Anda di halaman 1dari 13

FORMULIR STANDAR UNTUK

PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


PEKERJAAN/PAKET -
-
ITEM PEMBAYARAN NO :
JENIS PEKERJAAN : Memasang Rasuk untuk Lantai
SATUAN : M1
VOLUME :
LOKASI
PROP/KOTA/KODYA : JALAN TUA PAYA

PERKIRAAN HARGA JUMLAH


NO KOMPONEN SATUAN
KUANTITAS SATUAN HARGA ( Rp )
A Bahan
1 Kayu 1" x 2" Btg 0,030 Rp. - Rp. -
2 Paku 2"-5" Kg 0,400 Rp. 25.230,00 Rp. 10.092,00
3 Minyak Bekisting Ltr 0,200 Rp. - Rp. -
4 Kayu Mentangor / kruwing 3" x 4" x 4,8m' Btg 0,015 Rp. 103.507,69 Rp. 1.552,62
5 Triplek 6 mm Lbr 0,350 Rp. - Rp. -
6 Kayu Bulat 5-10 cm Btg 6,000 Rp. - Rp. -

JUMLAH HARGA BAHAN A Rp. 11.644,62


B Tenaga
1 Pekerja Org/ Hr 0,660 Rp. 90.000,00 Rp. 59.400,00
2 Tukang Kayu Org/ Hr 0,330 Rp. 100.000,00 Rp. 33.000,00
3 Kepala Tukang Org/ Hr 0,033 Rp. 120.000,00 Rp. 3.960,00
4 Mandor Org/ Hr 0,033 Rp. 140.000,00 Rp. 4.620,00

JUMLAH HARGA TENAGA B Rp. 100.980,00


C JUMLAH TENAGA DAN BAHAN ( A + B ) Rp. 112.624,62
Terpasang Rp. 112.624,62
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


PEKERJAAN/PAKET -
-
ITEM PEMBAYARAN NO :
JENIS PEKERJAAN : Memasang Papan untuk Lantai
SATUAN : M1
VOLUME :
LOKASI
PROP/KOTA/KODYA -

PERKIRAAN HARGA JUMLAH


NO KOMPONEN SATUAN
KUANTITAS SATUAN HARGA ( Rp )
A Bahan
1 Kayu 1" x 2" Btg 0,030 Rp. - Rp. -
2 Paku 2"-5" Kg 0,400 Rp. 25.230,00 Rp. 10.092,00
3 Minyak Bekisting Ltr 0,200 Rp. - Rp. -
4 Papan Mentangor / kruwing 1" x 8" x 4,8m' Kpg 0,015 Rp. 120.142,86 Rp. 1.802,14
5 Triplek 6 mm Lbr 0,350 Rp. - Rp. -
6 Kayu Bulat 5-10 cm Btg 6,000 Rp. - Rp. -

JUMLAH HARGA BAHAN A Rp. 11.894,14


B Tenaga
1 Pekerja Org/ Hr 0,660 Rp. 90.000,00 Rp. 59.400,00
2 Tukang Kayu Org/ Hr 0,330 Rp. 100.000,00 Rp. 33.000,00
3 Kepala Tukang Org/ Hr 0,033 Rp. 120.000,00 Rp. 3.960,00
4 Mandor Org/ Hr 0,033 Rp. 140.000,00 Rp. 4.620,00

JUMLAH HARGA TENAGA B Rp. 100.980,00


C JUMLAH TENAGA DAN BAHAN ( A + B ) Rp. 112.874,14
Terpasang Rp. 112.874,14
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


PEKERJAAN/PAKET -
-
ITEM PEMBAYARAN NO :
JENIS PEKERJAAN : Memasang Papan Lapis Dinding
SATUAN : M1
VOLUME :
LOKASI
PROP/KOTA/KODYA -

