bekesting 14.910 m2 Rp 5,930,855.82 3.49 - - - -
JUMLAH PEKERJAAN SUB TOTAL IV Rp 48,512,404.20 28.57 - - -
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako 103.850 m2 Rp 10,871,744.95 6.40 - - - -
JUMLAH PEKERJAAN SUB TOTAL V Rp 10,871,744.95 6.40 - - -
VI PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 207.700 m2 Rp 10,540,234.98 6.21 - - - -
2 Pekerjaan acian 207.700 m2 Rp 7,697,154.30 4.53 - - - -
JUMLAH PEKERJAAN SUB TOTAL VII Rp 18,237,389.28 10.74 - - -
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pekerjaan rabat beton bawah lantai t = 5 cm 2.590 m2 Rp 3,153,651.55 1.86 - - - -
2 Pekerjaan pemasangan keramik 40x40 polished 51.870 m2 Rp 12,606,687.09 7.42 - - - -
3 Pekerjaan pemasangan keramik 40x40 unpolished 14.000 m2 Rp 3,402,614.60 2.00 - - - -
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 19,162,953.24 11.28 - - -
VIII PEKERJAAN PLAFOND
1 Pek. Pas. plafond gypsumboard + rangka metal furing 56.000 m2 Rp 8,693,916.00 5.12 - - - -
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 8,693,916.00 5.12 - - -
IX PEKERJAAN PENUTUP ATAP
1 Pekerjaan rangka atap baja ringan 83.950 m2 Rp 15,482,562.70 9.12 - - - -
2 Pekerjaan pemasangan atap genteng metal 86.960 m2 Rp 10,283,020.00 6.05 - - - -
3 Pekerjaan pemasangan nok genteng 35.200 m1 Rp 3,309,785.60 1.95
4 Pekerjaan pemasangan lisplank GRC 33.000 m1 Rp 2,556,246.00 1.51 - - - -
JUMLAH PEKERJAAN SUB TOTAL IX Rp 31,631,614.30 18.63 - - -
X PEKERJAAN PINTU JENDELA
1 Pemasangan pintu almunium P1 2.000 unit Rp 5,769,584.92 3.40 - - - -
2 Pemasangan jendela almunium J1 1.000 unit Rp 2,535,043.42 1.49 - - - -
3 Pemasangan jendela almunium J2 6.000 unit Rp 7,378,575.06 4.34 - - - -
4 Pemasangan rooster R1 28.000 unit Rp 700,000.00 0.41 - - - -
JUMLAH PEKERJAAN SUB TOTAL XI Rp 16,383,203.40 9.65 - - -
XI PEKERJAAN ELEKTRIKAL
1 Instalasi titik lampu 14.000 titik Rp 2,380,000.00 1.40 - - - -
2 Pemasangan lampu SL LED 13 Watt downlight 4.000 titik Rp 580,000.00 0.34 - - - -
3 Pemasangan lampu LED 7 Watt downlight 3.000 titik Rp 420,000.00 0.25 - - - -
4 Pemasangan saklar tunggal 3.000 titik Rp 120,000.00 0.07 - - - -
5 Pemasangan saklar ganda 1.000 titik Rp 50,000.00 0.03 - - - -
6 Pemasangan stop kontak 2.000 titik Rp 90,000.00 0.05 - - - -
7 pemasangan box sekering 1.000 unit Rp 160,000.00 0.09 - - - -
JUMLAH PEKERJAAN SUB TOTAL XII Rp 3,800,000.00 2.24 - - -
XIII PEKERJAAN AKHIR
1 Pekerjaan pembersihan lokasi 1.000 LS Rp 500,000.00 0.29 - - - -
JUMLAH PEKERJAAN SUB TOTAL VI Rp 500,000.00 0.29 - - -
SUB TOTAL Rp 169,827,294.47 100.00 2.41 - 2.41

Tanjung Balai Karimun, 21 AGUSTUS 2017

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. SIDAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
LAPORAN PROGRESS MINGGUAN
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG INTANSI MINGGU KE
WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA PEMERINTAH KABUPATEN KARIMUN DINAS 2
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017 PEKERJAAN UMUM DAN PENATAAN RUANG TANGGAL
TANGGAL KONTRAK : 19 OKTOBER 2017 S/D 22-Aug-17
NILAI KONTRAK : Rp. 92.960.000- KONTRAKTOR PELAKSANA TANGGAL 28-Aug-17
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) BULAN KE
CV. PANUTAN JAYA
1 ( SATU )

BOBOT MINGGU INI MINGGU LALU S/D MINGGU INI


NO URAIAN PEKERJAAN
VOLUME SATUAN TOTAL HARGA % VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT

I PEKERJAAN PENDAHULUAN
1 Pekerjaan pas.papan proyek 1.000 Ls Rp 200,000.00 0.12 - 1.00 0.12 1.00 0.12
2 Pekerjaan pembersihan lokasi dan pemasangan bouwplank 1.000 Ls Rp 1,800,000.00 1.06 - 1.00 1.06 1.00 1.06
JUMLAH PEKERJAAN SUB TOTAL I Rp 2,000,000.00 1.18 - 1.18 1.18
II PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi 10.24 m3 Rp 441,548.80 0.26 - 10.24 0.26 10.24 0.26
2 Pek.pemadatan tanah t=52,0.37 & 0.22cm 30.73 m3 Rp 1,656,347.00 0.98 - 30.73 0.98 30.73 0.98
JUMLAH PEKERJAAN SUB TOTAL III Rp 2,097,895.80 1.24 - 1.24 1.24
III PEKERJAAN PONDASI
1 Pondasi Tapak 1 (PT.1)
1 Pek. Urugan Pasir 0.13 m3 Rp 34,720.40 0.02 0.13 0.02 - - 0.13 0.02
2 Pek. Beton Lantai Kerja 0.13 m3 Rp 158,291.39 0.09 0.13 0.09 - - 0.13 0.09
3 Pek. Pondasi Tapak
a. Beton 0.260 m3 Rp 380,314.72 0.22
b. Besi 73.09 kg Rp 887,082.37 0.52 73.09 0.52 - - 73.09 0.52
c. Bekesting 4.72 m2 Rp 691,262.88 0.41 4.72 0.41 - - 4.72 0.41
4 Pek. Urugan Tanah Kembali 0.50 m3 Rp 10,334.50 0.01 0.50 0.01 - - 0.50 0.01

2 Pondasi Tapak 2 (PT.2)


1 Pek. Urugan Pasir 0.38 m3 Rp 101,490.40 0.06 - - - - -
2 Pek. Beton Lantai Kerja 0.38 m3 Rp 462,697.91 0.27 - - - - -
3 Pek. Pondasi Tapak
a. Beton 0.77 m3 Rp 1,126,316.67 0.66 - - - - -
b. Besi 211.53 kg Rp 2,567,307.88 1.51 - - - - -
c. Bekesting 10.08 m2 Rp 1,476,256.32 0.87 - - - - -
4 Pek. Urugan Tanah Kembali 1.940 m3 Rp 40,097.86 0.02
JUMLAH PEKERJAAN SUB TOTAL III Rp 7,936,173.30 4.67 1.05 - 1.05
IV PEKERJAAN STRUKTUR
1 Sloof (15x 20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 16.000 m2 Rp 1,789,392.00 1.05
2 Kolom K1 (25 X 25)
- Beton 0.940 m3 Rp 1,374,983.98 0.81
- Pembesian 143.110 kg Rp 1,736,904.60 1.02
- Bekesting 7.540 m2 Rp 963,845.74 0.57
3 Kolom K2 (15 X 15)
- Beton 1.020 m3 Rp 1,492,003.90 0.88
- Pembesian 268.270 kg Rp 3,255,952.75 1.92
- Bekesting 9.050 m2 Rp 1,156,870.55 0.68
4 Balok (20x25)
- Beton 0.270 m3 Rp 394,942.21 0.23
- Pembesian 39.470 kg Rp 479,041.47 0.28
- Bekesting 3.710 m2 Rp 1,531,272.82 0.90
5 Balok B1 (15x20)
- Beton 1.350 m3 Rp 1,974,711.04 1.16
- Pembesian 231.300 kg Rp 2,807,253.41 1.65
- Bekesting 6.190 m2 Rp 2,554,872.98 1.50
6 RB.1 (15x20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 11.000 m2 Rp 4,540,162.00 2.67
7 Ringbalok (15x20)
- beton 0.220 m3 Rp 321,804.76 0.19
- Pembesian 37.010 kg Rp 449,184.82 0.26
- Bekesting 1.320 m2 Rp 544,819.44 0.32
8 Dak beton teras
- beton 2.720 m3 Rp 3,978,677.06 2.34
- Pembesian 225.230 kg Rp 2,733,582.73 1.61
- Bekesting 14.910 m2 Rp 5,930,855.82 3.49 - - - - -
JUMLAH PEKERJAAN SUB TOTAL IV Rp 48,512,404.20 28.57 - - -
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako 103.850 m2 Rp 10,871,744.95 6.40 - - - - -
JUMLAH PEKERJAAN SUB TOTAL V Rp 10,871,744.95 6.40 #REF! - -
VI PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 207.700 m2 Rp 10,540,234.98 6.21 - - - - -
2 Pekerjaan acian 207.700 m2 Rp 7,697,154.30 4.53 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VII Rp 18,237,389.28 10.74 - - -
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pekerjaan rabat beton bawah lantai t = 5 cm 2.590 m2 Rp 3,153,651.55 1.86 - - - - -
2 Pekerjaan pemasangan keramik 40x40 polished 51.870 m2 Rp 12,606,687.09 7.42
3 Pekerjaan pemasangan keramik 40x40 unpolished 14.000 m2 Rp 3,402,614.60 2.00
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 19,162,953.24 11.28 - - -
VIII PEKERJAAN PLAFOND
1 Pek. Pas. plafond gypsumboard + rangka metal furing 56.000 m2 Rp 8,693,916.00 5.12 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 8,693,916.00 5.12 - - -
IX PEKERJAAN PENUTUP ATAP
1 Pekerjaan rangka atap baja ringan 83.950 m2 Rp 15,482,562.70 9.12 - - - - -
2 Pekerjaan pemasangan atap genteng metal 86.960 m2 Rp 10,283,020.00 6.05 - - - - -
3 Pekerjaan pemasangan nok genteng 35.200 m1 Rp 3,309,785.60 1.95
4 Pekerjaan pemasangan lisplank GRC 33.000 m1 Rp 2,556,246.00 1.51 - - - - -
JUMLAH PEKERJAAN SUB TOTAL IX Rp 31,631,614.30 18.63 - - -
X PEKERJAAN PINTU JENDELA
1 Pemasangan pintu almunium P1 2.000 unit Rp 5,769,584.92 3.40 - - - - -
2 Pemasangan jendela almunium J1 1.000 unit Rp 2,535,043.42 1.49 - - - - -
3 Pemasangan jendela almunium J2 6.000 unit Rp 7,378,575.06 4.34 - - - - -
4 Pemasangan rooster R1 28.000 unit Rp 700,000.00 0.41 - - - - -
JUMLAH PEKERJAAN SUB TOTAL XI Rp 16,383,203.40 9.65 - - -
XI PEKERJAAN ELEKTRIKAL
1 Instalasi titik lampu 14.000 titik Rp 2,380,000.00 1.40 - - - - -
2 Pemasangan lampu SL LED 13 Watt downlight 4.000 titik Rp 580,000.00 0.34 - - - - -
3 Pemasangan lampu LED 7 Watt downlight 3.000 titik Rp 420,000.00 0.25
4 Pemasangan saklar tunggal 3.000 titik Rp 120,000.00 0.07
5 Pemasangan saklar ganda 1.000 titik Rp 50,000.00 0.03
6 Pemasangan stop kontak 2.000 titik Rp 90,000.00 0.05
7 pemasangan box sekering 1.000 unit Rp 160,000.00 0.09 - - - - -
JUMLAH PEKERJAAN SUB TOTAL XII Rp 3,800,000.00 2.24 - - -
XIII PEKERJAAN AKHIR
1 Pekerjaan pembersihan lokasi 1.000 LS Rp 500,000.00 0.29 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VI Rp 500,000.00 0.29 - - -
SUB TOTAL #REF! #REF! #REF! #REF! #REF!

Tanjung Balai Karimun, 28 AGUSTUS 2017

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
LAPORAN PROGRESS MINGGUAN
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG INTANSI MINGGU KE
WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA PEMERINTAH KABUPATEN KARIMUN DINAS 3
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017 PEKERJAAN UMUM DAN PENATAAN RUANG TANGGAL
TANGGAL KONTRAK : 19 OKTOBER 2017 S/D 29-Aug-17
NILAI KONTRAK : Rp. 92.960.000- KONTRAKTOR PELAKSANA TANGGAL 4-Sep-17
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) BULAN KE
CV. PANUTAN JAYA
1 ( SATU )

BOBOT MINGGU INI MINGGU LALU S/D MINGGU INI


NO URAIAN PEKERJAAN
VOLUME SATUAN TOTAL HARGA % VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT

I PEKERJAAN PENDAHULUAN
1 Pekerjaan pas.papan proyek 1.000 Ls Rp 200,000.00 0.12 - 1.00 0.12 1.00 0.12
2 Pekerjaan pembersihan lokasi dan pemasangan bouwplank 1.000 Ls Rp 1,800,000.00 1.06 - 1.00 1.06 1.00 1.06
JUMLAH PEKERJAAN SUB TOTAL I Rp 2,000,000.00 1.18 - 1.18 1.18
II PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi 10.24 m3 Rp 441,548.80 0.26 - 10.24 0.26 10.24 0.26
2 Pek.pemadatan tanah t=52,0.37 & 0.22cm 30.73 m3 Rp 1,656,347.00 0.98 - 30.73 0.98 30.73 0.98
JUMLAH PEKERJAAN SUB TOTAL III Rp 2,097,895.80 1.24 - 1.24 1.24
III PEKERJAAN PONDASI
1 Pondasi Tapak 1 (PT.1)
1 Pek. Urugan Pasir 0.13 m3 Rp 34,720.40 0.02 - 0.13 0.02 0.13 0.02
2 Pek. Beton Lantai Kerja 0.13 m3 Rp 158,291.39 0.09 - 0.13 0.09 0.13 0.09
3 Pek. Pondasi Tapak #DIV/0! - #DIV/0! - #DIV/0!
a. Beton 0.260 m3 Rp 380,314.72 0.22
b. Besi 73.09 kg Rp 887,082.37 0.52 - 73.09 0.52 73.09 0.52
c. Bekesting 4.72 m2 Rp 691,262.88 0.41 - 4.72 0.41 4.72 0.41
4 Pek. Urugan Tanah Kembali 0.50 m3 Rp 10,334.50 0.01 - 0.50 0.01 0.50 0.01

