NAMA PEKERJAAN :
PENGEMBANGAN INFRASTRUKTUR PERMUKIMAN ARUK (SAJINGAN BESAR)
KABUPATEN SAMBAS PROVINSI KALIMANTAN BARAT
NO. KONTRAK : KU.08.08/SPK/SATKERPKPK/XII/186.B/2015
TANGGAL KONTRAK : 17 Desember 2015
LOKASI : ARUK (SAJINGAN BESAR) KABUPATEN SAMBAS PROVINSI KALIMANTAN BARAT
LAPORAN MINGGUAN
Minggu Ke 76
Tanggal : 26 Mei s.d 01 Juni 2017
BSC
PT. IDEE MURNI PRATAMA
Jalan Jaksa No. 15A, Jakarta Pusat 10340 Telp. (021) 3920323, 3920264
No : 076/LAP-PRO-M76/PTIMP/V/2017
Perihal : Laporan Progress Minggu Ke-76
Kepada Yth :
Pejabat Pembuat Komitmen (PPK)
Pengembangan Infrastruktur Permukiman Aruk
(Sajingan Besar)
di
Tempat
Kontraktor Pelaksana
PT. IDEE MURNI PRATAMA
( Ir. Gunadi )
Site Manager
Tembusan :
1 Satker PKPK di Jakarta
2 Direksi Lapangan
3 KMP (Korprov)……
4 Konsultan Supervisi
PT. IDEE MURNI PRATAMA
Jalan Jaksa No. 15A, Jakarta Pusat 10340 Telp. (021) 3920323, 3920264
MINGGU KE LXXVI ( 76 )
PERTANGGAL : 26 Mei s.d 01 Juni 2017
1 PENGANTAR
2 DAFTAR ISI
3 LAPORAN UMUM
12 LAMPIRAN - LAMPIRAN
PT. IDEE MURNI PRATAMA
Jalan Jaksa No. 15A, Jakarta Pusat 10340 Telp. (021) 3920323, 3920264
* Nilai Kontrak :
II EVALUASI PEKERJAAN
A Prestasi Pekerjaan :
B Waktu Pelaksanaan :
D Masalah / Hambatan
1 Alat berat Grader rusak
Nama Pekerjaan : Pengembangan Infrastruktur Permukiman Aruk (Sajingan Besar), Kab. Sambas, Prov Kalimantan Barat Kontraktor Pelaksana : PT. Idee Murni Pratama
Nomor Kontrak : KU.08.08/SPK/SATKERPKPK/XII/186.B/2015 Konsultan MK/Supervisi : PT. Bennatin Surya Cipta
Tanggal Kontrak : 17 Desember 2015 Jangka Waktu Pelaksanaan : 630 Hari Kalender
Lokasi Kegiatan : Aruk (Sajingan Besar), Kabupaten Sambas, Provinsi Kalimantan Barat Waktu Yang Sudah Dilalui : 532 Hari
Sisa Waktu Pelaksanaan : 98 Hari
Pada hari ini Kamis, tanggal satu bulan juni Tahun dua ribu tujuh belas ( 01-06-17), kami yang bertanda tangan dibawah ini :
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
Tanggal Kontrak : 17 Desember 2015 Jangka Waktu Pelaksanaan : 630 Hari Kalender
Lokasi Kegiatan : ARUK (SAJINGAN BESAR), KABUPATEN SAMBAS, PROVINSI KALIMAN Waktu Yang Sudah Dilalui : 532 Hari
100%
I SPAM 22.7297 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 0.2560 ###
II IPAL Komunal 15.4050 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 ###
IV Peningkatan Jalan & Jembatan Ruas I, Sta. 00 + 000 - Sta 10 + 800 44.4605 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940 0.4940
TOTAL
100.000
RENCANA BOBOT PER MINGGU 1.4434 2.5345 2.5345 2.5345 2.7727 2.7727 2.8982 2.8982 2.8653 3.0306 2.8159 2.8159 2.7899 2.7837 2.5010 2.2108 2.3092 2.3448 2.3448 2.2870 1.8608 1.8608
RENCANA BOBOT KUMULATIF 39.9978 42.5323 45.0668 47.6013 50.3740 53.1468 56.0449 58.9431 61.8084 64.8389 67.6549 70.4708 73.2607 76.0444 78.5453 80.7561 83.0653 85.4101 87.7549 90.0420
0.601 91.9028 93.2896