PERKIRAAN HARGA JUMLAH


NO KOMPONEN SATUAN
KUANTITAS SATUAN HARGA ( Rp )
A Bahan
1 Kayu 1" x 2" Btg 0,030 Rp. 19.343,00 Rp. 580,29
2 Paku 2"-5" Kg 0,400 Rp. 25.230,00 Rp. 10.092,00
3 Minyak Bekisting Ltr 0,200 Rp. - Rp. -
4 Papan Jati 1" x 8" x 3,4m' Kpg 0,015 Rp. 295.087,72 Rp. 4.426,32
5 Triplek 6 mm Lbr 0,350 Rp. - Rp. -
6 Kayu Bulat 5-10 cm Btg 6,000 Rp. - Rp. -

JUMLAH HARGA BAHAN A Rp. 15.098,61


B Tenaga
1 Pekerja Org/ Hr 0,660 Rp. 90.000,00 Rp. 59.400,00
2 Tukang Kayu Org/ Hr 0,330 Rp. 100.000,00 Rp. 33.000,00
3 Kepala Tukang Org/ Hr 0,033 Rp. 120.000,00 Rp. 3.960,00
4 Mandor Org/ Hr 0,033 Rp. 140.000,00 Rp. 4.620,00

JUMLAH HARGA TENAGA B Rp. 100.980,00


C JUMLAH TENAGA DAN BAHAN ( A + B ) Rp. 116.078,61
Terpasang Rp. 116.078,61
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


PEKERJAAN/PAKET -
-
ITEM PEMBAYARAN NO :
JENIS PEKERJAAN : Memasang Rangka Atap Bahan Kayu
SATUAN : Btg
VOLUME :
LOKASI
PROP/KOTA/KODYA : JALAN TUA PAYA

PERKIRAAN HARGA JUMLAH


NO KOMPONEN SATUAN
KUANTITAS SATUAN HARGA ( Rp )
A Bahan
1 Kayu Mentangor / kruwing 2" x 3" x 4,8m' Btg 1,000 Rp. 60.071,43 Rp. 60.071,43
2 Kayu Mentangor / kruwing 2" x 2" x 4,8m' Btg 4,400 Rp. - Rp. -
3 Paku 2"-5" Kg 0,100 Rp. 25.230,00 Rp. 2.523,00

JUMLAH HARGA BAHAN A Rp. 62.594,43


B Tenaga
1 Pekerja Org/ Hr 0,300 Rp. 90.000,00 Rp. 27.000,00
2 Tukang Besi Org/ Hr 0,030 Rp. 100.000,00 Rp. 3.000,00
3 Kepala Tukang Org/ Hr 0,010 Rp. 120.000,00 Rp. 1.200,00
4 Mandor Org/ Hr 0,005 Rp. 140.000,00 Rp. 700,00

JUMLAH HARGA TENAGA B Rp. 31.900,00


C JUMLAH TENAGA DAN BAHAN ( A + B ) Rp. 94.494,43
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


PEKERJAAN/PAKET -
-
ITEM PEMBAYARAN NO :
JENIS PEKERJAAN : Memasang Rangka Atap Baja Ringan Ring Gdc
SATUAN Btg
VOLUME :
LOKASI
PROP/KOTA/KODYA -

PERKIRAAN HARGA JUMLAH


NO KOMPONEN SATUAN
KUANTITAS SATUAN HARGA ( Rp )
A Bahan
1 Supertruss C.75.75 Setara Zam Steel Btg 1,000 Rp. - Rp. -
2 Supertruss V Setara Zam Steel Btg 1,000 Rp. 67.280,00 Rp. 67.280,00
3 Paku Skrup Kg 0,100 Rp. 30.276,00 Rp. 3.027,60

JUMLAH HARGA BAHAN A Rp. 70.307,60


B Tenaga
1 Pekerja Org/ Hr 0,300 Rp. 90.000,00 Rp. 27.000,00
2 Tukang Besi Org/ Hr 0,030 Rp. 100.000,00 Rp. 3.000,00
3 Kepala Tukang Org/ Hr 0,010 Rp. 120.000,00 Rp. 1.200,00
4 Mandor Org/ Hr 0,005 Rp. 140.000,00 Rp. 700,00