2 Pondasi Tapak 2 (PT.2) - #DIV/0! - #DIV/0! - #DIV/0!


1 Pek. Urugan Pasir 0.38 m3 Rp 101,490.40 0.06 0.38 0.06 - - 0.38 0.06
2 Pek. Beton Lantai Kerja 0.38 m3 Rp 462,697.91 0.27 0.38 0.27 - - 0.38 0.27
3 Pek. Pondasi Tapak
a. Beton 0.77 m3 Rp 1,126,316.67 0.66 - - - - -
b. Besi 211.53 kg Rp 2,567,307.88 1.51 - - - - -
c. Bekesting 10.08 m2 Rp 1,476,256.32 0.87 - - - - -
4 Pek. Urugan Tanah Kembali 1.940 m3 Rp 40,097.86 0.02
JUMLAH PEKERJAAN SUB TOTAL III Rp 7,936,173.30 4.67 #DIV/0! #DIV/0! #DIV/0!
IV PEKERJAAN STRUKTUR
1 Sloof (15x 20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 16.000 m2 Rp 1,789,392.00 1.05
2 Kolom K1 (25 X 25)
- Beton 0.940 m3 Rp 1,374,983.98 0.81
- Pembesian 143.110 kg Rp 1,736,904.60 1.02
- Bekesting 7.540 m2 Rp 963,845.74 0.57
3 Kolom K2 (15 X 15)
- Beton 1.020 m3 Rp 1,492,003.90 0.88
- Pembesian 268.270 kg Rp 3,255,952.75 1.92
- Bekesting 9.050 m2 Rp 1,156,870.55 0.68
4 Balok (20x25)
- Beton 0.270 m3 Rp 394,942.21 0.23
- Pembesian 39.470 kg Rp 479,041.47 0.28
- Bekesting 3.710 m2 Rp 1,531,272.82 0.90
5 Balok B1 (15x20)
- Beton 1.350 m3 Rp 1,974,711.04 1.16
- Pembesian 231.300 kg Rp 2,807,253.41 1.65
- Bekesting 6.190 m2 Rp 2,554,872.98 1.50
6 RB.1 (15x20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 11.000 m2 Rp 4,540,162.00 2.67
7 Ringbalok (15x20)
- beton 0.220 m3 Rp 321,804.76 0.19
- Pembesian 37.010 kg Rp 449,184.82 0.26
- Bekesting 1.320 m2 Rp 544,819.44 0.32
8 Dak beton teras
- beton 2.720 m3 Rp 3,978,677.06 2.34
- Pembesian 225.230 kg Rp 2,733,582.73 1.61
- Bekesting 14.910 m2 Rp 5,930,855.82 3.49 14.91 3.49 - - 14.91 3.49
JUMLAH PEKERJAAN SUB TOTAL IV Rp 48,512,404.20 28.57 3.49 - 3.49
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako 103.850 m2 Rp 10,871,744.95 6.40 - - - - -
JUMLAH PEKERJAAN SUB TOTAL V Rp 10,871,744.95 6.40 #REF! - -
VI PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 207.700 m2 Rp 10,540,234.98 6.21 - - - - -
2 Pekerjaan acian 207.700 m2 Rp 7,697,154.30 4.53 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VII Rp 18,237,389.28 10.74 - - -
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pekerjaan rabat beton bawah lantai t = 5 cm 2.590 m2 Rp 3,153,651.55 1.86
2 Pekerjaan pemasangan keramik 40x40 polished 51.870 m2 Rp 12,606,687.09 7.42
3 Pekerjaan pemasangan keramik 40x40 unpolished 14.000 m2 Rp 3,402,614.60 2.00 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 19,162,953.24 11.28 - - -
VIII PEKERJAAN PLAFOND
1 Pek. Pas. plafond gypsumboard + rangka metal furing 56.000 m2 Rp 8,693,916.00 5.12 56.00 5.12 - - 56.00 5.12
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 8,693,916.00 5.12 5.12 - 5.12
IX PEKERJAAN PENUTUP ATAP
1 Pekerjaan rangka atap baja ringan 83.950 m2 Rp 15,482,562.70 9.12 - - - - -
2 Pekerjaan pemasangan atap genteng metal 86.960 m2 Rp 10,283,020.00 6.05 - - - - -
3 Pekerjaan pemasangan nok genteng 35.200 m1 Rp 3,309,785.60 1.95
4 Pekerjaan pemasangan lisplank GRC 33.000 m1 Rp 2,556,246.00 1.51 - - - - -
JUMLAH PEKERJAAN SUB TOTAL IX Rp 31,631,614.30 18.63 - - -
X PEKERJAAN PINTU JENDELA
1 Pemasangan pintu almunium P1 2.000 unit Rp 5,769,584.92 3.40 - - - - -
2 Pemasangan jendela almunium J1 1.000 unit Rp 2,535,043.42 1.49 - - - - -
3 Pemasangan jendela almunium J2 6.000 unit Rp 7,378,575.06 4.34 - - - - -
4 Pemasangan rooster R1 28.000 unit Rp 700,000.00 0.41 - - - - -
JUMLAH PEKERJAAN SUB TOTAL XI Rp 16,383,203.40 9.65 - - -
XI PEKERJAAN ELEKTRIKAL
1 Instalasi titik lampu 14.000 titik Rp 2,380,000.00 1.40 - - - - -
2 Pemasangan lampu SL LED 13 Watt downlight 4.000 titik Rp 580,000.00 0.34 - - - - -
3 Pemasangan lampu LED 7 Watt downlight 3.000 titik Rp 420,000.00 0.25
4 Pemasangan saklar tunggal 3.000 titik Rp 120,000.00 0.07
5 Pemasangan saklar ganda 1.000 titik Rp 50,000.00 0.03
6 Pemasangan stop kontak 2.000 titik Rp 90,000.00 0.05
7 pemasangan box sekering 1.000 unit Rp 160,000.00 0.09 - - - - -
JUMLAH PEKERJAAN SUB TOTAL XII Rp 3,800,000.00 2.24 - - -
XIII PEKERJAAN AKHIR
1 Pekerjaan pembersihan lokasi 1.000 LS Rp 500,000.00 0.29 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VI Rp 500,000.00 0.29 - - -
SUB TOTAL #REF! #REF! #REF! #REF! #REF!

Tanjung Balai Karimun, 04 SEPTEMBER 2017

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
LAPORAN PROGRESS MINGGUAN
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG INTANSI MINGGU KE
WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA PEMERINTAH KABUPATEN KARIMUN DINAS 4
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017 PEKERJAAN UMUM DAN PENATAAN RUANG TANGGAL
TANGGAL KONTRAK : 19 OKTOBER 2017 S/D 5-Sep-17
NILAI KONTRAK : Rp. 92.960.000- KONTRAKTOR PELAKSANA TANGGAL 11-Sep-17
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) BULAN KE
CV. PANUTAN JAYA
1 ( SATU )

BOBOT MINGGU INI MINGGU LALU S/D MINGGU INI


NO URAIAN PEKERJAAN
VOLUME SATUAN TOTAL HARGA % VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT

I PEKERJAAN PENDAHULUAN
1 Pekerjaan pas.papan proyek 1.000 Ls Rp 200,000.00 0.12 - 1.00 0.12 1.00 0.12
2 Pekerjaan pembersihan lokasi dan pemasangan bouwplank 1.000 Ls Rp 1,800,000.00 1.06 - 1.00 1.06 1.00 1.06
JUMLAH PEKERJAAN SUB TOTAL I Rp 2,000,000.00 1.18 - 1.18 1.18
II PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi 10.24 m3 Rp 441,548.80 0.26 - 10.24 0.26 10.24 0.26
2 Pek.pemadatan tanah t=52,0.37 & 0.22cm 30.73 m3 Rp 1,656,347.00 0.98 - 30.73 0.98 30.73 0.98
JUMLAH PEKERJAAN SUB TOTAL III Rp 2,097,895.80 1.24 - 1.24 1.24
III PEKERJAAN PONDASI
1 Pondasi Tapak 1 (PT.1)
1 Pek. Urugan Pasir 0.13 m3 Rp 34,720.40 0.02 - 0.13 0.02 0.13 0.02
2 Pek. Beton Lantai Kerja 0.13 m3 Rp 158,291.39 0.09 - 0.13 0.09 0.13 0.09
3 Pek. Pondasi Tapak #DIV/0! - #DIV/0! - #DIV/0!
a. Beton 0.260 m3 Rp 380,314.72 0.22
b. Besi 73.09 kg Rp 887,082.37 0.52 - 73.09 0.52 73.09 0.52
c. Bekesting 4.72 m2 Rp 691,262.88 0.41 - 4.72 0.41 4.72 0.41
4 Pek. Urugan Tanah Kembali 0.50 m3 Rp 10,334.50 0.01 - 0.50 0.01 0.50 0.01

2 Pondasi Tapak 2 (PT.2) #DIV/0! - #DIV/0! - #DIV/0!


1 Pek. Urugan Pasir 0.38 m3 Rp 101,490.40 0.06 - 0.38 0.06 0.38 0.06
2 Pek. Beton Lantai Kerja 0.38 m3 Rp 462,697.91 0.27 - 0.38 0.27 0.38 0.27
3 Pek. Pondasi Tapak
a. Beton 0.77 m3 Rp 1,126,316.67 0.66 0.77 0.66 - - 0.77 0.66
b. Besi 211.53 kg Rp 2,567,307.88 1.51 211.53 1.51 - - 211.53 1.51
c. Bekesting 10.08 m2 Rp 1,476,256.32 0.87 10.08 0.87 - - 10.08 0.87
4 Pek. Urugan Tanah Kembali 1.940 m3 Rp 40,097.86 0.02
JUMLAH PEKERJAAN SUB TOTAL III Rp 7,936,173.30 4.67 #DIV/0! #DIV/0! #DIV/0!
IV PEKERJAAN STRUKTUR
1 Sloof (15x 20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 16.000 m2 Rp 1,789,392.00 1.05
2 Kolom K1 (25 X 25)
- Beton 0.940 m3 Rp 1,374,983.98 0.81
- Pembesian 143.110 kg Rp 1,736,904.60 1.02
- Bekesting 7.540 m2 Rp 963,845.74 0.57
3 Kolom K2 (15 X 15)
- Beton 1.020 m3 Rp 1,492,003.90 0.88
- Pembesian 268.270 kg Rp 3,255,952.75 1.92
- Bekesting 9.050 m2 Rp 1,156,870.55 0.68
4 Balok (20x25)
- Beton 0.270 m3 Rp 394,942.21 0.23
- Pembesian 39.470 kg Rp 479,041.47 0.28
- Bekesting 3.710 m2 Rp 1,531,272.82 0.90
5 Balok B1 (15x20)
- Beton 1.350 m3 Rp 1,974,711.04 1.16
- Pembesian 231.300 kg Rp 2,807,253.41 1.65
- Bekesting 6.190 m2 Rp 2,554,872.98 1.50
6 RB.1 (15x20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 11.000 m2 Rp 4,540,162.00 2.67
7 Ringbalok (15x20)
- beton 0.220 m3 Rp 321,804.76 0.19
- Pembesian 37.010 kg Rp 449,184.82 0.26
- Bekesting 1.320 m2 Rp 544,819.44 0.32
8 Dak beton teras
- beton 2.720 m3 Rp 3,978,677.06 2.34
- Pembesian 225.230 kg Rp 2,733,582.73 1.61
- Bekesting 14.910 m2 Rp 5,930,855.82 3.49 - 14.91 3.49 14.91 3.49
JUMLAH PEKERJAAN SUB TOTAL IV Rp 48,512,404.20 28.57 - 3.49 3.49
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako 103.850 m2 Rp 10,871,744.95 6.40 - - - - -
JUMLAH PEKERJAAN SUB TOTAL V Rp 10,871,744.95 6.40 #REF! - -
VI PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 207.700 m2 Rp 10,540,234.98 6.21 - - - - -
2 Pekerjaan acian 207.700 m2 Rp 7,697,154.30 4.53 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VII Rp 18,237,389.28 10.74 - - -
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pekerjaan rabat beton bawah lantai t = 5 cm 2.590 m2 Rp 3,153,651.55 1.86
2 Pekerjaan pemasangan keramik 40x40 polished 51.870 m2 Rp 12,606,687.09 7.42
3 Pekerjaan pemasangan keramik 40x40 unpolished 14.000 m2 Rp 3,402,614.60 2.00 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 19,162,953.24 11.28 - - -
VIII PEKERJAAN PLAFOND
1 Pek. Pas. plafond gypsumboard + rangka metal furing 56.000 m2 Rp 8,693,916.00 5.12 - 56.00 5.12 56.00 5.12
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 8,693,916.00 5.12 - 5.12 5.12
IX PEKERJAAN PENUTUP ATAP
1 Pekerjaan rangka atap baja ringan 83.950 m2 Rp 15,482,562.70 9.12 - - - - -
2 Pekerjaan pemasangan atap genteng metal 86.960 m2 Rp 10,283,020.00 6.05 - - - - -
3 Pekerjaan pemasangan nok genteng 35.200 m1 Rp 3,309,785.60 1.95
4 Pekerjaan pemasangan lisplank GRC 33.000 m1 Rp 2,556,246.00 1.51 - - - - -
JUMLAH PEKERJAAN SUB TOTAL IX Rp 31,631,614.30 18.63 - - -
X PEKERJAAN PINTU JENDELA
1 Pemasangan pintu almunium P1 2.000 unit Rp 5,769,584.92 3.40 - - - - -
2 Pemasangan jendela almunium J1 1.000 unit Rp 2,535,043.42 1.49 - - - - -
3 Pemasangan jendela almunium J2 6.000 unit Rp 7,378,575.06 4.34 - - - - -
4 Pemasangan rooster R1 28.000 unit Rp 700,000.00 0.41 - - - - -
JUMLAH PEKERJAAN SUB TOTAL XI Rp 16,383,203.40 9.65 - - -
XI PEKERJAAN ELEKTRIKAL
1 Instalasi titik lampu 14.000 titik Rp 2,380,000.00 1.40 - - - - -
2 Pemasangan lampu SL LED 13 Watt downlight 4.000 titik Rp 580,000.00 0.34 - - - - -
3 Pemasangan lampu LED 7 Watt downlight 3.000 titik Rp 420,000.00 0.25
4 Pemasangan saklar tunggal 3.000 titik Rp 120,000.00 0.07
5 Pemasangan saklar ganda 1.000 titik Rp 50,000.00 0.03
6 Pemasangan stop kontak 2.000 titik Rp 90,000.00 0.05
7 pemasangan box sekering 1.000 unit Rp 160,000.00 0.09 - - - - -
JUMLAH PEKERJAAN SUB TOTAL XII Rp 3,800,000.00 2.24 - - -
XIII PEKERJAAN AKHIR
1 Pekerjaan pembersihan lokasi 1.000 LS Rp 500,000.00 0.29 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VI Rp 500,000.00 0.29 - - -
SUB TOTAL #REF! #REF! #REF! #REF! #REF!