REALISASI BOBOT PER MINGGU 0.9114 2.8031 0.5162 2.1835 1.9447 2.4751 2.9504 2.6975 2.3487 2.5711 2.5781 1.7028 2.3399 2.7714 2.7166 2.0242 1.4812 2.3530 2.3189 1.7153 0.8230 1.2451
REALISASI BOBOT KUMULATIF 0.000% 47.0041 49.8072 50.3233 52.5068 54.4516 56.9266 59.8771 62.5746 64.9233 67.4944 70.0724 71.7752 74.1151 76.8865 79.6030 81.6272 83.1084 85.4613 87.7803 89.4956 90.3186 91.5636
DEVIASI 7.0063 7.2749 5.2565 4.9055 4.0776 3.7798 3.8321 3.6315 3.1149 2.6555 2.4175 1.3044 0.8544 0.8421 1.0577 0.8711 0.0431 0.0512 0.0254 (0.5464) (1.5842) (1.7259)
TANGGAL
Tenaga Kerja SATUAN JUMLAH (org-
JUMAT SABTU MINGGU SENIN SELASA RABU KAMIS hari) KETERANGAN
26/05/17 27/05/17 28/05/17 29/05/17 30/05/17 31/05/17 01/06/17
A. STAF KONTRAKTOR :
1 Proyek Manager orang 1 1 1 1 1 1 1 7
2 Site Manager orang 1 1 1 1 1 1 1 7
3 Site Engineer orang 1 1 1 1 1 1 1 7
4 Kepala Supervisor orang 1 1 1 1 1 1 1 7
5 Kepala Administrasi & Keuangan orang 1 1 1 1 1 1 1 7
6 Supervisor Mechanical orang 1 1 1 1 1 1 1 7
7 Supervisor Jembatan orang 1 1 1 1 1 1 1 7
8 Drafter orang 1 1 1 1 1 1 1 7
9 Surveyor orang 1 1 1 1 1 1 1 7
10 Admin Logistic orang 1 1 1 1 1 1 1 7
11 Keuangan orang 1 1 1 1 1 1 1 7
12 Mekanik orang 3 3 3 3 3 3 3 21
13 Hubungan Masyarakat orang 1 1 1 1 1 1 1 7
14 Supervisor Jalan orang 1 1 1 1 1 1 1 7
15 Supervisor Batching Plant orang 1 1 1 1 1 1 1 7
16 Staf Logistic orang 1 1 1 1 1 1 1 7
17 Admin Proyek orang 1 1 1 1 1 1 1 7
Jumlah A 19 19 19 19 19 19 19 133
B. PEKERJA :
1 Mandor orang 8 8 8 8 8 8 8 56
2 Kepala Tukang orang 8 8 8 8 8 8 8 56
3 Tukang orang 16 16 16 16 16 16 16 112
4 Pembantu Tukang orang 56 56 56 56 56 56 56 392
5 Tenaga Kerja orang 80 80 80 80 80 80 80 560
6 Operator Alat orang 8 8 8 8 8 8 8 56
7 Tukang Las orang 1 1 1 1 1 1 1 7
8 Tukang Pipa orang 2 2 2 2 2 2 2 14
9 Semi Tukang orang 2 2 2 2 2 2 2 14
10 ceker orang 1 1 1 1 1 1 1 7
11 Security orang 8 8 8 8 8 8 8 56
12 Helper orang 4 4 4 4 4 4 4 28
13 Assisten Survey orang 2 2 2 2 2 2 2 14
14 Supir orang 11 11 11 11 11 11 11 77
15 Tenaga Harian Jalan orang 6 6 6 6 6 6 6 42
16 Harian Kantor orang 2 2 2 2 2 2 2 14
17 Harian Batching Plant orang 2 2 2 2 2 2 2 14
Jumlah B. 217 217 217 217 217 217 217 1,519
Jumlah A + B 236 236 236 236 236 236 236 1,652
Nama Pekerjaan : Pengembangan Infrastruktur Permukiman Aruk (Sajingan Besar),Kab. Sambas, Prov. Kalimantan Barat Kontraktor Pelaksana : PT IDEE MURNI PRATAMA
Nomor Kontrak : KU.08.08/SPK/SATKERPKPK/XII/186.B/2015 Konsultan Supervisi : PT BENNATIN SURYA CIPTA
Tanggal Kontrak : Thursday, December 17, 2015 Jangka Waktu Pelaksanaan Kegiatan : 630 Hari Kalender
Lokasi Kegiatan : Aruk (Sajingan Besar), Kabupaten Sambas, Provinsi Kalimantan Barat Waktu Yang Sudah Dilalui : 532 Hari
Minggu : 76 Sisa Waktu Pelaksanaan : 98 Hari
2 Semen Beton 111,320 Kg 100.00% 25-May-17 15% 13% 15% 17% 15% 11% 15% 12% 15% 17% 15% 16% 10% 14% 111,320.0 0.00%
