REKAPITULASI

MONTHLY CERTIFICATE (MC)


DESEMBER 2018 (MC-08)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 08
LOKASI : KABUPATEN SIMEULUE BULAN : DESEMBER
SUMBER DANA : APBA PERIODE : 01 DESEMBER s/d 10 DESEMBER
TAHUN ANGGARAN : 2018 TANGGAL : 10 DESEMBER 2018
PERUSAHAAN : CV. ASFAR RAYA HALAMAN : 1 dari 2
NO. & TGL. KONTRAK : 02/KPA.07/PELAYARAN/2018 & 11 MEI 2018
NO. & TGL. KONTRAK ADD-I : 06/KPA.07/PELAYARAN/2018 & 23 JULI 2018

KONTRAK ADD-I JUMLAH PEMBAYARAN


PEKERJAAN SELURUH
NO URAIAN PEKERJAAN JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI KET.
BOBOT (%) SENDIRI PEKERJAAN
(Rp)
(Rp) (Rp) (Rp) (%) (%)

I. PEKERJAAN PERSIAPAN 42,500,000.00 3.01 27,750,000.00 14,750,000.00 42,500,000.00 3.01 3.01


II. PEKERJAAN TANAH DAN PONDASI 575,289,263.66 40.76 486,086,708.30 89,205,273.79 575,289,263.66 40.76 40.76
III. PEKERJAAN BETON BERTULANG 460,342,809.37 32.62 427,718,881.75 32,624,222.45 460,342,809.37 32.62 32.62
IV. PEKERJAAN PASANGAN DAN PLESTERAN 5,640,113.16 0.40 - 5,640,113.16 5,640,113.16 0.40 0.40
V. PEKERJAAN LANTAI PADA JALAN 220,660,228.39 15.63 187,561,194.13 33,099,034.26 220,660,228.39 15.63 15.63
VI. PEKERJAAN LAIN-LAIN 106,970,223.98 7.58 106,970,223.98 - 106,970,223.98 7.58 7.58

I JUMLAH 1,411,402,638.56 100.00 1,236,087,008.15 175,318,643.66 1,411,402,638.56 100.00


II JUMLAH TOTAL 141,140,263.86 123,608,700.82 17,531,864.37 141,140,263.86
III PPN 10% 1,552,542,902.42 1,359,695,708.97 192,850,508.02 1,552,542,902.42
IV DIBULATKAN 1,552,540,000.00 1,359,695,708.00 192,850,508.00 1,552,540,000.00

V JUMLAH KOTOR SERTIFIKAT S/D BULAN INI 1,552,540,000.00 S/D BULAN INI
VI JUMLAH KOTOR SERTIFIKAT S/D BULAN LALU 1,359,695,708.00
VII JUMLAH KOTOR SERTIKAT BULAN INI (V) - (VI) 192,844,292.00
POTONGAN: BULAN INI
VIII PENGEMBALIAN UANG MUKA (VII) x 30% 57,853,287.60
IX RETENSI (VII) x 5% 9,642,214.60
X JUMLAH POTONGAN (VIII) + (IX) 67,495,502.20 S/D BULAN LALU
XI JUMLAH BERSIH SERTIFIKAT BULAN INI (VII) - (X) 125,348,789.80
XII JUMLAH BERSIH SERTIFIKAT BULAN INI DIBULATKAN 125,348,789.00

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR, A. Md HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager

Mengetahui/Menyetujui:
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

Ir. MAHYUS SYAFRIL


NIP: 19621125 199403 1 005
MONTHLY CERTIFICATE (MC)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 08
LOKASI : KABUPATEN SIMEULUE BULAN : DESEMBER
SUMBER DANA : APBA TANGGAL : 10 DESEMBER 2018
TAHUN ANGGARAN : 2018 HALAMAN : 1 dari 2
PERUSAHAAN : CV. ASFAR RAYA
NO. & TGL. KONTRAK : 02/KPA.07/PELAYARAN/2018 & 11 MEI 2018
NO. & TGL. KONTRAK ADD-I : 06/KPA.07/PELAYARAN/2018 & 23 JULI 2018

KONTRAK ADD-I REALISASI


S/D BULAN LALU BULAN INI S/D BULAN INI BOBOT
NO URAIAN PEKERJAAN HARGA SAT. JUMLAH HARGA BOBOT
VOLUME JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA %
(Rp) (Rp) % VOLUME VOLUME VOLUME
(Rp) (Rp) (Rp)
I. PEKERJAAN PERSIAPAN
1 Biaya Mobilisasi dan Demobilisasi 1.00 Paket 22,000,000.00 22,000,000.00 1.56 0.50 11,000,000.00 0.50 11,000,000.00 1.00 22,000,000.00 1.56
2 Pengukuran 1.00 Paket 5,000,000.00 5,000,000.00 0.35 1.00 5,000,000.00 - - 1.00 5,000,000.00 0.35
3 Bangunan Direksikeet dan Barak Kerja 1.00 Unit 10,000,000.00 10,000,000.00 0.71 1.00 10,000,000.00 - - 1.00 10,000,000.00 0.71
4 Papan Nama Proyek 1.00 Bh 500,000.00 500,000.00 0.04 1.00 500,000.00 - - 1.00 500,000.00 0.04
5 Dokumentasi/Administrasi/Asbuil Drawing 1.00 Paket 5,000,000.00 5,000,000.00 0.35 0.25 1,250,000.00 0.75 3,750,000.00 1.00 5,000,000.00 0.35
JUMLAH 42,500,000.00 3.01 27,750,000.00 14,750,000.00 42,500,000.00 3.01
II. PEKERJAAN TANAH DAN PONDASI
1 Galian Pelebaran Kolam dan Galian Sendimen Pendangkalan 3,795.00 M3 49,426.00 187,571,670.00 13.29 3,795.06 187,574,388.43 - - 3,795.06 187,571,670.00 13.29
2 Timbunan Tanah Pilihan ( didatangkan ) 180.00 M3 126,610.00 22,789,800.00 1.61 - - 180.00 22,789,800.00 180.00 22,789,800.00 1.61
4 Lantai Kerja Beton Cor t= 15 cm ( Kolom ) 2.48 M3 919,786.53 2,276,471.66 0.16 1.24 1,138,235.83 1.24 1,138,235.83 2.48 2,276,471.66 0.16
5 Pasangan Pondasi batu belah 1 PC : 4 PP ( Talud ) 348.00 M3 1,042,101.50 362,651,322.00 25.69 285.36 297,374,084.04 62.64 65,277,237.96 348.00 362,651,322.00 25.69
JUMLAH 575,289,263.66 40.76 486,086,708.30 89,205,273.79 575,289,263.66 40.76
III. PEKERJAAN BETON BERTULANG
1 Pek. Tiang Kolom Uk.20/30 cm 9.11 M3 6,129,000.00 55,822,932.00 3.96 7.29 44,658,345.60 1.82 11,164,586.40 9.11 55,822,932.00 3.96
2 Pek. Balok Bawah Uk. 20/25 cm 8.25 M3 5,648,300.00 46,598,475.00 3.30 8.25 46,598,475.00 - - 8.25 46,598,475.00 3.30
3 Pek. Balok Atas Uk. 20/40 cm 13.20 M3 6,471,300.00 85,421,160.00 6.05 10.56 68,336,928.00 2.64 17,084,232.00 13.20 85,421,160.00 6.05
Pekerjaan Cicin Beton Bertulang,Dia" 110 t= 80 cm, Tebal 10 cm dan Dia" 80
4 91.71 M3 2,856,900.00 262,000,242.37 18.56 90.18 257,625,133.15 1.53 4,375,404.05 91.71 262,000,242.37 18.56
t=60 cm Tebal 10 cm
5 Pembuatan Mal/Bekisting Cicin Beton dari Kayu 30.00 Unit 350,000.00 10,500,000.00 0.74 30.00 10,500,000.00 - - 30.00 10,500,000.00 0.74
JUMLAH 460,342,809.37 32.62 427,718,881.75 32,624,222.45 460,342,809.37 32.62
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Acian Balok Atas 1 PC : 4 PP . 132.00 M2 42,728.13 5,640,113.16 0.40 - 132.00 5,640,113.16 132.00 5,640,113.16 0.40
JUMLAH 5,640,113.16 0.40 0.00 5,640,113.16 5,640,113.16 0.40
V. PEKERJAAN LANTAI PADA JALAN
1 Beton cor Pada Jalan Dan Doking Perahu 239.90 BH 919,786.53 220,660,228.39 15.63 203.92 187,561,194.13 35.99 33,099,034.26 239.90 220,660,228.39 15.63
JUMLAH 220,660,228.39 15.63 187,561,194.13 33,099,034.26 220,660,228.39 15.63
VIII. PEKERJAAN LAIN-LAIN
1 Pengadaan dan Pemasangan Bolder ( Fabrikasi Lokal ) 10.00 Unit 3,000,000.00 30,000,000.00 2.13 10.00 30,000,000.00 - - 10.00 30,000,000.00 2.13
2 Pekerjaan Pembesian Lantai Doking 4,691.60 Kg 16,405.95 76,970,223.98 5.45 4,691.60 76,970,223.98 - - 4,691.60 76,970,223.98 5.45
JUMLAH 106,970,223.98 7.58 106,970,223.98 0.00 106,970,223.98 7.58

