RENCANA AGGARAN BIAYA (RAB)

ORGANISASI : DINAS PERUMAHAN DAN KAWASAN PERMUKIMAN KABUPATEN SORONG


PROGRAM : PROGRAM SARANA DAN PRASARANA SANITASI
KEGIATAN : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL
LOKASI : KELURAHAN KLASULUK, DISTRIK MARIAT
SUMBER DANA : DAK- PENUGASAN
JUMLAH : 54 UNIT

NO URAIAN PEKERJAAN Volume Satuan Harga Satuan Jumlah Harga


Rp Rp
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 - -
SUB TOTAL I -
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080 m2 210,469 227,306,088
2 Pek. Plesteran Camp. 1 : 3 1,296 m2 71,814 93,071,579
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 )
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,334 49,775,049
b. Pek. Begesting 216.00 m2 158,388 34,211,765
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198 15,804,658
4 Pek Urugan Pasir Dasar Septictank 22 m3 421,418 9,102,629
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 22 m3 1,453,620 31,398,192
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270 m 102,678 27,722,925
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54 m 78,653 4,247,235
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 65 m2 210,469 13,638,365
SUB TOTAL II 506,278,485
III BIAYA OPERASIONAL
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000 1,700,000
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000 3,000,000
3 Biaya Transportasi 1 Ls 2,000,000 2,000,000
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000 7,000,000
SUB TOTAL III 13,700,000
PPN+PPH 13%
JUMLAH Rp 519,978,485
PEMBULATAN Rp 520,000,000
REKAPITULASI RENCANA ANGGARAN BIAYA

ORGANISASI : DINAS PERUMAHAN & KAWASAN PERMUKIMAN KABUPATEN SORONG


PROGRAM : PROGRAM SARANA DAN PRASARANA SANITASI
KEGIATAN : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL
LOKASI : KELURAHAN MARIYAI, DISTRIK MARIAT
SUMBER DANA : DAK- PENUGASAN
JUMLAH : 47 UNIT

NO PEKERJAAN JUMLAH HARGA

I PEKERJAAN TANAH Rp -

II PEKERJAAN SANITAIR Rp 440,649,792

III BIAYA OPERASIONAL KSM Rp 22,625,000

BIAYA KONSTRUKSI Rp 463,274,792.11


PPN + PPH (12%) Rp 56,727,272.73
JUMLAH Rp 520,002,064.84
PEMBULATAN Rp 520,000,000.00

TERBILANG : LIMA RATUS DUA PULUH JUTA RUPIAH

KSM KELURAHAN MARIYAI TENAGA FASILITATOR LAPANGAN


DISTRIK MARIAT

HARTONO
KETUA TFL PEMBERDAYAAN TFL. TEKNIS

PEJABAT PEMBUAT KOMITMEN PLT. KEPALA DINAS PERUMAHAN & KAWASAN PERMUKIMAN
KABUPATEN SORONG

ANGKY JANUAR MANUPUTTY, ST HENDRIK


HENDRIKMOMOT,
MOMOT,ST,ST.
M.Sc
M.Sc
NIP. 19770101 201004 1 001 NIP. 19690315 199610 1 001
PEMERINTAH KABUPATEN SORONG
DINAS PERUMAHAN DAN KAWASAN PERMUKIMAN
JL. SORONG-KLAMONO
26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018
TIME SCHEDULE RENCANA
Agustus 2018 s/d Desember 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

Jumlah Harga AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER


6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec
Harga Satuan Bobot
NO Uraian Kegiatan Volume Satuan s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
(Rp.) (%)
12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec
(Rp) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0 0
SUB TOTAL I
100
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 4.09 4.09 4.09 4.09 4.09 3.95 3.95 3.95 3.95 1.86 1.86 1.86 1.86
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 2.09458 2.09458 2.09458 2.09458 2.16 2.16 2.16 1.01555 1.01555 1.01555
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 )
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 1.49 1.49 1.49 1.73 1.73 0.54 0.54 0.54
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 1.54 1.54 1.19 1.19 0.56 0.56
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 0.71 0.71 0.55 0.55 0.26 0.26
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 0.82 0.633188 0.297971
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 2.83 2.18 1.03
50
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 2.49562 1.928434 0.907498
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 0.38 0.30 0.14
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 0.61 0.61 0.474349 0.474349 0.223223 0.223223
SUB TOTAL II 506,278,484.55
BIAYA OPERASIONAL
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.15 0.12 0.06
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.27 0.21 0.10
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.18 0.14 0.07
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.63 0.49 0.23
- - 0 0
TOTAL 519,978,484.55 100
RENCANA FISIK PER MINGGU 5.18 4.25 6.37 6.19 9.01 5.30 4.74 4.28 6.29 4.07 8.43 8.59 6.10 4.18 2.26 1.92 4.23 5.14 2.48 1.00
RENCANA KOMULATIF 5.18 9.43 15.79 21.98 30.99 36.30 41.04 45.31 51.60 55.67 64.11 72.70 78.80 82.98 85.24 87.15 91.38 96.52 99.00 100
REALISASI FISIK PER MINGGU 4.31 3.56 3.55 5.72 5.72 3.49 8.08 5.19 5.06 4.60 7.93 5.35 2.71 4.83 7.10 6.65 5.07 6.35 3.97 0.77
REALISASI KOMULATIF 4.31 7.87 11.42 17.14 22.86 26.35 34.43 39.62 44.68 49.27 57.20 62.55 65.26 70.09 77.19 83.84 88.91 95.26 99.23 100
DEVIASI 0.87 1.56 4.37 4.84 8.14 9.94 6.60 5.69 6.93 6.40 6.91 10.15 13.54 12.89 8.04 3.31 2.47 1.26 -0.23 -

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE Nyujiantoro


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
TIME SCHEDULE REALISASI
Agustus 2018 s/d Desember 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
26/33.1/III/KONT/DA JULES D. ANTOH, SE

Jumlah Harga AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER


6-Aug 13-Aug 20-Aug 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oct 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec
NO Uraian Kegiatan Volume Satuan Harga Satuan Bobot
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
(Rp.) (%)
12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec
(Rp) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 2.56 3.06 3.56 4.06 4.56 3.82 4.32 4.82 6.48 6.48
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 1.93 2.43 2.93 3.54 1.77 3.54 1.77
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 )
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 1.95 1.95 3.01 2.66
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 1.34 1.34 2.07 1.83
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 1.24 0.96 0.84
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 0.36 0.36 0.55 0.49
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 1.23 1.23 1.90 1.68
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 1.09 1.09 1.68 1.48
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 0.33 0.26 0.23
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 1.07 0.83 0.73
SUB TOTAL II 506,278,484.55
BIAYA OPERASIONAL
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 - 0.33
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 - 0.58
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.05 0.05 0.29
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.67 0.27 0.40

TOTAL 519,978,484.55 100


RENCANA FISIK PER MINGGU 2.56 3.42 3.97 5.99 12.75 8.54 3.16 4.37 4.36 8.35 3.84 2.64 6.27 6.96 11.69 3.25 4.27 3.61 - -
REALISASI KOMULATIF 2.56 5.98 9.95 15.94 28.69 37.23 40.39 44.76 49.12 57.48 61.31 63.95 70.22 77.18 88.87 92.12 96.39 100.00 100.00 ###

