Capital Budgeting Pt. X - Network
Capital Budgeting Pt. X - Network
Analisa Keuangan
Internal Rate Of Return : 31%
Net Present Value : 36,678,944,254 at discount rate of
Pay Back Period : 95 bulan
8 Tahun
=2,29319 years
11%
Rp (37,038,214,803.54)
PVIF (31%) Rp 4,074,203,628.39
0.7634 -Rp 11,928,502,119.60 -Rp 11,928,502,119.60 Rp 7,335,813,146.38
0.5827 -Rp 9,250,600,225.87 -Rp 21,179,102,345.47
0.4438 Rp 2,366,866,474.72 -Rp 18,812,235,870.75 Rp 3,261,609,517.99
0.3396 Rp 2,827,607,148.40 -Rp 15,984,628,722.35
0.2592 Rp 3,015,531,682.07 -Rp 12,969,097,040.28 -0.088060656683693
0.1979 Rp 2,937,025,162.52 -Rp 10,032,071,877.76
0.1510 Rp 2,766,395,338.73 -Rp 7,265,676,539.03
0.1153 Rp 2,547,218,062.55 -Rp 4,718,458,476.48
0.0880 Rp 2,303,479,704.24 -Rp 2,414,978,772.24
0.0672 Rp 2,055,829,700.60 -Rp 359,149,071.64
-Rp 359,149,071.64
PVIF (20%)
0.8333 -Rp 13,020,724,150.20 -Rp 13,020,724,150.20
0.6944 -Rp 11,023,883,296.45 -Rp 24,044,607,446.65
0.5787 Rp 3,086,312,818.65 -Rp 20,958,294,628.00
0.4823 Rp 4,015,768,338.26 -Rp 16,942,526,289.74
0.4019 Rp 4,675,702,866.61 -Rp 12,266,823,423.13
0.3349 Rp 4,970,236,113.83 -Rp 7,296,587,309.30
0.2791 Rp 5,113,251,251.92 -Rp 2,183,336,057.38
0.2326 Rp 5,138,620,306.59 Rp 2,955,284,249.21
0.1938 Rp 5,072,890,530.47 Rp 8,028,174,779.68
0.1615 Rp 4,940,721,676.30 Rp 12,968,896,455.98
Rp 12,968,896,455.98
Tahun 7 Tahun 8 Tahun 9 Tahun 10
IDR IDR IDR IDR
18,320,498,932 22,092,090,742 26,175,905,730 30,592,703,878
0 0 0 0
0 0 0 0
0 0 0 0
18,320,498,932 22,092,090,742 26,175,905,730 30,592,703,878
26,954,018,423 49,046,109,165 75,222,014,894 105,814,718,772
Total
IDR
115,814,718,772
78,542,000,000
(78,542,000,000)
(10,000,000,000)
105,814,718,772
PROYEKSI CASH FLOW - 10 TAHUN
LEMBAGA PENYELENGGARAAN PENYIARAN MULTIPLEKSING
ZONA LAYANAN 4
PT. X-NETWORK
URAIAN
Arus Kas Dari Kegiatan Operasi
Laba (rugi) bersih Rp
20,000,000,000 10,000,000,000
(78,542,000,000)
78,542,000,000
20,000,000,000 10,000,000,000 - -
- - - -
26,175,905,730 30,592,703,878
3,833,350,000 3,833,350,000
(262,093,956) (288,303,352)
(11,081,545,138) (12,411,330,555)
(1,496,164,611) (1,675,704,364)
(6,543,976,432) (7,648,175,969)
10,625,475,592 12,402,539,638
- -
10,625,475,592 12,402,539,638
40,453,186,979 51,078,662,571
51,078,662,571 63,481,202,209
PROYEKSI RUGI LABA - 10 TAHUN
LEMBAGA PENYELENGGARAAN PENYIARAN MULTIPLEKSING
ZONA LAYANAN 4
PT. X-NETWORK
b. Biaya-Biaya :
- 1. Biaya BHP Jabotabek Rp 407,500,000 40,750,000 40,750,000 40,750,000 40,750,000
2. Biaya BHP Cilegon Rp 100,000,000 10,000,000 10,000,000 10,000,000 10,000,000
3. Biaya BHP Malingping Rp 100,000,000 10,000,000 10,000,000 10,000,000 10,000,000