JUMLAH HARGA TENAGA B Rp. 31.900,00


C JUMLAH TENAGA DAN BAHAN ( A + B ) Rp. 102.207,60
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


PEKERJAAN/PAKET -
-
ITEM PEMBAYARAN NO :
JENIS PEKERJAAN : Memasang Atap
SATUAN : M2
VOLUME :
LOKASI
PROP/KOTA/KODYA : JALAN TUA PAYA

PERKIRAAN HARGA JUMLAH


NO KOMPONEN SATUAN
KUANTITAS SATUAN HARGA ( Rp )
A Bahan
1 Atap Asbes 6 ak M2 1,000 Rp. 33.640,00 Rp. 33.640,00
2 Paku Spandek Kg 0,120 Rp. 30.276,00 Rp. 3.633,12

JUMLAH HARGA BAHAN A Rp. 37.273,12


B Tenaga
1 Pekerja Org/ Hr 0,200 Rp. 90.000,00 Rp. 18.000,00
2 Tukang Kayu Org/ Hr 0,020 Rp. 100.000,00 Rp. 2.000,00
3 Kepala Tukang Org/ Hr 0,010 Rp. 120.000,00 Rp. 1.200,00
4 Mandor Org/ Hr 0,005 Rp. 140.000,00 Rp. 700,00

JUMLAH HARGA TENAGA B Rp. 21.900,00


C JUMLAH TENAGA DAN BAHAN ( A + B ) Rp. 59.173,12
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


PEKERJAAN/PAKET -
-
ITEM PEMBAYARAN NO :
JENIS PEKERJAAN : Memasang Perabung Atap Spandek
SATUAN : M'
VOLUME :
LOKASI
PROP/KOTA/KODYA : JALAN TUA PAYA

PERKIRAAN HARGA JUMLAH


NO KOMPONEN SATUAN
KUANTITAS SATUAN HARGA ( Rp )
A Bahan
1 Perabung M' 1,050 Rp. 38.545,83 Rp. 40.473,13
2 Paku Spandek Kg 0,060 Rp. 30.276,00 Rp. 1.816,56

JUMLAH HARGA BAHAN A Rp. 42.289,69


B Tenaga
1 Pekerja Org/ Hr 0,010 Rp. 90.000,00 Rp. 900,00
2 Tukang Kayu Org/ Hr 0,001 Rp. 100.000,00 Rp. 100,00
3 Kepala Tukang Org/ Hr 0,001 Rp. 120.000,00 Rp. 120,00
4 Mandor Org/ Hr 0,001 Rp. 140.000,00 Rp. 140,00

JUMLAH HARGA TENAGA B Rp. 1.260,00


C JUMLAH TENAGA DAN BAHAN ( A + B ) Rp. 43.549,69
DAFTAR HARGA SATUAN UPAH PEKERJA

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


LOKASI : JALAN TUA PAYA

NO. UPAH TENAGA KERJA SATUAN HARGA SATUAN KETERANGAN

1 2 3 4 5

1 Mandor Org/ Hr 140.000,00


2 Kepala Tukang Org/ Hr 120.000,00
3 Tukang Batu Org/ Hr 100.000,00
4 Tukang Kayu Org/ Hr 100.000,00
5 Tukang Besi Org/ Hr 100.000,00
6 Tukang Cat Org/ Hr 100.000,00
7 Operator Alat Berat Org/ Hr 100.000,00
8 Tukang Listrik Org/ Hr 100.000,00
9 Tukang Pipa Org/ Hr 100.000,00
10 Tukang Org/ Hr 100.000,00
11 Pekerja Org/ Hr 90.000,00