3 Pasir 218,944 Kg 100.00% 25-May-17 15% 15% 15% 15% 15% 13% 15% 11% 15% 18% 15% 15% 10% 13% 218,944.0 0.00%
4 Batu 330,762 Kg 100.00% 25-May-17 15% 7% 15% 17% 15% 14% 15% 12% 15% 20% 12.5% 16% 12.5% 14% 330,762.0 0.00%
5 Besi 12 mm 217 Batang 100.00% 25-May-17 30% 31% 0% 23% 30% 12% 0% 18% 40% 16% 0% 0% 0% 0% 217.0 0.00%
6 Besi 8 mm 45 Batang 100.00% 25-May-17 10% 0% 10% 0% 20% 0% 20% 44% 10% 0% 10% 0% 20% 56% 45.0 0.00%
7 Besi 10 mm 104 Batang 100.00% 25-May-17 10% 20% 10% 39% 20% 19% 20% 0% 10% 0% 10% 22% 20% 0% 104.0 0.00%
8 Kaso 132 Batang 100.00% 25-May-17 15% 11% 15% 61% 15% 0% 15% 7% 15% 0% 15% 21% 10% 0% 132.0 0.00%
9 Papan 12 Keping 100.00% 25-May-17 15% 17% 15% 0% 15% 0% 15% 83% 15% 0% 15% 0% 10% 0% 12.0 0.00%
Nama Pekerjaan : Pengembangan Infrastruktur Permukiman Aruk (Sajingan Besar), Kab. Sambas, Prov. Kalimantan Barat Kontraktor Pelaksana : PT. IDEE MURNI PRATAMA
Nomor Kontrak : KU.08.08/SPK/SATKERPKPK/XII/186.B/2015 Konsultan Supervisi : PT BENNATIN SURYA CIPTA
Tanggal Kontrak : 17 Desember 2015 Jangka Waktu Pelaksanaan Kegiatan : 630 Haria Kalender
Lokasi Kegiatan : Aruk (Sajingan Besar), Kabupaten Sambas, Provinsi Kalimantan Barat Waktu Yang Sudah Dilalui : 532 Hari
Minggu : 76 Sisa Waktu Pelaksanaan : 98 Hari
Tahun 2016
No Uraian Pekerjaan Satuan Jumat Sabtu Minggu Senin Selasa Rabu Kamis Deviasi
Renc Real Renc Real Renc Real Renc Real Renc Real Renc Real Renc Real Vol %
1 Exavactor unit 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 10% 14.28% 5 0%
2 Dump Truck Kecil set 15% 14.28% 15% 14.28% 10% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 3 0%
3 Dump Truck Besar set 15% 14.28% 15% 14.28% 10% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 5 0%
4 Waterpass set 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 10% 14.28% 1 0%
5 Trado unit 0% 14.28% 0% 14.28% 0% 14.28% 0% 14.28% 0% 14.28% 50% 14.28% 50% 14.28% 1 0%
6 Motor Grader set 0% 7.14% 0% 7.14% 0% 7.14% 25% 7.14% 25% 7.14% 25% 7.14% 25% 7.14% 1 -50%
7 Vibrator buah 15% 14.28% 15% 14.28% 10% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 2 0%
8 Genset buah 0% 14.28% 0% 14.28% 0% 14.28% 0% 14.28% 30% 14.28% 30% 14.28% 40% 14.28% 3 0%
9 Motor unit 15% 14.28% 15% 14.28% 10% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 6 0%
10 Stamper Woles (Vibro) unit 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 2 0%
11 Bulldozer unit 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 1 0%
12 Theodolit unit 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 1 0%
13 Total Station unit 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 1 0%
14 Prisma unit 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 1 0%
14 Lori Unit 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 13 0%
