Mode 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23
1 RUMAH TIPE 48 64 days Tue 11/26/19 Fri 2/21/20
2 Pekerjaan Pondasi 14 days Tue 11/26/19 Fri 12/13/19
3 Pekerjaan Pengukuran/pemasangan Bowplank 1 day Tue 11/26/19 Tue 11/26/19
4 Pekerjaan Pembersihan Lapangan 3 days Tue 11/26/19 Thu 11/28/19
5 Pekerjaan Lost Kerja 2 days Tue 11/26/19 Wed 11/27/19
6 Pekerjaan galian tanah pondasi 2 days Fri 11/29/19 Mon 12/2/19
7 Pekerjaan timbunan tanah kembali 1 day Thu 12/5/19 Thu 12/5/19
8 pekerjaan timbunan tanah bawah lantai 1 day Thu 12/12/19 Thu 12/12/19
9 urugan pasir bawah lantai 1 day Fri 12/13/19 Fri 12/13/19
10 pekerjaan pasir urug bawah 1 day Fri 12/6/19 Fri 12/6/19
11 pasang pondasi batu gunung/batu kali 1:4 7 days Tue 12/3/19 Wed 12/11/19
12 Pekerjaan Beton 21 days Mon 12/16/19 Mon 1/13/20
13 Pekerjaan Sloof 2 days Mon 12/16/19 Tue 12/17/19
14 Pekerjaan Kolom 7 days Wed 12/18/19 Thu 12/26/19
Project: PENJADWALAN MANK Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Thu 12/5/19 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress