Fig. 10-I
DESIGN CRITERIA
10.4.1 The main points considered for design of River Crossing and Anchor towers are described below :
i. The normal Transmission Line Towers are designed with the assumption that wind would be acting on
conductor, Insulator & tower structure in longitudinal transverse direction. But, for very high
towers/structures of river crossing, the load on towers is evaluated after taking into account height
factor and basic wind pressure etc. The towers for river crossing should be designed for diagonal wind
load conditions also, which is an additional feature to take care of high velocity winds during severe
storms/cyclones etc. Behavior of wind will, however, depend on the river crossing locations and the
profile of crossing.
ii. The towers are so designed that the minimum factor of safety of individual member as well as over all
structure is not less than 2.5.
iii. Shielding angle is; less than 30° for 132 KV and 220 KV towers and 20° for 400 KV towers.
v. The wind on, towers is assumed to be acting at an angle to the line which may produce the maximum
combined effect of conductor and tower loadings in the tower members.
vi. Longitudinal load under broken wire condition due to power conductor and ground wire for Rx towers is
taken as 100% of the tension of conductor and ground wire at 32°C with no wind. This is multiplied by
Impact Load Factor of 2.65.
b. Anchor Towers
http://www.upptcl.org/tech_info/river_crossings_trans.htm 12/23/2010
UP Power Transmission Corporation Limited Page 2 of 6
Dead-end type towers designed for any combination of ground wire and two conductors on the same
side or three conductors on the same side and on the same span whichever is more stringent for a
particular member in the tower.
PARAMETERS
I. The main design parameters for River Crossing (Rx) Towers which should be clearly specified and whih are
presently being used in UPSEB are as follows:
II. The Salient features of Rx Towers presently being used in UPSEB are as follows:
If the Rx Towers are located in the meandering zone of, the river, Special Well-Type or Pile-type foundations
are provided. However, with normal or wet soil with unit weight of 940 Kg per Cu. Meter and bearing capacity
of 13675 Kg per Sq. Meter assuming angle of repose as. 15° the open cast fully submerged RCC
Foundations (Step type) should be provided.
2. Anchor Tower
I. Main features of Anchor Towers which are presently being used in UPSEB are as follows :
http://www.upptcl.org/tech_info/river_crossings_trans.htm 12/23/2010
UP Power Transmission Corporation Limited Page 3 of 6
10.6.1 No deviation is allowed on River Crossing Towers. All the towers from Anchor Tower to Anchor Tower
on River crossing portion should be in straight line. The Anchor Towers should be placed square to River
crossing portion. If any deviation is required to be given, it should be given on the normal line side only.
10.7.1 Position and method for calculations of following parameters are also enclosed for reference &
guidance :
The river crossing proposal should be submitted from the field covering following details :—
A. PROFILE:
i. Profile of river crossing and Anchor towers along with position of adjacent towers of the line of either
side of the river crossing.
ii. The profile should clearly indicate reduced level of HFL mark, Rx and Anchor tower locations, nearby
roads, bunds/embankment etc, if any.
iv. Sag curve of 75°C and no wind for each span from Anchor to Anchor towers.
v. Clearance of lowest power conductor from HFL mark for maximum sag calculated at 75° and no wind.
The minimum clearance required is 6.1 meters for 132 KV, 7.00 meters for 220 KV and 8.84 meters for
400 KV lines for non-navigable rivers.
B. PLAN:
i. Plan showing Rx Towers, Anchor towers, adjacent tower with span, roads, bridges, bunds and other
important structures etc.
iv. Whether Rx and/or Anchor towers will remain normally submerged in water, should also be indicated
clearly.
On Anchor towers shall also be submitted on the profile & plan sheet itself.
http://www.upptcl.org/tech_info/river_crossings_trans.htm 12/23/2010
UP Power Transmission Corporation Limited Page 4 of 6
D. NARRATIVE:
Narrative about the geographical conditions of the area and whether there would be any problem for right of
way etc. should also be submitted along with the proposal.
1. The following points may be borne in mind and implemented religiously before taking up construction activities for
river crossing
i. The tower parts should be checked with approved drawings and bill of material (B.O.M.) about
correctness of fabrication and supply.
ii. The survey and profile should be thoroughly checked at site. It should be ensured that the river
crossing portion from Anchor-to-Anchor are in straight line. No deviation is allowed on River Crossing
Towers and anchor towers on the river crossing side, i.e. the anchor towers should be placed square to
the river crossing portion.
During construction right from survey to final sagging and commissioning. The following precautions may be
taken to ensure execution & completion of River Crossing properly from all considerations :—
A. DURING FOUNDATION:
ii. The template should be placed and installed properly as per drawing for proper setting of
stubs and the following dimensions should be checked before concreting: -
a. Base width
c. Diagonals
iii. Proper Form Boxes or moulds should be used. If necessary shoring and shuttering
should be used to avoid falling of surrounding earth and its mixing with concrete.
iv. Depending on the condition, proper arrangement should be done for dewatering of pits,
preferably by power driven pumps.
v. The concrete in 1:2:4 ratio should be mixed in mechanical mixer, preferably power driven.
