Anda di halaman 1dari 14

Risk-Based Maintenance (RBM):

A New Approach for Process Plant


Inspection and Maintenance
Faisal I. Khan and Mahmoud Haddara
Faculty of Engineering and Applied Science, Memorial University of Newfoundland, St. John’s Newfoundland A1B 3X5, Canada;
fkhan@engr.mun.ca (for correspondence)

Published online 16 November 2004 in Wiley InterScience (www.interscience.wiley.com). DOI 10.1002/prs.10010

This paper discusses recently proposed methodology INTRODUCTION


for the design of an optimum maintenance manage- Plant safety is directly linked to the reliability of its
ment program. The methodology is based on integrat- operation. Higher reliability may be achieved through a
ing a reliability approach and a risk assessment strat- robust inspection and maintenance program. This is of
egy to obtain an optimum maintenance schedule. The particular importance in process industries because
method is called risk-based maintenance (RBM). First, they deal with hazardous substances under severe op-
the likely equipment failure scenarios are formulated. erating conditions. For achieving safe and efficient pro-
Out of the many likely failure scenarios, the ones that cess plant performance, it is essential to minimize and,
are most credible are subjected to a detailed study. if possible, to eliminate unscheduled breakdowns (fail-
Detailed consequence analysis is done for the selected ures). This could be achieved through an effective and
scenarios. Subsequently, a fault tree analysis is per- efficient inspection and maintenance management pro-
formed to determine the probability of failure. Finally, gram. In addition to the safety and reliability issues, the
risk is computed by combining the consequence anal- importance of effective and efficient maintenance man-
ysis and the probability analysis results. The calculated agement planning cannot be overemphasized. In a
risk is compared against known acceptable criteria. span of 50 years, maintenance policies underwent a
The frequency of maintenance tasks is obtained by paradigm shift. The concept of maintenance manage-
minimizing the estimated risk. The proposed method- ment changed from a necessary evil, performed primar-
ology is used to answer two questions: Which equip- ily as corrective action, into an integrated part of a total
ment should be included in a scheduled maintenance management system, actively participating in the
program? When should the maintenance be scheduled? achievement of the organization’s main objectives
Offshore oil and gas process facilities involve haz- [1, 2].
ardous chemicals (highly flammable and toxic) at ex- At the beginning of the twentieth century, the ASME
treme conditions of temperature and pressure. Proper Code focused principally on performance criteria to
maintenance of process equipment is one of the impor- improve safety and reduce the frequency of failure,
tant activities to ensure safe and continuous operation addressing pressure vessel and piping systems in par-
of the facility. RBM methodology has been used to ticular. Later, the importance of risk (event probability
develop a detailed maintenance plan for safe and fault multiplied by the consequences) was recognized as an
free operation of the facility. © 2004 American Institute important measure of system safety, and it was seen
of Chemical Engineers Process Saf Prog 23: 252–265, that risk analysis could be applied to design, material
2004 selection, defect criteria, fabrication, operation, main-
Keywords: maintenance planning, risk, risk-based tenance, and inspection. The risk has been, typically,
maintenance, risk assessment, reliability calculated in terms of cost (economic loss) and human
injury/death per unit time or cycle. The event proba-
Presented at the 37th Annual Loss Prevention Symposium, March 31–April 3, bility value can be calculated by considering a number
2003, New Orleans, LA.
of influencing variables such as system characteristics
© 2004 American Institute of Chemical Engineers (design, material selection, material defects, fabrica-

252 December 2004 Process Safety Progress (Vol.23, No.4)


Table 1. Risk matrix used by ASME SC6000 code.

Event Probability*
Consequence
Severity 100 ⬎ Event Probability ⬎ 10⫺2 10⫺2 ⬎ Event Probability ⬎ 10⫺4
Category Description Frequent (A) Probable (B) Occasional (C) Remote (D)
I Catastrophic 1 1 2 3
II Critical 1 2 3 4
III Marginal 2 3 4 5
IV Negligible 3 4 5 6

*1: high risk; 2: medium risk; 3: low risk; 4, 5, 6: tolerable risk.

