RAB Kantor Syahada 2020
RAB Kantor Syahada 2020
HARGA
URAIAN PEKERJAAN VOLUME
SATUAN JUMLAH
I Pekerjaan Tanah
1.1 Pek. Galian Tanah 3.75 m3 Rp122,000 Rp457,756
1.2 Pek. Urugan Tanah 6.66 m3 Rp137,000 Rp912,420
II Pekerjaan Pondasi
2.1 Pek. Pondasi Batu Kali Cp. 1 SP : 5 PP 1.17 m3 Rp786,000 Rp919,620
2.2 Pek. Pasangan Bata Merah (5 x 11 x 22) cm, ( t= 1 bata Ad. 1:3) 21.20 m2 Rp243,000 Rp5,152,572
IV Pekerjaan Dinding
4.1 Pek. Pasangan Bata Merah (5 x 11 x 22) cm, (t= 1/2 bata Ad. 1:3) 28.18 m2 Rp137,000 Rp3,860,660
4.2 Pek. Plesteran + acian 56.36 m2 Rp73,000 Rp4,114,280
4.3 Pek. Pengecatan Dinding ( Jotun ) 56.36 m2 Rp36,000 Rp2,028,960
4.4 pek. Keramik dinding 20 x 20 (Asia Tile Zara Blue) 4.20 m2 Rp161,000 Rp676,200
4.5 Pek. Rangka dinding (Besi Hollow Hitam 40x80) 1063.59 Kg Rp20,000 Rp21,271,716
4.6 Pek. Rangka dinding (Besi Hollow Hitam 40x40) 231.37 Kg Rp20,000 Rp4,627,405
4.7 Pek. Rangka dinding (Besi Hollow Hitam 20x40) 142.59 Kg Rp20,000 Rp2,851,773
4.8 Pek. Dinding dalam (Gypsumboard + Hollow Galvalum 20x40 ) 104.57 m2 Rp60,000 Rp6,274,320
4.9 Pek. Dinding luar (Spandek) 0,35 Warna silver 115.83 m2 Rp73,000 Rp8,455,415
V Pekerjaan Atap
5.1 Pek. Rangka Atap ( Reng Galvalum ) 0,4/0,45 6 meter 103.90 m2 Rp23,000 Rp2,389,608
5.2 Pek. Atap (Spandek) 0,35 warna Silver 103.90 m2 Rp73,000 Rp7,584,408
sabangconstruction.com Page 1 of 3
HARGA
URAIAN PEKERJAAN VOLUME
SATUAN JUMLAH
VI Pekerjaan Plafon
6.1 Pek. Rangka Plafon (hollow Galvalum) 20x40 79.94 m2 Rp27,000 Rp2,158,439
6.2 Pek. Plafon (Gypsumboard) 79.94 m2 Rp39,000 Rp3,117,746
6.3 Pek. Pengecatan Plafond ( Jotun ) 79.94 m2 Rp36,000 Rp2,877,919
X Pekerjaan Septictank
10.1 Pek. Galian tanah 6.00 m3 Rp122,000 Rp732,000
10.2 Pek. Pasangan Bata Merah (5 x 11 x 22) cm, (t= 1/2 bata Ad. 1:3) 16.00 m2 Rp137,000 Rp2,192,000
10.3 Pek. Plesteran 16.00 m2 Rp73,000 Rp1,168,000
10.4 Pek. Beton K175 0.60 m3 Rp982,000 Rp589,200
10.5 Pek. Tulangan ( Besi Polos d12) 26.00 Kg Rp17,000 Rp442,000
sabangconstruction.com Page 2 of 3
HARGA
URAIAN PEKERJAAN VOLUME
SATUAN JUMLAH
REKAPITULASI
I Pekerjaan Tanah = Rp1,370,176
II Pekerjaan Pondasi = Rp6,072,192
III Pekerjaan Lantai = Rp7,321,008
IV Pekerjaan Dinding = Rp54,160,730
V Pekerjaan Atap = Rp9,974,016
VI Pekerjaan Plafon = Rp8,154,104
VII Pekerjaan Kusen = Rp13,804,000
VIII Pekerjaan Elektrikal = Rp2,840,000
IX Pekerjaan Sanitair dan Plumbing = Rp11,807,000
X Pekerjaan Septictank = Rp5,123,200
Jumlah Rp120,626,426
Dibulatkan Rp120,000,000
PPN 10% Rp12,000,000
TOTAL Rp132,000,000