Jam Kerja Effektif 1 Hari 7 jam

DAFTAR HARGA SATUAN BAHAN BANGUNAN

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


LOKASI : JALAN TUA PAYA

NO. JENIS MATERIAL SATUAN HARGA SATUAN KETERANGAN

1 2 3 4 5

A BAHAN PASANGAN

1 Bata Merah Bh 2.018,40


2 Batako Bh 3.700,40
3 Batu Belah 15-20 cm M3 672.800,00
4 Batu Belah 15-20 cm Kg 498,37
5 Kerikil Granit 3/4" M3 807.360,00
6 Kerikil 3/4" Kg 598,04
7 Glass Block Bh - Terpasang
8 Pasir Beton/ Cor M3 302.760,00
9 Pasir Beton Kg 216,26
10 Pasir Pasang M3 302.760,00
11 Pasir Urug M3 302.760,00
12 Semen PC @ 50 Kg Kg 2.287,52
13 Semen Putih @ 50 Kg Kg -
14 Semen Warna Kg 30.276,00
15 Tanah Timbun ( Tanah Urug ) M3 67.280,00
16 Sirtu M3 -
17 Batu Terawang 20 x 20 cm Bh - Terpasang
18 Air Ltr 100,92

B BAHAN KAYU

1 Kayu Bulat 5-10 cm Btg 16.820,00


2 Kayu Cerucuk dia. 10-15cm Btg -
2 Kayu 2" x "2 Btg 42.050,00
3 Kayu Meranti ( kelas II ) M3 6.728.000,00
4 Kayu Campuran (Kelas III) M3 4.709.600,00
5 Kayu 1" x 2" Btg 19.343,00
6 Papan Cor kelapa Kpg 50.460,00
7 Papan Cor kelapa M3 M3 2.825.760,00
NO. JENIS MATERIAL SATUAN HARGA SATUAN KETERANGAN

1 2 3 4 5

Kayu Mentangor / kruwing 3" x 4" x 4,8m' Btg 103.507,69


6 Kayu Mentangor / kruwing 2" x 3" x 4,8m' Btg 60.071,43
7 Kayu Mentangor / kruwing 2" x 2" x 4,8m' Btg 60.071,43
8 Papan Mentangor / kruwing 3/4" x 8" x 4,8m' Kpg 89.706,67
9 Papan Mentangor / kruwing 1" x 8" x 4,8m' Kpg 120.142,86
10 Papan Meranti Mentangor 1" x 8" M3 6.728.000,00
11 Papan Meranti ( Kelas II ) 3/4" x 8" M3 6.728.000,00
12 Papan Jati 1" x 8" x 3,4m' Kpg 295.087,72
12 Tunjuk Langit Bh 5.046.000,00
13 Listplank Kayu 1" x 8" x 4,8 Kpg 120.142,86
14 Listplank GRC M' 63.075,00

C BAHAN BESI

1 Besi Beton Ø10 Btg 75.690,00


2 Besi Beton Ø12 Btg 126.150,00
3 Besi Beton Ø13 Btg 144.652,00

2 Kawat Beton ( Kawat Ikat ) Kg 21.866,00

D BAHAN LANTAI

1 Keramik Ukuran 60 x 60 KW II Bh 84.100,00


2 Keramik Ukuran 40 x 40 KW II Bh 25.230,00
3 Keramik Ukuran 20 x 40 KW II Bh 16.147,20
4 Plint Keramik 10 x 60 Bh 14.016,67

E BAHAN ATAP

1 Perabung M' 38.545,83


2 Atap genteng metal pasir M2 39.246,67
3 Atap Asbes 6 ak M2 33.640,00
4 Atap Go Green 7 ak M2 39.246,67
5 Atap Go Green 8 ak M2 44.853,33
6 Talang Air M1 72.326,00