tion), human factors, inspection, media, operation, and safety issues, but also takes into account other factors
maintenance [3– 6]. such as the off-site risk to the surrounding communi-
The ASME tentative standard SC6000 Hazardous Re- ties, environment, and the costs associated with busi-
lease Protection provides a risk-based criterion to pro- ness interruption. In applying the RBI process to a
tect personnel from hazards where both the probability plant, the facility needs to be considered in terms of
of failure of a system or one of its components and the individual process units, systems within these units,
consequences of personal injury resulting from such and components that constitute these systems. The
failure are judged [7, 8]. Protection can take many forms extent of the breakdown in process, system, and com-
such as remote locations, barriers, containment, con- ponent depends on the particular system being consid-
trolled venting or suppression, chemical inerting, or ered [2, 3, 6].
neutralizing. Protection methods usually affect conse- The proposed RBM methodology aims at optimizing
quences of component failure and performance meth- maintenance tasks while maintaining a high level of
ods typically affect event probability of failure. The equipment availability. This is achieved by a study of
proposed ASME SC6000 Hazardous Release Protection all possible failure modes, determining a realistic esti-
Standard (ASME, tentative standard) was discussed by mate for the level of risk associated with each failure
Brown [9]. Brown and Brown [7] suggest guidelines mode, and designing a maintenance strategy that min-
with respect to procedures and criteria in determining imizes the occurrence of the high-risk failure modes.
what can be considered a suitable protection from This paper has two main objectives: (1) to present a
hazardous release. SC6000 provides risk criteria only brief description of the methodology and (2) to discuss
for hazards to personnel (primary receptors); however, its application to an offshore process facility. This case
it may also be used to assess risk associated with study serves to illustrate the methodology and shows
economic loss and environmental damage (secondary the type or results that can be expected from such a
and protective receptors). No system limits are im- method.
posed by SC6000 except as specified by the system
standards and design [3]. THE RISK-BASED MAINTENANCE METHODOLOGY
The ASME SC6000 involves six main steps [8]. These The recently proposed risk-based maintenance
are: (1) identification of hazards from pressure systems; (RBM) methodology aims to reduce the overall risk of
(2) estimate of the magnitude of hazards; (3) perfor- the operating facilities [6]. In areas of high and medium
mance criteria for personnel according to severity cat- risk, a focused maintenance effort is required, whereas
egories; (4) risk assessment using two levels: Level in areas of low risk the effort is minimized. RBM sug-
I—without protective systems and Level II—inclusion gests a set of recommendations on how many preven-
of protective methods; (5) optional redesign of the tive tasks (the type and frequency) are required. The
source system or an iterative redesign of the protective quantitative value of risk is the basis for prioritization of
system if the risk is not tolerable; and (6) repeat steps 1 inspection and maintenance activities. Detailed de-
to 5 for each hazard and type of receptor as identified. scription of the methodology is presented in the sub-
ASME SC6000 quantifies risk on a scale of 1 to 6 sequent sections.
based on a 4 ⫻ 4 matrix of event probability (A, B, C, The RBM methodology is composed of three mod-
D) vs. consequence severity (I, II, III, IV) as shown in ules that are interactively linked. The RBM process
Table 1 [8]. A risk of 3 or greater is considered a starts with dividing the complete system under study
tolerable risk (Table 1). into small manageable units. Each unit is subjected to
The concept of risk-based inspection and mainte- the different steps shown in Figures 1, 2, and 3. The
nance (RBI) was developed to achieve tolerable risk risk, computed for a specific failure scenario(s) of a
criteria. In this policy, the high-risk components are unit, is compared against the acceptance criteria. If the
inspected and maintained with greater frequency than risk exceeds the criteria, the failure scenario is revalu-
that used to inspect components associated with lower ated for optimal maintenance/inspection duration that
risk. RBI is a part of a broader risk management pro- would bring down the exceeded risk to an acceptable
gram that considers not only the assessment of on-site level. This process is repeated for each unit. Results

Process Safety Progress (Vol.23, No.4) December 2004 253


Figure 1. Description of risk estimation module.

obtained for all units are combined to develop an tion of a scenario does not mean it will indeed occur, but
overall maintenance plan for the system. Detailed de- that there is a possibility of its occurrence. Failure scenar-
scription of each step of RBM methodology is pre- ios are generated based on the operational characteristics
sented in a subsequent section. of the system, physical conditions under which operation
occur, geometry of the system, and safety arrangements.
Module I: Risk Estimation Recently Khan [10] proposed a systematic procedure—
This module is composed of four steps that are maximum credible accident scenario (MCAS)—to eval-
logically linked, as shown in Figure 1. A brief descrip- uate failure (accident) scenarios in a process system.
tion of each step is presented below. The developed failure scenarios may be screened to
shortlist those that are more relevant for the scope of
Step I.1: Failure Scenario Development the study. This approach optimizes the effort without
A scenario is a description of a typical situation (a set compromising the accuracy of the overall study results.
of possible events or situations) that leads to failure event. It is advisable to consider one or two most appropriate
It is the basis of risk study; it tells us what may happen so failure scenarios for each unit. MCAS may be used as a
that we can devise ways and means of preventing or tool to shortlist (screen unimportant scenarios) failure
minimizing the possibility of its occurrence. The expecta- scenarios.

254 December 2004 Process Safety Progress (Vol.23, No.4)


Figure 2. Description of risk evaluation model.