Tanjung Balai Karimun, 11 SEPTEMBER 2017

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
LAPORAN PROGRESS MINGGUAN
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG INTANSI MINGGU KE
WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA PEMERINTAH KABUPATEN KARIMUN DINAS 5
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017 PEKERJAAN UMUM DAN PENATAAN RUANG TANGGAL
TANGGAL KONTRAK : 19 OKTOBER 2017 S/D 12-Sep-17
NILAI KONTRAK : Rp. 92.960.000- KONTRAKTOR PELAKSANA TANGGAL 18-Sep-17
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) BULAN KE
CV. PANUTAN JAYA
2 ( Dua )

BOBOT MINGGU INI MINGGU LALU S/D MINGGU INI


NO URAIAN PEKERJAAN
VOLUME SATUAN TOTAL HARGA % VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT

I PEKERJAAN PENDAHULUAN
1 Pekerjaan pas.papan proyek 1.000 Ls Rp 200,000.00 0.12 - 1.00 0.12 1.00 0.12
2 Pekerjaan pembersihan lokasi dan pemasangan bouwplank 1.000 Ls Rp 1,800,000.00 1.06 - 1.00 1.06 1.00 1.06
JUMLAH PEKERJAAN SUB TOTAL I Rp 2,000,000.00 1.18 - 1.18 1.18
II PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi 10.24 m3 Rp 441,548.80 0.26 - 10.24 0.26 10.24 0.26
2 Pek.pemadatan tanah t=52,0.37 & 0.22cm 30.73 m3 Rp 1,656,347.00 0.98 - 30.73 0.98 30.73 0.98
JUMLAH PEKERJAAN SUB TOTAL III Rp 2,097,895.80 1.24 - 1.24 1.24
III PEKERJAAN PONDASI
1 Pondasi Tapak 1 (PT.1)
1 Pek. Urugan Pasir 0.13 m3 Rp 34,720.40 0.02 - 0.13 0.02 0.13 0.02
2 Pek. Beton Lantai Kerja 0.13 m3 Rp 158,291.39 0.09 - 0.13 0.09 0.13 0.09
3 Pek. Pondasi Tapak #DIV/0! - #DIV/0! - #DIV/0!
a. Beton 0.260 m3 Rp 380,314.72 0.22
b. Besi 73.09 kg Rp 887,082.37 0.52 - 73.09 0.52 73.09 0.52
c. Bekesting 4.72 m2 Rp 691,262.88 0.41 - 4.72 0.41 4.72 0.41
4 Pek. Urugan Tanah Kembali 0.50 m3 Rp 10,334.50 0.01 - 0.50 0.01 0.50 0.01

2 Pondasi Tapak 2 (PT.2) #DIV/0! - #DIV/0! - #DIV/0!


1 Pek. Urugan Pasir 0.38 m3 Rp 101,490.40 0.06 - 0.38 0.06 0.38 0.06
2 Pek. Beton Lantai Kerja 0.38 m3 Rp 462,697.91 0.27 - 0.38 0.27 0.38 0.27
3 Pek. Pondasi Tapak
a. Beton 0.77 m3 Rp 1,126,316.67 0.66 - 0.77 0.66 0.77 0.66
b. Besi 211.53 kg Rp 2,567,307.88 1.51 - 211.53 1.51 211.53 1.51
c. Bekesting 10.08 m2 Rp 1,476,256.32 0.87 - 10.08 0.87 10.08 0.87
4 Pek. Urugan Tanah Kembali 1.940 m3 Rp 40,097.86 0.02
JUMLAH PEKERJAAN SUB TOTAL III Rp 7,936,173.30 4.67 #DIV/0! #DIV/0! #DIV/0!
IV PEKERJAAN STRUKTUR
1 Sloof (15x 20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 16.000 m2 Rp 1,789,392.00 1.05
2 Kolom K1 (25 X 25)
- Beton 0.940 m3 Rp 1,374,983.98 0.81
- Pembesian 143.110 kg Rp 1,736,904.60 1.02
- Bekesting 7.540 m2 Rp 963,845.74 0.57
3 Kolom K2 (15 X 15)
- Beton 1.020 m3 Rp 1,492,003.90 0.88
- Pembesian 268.270 kg Rp 3,255,952.75 1.92
- Bekesting 9.050 m2 Rp 1,156,870.55 0.68
4 Balok (20x25)
- Beton 0.270 m3 Rp 394,942.21 0.23
- Pembesian 39.470 kg Rp 479,041.47 0.28
- Bekesting 3.710 m2 Rp 1,531,272.82 0.90
5 Balok B1 (15x20)
- Beton 1.350 m3 Rp 1,974,711.04 1.16
- Pembesian 231.300 kg Rp 2,807,253.41 1.65
- Bekesting 6.190 m2 Rp 2,554,872.98 1.50
6 RB.1 (15x20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 11.000 m2 Rp 4,540,162.00 2.67
7 Ringbalok (15x20)
- beton 0.220 m3 Rp 321,804.76 0.19
- Pembesian 37.010 kg Rp 449,184.82 0.26
- Bekesting 1.320 m2 Rp 544,819.44 0.32
8 Dak beton teras
- beton 2.720 m3 Rp 3,978,677.06 2.34
- Pembesian 225.230 kg Rp 2,733,582.73 1.61
- Bekesting 14.910 m2 Rp 5,930,855.82 3.49 - 14.91 3.49 14.91 3.49
JUMLAH PEKERJAAN SUB TOTAL IV Rp 48,512,404.20 28.57 - 3.49 3.49
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako 103.850 m2 Rp 10,871,744.95 6.40 103.85 6.40 - - 103.85 6.40
JUMLAH PEKERJAAN SUB TOTAL V Rp 10,871,744.95 6.40 6.40 - 6.40
VI PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 207.700 m2 Rp 10,540,234.98 6.21 207.70 6.21 - - 207.70 6.21
2 Pekerjaan acian 207.700 m2 Rp 7,697,154.30 4.53 207.70 4.53 - - 207.70 4.53
JUMLAH PEKERJAAN SUB TOTAL VII Rp 18,237,389.28 10.74 10.74 - 10.74
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pekerjaan rabat beton bawah lantai t = 5 cm 2.590 m2 Rp 3,153,651.55 1.86
2 Pekerjaan pemasangan keramik 40x40 polished 51.870 m2 Rp 12,606,687.09 7.42
3 Pekerjaan pemasangan keramik 40x40 unpolished 14.000 m2 Rp 3,402,614.60 2.00 14.00 2.00 - - 14.00 2.00
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 19,162,953.24 11.28 2.00 - 2.00
VIII PEKERJAAN PLAFOND
1 Pek. Pas. plafond gypsumboard + rangka metal furing 56.000 m2 Rp 8,693,916.00 5.12 - 56.00 5.12 56.00 5.12
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 8,693,916.00 5.12 - 5.12 5.12
IX PEKERJAAN PENUTUP ATAP
1 Pekerjaan rangka atap baja ringan 83.950 m2 Rp 15,482,562.70 9.12 - - - - -
2 Pekerjaan pemasangan atap genteng metal 86.960 m2 Rp 10,283,020.00 6.05 - - - - -
3 Pekerjaan pemasangan nok genteng 35.200 m1 Rp 3,309,785.60 1.95
4 Pekerjaan pemasangan lisplank GRC 33.000 m1 Rp 2,556,246.00 1.51 16.50 0.75 - - 16.50 0.75
JUMLAH PEKERJAAN SUB TOTAL IX Rp 31,631,614.30 18.63 0.75 - 0.75
X PEKERJAAN PINTU JENDELA
1 Pemasangan pintu almunium P1 2.000 unit Rp 5,769,584.92 3.40 - - - - -
2 Pemasangan jendela almunium J1 1.000 unit Rp 2,535,043.42 1.49 - - - - -
3 Pemasangan jendela almunium J2 6.000 unit Rp 7,378,575.06 4.34 - - - - -
4 Pemasangan rooster R1 28.000 unit Rp 700,000.00 0.41 - - - - -
JUMLAH PEKERJAAN SUB TOTAL XI Rp 16,383,203.40 9.65 - - -
XI PEKERJAAN ELEKTRIKAL
1 Instalasi titik lampu 14.000 titik Rp 2,380,000.00 1.40 - - - - -
2 Pemasangan lampu SL LED 13 Watt downlight 4.000 titik Rp 580,000.00 0.34 - - - - -
3 Pemasangan lampu LED 7 Watt downlight 3.000 titik Rp 420,000.00 0.25
4 Pemasangan saklar tunggal 3.000 titik Rp 120,000.00 0.07
5 Pemasangan saklar ganda 1.000 titik Rp 50,000.00 0.03
6 Pemasangan stop kontak 2.000 titik Rp 90,000.00 0.05
7 pemasangan box sekering 1.000 unit Rp 160,000.00 0.09 - - - - -
JUMLAH PEKERJAAN SUB TOTAL XII Rp 3,800,000.00 2.24 - - -
XIII PEKERJAAN AKHIR
1 Pekerjaan pembersihan lokasi 1.000 LS Rp 500,000.00 0.29 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VI Rp 500,000.00 0.29 - - -
SUB TOTAL #REF! #REF! #REF! #REF! #REF!

Tanjung Balai Karimun, 18 SEPTEMBER 2017

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
LAPORAN PROGRESS MINGGUAN
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG INTANSI MINGGU KE
WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA PEMERINTAH KABUPATEN KARIMUN DINAS 6
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017 PEKERJAAN UMUM DAN PENATAAN RUANG TANGGAL
TANGGAL KONTRAK : 19 OKTOBER 2017 S/D 19-Sep-17
NILAI KONTRAK : Rp. 92.960.000- KONTRAKTOR PELAKSANA TANGGAL 25-Sep-17
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) BULAN KE
CV. PANUTAN JAYA
2 ( Dua )

BOBOT MINGGU INI MINGGU LALU S/D MINGGU INI


NO URAIAN PEKERJAAN
VOLUME SATUAN TOTAL HARGA % VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT

I PEKERJAAN PENDAHULUAN
1 Pekerjaan pas.papan proyek 1.000 Ls Rp 200,000.00 0.12 - 1.00 0.12 1.00 0.12
2 Pekerjaan pembersihan lokasi dan pemasangan bouwplank 1.000 Ls Rp 1,800,000.00 1.06 - 1.00 1.06 1.00 1.06
JUMLAH PEKERJAAN SUB TOTAL I Rp 2,000,000.00 1.18 - 1.18 1.18
II PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi 10.24 m3 Rp 441,548.80 0.26 - 10.24 0.26 10.24 0.26
2 Pek.pemadatan tanah t=52,0.37 & 0.22cm 30.73 m3 Rp 1,656,347.00 0.98 - 30.73 0.98 30.73 0.98
JUMLAH PEKERJAAN SUB TOTAL III Rp 2,097,895.80 1.24 - 1.24 1.24
III PEKERJAAN PONDASI
1 Pondasi Tapak 1 (PT.1)
1 Pek. Urugan Pasir 0.13 m3 Rp 34,720.40 0.02 - 0.13 0.02 0.13 0.02
2 Pek. Beton Lantai Kerja 0.13 m3 Rp 158,291.39 0.09 - 0.13 0.09 0.13 0.09
3 Pek. Pondasi Tapak #DIV/0! - #DIV/0! - #DIV/0!
a. Beton 0.260 m3 Rp 380,314.72 0.22
b. Besi 73.09 kg Rp 887,082.37 0.52 - 73.09 0.52 73.09 0.52
c. Bekesting 4.72 m2 Rp 691,262.88 0.41 - 4.72 0.41 4.72 0.41
4 Pek. Urugan Tanah Kembali 0.50 m3 Rp 10,334.50 0.01 - 0.50 0.01 0.50 0.01

2 Pondasi Tapak 2 (PT.2) #DIV/0! - #DIV/0! - #DIV/0!


1 Pek. Urugan Pasir 0.38 m3 Rp 101,490.40 0.06 - 0.38 0.06 0.38 0.06
2 Pek. Beton Lantai Kerja 0.38 m3 Rp 462,697.91 0.27 - 0.38 0.27 0.38 0.27
3 Pek. Pondasi Tapak
a. Beton 0.77 m3 Rp 1,126,316.67 0.66 - 0.77 0.66 0.77 0.66
b. Besi 211.53 kg Rp 2,567,307.88 1.51 - 211.53 1.51 211.53 1.51
c. Bekesting 10.08 m2 Rp 1,476,256.32 0.87 - 10.08 0.87 10.08 0.87
4 Pek. Urugan Tanah Kembali 1.940 m3 Rp 40,097.86 0.02
JUMLAH PEKERJAAN SUB TOTAL III Rp 7,936,173.30 4.67 #DIV/0! #DIV/0! #DIV/0!
IV PEKERJAAN STRUKTUR
1 Sloof (15x 20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 16.000 m2 Rp 1,789,392.00 1.05
2 Kolom K1 (25 X 25)
- Beton 0.940 m3 Rp 1,374,983.98 0.81
- Pembesian 143.110 kg Rp 1,736,904.60 1.02
- Bekesting 7.540 m2 Rp 963,845.74 0.57
3 Kolom K2 (15 X 15)
- Beton 1.020 m3 Rp 1,492,003.90 0.88
- Pembesian 268.270 kg Rp 3,255,952.75 1.92
- Bekesting 9.050 m2 Rp 1,156,870.55 0.68
4 Balok (20x25)
- Beton 0.270 m3 Rp 394,942.21 0.23
- Pembesian 39.470 kg Rp 479,041.47 0.28
- Bekesting 3.710 m2 Rp 1,531,272.82 0.90
5 Balok B1 (15x20)
- Beton 1.350 m3 Rp 1,974,711.04 1.16
- Pembesian 231.300 kg Rp 2,807,253.41 1.65
- Bekesting 6.190 m2 Rp 2,554,872.98 1.50
6 RB.1 (15x20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 11.000 m2 Rp 4,540,162.00 2.67
7 Ringbalok (15x20)
- beton 0.220 m3 Rp 321,804.76 0.19
- Pembesian 37.010 kg Rp 449,184.82 0.26
- Bekesting 1.320 m2 Rp 544,819.44 0.32
8 Dak beton teras
- beton 2.720 m3 Rp 3,978,677.06 2.34
- Pembesian 225.230 kg Rp 2,733,582.73 1.61
- Bekesting 14.910 m2 Rp 5,930,855.82 3.49 - 14.91 3.49 14.91 3.49
JUMLAH PEKERJAAN SUB TOTAL IV Rp 48,512,404.20 28.57 - 3.49 3.49
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako 103.850 m2 Rp 10,871,744.95 6.40 - 103.85 6.40 103.85 6.40
JUMLAH PEKERJAAN SUB TOTAL V Rp 10,871,744.95 6.40 #REF! 6.40 6.40
VI PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 207.700 m2 Rp 10,540,234.98 6.21 - 207.70 6.21 207.70 6.21
2 Pekerjaan acian 207.700 m2 Rp 7,697,154.30 4.53 - 207.70 4.53 207.70 4.53
JUMLAH PEKERJAAN SUB TOTAL VII Rp 18,237,389.28 10.74 - 10.74 10.74
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pekerjaan rabat beton bawah lantai t = 5 cm 2.590 m2 Rp 3,153,651.55 1.86
2 Pekerjaan pemasangan keramik 40x40 polished 51.870 m2 Rp 12,606,687.09 7.42
3 Pekerjaan pemasangan keramik 40x40 unpolished 14.000 m2 Rp 3,402,614.60 2.00 - 14.00 2.00 14.00 2.00
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 19,162,953.24 11.28 - 2.00 2.00
VIII PEKERJAAN PLAFOND
1 Pek. Pas. plafond gypsumboard + rangka metal furing 56.000 m2 Rp 8,693,916.00 5.12 - 56.00 5.12 56.00 5.12
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 8,693,916.00 5.12 - 5.12 5.12
IX PEKERJAAN PENUTUP ATAP
1 Pekerjaan rangka atap baja ringan 83.950 m2 Rp 15,482,562.70 9.12 - - - - -
2 Pekerjaan pemasangan atap genteng metal 86.960 m2 Rp 10,283,020.00 6.05 - - - - -
3 Pekerjaan pemasangan nok genteng 35.200 m1 Rp 3,309,785.60 1.95
4 Pekerjaan pemasangan lisplank GRC 33.000 m1 Rp 2,556,246.00 1.51 16.50 0.75 16.50 0.75 33.00 1.51
JUMLAH PEKERJAAN SUB TOTAL IX Rp 31,631,614.30 18.63 0.75 0.75 1.51
X PEKERJAAN PINTU JENDELA
1 Pemasangan pintu almunium P1 2.000 unit Rp 5,769,584.92 3.40 2.00 3.40 - - 2.00 3.40
2 Pemasangan jendela almunium J1 1.000 unit Rp 2,535,043.42 1.49 1.00 1.49 - - 1.00 1.49
3 Pemasangan jendela almunium J2 6.000 unit Rp 7,378,575.06 4.34 6.00 4.34 - - 6.00 4.34
4 Pemasangan rooster R1 28.000 unit Rp 700,000.00 0.41 28.00 0.41 - - 28.00 0.41
JUMLAH PEKERJAAN SUB TOTAL XI Rp 16,383,203.40 9.65 9.65 - 9.65
XI PEKERJAAN ELEKTRIKAL
1 Instalasi titik lampu 14.000 titik Rp 2,380,000.00 1.40 - - - - -
2 Pemasangan lampu SL LED 13 Watt downlight 4.000 titik Rp 580,000.00 0.34 - - - - -
3 Pemasangan lampu LED 7 Watt downlight 3.000 titik Rp 420,000.00 0.25
4 Pemasangan saklar tunggal 3.000 titik Rp 120,000.00 0.07
5 Pemasangan saklar ganda 1.000 titik Rp 50,000.00 0.03
6 Pemasangan stop kontak 2.000 titik Rp 90,000.00 0.05
7 pemasangan box sekering 1.000 unit Rp 160,000.00 0.09 - - - - -
JUMLAH PEKERJAAN SUB TOTAL XII Rp 3,800,000.00 2.24 - - -
XIII PEKERJAAN AKHIR
1 Pekerjaan pembersihan lokasi 1.000 LS Rp 500,000.00 0.29 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VI Rp 500,000.00 0.29 - - -
SUB TOTAL #REF! #REF! #REF! #REF! #REF!

Tanjung Balai Karimun, 25 SEPTEMBER 2017

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
LAPORAN PROGRESS MINGGUAN
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG INTANSI MINGGU KE
WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA PEMERINTAH KABUPATEN KARIMUN DINAS 7
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017 PEKERJAAN UMUM DAN PENATAAN RUANG TANGGAL
TANGGAL KONTRAK : 19 OKTOBER 2017 S/D 26-Sep-17
NILAI KONTRAK : Rp. 92.960.000- KONTRAKTOR PELAKSANA TANGGAL 2-Oct-17
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) BULAN KE
CV. PANUTAN JAYA
2 ( Dua )

BOBOT MINGGU INI MINGGU LALU S/D MINGGU INI


NO URAIAN PEKERJAAN
VOLUME SATUAN TOTAL HARGA % VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT

I PEKERJAAN PENDAHULUAN
1 Pekerjaan pas.papan proyek 1.000 Ls Rp 200,000.00 0.12 - 1.00 0.12 1.00 0.12
2 Pekerjaan pembersihan lokasi dan pemasangan bouwplank 1.000 Ls Rp 1,800,000.00 1.06 - 1.00 1.06 1.00 1.06
JUMLAH PEKERJAAN SUB TOTAL I Rp 2,000,000.00 1.18 - 1.18 1.18
II PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi 10.24 m3 Rp 441,548.80 0.26 - 10.24 0.26 10.24 0.26
2 Pek.pemadatan tanah t=52,0.37 & 0.22cm 30.73 m3 Rp 1,656,347.00 0.98 - 30.73 0.98 30.73 0.98
JUMLAH PEKERJAAN SUB TOTAL III Rp 2,097,895.80 1.24 - 1.24 1.24
III PEKERJAAN PONDASI
1 Pondasi Tapak 1 (PT.1)
1 Pek. Urugan Pasir 0.13 m3 Rp 34,720.40 0.02 - 0.13 0.02 0.13 0.02
2 Pek. Beton Lantai Kerja 0.13 m3 Rp 158,291.39 0.09 - 0.13 0.09 0.13 0.09
3 Pek. Pondasi Tapak #DIV/0! - #DIV/0! - #DIV/0!
a. Beton 0.260 m3 Rp 380,314.72 0.22
b. Besi 73.09 kg Rp 887,082.37 0.52 - 73.09 0.52 73.09 0.52
c. Bekesting 4.72 m2 Rp 691,262.88 0.41 - 4.72 0.41 4.72 0.41
4 Pek. Urugan Tanah Kembali 0.50 m3 Rp 10,334.50 0.01 - 0.50 0.01 0.50 0.01

2 Pondasi Tapak 2 (PT.2) #DIV/0! - #DIV/0! - #DIV/0!


1 Pek. Urugan Pasir 0.38 m3 Rp 101,490.40 0.06 - 0.38 0.06 0.38 0.06
2 Pek. Beton Lantai Kerja 0.38 m3 Rp 462,697.91 0.27 - 0.38 0.27 0.38 0.27
3 Pek. Pondasi Tapak
a. Beton 0.77 m3 Rp 1,126,316.67 0.66 - 0.77 0.66 0.77 0.66
b. Besi 211.53 kg Rp 2,567,307.88 1.51 - 211.53 1.51 211.53 1.51
c. Bekesting 10.08 m2 Rp 1,476,256.32 0.87 - 10.08 0.87 10.08 0.87
4 Pek. Urugan Tanah Kembali 1.940 m3 Rp 40,097.86 0.02
JUMLAH PEKERJAAN SUB TOTAL III Rp 7,936,173.30 4.67 #DIV/0! #DIV/0! #DIV/0!
IV PEKERJAAN STRUKTUR
1 Sloof (15x 20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 16.000 m2 Rp 1,789,392.00 1.05
2 Kolom K1 (25 X 25)
- Beton 0.940 m3 Rp 1,374,983.98 0.81
- Pembesian 143.110 kg Rp 1,736,904.60 1.02
- Bekesting 7.540 m2 Rp 963,845.74 0.57
3 Kolom K2 (15 X 15)
- Beton 1.020 m3 Rp 1,492,003.90 0.88
- Pembesian 268.270 kg Rp 3,255,952.75 1.92
- Bekesting 9.050 m2 Rp 1,156,870.55 0.68
4 Balok (20x25)
- Beton 0.270 m3 Rp 394,942.21 0.23
- Pembesian 39.470 kg Rp 479,041.47 0.28
- Bekesting 3.710 m2 Rp 1,531,272.82 0.90
5 Balok B1 (15x20)
- Beton 1.350 m3 Rp 1,974,711.04 1.16
- Pembesian 231.300 kg Rp 2,807,253.41 1.65
- Bekesting 6.190 m2 Rp 2,554,872.98 1.50
6 RB.1 (15x20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 11.000 m2 Rp 4,540,162.00 2.67
7 Ringbalok (15x20)
- beton 0.220 m3 Rp 321,804.76 0.19
- Pembesian 37.010 kg Rp 449,184.82 0.26
- Bekesting 1.320 m2 Rp 544,819.44 0.32
8 Dak beton teras
- beton 2.720 m3 Rp 3,978,677.06 2.34
- Pembesian 225.230 kg Rp 2,733,582.73 1.61
- Bekesting 14.910 m2 Rp 5,930,855.82 3.49 - 14.91 3.49 14.91 3.49
JUMLAH PEKERJAAN SUB TOTAL IV Rp 48,512,404.20 28.57 - 3.49 3.49
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako 103.850 m2 Rp 10,871,744.95 6.40 - 103.85 6.40 103.85 6.40
JUMLAH PEKERJAAN SUB TOTAL V Rp 10,871,744.95 6.40 #REF! 6.40 6.40
VI PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 207.700 m2 Rp 10,540,234.98 6.21 - 207.70 6.21 207.70 6.21
2 Pekerjaan acian 207.700 m2 Rp 7,697,154.30 4.53 - 207.70 4.53 207.70 4.53
JUMLAH PEKERJAAN SUB TOTAL VII Rp 18,237,389.28 10.74 - 10.74 10.74
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pekerjaan rabat beton bawah lantai t = 5 cm 2.590 m2 Rp 3,153,651.55 1.86
2 Pekerjaan pemasangan keramik 40x40 polished 51.870 m2 Rp 12,606,687.09 7.42
3 Pekerjaan pemasangan keramik 40x40 unpolished 14.000 m2 Rp 3,402,614.60 2.00 - 14.00 2.00 14.00 2.00
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 19,162,953.24 11.28 - 2.00 2.00
VIII PEKERJAAN PLAFOND
1 Pek. Pas. plafond gypsumboard + rangka metal furing 56.000 m2 Rp 8,693,916.00 5.12 - 56.00 5.12 56.00 5.12
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 8,693,916.00 5.12 - 5.12 5.12
IX PEKERJAAN PENUTUP ATAP
1 Pekerjaan rangka atap baja ringan 83.950 m2 Rp 15,482,562.70 9.12 - - - - -
2 Pekerjaan pemasangan atap genteng metal 86.960 m2 Rp 10,283,020.00 6.05 - - - - -
3 Pekerjaan pemasangan nok genteng 35.200 m1 Rp 3,309,785.60 1.95
4 Pekerjaan pemasangan lisplank GRC 33.000 m1 Rp 2,556,246.00 1.51 - 33.00 1.51 33.00 1.51
JUMLAH PEKERJAAN SUB TOTAL IX Rp 31,631,614.30 18.63 - 1.51 1.51
X PEKERJAAN PINTU JENDELA
1 Pemasangan pintu almunium P1 2.000 unit Rp 5,769,584.92 3.40 - 2.00 3.40 2.00 3.40
2 Pemasangan jendela almunium J1 1.000 unit Rp 2,535,043.42 1.49 - 1.00 1.49 1.00 1.49
3 Pemasangan jendela almunium J2 6.000 unit Rp 7,378,575.06 4.34 - 6.00 4.34 6.00 4.34
4 Pemasangan rooster R1 28.000 unit Rp 700,000.00 0.41 - 28.00 0.41 28.00 0.41
JUMLAH PEKERJAAN SUB TOTAL XI Rp 16,383,203.40 9.65 - 9.65 9.65
XI PEKERJAAN ELEKTRIKAL
1 Instalasi titik lampu 14.000 titik Rp 2,380,000.00 1.40 14.00 1.40 - - 14.00 1.40
2 Pemasangan lampu SL LED 13 Watt downlight 4.000 titik Rp 580,000.00 0.34 4.00 0.34 - - 4.00 0.34
3 Pemasangan lampu LED 7 Watt downlight 3.000 titik Rp 420,000.00 0.25
4 Pemasangan saklar tunggal 3.000 titik Rp 120,000.00 0.07
5 Pemasangan saklar ganda 1.000 titik Rp 50,000.00 0.03
6 Pemasangan stop kontak 2.000 titik Rp 90,000.00 0.05
7 pemasangan box sekering 1.000 unit Rp 160,000.00 0.09 1.00 0.09 - - 1.00 0.09
JUMLAH PEKERJAAN SUB TOTAL XII Rp 3,800,000.00 2.24 1.84 - 1.84
XIII PEKERJAAN AKHIR
1 Pekerjaan pembersihan lokasi 1.000 LS Rp 500,000.00 0.29 - - - - -
JUMLAH PEKERJAAN SUB TOTAL VI Rp 500,000.00 0.29 - - -
SUB TOTAL #REF! #REF! #REF! #REF! #REF!

Tanjung Balai Karimun, 02 OKTOBER 2017

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
LAPORAN PROGRESS MINGGUAN
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG INTANSI MINGGU KE
WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA PEMERINTAH KABUPATEN KARIMUN DINAS 8
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017 PEKERJAAN UMUM DAN PENATAAN RUANG TANGGAL
TANGGAL KONTRAK : 19 OKTOBER 2017 S/D 3-Oct-17
NILAI KONTRAK : Rp. 92.960.000- KONTRAKTOR PELAKSANA TANGGAL 9-Oct-17
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) BULAN KE
CV. PANUTAN JAYA
2 ( Dua )

BOBOT MINGGU INI MINGGU LALU S/D MINGGU INI


NO URAIAN PEKERJAAN
VOLUME SATUAN TOTAL HARGA % VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT

I PEKERJAAN PENDAHULUAN
1 Pekerjaan pas.papan proyek 1.000 Ls Rp 200,000.00 0.12 - 1.00 0.12 1.00 0.12
2 Pekerjaan pembersihan lokasi dan pemasangan bouwplank 1.000 Ls Rp 1,800,000.00 1.06 - 1.00 1.06 1.00 1.06
JUMLAH PEKERJAAN SUB TOTAL I Rp 2,000,000.00 1.18 - 1.18 1.18
II PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi 10.24 m3 Rp 441,548.80 0.26 - 10.24 0.26 10.24 0.26
2 Pek.pemadatan tanah t=52,0.37 & 0.22cm 30.73 m3 Rp 1,656,347.00 0.98 - 30.73 0.98 30.73 0.98
JUMLAH PEKERJAAN SUB TOTAL III Rp 2,097,895.80 1.24 - 1.24 1.24
III PEKERJAAN PONDASI
1 Pondasi Tapak 1 (PT.1)
1 Pek. Urugan Pasir 0.13 m3 Rp 34,720.40 0.02 - 0.13 0.02 0.13 0.02
2 Pek. Beton Lantai Kerja 0.13 m3 Rp 158,291.39 0.09 - 0.13 0.09 0.13 0.09
3 Pek. Pondasi Tapak #DIV/0! - #DIV/0! - #DIV/0!
a. Beton 0.260 m3 Rp 380,314.72 0.22
b. Besi 73.09 kg Rp 887,082.37 0.52 - 73.09 0.52 73.09 0.52
c. Bekesting 4.72 m2 Rp 691,262.88 0.41 - 4.72 0.41 4.72 0.41
4 Pek. Urugan Tanah Kembali 0.50 m3 Rp 10,334.50 0.01 - 0.50 0.01 0.50 0.01

