Kegiatan Proyek Pembuatan Digital Piano Waktu Normal Dengan Crash Time

Immediete Normal
Activity Description Crash Time Normal Cost Cras Cost
Predecessors Time
A Feasibility Study - 4 2 Rp 100,000,000 Rp 108,000
B Concept Design - 6 4 Rp 75,000,000 Rp 85,000,000
C Product Design A 4 2 Rp 16,000,000 Rp 18,000,000
D Part Design A,B 8 6 Rp 14,000,000 Rp 19,000,000
E 1st Trial C 8 4 Rp 45,000,000 Rp 57,000,000
F 2nd Trial (for production) C 6 4 Rp 20,000,000 Rp 23,000,000
G Molding & Tooling D,E 10 6 Rp 150,000,000 Rp 160,000,000
H Pre Production F,G 4 2 Rp 15,000,000 Rp 18,500,000
I Mass Production H 6 4 Rp 30,000,000 Rp 37,000,000

2. Jaringan Jalur Kritis Waktu Normal / Network Planning (Jaringan Hitung Maju)

0 A 4 4 C 8 8 F 14
0 4 4 4 4 8 20 26
6
Mulai
0 0
8 E 16 26 H 30 30
I 36
0 0 0 26 36
8 8 16 30 30
4 6

0 B 6 6 D 14 16
G 26
2 6 8 8 8 16 16 26
10

2. Jaringan Hitung Mundur

0 A 4 4 C 8 8 F 14

Mulai 4 4 6

0 0
8 E 16 26 H 30 30
I 36
0
8 4 6

0 B 6 6 D 14 16
G 26

6 8 10

2 Menentukan Jalur Kritis

Immediete SLACK
Activity Description Time Week ES EF LS JALUR KRITIS
Predecessors ( = LS-ES )
A Feasibility Study - 4 0 4 0 0 YA
B Concept Design - 6 0 6 2 2 TIDAK
C Product Design A 4 4 8 4 0 YA
D Part Design A,B 8 6 14 8 2 TIDAK
E 1st Trial C 8 8 16 8 0 YA
F 2nd Trial (for production) C 6 8 14 20 12 TIDAK
G Molding & Tooling D,E 10 16 26 16 0 YA
H Pre Production F,G 4 26 30 26 0 YA
I Mass Production H 6 30 36 30 0 YA

No. Jalur - Jalur Kegiatan Waktu Yang Dibutuhkan


1 A-C-E-G-H-I 4+4+8+10+4+6 = 36
2 A-C-F-H-I 4+4+6+4+6 = 24
3 A-D-G-H-I 4+8+10+4+6 = 32
4 B-D-G-H-I 6+8+10+4+6 = 34

Diketahui jalur kritisnya adalah A-C-E-G-H-I dengan waktu yang dibutuhkan 36 minggu. Jadi, waktu
penyelesaian yang optimal dengan asumsi perhitungan waktu normal dalam proyek tersebut adalah 36
minggu degan biaya
Rp 465.000.000,-.
Diketahui jalur kritisnya adalah A-C-E-G-H-I dengan waktu yang dibutuhkan 36 minggu. Jadi, waktu
penyelesaian yang optimal dengan asumsi perhitungan waktu normal dalam proyek tersebut adalah 36
minggu degan biaya
Rp 465.000.000,-.

Tabel Biaya akselerasi per unit waktu (Slope)

Immediate
Activity Normal Week Crash Time Normal Cost Crash Cost Slove Jalur Kritis
Predecessors
A - 4 2 Rp 100,000,000 Rp 108,000,000 Rp 4,000,000 YA
B - 6 4 Rp 75,000,000 Rp 85,000,000 Rp 5,000,000 TIDAK
C A 4 2 Rp 16,000,000 Rp 18,000,000 Rp 1,000,000 YA
D A,B 8 6 Rp 14,000,000 Rp 19,000,000 Rp 2,500,000 TIDAK
E C 8 4 Rp 45,000,000 Rp 57,000,000 Rp 3,000,000 YA
F C 6 4 Rp 20,000,000 Rp 23,000,000 Rp 1,500,000 TIDAK
G D,E 10 5 Rp 150,000,000 Rp 160,000,000 Rp 2,000,000 YA
H F,G 4 2 Rp 15,000,000 Rp 18,500,000 Rp 1,750,000 YA
I H 6 4 Rp 30,000,000 Rp 37,000,000 Rp 3,500,000 YA
Waktu Yang Dibutuhkan (Minggu) Biaya ($)
Activity Prodecessor
Normal Time Crash Time Normal Cost Cras Cost
A - 4 2 $ 1,000 $ 1,100
B A 3 2 $ 600 $ 800
C A 2 1 $ 500 $ 600
D B 4 3 $ 1,200 $ 1,600
E B,C 4 2 $ 800 $ 1,200
F E,D 2 1 Rp 1,000 Rp 1,200
Total Biaya $ 5,100

4 B 7 7 D 11
4 7 11
3 7 4
Mulai
0 0 0 A 4
0 0 0 4
0 4

4 C 6 6 E 10 11 F 13
5 7 4 11 11
2 7 2 13

No. Jalur - Jalur Kegiatan Waktu Yang Dibutuhkan


1 A-B-D-F 4+3+4+2 = 13
2 A-B-E-F 4+3+4+2 = 13
3 A-C-E-F 4+2+4+2 = 12

Diketahui jalur kritisnya adalah A-B-D-F dengan waktu yang dibutuhkan 13 minggu. Jadi, waktu penyelesaian
yang optimal dengan asumsi perhitungan waktu normal dalam proyek tersebut adalah 13 minggu degan biaya
$ 5.100,-.

SLACK
Activity Prodecessor Time Week ES EF LS JALUR KRITIS
( = LS-ES )
A - 4 0 4 0 0 YA
B A 3 4 7 4 0 YA
C A 2 4 6 5 1 TIDAK
D B 4 7 11 7 0 YA
E B,C 4 6 10 7 1 TIDAK
F E,D 2 11 13 11 0 YA

Tabel Biaya akselerasi per unit waktu (Slope)

Waktu Yang Dibutuhkan (Minggu) Biaya ($)


Activity Prodecessor Slope Jalur Kritis
Normal Time Crash Time Normal Cost Cras Cost
A - 4 2 $ 1,000 $ 1,100 Rp 50 YA
B A 6 4 $ 600 $ 800 Rp 100 YA
C A 4 2 $ 500 $ 600 Rp 50 TIDAK
D B 8 6 $ 1,200 $ 1,600 Rp 200 YA
E B,C 8 4 $ 800 $ 1,200 Rp 100 TIDAK
F E,D 6 4 Rp 1,000 Rp 1,200 Rp 100 YA