15 Molen buah 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 3 0%
16 Cutting Well buah 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 14.28% 3 0%
17 Gunting besi buah 15% 14.28% 15% 14.28% 10% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 2 0%
18 Truk Mixer unit 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 10% 14.28% 3 0%
19 Truk Tanki air unit 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 10% 14.28% 1 0%
20 Mobil Strada unit 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 10% 14.28% 2 0%
21 Batching Plant unit 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 15% 14.28% 10% 14.28% 1 0%
S = Siap
R = Rusak
O = Operasional
LAPORAN CUACA
Minggu Ke 76
Tanggal : 26 Mei s.d 01 Juni 2017
Nama Pekerjaan : Pengembangan Infrastruktur Permukiman Aruk (Sajingan Besar), Kab.Sambas, ProvKontraktor Pelaksana : PT. IDEE MURNI PRATAMA
Nomor Kontrak : KU.08.08/SPK/SATKERPKPK/XII/186.B/2015 Konsultan Supervisi : PT BENNATIN SURYA CIPTA
Tanggal Kontrak : 17 Desember 2015 Jangka Waktu Pelaksanaan Kegiatan : 630 Hari Kalender
Lokasi Kegiatan : Aruk (Sajingan Besar), Kabupaten Sambas, Provinsi Kalimantan Barat Waktu Yang Sudah Dilalui : 532 Hari
Sisa Waktu Pelaksanaan : 98 Hari
Waktu (JAM)
No TANGGAL KETERANGAN
0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
1 26 Mei 2017
3 28 Mei 2017
5 30 Mei 2017
7 01 Juni 2017
1 Galian biasa Ruas 1 Terkena alat berat Tanda pengaman Penjagaan sekitar jalan dan pemasangan rambu
2 Potong besi (Pabrikasi besi) Tangan terluka, Mata terkena Memakai sarung tangan dan Persiapan kotak P3K, memantau Tukang agar sesuai
serpihan kacamata safety prosedur
3 Persiapan badan jalan Terkena alat berat Pemasangan rambu pengaman Persiapan kotak P3K
dan penjagaan disekitar
4 Galian tanah Terkena alat berat Penggunaan sepatu safety dan Dikaitkan dengan peraturan yang berlaku
rompi
5 Pembuatan bekesting Terkena martil dan paku Memakai sarung tangan Persiapan kotak P3K dan tukang di ingatkan
6 Kecelakaan di jalan Standart kendaraan dicek dahulu, Persiapan K3 di setiap kendaraan.
Pengadaan Material Batu, Pasir safety belt.
7 Galian saluran Terkena cangkul Memakai sepatu safety Mengingatkan tukang dan persiapan kotak P3K
8 Pemasangan saluran Kejatuhan Beton Drainase Memakai sepatu safety Mengingatkan tukang dan persiapan kotak P3K
9 Galian lubang IPAL Kejatuhan tanah Memakai helm dan sepatu Penjagaan sekitar galian
Progres : 50%
Progres : 75%
Progres : 75%
Obyek :
Stok Pipa RRJ
Progres : Progres
Obyek :
Stok Pipa RRJ
Progres : Progres
Obyek :
Stok Pipa Galvanis
Progres : Progres
Obyek :
Stok pipa HDPE
Progres : Progres
Progres : 100%
Koordinat :
Progres : 100%
Koordinat :
Progres : 100%
Koordinat :
PT. IDEE MURNI PRATAMA
Jalan Jaksa No. 15A, Jakarta Pusat 10340 Telp. (021) 3920323, 3920264
Stasiun : Zona 3
Progres :
Koordinat :
Stasiun : Zona 3
Progres :
Koordinat :