2 Pondasi Tapak 2 (PT.2) #DIV/0! - #DIV/0! - #DIV/0!


1 Pek. Urugan Pasir 0.38 m3 Rp 101,490.40 0.06 - 0.38 0.06 0.38 0.06
2 Pek. Beton Lantai Kerja 0.38 m3 Rp 462,697.91 0.27 - 0.38 0.27 0.38 0.27
3 Pek. Pondasi Tapak
a. Beton 0.77 m3 Rp 1,126,316.67 0.66 - 0.77 0.66 0.77 0.66
b. Besi 211.53 kg Rp 2,567,307.88 1.51 - 211.53 1.51 211.53 1.51
c. Bekesting 10.08 m2 Rp 1,476,256.32 0.87 - 10.08 0.87 10.08 0.87
4 Pek. Urugan Tanah Kembali 1.940 m3 Rp 40,097.86 0.02
JUMLAH PEKERJAAN SUB TOTAL III Rp 7,936,173.30 4.67 #DIV/0! #DIV/0! #DIV/0!
IV PEKERJAAN STRUKTUR
1 Sloof (15x 20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 16.000 m2 Rp 1,789,392.00 1.05
2 Kolom K1 (25 X 25)
- Beton 0.940 m3 Rp 1,374,983.98 0.81
- Pembesian 143.110 kg Rp 1,736,904.60 1.02
- Bekesting 7.540 m2 Rp 963,845.74 0.57
3 Kolom K2 (15 X 15)
- Beton 1.020 m3 Rp 1,492,003.90 0.88
- Pembesian 268.270 kg Rp 3,255,952.75 1.92
- Bekesting 9.050 m2 Rp 1,156,870.55 0.68
4 Balok (20x25)
- Beton 0.270 m3 Rp 394,942.21 0.23
- Pembesian 39.470 kg Rp 479,041.47 0.28
- Bekesting 3.710 m2 Rp 1,531,272.82 0.90
5 Balok B1 (15x20)
- Beton 1.350 m3 Rp 1,974,711.04 1.16
- Pembesian 231.300 kg Rp 2,807,253.41 1.65
- Bekesting 6.190 m2 Rp 2,554,872.98 1.50
6 RB.1 (15x20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 11.000 m2 Rp 4,540,162.00 2.67
7 Ringbalok (15x20)
- beton 0.220 m3 Rp 321,804.76 0.19
- Pembesian 37.010 kg Rp 449,184.82 0.26
- Bekesting 1.320 m2 Rp 544,819.44 0.32
8 Dak beton teras
- beton 2.720 m3 Rp 3,978,677.06 2.34
- Pembesian 225.230 kg Rp 2,733,582.73 1.61
- Bekesting 14.910 m2 Rp 5,930,855.82 3.49 - 14.91 3.49 14.91 3.49
JUMLAH PEKERJAAN SUB TOTAL IV Rp 48,512,404.20 28.57 - 3.49 3.49
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako 103.850 m2 Rp 10,871,744.95 6.40 - 103.85 6.40 103.85 6.40
JUMLAH PEKERJAAN SUB TOTAL V Rp 10,871,744.95 6.40 #REF! 6.40 6.40
VI PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 207.700 m2 Rp 10,540,234.98 6.21 - 207.70 6.21 207.70 6.21
2 Pekerjaan acian 207.700 m2 Rp 7,697,154.30 4.53 - 207.70 4.53 207.70 4.53
JUMLAH PEKERJAAN SUB TOTAL VII Rp 18,237,389.28 10.74 - 10.74 10.74
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pekerjaan rabat beton bawah lantai t = 5 cm 2.590 m2 Rp 3,153,651.55 1.86
2 Pekerjaan pemasangan keramik 40x40 polished 51.870 m2 Rp 12,606,687.09 7.42
3 Pekerjaan pemasangan keramik 40x40 unpolished 14.000 m2 Rp 3,402,614.60 2.00 - 14.00 2.00 14.00 2.00
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 19,162,953.24 11.28 - 2.00 2.00
VIII PEKERJAAN PLAFOND
1 Pek. Pas. plafond gypsumboard + rangka metal furing 56.000 m2 Rp 8,693,916.00 5.12 - 56.00 5.12 56.00 5.12
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 8,693,916.00 5.12 - 5.12 5.12
IX PEKERJAAN PENUTUP ATAP
1 Pekerjaan rangka atap baja ringan 83.950 m2 Rp 15,482,562.70 9.12 83.950 9.12 - - 83.95 9.12
2 Pekerjaan pemasangan atap genteng metal 86.960 m2 Rp 10,283,020.00 6.05 86.96 6.05 - - 86.96 6.05
3 Pekerjaan pemasangan nok genteng 35.200 m1 Rp 3,309,785.60 1.95
4 Pekerjaan pemasangan lisplank GRC 33.000 m1 Rp 2,556,246.00 1.51 - 33.00 1.51 33.00 1.51
JUMLAH PEKERJAAN SUB TOTAL IX Rp 31,631,614.30 18.63 15.17 1.51 16.68
X PEKERJAAN PINTU JENDELA
1 Pemasangan pintu almunium P1 2.000 unit Rp 5,769,584.92 3.40 - 2.00 3.40 2.00 3.40
2 Pemasangan jendela almunium J1 1.000 unit Rp 2,535,043.42 1.49 - 1.00 1.49 1.00 1.49
3 Pemasangan jendela almunium J2 6.000 unit Rp 7,378,575.06 4.34 - 6.00 4.34 6.00 4.34
4 Pemasangan rooster R1 28.000 unit Rp 700,000.00 0.41 - 28.00 0.41 28.00 0.41
JUMLAH PEKERJAAN SUB TOTAL XI Rp 16,383,203.40 9.65 - 9.65 9.65
XI PEKERJAAN ELEKTRIKAL
1 Instalasi titik lampu 14.000 titik Rp 2,380,000.00 1.40 - 14.00 1.40 14.00 1.40
2 Pemasangan lampu SL LED 13 Watt downlight 4.000 titik Rp 580,000.00 0.34 - 4.00 0.34 4.00 0.34
3 Pemasangan lampu LED 7 Watt downlight 3.000 titik Rp 420,000.00 0.25
4 Pemasangan saklar tunggal 3.000 titik Rp 120,000.00 0.07
5 Pemasangan saklar ganda 1.000 titik Rp 50,000.00 0.03
6 Pemasangan stop kontak 2.000 titik Rp 90,000.00 0.05
7 pemasangan box sekering 1.000 unit Rp 160,000.00 0.09 - 1.00 0.09 1.00 0.09
JUMLAH PEKERJAAN SUB TOTAL XII Rp 3,800,000.00 2.24 - 1.84 1.84
XIII PEKERJAAN AKHIR
1 Pekerjaan pembersihan lokasi 1.000 LS Rp 500,000.00 0.29 1.000 0.29 - - 1.00 0.29
JUMLAH PEKERJAAN SUB TOTAL VI Rp 500,000.00 0.29 0.29 - 0.29
SUB TOTAL #REF! #REF! #REF! #REF! #REF!

Tanjung Balai Karimun, 09 OKTOBER 2017

DI Ketahui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. PANUTAN JAYA
PEJABAT PELAKSANA TEKNIS KEGIATAN ( PPTK )

AZRIE IRAWAN ARIF KUSHARYADI SYAMSUL BAHRI, ST


Nip. 19810317 201001 1 006 INSPECTOR PPENANGGUNG JAWAB LAPANGAN
BULAN KE : INSTANSI

1
REKAPITULASI BULANAN KEMAJUAN
TANGGAL : PEMERINTAH KABUPATEN KARIMUN DINAS
PROGRES PEKERJAAN 15 AGUSTUS 2017 S/D PEKERJAAN UMUM DAN PENATAAN RUANG
21
AGUSTUS 2017
KEGIATAN : KONTRAKTOR PELAKSANA
PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA
RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN
TEBING
CV. PANUTAN JAYA
PEKERJAAN : BELANJA PEMBANGUNAN MASJID PULAU SETUNAK KECAMATAN KARIMUN
NO KONTRAK : 2/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 15 Agustus 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 186.180.000-
WAKTU PELAKSANAAN : 60 HK ( ENAM PULUH HARI KALENDER ) CV. ASKA PERKASA KONSULATAN

TAHAP TAHAP PERSENTASE


PENYELESAIAN PENYELESAIAN JUMLAH BOBOT PENYELESAIAN
TOTAL PEKERJAAN BULAN PEKERJAAN BULAN S/D BULAN INI TERHADAP ITEM
NO. URAIAN PEKERJAAN JUMLAH HARGA
BOBOT INI LALU PEKERJAAN

BOBOT BOBOT BOBOT %

I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 #NAME?


#NAME? 1.18 - 1.18 #NAME?

IVIII PEKERJAAN TANAH Rp 2,097,895.80 #NAME?


#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
IV PEKERJAAN PONDASI Rp 7,936,173.30 #NAME?
#NAME? #NAME? #DIV/0! #DIV/0!
- #DIV/0!
V PEKERJAAN STRUKTUR Rp 48,512,404.20 #NAME?
#NAME? 3.49 - 3.49- #NAME?

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 #NAME?


#NAME? #NAME? #DIV/0! #DIV/0!
- #DIV/0!
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 #NAME?
#NAME? - - -- #NAME?
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 #NAME?
#NAME? - - -- #NAME?
IX PEKERJAAN PLAFOND Rp 8,693,916.00 #NAME?
#NAME? 5.12 - 5.12 #NAME?
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 #NAME?
#NAME? - - -- #NAME?
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 #NAME?
#NAME? - - -- #NAME?
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 #NAME? - - - #NAME?

XIII #NAME? #NAME? #NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!


XIII PEKERJAAN AKHIR Rp 500,000.00 #NAME? - - - #NAME?
a JUMLAH #NAME? #NAME? #NAME? #DIV/0! #DIV/0!
b Realisasi Rencana Minggu Ini
c Realisasi Tercapai Minggu Ini #DIV/0!
d Deviasi #DIV/0!

DI Setujui Oleh ; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. PANUTAN JAYA
PEJABAT PEMBUAT KOMITMEN ( PPK )

HIKMA DINI FAHMI,ST SUDIRMAN


NIP. 19790611 200904 2 003 Direktur

Di Periksa Oleh;
KONSULTAN PENGAWAS
CV. ASKA PERKASA KONSULTAN

AHMAD MUDA BAHRI, ST


Supervisi Engineer
BULAN KE : INSTANSI

2
REKAPITULASI BULANAN KEMAJUAN
TANGGAL : PEMERINTAH KABUPATEN KARIMUN DINAS
PROGRES PEKERJAAN 12 SEPTEMBER 2017 S/D PEKERJAAN UMUM DAN PENATAAN RUANG
28
AGUSTUS 2017
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA KONTRAKTOR PELAKSANA
RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN
TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA CV. PANUTAN JAYA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
60 HK ( ENAM PULUH HARI
WAKTU PELAKSANAAN :
KALENDER )
CV. ASKA PERKASA KONSULATAN

TAHAP TAHAP PERSENTASE


PENYELESAIAN PENYELESAIAN JUMLAH BOBOT PENYELESAIAN
TOTAL PEKERJAAN BULAN PEKERJAAN BULAN S/D BULAN INI TERHADAP ITEM
NO. URAIAN PEKERJAAN JUMLAH HARGA
BOBOT INI LALU PEKERJAAN

BOBOT BOBOT BOBOT %

I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 #NAME? - 1.18 1.18 #NAME?

IVIII PEKERJAAN TANAH Rp 2,097,895.80 #NAME? #NAME? #NAME? #NAME? #NAME?


IV PEKERJAAN PONDASI Rp 7,936,173.30 #NAME? #NAME? #NAME? #NAME?
- #NAME?
V PEKERJAAN STRUKTUR Rp 48,512,404.20 #NAME? - 3.49 3.49- #NAME?

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 #NAME?


#NAME? #NAME? #NAME? #NAME?
- #NAME?
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 #NAME?
#NAME? #NAME? - #NAME?
- #NAME?
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 #NAME?
#NAME? 2.00 - 2.00- #NAME?
IX PEKERJAAN PLAFOND Rp 8,693,916.00 #NAME?
#NAME? - 5.12 5.12 #NAME?
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 #NAME?
#NAME? 16.68 - 16.68- #NAME?
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 #NAME?
#NAME? #NAME? - #NAME?
- #NAME?
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 #NAME? 1.84 - 1.84 #NAME?

XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?


XIII PEKERJAAN AKHIR Rp 500,000.00 #NAME? 0.29 - 0.29 #NAME?
a JUMLAH #NAME? #NAME? #NAME? #NAME? #NAME?
b Realisasi Rencana Minggu Ini
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Setujui Oleh ; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. PANUTAN JAYA
PEJABAT PEMBUAT KOMITMEN ( PPK )

HIKMA DINI FAHMI,ST SUDIRMAN


NIP. 19790611 200904 2 003 Direktur

Di Periksa Oleh;
KONSULTAN PENGAWAS
CV. ASKA PERKASA KONSULTAN

AHMAD MUDA BAHRI, ST


Supervisi Engineer
BULAN KE : INSTANSI

3
REKAPITULASI BULANAN KEMAJUAN
TANGGAL : PEMERINTAH KABUPATEN KARIMUN DINAS
PROGRES PEKERJAAN 10 OKTOBER 2017 S/D PEKERJAAN UMUM DAN PENATAAN RUANG
04
SEPTEMBER 2017
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA KONTRAKTOR PELAKSANA
RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN
TEBING
PEKERJAAN : PEMBANGUNAN TEMPAT WUDHU MASJID NURUL TAQWA CV. PANUTAN JAYA
NO KONTRAK : 72/SPK/FASUM-PK/TR/DPUPR/APBD-P/2017
TANGGAL KONTRAK : 19 OKTOBER 2017 KONSULTAN PENGAWAS
NILAI KONTRAK : Rp. 92.960.000-
60 HK ( ENAM PULUH HARI
WAKTU PELAKSANAAN :
KALENDER )
CV. ASKA PERKASA KONSULATAN

TAHAP TAHAP PERSENTASE


PENYELESAIAN PENYELESAIAN JUMLAH BOBOT PENYELESAIAN
TOTAL PEKERJAAN BULAN PEKERJAAN BULAN S/D BULAN INI TERHADAP ITEM
NO. URAIAN PEKERJAAN JUMLAH HARGA
BOBOT INI LALU PEKERJAAN

BOBOT BOBOT BOBOT %

I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 #NAME? - 1.18 1.18 #NAME?

IVIII PEKERJAAN TANAH Rp 2,097,895.80 #NAME? #NAME? #NAME? #NAME? #NAME?


IV PEKERJAAN PONDASI Rp 7,936,173.30 #NAME? #NAME? #NAME? #NAME?
- #NAME?
V PEKERJAAN STRUKTUR Rp 48,512,404.20 #NAME? - 3.49 3.49- #NAME?

VIVI PEKERJAAN PASANGAN DINDING Rp 10,871,744.95 #NAME?


#NAME? #NAME? #NAME? #NAME?
- #NAME?
VII PEKERJAAN PLESTERAN Rp 18,237,389.28 #NAME?
#NAME? #NAME? - #NAME?
- #NAME?
VIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING Rp 19,162,953.24 #NAME?
#NAME? - 2.00 2.00- #NAME?
IX PEKERJAAN PLAFOND Rp 8,693,916.00 #NAME?
#NAME? - 5.12 5.12 #NAME?
X PEKERJAAN PENUTUP ATAP Rp 31,631,614.30 #NAME?
#NAME? 15.17 - 15.17- #NAME?
XI PEKERJAAN PINTU JENDELA Rp 16,383,203.40 #NAME?
#NAME? #NAME? - #NAME?
- #NAME?
XII PEKERJAAN ELEKTRIKAL Rp 3,800,000.00 #NAME? - 1.84 1.84 #NAME?

XIII #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?


XIII PEKERJAAN AKHIR Rp 500,000.00 #NAME? 0.29 0.29 0.59 #NAME?
a JUMLAH #NAME? #NAME? #NAME? #NAME? #NAME?
b Realisasi Rencana Minggu Ini
c Realisasi Tercapai Minggu Ini #NAME?
d Deviasi #NAME?

DI Setujui Oleh ; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. PANUTAN JAYA
PEJABAT PEMBUAT KOMITMEN ( PPK )

HIKMA DINI FAHMI,ST SUDIRMAN


NIP. 19790611 200904 2 003 Direktur

Di Periksa Oleh;
KONSULTAN PENGAWAS
CV. ASKA PERKASA KONSULTAN

AHMAD MUDA BAHRI, ST


Supervisi Engineer
LAPORAN BULANAN KEMAJUAN PEKERJAAN
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG INTANSI BULAN KE
WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING PEMERINTAH KABUPATEN KARIMUN 1
PEKERJAAN : REHABILITASI BALAI DESA BUKIT SIDOMULYO I KEL. TANJUNG BALAI KEC.KARIMUN DINAS PEKERJAAN UMUM DAN TANGGAL
NO KONTRAK : 21/SPK/FASUM-PK/TR/DPUPR/2017 PENATAAN RUANG S/D 15-Aug-17
TANGGAL KONTRAK : 15 AGUSTUS 2017 KONTRAKTOR PELAKSANA TANGGAL 11-Sep-17
NILAI KONTRAK : Rp. 140.260.000- MINGGU
WAKTU PELAKSANAAN : 90 HK ( Sembilan Puluh Hari Kalender )
CV. SIDAN JAYA
1, 2, 3, 4

PERSENTASE
TAHAP PENYELESAIAN
TAHAP PENYELESAIAN PENYELESAIAN
ADDENDUM BOBOT PEKERJAAN BULAN
PEKERJAAN BULAN INI TERHADAP ITEM
NO URAIAN PEKERJAAN LALU
PEKERJAAN

VOLUME Jumlah
SATUAN TOTAL HARGA VOLUME BOBOT VOLUME BOBOT %
KONTRAK Bobot
I PEKERJAAN PENDAHULUAN
1 Pekerjaan pas.papan proyek 1.000 Ls Rp 200,000.00 0.12 1.00 0.12 - 0.12 100%
2 Pekerjaan pembersihan lokasi dan pemasangan bouwplank 1.000 Ls Rp 1,800,000.00 1.06 1.00 1.06 - 1.06 100%
JUMLAH PEKERJAAN SUB TOTAL I Rp 2,000,000.00 1.18 1.18 - 1.18
II PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi 10.24 m3 Rp 441,548.80 0.26 10.24 0.26 - 0.26 100%
2 Pek.pemadatan tanah t=52,0.37 & 0.22cm 30.73 m3 Rp 1,656,347.00 0.98 30.73 0.98 - 0.98 100%
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!