F BAHAN DINDING DAN LANGIT - LANGIT

1 Gibsun Setara Jaya Board 8 mm Lbr 92.510,00


2 Plafon PVC Lbr 470.960,00
3 Ekafuring M' 14.016,67
4 List Kayu Pracetak M' -
5 Triplek 4 mm Lbr 114.376,00
4 Triplek 6 mm Lbr 142.970,00
5 Triplek 8 mm Lbr 193.430,00

G BAHAN PIPA

1 Pipa Wavin D 3 " M' 23.828,33 Terpasang


2 Pipa Wavin D 2 " M' 14.016,67 Terpasang
3 Pipa Wavin D 1.1/5 " M' 23.828,33 Terpasang
4 Pipa Wavin D 1/5 " M' 23.828,33 Terpasang
5 Pipa Wavin D 1/2" M' 8.410,00 Terpasang
6 Pipa Wavin D 3/4" M' 11.774,00 Terpasang

H BAHAN SANITAIR

1 Kloset Duduk Keramik Bh 3.027.600,00 Terpasang


2 Kran Air 1/2" Bh 21.025,00 Terpasang
3 Wastafel Keramik Bh 1.682.000,00 Terpasang
4 Floor Drain Stainless Steel Bh 45.414,00
NO. JENIS MATERIAL SATUAN HARGA SATUAN KETERANGAN

1 2 3 4 5

I BAHAN PAKU

1 Paku 2"-5" Kg 25.230,00


2 Paku 1/2"-1" Kg 25.230,00
3 Paku Spandek Kg 30.276,00
4 Paku Gypsum Kg 30.276,00
5 Paku Kayu Kg 25.230,00
6 Paku Skrup Kg 30.276,00
7 Paku Tripleks/ Teakwood Kg 30.276,00

J BAHAN PENGGANTUNG/ KUNCI

1 Engsel Pintu Bh 53.824,00 Terpasang


2 Grendel Pintu Bh 112.694,00 Terpasang
3 Kunci Tanam 2 x Putar Bh 538.240,00 Terpasang

K BAHAN STAINLESS

1 Stainless Steel M' 2.523.000,00

L BAHAN HOLLOW

1 Besi Hollow 1,1/2" x 1/2" M' 1.345.600,00


2 Besi Hollow 1/2" M' 1.051.250,00

M BAHAN PLAT BESI

1 Plat Besi 2mm M2 756.900,00


2 Besi 1,1/2" x 3mm M' 252.300,00

N BAHAN KACA

1 Kaca Hitam 5mm + Rangka Alumunium M2 945.284,00 Terpasang


2 Kaca Bening 5mm + Rangka Alumunium M2 943.602,00 Terpasang
3 Kaca Reflective + Rangka Alumunium M2 1.473.432,00 Terpasang

O BAHAN BATU ALAM


1 Batu Alam M2 386.860,00 Terpasang

P BAHAN COMPOSITE

1 Composite USA + Rangka M2 1.513.800,00 Terpasang

Q BAHAN LISTRIK

1 Titik Lampu Ttk 235.480,00


2 Sarang Lampu Down Light Komplit Bh 58.870,00
3 Lampu SL 20 Watt Bh 100.920,00
4 Arde Pentanahan Netral (Lengkap) Bh 588.700,00
5 Stop Kontak Bh 33.640,00
6 Saklar Ganda Bh 25.230,00
7 Saklar Triple Bh 33.640,00
8 Panel MCB Komplit Bh 84.100,00
9 Cabel tunggal 2,5mm - 100m M' 4.709,60
10 meteran 1300w Ls 3.784.500,00
11 Mesin Genset Ls 5.046.000,00
NO. JENIS MATERIAL SATUAN HARGA SATUAN KETERANGAN