JUMLAH 1,411,402,638.56 100.00 1,236,087,008.15 175,318,643.66 1,411,402,638.56 100.00

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR, A. Md HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager
REKAPITULASI
MONTHLY CERTIFICATE (MC)
NOPEMBER 2018 (MC-07)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 07
LOKASI : KABUPATEN SIMEULUE BULAN : NOPEMBER
SUMBER DANA : APBA PERIODE : 01 NOPEMBER s/d 30 NOPEMBER
TAHUN ANGGARAN : 2018 TANGGAL : 30 NOPEMBER 2018
PERUSAHAAN : CV. ASFAR RAYA HALAMAN : 1 dari 2
NO. & TGL. KONTRAK : 02/KPA.07/PELAYARAN/2018 & 11 MEI 2018
NO. & TGL. KONTRAK ADD-I : 06/KPA.07/PELAYARAN/2018 & 23 JULI 2018

KONTRAK ADD-I JUMLAH PEMBAYARAN


PEKERJAAN SELURUH
NO URAIAN PEKERJAAN JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI KET.
BOBOT (%) SENDIRI PEKERJAAN
(Rp)
(Rp) (Rp) (Rp) (%) (%)

I. PEKERJAAN PERSIAPAN 42,500,000.00 3.01 27,750,000.00 - 27,750,000.00 2.24 1.97


II. PEKERJAAN TANAH DAN PONDASI 575,289,263.66 40.76 267,357,679.27 218,729,029.03 486,086,708.30 39.32 34.44
III. PEKERJAAN BETON BERTULANG 460,342,809.37 32.62 268,467,421.50 159,251,460.25 427,718,881.75 34.60 30.30
IV. PEKERJAAN PASANGAN DAN PLESTERAN 5,640,113.16 0.40 - - - - -
V. PEKERJAAN LANTAI PADA JALAN 220,660,228.39 15.63 143,429,148.45 44,132,045.68 187,561,194.13 15.17 13.29
VI. PEKERJAAN LAIN-LAIN 106,970,223.98 7.58 - 106,970,223.98 106,970,223.98 8.65 7.58

I JUMLAH 1,411,402,638.56 100.00 707,004,249.22 529,082,758.94 1,236,087,008.15 87.58


II JUMLAH TOTAL 141,140,263.86 70,700,424.92 52,908,275.89 123,608,700.82
III PPN 10% 1,552,542,902.42 777,704,674.14 581,991,034.83 1,359,695,708.97
IV DIBULATKAN 1,552,540,000.00 777,704,674.00 581,991,034.00 1,359,695,708.00

V JUMLAH KOTOR SERTIFIKAT S/D BULAN INI 1,359,695,708.00 S/D BULAN INI
VI JUMLAH KOTOR SERTIFIKAT S/D BULAN LALU 777,704,674.00
VII JUMLAH KOTOR SERTIKAT BULAN INI (V) - (VI) 581,991,034.00
POTONGAN: BULAN INI
VIII PENGEMBALIAN UANG MUKA (VII) x 30% 174,597,310.20
IX RETENSI (VII) x 5% 29,099,551.70
X JUMLAH POTONGAN (VIII) + (IX) 203,696,861.90 S/D BULAN LALU
XI JUMLAH BERSIH SERTIFIKAT BULAN INI (VII) - (X) 378,294,172.10
XII JUMLAH BERSIH SERTIFIKAT BULAN INI DIBULATKAN 378,294,172.00

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR, A. Md HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager

Mengetahui/Menyetujui:
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

Ir. MAHYUS SYAFRIL


NIP: 19621125 199403 1 005
MONTHLY CERTIFICATE (MC)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 07
LOKASI : KABUPATEN SIMEULUE BULAN : NOPEMBER
SUMBER DANA : APBA TANGGAL : 30 NOPEMBER 2018
TAHUN ANGGARAN : 2018 HALAMAN : 1 dari 2
PERUSAHAAN : CV. ASFAR RAYA
NO. & TGL. KONTRAK : 02/KPA.07/PELAYARAN/2018 & 11 MEI 2018
NO. & TGL. KONTRAK ADD-I : 06/KPA.07/PELAYARAN/2018 & 23 JULI 2018

KONTRAK ADD-I REALISASI


S/D BULAN LALU BULAN INI S/D BULAN INI BOBOT
NO URAIAN PEKERJAAN HARGA SAT. JUMLAH HARGA BOBOT
VOLUME JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA %
(Rp) (Rp) % VOLUME VOLUME VOLUME
(Rp) (Rp) (Rp)
I. PEKERJAAN PERSIAPAN
1 Biaya Mobilisasi dan Demobilisasi 1.00 Paket 22,000,000.00 22,000,000.00 1.56 0.50 11,000,000.00 - - 0.50 11,000,000.00 0.78
2 Pengukuran 1.00 Paket 5,000,000.00 5,000,000.00 0.35 1.00 5,000,000.00 - - 1.00 5,000,000.00 0.35
3 Bangunan Direksikeet dan Barak Kerja 1.00 Unit 10,000,000.00 10,000,000.00 0.71 1.00 10,000,000.00 - - 1.00 10,000,000.00 0.71
4 Papan Nama Proyek 1.00 Bh 500,000.00 500,000.00 0.04 1.00 500,000.00 - - 1.00 500,000.00 0.04
5 Dokumentasi/Administrasi/Asbuil Drawing 1.00 Paket 5,000,000.00 5,000,000.00 0.35 0.25 1,250,000.00 - - 0.25 1,250,000.00 0.09
JUMLAH 42,500,000.00 3.01 27,750,000.00 0.00 27,750,000.00 1.97
II. PEKERJAAN TANAH DAN PONDASI
1 Galian Pelebaran Kolam dan Galian Sendimen Pendangkalan 3,795.00 M3 49,426.00 187,571,670.00 13.29 3,795.06 187,574,388.43 - - 3,795.06 187,574,388.43 13.29
2 Timbunan Tanah Pilihan ( didatangkan ) 180.00 M3 126,610.00 22,789,800.00 1.61 - - - - - - -
4 Lantai Kerja Beton Cor t= 15 cm ( Kolom ) 2.48 M3 919,786.53 2,276,471.66 0.16 - - 1.24 1,138,235.83 1.24 1,138,235.83 0.08
5 Pasangan Pondasi batu belah 1 PC : 4 PP ( Talud ) 348.00 M3 1,042,101.50 362,651,322.00 25.69 76.56 79,783,290.84 208.80 217,590,793.20 285.36 297,374,084.04 21.07
JUMLAH 575,289,263.66 40.76 267,357,679.27 218,729,029.03 486,086,708.30 34.44
III. PEKERJAAN BETON BERTULANG
1 Pek. Tiang Kolom Uk.20/30 cm 9.11 M3 6,129,000.00 55,822,932.00 3.96 0.91 5,582,293.20 6.38 39,076,052.40 7.29 44,658,345.60 3.16
2 Pek. Balok Bawah Uk. 20/25 cm 8.25 M3 5,648,300.00 46,598,475.00 3.30 - - 8.25 46,598,475.00 8.25 46,598,475.00 3.30
3 Pek. Balok Atas Uk. 20/40 cm 13.20 M3 6,471,300.00 85,421,160.00 6.05 - - 10.56 68,336,928.00 10.56 68,336,928.00 4.84
Pekerjaan Cicin Beton Bertulang,Dia" 110 t= 80 cm, Tebal 10 cm dan Dia" 80
4 91.71 M3 2,856,900.00 262,000,242.37 18.56 88.34 252,385,128.30 1.83 5,240,004.85 90.18 257,625,133.15 18.25
t=60 cm Tebal 10 cm
5 Pembuatan Mal/Bekisting Cicin Beton dari Kayu 30.00 Unit 350,000.00 10,500,000.00 0.74 30.00 10,500,000.00 - - 30.00 10,500,000.00 0.74
JUMLAH 460,342,809.37 32.62 268,467,421.50 159,251,460.25 427,718,881.75 30.30
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Acian Balok Atas 1 PC : 4 PP . 132.00 M2 42,728.13 5,640,113.16 0.40 -
JUMLAH 5,640,113.16 0.40 0.00 0.00 0.00 0.00
V. PEKERJAAN LANTAI PADA JALAN
1 Beton cor Pada Jalan Dan Doking Perahu 239.90 BH 919,786.53 220,660,228.39 15.63 155.94 143,429,148.45 47.98 44,132,045.68 203.92 187,561,194.13 13.29
JUMLAH 220,660,228.39 15.63 143,429,148.45 44,132,045.68 187,561,194.13 13.29
VIII. PEKERJAAN LAIN-LAIN
1 Pengadaan dan Pemasangan Bolder ( Fabrikasi Lokal ) 10.00 Unit 3,000,000.00 30,000,000.00 2.13 - 10.00 30,000,000.00 10.00 30,000,000.00 2.13
2 Pekerjaan Pembesian Lantai Doking 4,691.60 Kg 16,405.95 76,970,223.98 5.45 - 4,691.60 76,970,223.98 4,691.60 76,970,223.98 5.45
JUMLAH 106,970,223.98 7.58 0.00 106,970,223.98 106,970,223.98 7.58

JUMLAH 1,411,402,638.56 100.00 707,004,249.22 529,082,758.94 1,236,087,008.15 87.58

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR, A. Md HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager
REKAPITULASI
MONTHLY CERTIFICATE (MC)
SEPTEMBER 2018 (MC-05)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 05
LOKASI : KABUPATEN SIMEULUE BULAN : SEPTEMBER
SUMBER DANA : APBA PERIODE : 01 SEPTEMBER s/d 30 SEPTEMBER
TAHUN ANGGARAN : 2018 TANGGAL : 30 SEPTEMBER 2018
PERUSAHAAN : CV. ASFAR RAYA HALAMAN : 1 dari 3
NO. & TGL. KONTRAK : 02/KPA.07/PELAYARAN/2018 & 11 MEI 2018
NO. & TGL. KONTRAK ADD-I : 06/KPA.07/PELAYARAN/2018 & 23 JULI 2018

KONTRAK ADD-I JUMLAH PEMBAYARAN


PEKERJAAN SELURUH
NO URAIAN PEKERJAAN JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI KET.
BOBOT (%) SENDIRI PEKERJAAN
(Rp)
(Rp) (Rp) (Rp) (%) (%)

I. PEKERJAAN PERSIAPAN 42,500,000.00 3.01 27,750,000.00 - 27,750,000.00 6.32 1.97


II. PEKERJAAN TANAH DAN PONDASI 575,289,263.66 40.76 81,596,394.88 75,028,668.00 156,625,062.88 35.68 11.10
III. PEKERJAAN BETON BERTULANG 460,342,809.37 32.62 131,885,007.11 78,600,072.71 210,485,079.82 47.95 14.91
IV. PEKERJAAN PASANGAN DAN PLESTERAN 5,640,113.16 0.40 - - - - -
V. PEKERJAAN LANTAI PADA JALAN 220,660,228.39 15.63 - 44,132,045.68 44,132,045.68 10.05 3.13
VI. PEKERJAAN LAIN-LAIN 106,970,223.98 7.58 - - - - -

I JUMLAH 1,411,402,638.56 100.00 241,231,401.99 197,760,786.39 438,992,188.38 31.10


II JUMLAH TOTAL 141,140,263.86 24,123,140.20 19,776,078.64 43,899,218.84
III PPN 10% 1,552,542,902.42 265,354,542.19 217,536,865.03 482,891,407.22
IV DIBULATKAN 1,552,540,000.00 265,354,542.00 217,536,865.00 482,891,407.00

V JUMLAH KOTOR SERTIFIKAT S/D BULAN INI 482,891,407.00 S/D BULAN INI
VI JUMLAH KOTOR SERTIFIKAT S/D BULAN LALU 265,354,542.00
VII JUMLAH KOTOR SERTIKAT BULAN INI (V) - (VI) 217,536,865.00
POTONGAN: BULAN INI
VIII PENGEMBALIAN UANG MUKA (VII) x 30% 65,261,059.50
IX RETENSI (VII) x 5% 10,876,843.25
X JUMLAH POTONGAN (VIII) + (IX) 76,137,902.75 S/D BULAN LALU
XI JUMLAH BERSIH SERTIFIKAT BULAN INI (VII) - (X) 141,398,962.25
XII JUMLAH BERSIH SERTIFIKAT BULAN INI DIBULATKAN 141,398,962.00

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager

Mengetahui/Menyetujui:
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

Ir. MAHYUS SYAFRIL


NIP: 19621125 199403 1 005
MONTHLY CERTIFICATE (MC)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 05
LOKASI : KABUPATEN SIMEULUE BULAN : SEPTEMBER
SUMBER DANA : APBA TANGGAL : 30 SEPTEMBER 2018
TAHUN ANGGARAN : 2018 HALAMAN : 1 dari 2
PERUSAHAAN : CV. ASFAR RAYA
NO. & TGL. KONTRAK : 02/KPA.07/PELAYARAN/2018 & 11 MEI 2018
NO. & TGL. KONTRAK ADD-I : 06/KPA.07/PELAYARAN/2018 & 23 JULI 2018