#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!


#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
JUMLAH PEKERJAAN SUB TOTAL III Rp 2,097,895.80 1.24 #NAME? #DIV/0! #DIV/0!
III PEKERJAAN PONDASI
1 Pondasi Tapak 1 (PT.1)
1 Pek. Urugan Pasir 0.13 m3 Rp 34,720.40 0.02 0.13 0.02 - 0.02 100%
2 Pek. Beton Lantai Kerja 0.13 m3 Rp 158,291.39 0.09 0.13 0.09 - 0.09 100%
3 Pek. Pondasi Tapak - #DIV/0! #DIV/0! #DIV/0! #DIV/0!
a. Beton 0.260 m3 Rp 380,314.72 0.22
b. Besi 73.09 kg Rp 887,082.37 0.52 73.09 0.52 - 0.52 100%
c. Bekesting 4.72 m2 Rp 691,262.88 0.41 4.72 0.41 - 0.41 100%
4 Pek. Urugan Tanah Kembali 0.50 m3 Rp 10,334.50 0.01 0.50 0.01 - 0.01 100%

2 Pondasi Tapak 2 (PT.2) - #DIV/0! #DIV/0! #DIV/0! #DIV/0!


1 Pek. Urugan Pasir 0.38 m3 Rp 101,490.40 0.06 0.38 0.06 - 0.06 100%
2 Pek. Beton Lantai Kerja 0.38 m3 Rp 462,697.91 0.27 0.38 0.27 - 0.27 100%
3 Pek. Pondasi Tapak
a. Beton 0.77 m3 Rp 1,126,316.67 0.66 0.77 0.66 - 0.66 100%
b. Besi 211.53 kg Rp 2,567,307.88 1.51 211.53 1.51 - 1.51 100%
c. Bekesting 10.08 m2 Rp 1,476,256.32 0.87 10.08 0.87 - 0.87 100%
4 Pek. Urugan Tanah Kembali 1.940 m3 Rp 40,097.86 0.02
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
JUMLAH PEKERJAAN SUB TOTAL III Rp 7,936,173.30 4.67 #NAME? #DIV/0! #DIV/0!
IV PEKERJAAN STRUKTUR
1 Sloof (15x 20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 16.000 m2 Rp 1,789,392.00 1.05
2 Kolom K1 (25 X 25)
- Beton 0.940 m3 Rp 1,374,983.98 0.81
- Pembesian 143.110 kg Rp 1,736,904.60 1.02
- Bekesting 7.540 m2 Rp 963,845.74 0.57
3 Kolom K2 (15 X 15)
- Beton 1.020 m3 Rp 1,492,003.90 0.88
- Pembesian 268.270 kg Rp 3,255,952.75 1.92
- Bekesting 9.050 m2 Rp 1,156,870.55 0.68
4 Balok (20x25)
- Beton 0.270 m3 Rp 394,942.21 0.23
- Pembesian 39.470 kg Rp 479,041.47 0.28
- Bekesting 3.710 m2 Rp 1,531,272.82 0.90
5 Balok B1 (15x20)
- Beton 1.350 m3 Rp 1,974,711.04 1.16
- Pembesian 231.300 kg Rp 2,807,253.41 1.65
- Bekesting 6.190 m2 Rp 2,554,872.98 1.50
6 RB.1 (15x20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 11.000 m2 Rp 4,540,162.00 2.67
7 Ringbalok (15x20)
- beton 0.220 m3 Rp 321,804.76 0.19
- Pembesian 37.010 kg Rp 449,184.82 0.26
- Bekesting 1.320 m2 Rp 544,819.44 0.32
8 Dak beton teras
- beton 2.720 m3 Rp 3,978,677.06 2.34
- Pembesian 225.230 kg Rp 2,733,582.73 1.61
- Bekesting 14.910 m2 Rp 5,930,855.82 3.49 14.91 3.49 - 3.49 100%
JUMLAH PEKERJAAN SUB TOTAL IV Rp 48,512,404.20 28.57 3.49 - 3.49
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako 103.850 m2 Rp 10,871,744.95 6.40 - - - - 0%
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
JUMLAH PEKERJAAN SUB TOTAL V Rp 10,871,744.95 6.40 #NAME? #DIV/0! #DIV/0!
VI PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 207.700 m2 Rp 10,540,234.98 6.21 - - - - 0%
2 Pekerjaan acian 207.700 m2 Rp 7,697,154.30 4.53 - - - - 0%
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
JUMLAH PEKERJAAN SUB TOTAL VII Rp 18,237,389.28 10.74 #NAME? #DIV/0! #DIV/0!
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pekerjaan rabat beton bawah lantai t = 5 cm 2.590 m2 Rp 3,153,651.55 1.86
2 Pekerjaan pemasangan keramik 40x40 polished 51.870 m2 Rp 12,606,687.09 7.42
3 Pekerjaan pemasangan keramik 40x40 unpolished 14.000 m2 Rp 3,402,614.60 2.00 - - - - 0%
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 19,162,953.24 11.28 - - -
VIII PEKERJAAN PLAFOND
1 Pek. Pas. plafond gypsumboard + rangka metal furing 56.000 m2 Rp 8,693,916.00 5.12 56.00 5.12 - 5.12 100%
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 8,693,916.00 5.12 5.12 - 5.12
IX PEKERJAAN PENUTUP ATAP
1 Pekerjaan rangka atap baja ringan 83.950 m2 Rp 15,482,562.70 9.12 - - - - 0%
2 Pekerjaan pemasangan atap genteng metal 86.960 m2 Rp 10,283,020.00 6.05 - - - - 0%
3 Pekerjaan pemasangan nok genteng 35.200 m1 Rp 3,309,785.60 1.95
4 Pekerjaan pemasangan lisplank GRC 33.000 m1 Rp 2,556,246.00 1.51 - - - - 0%
JUMLAH PEKERJAAN SUB TOTAL IX Rp 31,631,614.30 18.63 - - -
X PEKERJAAN PINTU JENDELA
1 Pemasangan pintu almunium P1 2.000 unit Rp 5,769,584.92 3.40 - - - - 0%
2 Pemasangan jendela almunium J1 1.000 unit Rp 2,535,043.42 1.49 - - - - 0%
3 Pemasangan jendela almunium J2 6.000 unit Rp 7,378,575.06 4.34 - - - - 0%
4 Pemasangan rooster R1 28.000 unit Rp 700,000.00 0.41 - - - - 0%
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
JUMLAH PEKERJAAN SUB TOTAL XI Rp 16,383,203.40 9.65 - - -
XI PEKERJAAN ELEKTRIKAL
1 Instalasi titik lampu 14.000 titik Rp 2,380,000.00 1.40 - - - - 0%
2 Pemasangan lampu SL LED 13 Watt downlight 4.000 titik Rp 580,000.00 0.34 - - - - 0%
3 Pemasangan lampu LED 7 Watt downlight 3.000 titik Rp 420,000.00 0.25
4 Pemasangan saklar tunggal 3.000 titik Rp 120,000.00 0.07
5 Pemasangan saklar ganda 1.000 titik Rp 50,000.00 0.03
6 Pemasangan stop kontak 2.000 titik Rp 90,000.00 0.05
7 pemasangan box sekering 1.000 unit Rp 160,000.00 0.09 - - - - 0%
JUMLAH PEKERJAAN SUB TOTAL XII Rp 3,800,000.00 2.24 - - -

#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!


#NAME? #NAME? #DIV/0! #DIV/0! #DIV/0!
#NAME? #DIV/0! #DIV/0!
XIII PEKERJAAN AKHIR
1 Pekerjaan pembersihan lokasi 1.000 LS Rp 500,000.00 0.29 - - - - 0%
JUMLAH PEKERJAAN SUB TOTAL VI Rp 500,000.00 0.29 - - -
SUB TOTAL Rp 169,827,294.47 100.00 #NAME? #DIV/0! #DIV/0!

Tanjung Balai Karimun, 11 SEPTEMBER 2017

DI Setujui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. SIDAN JAYA
PEJABAT PEMBUAT KOMITMEN ( PPK )

HIKMA DINI FAHMI,ST AHMAD MUDA BAHRI, ST SUDIRMAN


NIP. 19790611 200904 2 003 Supervisi Engineer Direktur
LAPORAN BULANAN KEMAJUAN PEKERJAAN
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG INTANSI BULAN KE
WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING PEMERINTAH KABUPATEN KARIMUN 2
PEKERJAAN : REHABILITASI BALAI DESA BUKIT SIDOMULYO I KEL. TANJUNG BALAI KEC.KARIMUN DINAS PEKERJAAN UMUM DAN TANGGAL
NO KONTRAK : 21/SPK/FASUM-PK/TR/DPUPR/2017 PENATAAN RUANG S/D 12-Sep-17
TANGGAL KONTRAK : 15 AGUSTUS 2017 KONTRAKTOR PELAKSANA TANGGAL 9-Oct-17
NILAI KONTRAK : Rp. 140.260.000- MINGGU
WAKTU PELAKSANAAN : 90 HK ( Sembilan Puluh Hari Kalender )
CV. SIDAN JAYA
5. 6, 7, 8

PERSENTASE
TAHAP PENYELESAIAN
TAHAP PENYELESAIAN PENYELESAIAN
ADDENDUM BOBOT PEKERJAAN BULAN
PEKERJAAN BULAN INI TERHADAP ITEM
NO URAIAN PEKERJAAN LALU
PEKERJAAN

VOLUME Jumlah
SATUAN TOTAL HARGA VOLUME BOBOT VOLUME BOBOT %
KONTRAK Bobot
I PEKERJAAN PENDAHULUAN
1 Pekerjaan pas.papan proyek 1.000 Ls Rp 200,000.00 0.12 - - 1.00 0.12 0.12 100%
2 Pekerjaan pembersihan lokasi dan pemasangan bouwplank 1.000 Ls Rp 1,800,000.00 1.06 - - 1.00 1.06 1.06 100%
JUMLAH PEKERJAAN SUB TOTAL I Rp 2,000,000.00 1.18 - 1.18 1.18
II PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi 10.24 m3 Rp 441,548.80 0.26 - - 10.24 0.26 0.26 100%
2 Pek.pemadatan tanah t=52,0.37 & 0.22cm 30.73 m3 Rp 1,656,347.00 0.98 - - 30.73 0.98 0.98 100%
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
JUMLAH PEKERJAAN SUB TOTAL III Rp 2,097,895.80 1.24 #NAME? #NAME? #NAME?
III PEKERJAAN PONDASI
1 Pondasi Tapak 1 (PT.1)
1 Pek. Urugan Pasir 0.13 m3 Rp 34,720.40 0.02 - - 0.13 0.02 0.02 100%
2 Pek. Beton Lantai Kerja 0.13 m3 Rp 158,291.39 0.09 - - 0.13 0.09 0.09 100%
3 Pek. Pondasi Tapak - #DIV/0! - #DIV/0! #DIV/0! #DIV/0!
a. Beton 0.260 m3 Rp 380,314.72 0.22
b. Besi 73.09 kg Rp 887,082.37 0.52 - - 73.09 0.52 0.52 100%
c. Bekesting 4.72 m2 Rp 691,262.88 0.41 - - 4.72 0.41 0.41 100%
4 Pek. Urugan Tanah Kembali 0.50 m3 Rp 10,334.50 0.01 - - 0.50 0.01 0.01 100%

2 Pondasi Tapak 2 (PT.2) - #DIV/0! - #DIV/0! #DIV/0! #DIV/0!


1 Pek. Urugan Pasir 0.38 m3 Rp 101,490.40 0.06 - - 0.38 0.06 0.06 100%
2 Pek. Beton Lantai Kerja 0.38 m3 Rp 462,697.91 0.27 - - 0.38 0.27 0.27 100%
3 Pek. Pondasi Tapak
a. Beton 0.77 m3 Rp 1,126,316.67 0.66 - - 0.77 0.66 0.66 100%
b. Besi 211.53 kg Rp 2,567,307.88 1.51 - - 211.53 1.51 1.51 100%
c. Bekesting 10.08 m2 Rp 1,476,256.32 0.87 - - 10.08 0.87 0.87 100%
4 Pek. Urugan Tanah Kembali 1.940 m3 Rp 40,097.86 0.02
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
JUMLAH PEKERJAAN SUB TOTAL III Rp 7,936,173.30 4.67 #NAME? #NAME? #NAME?
IV PEKERJAAN STRUKTUR
1 Sloof (15x 20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 16.000 m2 Rp 1,789,392.00 1.05
2 Kolom K1 (25 X 25)
- Beton 0.940 m3 Rp 1,374,983.98 0.81
- Pembesian 143.110 kg Rp 1,736,904.60 1.02
- Bekesting 7.540 m2 Rp 963,845.74 0.57
3 Kolom K2 (15 X 15)
- Beton 1.020 m3 Rp 1,492,003.90 0.88
- Pembesian 268.270 kg Rp 3,255,952.75 1.92
- Bekesting 9.050 m2 Rp 1,156,870.55 0.68
4 Balok (20x25)
- Beton 0.270 m3 Rp 394,942.21 0.23
- Pembesian 39.470 kg Rp 479,041.47 0.28
- Bekesting 3.710 m2 Rp 1,531,272.82 0.90
5 Balok B1 (15x20)
- Beton 1.350 m3 Rp 1,974,711.04 1.16
- Pembesian 231.300 kg Rp 2,807,253.41 1.65
- Bekesting 6.190 m2 Rp 2,554,872.98 1.50
6 RB.1 (15x20)
- Beton 1.200 m3 Rp 1,755,298.70 1.03
- Pembesian 205.600 kg Rp 2,495,336.36 1.47
- Bekesting 11.000 m2 Rp 4,540,162.00 2.67
7 Ringbalok (15x20)
- beton 0.220 m3 Rp 321,804.76 0.19
- Pembesian 37.010 kg Rp 449,184.82 0.26
- Bekesting 1.320 m2 Rp 544,819.44 0.32
8 Dak beton teras
- beton 2.720 m3 Rp 3,978,677.06 2.34
- Pembesian 225.230 kg Rp 2,733,582.73 1.61
- Bekesting 14.910 m2 Rp 5,930,855.82 3.49 - - 14.91 3.49 3.49 100%
JUMLAH PEKERJAAN SUB TOTAL IV Rp 48,512,404.20 28.57 - 3.49 3.49
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako 103.850 m2 Rp 10,871,744.95 6.40 103.85 6.40 - - 6.40 100%
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
JUMLAH PEKERJAAN SUB TOTAL V Rp 10,871,744.95 6.40 #NAME? #NAME? #NAME?
VI PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 207.700 m2 Rp 10,540,234.98 6.21 207.70 6.21 - - 6.21 100%
2 Pekerjaan acian 207.700 m2 Rp 7,697,154.30 4.53 207.70 4.53 - - 4.53 100%
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
JUMLAH PEKERJAAN SUB TOTAL VII Rp 18,237,389.28 10.74 #NAME? #NAME? #NAME?
VII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 Pekerjaan rabat beton bawah lantai t = 5 cm 2.590 m2 Rp 3,153,651.55 1.86
2 Pekerjaan pemasangan keramik 40x40 polished 51.870 m2 Rp 12,606,687.09 7.42
3 Pekerjaan pemasangan keramik 40x40 unpolished 14.000 m2 Rp 3,402,614.60 2.00 14.00 2.00 - - 2.00 100%
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 19,162,953.24 11.28 2.00 - 2.00
VIII PEKERJAAN PLAFOND
1 Pek. Pas. plafond gypsumboard + rangka metal furing 56.000 m2 Rp 8,693,916.00 5.12 - - 56.00 5.12 5.12 100%
JUMLAH PEKERJAAN SUB TOTAL VIII Rp 8,693,916.00 5.12 - 5.12 5.12
IX PEKERJAAN PENUTUP ATAP
1 Pekerjaan rangka atap baja ringan 83.950 m2 Rp 15,482,562.70 9.12 83.95 9.12 - - 9.12 100%
2 Pekerjaan pemasangan atap genteng metal 86.960 m2 Rp 10,283,020.00 6.05 86.96 6.05 - - 6.05 100%
3 Pekerjaan pemasangan nok genteng 35.200 m1 Rp 3,309,785.60 1.95
4 Pekerjaan pemasangan lisplank GRC 33.000 m1 Rp 2,556,246.00 1.51 33.00 1.51 - - 1.51 100%
JUMLAH PEKERJAAN SUB TOTAL IX Rp 31,631,614.30 18.63 16.68 - 16.68
X PEKERJAAN PINTU JENDELA
1 Pemasangan pintu almunium P1 2.000 unit Rp 5,769,584.92 3.40 2.00 3.40 - - 3.40 100%
2 Pemasangan jendela almunium J1 1.000 unit Rp 2,535,043.42 1.49 1.00 1.49 - - 1.49 100%
3 Pemasangan jendela almunium J2 6.000 unit Rp 7,378,575.06 4.34 6.00 4.34 - - 4.34 100%
4 Pemasangan rooster R1 28.000 unit Rp 700,000.00 0.41 28.00 0.41 - - 0.41 100%
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
JUMLAH PEKERJAAN SUB TOTAL XI Rp 16,383,203.40 9.65 #NAME? #NAME? #NAME?
XI PEKERJAAN ELEKTRIKAL
1 Instalasi titik lampu 14.000 titik Rp 2,380,000.00 1.40 14.00 1.40 - - 1.40 100%
2 Pemasangan lampu SL LED 13 Watt downlight 4.000 titik Rp 580,000.00 0.34 4.00 0.34 - - 0.34 100%
3 Pemasangan lampu LED 7 Watt downlight 3.000 titik Rp 420,000.00 0.25
4 Pemasangan saklar tunggal 3.000 titik Rp 120,000.00 0.07
5 Pemasangan saklar ganda 1.000 titik Rp 50,000.00 0.03
6 Pemasangan stop kontak 2.000 titik Rp 90,000.00 0.05
7 pemasangan box sekering 1.000 unit Rp 160,000.00 0.09 1.00 0.09 - - 0.09 100%
JUMLAH PEKERJAAN SUB TOTAL XII Rp 3,800,000.00 2.24 1.84 - 1.84

#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?


#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
XIII PEKERJAAN AKHIR
1 Pekerjaan pembersihan lokasi 1.000 LS Rp 500,000.00 0.29 1.00 0.29 - - 0.29 100%
JUMLAH PEKERJAAN SUB TOTAL VI Rp 500,000.00 0.29 0.29 - 0.29
SUB TOTAL Rp 169,827,294.47 100.00 #NAME? #NAME? #NAME?

Tanjung Balai Karimun, 09 OKTOBER 2017

DI Setujui Oleh ; Di Periksa Oleh; DI Buat Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN CV. SIDAN JAYA
PEJABAT PEMBUAT KOMITMEN ( PPK )

HIKMA DINI FAHMI,ST AHMAD MUDA BAHRI, ST SUDIRMAN


NIP. 19790611 200904 2 003 Supervisi Engineer Direktur
JADWAL WAKTU PELAKSANAAN

KEGIATAN : Peningkatan Pembangunan Sarana dan Prasarana Fasilitas Umum Wilayah Administrasi Kecamatan Karimun, Meral, Meral Barat dan Tebing
PEKERJAAN : Rehabilitasi Balai Desa Bukit Sidomulyo I Kelurahan Tanjung Balai Kecamatan Karimun
Prop / Kab / Kodya : Kepri / Kabupaten Karimun

BULAN I BULAN II
BOBOT MINGGU KE MINGGU KE
NO URAIAN PEKERJAAN
(%)
1 2 3 4 5 6 7 8

I PEKERJAAN PERSIAPAN 0.85 0.85

II PEKERJAAN TANAH DAN PONDASI TAPAK 2.62 2.62

III PEKERJAAN BETON 1.07 0.27 0.27 0.27 0.27

IV PEKERJAAN DINDING PASANGAN 14.53 14.53

V PEKERJAAN PLESTERAN 5.88 5.88


PEKERJAAN PENUTUP LANTAI DAN PENUTUP
VI 9.87 9.87
DINDING
VII PEKERJAAN PLAFOND 14.32 14.32

VIII PEKERJAAN PINTU JENDELA 16.03 16.03

IX PEKERJAAN PENGECATAN 2.11 2.11

X PEKERJAAN INSTALASI AIR 14.07 14.07

XI PEKERJAAN ELEKTRIKAL 5.39 5.39

XII PEKERJAAN PERKERASAN PAVING 12.88 12.88

XIII PEKERJAANAKHIR 0.39 0.39

JUMLAH 100.00
RELISASI RENCANA MINGGUAN 3.73 0.27 0.27 30.55 44.42 2.11 18.27 0.39
RENCANA KOMULATIF MINGGUAN 3.73 4.00 4.27 34.82 79.23 81.34 99.61 100.00
BOBOT KOMULATIF MINGGUAN 2.41 #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

BOBOT RELISASI MINGGUAN 2.41 #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
Deviasi (1.32) #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

Keterangan :

DI Setujui Oleh ; Di Periksa Oleh;


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KONSULTAN PENGAWAS
KABUPATEN KARIMUN CV. ASKA PERKASA KONSULTAN
PEJABAT PEMBUAT KOMITMEN ( PPK )

HIKMA DINI FAHMI,ST AHMAD MUDA BAHRI, ST


NIP. 19790611 200904 2 003 Supervisi Engineer
WAKTU PELAKSANAAN

Wilayah Administrasi Kecamatan Karimun, Meral, Meral Barat dan Tebing

KET
Masa
Pemeliharaan
(60 Hari Kalender)
100%

90%

80%

70%

60%
Bulan Ke 1

Bulan Ke 2
50%

40%

30%

20%

10%

0%

DI Buat Oleh;

KONTRAKTOR PELAKSANA
CV. PANUTAN JAYA

SUDIRMAN
Direktur
JADWAL WAKTU PELAKSANAAN

Kegiatan : Peningkatan Pembangunan Sarana dan Prasarana Fasilitas Umum Wilayah Administrasi Kecamatan Karimun, Meral, Meral Barat dan Tebing

Pekerjaan : Pembangunan Tempat Wudhu Masjid Nurul Taqwa

Prop / Kab / Kodya : Kepri / Kabupaten Karimun

BULAN I BULAN II
NO URAIAN PEKERJAAN BOBOT MINGGU KE MINGGU KE Masa
(%) Pemeliharaan
1 2 3 4 5 6 7 8 (60 Hari Kalender)

I PEKERJAAN PERSIAPAN 0.82 0.82

II PEKERJAAN TANAH DAN PONDASI TAPAK 1.66 1.66

III PEKERJAAN BETON 41.88 10.47 10.47 10.47 10.47

IV PEKERJAAN DINDING PASANGAN 2.58 2.58

V PEKERJAAN PLESTERAN 4.41 4.41

PEKERJAAN PENUTUP LANTAI DAN PENUTUP


VI 9.88 9.88
DINDING

Bulan Ke 1
VII PEKERJAAN PLAFOND 2.23 2.23

VIII PEKERJAAN PINTU JENDELA 2.30 2.30

IX PEKERJAAN PENGECATAN 10.33 10.33

X PEKERJAAN INSTALASI AIR 12.51 12.51

XI PEKERJAAN ELEKTRIKAL 0.98 0.98

XII PEKERJAAN PERKERASAN PAVING 9.89 9.89

XIII PEKERJAAN AKHIR 0.53 0.53

JUMLAH 100.00

JUMLAH RENCANA MINGGUAN 12.96 10.47 10.47 27.33 17.04 10.33 10.88 0.53

JUMLAH KOMULATIF BULANAN 12.96 23.43 33.90 61.23 78.27 88.59 99.47 100.00

Keterangan :

Minggu Ke - 7 = 3 Hari Kalender

Tanjung Balai Karimun, 10 Oktober 2017


CV. PANUTAN JAYA

SUDIRMAN
Direktur
WAKTU PELAKSANAAN

ayah Administrasi Kecamatan Karimun, Meral, Meral Barat dan Tebing

KET
Masa
Pemeliharaan
(60 Hari Kalender)
100%

90%

80%

70%

60%

Bulan Ke 2
50%

40%

30%

20%

10%

0%
BACK UP DATA
GAMBAR NO URAIAN PEKERJAAN

### ###

1 ###
###

###

II PEKERJAAN TANAH
### #NAME?
### ###
###

###

###

### ###
Pek.Galian Tanah Pondasi

###

###

######
Pek.Galian Tanah Pondasi

###

###

6 ###
Pek.Galian Tanah Pondasi

###

###
PERHITUNGAN

URAIAN PEKERJAAN Sat Pjg Lbr Tgg Byk V Total

= 4.44
Pondasi m2 1 x 1 x 0.10 x 20 = 2.00
Sloof m2 121.8 x 0.2 x 0.10 x 1 = 2.44
4.44
= 28.74
m3 1 x 1 x 0.95 x 20 = 19.00
Sloof m3 121.8 x 0.2 x 0.40 x 1 = 9.74
28.74

PEKERJAAN TANAH
#NAME?
0.3
m3 1 x 1 x 0.3 x 20 = 6.00 6.00

kg 2.5 x 14 x 0.88776 x 20 = 621.43 621.43

m2 4 x 0.3 x 20 = 24.00 24.00

Pek.Galian Tanah Pondasi M3 0.30 x 0.3 x 0.15 x 20 = 0.27 0.27

kg 244.6272
Tulangan 0.88776 x 1.6 x 8 x 20 = 227.26656
Sengkang 0.39456 x 1.1 x 2 x 20 = 17.36064
244.6272
m2 = 3.6
0.3 x 0.15 x 4 x 20 = 3.6

Pek.Galian Tanah Pondasi


M3 121.8 x 0.20 x 0.40 x 1 = 9.744 = 9.74

= 1948.39
Tulangan 1.58 x 124 x 6 x 1 = 1174.21056
Tulangan Tambah 1.58 x 2.5 x 88 x 1 = 347.2128
Tulangan Tambah 1.58 x 1.2 x 36 x 1 = 68.179968

0.39 x 1.1 x 826.66667 x 1 = 358.78656


1948.389888
m2 121.8 x 0.1 x 2 = 24.36

Pek.Galian Tanah Pondasi m3 3.6 x 0.3 x 0.3 x 20 = 6.48 6.48

Tulangan 1.57824 x 4 x 8 x 20 = 1010.0736 1258.91


0.39456 x 1.1 x 29 x 20 = 248.83584
1258.90944

3.6 x 0.3 x 4 x 20 = 86.4 86.40


BACK UP DATA
GAMBAR NO URAIAN PEKERJAAN
### ###
7 ###
###

###

###

8 ###
###

###

###

###
III PEKERJAAN PONDASI
###

###

###

######
Pek.Galian Tanah Pondasi

###

###
PERHITUNGAN

URAIAN PEKERJAAN Sat Pjg Lbr Tgg Byk V Total

m3 16.2 x 12.2 x 0.12 = 23.7168 = 23.72

kg 0.6165 x 16.3 x 80 x 2 = 1607.832 = 3225.53


0.6165 x 12.3 x 106.66667 x 2 = 1617.696
3225.528

m2 4.8 x 3.8 x 8 = 145.92 180.10


1.8 x 3.8 x 4 = 27.36
56.8 x 0.12 x 1 = 6.816
180.096

m3 124 x 0.28 x 0.2 = 6.944 6.94

kg 1.57824 x 124 x 6 = 1174.21056 2084.12


Tulangan 1.57824 x 3.2 x 88 = 444.432384
1.57824 x 1.3 x 52 = 106.689024

Sengkang 0.39456 x 1.1 x 826.66667 = 358.78656


2084.118528

121.8 X 0.28 X 2 = 68.208 92.57


121.8 X 0.2 X 1 = 24.36

PEKERJAAN PONDASI
m3 0.8 x 0.8 x 0.1 x 4 = 0.256 = 0.35
SLOOF PONADIS M3 4.70 X 0.20 X 0.1 X 1 = 0.094
m3 0.8 x 0.8 x 0.8 x 4 = 2.048 = 2.189
SLOOF PONADIS 4.70 X 0.20 X 0.15 X 1 = 0.141
m3 0.8 x 0.8 x 0.05 x 4 = 0.128

Pek.Galian Tanah Pondasi m3 0.3 x 0.3 x 1 x 1 = 0.09

kg = 8.969664
Tulangan 1.58 x 1.1 x 4 x 1 = 6.944256
Sengkang 0.39 x 0.7 x 7.3333333 x 1.00 = 2.025408
8.969664
0.3 x 1 x 2 = 0.6
BACK UP DATA
GAMBAR NO URAIAN PEKERJAAN

8 Pek. Urugan Tanah Kembali


###

###

###

9###

###

1-0###

###
PERHITUNGAN

URAIAN PEKERJAAN Sat Pjg Lbr Tgg Byk V Total

Pek. Urugan Tanah Kembali


= 0.77
Beton Tapak 0.8 x 0.8 x 0.25 x 4 = 0.64
Beton Stump 0.25 x 0.25 x 0.5 x 4 = 0.125
0.77
KG 113.40
Tulangan Pondasi 0.88776 x 2 x 10.00 x 4 = 71.0208
Tulangan Stump 0.88776 x 1.6 x 6.00 x 4 = 34.089984
Sengkang 0.39456 x 0.7 x 7.50 x 4 = 8.28576
113.40
Stum Pondasi 0.5 x 0.2 x 4.00 x 4 = 1.60

#NAME? m3 0.2 x 0.2 x 2.6 x 4 = = 0.42

#NAME? kg
Tulangan 0.88776 x 2.8 x 6 x 4 = 59.657472 80.27
Sengkang 0.394304 x 0.7 x 18.666667 x 4 = 20.60895573
80.26642773
#NAME? m2 0.2 x 2.6 x 4 x 4 = 8.32