Step I.2: Consequence Assessment damage zones attributed to fires, explosion, and toxic
The objective here is to quantify the potential con- load. Finally, toxic gas models are used to predict
sequences of the credible failure scenario. Initially, human response to different levels of exposures to
consequences are quantified in terms of damage radii toxic chemicals. There are many computational tools
(the radius of the area in which the damage would available to conduct this step such as WHAZAN-II,
readily occur), damage to property, and toxic effects PHAST, SAFETI (DNV, The Netherlands), OHRA toolkit
(chronic/acute toxicity). The calculated damage radii (DNV, Norway), RISK (AEA technology, UK), and
are later used to assess human health and environmen- SQRM (Electrowatt Ltd., UK), and MAXCRED (CPET,
tal and production losses (in terms of dollars). This
India). A review of these software capabilities and de-
allows one to distinguish between prioritization per-
tails of MAXCRED are discussed in Khan and Abbasi
formed on each category. It is of great practical benefit
to separate the consequences of failure analysis from [11]. MAXCRED is one of the recent tools that uses the
the consequences of failure mode analysis. latest models of fires, explosions, and toxic release and
The assessment of consequences involves a wide dispersion [11] to calculate damage radii. The main data
variety of mathematical models. For example, source inputs required by MAXCRED are: operating tempera-
models are used to predict the rate of release of haz- ture, operating pressure, physicochemical properties
ardous materials, the degree of flashing, and the rate of (phase, heat of combustion, densities, etc.), atmo-
evaporation. Models for explosions and fires are used spheric conditions (temperature pressure, wind speed),
to predict the characteristics of explosions and fires. and level of confinement. MAXCRED is available from
The impact-intensity models are used to predict the the author (Faisal Khan) for academic use.

Process Safety Progress (Vol.23, No.4) December 2004 255


Figure 3. Description of maintenance planning module.

The total consequences assessment is a combination Financial loss. Factor B accounts for the damage to
of four major categories of consequences (described the property of asset lost and may be estimated for each
below). The method of quantification of these four accident scenario using the following relation:
categories may change according to the scope of the
study undertaken. In the present context—process op- B i ⫽ damage area ⫻ asset density (2)
eration—these are defined as follows.
System performance loss. Factor A accounts for the
system’s performance loss resulting from failure of the
system or part of the system. This is estimated in terms
B⫽ 冘B
i⫽1,n
i (3)

of dollars lost using the following equation:


where i denotes the number of events, such as fire,
A i ⫽ total time lost ⫻ loss rate (1) explosion, toxic release, and the like. Asset density is
measured in terms of $/area.
Loss rate ($/time) depends on the importance of the Human health loss. Similar to the factor for financial
unit to the production system. loss, the human health loss factor is estimated in terms

256 December 2004 Process Safety Progress (Vol.23, No.4)


Figure 4. Simplified process flow diagram of process operation on a typical offshore platform.

of dollars for each accident scenario using the follow- IM is the importance factor and ranges from 0.1 to 1.0.
ing equation: If the damage radius is higher than the distance be-
tween the accident location and the location of sensi-
C i ⫽ damage area ⫻ population density ⫻ PDF (4) tive ecosystem, a value of 1.0 is taken. This parameter
is quantified with the help of earlier work of Khan and
⫻ dollar value of human health Abbasi [13]. The following values are suggested for the

C⫽ 冘C
i⫽1,n
i (5)
environment media: 0.1 for air (coastal zone), 0.5 for
water body, and 0.8 for soil.

Step I.3: Probabilistic Failure Analysis


The PDF defines the population distribution factor, Probabilistic failure analysis is conducted using fault
which reflects the heterogeneity of the population dis- tree analysis (FTA), which is an analytical tool that uses
tribution. If the population is uniformly distributed in deductive reasoning to determine the occurrence of an
the region of study (⬃500 m radius), the factor is undesired event. One can use a fault tree analysis along
assigned a value of 1; if the population is localized and with component failure data and human reliability data
away from the point of accident occurrence the lowest to determine the frequency of occurrence of an event
value 0.2 is assigned. Values for this parameter have or probability of failure for defined period of time.
been adapted from the latest work of Hirst and Carter In this step of RBM, fault trees are constructed for
[12]. Population density is measured in terms of popu- various likely initiating events, which may eventually
lation per unit area. The dollar value of human health lead to the “top” event or the failure scenario. To
will change from place to place and will also depend facilitate probabilistic fault tree analysis a methodology
on the extent of the work stress. In the present work a designated “analytical simulation” and a complete au-
value of 1.0E⫹6, is used. tomated tool—PROFAT—was also developed. It is be-
Environment and/or ecological loss. Factor D ac- yond the scope of this paper to discuss details of
counts for ecosystem damage, which can be estimated methodology and the automated tool. Interested read-
as ers may see details in Khan and Abbasi [14, 15]. PRO-
FAT is available from the author free of charge for
D i ⫽ damage area ⫻ IM ⫻ environment media (6) academic use.
⫻ dollar value of environmental damage Step I.4: Risk Estimation

冘D
Based on the results of the consequence analysis
D⫽ i (7) and probabilistic failure analysis, the risk posed by
i⫽1,n each unit was estimated. The consequence analysis

Process Safety Progress (Vol.23, No.4) December 2004 257


Table 2. Failure scenarios and their likely consequences in terms of dollars lost.