KONTRAK ADD-I REALISASI


S/D BULAN LALU BULAN INI S/D BULAN INI BOBOT
NO URAIAN PEKERJAAN HARGA SAT. JUMLAH HARGA BOBOT
VOLUME JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA %
(Rp) (Rp) % VOLUME VOLUME VOLUME
(Rp) (Rp) (Rp)
I. PEKERJAAN PERSIAPAN
1 Biaya Mobilisasi dan Demobilisasi 1.00 Paket 22,000,000.00 22,000,000.00 1.56 0.50 11,000,000.00 - - 0.50 11,000,000.00 0.78
2 Pengukuran 1.00 Paket 5,000,000.00 5,000,000.00 0.35 1.00 5,000,000.00 - - 1.00 5,000,000.00 0.35
3 Bangunan Direksikeet dan Barak Kerja 1.00 Unit 10,000,000.00 10,000,000.00 0.71 1.00 10,000,000.00 - - 1.00 10,000,000.00 0.71
4 Papan Nama Proyek 1.00 Bh 500,000.00 500,000.00 0.04 1.00 500,000.00 - - 1.00 500,000.00 0.04
5 Dokumentasi/Administrasi/Asbuil Drawing 1.00 Paket 5,000,000.00 5,000,000.00 0.35 0.25 1,250,000.00 - - 0.25 1,250,000.00 0.09
JUMLAH 42,500,000.00 3.01 27,750,000.00 0.00 27,750,000.00 1.97
II. PEKERJAAN TANAH DAN PONDASI
1 Galian Pelebaran Kolam dan Galian Sendimen Pendangkalan 3,795.00 M3 49,426.00 187,571,670.00 13.29 1,650.88 81,596,394.88 1,518.00 75,028,668.00 3,168.88 156,625,062.88 11.10
2 Timbunan Tanah Pilihan ( didatangkan ) 180.00 M3 126,610.00 22,789,800.00 1.61 - - - - - - -
4 Lantai Kerja Beton Cor t= 15 cm ( Kolom ) 2.48 M3 919,786.53 2,276,471.66 0.16 - - - - - - -
5 Pasangan Pondasi batu belah 1 PC : 4 PP ( Talud ) 348.00 M3 1,042,101.50 362,651,322.00 25.69 - - - - - - -
JUMLAH 575,289,263.66 40.76 81,596,394.88 75,028,668.00 156,625,062.88 11.10
III. PEKERJAAN BETON BERTULANG
1 Pek. Tiang Kolom Uk.20/30 cm 9.11 M3 6,129,000.00 55,822,932.00 3.96 - -
2 Pek. Balok Bawah Uk. 20/25 cm 8.25 M3 5,648,300.00 46,598,475.00 3.30 - -
3 Pek. Balok Atas Uk. 20/40 cm 13.20 M3 6,471,300.00 85,421,160.00 6.05 - -
Pekerjaan Cicin Beton Bertulang,Dia" 110 t= 80 cm, Tebal 10 cm dan Dia" 80
4 91.71 M3 2,856,900.00 262,000,242.37 18.56 42.49 121,385,007.11 27.51 78,600,072.71 70.00 199,985,079.82 14.17
t=60 cm Tebal 10 cm
5 Pembuatan Mal/Bekisting Cicin Beton dari Kayu 30.00 Unit 350,000.00 10,500,000.00 0.74 30.00 10,500,000.00 - - 30.00 10,500,000.00 0.74
JUMLAH 460,342,809.37 32.62 131,885,007.11 78,600,072.71 210,485,079.82 14.91
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Acian Balok Atas 1 PC : 4 PP . 132.00 M2 42,728.13 5,640,113.16 0.40 -
JUMLAH 5,640,113.16 0.40 0.00 0.00 0.00 0.00
V. PEKERJAAN LANTAI PADA JALAN
1 Beton cor Pada Jalan Dan Doking Perahu 239.90 BH 919,786.53 220,660,228.39 15.63 47.98 44,132,045.68 47.98 44,132,045.68 3.13
JUMLAH 220,660,228.39 15.63 0.00 44,132,045.68 44,132,045.68 3.13
VIII. PEKERJAAN LAIN-LAIN
1 Pengadaan dan Pemasangan Bolder ( Fabrikasi Lokal ) 10.00 Unit 3,000,000.00 30,000,000.00 2.13
2 Pekerjaan Pembesian Lantai Doking 4,691.60 Kg 16,405.95 76,970,223.98 5.45
JUMLAH 106,970,223.98 2.13 0.00 0.00 0.00 0.00

JUMLAH 1,411,402,638.56 94.55 241,231,401.99 197,760,786.39 438,992,188.38 31.10

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager
REKAPITULASI
MONTHLY CERTIFICATE (MC)
AGUSTUS 2018 (MC-04)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 04
LOKASI : KABUPATEN SIMEULUE BULAN : AGUSTUS
SUMBER DANA : APBA PERIODE : 01 AGUSTUS s/d 31 AGUSTUS
TAHUN ANGGARAN : 2018 TANGGAL : 31 AGUSTUS 2018
PERUSAHAAN : CV. ASFAR RAYA HALAMAN : 1 dari 3
NO. & TGL. KONTRAK : 02/KPA.07/PELAYARAN/2018 & 11 MEI 2018
NO. & TGL. KONTRAK ADD-I : 06/KPA.07/PELAYARAN/2018 & 23 JULI 2018

KONTRAK ADD-I JUMLAH PEMBAYARAN


PEKERJAAN SELURUH
NO URAIAN PEKERJAAN JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI KET.
BOBOT (%) SENDIRI PEKERJAAN
(Rp)
(Rp) (Rp) (Rp) (%) (%)

I. PEKERJAAN PERSIAPAN 42,500,000.00 3.01 27,750,000.00 - 27,750,000.00 11.50 1.97


II. PEKERJAAN TANAH DAN PONDASI 575,289,263.66 40.76 81,596,394.88 - 81,596,394.88 33.82 5.78
III. PEKERJAAN BETON BERTULANG 460,342,809.37 32.62 53,284,934.40 78,600,072.71 131,885,007.11 54.67 9.34
IV. PEKERJAAN PASANGAN DAN PLESTERAN 5,640,113.16 0.40 - - - - -
V. PEKERJAAN LANTAI PADA JALAN 220,660,228.39 15.63 - - - - -
VI. PEKERJAAN LAIN-LAIN 106,970,223.98 7.58 - - - - -

I JUMLAH 1,411,402,638.56 100.00 162,631,329.28 78,600,072.71 241,231,401.99 17.09


II JUMLAH TOTAL 141,140,263.86 16,263,132.93 7,860,007.27 24,123,140.20
III PPN 10% 1,552,542,902.42 178,894,462.21 86,460,079.98 265,354,542.19
IV DIBULATKAN 1,552,540,000.00 178,894,462.00 86,460,079.00 265,354,542.00

V JUMLAH KOTOR SERTIFIKAT S/D BULAN INI 265,354,542.00 S/D BULAN INI
VI JUMLAH KOTOR SERTIFIKAT S/D BULAN LALU 178,894,462.00
VII JUMLAH KOTOR SERTIKAT BULAN INI (V) - (VI) 86,460,080.00
POTONGAN: BULAN INI
VIII PENGEMBALIAN UANG MUKA (VII) x 30% 25,938,024.00
IX RETENSI (VII) x 5% 4,323,004.00
X JUMLAH POTONGAN (VIII) + (IX) 30,261,028.00 S/D BULAN LALU
XI JUMLAH BERSIH SERTIFIKAT BULAN INI (VII) - (X) 56,199,052.00
XII JUMLAH BERSIH SERTIFIKAT BULAN INI DIBULATKAN 56,199,052.00

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager

Mengetahui/Menyetujui:
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

T. Faisal, ST, MT
NIP: 19750114 200312 1 003
MONTHLY CERTIFICATE (MC)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 04
LOKASI : KABUPATEN SIMEULUE BULAN : AGUSTUS
SUMBER DANA : APBA TANGGAL : 31 AGUSTUS 2018
TAHUN ANGGARAN : 2018 HALAMAN : 1 dari 2
PERUSAHAAN : CV. ASFAR RAYA
NO. & TGL. KONTRAK : 02/KPA.07/PELAYARAN/2018 & 11 MEI 2018
NO. & TGL. KONTRAK ADD-I : 06/KPA.07/PELAYARAN/2018 & 23 JULI 2018