#NAME? m3 0.25 x 0.2 x 4.70 x 1 = 0.24

#NAME? 34.92
Tulangan 0.89 x 4.70 x 6 x 1 = 25.034832
0.394304 x 0.8 x 31.333333 x 1 = 9.883886933
34.91871893

= 1.54
plat Lantai Tangga m3 6.99 x 1 x 0.1 = 0.699
Anak Tanggak 1 x 0.03 x 19 = 0.57
Bordes 1 x 1.35 x 0.12 = 0.162
2.25 x 0.4 x 0.12 = 0.108
1.539

Tulangan Plat Lantai 0.6165 x 6.99 x 10 = 43.09335 191.45


0.6165 x 1 x 46.6 = 28.7289
71.82225
Tulangan Anak Tangga
0.6165 x 1 x 57 = 35.1405
sengkang 0.39456 x 0.6 x 126.66667 = 29.98656
65.12706
BACK UP DATA
GAMBAR NO URAIAN PEKERJAAN

###

3 ###
###

###

###

###
###

###

###

###
###

###

###
PERHITUNGAN

URAIAN PEKERJAAN Sat Pjg Lbr Tgg Byk V Total

Tulangan Bordes 1 0.6165 x 1 x 13.500 x 2 = 16.6455


0.6165 x 1.35 x 10 x 2 = 16.6455
2 0.6165 x 2.15 x 4.0 x 2 = 10.6038
0.6165 x 0.4 x 21.5 x 2 = 10.6038
54.4986

Plat Lantai 6.99 x 1 = 6.99


Sisi Samping 6.99 X 0.1 X 2 = 1.398
Anak Tangga 0.03 x 2 x 19 = 1.14
Sisi Samping 1 x 0.2 x 19 = 3.8
Bordes 1.1 X 1.35 X 1 = 1.485
Sisi Samping 4.9 X 0.12 X 1 = 0.588
Bordes 0.4 X 2.15 X 1 = 0.86
4.7 X 0.12 X 1 = 0.564
16.825

M3 0.25 X 0.25 X 3.5 X 20 = 4.38

691.27
Tulangan 0.88776 x 3.7 x 8 x 20 = 525.55392
Sengkang 0.39456 x 0.9 x 23.333333 x 20 = 165.7152
691.26912

0.25 x 3.5 x 4 x 20 = 70

121.8 x 0.2 x 0.2 x 1 = 4.87

= 764.91
Tulangan 0.88776 x 121.8 x 5 x 1 = 540.64584
Sengkang 0.39456 x 0.7 x 812 x 1 = 224.267904
764.913744

121.8 x 0.2 x 3 x 2 = 146.16 = 146.16

3.5 x 0.13 x 0.13 x 13 = = 0.77

168.43
Tulangan 0.6165 x 3.7 x 4 x 13 = 118.6146 ###
Sengkang 0.22194 x 0.7 x 24.666667 x 13 = 49.818132
168.432732
3.5 x 0.13 x 2 x 13 = 11.83
BACK UP DATA
GAMBAR NO URAIAN PEKERJAAN
IV PEKERJAAN STRUKTUR
0 - Bekesting
PERHITUNGAN

URAIAN PEKERJAAN Sat Pjg Lbr Tgg Byk V Total


PEKERJAAN STRUKTUR
- Bekesting m2
Memanjang 3.75 x 3.5 x 17 = 224.475 = 373.89
Melintang 4.75 x 3.5 x 10 = 166.25
1.75 x 3.5 x 2 = 12.25
wc 2.835 x 3.5 x 1 =
3.8 x 3.2 x 1 =
Layar 2.13 x 6 x 2 = 25.56
428.535

Dikurangi Pertemuan Terdap Pintu, Jendela Dan Kolom Praktis


p1 2.86 x 1.56 x 1 = 4.46
p2 2.15 x 0.9 x 8 = 15.48
p3 2.15 x 0.85 x 4 = 7.31
j1 1.6 x 0.8 x 16 = 20.48
j2 0.5 x 0.5 x 4 = 1.00
48.73

kp 0.13 x 3.5 x 13 = 5.915

54.65
BACK UP DATA
GAMBAR NO URAIAN PEKERJAAN
V PEKERJAAN PASANGAN DINDING
1 Pekerjaan pas.dinding batako
PERHITUNGAN

URAIAN PEKERJAAN Sat Pjg Lbr Tgg Byk V Total


PEKERJAAN PASANGAN DINDING
Pekerjaan pas.dinding batako m2 295.22
Rumus
LD = Lebar Diagonal = 1426 cm
L1 = Lebar Atap 1 = 713 cm
L2 = Lebar Atap 2 = 713 cm
cos 25 = 0.882

alpha = 1426 = 1616.78 cm 16.1678 m


0.882

luas = 16.1678 x 18.26 = 295.22 m2

272.88
###

(REVISI TIME SCHEDULE) RE SCHEDULE

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG WILAYAH ADMINISTRASI KECAMATAN KARIMUN, MERAL, MERAL BARAT DAN TEBING

JANGKA WAKTU PELAKSANAAN = 150 HARI KALENDE

BULAN KE-1 BULAN KE-2 BULAN KE-3

BOBOT
NO URAIAN PEKERJAAN JUMLAH 1 2 3 4 5 6 7 8 9 10 11 12
%

7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep

13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug 31-Aug 7-Sep 14-Sep 21-Sep 28-Sep

I PEKERJAAN PENDAHULUAN Rp 2,000,000.00 #NAME? #NAME? #NAME?

II PEKERJAAN TANAH #NAME? #NAME? #NAME? #NAME? #NAME?

III PEKERJAAN STRUKTUR

A Lantai I Rp 4,195,791.60 #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

A1 Tangga Rp 7,936,173.30 #NAME?

B Lantai II #NAME? #NAME? #NAME? #NAME?

IV PEKERJAAN ARSITEKTUR Rp 48,512,404.20 #NAME? #NAME?

V PEKERJAAN ATAP Rp 10,871,744.95 #NAME?

VI PEKERJAAN KERAMIK Rp 18,237,389.28 #NAME?

VII PEKERJAAN PLAFOND Rp 19,162,953.24 #NAME?

VIII PEKERJAAN SANITASI Rp 8,693,916.00 #NAME?

IX PEKERJAAN ELEKTRIK Rp 31,631,614.30 #NAME? #NAME?

X PEK. KUSEN, PINTU DAN JENDELA DAN PAGAR TERAS #NAME? #NAME? #NAME?

XI PEKERJAAN PENGECATAN #NAME? #NAME?

XII PEKERJAAN AKHIR #NAME? #NAME?

JUMLAH #NAME? #NAME?


Rencana Realisasi Fisik Pekerjaan Minggu Ini #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
Rencana Komulatif Seluruh Pekerjaan Minggu Ini #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?
Realisasi Fisik Pekerjaan Minggu Ini
Bobot Komulatif Seluruh Pekerjaan Minggu Ini
DEVIASI
7 7 7 7 7 7 7 7 7 7 7 7
0 ###
#NAME? ###
#NAME? ###
#NAME? ###

0 ###
0 ###
CHEDULE) RE SCHEDULE

JANGKA WAKTU PELAKSANAAN = 150 HARI KALENDER ( TAHUN 2017 )

BULAN KE-4 BULAN KE-5 MASA


PER PEMELIHARAAN
13 14 15 16 17 18 19 20 21 22 SEN (BULAN)
TASE
29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec

5-Oct 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov 30-Nov 3-Dec

100

#NAME? #NAME?

#NAME? #NAME?
MASA
#NAME? #NAME?
PEMELIHARAAN
#NAME? 180 (Seratus
50
#NAME? Delapan Puluh)
Hari Kalender
#NAME?

#NAME?

#NAME?

#NAME? #NAME?

#NAME? ###

### 0

#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? 0.00 #NAME? #NAME? #NAME?
#NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?

7 7 7 7 7 7 7 7 7 7
0 0
### ###
### ###

0 2.413
0 -1.3205
FORMULIR REKAPITULASI PERHITUNGAN TKDN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG WILAYAH ADMINISTR

Nilai Gabungan Barang/ Jasa (Rp) #NAME? TKDN


Total
Uraian Pekerjaan Barang/ Jasa
DALAM NEGERI LUAR NEGERI % Gabungan
(Rp) KDN (Rp)
(1) (2) (3) (4) (5) (6) (7)
A. Barang
I. Material Langsung (Bahan Baku) 70.00% - #NAME? #NAME? #NAME? #NAME?
II. Peralatan (Barang Jadi) 30.00% - #NAME? #NAME? #NAME? #NAME?
Sub Total Barang A 100.00% - #NAME? #NAME? #NAME?

B. J a s a
III. Manajemen Proyek dan Perekayasaan 50.00% - #NAME? #NAME? #NAME? #NAME?
IV. Alat Kerja/ Fasilitas Kerja 16.67% - #NAME? #NAME? #NAME? #NAME?
V. Konstruksi dan Fabrikasi 16.67% - #NAME? #NAME? #NAME? #NAME?
VI. Jasa Umum 16.67% - #NAME? #NAME? #NAME? #NAME?
Sub Total Jasa B 100.00% #NAME? #NAME? #NAME?

C. Total Biaya ( A + B ) #NAME? #NAME?

#NAME?
Dibuat Oleh,
#NAME?

#NAME?
#NAME?
PRA RENCANA KESELAMATAN DAN KESEHATAN KERJA KONTRAK
#NAME? ( PRA - RK3K )

1. KEBIJAKAN K-3
Dengan ini saya :
NAMA : #NAME?
JABATAN : #NAME?
NAMA PERUSAHAAN : #NAME?

akan menerapkan Sistim Manajemen Keselamatan Dan Kesehatan Kerja ( K3 ) dalam melaksanakan Kegiatan/Pekerjaan sebagai berikut :

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA FASILITAS UMUM BIDANG TATA RUANG WILAYAH ADMINISTRASI KEC

JENIS/TYPE IDENTIFIKASI JENIS


NO. PENGENDALIAN RISIKO K3
PEKERJAAN BAHAYA DAN RISIKO K3
1 2 3 4

1. Pek. Pengukuran, Bouplank dan Jenis Bahaya : Pengendalian Resiko K3


Pembersihan Lokasi - Terkena alat bantu untuk pembersihan lokasi - Menggunakan sepatu kerja ( boot )
Risiko : - Memastikan luasan kerja yang cukup
- Luka Berat/Ringan - Menggunakan peralatan yang sesuai/baik
- Menggunakan tanda/rambu pengaman

2. Mobilisasi dan Demobilisasi Jenis Bahaya : Pengendalian Resiko K3


- Tabrakan - Harus dikawal oleh pihak terkait
Risiko : - Menggunakan APD secara tepat, Lengkap dan Benar
- Luka Berat/Ringan/Meninggal - Menggunakan peralatan yang sesuai/baik
- Kordinasi dengan pihak terkait

3 Pengerjaan Beton Jenis Bahaya : Pengendalian Resiko K3


- Pembesian - Terkena bahan dan alat bantu pekerjaan pembesian - Memastikan luasan kerja yang cukup
- Bekisting - Terkena bahan dan alat bantu pekerjaan bekisting - Menggunakan tanda/rambu pengaman
- Pengecoran - Terkena bahan dan alat bantu pekerjaan pengecoran - Menggunakan peralatan yang sesuai/baik
- Terjatuh dari Ketinggian - Menggunakan APD secara tepat, lengkap dan benar
Risiko : - Scafolding / andang harus terpasang dgn benar
- Luka Berat/Ringan/Meninggal

4 Pemasangan Keramik Jenis Bahaya : Pengendalian Resiko K3


- Terkena Pecahan Keramik - Memastikan luasan kerja yang cukup
- Terluka karena grenda - Menggunakan peralatan yang sesuai/baik
Risiko : - Menggunakan APD secara tepat, lengkap dan benar
- Luka Berat/Ringan

5 Pemasangan Atap Jenis Bahaya : Pengendalian Resiko K3


- Terjatuh dari Ketinggian - Memastikan luasan kerja yang cukup
- Tertimpa rangka baja ringan / atap - Menggunakan tanda/rambu pengaman
Risiko : - Menggunakan peralatan yang sesuai/baik
- Luka Berat/Ringan/Meninggal - Menggunakan APD secara tepat, lengkap dan benar
- Memastikan Pemasangan Scafolding sesuai aturan

6 Instalasi Listrik Jenis Bahaya : Pengendalian Resiko K3


- Kesetrum - Memastikan peralatan listrik yang standard PUIL
Risiko : - Menggunakan peralatan yang sesuai/baik
- Luka Berat/Ringan/Meninggal - Menggunakan APD secara tepat, lengkap dan benar

7 Pasang Batako Jenis Bahaya : Pengendalian Resiko K3


- Terjatuh dari Ketinggian - Memastikan bahwa scafolding/ andang terpasang dgn benar
- Tertimpa dinding yang ambruk - Menggunakan peralatan yang sesuai/baik
- Menggunakan APD secara tepat, lengkap dan benar
Risiko : - Tahapan pemasangan dinding harus sesuai aturan
- Luka Berat/Meninggal

8 Pengecatan Jenis Bahaya : Pengendalian Resiko K3


- Keracunan - Ruangan harus terbuka, jendela dan pintu harus dibuka
Risiko : - Menggunakan peralatan yang sesuai/baik
- Luka Berat/Meninggal - Menggunakan APD secara tepat, lengkap dan benar

9 Pengelasan Jenis Bahaya : Pengendalian Resiko K3


- Terbakar kawat las - Menggunakan peralatan yang sesuai/baik
- Mata terpercik api las - Menggunakan APD secara tepat, lengkap dan benar
JENIS/TYPE IDENTIFIKASI JENIS
NO. PENGENDALIAN RISIKO K3
PEKERJAAN BAHAYA DAN RISIKO K3
1 2 3 4
Risiko :
- Luka Berat/Meninggal
JENIS/TYPE IDENTIFIKASI JENIS
NO. PENGENDALIAN RISIKO K3
PEKERJAAN BAHAYA DAN RISIKO K3
1 2 3 4
2. PEMENUHAN PERUNDANG-UNDANGAN DAN PERSYARATAN LAINNYA

a. UU No. I Tahun 1970 Tentang Keselamatan Kerja


b. UU No. 18 Tahun 1999 Tentang Jasa Konstruksi
c. Peraturan Mentri PU No. 09/PRT/M/2008 tentang Pedoman Sistem Manajemen Keselamatan dan Kesehatan Kerja ( SMK3 ) Konstruksi Bidang PU

3. SASARAN K3 DAN PROGRAM K3

I. SASARAN K3
a. Tidak ada kecelakaan kerja yang berdampak korban jiwa ( Zero Fatal Accident ).
b. Tingkat penerapan elemen SMK3 minimal 80%.
c. Semua pekerja wajib memakai APD yang sesuai bahan dan risiko pekerjaannya masing-masing.

II. PROGRAM K3
a. Melaksanakan Rencana K3 dengan menyediakan sumber daya K3 (APD, rambu-rambu, spanduk, pagar pengaman, jaring pengaman, dll) secara konsisten.

b. Melakukan inspeksi secara rutin terhadap kondisi dan cara kerja berbahaya.
c. Memastikan semua pekerja untuk mematuhi peraturan yang telah ditetapkan.

4. STRUKTUR ORGANISASI K3
PENANGGUNG JAWAB K3

EMERGENCY/DARURAT P3K KEBAKARAN

###
Dibuat Oleh,
###

###
###