1.0 Purpose
2.0 Definition
Pipe pushed through the ground using high performance hydraulic equipment
with minimum disturbance to the sub-strata for the pipes dia from 20" and
above using steerable head remote controlled, which guarantees a high level
of accuracy.
3.0 Responsibilities
3.1 The Division Manager is responsible for ensuring the integrity of the
process in accordance with contract requirements.
3.2 The Field Supervisor is responsible for Safety and process operations to
an acceptable level.
3.3 The Q.C. Coordinator shall verify the production activities on a spot
check basis (depending upon the contract).
3.4 The Safety Officer is responsible for verifying that Safety requirements
are being met, on a spot check basis (depending upon the contract).
For this project the thrust and reception pit will be constructed on
either side of the two designated obstacles - a road in one case and
existing utilities in the other.
Survey points are then transferred from the datum points and fixed
points set in the compacted base slab for easy reference.
Page 3
Anabeeb Pipeline Division
The Micro-tunneling rig will be set up in the launch pit on the level
concrete pad. A double skinned, steel wall will be installed against the
rear wall of the pit to withstand the pipe’s thrusting force.
The reception pit is a receiving pit created to recover the steering head
and equipment. This is excavated at termination point. The reception
pit dimensions: 5 m long x 9 m wide x depth to suit.
4.2.1. General
Page 4
Anabeeb Pipeline Division
The only excavation required from the surface is for thrust and
reception pits.
The mixed/rock cutting head is used for this project. The cutting
wheel is equipped with carbide tipped tools to cut the entire face
of the tunnel. Excavated material passes through openings in
the cutting wheel into the crushing/mixing chamber.
Page 5
Anabeeb Pipeline Division
Page 6
Anabeeb Pipeline Division
The container may also be used with AVT type machines using
auger material transport, if so required at a later date.
Page 7
Anabeeb Pipeline Division
Via the main processor, the actual position of the cutting head is
calculated and displayed graphically on a color monitor built into
the control panel. A complete record of the thrust is stored in
the processor and a printout is available at any time during the
thrust via the printer provided in the control/power pack module
Page 8
Anabeeb Pipeline Division
Once the spacers and carrier pipe have been inserted, both ends
of the sleeve pipe are closed with steel plates and both the
Carrier Pipe ends pass through the steel plate.
Page 9
Anabeeb Pipeline Division
This pumping process will continue until the sleeve pipe is full.
The sleeve pipe will be full when the grout flows through the
other end (hole) of the pipe.
5 SAFETY
5.1 GENERAL
General PPE supplied are, overalls, safety shoes or boots and helmet.
Other protection such as safety glasses/goggles, gloves, ear plugs,
safety belt/harness, masks are supplied appropriate for the task being
performed.
Page 10
Anabeeb Pipeline Division
5.4 PERMITS
To prevent any job delays, all necessary permits and ID’s have to be
available before commencing any mobilization/works:
6. QUALITY
6.1 GENERAL
6.2 REPORTING
Page 11
Anabeeb Pipeline Division
DIVISION MANAGER
PLD PLD
(QA/QC) HSE
OFFICER
PLD
SUPERVISOR
LABOURERS
Page 12