Accidence Consequences**
Section Scenario* Accidence Scenario Description (million dollars lost)
Separation BLEVE Explosure release of crude oil from 186.12
section followed by any of the unit which on burning
fire ball causing heat, shock wave, and toxic
load
Low-pressure BLEVE Release of hydrocarbon gas from any 40.74
compression followed by of the unit which on burning
section fire ball causing heat, shock wave, and toxic
load
Medium-pressure BLEVE Instantaneous Release of hydrocarbon 382.17
compression followed by gas from any of the unit which on
section fire ball burning causing heat, shock wave,
and toxic load
High-pressure BLEVE Explosive release of hydrocarbon gas 814.70
compression followed by from any of the unit which on
section fire ball burning causing heat, shock wave,
and toxic load

*BLEVE, boiling liquid expanding vapor explosion.


**Appendix I provides an illustrative example of how the consequences are converted to dollar values.

encompasses factors of fatality, economics, the envi- Module III: Maintenance Planning
ronment, and the system performance losses. Thus, the Units marked in Module II are studied in detail to
level of risk calculated reflects the total risk for the reduce the risk through optimal maintenance planning.
system. The computed risk will be evaluated against This module consists of two steps, which are logically
the acceptance criteria in the next module. linked, as shown in Figure 3. A brief account of each
step is discussed below.
Module II: Risk Evaluation Step III.1: Estimation of Optimal Maintenance Duration
This module of RBM is aimed to evaluate the earlier Units whose risk exceeds the acceptance criteria are
computed risk through the algorithm shown in Figure each subjected to detailed investigation. The investiga-
2. This module consists of two steps as detailed below. tion includes identification of basic causes of failure
and their functions. Using these details a reverse fault
Step II.1: Setting Up Acceptance Criteria tree analysis is conducted for a targeted value of top
As acceptance of risk may be different from one event (component failure probability/rate). This analy-
organization to another and from one system to an- sis gives an optimal maintenance time for the compo-
other; the present authors have suggested an open- nent under study. This process is repeated for all units/
ended methodology. In this step the user sets up risk components in this category. A maintenance plan can
acceptance criteria that depend on the scope of the then be developed based on maintenance times arrived
study, the criticality of the system, and the policy or at in the previous step.
strategy of the organization. Some of the commonly
used risk criteria are ALARP (as low as reasonably Step III.2: Reestimation and Reevaluation of Risk
possible), HSE land use planning criteria, Dutch crite- This is an optional step and aimed at verifying that
ria, and Advisory Committee on dangerous substances the maintenance plan developed will produce an ac-
(ACDS) risk criteria. For example, according to Dutch cepted risk level for the complete system. In this step,
risk criteria, risk of one or less fatality, having proba- step 4 of Module I and step 2 of Module II are repeated
bility of occurrence 10⫺5 (per year), is acceptable. using revised values for the failure probabilities. The
result of this step will clearly determine whether the
developed maintenance plan is effective in the manag-
Step II.2: Risk Comparison against Acceptance Criteria ing risk.
The risk computed in Module I is compared against
the risk acceptance criteria setup in the previous step. Application of RBM to an Offshore Process
A unit/component whose risk exceeds the acceptance Facility
criteria is marked for further analysis to reduce its risk.
The exercise is repeated for all the units/components Process Description
of the system. The marked units are subsequently pro- The above methodology has been used to develop a
cessed in Module III for maintenance planning. maintenance plan for a process facility on an offshore

258 December 2004 Process Safety Progress (Vol.23, No.4)


Table 3. Results of consequence (output of MAXCRED) for probable failure scenario of separation section.

Parameter Value
Explosion: BLEVE
Total energy released, kJ 7.0E⫹06
Peak overpressure, kPa 199.00
Variation of overpressure in air, kPa/s 136.00
Shock velocity of air, m/s 511.00
Duration of shock wave, ms 37.0
Missile characteristics
Initial velocity, m/s 39.00
Kinetic energy of fragment, kJ 1.47E⫹03
Fragment velocity at study point, m/s 38.00
Penetration ability at study point (based on empirical models)
Concrete structure, m 0.005
Brick structure, m 0.007
Steel structure, m 0.003
Damage radii (DR) for various degrees of damage due to overpressure
DR for 100% damage, m 20
DR for 100% fatality or 50% damage, m 30
DR for 50% fatality or 25% damage, m 44
Damage radii (DR) for various degrees of damage due to missile
DR for 100% damage or 100% fatality, m 1046
DR for 50% damage or 100% fatality, m 1131
DR for 100% fatality or 10% damage, m 1208
Fire: fireball
Radius of the fireball, m 245.00
Duration of the fireball, s 100.00
Energy released by fireball, kJ 8.85E⫹08
Radiation heat flux, kJ/m2 337,993.00
Damage radii (DR) due to thermal load
DR for 100% fatality/damage, m 177
DR for 50% fatality/damage, m 222
DR for 100% third degree of burn, m 256
DR for 50% third degree of burn, m 329
Toxic release and dispersion
Box instantaneous model: evevated source
Concentration at distance of 200 m, kj/m3 2.56E-01
Heavy gas puff characteristics
Ground level concentration of puff, kg/m3 1.52E-01
Ground level concentration on puff axis, kg/m3 1.52E-02
Cloud radius, m 5.51E⫹02
Maximum distance traveled by the cloud, m 6.56E⫹02
Maximum ground level concentration, kg/m3 2.91E⫹02
Damage radii (DR) for various degrees of damage
DR for 100% lethality, m 6084
DR for 50% lethality, m 7820
DR for 10% lethality, m 14,011