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE Nyujiantoro


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( I )
6 Agustus 2018 s/d 12 Agustus 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
(%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 - - 101.11 4.09 101.11 4.09 - - 63.29 2.56 63.29 2.56 1,016.71 41.15 (1.53)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 - - - - - - - - - - - - 1,296.00 17.90 0.00
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 )
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 - - - - - - - - - - - - 25.92 9.57 0.00
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 - - - - - - - - - - - - 216.00 6.58 0.00
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 - - - - - - - - - - - - 1,197.50 3.04 0.00
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 - - 10.11 0.82 10.11 0.82 - - - - - - 21.60 1.75 (0.82)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 - - - - - - - - - - - - 21.60 6.04 0.00
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 - - - - - - - - - - - - 270.00 5.33 0.00
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 - - - - - - - - - - - - 54.00 0.82 0.00
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 - - - - - - - - - - - - 64.80 2.62 0.00
SUB TOTAL II 506,278,484.55
BIAYA OPERASIONAL
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 - - - - - - - - - - - - 1.00 0.33 0.00
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 - - 0.47 0.27 0.47 0.27 - - - - - - 1.00 0.58 (0.27)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 - - - - - - - - - - - - 1.00 0.38 0.00
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 - - - - - - - - - - - - 1.00 1.35 0.00
-
TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 0.00 5.18 5.18 0.00 2.56 2.56 4,188.13 97.44 (2.62)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( II )
13 Agustus 2018 s/d 19 Agustus 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
(%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 101.11 4.09 101.11 4.09 202.21 8.18 63.29 2.56 75.65 3.06 138.94 5.62 941.06 38.09 (2.56)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 - - - - - - - - - - - - 1,296.00 17.90 0.00
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 )
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 - - - - - - - - - - - - 25.92 9.57 0.00
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 - - - - - - - - - - - - 216.00 6.58 0.00
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 - - - - - - - - - - - - 1,197.50 3.04 0.00
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 10.11 0.82 - - 10.11 0.82 - - 4.40 0.36 4.40 0.36 17.20 1.39 (0.46)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 - - - - - - - - - - - - 21.60 6.04 0.00
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 - - - - - - - - - - - - 270.00 5.33 0.00
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 - - - - - - - - - - - - 54.00 0.82 0.00
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 - - - - - - - - - - - - 64.80 2.62 0.00
SUB TOTAL II 506,278,484.55
BIAYA OPERASIONAL
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 - - 0.47 0.15 0.47 0.15 - - - - - - 1.00 0.33 (0.15)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.47 0.27 - - 0.47 0.27 - - - - - - 1.00 0.58 (0.27)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 - - - - - - - - - - - - 1.00 0.38 0.00
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 - - - - - - - - - - - - 1.00 1.35 0.00

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 5.18 4.25 9.43 2.56 3.42 5.98 4,108.08 94.02 (3.45)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( III )
20 Agustus 2018 s/d 26 Agustus 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
(%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 202.21 8.18 101.11 4.09 303.32 12.28 138.94 5.62 88.00 3.56 226.94 9.19 853.06 34.53 (3.09)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 - - 151.66 2.09 151.66 2.09 - - - - - - 1,296.00 17.90 (2.09)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 - - - - - - - - - - - - 25.92 9.57 0.00
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 - - - - - - - - - - - - 216.00 6.58 0.00
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 - - - - - - - - - - - - 1,197.50 3.04 0.00
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 10.11 0.82 - - 10.11 0.82 4.40 0.36 4.40 0.36 8.80 0.71 12.80 1.04 (0.11)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 - - - - - - - - - - - - 21.60 6.04 0.00
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 - - - - - - - - - - - - 270.00 5.33 0.00
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 - - - - - - - - - - - - 54.00 0.82 0.00
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 - - - - - - - - - - - - 64.80 2.62 0.00
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.47 0.15 - - 0.47 0.15 - - - - - - 1.00 0.33 (0.15)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.47 0.27 - - 0.47 0.27 - - - - - - 1.00 0.58 (0.27)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 - - 0.47 0.18 0.47 0.18 - - 0.13 0.05 0.13 0.05 0.87 0.33 (0.13)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 - - - - - - - - - - - - 1.00 1.35 0.00

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 9.43 6.37 15.79 5.98 3.97 9.95 4,015.55 90.05 (5.85)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( IV )
27 Agustus 2018 s/d 02 September 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
(%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 303.32 12.28 101.11 4.09 404.43 16.37 226.94 9.19 100.35 4.06 327.29 13.25 752.71 30.47 (3.12)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 151.66 2.09 151.66 2.09 303.32 4.19 - - 139.80 1.93 139.80 1.93 1,156.20 15.97 (2.26)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 - - - - - - - - - - - - 25.92 9.57 0.00
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 - - - - - - - - - - - - 216.00 6.58 0.00
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 - - - - - - - - - - - - 1,197.50 3.04 0.00
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 10.11 0.82 - - 10.11 0.82 8.80 0.71 - - 8.80 0.71 12.80 1.04 (0.11)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 - - - - - - - - - - - - 21.60 6.04 0.00
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 - - - - - - - - - - - - 270.00 5.33 0.00
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 - - - - - - - - - - - - 54.00 0.82 0.00
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 - - - - - - - - - - - - 64.80 2.62 0.00
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.47 0.15 - - 0.47 0.15 - - - - - - 1.00 0.33 (0.15)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.47 0.27 - - 0.47 0.27 - - - - - - 1.00 0.58 (0.27)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.47 0.18 - - 0.47 0.18 0.13 0.05 - - 0.13 0.05 0.87 0.33 (0.13)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 - - - - - - - - - - - - 1.00 1.35 0.00

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 15.79 6.19 21.98 9.95 5.99 15.94 3,775.40 84.06 (6.04)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN BULANAN ( I )
6 Agustus 2018 s/d 02 September 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI BULAN INI
Jumlah Harga
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
(%) bulan lalu bulan ini bulan ini BULAN LALU BULAN INI BULAN INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 - - 404.43 16.37 404.43 16.37 - - 327.29 13.25 327.29 13.25 752.71 30.47 (3.12)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 - - 303.32 4.19 303.32 4.19 - - 139.80 1.93 139.80 1.93 1,156.20 15.97 (2.26)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 )
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 - - - - - - - - - - - - 25.92 9.57 0.00
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 - - - - - - - - - - - - 216.00 6.58 0.00
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 - - - - - - - - - - - - 1,197.50 3.04 0.00
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 - - 10.11 0.82 10.11 0.82 - - 8.80 0.71 8.80 0.71 12.80 1.04 (0.11)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 - - - - - - - - - - - - 21.60 6.04 0.00
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 - - - - - - - - - - - - 270.00 5.33 0.00
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 - - - - - - - - - - - - 54.00 0.82 0.00
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 - - - - - - - - - - - - 64.80 2.62 0.00
SUB TOTAL II 506,278,484.55
BIAYA OPERASIONAL
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 - - 0.47 0.15 0.47 0.15 - - - - - - 1.00 0.33 (0.15)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 - - 0.47 0.27 0.47 0.27 - - - - - - 1.00 0.58 (0.27)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 - - 0.47 0.18 0.47 0.18 - - 0.13 0.05 0.13 0.05 0.87 0.33 (0.13)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 - - - - - - - - - - - - 1.00 1.35 0.00