4. Biaya BHP Pandeglang Rp 100,000,000 10,000,000 10,000,000 10,000,000 10,000,000
- 1. Biaya Listrik Sistem Pemancar Jabotabek Rp 18,475,776,000 1,847,577,600 1,847,577,600 1,847,577,600 1,847,577,600
2. Biaya Listrik Sistem Pemancar Cilegon Rp 3,580,848,000 358,084,800 358,084,800 358,084,800 358,084,800
3. Biaya Listrik Sistem Pemancar Malingping Rp 3,580,848,000 358,084,800 358,084,800 358,084,800 358,084,800
4. Biaya Listrik Sistem Pemancar Pandeglang Rp 3,580,848,000 358,084,800 358,084,800 358,084,800 358,084,800
- 1. Pemeliharaan Sistem Pemancar Jabotabek Rp 1,800,000,000 180,000,000 180,000,000 180,000,000 180,000,000
2. Pemeliharaan Sistem Pemancar Cilegon Rp 1,800,000,000 180,000,000 180,000,000 180,000,000 180,000,000
3. Pemeliharaan Sistem Pemancar Malingping Rp 1,800,000,000 180,000,000 180,000,000 180,000,000 180,000,000
4. Pemeliharaan Sistem Pemancar Pandeglang Rp 1,800,000,000 180,000,000 180,000,000 180,000,000 180,000,000
Total Pendapatan Bruto Rp 364,545,876,570 6,400,000,000 18,500,000,000 29,700,000,000 32,670,000,000 35,937,000,000 39,530,700,000
b. Biaya-Biaya :
- 1. Biaya BHP Jabotabek Rp 407,500,000 40,750,000 40,750,000 40,750,000 40,750,000 40,750,000 40,750,000
2. Biaya BHP Cilegon Rp 100,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000
3. Biaya BHP Malingping Rp 100,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000
4. Biaya BHP Pandeglang Rp 100,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000
- 1. Biaya Listrik Sistem Pemancar Jabotabek Rp 18,475,776,000 1,847,577,600 1,847,577,600 1,847,577,600 1,847,577,600 1,847,577,600 1,847,577,600
2. Biaya Listrik Sistem Pemancar Cilegon Rp 3,580,848,000 358,084,800 358,084,800 358,084,800 358,084,800 358,084,800 358,084,800
3. Biaya Listrik Sistem Pemancar Malingping Rp 3,580,848,000 358,084,800 358,084,800 358,084,800 358,084,800 358,084,800 358,084,800
4. Biaya Listrik Sistem Pemancar Pandeglang Rp 3,580,848,000 358,084,800 358,084,800 358,084,800 358,084,800 358,084,800 358,084,800
- 1. Pemeliharaan Sistem Pemancar Jabotabek Rp 1,800,000,000 180,000,000 180,000,000 180,000,000 180,000,000 180,000,000 180,000,000
2. Pemeliharaan Sistem Pemancar Cilegon Rp 1,800,000,000 180,000,000 180,000,000 180,000,000 180,000,000 180,000,000 180,000,000
3. Pemeliharaan Sistem Pemancar Malingping Rp 1,800,000,000 180,000,000 180,000,000 180,000,000 180,000,000 180,000,000 180,000,000
4. Pemeliharaan Sistem Pemancar Pandeglang Rp 1,800,000,000 180,000,000 180,000,000 180,000,000 180,000,000 180,000,000 180,000,000
Pendapatan dari Operasional Rp 127,098,103,089 (15,625,494,000) (5,719,268,173) 5,504,936,463 8,515,216,404 11,841,817,761 15,510,887,387