1 2 3 4 5
R BAHAN PINTU & JENDELA

1 Pintu Panel + Kusen (Kayu) kelas II M2 1.143.760,00 Terpasang


2 Pintu Kaca Bening 5mm + Stiker Blur + Kusen Alumunium M2 1.110.120,00 Terpasang
3 Pintu Kaca Bening 12mm + stiker Blur + Kusen Alumunium M2 1.412.880,00 Terpasang
4 Pintu Kaca Blur + Kusen Alumunium M2 1.126.940,00 Terpasang
5 Jendela Kaca Reflective + Kusen Alumunium M2 1.473.432,00 Terpasang
6 Jendela Kaca Hitam 5 mm + Kusen Alumunium M2 945.284,00 Terpasang
7 Pintu PVC Bh 841.000,00 Terpasang

S BAHAN FINISHING

1 Cat Minyak Kimton Kg 151.380,00


2 Cat Tembok Nipon Kg 26.071,00
3 Minyak Bekisting Ltr 21.025,00
4 Minyak Cat Ltr 42.050,00
5 Plamir ex. RJ Kg 42.050,00

T BAHAN BAJA RINGAN

1 Supertruss C.75.75 Setara Zam Steel Btg 92.510,00 Terpasang


2 Supertruss V Setara Zam Steel Btg 67.280,00 Terpasang

U BAHAN PERLENGKAPAN

1 AC 2 Pk Unit 9.671.500,00 Terpasang


2 Exhaust Fan Ventilasi Unit 925.100,00 Terpasang
3 Bak PVC Bh 841.000,00
4 Racun Api Drv Chemical Bh 1.757.690,00

V BAHAN PLASTIK
Drum Material Plastik Bh 420.500,00

V PERALATAN

1 Alat Berat Jam -


2 Alat Pancang M' -
3 Join Lass Ls -
ENGINEER ESTIMATE ( EE )

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


LOKASI : JALAN TUA PAYA

HARGA SAT JMLH. TOTAL


NO URAIAN PEKERJAAN VOLUME
( Rp ) ( Rp )
1 2 3 4 5

I. PEKERJAAN PENDAHULUAN
1 Pengukuran dan Pemancangan Patok 52,70 M' 22.232,03 1.171.627,93
2 Pemb. Direksi Keet dan Gudang Bahan 1,00 Ls 5.000.000,00 5.000.000,00
6.171.627,93
II. PEK. PAS PELAMPUNG
1 Pek. Perakitan Pelampung Bahan Drum Plastik 60,00 Bh 420.500,00 25.230.000,00
2 Pek. Tali Ikat 6mm 1,00 Ls 3.000.000,00 3.000.000,00
3 Pek. Baut Angkur 13mm 175,00 Btg 50.000,00 8.750.000,00
36.980.000,00
III PEKERJAAN LANTAI DAN DINDING

1 Pek. Kayu Rasuk Lantai Kayu 2" x 4" x 4,8m' 92,50 Btg 112.624,62 10.417.776,92
2 Pek. Lantai Papan 1.1/2' x 8' x 4,8m' 150,00 Kpg 112.874,14 16.931.121,43
3 Pek. Tiang Dinding Kayu 2" x 4" x 4,8m' (lapis dua) 18,00 Btg 112.624,62 2.027.243,08
3 Pek. Dinding Papan 1.1/2' x 8' x 4,8m' 95,00 Kpg 112.874,14 10.723.043,57
40.099.185,00

IV PEKERJAAN PAGAR
1 Pek. Tiang Pagar Ø15cm P.1,2m 45,00 Btg 16.820,00 756.900,00
4 Pek. Pagar Kasaw Ø15cm P.1,2m 135,00 M³ 16.820,00 2.270.700,00
3.027.600,00

V PEKERJAAN PINTU
1 Pek. Pintu Genset 1,00 Bh 680.000,00 680.000,00
2 Pek. Pintu Wc PVC 2,00 Bh 1.110.120,00 2.220.240,00
1 Engsel Pintu 12,00 Bh 53.824,00 645.888,00
2 Grendel Pintu 3,00 Bh 112.694,00 338.082,00
3.884.210,00
VI PEKERJAAN LISTRIK
1 Instalasi Listrik 20,00 Titik 235.480,00 4.709.600,00
2 MCB 2,00 Bh 84.100,00 168.200,00
3 Stop Kontak Tunggal 8,00 Bh 33.640,00 269.120,00
4 Saklar Mata 3 5,00 Bh 33.640,00 168.200,00
5 Saklar Mata 2 2,00 Bh 25.230,00 50.460,00
6 Lampu Atom Hias 1,00 Bh 1.250.000,00 1.250.000,00
7 Lampu LED 20 Watt 26,00 Bh 55.000,00 1.430.000,00
8.045.580,00
VII PEKERJAAN INSTALASI AIR & SANITASI
1 Pek. Tempat cuci piring 1,00 Bh 400.000,00 400.000,00
2 Pek. Closet Jongkok 2,00 Bh 3.027.600,00 6.055.200,00
3 Bak PVC 2,00 Bh 841.000,00 1.682.000,00
4 Pek. Instalasi Air Bersih 1,00 Ls 500.000,00 500.000,00
5 Pek. Instalasi Air Kotor 1,00 Ls 500.000,00 500.000,00
7 Fantrye 1,00 Ls 500.000,00 500.000,00
9 Tanky Air 1000 Ltr 1,00 Ls 1.300.000,00 1.300.000,00
10.937.200,00
VIII PEKERJAAN ATAP
1 Pek. Kuda- kuda Atap 2/3" 28,33 Btg 94.494,43 2.677.342,14
2 Pek. Gulung- gulung Atap 2/2" 34,00 Btg 102.207,60 3.475.058,40
3 Pek. Atap Asbes 104,00 M² 59.173,12 6.154.004,48
4 Pek. Perabung 28,00 M' 43.549,69 1.219.391,18
5 List Plank Kayu 1" x 8" x 4,8m' 25,00 Kpg 139.857,60 3.496.440,00
6 Pas Talang Air 50,00 M' 72.326,00 3.616.300,00
20.638.536,20
IX PEKERJAAN AKHIR
1 Pek. Pas Mesin Genset 1,00 Ls 5.046.000,00 5.046.000,00
2 Pek. Pembersihan Akhir 1,00 Ls 1.500.000,00 1.500.000,00
6.546.000,00
REKAPITULASI

KEGIATAN : PEMBANGUNAN RESTORAN APUNG


LOKASI : JALAN TUA PAYA

I. PEKERJAAN PENDAHULUAN Rp 6.171.627,93

II. PEK. PAS PELAMPUNG Rp 36.980.000,00

III. PEKERJAAN LANTAI DAN DINDING Rp 40.099.185,00

IV. PEKERJAAN PAGAR Rp 3.027.600,00

V. PEKERJAAN PINTU Rp 3.884.210,00

VI. PEKERJAAN LISTRIK Rp 8.045.580,00

VII. PEKERJAAN INSTALASI AIR & SANITASI Rp 10.937.200,00

VIII. PEKERJAAN ATAP Rp 20.638.536,20

IX. PEKERJAAN AKHIR Rp 6.546.000,00


JUMLAH . = Rp 136.329.939,13

PPH/PPN 11 % = Rp 13.632.993,91

JUMLAH TOTAL = Rp 149.962.933,04

DIBULATKAN = Rp 149.970.000,00

Terbilang : Seratus empat puluh sembilan juta sembilan ratus tujuh puluh ribu Rupiah

Tanjung Pinang, .....................2019

Diperiksa Oleh : Dibuat Oleh :


PEJABAT PEMBUAT KOMITMEN (PPK) CV. HABIS GELAP TERBITLAH TERANG
DINAS PARIWISATA
KEPULAUAN RIAU

BAH LEM , SH SETIA PUTRA, ST, IAI


NIP. 1982 0403 201101 1 011 Supervisi Engineer