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 0.00 21.98 21.98 0.00 15.94 15.94 3,775.40 84.06 (6.04)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( V )
03 September s/d 09 September 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) volume
bobot
volume
bobot
volume
bobot
VOLUME
BOBOT
VOLUME
BOBOT
VOLUME
BOBOT
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 404.43 16.37 101.11 4.09 505.53 20.46 327.29 13.25 112.71 4.56 440.00 17.81 640.00 25.90 (2.65)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 303.32 4.19 151.66 2.09 454.98 6.28 139.80 1.93 176.00 2.43 315.80 4.36 980.20 13.54 (1.92)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 - - - - - - - - 5.28 1.95 5.28 1.95 20.64 7.62 1.95
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 - - - - - - - - 44.00 1.34 44.00 1.34 172.00 5.24 1.34
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 - - - - - - - - 487.87 1.24 487.87 1.24 709.63 1.80 1.24
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 10.11 0.82 - - 10.11 0.82 8.80 0.71 - - 8.80 0.71 12.80 1.04 (0.11)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 - - 10.11 2.83 10.11 2.83 - - 4.40 1.23 4.40 1.23 17.20 4.81 (1.60)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 - - - - - - - - - - - - 270.00 5.33 0.00
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 - - - - - - - - - - - - 54.00 0.82 0.00
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 - - - - - - - - - - - - 64.80 2.62 0.00
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.47 0.15 - - 0.47 0.15 - - - - - - 1.00 0.33 (0.15)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.47 0.27 - - 0.47 0.27 - - - - - - 1.00 0.58 (0.27)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.47 0.18 - - 0.47 0.18 0.13 0.05 - - 0.13 0.05 0.87 0.33 (0.13)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 - - - - - - - - - - - - 1.00 1.35 0.00

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 21.98 9.01 30.99 15.94 12.75 28.69 2,945.14 71.31 (2.30)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( VI )
10 September s/d 16 September 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
(%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 505.53 20.46 - - 505.53 20.46 440.00 17.81 - - 440.00 17.81 640.00 25.90 (2.65)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 454.98 6.28 151.66 2.09 606.64 8.38 315.80 4.36 212.20 2.93 528.00 7.29 768.00 10.61 (1.09)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 - - - - - - 5.28 1.95 5.28 1.95 10.56 3.90 15.36 5.67 3.90
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 - - - - - - 44.00 1.34 44.00 1.34 88.00 2.68 128.00 3.90 2.68
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 - - 280.27 0.71 280.27 0.71 487.87 1.24 - - 487.87 1.24 709.63 1.80 0.53
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 10.11 0.82 - - 10.11 0.82 8.80 0.71 - - 8.80 0.71 12.80 1.04 (0.11)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 10.11 2.83 - - 10.11 2.83 4.40 1.23 4.40 1.23 8.80 2.46 12.80 3.58 (0.37)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 - - 126.38 2.50 126.38 2.50 - - 55.00 1.09 55.00 1.09 215.00 4.25 (1.41)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 - - - - - - - - - - - - 54.00 0.82 0.00
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 - - - - - - - - - - - - 64.80 2.62 0.00
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.47 0.15 - - 0.47 0.15 - - - - - - 1.00 0.33 (0.15)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.47 0.27 - - 0.47 0.27 - - - - - - 1.00 0.58 (0.27)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.47 0.18 - - 0.47 0.18 0.13 0.05 - - 0.13 0.05 0.87 0.33 (0.13)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 - - - - - - - - - - - - 1.00 1.35 0.00

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 30.99 5.30 36.30 28.69 8.54 37.23 2,624.26 62.77 0.93

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( VII )
17 September s/d 23 September 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
(%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 505.53 20.46 - - 505.53 20.46 440.00 17.81 - - 440.00 17.81 640.00 25.90 (2.65)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 606.64 8.38 - - 606.64 8.38 528.00 7.29 - - 528.00 7.29 768.00 10.61 (1.09)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 - - 4.04 1.49 4.04 1.49 10.56 3.90 - - 10.56 3.90 15.36 5.67 2.41
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 - - 50.55 1.54 50.55 1.54 88.00 2.68 - - 88.00 2.68 128.00 3.90 1.14
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 280.27 0.71 280.27 0.71 560.53 1.42 487.87 1.24 - - 487.87 1.24 709.63 1.80 (0.18)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 10.11 0.82 - - 10.11 0.82 8.80 0.71 - - 8.80 0.71 12.80 1.04 (0.11)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 10.11 2.83 - - 10.11 2.83 8.80 2.46 - - 8.80 2.46 12.80 3.58 (0.37)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 126.38 2.50 - - 126.38 2.50 55.00 1.09 55.00 1.09 110.00 2.17 160.00 3.16 (0.32)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 - - 25.28 0.38 25.28 0.38 - - 22.00 0.33 22.00 0.33 32.00 0.48 (0.05)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 - - 15.17 0.61 15.17 0.61 - - 26.40 1.07 26.40 1.07 38.40 1.55 0.45
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.47 0.15 - - 0.47 0.15 - - - - - - 1.00 0.33 (0.15)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.47 0.27 - - 0.47 0.27 - - - - - - 1.00 0.58 (0.27)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.47 0.18 - - 0.47 0.18 0.13 0.05 - - 0.13 0.05 0.87 0.33 (0.13)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 - - - - - - - - 0.50 0.67 0.50 0.67 0.50 0.67 0.67

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 36.30 4.74 41.04 37.23 3.16 40.39 2,520.36 59.61 (0.65)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( VIII )
24 September s/d 30 September 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.)
(%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 505.53 20.46 - - 505.53 20.46 440.00 17.81 94.31 3.82 534.31 21.63 545.69 22.09 1.16
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 606.64 8.38 - - 606.64 8.38 528.00 7.29 - - 528.00 7.29 768.00 10.61 (1.09)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 4.04 1.49 4.04 1.49 8.09 2.99 10.56 3.90 - - 10.56 3.90 15.36 5.67 0.91
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 50.55 1.54 50.55 1.54 101.11 3.08 88.00 2.68 - - 88.00 2.68 128.00 3.90 (0.40)
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 560.53 1.42 - - 560.53 1.42 487.87 1.24 - - 487.87 1.24 709.63 1.80 (0.18)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 10.11 0.82 - - 10.11 0.82 8.80 0.71 6.80 0.55 15.60 1.26 6.00 0.49 0.44
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 10.11 2.83 - - 10.11 2.83 8.80 2.46 - - 8.80 2.46 12.80 3.58 (0.37)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 126.38 2.50 - - 126.38 2.50 110.00 2.17 - - 110.00 2.17 160.00 3.16 (0.32)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 25.28 0.38 - - 25.28 0.38 22.00 0.33 - - 22.00 0.33 32.00 0.48 (0.05)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 15.17 0.61 15.17 0.61 30.33 1.23 26.40 1.07 - - 26.40 1.07 38.40 1.55 (0.16)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.47 0.15 - - 0.47 0.15 - - - - - - 1.00 0.33 (0.15)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.47 0.27 - - 0.47 0.27 - - - - - - 1.00 0.58 (0.27)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.47 0.18 - - 0.47 0.18 0.13 0.05 - - 0.13 0.05 0.87 0.33 (0.13)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 - - 0.47 0.63 0.47 0.63 0.50 0.67 - - 0.50 0.67 0.50 0.67 0.04

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 41.04 4.28 45.31 40.39 4.37 44.76 2,419.25 55.24 (0.56)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN BULANAN ( II )
03 September s/d 30 September 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI BULAN INI
Jumlah Harga
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
(%) bulan lalu bulan ini bulan ini BULAN LALU BULAN INI BULAN INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 404.43 16.37 101.11 4.09 505.53 20.46 327.29 13.25 207.02 8.38 534.31 21.63 545.69 22.09 1.16
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 303.32 4.19 303.32 4.19 606.64 8.38 139.80 1.93 388.20 5.36 528.00 7.29 768.00 10.61 (1.09)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 - - 8.09 2.99 8.09 2.99 - - 10.56 3.90 10.56 3.90 15.36 5.67 0.91
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 - - 101.11 3.08 101.11 3.08 - - 88.00 2.68 88.00 2.68 128.00 3.90 (0.40)
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 - - 560.53 1.42 560.53 1.42 - - 487.87 1.24 487.87 1.24 709.63 1.80 (0.18)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 10.11 0.82 - - 10.11 0.82 8.80 0.71 6.80 0.55 15.60 1.26 6.00 0.49 0.44
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 - - 10.11 2.83 10.11 2.83 - - 8.80 2.46 8.80 2.46 12.80 3.58 (0.37)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 - - 126.38 2.50 126.38 2.50 - - 110.00 2.17 110.00 2.17 160.00 3.16 (0.32)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 - - 25.28 0.38 25.28 0.38 - - 22.00 0.33 22.00 0.33 32.00 0.48 (0.05)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 - - 30.33 1.23 30.33 1.23 - - 26.40 1.07 26.40 1.07 38.40 1.55 (0.16)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.47 0.15 - - 0.47 0.15 - - - - - - 1.00 0.33 (0.15)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.47 0.27 - - 0.47 0.27 - - - - - - 1.00 0.58 (0.27)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.47 0.18 - - 0.47 0.18 0.13 0.05 - - 0.13 0.05 0.87 0.33 (0.13)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 - - 0.47 0.63 0.47 0.63 - - 0.50 0.67 0.50 0.67 0.50 0.67 0.04