D. INVESTING ACTIVITIES
a. Infrastructure (gedung, M&E dll) Jabodetabek Rp (26,705,000,000) (26,705,000,000)
b. Infrastructure (gedung, M&E dll) Cilegon Rp (16,779,000,000) (16,779,000,000)
c. Infrastructure (gedung, M&E dll) Malingping Rp (17,529,000,000) (17,529,000,000)
d. Infrastructure (gedung, M&E dll) Pandeglang Rp (17,529,000,000) (17,529,000,000)
e. Modal Kerja Rp (10,000,000,000) - (10,000,000,000)
CASH DARI OPERASIONAL Rp (88,542,000,000) (59,109,494,000) (40,777,268,173) 5,504,936,463 8,515,216,404 11,841,817,761 15,510,887,387
E. FINANCING ACTIVITIES
a. Pinjaman Investasi Jabodetabek Rp 26,705,000,000
b. Pinjaman Investasi Cilegon Rp 16,779,000,000
c. Pinjaman Investasi Malingping Rp 17,529,000,000
d. Pinjaman Investasi Pandeglang Rp 17,529,000,000
e. Pinjaman Modal Kerja Rp 20,000,000,000 10,000,000,000
f. Pengembalian Investasi & Modal Kerja Rp 88,542,000,000 - - 10,000,000,000 10,000,000,000 15,000,000,000 15,000,000,000
32,210,200,000
8,784,600,000
732,050,000
1,756,920,000
43,483,770,000
10%
265,734,150
-
88,578,050
88,578,050
442,890,250
40,750,000
10,000,000
10,000,000
10,000,000
1,847,577,600
358,084,800
358,084,800
358,084,800
180,000,000
180,000,000
180,000,000
180,000,000
3,712,582,000
5,382,324,420
637,761,960
212,587,320
1,062,936,600
193,627,225
-
1,700,698,560
425,174,640
488,812,654
21,258,732
1,062,937
10,629,366
42,517,464
5,750,605,904
3,833,350,000
19,763,347,781
23,918,820,031
19,564,949,969
19,564,949,969
20,000,000,000
8,248,283,636
8,683,333,668
8,248,283,636
PROYEKSI NERACA - 10 TAHUN
LEMBAGA PENYELENGGARAAN PENYIARAN MULTIPLEKSING
ZONA LAYANAN 4
PT. X-NETWORK
building 5%
Machinery 5.0%
Aktiva Modal Awal Tahun 1
Aktiva Lancar
Kas 20,000,000,000 3,381,520,847
Piutang 0 350,684,932
Aktiva lancar lainnya 0 0
Total Aktiva Lancar 20,000,000,000 3,732,205,779
Aktiva Tetap
Bangunan & Infrastruktur 2,940,000,000 2,940,000,000
Tanah 1,875,000,000 1,875,000,000
Mesin dan peralatan 73,727,000,000 73,727,000,000
Akumulasi Penyusutan 0 3,833,350,000
Total Aktiva Tetap 78,542,000,000 74,708,650,000
Pendapatan 0 (15,625,494,000)
Total Modal 20,000,000,000 4,374,506,000
0 0
-
-
147,000,000
3,686,350,000
Tahun 2 Tahun 3 Tahun 4 Tahun 5 Tahun 6
0 0 0 0 0
9,323,211,112 8,565,207,558 7,716,243,577 6,765,403,919 5,700,463,502
0 0 0 0 0
(21,500,901,973) (16,167,719,291) (7,841,432,045) 3,792,563,643 13,975,139,619
- - - - 0
Tahun 7 Tahun 8 Tahun 9 Tahun 10
0 0 0 0
4,507,730,234 3,171,868,975 1,675,704,364 0
0 0 0 0
27,715,513,817 44,284,581,874 63,916,511,171 86,861,039,079
0 0 0 0
PENDAPATAN DARI SEWA
Tahun1
No Jabatan Qty Salary /bulan Total Gaji /Tahun
Tahun
IDR IDR
1 Direktur Utama 1 25,000,000 12 300,000,000