KONTRAK ADD-I REALISASI


S/D BULAN LALU BULAN INI S/D BULAN INI BOBOT
NO URAIAN PEKERJAAN HARGA SAT. JUMLAH HARGA BOBOT
VOLUME JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA %
(Rp) (Rp) % VOLUME VOLUME VOLUME
(Rp) (Rp) (Rp)
I. PEKERJAAN PERSIAPAN
1 Biaya Mobilisasi dan Demobilisasi 1.00 Paket 22,000,000.00 22,000,000.00 1.56 0.50 11,000,000.00 - - 0.50 11,000,000.00 0.78
2 Pengukuran 1.00 Paket 5,000,000.00 5,000,000.00 0.35 1.00 5,000,000.00 - - 1.00 5,000,000.00 0.35
3 Bangunan Direksikeet dan Barak Kerja 1.00 Unit 10,000,000.00 10,000,000.00 0.71 1.00 10,000,000.00 - - 1.00 10,000,000.00 0.71
4 Papan Nama Proyek 1.00 Bh 500,000.00 500,000.00 0.04 1.00 500,000.00 - - 1.00 500,000.00 0.04
5 Dokumentasi/Administrasi/Asbuil Drawing 1.00 Paket 5,000,000.00 5,000,000.00 0.35 0.25 1,250,000.00 - - 0.25 1,250,000.00 0.09
JUMLAH 42,500,000.00 3.01 27,750,000.00 0.00 27,750,000.00 1.97
II. PEKERJAAN TANAH DAN PONDASI
1 Galian Pelebaran Kolam dan Galian Sendimen Pendangkalan 3,795.00 M3 49,426.00 187,571,670.00 13.29 1,650.88 81,596,394.88 - - 1,650.88 81,596,394.88 5.78
2 Timbunan Tanah Pilihan ( didatangkan ) 180.00 M3 126,610.00 22,789,800.00 1.61 - - - - - - -
4 Lantai Kerja Beton Cor t= 15 cm ( Kolom ) 2.48 M3 919,786.53 2,276,471.66 0.16 - - - - - - -
5 Pasangan Pondasi batu belah 1 PC : 4 PP ( Talud ) 348.00 M3 1,042,101.50 362,651,322.00 25.69 - - - - - - -
JUMLAH 575,289,263.66 40.76 81,596,394.88 0.00 81,596,394.88 5.78
III. PEKERJAAN BETON BERTULANG
1 Pek. Tiang Kolom Uk.20/30 cm 9.11 M3 6,129,000.00 55,822,932.00 3.96 - -
2 Pek. Balok Bawah Uk. 20/25 cm 8.25 M3 5,648,300.00 46,598,475.00 3.30 - -
3 Pek. Balok Atas Uk. 20/40 cm 13.20 M3 6,471,300.00 85,421,160.00 6.05 - -
Pekerjaan Cicin Beton Bertulang,Dia" 110 t= 80 cm, Tebal 10 cm dan Dia" 80
4 91.71 M3 2,856,900.00 262,000,242.37 18.56 14.98 42,784,934.40 27.51 78,600,072.71 42.49 121,385,007.11 8.60
t=60 cm Tebal 10 cm
5 Pembuatan Mal/Bekisting Cicin Beton dari Kayu 30.00 Unit 350,000.00 10,500,000.00 0.74 30.00 10,500,000.00 - - 30.00 10,500,000.00 0.74
JUMLAH 460,342,809.37 32.62 53,284,934.40 78,600,072.71 131,885,007.11 9.34
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Acian Balok Atas 1 PC : 4 PP . 132.00 M2 42,728.13 5,640,113.16 0.40 -
JUMLAH 5,640,113.16 0.40 0.00 0.00 0.00 0.00
V. PEKERJAAN LANTAI PADA JALAN
1 Beton cor Pada Jalan Dan Doking Perahu 239.90 BH 919,786.53 220,660,228.39 15.63
JUMLAH 220,660,228.39 15.63 0.00 0.00 0.00 0.00
VIII. PEKERJAAN LAIN-LAIN
1 Pengadaan dan Pemasangan Bolder ( Fabrikasi Lokal ) 10.00 Unit 3,000,000.00 30,000,000.00 2.13
2 Pekerjaan Pembesian Lantai Doking 4,691.60 Kg 16,405.95 76,970,223.98 5.45
JUMLAH 106,970,223.98 2.13 0.00 0.00 0.00 0.00

JUMLAH 1,411,402,638.56 94.55 162,631,329.28 78,600,072.71 241,231,401.99 17.09

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager
REKAPITULASI
MONTHLY CERTIFICATE (MC)
JULI 2018 (MC-03)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 03
LOKASI : KABUPATEN SIMEULUE BULAN : JULI
SUMBER DANA : APBA PERIODE : 01 JULI s/d 31 JULI
TAHUN ANGGARAN : 2018 TANGGAL : 31 JULI 2018
PERUSAHAAN : CV. ASFAR RAYA HALAMAN : 1 dari 2
NO. KONTRAK : 02/KPA.07/PELAYARAN/2018
TANGGAL KONTRAK : 11 MEI 2018

KONTRAK JUMLAH PEMBAYARAN


PEKERJAAN SELURUH
NO URAIAN PEKERJAAN JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI KET.
BOBOT (%) SENDIRI PEKERJAAN
(Rp)
(Rp) (Rp) (Rp) (%) (%)

I. PEKERJAAN PERSIAPAN 42,500,000.00 3.01 27,750,000.00 - 27,750,000.00 17.06 1.97


II. PEKERJAAN TANAH DAN PONDASI 514,355,423.37 36.44 23,313,255.68 58,283,139.20 81,596,394.88 50.17 5.78
III. PEKERJAAN BETON BERTULANG 498,520,542.00 35.32 - 53,284,934.40 53,284,934.40 32.76 3.78
IV. PEKERJAAN PASANGAN DAN PLESTERAN 8,203,800.96 0.58 - - - - -
V. PEKERJAAN LANTAI PADA JALAN 267,657,880.23 18.96 - - - - -
VI. PEKERJAAN PENGECATAN 5,164,992.00 0.37 - - - - -
VII. PENGADAAN DAN PEMASANGAN LAMPU SOLAR CELL 45,000,000.00 3.19 - - - - -
VIII. PEKERJAAN LAIN-LAIN 30,000,000.00 2.13 - - - - -

I JUMLAH 1,411,402,638.56 100.00 51,063,255.68 111,568,073.60 162,631,329.28 11.52


II JUMLAH TOTAL 141,140,263.86 5,106,325.57 11,156,807.36 16,263,132.93
III PPN 10% 1,552,542,902.42 56,169,581.25 122,724,880.96 178,894,462.21
IV DIBULATKAN 1,552,540,000.00 56,169,581.00 122,724,880.00 178,894,462.00

V JUMLAH KOTOR SERTIFIKAT S/D BULAN INI 178,894,462.00 S/D BULAN INI
VI JUMLAH KOTOR SERTIFIKAT S/D BULAN LALU 56,169,581.00
VII JUMLAH KOTOR SERTIKAT BULAN INI (V) - (VI) 122,724,881.00
POTONGAN: BULAN INI
VIII PENGEMBALIAN UANG MUKA (VII) x 30% 36,817,464.30
IX RETENSI (VII) x 5% 6,136,244.05
X JUMLAH POTONGAN (VIII) + (IX) 42,953,708.35 S/D BULAN LALU
XI JUMLAH BERSIH SERTIFIKAT BULAN INI (VII) - (X) 79,771,172.65
XII JUMLAH BERSIH SERTIFIKAT BULAN INI DIBULATKAN 79,771,172.00

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager

Mengetahui/Menyetujui:
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

T. Faisal, ST, MT
NIP: 19750114 200312 1 003
MONTHLY CERTIFICATE (MC)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 03
LOKASI : KABUPATEN SIMEULUE BULAN : JULI
SUMBER DANA : APBA TANGGAL : 31 JULI 2018
TAHUN ANGGARAN : 2018 HALAMAN : 1 dari 2
PERUSAHAAN : CV. ASFAR RAYA
NO. KONTRAK : 02/KPA.07/PELAYARAN/2018
TANGGAL KONTRAK : 11 MEI 2018