Process Safety Progress (Vol.23, No.4) December 2004 259


Figure 5. Fault tree for failure scenario in separation section; basic events (numbers in circle) are explained in
Table 4.

platform. The purpose of the offshore production plat- system (section) are listed in Table 2. These failure
form is to operate the wells, and to separate the fluid scenarios have been subjected to consequence assess-
produced from the wells into oil, gas condensate, gas, ment.
and water. The well fluid passes through separators Consequence analysis. Consequence analysis has
where it is separated into the four major components. been carried out for all envisaged failure scenarios for
The oil and gas condensate are subsequently pumped each of the four subsystems. Because most of the units
to an onshore facility. Gas is compressed using centrif- involve processing of chemicals at extreme operating
ugal compressors. Compressed gas is passed through conditions (high temperature and pressure), the con-
the flash drum where the pressure is reduced. The sequences of any failure would be extensive. Table 3
resulting condensate is separated out. The gas is sub- shows the results of a typical failure scenario (results of
sequently dried and purified. It is further compressed MAXCRED) in the separation section. It is evident from
to higher pressure using reciprocating compressors. the table that release of crude oil and its combustion
Part of the gas is used at the wells and for power would cause severe consequences. A devastating
generation on the platform. The remaining gas is shock wave can be expected to cover an area of more
pumped back with a small amount being flared. A than 40 m radius, a lethal heat load would be operative
simplified process flow diagram is presented in Fig- over an area of more than 325 m radius, and a toxic
ure 4. load is likely to build up over an area of 14 km radius.
These consequences clearly indicate that most of the
Module I: Risk Estimation facilities and personnel on board are likely to be af-
Failure scenarios. The complete process system has fected by any such eventuality. This indicates that the
been divided into four functional subsystems according consequences will result in human fatalities as well as
to their operational characteristic (Figure 4). The most environmental damage. To homogenize the conse-
credible failure scenarios developed for each sub- quences and bring them to the same scale, we have

260 December 2004 Process Safety Progress (Vol.23, No.4)


Table 4. Details of separation section.

Unit Number in Failure Revised Failure


Figure 5 Unit Name Frequency* (h⫺1) Frequency** (h⫺1)
1 High-pressure separator 1.50E-05 7.50E-06
2 Valve 100 5.70E-5 4.60E-5
3 Mixer 100 1.50E-4 1.50E-4
4 Medium-pressure separator 3.30E-5 1.50E-5
5 Valve 101 2.50E-4 2.24E-5
6 Mixer 101 1.57E-4 1.50E-4
7 Heater 100 4.60E-5 2.32E-5
8 Low-pressure separator 6.35E-6 3.20E-6
9 Valve 102 1.56E-4 1.84E-5
10 Cooler 101 7.1E-5 7.1E-5

Safety Arrangements Installed (Figure 6)


11 Distributed node for 9.71E-5 9.71E-5
hydrocarbon detection
12 Flame detector 7.36E-6 7.36E-6
13 Fire suppression system 5.00E-6 5.00E-6
14 Distributed emergency 1.39E-4 1.39E-4
shut down system

*Failure data obtained from OREDA [16].


**Failure frequencies calculated on the basis of target risk value.

Table 5. Typical out from PROFAT software.

Event Not Improvement


Occurring Failure Frequency (h⫺1) Improvement Index
0 5.232692e-04 0.000000e⫹00 0.000000
1 5.083382e-04 5.972394e-05 2.856901
2 4.663616e-04 2.276302e-04 10.88871
3 5.233288e-04 2.383895e-07 0.011403
4 4.903674e-04 1.316071e-04 6.295438
5 2.673715e-04 1.023591e-03 48.96358
6 5.232692e-04 1.455192e-10 0.000007
7 5.233288e-04 2.383895e-07 0.011403
8 5.169809e-04 2.515325e-05 1.203208
9 3.673881e-04 6.235243e-04 29.82635
10 5.233288e-04 2.383895e-07 0.011403