1. Jabodetabek menggunakan litstrik sebesar : 158,4 KVA maka biaya listrik perbulan :
2. Cilegon menggunakan listrik sebesar : 30,7 KVA maka biaya listrik per bulan :
3. Pandeglang menggunakan listrik sebesar : 30,7 KVA maka biaya listrik per bulan :
4. Malingping menggunakan listrik sebesar : 30,7 KVA maka biaya listrik per bulan :
Yearly
Rp 1,847,577,600
Rp 358,084,800
HARGA
NO URAIAN VOLUME SATUAN
(Rp)
I JABODETABEK
A TANAH eksisting
B MENARA eksisting
C BANGUNAN GEDUNG
1. Gedung Pemancar 80 m eksisting
2. Gedung Mekanikal dan Elektrikal 40 m eksisting
3. Gedung Administrasi 100 m eksisting
D PERALATAN TRANSMISI
1. Antenna System
- Antenna System 32 panel 1 eksisting
- Coaxial Feeder 3 1/8 " 250 m eksisting
- Patch Pannel eksisting
- Dummy Load 20 KW eksisting
2. Pemancar TV digital Solid State dual 2 6,000,000,000
drive 5 KW
- Channel Combiner 1 1,250,000,000
3. Program Input Monitoring (PIM) 1 300,000,000
4. Head End
- Encoder MPEG 4 10 275,000,000
- Multiplex 8:1 2 250,000,000
5. Meassuring Equipment 1 1,500,000,000
HARGA
NO URAIAN VOLUME SATUAN
(Rp)
II CILEGON
C BANGUNAN GEDUNG
1. Gedung Pemancar & Administrasi 80 m 4,000,000
2. Gedung Mekanikal dan Elektrikal 40 m 4,000,000
D PERALATAN TRANSMISI
1. Antenna System
- Antenna System 16 panel 1 500,000,000
- Coaxial Feeder 1 5/8 " 150 m 500,000
- Patch Pannel 1 50,000,000
- Dummy Load 5 KW 1 50,000,000
2. Pemancar TV digital Solid State dual 2 1,000,000,000
drive 500 W
TOTAL
BIAYA PEMBANGUNAN PENYELENGGARAAN LP3M TV DIGITAL PANDEGLANG
HARGA
NO URAIAN VOLUME SATUAN
(Rp)
III PANDEGLANG
C BANGUNAN GEDUNG
1. Gedung Pemancar 80 m 4,000,000
2. Gedung Mekanikal dan Elektrikal 40 m 4,000,000
3. Gedung Administrasi 0m 3,000,000
D PERALATAN TRANSMISI
1. Antenna System
- Antenna System 16 panel 1 500,000,000
- Coaxial Feeder 1 5/8 " 150 m 500,000
- Patch Pannel 1 50,000,000
- Dummy Load 5 KW 1 50,000,000
2. Pemancar TV digital Solid State dual 2 1,000,000,000
drive 500 W
- Channel Combiner 0 1,250,000,000
3. Program Input Monitoring (PIM) 1 300,000,000
4. Head End
- Encoder MPEG 4 10 275,000,000
- Multiplex 8:1 2 250,000,000
5. Meassuring Equipment 0 1,500,000,000
TOTAL
C BANGUNAN GEDUNG
1. Gedung Pemancar 80 m 4,000,000
2. Gedung Mekanikal dan Elektrikal 40 m 4,000,000
3. Gedung Administrasi 0m 3,000,000
D PERALATAN TRANSMISI
1. Antenna System
- Antenna System 16 panel 1 500,000,000
- Coaxial Feeder 1 5/8 " 150 m 500,000
- Patch Pannel 1 50,000,000
- Dummy Load 5 KW 1 50,000,000
2. Pemancar TV digital Solid State dual 2 1,000,000,000
drive 500 W
- Channel Combiner 0 1,250,000,000
3. Program Input Monitoring (PIM) 1 300,000,000
4. Head End
- Encoder MPEG 4 10 275,000,000