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 21.98 23.33 45.31 15.94 28.82 44.76 2,419.25 55.24 (0.56)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( IX )
01 Oktober s/d 07 Oktober 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 505.53 20.46 ### 3.95 603.19 24.42 534.31 21.63 106.67 4.32 640.98 25.94 439.02 17.77 1.53
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 606.64 8.38 - - 606.64 8.38 528.00 7.29 - - 528.00 7.29 768.00 10.61 (1.09)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 8.09 2.99 4.04 1.49 12.13 4.48 10.56 3.90 - - 10.56 3.90 15.36 5.67 (0.58)
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 101.11 3.08 - - 101.11 3.08 88.00 2.68 - - 88.00 2.68 128.00 3.90 (0.40)
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 560.53 1.42 - - 560.53 1.42 487.87 1.24 - - 487.87 1.24 709.63 1.80 (0.18)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 10.11 0.82 7.81 0.63 17.92 1.45 15.60 1.26 - - 15.60 1.26 6.00 0.49 (0.19)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 10.11 2.83 - - 10.11 2.83 8.80 2.46 - - 8.80 2.46 12.80 3.58 (0.37)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 126.38 2.50 - - 126.38 2.50 110.00 2.17 - - 110.00 2.17 160.00 3.16 (0.32)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 25.28 0.38 - - 25.28 0.38 22.00 0.33 - - 22.00 0.33 32.00 0.48 (0.05)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 30.33 1.23 - - 30.33 1.23 26.40 1.07 - - 26.40 1.07 38.40 1.55 (0.16)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.47 0.15 - - 0.47 0.15 - - - - - - 1.00 0.33 (0.15)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.47 0.27 0.36 0.21 0.83 0.48 - - - - - - 1.00 0.58 (0.48)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.47 0.18 - - 0.47 0.18 0.13 0.05 0.12 0.05 0.25 0.10 0.75 0.29 (0.08)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.47 0.63 - - 0.47 0.63 0.50 0.67 - - 0.50 0.67 0.50 0.67 0.04

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 45.31 6.29 51.60 44.76 4.36 49.12 2,312.46 50.88 (2.48)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( X )
08 Oktober s/d 14 Oktober 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) volume
bobot
volume
bobot
volume
bobot
VOLUME
BOBOT
VOLUME
BOBOT
VOLUME
BOBOT
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 603.19 24.42 97.66 3.95 700.85 28.37 640.98 25.94 119.02 4.82 760.00 30.76 320.00 12.95 2.39
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 606.64 8.38 - - 606.64 8.38 528.00 7.29 256.00 3.54 784.00 10.83 512.00 7.07 2.45
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 12.13 4.48 - - 12.13 4.48 10.56 3.90 - - 10.56 3.90 15.36 5.67 (0.58)
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 101.11 3.08 - - 101.11 3.08 88.00 2.68 - - 88.00 2.68 128.00 3.90 (0.40)
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 560.53 1.42 - - 560.53 1.42 487.87 1.24 - - 487.87 1.24 709.63 1.80 (0.18)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 17.92 1.45 - - 17.92 1.45 15.60 1.26 - - 15.60 1.26 6.00 0.49 (0.19)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 10.11 2.83 - - 10.11 2.83 8.80 2.46 - - 8.80 2.46 12.80 3.58 (0.37)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 126.38 2.50 - - 126.38 2.50 110.00 2.17 - - 110.00 2.17 160.00 3.16 (0.32)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 25.28 0.38 - - 25.28 0.38 22.00 0.33 - - 22.00 0.33 32.00 0.48 (0.05)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 30.33 1.23 - - 30.33 1.23 26.40 1.07 - - 26.40 1.07 38.40 1.55 (0.16)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.47 0.15 0.36 0.12 0.83 0.27 - - - - - - 1.00 0.33 (0.27)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.83 0.48 - - 0.83 0.48 - - - - - - 1.00 0.58 (0.48)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.47 0.18 - - 0.47 0.18 0.25 0.10 - - 0.25 0.10 0.75 0.29 (0.08)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.47 0.63 - - 0.47 0.63 0.50 0.67 - - 0.50 0.67 0.50 0.67 0.04

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 51.60 4.07 55.67 49.12 8.35 57.48 1,937.44 42.52 1.80

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( XI )
15 Oktober s/d 21 Oktober 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) volume
bobot
volume
bobot
volume
bobot
VOLUME
BOBOT
VOLUME
BOBOT
VOLUME
BOBOT
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 700.85 28.37 97.66 3.95 798.51 32.32 760.00 30.76 - - 760.00 30.76 320.00 12.95 (1.56)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 606.64 8.38 156.26 2.16 762.89 10.54 784.00 10.83 128.00 1.77 912.00 12.60 384.00 5.30 2.06
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 12.13 4.48 - - 12.13 4.48 10.56 3.90 - - 10.56 3.90 15.36 5.67 (0.58)
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 101.11 3.08 - - 101.11 3.08 88.00 2.68 68.00 2.07 156.00 4.75 60.00 1.83 1.67
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 560.53 1.42 - - 560.53 1.42 487.87 1.24 - - 487.87 1.24 709.63 1.80 (0.18)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 17.92 1.45 - - 17.92 1.45 15.60 1.26 - - 15.60 1.26 6.00 0.49 (0.19)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 10.11 2.83 7.81 2.18 17.92 5.01 8.80 2.46 - - 8.80 2.46 12.80 3.58 (2.55)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 126.38 2.50 - - 126.38 2.50 110.00 2.17 - - 110.00 2.17 160.00 3.16 (0.32)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 25.28 0.38 - - 25.28 0.38 22.00 0.33 - - 22.00 0.33 32.00 0.48 (0.05)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 30.33 1.23 - - 30.33 1.23 26.40 1.07 - - 26.40 1.07 38.40 1.55 (0.16)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.83 0.27 - - 0.83 0.27 - - - - - - 1.00 0.33 (0.27)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.83 0.48 - - 0.83 0.48 - - - - - - 1.00 0.58 (0.48)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.47 0.18 0.36 0.14 0.83 0.32 0.25 0.10 - - 0.25 0.10 0.75 0.29 (0.22)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.47 0.63 - - 0.47 0.63 0.50 0.67 - - 0.50 0.67 0.50 0.67 0.04