expressed all losses (functionality, assets, human, and failure scenario. This will be done in this step. First, a
environment) in terms of dollars. The last column of fault tree is developed for the failure scenario in a
Table 2 illustrates the results of consequences analysis particular processing section. Figure 5 illustrates the
in terms of lost dollars. How these are calculated is typical fault tree for separation section. The developed
shown with help from an example in Appendix A. It fault trees are subsequently simulated using analytical
may be concluded from this analysis (Table 2) that the simulation approach and PROFAT software. The failure
high-pressure compression section is likely to cause data for basic events (causes) used in the simulation
maximum damage, whereas the low-pressure com- study are adopted from OREDA [16]. Table 4 lists the
pression section is likely to cause the least conse- failure data adopted from OREDA [16] and Lees [17] for
quence. It is worth mentioning that each section con- the separation section. Typical output of PROFAT for a
sists of a set of units, and the consequences are failure scenario in the separation section is shown in
estimated for the most credible accident scenario in the Table 5. The right-hand column of the table indicates
section. the importance factor, which illustrates the percentage
Probabilistic failure analysis. To calculate the risk contribution of each basic event in producing this sce-
factor for each processing section, it is necessary to nario. It may be seen from Table 5 that event 5 (Valve
know the probability of occurrence of the envisaged 101) is contributing about 48% to the accident followed

Process Safety Progress (Vol.23, No.4) December 2004 261


Table 6. Results of risk estimation and evaluation module.

Failure Frequency
of Envisaged Risk Factor* Suggested Additional
Section Scenario (h⫺1) ($/h) Safety Measures
Separation 5.23E-4 9.73E⫹4 • Distributed node for
section hydrocarbon detection
• Flame detector
• Fire suppression
system
• Distributed emergency
shutdown system
Low-pressure 3.59E-4 1.45E⫹4 • Fire suppression
compression system
section • Distributed emergency
shutdown system
Medium-pressure 1.34E-07 51.28 • Fire suppression
compression system
section
High-pressure 1.02E-06 529.11 • Fire suppression
compression system
section • Distributed emergency
shutdown system

*Details of how these numbers (risk) are derived are shown in Appendix A.

by event 9 (valve 102), event 2 (valve 100), and event the details of the study for the separation section are
4 (moderate pressure separator). Controlling or main- given as follows:
taining these events will significantly reduce the total
probability of occurrence of failure. Similar studies • A fault tree for the separation section failure sce-
were conducted for the other units. nario is redeveloped after implementing addi-
Risk computation. In this step, the results of conse- tional safety measures, as shown in Figure 6.
quence and probabilistic analyses are combined to • A reverse fault tree analysis is conducted by as-
quantify the risk factors. The risk factor for each pro- signing a desired failure probability to the top
cess section is shown in Table 6. It is evident from the event (failure scenario of the unit). This assigned
table that the separation section has the maximum risk value for the failure probability is estimated con-
factor of 973.4E⫹2 $/h, and the medium compression sidering acceptable risk value. For example, for
section has the lowest risk factor of 51.3 $/h. The the separation section it is calculated as 5.373 ⫻
acceptable risk criterion for the present problem is 10⫺9.
considered as 1.0 $/h; any value higher than this is • The reverse fault tree analysis gave the optimal
unacceptable. times at which maintenance/inspection is to be
performed. For example, the optimal mainte-
Module II: Risk Evaluation nance/inspection duration of Valve 101 is esti-
By studying the risk factors estimated for the differ- mated as 32 days. Details of the steps involve in
ent sections, it is evident that the estimated risk factors estimating maintenance/inspection intervals with
for all units exceed multiple times the acceptance level. example are presented in Appendix B.
This indicates that maintenance and inspection plan • Using the revised failure frequency (rightmost col-
alone may not be sufficient to reduce risk, and thus umn of Table 6) obtained by adding the safety
additional safety measures are needed. In consider- measures and maintenance plan, fault tree analy-
ation of these facts, additional safety measures have sis is reconducted. The failure probability is cal-
been suggested for the most vulnerable units of each culated as 1.928 ⫻ 10⫺9. Using this value and
section (see last four columns of Table 4) and a new dollar consequences value (186.12 ⫻ 106) the risk
maintenance schedule was developed. The details are factor is calculated as 0.36 $/h. This value if far
discussed in next section. less than 1 $/h (target risk value); therefore, it is
safe to say the developed maintenance plan along
Module III: Maintenance Planning with safety measures are able to maintain the risk
As a first step of this study, additional safety mea- in acceptable region.
sures are suggested for each section according to its • These steps are repeated for each unit of the
requirements. Table 6 lists the suggested safety mea- system to estimate the optimal maintenance
sures. An effective maintenance and inspection plan is and/or inspection times. The detailed results for
developed for each section. To illustrate the procedure, all four sections and their units are shown in Table

262 December 2004 Process Safety Progress (Vol.23, No.4)


Figure 6. Revised fault tree for failure scenario in separation section after taking into account additional safety
measures.

