KENDARAAN BERMOTOR
KENDARAAN RINGAN (H)
JUMLAH TOTAL
TRUK 5 AS (M)
TRUK 2 AS (K)
TRUK 3 AS (L)
TRUK 2 AS (J)
BUS (I)
1 2 3 4 5b 6a
980 490 230 410 330 280 2,720
KENDARAAN BERMOTOR
KENDARAAN RINGAN (H)
JUMLAH TOTAL
TRUK 5 AS (M)
TRUK 2 AS (K)
TRUK 3 AS (L)
TRUK 2 AS (J)
BUS (I)
1 2 3 4 5b 6a
490 882 506 902 726 616 4,122
1. Ditetapkan :
Faktor penyesuaian ( F ) ;
Fcw = 1.00 Faktor Penyesuaian Lebar Jalur Lalu-lintas
Fsp = 1.00 2/2 UD Faktor Penyesuaian Pemisah Arah
Fsf = 0.95 Faktor Penyesuaian Hambatan Samping
C = Co x F
C = 2,755.00 pcu/h
QV 2,720.00
DS Lapangan = = = 0.99
C 2,755.00
0.67
KTOR PENYESUAIAN PEMISAH ARAH
100-0
0.70
0.85
TAHUN KE -
NO. URAIAN SATUAN
1 2 3 4 5 6 7 8 9 10
8 ESAL 4 ( x 10 ^6 )
KENDARAAN RINGAN (H) KEND 78 81 83 86 89 93 95 97 100 102
BUS (I) KEND 76 79 81 84 87 90 92 95 97 100
TRUK 2 AS (J) KEND 283 293 303 313 324 336 344 23 23 24
TRUK 2 AS (K) KEND 1,091 1,129 1,168 1,209 1,252 1,296 1,328 997 1,022 1,048
TRUK 3 AS (L) KEND 1,534 1,588 1,644 1,701 1,761 1,822 1,868 757 776 796
TRUK 5 AS (M) KEND 2,272 2,351 2,433 2,519 2,607 2,698 2,765 1,087 1,114 1,142
JUMLAH ESA KEND 5,333 5,520 5,713 5,913 6,120 6,334 6,493 3,057 3,133 3,211
10 KAPASITAS JALAN
- LHR KEND/HR 2,720 2,815 2,914 3,016 3,121 3,231 3,154 3,265 3,379 3,397
LHR SMP/HR 4,122 4,266 4,416 4,570 4,730 4,896 4,780 4,948 5,121 5,148
- Kapasitas (C) 2,755 2,755 2,755 2,755 2,755 2,755 2,755 2,755 2,755 2,755
- Volume LL ( QV ) 2,720 2,815 2,914 3,016 3,121 3,231 3,154 3,265 3,379 3,430
- VC - R 0.99 1.02 1.06 1.09 1.13 1.17 1.14 1.19 1.23 1.25
4 0.300 0.450
5 0.250 0.425
6 0.200 0.400
PERHITUNGAN TEBAL PERKERASAN (PELEBARAN) / BARU
JALAN BARU
Formula
Log Wt = Zr x S0 + 9,36 Log (SN + 1) - 0,20 + (Log (DPSI/(4,2-1,5))/(0,4+(1094/(SN+1)^5,19))
+ 2,32 Log MR - 8,07
Design (Pelebaran)
AC - WC Mod, thickness ( cm ) Ms = 1000 = 4.00 a1= 0.42 1.68
AC - BC Mod, thickness ( cm ) Ms = 1000 = 6.00 a2= 0.40 2.40
AC- Bace, thickness ( cm ) = 16.00 a3= 0.36 5.76
Cement Teated Base ( CTB) CBR 90 % = 15.00 a5= 0.21 3.15
Aggregat Class A (cm) CBR 90 % = 15.00 a6= 0.14 2.03
Total Tebal = 56.00 Total 15.02 cm
Summary :
AC - WC, thickness ( cm ) = 4
AC - BC , thickness ( cm ) = 6
AC- Bace, thickness ( cm ) = 16
Cement Teated Base ( CTB) = 15
Aggregat Clas B, thickness ( cm ) = 15 CEK SN LAPIS PONDASI = 34.47 %
CBR tanah equal 3,8%
Alternatif Bagan Desain 3A:
Desain Perkerasan Lentur - Aspal dng Lapis Pondasi Berbutir
(Solusi untuk Reliabilitas 80% Umur Rencana 20 Tahun)
STRUKTUR PERKERASAN
FF1 FF2 FF3 FF4 FF5 FF6 FF7 FF8 FF9
Solusi yang dipilih Lihat Catatan 3 Lihat Catatan 3
Pengulangan beban
sumbu desain 20
tahun di lajur rencana 1-2 2-4 4–7 7 - 10 10 - 20 20 - 30 30 - 50 50 - 100 100 - 200
(pangkat 5)
(106 CESA5)
KETEBALAN LAPIS PERKERASAN (mm)
AC WC 40 40 40 40 40 40 40 40 40
AC BC 60 60 60 60 60 60 60 60 60
AC Base 0 70 80 105 145 160 180 210 245
LPA 400 300 300 300 300 300 300 300 300
Catatan 1 1 2 2 3 3 3 3 3