KONTRAK REALISASI
S/D BULAN LALU BULAN INI S/D BULAN INI BOBOT
NO URAIAN PEKERJAAN HARGA SAT. JUMLAH HARGA BOBOT
VOLUME JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA %
(Rp) (Rp) % VOLUME VOLUME VOLUME
(Rp) (Rp) (Rp)
I. PEKERJAAN PERSIAPAN
1 Biaya Mobilisasi dan Demobilisasi 1.00 Paket 22,000,000.00 22,000,000.00 1.56 0.50 11,000,000.00 - - 0.50 11,000,000.00 0.78
2 Pengukuran 1.00 Paket 5,000,000.00 5,000,000.00 0.35 1.00 5,000,000.00 - - 1.00 5,000,000.00 0.35
3 Bangunan Direksikeet dan Barak Kerja 1.00 Unit 10,000,000.00 10,000,000.00 0.71 1.00 10,000,000.00 - - 1.00 10,000,000.00 0.71
4 Papan Nama Proyek 1.00 Bh 500,000.00 500,000.00 0.04 1.00 500,000.00 - - 1.00 500,000.00 0.04
5 Dokumentasi/Administrasi/Asbuil Drawing 1.00 Paket 5,000,000.00 5,000,000.00 0.35 0.25 1,250,000.00 - - 0.25 1,250,000.00 0.09
JUMLAH 42,500,000.00 3.01 27,750,000.00 0.00 27,750,000.00 1.97
II. PEKERJAAN TANAH DAN PONDASI
1 Galian Pelebaran Kolam dan Galian Sendimen Pendangkalan 2,358.40 M3 49,426.00 116,566,278.40 8.26 471.68 23,313,255.68 1,179.20 58,283,139.20 1,650.88 81,596,394.88 5.78
2 Timbunan Tanah Pilihan ( didatangkan ) 180.00 M3 126,610.00 22,789,800.00 1.61 - - - - - - -
3 Pekerjaan Cerucuk Bambu T=1 m' ( terpancang ) 300.00 Bh 30,000.00 9,000,000.00 0.64 - - - - - - -
4 Lantai Kerja Beton Cor t= 15 cm ( Kolom ) 3.64 M3 919,786.53 3,348,022.97 0.24 - - - - - - -
5 Pasangan Pondasi batu belah 1 PC : 4 PP ( Talud ) 348.00 M3 1,042,101.50 362,651,322.00 25.69 - - - - - - -
JUMLAH 514,355,423.37 36.44 23,313,255.68 58,283,139.20 81,596,394.88 5.78
III. PEKERJAAN BETON BERTULANG
1 Pek. Tiang Kolom Uk.20/30 cm 13.39 M3 6,129,000.00 82,067,310.00 5.81
2 Pek. Balok Bawah Uk. 20/25 cm 12.00 M3 5,648,300.00 67,779,600.00 4.80
3 Pek. Balok Atas Uk. 20/40 cm 19.20 M3 6,471,300.00 124,248,960.00 8.80
Pekerjaan Cicin Beton Bertulang,Dia" 110 t= 80 cm, Tebal 10 cm dan Dia" 80
4 74.88 M3 2,856,900.00 213,924,672.00 15.16 14.98 42,784,934.40 14.98 42,784,934.40 3.03
t=60 cm Tebal 10 cm
5 Pembuatan Mal/Bekisting Cicin Beton dari Kayu 30.00 Unit 350,000.00 10,500,000.00 0.74 30.00 10,500,000.00 30.00 10,500,000.00 0.74
JUMLAH 498,520,542.00 35.32 0.00 53,284,934.40 53,284,934.40 3.78
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Acian Balok Atas 1 PC : 4 PP . 192.00 M2 42,728.13 8,203,800.96 0.58
JUMLAH 8,203,800.96 0.58 0.00 0.00 0.00 0.00
V. PEKERJAAN LANTAI PADA JALAN
1 Beton cor Pada Jalan Dan Doking Perahu 291.00 BH 919,786.53 267,657,880.23 18.96
JUMLAH 267,657,880.23 18.96 0.00 0.00 0.00 0.00
VI. PEKERJAAN PENGECATAN
1 Cat Tembok 192.00 Unit 26,901.00 5,164,992.00 0.37
JUMLAH 5,164,992.00 0.37 0.00 0.00 0.00 0.00
VII. PENGADAAN DAN PEMASANGAN LAMPU SOLAR CELL
1 Pengadaan dan Pemasangan Lampu PJU Solar Cell 3.00 Taksir 15,000,000.00 45,000,000.00 3.19
JUMLAH 45,000,000.00 3.19 0.00 0.00 0.00 0.00
VIII. PEKERJAAN LAIN-LAIN
1 Pengadaan dan Pemasangan Bolder ( Fabrikasi Lokal ) 10.00 Unit 3,000,000.00 30,000,000.00 2.13
JUMLAH 30,000,000.00 2.13 0.00 0.00 0.00 0.00

JUMLAH 1,411,402,638.56 100.00 51,063,255.68 111,568,073.60 162,631,329.28 11.52

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager
REKAPITULASI
MONTHLY CERTIFICATE (MC)
JUNI 2018 (MC-02)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 02
LOKASI : KABUPATEN SIMEULUE BULAN : JUNI
SUMBER DANA : APBA PERIODE : 01 JUNI s/d 30 JUNI
TAHUN ANGGARAN : 2018 TANGGAL : 30 JUNI 2018
PERUSAHAAN : CV. ASFAR RAYA HALAMAN : 1 dari 2
NO. KONTRAK : 02/KPA.07/PELAYARAN/2018
TANGGAL KONTRAK : 11 MEI 2018

KONTRAK JUMLAH PEMBAYARAN


PEKERJAAN SELURUH
NO URAIAN PEKERJAAN JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI KET.
BOBOT (%) SENDIRI PEKERJAAN
(Rp)
(Rp) (Rp) (Rp) (%) (%)

I. PEKERJAAN PERSIAPAN 42,500,000.00 3.01 - 27,750,000.00 27,750,000.00 54.34 1.97


II. PEKERJAAN TANAH DAN PONDASI 514,355,423.37 36.44 - 23,313,255.68 23,313,255.68 45.66 1.65
III. PEKERJAAN BETON BERTULANG 498,520,542.00 35.32 - - - - -
IV. PEKERJAAN PASANGAN DAN PLESTERAN 8,203,800.96 0.58 - - - - -
V. PEKERJAAN LANTAI PADA JALAN 267,657,880.23 18.96 - - - - -
VI. PEKERJAAN PENGECATAN 5,164,992.00 0.37 - - - - -
VII. PENGADAAN DAN PEMASANGAN LAMPU SOLAR CELL 45,000,000.00 3.19 - - - - -
VIII. PEKERJAAN LAIN-LAIN 30,000,000.00 2.13 - - - - -

I JUMLAH 1,411,402,638.56 100.00 - 51,063,255.68 51,063,255.68 3.62


II JUMLAH TOTAL 141,140,263.86 - 5,106,325.57 5,106,325.57
III PPN 10% 1,552,542,902.42 - 56,169,581.25 56,169,581.25
IV DIBULATKAN 1,552,540,000.00 - 56,169,581.00 56,169,581.00

V JUMLAH KOTOR SERTIFIKAT S/D BULAN INI 56,169,581.00 S/D BULAN INI
VI JUMLAH KOTOR SERTIFIKAT S/D BULAN LALU -
VII JUMLAH KOTOR SERTIKAT BULAN INI (V) - (VI) 56,169,581.00
POTONGAN: BULAN INI
VIII PENGEMBALIAN UANG MUKA (VII) x 30% 16,850,874.30
IX RETENSI (VII) x 5% 2,808,479.05
X JUMLAH POTONGAN (VIII) + (IX) 19,659,353.35 S/D BULAN LALU
XI JUMLAH BERSIH SERTIFIKAT BULAN INI (VII) - (X) 36,510,227.65
XII JUMLAH BERSIH SERTIFIKAT BULAN INI DIBULATKAN 36,510,227.00

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager

Mengetahui/Menyetujui:
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

T. Faisal, ST, MT
NIP: 19750114 200312 1 003
MONTHLY CERTIFICATE (MC)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 02
LOKASI : KABUPATEN SIMEULUE BULAN : JUNI
SUMBER DANA : APBA TANGGAL : 30 JUNI 2018
TAHUN ANGGARAN : 2018 HALAMAN : 1 dari 2
PERUSAHAAN : CV. ASFAR RAYA
NO. KONTRAK : 02/KPA.07/PELAYARAN/2018
TANGGAL KONTRAK : 11 MEI 2018