7. How these maintenance/inspection intervals quantitative than available methodologies and is com-
are calculated is shown in Appendix B with illus- posed of three main modules: (1) risk estimation mod-
trative examples. ule, (2) risk evaluation module, and (3) maintenance
planning module.
Revised risk factors for all four sections have been
calculated using the results of the previous section. The The paper illustrates the applicability of the meth-
values for the revised risk factors are shown in the last odology to an offshore process facility. Among the four
column of Table 7. It is seen that the revised risk factors sections of the system, the separation section was iden-
are well within acceptable limits. tified to have the highest risk factor. Additional safety
measures are suggested and implemented to reduce
DISCUSSION AND CONCLUSIONS the probability of failure occurrence. A maintenance
In this paper we have briefly discussed the recently program is designed by using the revised system. It has
proposed methodology for a risk-based maintenance been demonstrated that this strategy reduces the high
strategy. The methodology is more comprehensive and level of risk to an acceptable level.

Process Safety Progress (Vol.23, No.4) December 2004 263


Table 7. Results of risk estimation and evaluation • How frequent should inspection/maintenance
module.* tasks be to control these failures?
Such a maintenance planning approach is expected
Maintenance Revised Risk to provide a cost-effective maintenance program. The
Schedule Factor** risk-based approach minimizes the consequences (re-
Section and Units (days) ($/h) lated to safety, economics, and environment) of a sys-
Separation section tem outage/failure. This will, in turn, result in a better
Valve 101 32 asset and capital utilization. A risk-based maintenance
Mixer 100 270 plan can be used to improve the existing maintenance
High-pressure 365 policies through optimal decision procedures in differ-
separator ent phases of the life cycle of a system.
Medium-pressure 165 The failure of a system is rarely the result of a single
separator failure, but rather the result of a combination of a series
Valve 100 30 0.36 of interacting events. As a result, risk-based mainte-
Mixer 101 270 nance must not be perceived as a static exercise to be
Heater 100 365 performed once. It is a dynamic process, which must
Low-pressure 365 be updated and upgraded as additional information
separator becomes available. In other words, risk-based mainte-
Valve 102 43 nance must be performed iteratively using new infor-
Cooler 101 365 mation that becomes available with time.
Low-pressure
APPENDIX A
compression
section Consequence Analysis
Low-pressure 98
scrubber General Input Data
Cooler 98 0.035
Low-pressure 37 • Loss rate: 1000 $/h
compressor • Asset density: 500 $/m2
Mixer 190 • Total population on the platform: 50 people
Medium-pressure • PDF: 0.2
compression • Environmental loss value: 100,000 $/km2
section • Human health loss value: 1.0 ⫻ 106 $/person
Medium-pressure 88
Specific Data for Separation Section
scrubber
Cooler 365 0.013 • Hours lost: 500 h
Medium-pressure 42 • Damage radii: 329 m
compressor • Environmental damage radii: 14 km
Mixer 106 • Importance factor: 0.1
High-pressure • Functionality loss (A) ⫽ 500 ⫻ 1000 ⫽ 0.5 ⫻ 106
compression • Asset loss (B) ⫽ ␲ ⫻ 329 ⫻ 329 ⫻ 500 ⫽ 170.02
section ⫻ 106
High-pressure 37 • Human health loss (C) ⫽ 50 ⫻ 0.2 ⫻ 1 ⫻ 106 ⫽
scrubber 10.0 ⫻ 106
High-pressure 18 0.64 • Environmental damage (D) ⫽ ␲ ⫻ 14 ⫻ 14 ⫻ 0.1
compressor ⫻ 100,000 ⫽ 6.1 ⫻ 106
Cooler 365 • Total loss ⫽ 186.12 ⫻ 106
Mixer 190 • Failure frequency ⫽ 5.230 ⫻ 10⫺4/h
• Consequences ⫽ 186.12 ⫻ 106
*Sample calculations are shown in Appendix B. • Risk factor ⫽ 5.230 ⫻ 10⫺4 ⫻ 186.12 ⫻ 106 ⫽
**Risk factors after incorporating additional safety mea- 97,340 $/h
sures and maintenance schedule.
APPENDIX B

Maintenance/Inspection Interval Calculations


Risk assessment integrates reliability analysis with
safety and environmental issues. Risk-based mainte- Separation Section
nance uses the answers to the five following questions
• Risk factor without safety measures and mainte-
in developing an optimum maintenance strategy:
nance plan ⫽ 97,340 $/h
• What can cause the system to fail? • Target risk factor ⫽ 1 $/h
• How can it cause the system to fail? To achieve this target risk, two major steps are taken
• What are the consequences of failure? to improve the probability of occurrence of the failure
• How probable is the failure? scenario:

264 December 2004 Process Safety Progress (Vol.23, No.4)


1. Safety measures are design and implemented: lease prevention by inspection and maintenance, J
There are four safety measures suggested, the de- Pressure Vessel Technol 122 (2000), 362–367.
tails of which are given in Tables 4 and 6. 4. F.I. Khan and S.A. Abbasi, Safe maintenance prac-
2. Maintenance and inspection plan is developed tice, Chem Ind Digest March (1998a), 91–105.
based on optimal interval (details of this are given 5. F.I. Khan and S.A. Abbasi, Risk assessment in
below). chemical process industries: Advanced techniques,
Discovery Publishing House, New Delhi, India,
• Target failure frequency (based on target risk) ⫽ 1998b.
1/186.12 ⫻ 106 ⫽ 5.37 ⫻ 10⫺9/h 6. F.I. Khan and M. Haddara, Risk-based maintenance
• Annual failure probability related to this target (RBM): A quantitative approach for maintenance/
frequency (8760 h) ⫽ 4.70 ⫻ 10⫺5 inspection scheduling and planning, Transaction of
• This failure probability is used as target failure IChem Process Safety and Environmental Protec-
probability in the fault tree (top event probabil- tion, 82(B6), 1–14.
ity), and a reverse analysis is conducted to calcu- 7. S.J. Brown and T.J. Brown, Hazardous release pro-
late failure probability of basic units such as tection: Code and standard considerations for pres-
valves (100, 101, 102), mixer, etc. The details for sure systems, Proc Safety Prog 14 (1995), 244 –256.
valve 101 and mixer are given below. 8. American Society of Mechanical Engineers (ASME),
American Society of Mechanical Engineers Code
Valve 101 Committee SC6000, Hazardous release protection,
• Earlier failure frequency ⫽ 2.56 ⫻ 10⫺4/h ASME, New York, 2000.
• Annual probability of failure (8760 h) ⫽ (1 ⫺ 9. S.J. Brown, An overview of the proposed ASME Code
⫺4
␭t ⫺2.56⫻10 ⫻8760 BPTC/HPSC SC6000, Hazardous release protection,
e ) ⫽ (1 ⫺ e ) ⫽ 0.8938
• Required annual failure probability that helps to Process Safety Symp, 1994, Vol. 1, Feb.–Mar.
achieve the target failure probability of this sec- 10. F.I. Khan, Maximum credible accident scenario for
tion (separation section, 4.70 ⫻ 10⫺5) ⫽ 0.1787 realistic and reliable risk assessment, Chem Eng
• Maintenance and inspection interval required to Prog November (2001), 55– 67.
achieve this target probability 11. F.I. Khan and S.A. Abbasi, MAXCRED—A new soft-
⫺ln关1 ⫺ p兴 ⫺ln关1 ⫺ 0.1787兴 ware package for rapid risk assessment in chemical
⫽ ⫽ 32 days process industries, Environ Model Software 14
␭ 2.56 ⫻ 10⫺4 (1999a), 11–25.
12. I.L. Hirst and D.A. Carter, A “worst case” method-
Mixer ology for risk assessment of major accident instal-
lations, Proc Safety Prog 19 (2000), 78 – 82.
• Earlier failure frequency ⫽ 1.5 ⫻ 10⫺4/h
13. F.I. Khan and S.A. Abbasi, Accident hazard index:
• Annual probability of failure (8760 h) ⫽ (1 ⫺
␭t ⫺4
⫺1.5⫻10 ⫻8760 A multi-attribute scheme for process industry haz-
e ) ⫽ (1 ⫺ e ) ⫽ 0.7312
ard rating, IChemE Environ Protect Safety 75B
• Required annual failure probability that helps to
(1997), 217.
achieve the target failure probability of this sec-
14. F.I. Khan and S.A. Abbasi, PROFAT: A user-friendly
tion (separation section, 4.70 ⫻ 10⫺5) ⫽ 0.6216
system for probabilistic fault tree analysis, Proc
• Maintenance and inspection interval required to
Safety Prog 18 (1999b), 42– 49.
achieve this target probability
15. F.I. Khan and S.A. Abbasi, Analytical simulation
⫺ln关1 ⫺ p兴 ⫺ln关1 ⫺ 0.6216兴 and PROFAT II: A new methodology and a com-
⫽ ⫽ 270 days
␭ 2.56 ⫻ 10⫺4 puter automated tool for fault tree analysis in
chemical process industries, J Hazard Mater 75
LITERATURE CITED (2000), 1–27.
1. E.G. Frankel, System reliability and risk analysis, Klu- 16. Orissa Renewable Energy Development Agency
wer Academic, Dordrecht, The Netherlands, 1998. (OREDA), Offshore reliability data handbook, 3rd
2. S. Apeland and T. Aven, Risk based maintenance ed., DNV Veritasveien 1, N-1322 Hovik, Norway,
optimization: Foundation issues, Reliability Eng 1997.
Syst Safety 67 (2000), 285–292. 17. F.P. Lees, Loss prevention in CPI, Butterworths,
3. S.J. Brown and I.L. May, Risk-based hazardous re- London, 1996.

Process Safety Progress (Vol.23, No.4) December 2004 265

Anda mungkin juga menyukai