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 55.67 8.43 64.11 57.48 3.84 61.31 1,741.44 38.69 (2.79)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( XII )
22 Oktober s/d 28 Oktober 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) volume
bobot
volume
bobot
volume
bobot
VOLUME
BOBOT
VOLUME
BOBOT
VOLUME
BOBOT
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 798.51 32.32 97.66 3.95 896.17 36.27 760.00 30.76 - - 760.00 30.76 320.00 12.95 (5.51)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 762.89 10.54 156.26 2.16 919.15 12.69 912.00 12.60 - - 912.00 12.60 384.00 5.30 (0.10)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 12.13 4.48 - - 12.13 4.48 10.56 3.90 - - 10.56 3.90 15.36 5.67 (0.58)
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 101.11 3.08 - - 101.11 3.08 156.00 4.75 - - 156.00 4.75 60.00 1.83 1.67
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 560.53 1.42 216.57 0.55 777.10 1.97 487.87 1.24 376.99 0.96 864.86 2.20 332.64 0.84 0.22
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 17.92 1.45 - - 17.92 1.45 15.60 1.26 - - 15.60 1.26 6.00 0.49 (0.19)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 17.92 5.01 - - 17.92 5.01 8.80 2.46 - - 8.80 2.46 12.80 3.58 (2.55)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 126.38 2.50 97.66 1.93 224.04 4.42 110.00 2.17 85.00 1.68 195.00 3.85 75.00 1.48 (0.57)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 25.28 0.38 - - 25.28 0.38 22.00 0.33 - - 22.00 0.33 32.00 0.48 (0.05)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 30.33 1.23 - - 30.33 1.23 26.40 1.07 - - 26.40 1.07 38.40 1.55 (0.16)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.83 0.27 - - 0.83 0.27 - - - - - - 1.00 0.33 (0.27)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.83 0.48 - - 0.83 0.48 - - - - - - 1.00 0.58 (0.48)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.83 0.32 - - 0.83 0.32 0.25 0.10 - - 0.25 0.10 0.75 0.29 (0.22)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.47 0.63 - - 0.47 0.63 0.50 0.67 - - 0.50 0.67 0.50 0.67 0.04

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 64.11 8.59 72.70 61.31 2.64 63.95 1,279.45 36.05 (8.75)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN BULANAN ( III )
01 Oktober s/d 28 Oktober 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI BULAN INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) bulan lalu bulan ini bulan ini BULAN LALU BULAN INI BULAN INI BOBOT
VOLUME
(Rp) volume
bobot
volume
bobot
volume
bobot
VOLUME
BOBOT
VOLUME
BOBOT
VOLUME
BOBOT
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 505.53 20.46 390.64 15.81 896.17 36.27 534.31 21.63 225.69 9.13 760.00 30.76 320.00 12.95 (5.51)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 606.64 8.38 312.51 4.32 919.15 12.69 528.00 7.29 384.00 5.30 912.00 12.60 384.00 5.30 (0.10)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 8.09 2.99 4.04 1.49 12.13 4.48 10.56 3.90 - - 10.56 3.90 15.36 5.67 (0.58)
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 101.11 3.08 - - 101.11 3.08 88.00 2.68 68.00 2.07 156.00 4.75 60.00 1.83 1.67
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 560.53 1.42 216.57 0.55 777.10 1.97 487.87 1.24 376.99 0.96 864.86 2.20 332.64 0.84 0.22
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 10.11 0.82 7.81 0.63 17.92 1.45 15.60 1.26 - - 15.60 1.26 6.00 0.49 (0.19)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 10.11 2.83 7.81 2.18 17.92 5.01 8.80 2.46 - - 8.80 2.46 12.80 3.58 (2.55)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 126.38 2.50 97.66 1.93 224.04 4.42 110.00 2.17 85.00 1.68 195.00 3.85 75.00 1.48 (0.57)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 25.28 0.38 - - 25.28 0.38 22.00 0.33 - - 22.00 0.33 32.00 0.48 (0.05)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 30.33 1.23 - - 30.33 1.23 26.40 1.07 - - 26.40 1.07 38.40 1.55 (0.16)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.47 0.15 0.36 0.12 0.83 0.27 - - - - - - 1.00 0.33 (0.27)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.47 0.27 0.36 0.21 0.83 0.48 - - - - - - 1.00 0.58 (0.48)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.47 0.18 0.36 0.14 0.83 0.32 0.13 0.05 0.12 0.05 0.25 0.10 0.75 0.29 (0.22)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.47 0.63 - - 0.47 0.63 0.50 0.67 - - 0.50 0.67 0.50 0.67 0.04

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 45.31 27.38 72.70 44.76 19.19 63.95 1,279.45 36.05 (8.75)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( XIII )
29 Oktober s/d 04 November 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 896.17 36.27 - - 896.17 36.27 760.00 30.76 - - 760.00 30.76 320.00 12.95 (5.51)
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 919.15 12.69 156.26 2.16 ### 14.85 912.00 12.60 - - 912.00 12.60 384.00 5.30 (2.26)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 12.13 4.48 4.69 1.73 16.82 6.21 10.56 3.90 8.16 3.01 18.72 6.91 7.20 2.66 0.70
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 101.11 3.08 39.06 1.19 140.17 4.27 156.00 4.75 - - 156.00 4.75 60.00 1.83 0.48
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 777.10 1.97 216.57 0.55 993.67 2.52 864.86 2.20 - - 864.86 2.20 332.64 0.84 (0.33)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 17.92 1.45 - - 17.92 1.45 15.60 1.26 - - 15.60 1.26 6.00 0.49 (0.19)
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 17.92 5.01 - - 17.92 5.01 8.80 2.46 6.80 1.90 15.60 4.36 6.00 1.68 (0.65)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 224.04 4.42 - - 224.04 4.42 195.00 3.85 - - 195.00 3.85 75.00 1.48 (0.57)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 25.28 0.38 - - 25.28 0.38 22.00 0.33 17.00 0.26 39.00 0.59 15.00 0.23 0.21
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 30.33 1.23 11.72 0.47 42.05 1.70 26.40 1.07 20.40 0.83 46.80 1.89 18.00 0.73 0.19
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.83 0.27 - - 0.83 0.27 - - - - - - 1.00 0.33 (0.27)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.83 0.48 - - 0.83 0.48 - - - - - - 1.00 0.58 (0.48)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.83 0.32 - - 0.83 0.32 0.25 0.10 - - 0.25 0.10 0.75 0.29 (0.22)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.47 0.63 - - 0.47 0.63 0.50 0.67 0.20 0.27 0.70 0.94 0.30 0.40 0.31

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 72.70 6.10 78.80 63.95 6.27 70.22 1,226.89 29.78 (8.58)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( XIV )
05 November s/d 11 November 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) volume
bobot
volume
bobot
volume
bobot
VOLUME
BOBOT
VOLUME
BOBOT
VOLUME
BOBOT
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 896.17 36.27 - - 896.17 36.27 760.00 30.76 160.00 6.48 920.00 37.24 160.00 6.48 0.96
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 1,075.40 14.85 - - 1,075.40 14.85 912.00 12.60 - - 912.00 12.60 384.00 5.30 (2.26)
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 16.82 6.21 4.69 1.73 21.51 7.94 18.72 6.91 - - 18.72 6.91 7.20 2.66 (1.03)
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 140.17 4.27 39.06 1.19 179.23 5.46 156.00 4.75 - - 156.00 4.75 60.00 1.83 (0.71)
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 993.67 2.52 - - 993.67 2.52 864.86 2.20 - - 864.86 2.20 332.64 0.84 (0.33)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 17.92 1.45 - - 17.92 1.45 15.60 1.26 6.00 0.49 21.60 1.75 - - 0.30
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 17.92 5.01 - - 17.92 5.01 15.60 4.36 - - 15.60 4.36 6.00 1.68 (0.65)
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 224.04 4.42 - - 224.04 4.42 195.00 3.85 - - 195.00 3.85 75.00 1.48 (0.57)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 25.28 0.38 19.53 0.30 44.81 0.68 39.00 0.59 - - 39.00 0.59 15.00 0.23 (0.09)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 42.05 1.70 11.72 0.47 53.77 2.18 46.80 1.89 - - 46.80 1.89 18.00 0.73 (0.28)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.83 0.27 - - 0.83 0.27 - - - - - - 1.00 0.33 (0.27)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.83 0.48 - - 0.83 0.48 - - - - - - 1.00 0.58 (0.48)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.83 0.32 - - 0.83 0.32 0.25 0.10 - - 0.25 0.10 0.75 0.29 (0.22)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.47 0.63 0.36 0.49 0.83 1.12 0.70 0.94 - - 0.70 0.94 0.30 0.40 (0.17)