- Multiplex 8:1 2 250,000,000
5. Meassuring Equipment 0 1,500,000,000
TOTAL
TOTAL Capex
AL JABODETABEK
JUMLAH
HARGA
(Rp)
-
-
-
-
-
-
-
12,000,000,000 12,000,000,000
-
1,250,000,000 1,250,000,000
300,000,000 300,000,000
-
2,750,000,000 2,750,000,000
500,000,000 500,000,000
1,500,000,000 1,500,000,000
-
-
7,500,000,000 7,500,000,000
750,000,000 750,000,000
-
-
- -
- -
- -
- -
80,000,000 80,000,000
75,000,000 75,000,000
26,705,000,000
26,705,000,000
ITAL CILEGON
JUMLAH
HARGA
(Rp)
JUMLAH
HARGA
(Rp)
625,000,000 625,000,000
-
750,000,000 750,000,000
-
- -
320,000,000 320,000,000
160,000,000 160,000,000
- -
-
- -
- -
500,000,000 500,000,000
75,000,000 75,000,000
50,000,000 50,000,000
50,000,000 50,000,000
2,000,000,000 2,000,000,000
-
- -
300,000,000 300,000,000
-
2,750,000,000 2,750,000,000
500,000,000 500,000,000
- -
-
-
7,500,000,000 7,500,000,000
750,000,000 750,000,000
-
-
200,000,000 200,000,000
300,000,000 300,000,000
300,000,000 300,000,000
250,000,000 250,000,000
24,000,000 24,000,000
125,000,000 125,000,000
15,674,000,000
17,529,000,000
MALINGPING
JUMLAH
HARGA
(Rp)
625,000,000 625,000,000
-
750,000,000 750,000,000
-
- -
320,000,000 320,000,000
160,000,000 160,000,000
- -
-
- -
- -
500,000,000 500,000,000
75,000,000 75,000,000
50,000,000 50,000,000
50,000,000 50,000,000
2,000,000,000 2,000,000,000
-
- -
300,000,000 300,000,000
-
2,750,000,000 2,750,000,000
500,000,000 500,000,000
- -
-
-
7,500,000,000 7,500,000,000
750,000,000 750,000,000
-
-
200,000,000 200,000,000
300,000,000 300,000,000
300,000,000 300,000,000
250,000,000 250,000,000
24,000,000 24,000,000
125,000,000 125,000,000
15,674,000,000
17,529,000,000
78,542,000,000
MODAL KERJA - 10 TAHUN
(3,539,683,283)
Rate 12.0%
(1,876,788,888)
Tahun Pinjaman Pokok Pinjaman Pemby Pokok
IDR IDR IDR
1 0 0
2 10,000,000,000 9,323,211,112 676,788,888
3 8,565,207,558 758,003,554
4 7,716,243,577 848,963,981
5 6,765,403,919 950,839,658
6 5,700,463,502 1,064,940,417
7 4,507,730,234 1,192,733,267
8 3,171,868,975 1,335,861,260
9 1,675,704,364 1,496,164,611
10 0 1,675,704,364
Bunga Pembayaran
IDR IDR
2,400,000,000 3,539,683,283
2,263,238,006 3,539,683,283
2,110,064,573 3,539,683,283
1,938,510,328 3,539,683,283
1,746,369,573 3,539,683,283
1,531,171,928 3,539,683,283
1,290,150,565 3,539,683,283
1,020,206,639 3,539,683,283
717,869,441 3,539,683,283
379,251,780 3,539,683,283
Bunga Pembayaran
IDR IDR
1,200,000,000 1,876,788,888
1,118,785,333 1,876,788,888
1,027,824,907 1,876,788,888
925,949,229 1,876,788,888
811,848,470 1,876,788,888
684,055,620 1,876,788,888
540,927,628 1,876,788,888
380,624,277 1,876,788,888
201,084,524 1,876,788,888
PINJAMAN JANGKA PANJANG - 10 TAHUN
(13,900,690,221)
Rate 12.0%