KONTRAK REALISASI
S/D BULAN LALU BULAN INI S/D BULAN INI BOBOT
NO URAIAN PEKERJAAN HARGA SAT. JUMLAH HARGA BOBOT
VOLUME JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA %
(Rp) (Rp) % VOLUME VOLUME VOLUME
(Rp) (Rp) (Rp)
I. PEKERJAAN PERSIAPAN
1 Biaya Mobilisasi dan Demobilisasi 1.00 Paket 22,000,000.00 22,000,000.00 1.56 0.50 11,000,000.00 0.50 11,000,000.00 0.78
2 Pengukuran 1.00 Paket 5,000,000.00 5,000,000.00 0.35 1.00 5,000,000.00 1.00 5,000,000.00 0.35
3 Bangunan Direksikeet dan Barak Kerja 1.00 Unit 10,000,000.00 10,000,000.00 0.71 1.00 10,000,000.00 1.00 10,000,000.00 0.71
4 Papan Nama Proyek 1.00 Bh 500,000.00 500,000.00 0.04 1.00 500,000.00 1.00 500,000.00 0.04
5 Dokumentasi/Administrasi/Asbuil Drawing 1.00 Paket 5,000,000.00 5,000,000.00 0.35 0.25 1,250,000.00 0.25 1,250,000.00 0.09
JUMLAH 42,500,000.00 3.01 0.00 27,750,000.00 27,750,000.00 1.97
II. PEKERJAAN TANAH DAN PONDASI
1 Galian Pelebaran Kolam dan Galian Sendimen Pendangkalan 2,358.40 M3 49,426.00 116,566,278.40 8.26 471.68 23,313,255.68 471.68 23,313,255.68 1.65
2 Timbunan Tanah Pilihan ( didatangkan ) 180.00 M3 126,610.00 22,789,800.00 1.61 - - - - -
3 Pekerjaan Cerucuk Bambu T=1 m' ( terpancang ) 300.00 Bh 30,000.00 9,000,000.00 0.64 - - - - -
4 Lantai Kerja Beton Cor t= 15 cm ( Kolom ) 3.64 M3 919,786.53 3,348,022.97 0.24 - - - - -
5 Pasangan Pondasi batu belah 1 PC : 4 PP ( Talud ) 348.00 M3 1,042,101.50 362,651,322.00 25.69 - - - - -
JUMLAH 514,355,423.37 36.44 0.00 23,313,255.68 23,313,255.68 1.65
III. PEKERJAAN BETON BERTULANG
1 Pek. Tiang Kolom Uk.20/30 cm 13.39 M3 6,129,000.00 82,067,310.00 5.81
2 Pek. Balok Bawah Uk. 20/25 cm 12.00 M3 5,648,300.00 67,779,600.00 4.80
3 Pek. Balok Atas Uk. 20/40 cm 19.20 M3 6,471,300.00 124,248,960.00 8.80
Pekerjaan Cicin Beton Bertulang,Dia" 110 t= 80 cm, Tebal 10 cm dan Dia" 80
4 74.88 M3 2,856,900.00 213,924,672.00 15.16
t=60 cm Tebal 10 cm
5 Pembuatan Mal/Bekisting Cicin Beton dari Kayu 30.00 Unit 350,000.00 10,500,000.00 0.74
JUMLAH 498,520,542.00 35.32 0.00 0.00 0.00 0.00
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Acian Balok Atas 1 PC : 4 PP . 192.00 M2 42,728.13 8,203,800.96 0.58
JUMLAH 8,203,800.96 0.58 0.00 0.00 0.00 0.00
V. PEKERJAAN LANTAI PADA JALAN
1 Beton cor Pada Jalan Dan Doking Perahu 291.00 BH 919,786.53 267,657,880.23 18.96
JUMLAH 267,657,880.23 18.96 0.00 0.00 0.00 0.00
VI. PEKERJAAN PENGECATAN
1 Cat Tembok 192.00 Unit 26,901.00 5,164,992.00 0.37
JUMLAH 5,164,992.00 0.37 0.00 0.00 0.00 0.00
VII. PENGADAAN DAN PEMASANGAN LAMPU SOLAR CELL
1 Pengadaan dan Pemasangan Lampu PJU Solar Cell 3.00 Taksir 15,000,000.00 45,000,000.00 3.19
JUMLAH 45,000,000.00 3.19 0.00 0.00 0.00 0.00
VIII. PEKERJAAN LAIN-LAIN
1 Pengadaan dan Pemasangan Bolder ( Fabrikasi Lokal ) 10.00 Unit 3,000,000.00 30,000,000.00 2.13
JUMLAH 30,000,000.00 2.13 0.00 0.00 0.00 0.00

JUMLAH 1,411,402,638.56 100.00 0.00 51,063,255.68 51,063,255.68 3.62

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager
REKAPITULASI
MONTHLY CERTIFICATE (MC)
MEI 2018 (MC-01)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 01
LOKASI : KABUPATEN SIMEULUE BULAN : MEI
SUMBER DANA : APBA PERIODE : 11 MEI s/d 31 MEI
TAHUN ANGGARAN : 2018 TANGGAL : 31 MEI 2018
PERUSAHAAN : CV. ASFAR RAYA HALAMAN : 1 dari 2
NO. KONTRAK : 02/KPA.07/PELAYARAN/2018
TANGGAL KONTRAK : 11 MEI 2018

KONTRAK JUMLAH PEMBAYARAN


PEKERJAAN SELURUH
NO URAIAN PEKERJAAN JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI KET.
BOBOT (%) SENDIRI PEKERJAAN
(Rp)
(Rp) (Rp) (Rp) (%) (%)

I. PEKERJAAN PERSIAPAN 42,500,000.00 3.01 0.00 0.00 0.00 0.00 0.00


II. PEKERJAAN TANAH DAN PONDASI 514,355,423.37 36.44
III. PEKERJAAN BETON BERTULANG 498,520,542.00 35.32
IV. PEKERJAAN PASANGAN DAN PLESTERAN 8,203,800.96 0.58
V. PEKERJAAN LANTAI PADA JALAN 267,657,880.23 18.96
VI. PEKERJAAN PENGECATAN 5,164,992.00 0.37
VII. PENGADAAN DAN PEMASANGAN LAMPU SOLAR CELL 45,000,000.00 3.19
VIII. PEKERJAAN LAIN-LAIN 30,000,000.00 2.13

I JUMLAH 1,411,402,638.56 100.00 0.00 0.00 0.00 0.00


II JUMLAH TOTAL 141,140,263.86 0.00 0.00 0.00
III PPN 10% 1,552,542,902.42 0.00 0.00 0.00
IV DIBULATKAN 1,552,540,000.00 0.00 0.00 0.00

V JUMLAH KOTOR SERTIFIKAT S/D BULAN INI 0.00 S/D BULAN INI
VI JUMLAH KOTOR SERTIFIKAT S/D BULAN LALU 0.00
VII JUMLAH KOTOR SERTIKAT BULAN INI (V) - (VI) 0.00
POTONGAN: BULAN INI
VIII PENGEMBALIAN UANG MUKA (VII) x 20% 0.00
IX RETENSI (VII) x 5% 0.00
X JUMLAH POTONGAN (VIII) + (IX) 0.00 S/D BULAN LALU
XI JUMLAH BERSIH SERTIFIKAT BULAN INI (VII) - (X) 0.00
XII JUMLAH BERSIH SERTIFIKAT BULAN INI DIBULATKAN 0.00

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager

Mengetahui/Menyetujui:
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

T. Faisal, ST, MT
NIP: 19750114 200312 1 003
MONTHLY CERTIFICATE (MC)

PEKERJAAN : PENINGKATAN DERMAGA RAKYAT DESA LAMEREM KAB. SIMEULUE (DOKA) SERTIFIKAT : 01
LOKASI : KABUPATEN SIMEULUE BULAN : MEI
SUMBER DANA : APBA TANGGAL : 31 MEI 2018
TAHUN ANGGARAN : 2018 HALAMAN : 1 dari 2
PERUSAHAAN : CV. ASFAR RAYA
NO. KONTRAK : 02/KPA.07/PELAYARAN/2018
TANGGAL KONTRAK : 11 MEI 2018