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 78.80 4.18 82.98 70.22 6.96 77.18 1,060.89 22.82 (5.80)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( XV )
12 November s/d 18 November 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) volume
bobot
volume
bobot
volume
bobot
VOLUME
BOBOT
VOLUME
BOBOT
VOLUME
BOBOT
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 896.17 36.27 45.96 1.86 942.13 38.13 920.00 37.24 160.00 6.48 ### 43.71 - - 5.58
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 ### 14.85 - - ### 14.85 912.00 12.60 256.00 3.54 ### 16.13 128.00 1.77 1.28
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 21.51 7.94 - - 21.51 7.94 18.72 6.91 - - 18.72 6.91 7.20 2.66 (1.03)
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 179.23 5.46 - - 179.23 5.46 156.00 4.75 - - 156.00 4.75 60.00 1.83 (0.71)
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 993.67 2.52 - - 993.67 2.52 864.86 2.20 - - 864.86 2.20 332.64 0.84 (0.33)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 17.92 1.45 3.68 0.30 21.60 1.75 21.60 1.75 - - 21.60 1.75 - - 0.00
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 17.92 5.01 - - 17.92 5.01 15.60 4.36 6.00 1.68 21.60 6.04 - - 1.03
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 224.04 4.42 - - 224.04 4.42 195.00 3.85 - - 195.00 3.85 75.00 1.48 (0.57)
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 44.81 0.68 - - 44.81 0.68 39.00 0.59 - - 39.00 0.59 15.00 0.23 (0.09)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 53.77 2.18 - - 53.77 2.18 46.80 1.89 - - 46.80 1.89 18.00 0.73 (0.28)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.83 0.27 - - 0.83 0.27 - - - - - - 1.00 0.33 (0.27)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.83 0.48 0.17 0.10 1.00 0.58 - - - - - - 1.00 0.58 (0.58)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.83 0.32 - - 0.83 0.32 0.25 0.10 - - 0.25 0.10 0.75 0.29 (0.22)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.83 1.12 - - 0.83 1.12 0.70 0.94 - - 0.70 0.94 0.30 0.40 (0.17)

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 82.98 2.26 85.24 77.18 11.69 88.87 638.89 11.13 3.63

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( XVI )
19 November s/d 25 November 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 942.13 38.13 45.96 1.86 988.09 39.99 ### 43.71 - - 1,080.00 43.71 - - 3.72
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 ### 14.85 - - ### 14.85 ### 16.13 128.00 1.77 1,296.00 17.90 - - 3.05
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 21.51 7.94 - - 21.51 7.94 18.72 6.91 - - 18.72 6.91 7.20 2.66 (1.03)
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 179.23 5.46 - - 179.23 5.46 156.00 4.75 - - 156.00 4.75 60.00 1.83 (0.71)
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 993.67 2.52 - - 993.67 2.52 864.86 2.20 - - 864.86 2.20 332.64 0.84 (0.33)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 21.60 1.75 - - 21.60 1.75 21.60 1.75 - - 21.60 1.75 - - 0.00
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 17.92 5.01 - - 17.92 5.01 21.60 6.04 - - 21.60 6.04 - - 1.03
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 224.04 4.42 - - 224.04 4.42 195.00 3.85 75.00 1.48 270.00 5.33 - - 0.91
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 44.81 0.68 - - 44.81 0.68 39.00 0.59 - - 39.00 0.59 15.00 0.23 (0.09)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 53.77 2.18 - - 53.77 2.18 46.80 1.89 - - 46.80 1.89 18.00 0.73 (0.28)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.83 0.27 0.17 0.06 1.00 0.33 - - - - - - 1.00 0.33 (0.33)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 1.00 0.58 - - 1.00 0.58 - - - - - - 1.00 0.58 (0.58)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.83 0.32 - - 0.83 0.32 0.25 0.10 - - 0.25 0.10 0.75 0.29 (0.22)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.83 1.12 - - 0.83 1.12 0.70 0.94 - - 0.70 0.94 0.30 0.40 (0.17)

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 85.24 1.92 87.15 88.87 3.25 92.12 435.89 7.88 4.97

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN BULANAN ( IV )
29 Oktober s/d 25 November 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI BULAN INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) bulan lalu bulan ini bulan ini BULAN LALU BULAN INI BULAN INI BOBOT
VOLUME
(Rp) volume
bobot
volume
bobot
volume
bobot
VOLUME
BOBOT
VOLUME
BOBOT
VOLUME
BOBOT
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 896.17 36.27 91.91 3.72 988.09 39.99 760.00 30.76 320.00 12.95 1,080.00 43.71 - - 3.72
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 919.15 12.69 156.26 2.16 ### 14.85 912.00 12.60 384.00 5.30 1,296.00 17.90 - - 3.05
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) - -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 12.13 4.48 9.38 3.46 21.51 7.94 10.56 3.90 8.16 3.01 18.72 6.91 7.20 2.66 (1.03)
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 101.11 3.08 78.13 2.38 179.23 5.46 156.00 4.75 - - 156.00 4.75 60.00 1.83 (0.71)
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 777.10 1.97 216.57 0.55 993.67 2.52 864.86 2.20 - - 864.86 2.20 332.64 0.84 (0.33)
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 17.92 1.45 3.68 0.30 21.60 1.75 15.60 1.26 6.00 0.49 21.60 1.75 - - 0.00
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 17.92 5.01 - - 17.92 5.01 8.80 2.46 12.80 3.58 21.60 6.04 - - 1.03
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 224.04 4.42 - - 224.04 4.42 195.00 3.85 75.00 1.48 270.00 5.33 - - 0.91
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 25.28 0.38 19.53 0.30 44.81 0.68 22.00 0.33 17.00 0.26 39.00 0.59 15.00 0.23 (0.09)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 30.33 1.23 23.44 0.95 53.77 2.18 26.40 1.07 20.40 0.83 46.80 1.89 18.00 0.73 (0.28)
SUB TOTAL II 506,278,484.55 - -
BIAYA OPERASIONAL - -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 0.83 0.27 0.17 0.06 1.00 0.33 - - - - - - 1.00 0.33 (0.33)
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 0.83 0.48 0.17 0.10 1.00 0.58 - - - - - - 1.00 0.58 (0.58)
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.83 0.32 - - 0.83 0.32 0.25 0.10 - - 0.25 0.10 0.75 0.29 (0.22)
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.47 0.63 0.36 0.49 0.83 1.12 0.50 0.67 0.20 0.27 0.70 0.94 0.30 0.40 (0.17)

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 72.70 14.45 87.15 63.95 28.17 92.12 435.89 7.88 4.97