Hand mixing should not be allowed.
vi. Proper laying and filling of concrete should be ensured. It should be done continuously,
uniformly and properly with power drive vibrators.
vii. The concreting of a particular leg should be done continuously and uninterruptedly to
ensure proper bonding.
viii. It is also preferable that concreting of 2 diagonally opposite legs is done simultaneously.
ix. The levels of all the 4 legs should be checked before concreting during concreting and
after completion of concreting job also.
x. The curing should be done properly and continuously for a period of at least 10 days.
xii. The stub setting template should be opened only after the back filling.
ii. It should be ensured that all the bolts & nuts of correct sizes are provided on all the
members as per drawings and no hole is left blank.
iii. All the cleats, gusset plate and pack washers should be provided as per drawing.
iv. After erection of each panel and sections, the levels and verticality should be checked
and corrective measures be taken, if necessary.
v. If the erection of tower is partial then it should be anchored properly and suitably before
resuming work on next day.
vi. After completion of erection each & every bolt should be tightened properly and checked
thoroughly.
viii. Insulator strings should be assembled on the ground and hoisted properly before
http://www.upptcl.org/tech_info/river_crossings_trans.htm 12/23/2010
UP Power Transmission Corporation Limited Page 5 of 6
C. DURING STRINGING:
i. Before stringing it should be ensured that all the bolts & nuts have been tightened and
punching and hammering of the left over threads has also been done.
ii. The placement of Rx & Anchor Towers has been done as per approved survey and profile
and that all the towers of River Crossing portion from Anchor to Anchor are placed in straight
line i.e. square to the river crossing portion. It may be noted that no deviation is permitted.
iii. River Crossing span is as per approved profile and within the maximum designed spans.
iv. Levels & verticality of all the towers is Okay.
v. The stringing should be done as per standard norms & practices by using ground rollers,
aerial rollers (with high quality Ball rollers for minimum friction), Snatch Pully Blocks,
Hydraulic pressures, proper T & P and equipment, preferably by Tension Stringing
Equipment.
vi. It should be ensured that E/W is strung and securely clamped to the tower before the
conductors are drawn up in the order of top conductor first then the middle and bottom
conductors at the end.
vii. It is also desirable that paying & tensioning of both the conductors on a particular cross arm
is done is simultaneously, so as to maintain identical tension time history.
viii. The traveler surface in contact with aluminium surface of conductor should be of such a
material that the conductor is not damaged due to contact with material such as neoprene
rubber or Stainless steel.
ix. The conductor should not be rubbed with any rough ground surface and it should not also
damage the standing crops.
x. During pulling out operation the tension in each conductor and E/W shall not exceed
designed working tension of the conductor at the actual prevailing temperature.
xi. After being pulled the conductor and E/W shall not be allowed to hang in the stringing blocks
for more than 96 hours before being pulled to the specified sag. During the time the
conductors and E/W are on the stringing block before sagging in, it should be ensured that
the conductors and E/W are not damaged due to clashing, vibration or other causes.
D. FINAL SAGGING:
i. The conductors and E/W shall be sagged in accordance with the approved stringing
charts before final clamping. The conductors shall be pulled-up to the desired sag and left
in travelers at least for one hour after which the sag shall be checked and adjusted if
necessary before transferring the conductors from the travelers to the suspension
clamps.
iv. Dynamo-meters should be used in checking the tension in the conductors and EAV.
v. The sage shall also be checked when the conductors have been drawn up and
transferred from aerial blocks to the insulator clamps.
vi. Sagging operations shall not be carried out under wind, extremely low temperature or
other adverse conditions which prevent satisfactory sagging.
i. Sufficient backfilled earth is lying over each foundation pit and it is adequately
compacted.
ii. Concrete chimneys and their copings are in good and finally shaped conditions.
iii. All the tower members are correctly used strictly according to finally approved drawings
and are free from any defect or damage, whatsoever.
iv. All the bolts are fully tightened and they are properly punched.
v. The stringing of the conductors and earth wire has been done as per the approved sag
tensions charts and desired clearances are available.
vi. No damage, minor or major to the conductors, earth wire accessories and insulator
strings, still unattended are noticed.
ANNEXURE -
SAG AND TENSION CALCULATIONS FOR CONDUCTOR/EARTH WIRE FOR RIVER CROSSINGS
1
ANNEXURE -
METHOD FOR GROUND CLEARANCE CALCULATIONS FOR RIVER CROSSINGS
2
ANNEXURE -
METHOD FOR WEIGHT SPAN CALCULATIONS FOR RIVER CROSSINGS
3
ANNEXURE -
STRINGING CHARTS FOR RIVER CROSSINGS
4
Back
http://www.upptcl.org/tech_info/river_crossings_trans.htm 12/23/2010
UP Power Transmission Corporation Limited Page 6 of 6
Best viewed at 1024*768 pixels resolution with IE 6.0 or above. | Check E-mail | E-mail Directory
| Disclaimer Powered by: updesco | omni-NET
http://www.upptcl.org/tech_info/river_crossings_trans.htm 12/23/2010