KONTRAK REALISASI
S/D BULAN LALU BULAN INI S/D BULAN INI BOBOT
NO URAIAN PEKERJAAN HARGA SAT. JUMLAH HARGA BOBOT
VOLUME JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA %
(Rp) (Rp) % VOLUME VOLUME VOLUME
(Rp) (Rp) (Rp)
I. PEKERJAAN PERSIAPAN
1 Biaya Mobilisasi dan Demobilisasi 1.00 Paket 22,000,000.00 22,000,000.00 1.56
2 Pengukuran 1.00 Paket 5,000,000.00 5,000,000.00 0.35
3 Bangunan Direksikeet dan Barak Kerja 1.00 Unit 10,000,000.00 10,000,000.00 0.71
4 Papan Nama Proyek 1.00 Bh 500,000.00 500,000.00 0.04
5 Dokumentasi/Administrasi/Asbuil Drawing 1.00 Paket 5,000,000.00 5,000,000.00 0.35
JUMLAH 42,500,000.00 3.01 0.00 0.00 0.00 0.00
II. PEKERJAAN TANAH DAN PONDASI
1 Galian Pelebaran Kolam dan Galian Sendimen Pendangkalan 2,358.40 M3 49,426.00 116,566,278.40 8.26
2 Timbunan Tanah Pilihan ( didatangkan ) 180.00 M3 126,610.00 22,789,800.00 1.61
3 Pekerjaan Cerucuk Bambu T=1 m' ( terpancang ) 300.00 Bh 30,000.00 9,000,000.00 0.64
4 Lantai Kerja Beton Cor t= 15 cm ( Kolom ) 3.64 M3 919,786.53 3,348,022.97 0.24
5 Pasangan Pondasi batu belah 1 PC : 4 PP ( Talud ) 348.00 M3 1,042,101.50 362,651,322.00 25.69
JUMLAH 514,355,423.37 36.44 0.00 0.00 0.00 0.00
III. PEKERJAAN BETON BERTULANG
1 Pek. Tiang Kolom Uk.20/30 cm 13.39 M3 6,129,000.00 82,067,310.00 5.81
2 Pek. Balok Bawah Uk. 20/25 cm 12.00 M3 5,648,300.00 67,779,600.00 4.80
3 Pek. Balok Atas Uk. 20/40 cm 19.20 M3 6,471,300.00 124,248,960.00 8.80
Pekerjaan Cicin Beton Bertulang,Dia" 110 t= 80 cm, Tebal 10 cm dan Dia" 80
4 74.88 M3 2,856,900.00 213,924,672.00 15.16
t=60 cm Tebal 10 cm
5 Pembuatan Mal/Bekisting Cicin Beton dari Kayu 30.00 Unit 350,000.00 10,500,000.00 0.74
JUMLAH 498,520,542.00 35.32 0.00 0.00 0.00 0.00
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Acian Balok Atas 1 PC : 4 PP . 192.00 M2 42,728.13 8,203,800.96 0.58
JUMLAH 8,203,800.96 0.58 0.00 0.00 0.00 0.00
V. PEKERJAAN LANTAI PADA JALAN
1 Beton cor Pada Jalan Dan Doking Perahu 291.00 BH 919,786.53 267,657,880.23 18.96
JUMLAH 267,657,880.23 18.96 0.00 0.00 0.00 0.00
VI. PEKERJAAN PENGECATAN
1 Cat Tembok 192.00 Unit 26,901.00 5,164,992.00 0.37
JUMLAH 5,164,992.00 0.37 0.00 0.00 0.00 0.00
VII. PENGADAAN DAN PEMASANGAN LAMPU SOLAR CELL
1 Pengadaan dan Pemasangan Lampu PJU Solar Cell 3.00 Taksir 15,000,000.00 45,000,000.00 3.19
JUMLAH 45,000,000.00 3.19 0.00 0.00 0.00 0.00
VIII. PEKERJAAN LAIN-LAIN
1 Pengadaan dan Pemasangan Bolder ( Fabrikasi Lokal ) 10.00 Unit 3,000,000.00 30,000,000.00 2.13
JUMLAH 30,000,000.00 2.13 0.00 0.00 0.00 0.00
JUMLAH 1,411,402,638.56 197.87 0.00 0.00 0.00

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN CV. CATRO ENGINEERING CV. ASFAR RAYA
DINAS PERHUBUNGANACEH

AL MUNAWAR HUSLAN ERIN SIMBARA, ST FACHRURRAZI, ST


NIP: 19820417 201212 1 002 Chief Inspector Site Manager
REKAPITULASI
MONTHLY CERTIFICATE (MC)
JUNI 2017 (MC-02)

PEKERJAAN : XXX SERTIFIKAT : 02


LOKASI : XXX BULAN : XXX
SUMBER DANA : XXX PERIODE : 01 JUN s/d 30 JUN
TAHUN ANGGARAN : XXX TANGGAL : 30 JUNI 2017
PERUSAHAAN : XXX HALAMAN : 1 dari 3
NO. KONTRAK : XXX
TANGGAL KONTRAK : XXX

KONTRAK JUMLAH PEMBAYARAN


PEKERJAAN SELURUH
NO URAIAN PEKERJAAN JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI KET.
BOBOT (%) SENDIRI PEKERJAAN
(Rp) (Rp) (Rp) (Rp) (%) (%)

A. PEKERJAAN PERSIAPAN #VALUE! #VALUE! 0.00 0.00 0.00 0.00 0.00

B. PEKERJAAN JETTY KIRI #VALUE! #VALUE! 0.00 0.00 0.00 0.00 0.00

I JUMLAH #VALUE! #VALUE! 0.00 0.00 0.00 0.00


II JUMLAH TOTAL #VALUE! 0.00 0.00 0.00
III PPN 10% #VALUE! 0.00 0.00 0.00
IV DIBULATKAN XXX 0.00 0.00 0.00

V JUMLAH KOTOR SERTIFIKAT S/D BULAN INI 0.00 S/D BULAN INI
VI JUMLAH KOTOR SERTIFIKAT S/D BULAN LALU 0.00
VII JUMLAH KOTOR SERTIKAT BULAN INI (V) - (VI) 0.00
POTONGAN: BULAN INI
VIII PENGEMBALIAN UANG MUKA (VII) x 20% 0.00
IX RETENSI (VII) x 5% 0.00
X JUMLAH POTONGAN (VIII) + (IX) 0.00 S/D BULAN LALU
XI JUMLAH BERSIH SERTIFIKAT BULAN INI (VII) - (X) 0.00
XII JUMLAH BERSIH SERTIFIKAT BULAN INI DIBULATKAN 0.00

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN XXX XXX
DINAS PERHUBUNGANACEH

AL MUNAWAR XXX XXX


NIP: 19820417 201212 1 002 Team Leader Project Manager

Mengetahui/Menyetujui:
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

T. Faisal, ST, MT
NIP: 19750114 200312 1 003
MONTHLY CERTIFICATE (MC)

PEKERJAAN : XXX SERTIFIKAT : 02


LOKASI : XXX BULAN : JUNI
SUMBER DANA : XXX TANGGAL : 30 JUNI 2017
TAHUN ANGGARAN : XXX HALAMAN : 2 dari 3
PERUSAHAAN : XXX
NO. KONTRAK : XXX
TANGGAL KONTRAK : XXX

KONTRAK REALISASI
S/D BULAN LALU BULAN INI S/D BULAN INI BOBOT
NO URAIAN PEKERJAAN HARGA SAT. JUMLAH HARGA BOBOT
VOLUME JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA %
(Rp) (Rp) % VOLUME VOLUME VOLUME
(Rp) (Rp) (Rp)
A. PEKERJAAN PERSIAPAN
1 XXX XXX Ls XXX #VALUE! #VALUE! - - - - - -
2 XXX XXX Ls XXX #VALUE! #VALUE! - - - - - -
3 XXX XXX Ls XXX #VALUE! #VALUE! - - - - - -
4 XXX XXX m2 XXX #VALUE! #VALUE! - - - - - -
5 XXX XXX Ls XXX #VALUE! #VALUE! - - - - - -
6 XXX XXX Ls XXX #VALUE! #VALUE! - - - - - -
7 XXX XXX Ls XXX #VALUE! #VALUE! - - - - - -
Sub Jumlah A #VALUE! #VALUE! - - -

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN XXX XXX
DINAS PERHUBUNGANACEH

AL MUNAWAR XXX XXX


NIP: 19820417 201212 1 002 Team Leader Project Manager
MONTHLY CERTIFICATE (MC)

PEKERJAAN : XXX SERTIFIKAT : 02


LOKASI : XXX BULAN : JUNI
SUMBER DANA : XXX TANGGAL : 30 JUNI 2017
TAHUN ANGGARAN : XXX HALAMAN : 3 dari 3
PERUSAHAAN : XXX
NO. KONTRAK : XXX
TANGGAL KONTRAK : XXX

KONTRAK REALISASI
S/D BULAN LALU BULAN INI S/D BULAN INI BOBOT
NO URAIAN PEKERJAAN HARGA SAT. JUMLAH HARGA BOBOT
VOLUME JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA %
(Rp) (Rp) % VOLUME VOLUME VOLUME
(Rp) (Rp) (Rp)
B. PEKERJAAN JETTY KIRI
1 XXX XXX m2 XXX #VALUE! #VALUE! - - - - - -
2 XXX XXX m3 XXX #VALUE! #VALUE! - - - - - -
3 XXX XXX m3 XXX #VALUE! #VALUE! - - - - - -
4 XXX XXX m3 XXX #VALUE! #VALUE! - - - - - -
5 XXX XXX m3 XXX #VALUE! #VALUE! - - - - - -
Sub Jumlah B #VALUE! #VALUE! - - -

Disetujui oleh : Diperiksa oleh : Diajukan oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultan Pengawas Kontraktor Pelaksana
BIDANG PELAYARAN XXX XXX
DINAS PERHUBUNGANACEH

AL MUNAWAR XXX XXX


NIP: 19820417 201212 1 002 Team Leader Project Manager