Stasiun : Zona 2
Progres :
Koordinat :
PT. IDEE MURNI PRATAMA
Jalan Jaksa No. 15A, Jakarta Pusat 10340 Telp. (021) 3920323, 3920264
Progres : 0%
Progres : 50%
Obyek :
Peningkatan Jalan Ruas 1
Progres : 50%
Obyek :
Peningkatan Jalan Ruas 1
Progres : 75%
Progres : 0%
Progres : 25%
Obyek :
Peningkatan Jalan Ruas 1
Progres : 50%
Obyek :
Peningkatan Jalan Ruas 1
Progres : 75%
Stasiun : PLBN
Progres : 0% Progres
Stasiun : PLBN
Stasiun : PLBN
Stasiun : PLBN
Progres : 0% Progres
Stasiun : PLBN
Stasiun : PLBN
Progres : 0% Progres
Obyek :
Pekerjaan Garasi Truck dan
Landasan Container, GWT
Stasiun : PLBN
Koordinat : Koordinat
Obyek :
Pekerjaan jalan penghubung ruas 1
& 2 ( Gg. Batu Anyok)
Stasiun : Aping
Progres : 75% :
Koordinat : Koordinat
Koordinat : Koordinat
PT. IDEE MURNI PRATAMA
Jalan Jaksa No. 15A, Jakarta Pusat 10340 Telp. (021) 3920323, 3920264
Stasiun : PLBN
Progres :
Koordinat :
Stasiun : PLBN
Progres :
Koordinat :
Progres :
Koordinat :
KEMENTERIAN PEKERJAAN UMUM
DIREKTORAT JENDERAL CIPTA KARYA
SATUAN KERJA PENGEMBANGAN KAWASAN PERMUKIMAN STRATEGIS
K2
SUMMARY REPORT
1-Jun-17
NAMA PROYEK
KETERANGAN DOKUMENTASI
Kumulatif rencana progress fisik s/d minggu ini 93.2896%
Kumulatif realisasi progress fisik s/d minggu ini 91.5637% Pemilik Proyek : Kementerian Pekerjaan Umum dan Perumahan Rakyat
Deviasi -1.7259% Pemberi Tugas : SATKER PKPK
Konsultan Supervisor : PT. BENNATIN SURYA CIPTA FOTO PROGRESS
AKTIVITAS KERJA MINGGU INI LOKASI Kontraktor Pelaksana : PT. IDEE MURNI PRATAMA
Pekerjaan Beton Rigid Ruas 1 Dusun Aping No. Kontrak : KU.08.08/SPK/SATKERPKPK/XII/186.B/2015
Persiapan badan jalan Ruas 1 Dusun Aping Nilai Kontrak :
Pekerjaan Galian IPAL di Kampung Beruang Dusun Beruang Jangka Waktu : 630 hari Direksi Keet
Produksi U-dict atau saluran drainase tipe U Dusun Aruk Laporan Mingguan Ke : 76 (26 Mei - 01 Juni 2017)
Pekerjaan Pemasangan Saluran Ruas 1 Dusun Aping Waktu Pelaksanaan : 532 hari
Persiapan badan jalan Ruas 2 Dusun Beruang
FOTO PROGRESS
Saluran Ruas 2
Sisa Waktu Pelaksanaan : 98 hari
RENCANA KERJA MINGGU YANG AKAN DATANG LOKASI RESUME PROGRES PEKERJAAN MINGGU INI
Pekerjaan Timbunan Material Setempat Jalan Ruas 2 Aping JENIS PEKERJAAN Bobot Pekerjaan (%)
Deviasi
Pekerjaan Box Culvert Ruas 2 Aping No. Jumlah Awal Rencana Progres
Galian Saluran Drainase U-ditch Jalan Ruas 1 Aping 1 SPAM 17.6937% 0.2560% 18.0984% 17.8424%
Pekerjaan Timbunan jalan Ruas 1 Aping 2 IPAL KOMUNAL 13.7656% 0.1712% 13.8612% 13.6900%
Pekerjaan Lapisan jalan Agregat B Ruas 1 Aping 3 Persampahan 0.2752% 0% 0.8549% 0.8348% FOTO PROGRESS
Pekerjaan persiapan Badan Jalan Ruas 2 Beruang 4 Peningkatan jalan & jembatan Ruas I 44.2019% 0.4940% 44.2036% 43.7096%
Pekerjaan pemasangan Pipa SPAM 6" Aruk 5 Peningkatan Jalan & Jembatan Ruas II 14.3820% 0.1733% 14.5454% 14.3721% Pasangan Batu diPLBN
Catatan