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( XVII )
26 November s/d 02 Desember 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) (%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) volume
bobot
volume
bobot
volume
bobot
VOLUME
BOBOT
VOLUME
BOBOT
VOLUME
BOBOT
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 988.09 39.99 45.96 1.86 1,034.04 41.85 1,080.00 43.71 - - 1,080.00 43.71 - - 1.86
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 1,075.40 14.85 73.53 1.02 1,148.94 15.87 1,296.00 17.90 - - 1,296.00 17.90 - - 2.03
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 21.51 7.94 - - 21.51 7.94 18.72 6.91 - - 18.72 6.91 7.20 2.66 (1.03)
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 179.23 5.46 - - 179.23 5.46 156.00 4.75 60.00 1.83 216.00 6.58 - - 1.12
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 993.67 2.52 101.92 0.26 1,095.59 2.78 864.86 2.20 332.64 0.84 1,197.50 3.04 - - 0.26
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 21.60 1.75 - - 21.60 1.75 21.60 1.75 - - 21.60 1.75 - - 0.00
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 17.92 5.01 3.68 1.03 21.60 6.04 21.60 6.04 - - 21.60 6.04 - - 0.00
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 224.04 4.42 - - 224.04 4.42 270.00 5.33 - - 270.00 5.33 - - 0.91
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 44.81 0.68 - - 44.81 0.68 39.00 0.59 - - 39.00 0.59 15.00 0.23 (0.09)
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 53.77 2.18 - - 53.77 2.18 46.80 1.89 - - 46.80 1.89 18.00 0.73 (0.28)
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 1.00 0.33 - - 1.00 0.33 - - 1.00 0.33 1.00 0.33 - - 0.00
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 1.00 0.58 - - 1.00 0.58 - - 1.00 0.58 1.00 0.58 - - 0.00
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.83 0.32 0.17 0.07 1.00 0.38 0.25 0.10 0.75 0.29 1.00 0.38 - - 0.00
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.83 1.12 - - 0.83 1.12 0.70 0.94 0.30 0.40 1.00 1.35 - - 0.23

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 87.15 4.23 91.38 92.12 4.27 96.39 40.20 3.61 5.01

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN MINGGUAN ( XVIII )
03 November s/d 09 Desember 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN S/D


RENCANA REALISASI MINGGU INI
Jumlah Harga
Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.)
(%) minggu lalu minggu ini minggu ini MINGGU LALU MINGGU INI MINGGU INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 1,034.04 41.85 45.96 1.86 1,080.00 43.71 1,080.00 43.71 - - 1,080.00 43.71 - - 0.00
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 1,148.94 15.87 73.53 1.02 1,222.47 16.88 1,296.00 17.90 - - 1,296.00 17.90 - - 1.02
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 21.51 7.94 1.47 0.54 22.98 8.49 18.72 6.91 7.20 2.66 25.92 9.57 - - 1.09
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 179.23 5.46 18.38 0.56 197.62 6.02 216.00 6.58 - - 216.00 6.58 - - 0.56
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 1,095.59 2.78 101.92 0.26 1,197.50 3.04 1,197.50 3.04 - - 1,197.50 3.04 - - 0.00
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 21.60 1.75 - - 21.60 1.75 21.60 1.75 - - 21.60 1.75 - - 0.00
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 21.60 6.04 - - 21.60 6.04 21.60 6.04 - - 21.60 6.04 - - 0.00
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 224.04 4.42 45.96 0.91 270.00 5.33 270.00 5.33 - - 270.00 5.33 - - 0.00
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 44.81 0.68 - - 44.81 0.68 39.00 0.59 15.00 0.23 54.00 0.82 - - 0.14
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 53.77 2.18 - - 53.77 2.18 46.80 1.89 18.00 0.73 64.80 2.62 - - 0.45
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 1.00 0.33 - - 1.00 0.33 1.00 0.33 - - 1.00 0.33 - - 0.00
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 1.00 0.58 - - 1.00 0.58 1.00 0.58 - - 1.00 0.58 - - 0.00
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 1.00 0.38 - - 1.00 0.38 1.00 0.38 - - 1.00 0.38 - - 0.00
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.83 1.12 - - 0.83 1.12 1.00 1.35 - - 1.00 1.35 - - 0.23

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 91.38 5.14 96.52 96.39 3.61 100.00 - - 3.48

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
LAPORAN BULANAN ( V )
26 November s/d 7 Desember 2018

TANGKI SEPTIC INDIVIDUAL


26/33.1/III/KONT/DAK-P/PKSKA-DM/PKP/2018

PAKET : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL


KSM : KELURAHAN KLASULUK
NAMA TFL : IRVAN BONGI, ST
JULES D. ANTOH, SE

SISA PEKERJAAN
RENCANA REALISASI S/D BULAN INI
Jumlah Harga
Uraian Kegiatan Volume Satuan Harga Satuan (Rp.) Bobot s/d rencana s/d S/D PRESTASI S/D DEVIASI
(%) bulan lalu bulan ini bulan ini BULAN LALU BULAN INI BULAN INI BOBOT
VOLUME
(Rp) bobot bobot bobot BOBOT BOBOT BOBOT
volume volume volume VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
I PEKERJAAN TANAH
1 Galian tanah biasa 343.33 m3 0 0
SUB TOTAL I
II PEKERJAAN SANITAIR
1 Pek. Pas. Batu Camp. 1 : 3 (tebal 1/2 batu) 1,080.00 m2 210,468.60 227,306,088.00 43.71 988.09 39.99 91.91 3.72 1,080.00 43.71 760.00 43.71 - - 760.00 43.71 - - 0.00
2 Pek. Plesteran Camp. 1 : 3 1,296.00 m2 71,814.49 93,071,579.04 17.90 1,075.40 14.85 220.60 3.05 1,296.00 17.90 912.00 17.90 - - 912.00 17.90 - - 0.00
3 Pek. Cor Plat Penutup ( camp 1 : 2 : 3 ) -
a. Pek. COR lantai plat Penutup 25.92 m3 1,920,333.67 49,775,048.84 9.57 21.51 7.94 4.41 1.63 25.92 9.57 10.56 6.91 7.20 2.66 17.76 9.57 - - 0.00
b. Pek. Begesting 216.00 m2 158,387.80 34,211,764.80 6.58 179.23 5.46 36.77 1.12 216.00 6.58 156.00 4.75 60.00 1.83 216.00 6.58 - - 0.00
c. Pek. Besi U 24 (POLOS) besi θ 10 1,197.50 kg 13,198.00 15,804,657.79 3.04 993.67 2.52 203.83 0.52 1,197.50 3.04 864.86 2.20 332.64 0.84 1,197.50 3.04 - - 0.00
4 Pek Urugan Pasir Dasar Septictank 21.60 m3 421,418.00 9,102,628.80 1.75 21.60 1.75 - - 21.60 1.75 15.60 1.75 - - 15.60 1.75 - - 0.00
5 Pek. Cor Dasar Septic Tank ( camp 1 : 3 : 5 ) 21.60 m3 1,453,620.00 31,398,192.00 6.04 17.92 5.01 3.68 1.03 21.60 6.04 8.80 6.04 - - 8.80 6.04 - - 0.00
6 Pek. Pas. pipa septictank dia. 3 in+ Acc 270.00 m 102,677.50 27,722,925.00 5.33 224.04 4.42 45.96 0.91 270.00 5.33 195.00 5.33 - - 195.00 5.33 - - 0.00
7 Pek. Pas. Pipa Penguapan dia. 1,5 in & Acc 54.00 m 78,652.50 4,247,235.00 0.82 44.81 0.68 9.19 0.14 54.00 0.82 22.00 0.59 15.00 0.23 37.00 0.82 - - 0.00
8 Pek. Sumur resapan dia. 60 cm tinggi 50 cm 64.80 m2 210,468.60 13,638,365.28 2.62 53.77 2.18 11.03 0.45 64.80 2.62 26.40 1.89 18.00 0.73 44.40 2.62 - - 0.00
SUB TOTAL II 506,278,484.55 -
BIAYA OPERASIONAL -
1 Biaya Dokumentasi/Pelaporan 1 Ls 1,700,000.00 1,700,000.00 0.33 1.00 0.33 - - 1.00 0.33 - - 1.00 0.33 1.00 0.33 - - 0.00
2 Biaya Pertemuan/Konsumsi Harian/Akomodasi 1 Ls 3,000,000.00 3,000,000.00 0.58 1.00 0.58 - - 1.00 0.58 - - 1.00 0.58 1.00 0.58 - - 0.00
3 Biaya Transportasi 1 Ls 2,000,000.00 2,000,000.00 0.38 0.83 0.32 0.17 0.07 1.00 0.38 0.25 0.10 0.75 0.29 1.00 0.38 - - 0.00
4 Honor KSM (4 orang) + Pan.Peng (3 orang) 1 Ls 7,000,000.00 7,000,000.00 1.35 0.83 1.12 0.17 0.23 1.00 1.35 0.50 0.94 0.30 0.40 0.80 1.35 - - 0.00

