LAPORAN KEMAJUAN PEKERJAAN

PEKERJAAN PEMBANGUNAN JALAN LINGKUNGAN KP. ASIR - ASIR BUJANG


LOKASI KP. ASIR-ASIR KEC. LUT TAWAR KAB. ACEH TENGAH
NO. KONTRAK 620/02/SP/OTSUS-APBK/DPP/2019
TGL. KONTRAK 15 Juli 2019
NILAI KONTRAK Rp 796.587.000
SUMBER DANA DOKA - APBK
TAHUN ANGGARAN 2019
KONTRAKTOR PELAKSANA CV.GATRACO
KONSULTAN SUPERVISI CV. GRAHA KARYA CONSULTANT

MINGGU - 12
PERIODE
30 September 2019 S.D 07 Oktober 2019
BULAN LALU BILAN INI S.D BULAN INI
No. Mata HARGA SATUAN JUMLAH HARGA
URAIAN PEKERJAAN VOLUME SATUAN BOBOT (%) VOLUME PERSEN BOBOT(%) VOLUME PERSEN BOBOT(%) VOLUME PERSEN BOBOT(%)
Pembayaran (Rp.) (Rp.)

DIVISI 1. UMUM
1.2 Mobilisasi 1,00 Ls 63.300.000,00 Rp 63.300.000,00 8,741 0,750 75,000% 6,556 0,250 25,000% 2,185 1,000 100,000% 8,741
Sub Jumlah Rp 63.300.000,00 8,741 6,556 2,185 8,741
DIVISI 2. PEKERJAAN DRAINASE
2.1.(1) Galian Selokan Drainase Dan Saluran Air 130,000 M3 Rp 41.500,00 Rp 5.395.000,00 0,745 0,000 0,000% 0,000 0,000 0,000 0,000 0,000% 0,000
2.2.(1) Pasangan Batu Dengan Mortal - M3 Rp - Rp - 0,000 0,000 0,000% 0,000 0,000 0,000 0,000 0,000% 0,000
2.3. (1) Gorong-gorong Pipa Beton Bertulang, diameter 35 - 45 cm - Rp - Rp - 0,000 0,000 0,000% 0,000 0,000 0,000 0,000 0,000% 0,000
2.3.(2) Gorong-gorong Pipa Beton Bertulang, diameter 55 - 65 cm - Rp 869.600,00 Rp - 0,000 0,000 0,000% 0,000 0,000 0,000 0,000 0,000% 0,000
Sub Jumlah Rp 5.395.000,00 0,745 0,000 0,000 0,000

DIVISI 3. PEKERJAAN TANAH


3.2.(2) Timbunan Pilihan 74,92 M3 170.000,00 Rp 12.735.595,26 1,759 74,915 100,000% 1,759 0,000 0,000 74,915 100,000% 1,759
3.3.(1) Penyiapan Badan Jalan 1.499,44 M3 1.900,00 Rp 2.848.926,71 0,393 1.499,435 100,000% 0,393 0,000 0,000 1.499,435 100,000% 0,393
Sub Jumlah Rp 15.584.521,97 2,152 2,152 0,000 2,152
DIVISI 5. PERKERASAN BERBUTIR
5.1.(1) Lapis Pondasi Agregat Kelas A 179,932 M3 Rp 590.900,00 Rp 106.321.944,67 14,682 179,932 100,000% 14,682 0,000 - 179,932 100,000% 14,682
5.1.(2) Lapis Pondasi Agregat Kelas B 299,887 M3 Rp 526.700,00 Rp 157.950.494,32 21,811 299,887 100,000% 21,811 0,000 - 299,887 100,000% 21,811
Sub Jumlah Rp 264.272.438,99 36,493 36,493 0,000 36,493
DIVISI 6. PERKERASAN ASPAL
6.1(1)(a) Lapis Resap Pengikat - Aspal Cair 839,684 Liter Rp 14.900,00 Rp 12.511.286,54 1,728 839,684 100,000% 1,728 0,000 0,000 839,684 100,000% 1,728
6.3(6a) Laston Lapis Antara (AC-BC) 165,538 Ton Rp 1.543.500,00 Rp 255.507.341,12 35,283 82,769 50,000% 17,641 82,769 50,000% 17,641 165,538 100,000% 35,283
Sub Jumlah Rp 268.018.627,66 37,010 19,369 17,641 37,010
DIVISI 7. STRUKTUR
7.1(8) Beton Mutu Rendah fc'= 15 Mpa (K.175) 59,977 M3 Rp 1.794.000,00 Rp 107.599.463,38 14,858 0,000 0,000% 0,000 0,000 0,000 0,000 0,000% 0,000
Sub Jumlah Rp 107.599.463,38 14,858 0,000 0,000 0,000
TOTAL Rp 724.170.052 100,000 64,570 19,827 84,397
PPN (10 %) Rp 72.417.005,20
GRAND TOTAL Rp 796.587.057,20
DIBULATKAN Rp 796.587.000,00

Mengetahui / Menyetujui Dibuat Oleh :


Pejabat Pelaksana Teknis Kegiatan (PPTK) Konsultan Supervisi
Kegiatan Peningkatan Jalan ( Dak Reguler ) CV. GRAHA KARYA CONSULTANT
Kabupaten Aceh Tengah

PEMBINA UTAMA MUDA, IV/C NIP. 19640814 199303 1 006 43810


PEJABAT PENGGUNA ANGGARAN/ PENGGUNA BARANG DINAS PERUMAHAN DAN PERMUKIMAN KABUPATEN ACEH TENGAH SELAKU PEJABAT PEMBUAT KOMITMEN (PPK) Site Engineer