TOTAL 519,978,484.55
JUMLAH BOBOT PEKERJAAN 100 87.15 12.85 100.00 92.12 7.88 100.00 - - (0.00)

Pejabat Pembuat Komitmen Tenaga Fasilitator Lapangan Kelompok Swadaya Masyarakat


TFL. Teknis TFL. Pemberdayaan Kel. Klasuluk

Angky Januar Manuputty, ST IRVAN BONGI, ST JULES D. ANTOH, SE NYUJIANTORO


NIP. 19770101 201004 1 001 TFL Teknik TFL Pemberdayaan Ketua
1 2 3 a b c 4 5 6 7 8 9 10 11 12

Pek. Cor Pek. Biaya


Pek. Pas. Pek. Cor Pek Pek. Pas. Pek. Pas. Honor
Batu Pek. Plat a. Pek. c. Pek. Besi U Urugan Dasar pipa Pipa Sumur Biaya Pertemua Biaya KSM (4
Plesteran COR lantai b. Pek. Septic resapan Dokument n/Konsum
Camp. 1 : Camp. 1 : Penutup 24 (POLOS) Pasir septictank Penguapa dia. 60 cm asi/Pelapo Transport orang) +
KLASULUK 3 (tebal ( camp 1 :
plat Begesting
besi θ 10 Dasar
Tank
dia. 3 in+ n dia. 1,5
si
asi Pan.Peng
3 Penutup ( camp 1 : tinggi 50 ran Harian/Ak
1/2 batu) 2:3) Septictank Acc in & Acc (3 orang)
3:5) cm omodasi

m2 m2 m3 m2 kg m3 m3 m m m2
06/08/2018 14.25
07/08/2018 14.35
08/08/2018 14.45
1 09/08/2018 14.55
10/08/2018 14.65
11/08/2018 14.75
12/08/2018 87.00 - - - - - - - - - - - - - -
13/08/2018 14.33 0.23
14/08/2018 14.43 0.43
15/08/2018 14.53 0.63
2 16/08/2018 14.63 0.83
17/08/2018 14.73 1.03
18/08/2018 14.83 1.23
19/08/2018 87.50 - - - - - 4.40 - - - - - - - -
20/08/2018 14.42 0.23 0.13
21/08/2018 14.52 0.43
22/08/2018 14.62 0.63
3 23/08/2018 14.72 0.83
24/08/2018 14.82 1.03
25/08/2018 14.92 1.23
26/08/2018 88.00 - - - - - 4.40 - - - - - - 0.13 -
27/08/2018 14.50 29.00
28/08/2018 14.60 29.10
29/08/2018 14.70 29.20
4 30/08/2018 14.80 29.30
31/08/2018 14.90 29.40
01/09/2018 15.00 29.50
02/09/2018 88.50 175.50 - - - - - - - - - - - - -
03/09/2018 14.58 29.08 0.63 7.18 80.31 -
04/09/2018 14.68 29.18 0.73 7.24 80.71 -
05/09/2018 14.78 29.28 0.83 7.30 81.11
5 06/09/2018 14.88 29.38 0.93 7.36 81.51 -
07/09/2018 14.98 29.48 1.03 7.42 81.91 -
08/09/2018 15.08 29.58 1.13 7.48 82.31 -
09/09/2018 89.00 176.00 - 5.28 44.00 487.87 - - - - - - - - -
10/09/2018 29.17 0.63 7.18 0.63 6.67
11/09/2018 29.27 0.73 7.24 0.67 7.67
12/09/2018 29.37 0.83 7.30 0.71 8.67
6 13/09/2018 29.47 0.93 7.36 0.75 9.67
14/09/2018 29.57 1.03 7.42 0.79 10.67
15/09/2018 29.67 1.13 7.48 0.83 11.67
16/09/2018 - 176.50 - 5.28 44.00 - - 4.40 55.00 - - - - - -
17/09/2018 8.17 4.00 4.15 0.50
18/09/2018 8.57 4.00 4.25
19/09/2018 8.97 4.00 4.35
7 20/09/2018 9.37 4.00 4.45
21/09/2018 9.77 3.00 4.55
22/09/2018 10.17 3.00 4.65
23/09/2018 - - - - - - - - 55.00 22.00 26.40 - - - 0.50
24/09/2018 17.19 1.03
25/09/2018 17.39 1.07
26/09/2018 17.59 1.11
8 27/09/2018 17.79 1.15
28/09/2018 17.99 1.19
29/09/2018 18.19 1.23
30/09/2018 106.17 - - - - - 6.80 - - - - - - - -
01/10/2018 17.28
02/10/2018 17.48
03/10/2018 17.68
9 04/10/2018 17.88
05/10/2018 18.08 0.12
06/10/2018 18.28
07/10/2018 106.67 - - - - - - - - - - - - 0.12 -
08/10/2018 17.36 42.42
09/10/2018 17.56 42.52
10/10/2018 17.76 42.62
10 11/10/2018 17.96 42.72
12/10/2018 18.16 42.82
13/10/2018 18.36 42.92
14/10/2018 107.17 256.00 - - - - - - - - - - - - -
15/10/2018 21.08 10.33
16/10/2018 21.18 10.73
17/10/2018 21.28 11.13
11 18/10/2018 21.38 11.53
19/10/2018 21.48 11.93
20/10/2018 21.58 12.33
21/10/2018 - 128.00 - - 68.00 - - - - - - - - - -
22/10/2018 62.58 13.17
23/10/2018 62.68 13.57
24/10/2018 62.78 13.97
12 25/10/2018 62.88 14.37
26/10/2018 62.98 14.77
27/10/2018 63.08 15.17
28/10/2018 - - - - - 376.99 - - 85.00 - - - - - -
29/10/2018 1.36 1.13 2.58 3.15
30/10/2018 1.36 1.13 2.68 3.25
31/10/2018 1.36 1.13 2.78 3.35
13 01/11/2018 1.36 1.13 2.88 3.45
02/11/2018 1.36 1.13 2.98 3.55
03/11/2018 1.36 1.13 3.08 3.65
04/11/2018 - - - 8.16 - - - 6.80 - 17.00 20.40 - - - -
05/11/2018 25.67 0.50 0.20
06/11/2018 26.07 0.70
07/11/2018 26.47 0.90
14 08/11/2018 26.87 1.10
09/11/2018 27.27 1.30
10/11/2018 27.67 1.50
11/11/2018 160.00 - - - - - 6.00 - - - - - - - 0.20
12/11/2018 25.67 42.17 -
13/11/2018 26.07 42.37 -
14/11/2018 26.47 42.57 -
15 15/11/2018 26.87 42.77 -
16/11/2018 27.27 42.97 -
17/11/2018 27.67 43.17 -
18/11/2018 160.00 256.00 - - - - - - - - - - - - -
19/11/2018 21.08 12.25
20/11/2018 21.18 12.35
21/11/2018 21.28 12.45
16 22/11/2018 21.38 12.55
23/11/2018 21.48 12.65
24/11/2018 21.58 12.75
25/11/2018 - 128.00 - - - - - - 75.00 - - - - - -
26/11/2018 9.75 54.94
27/11/2018 10.15 55.14
28/11/2018 10.55 55.34
17 29/11/2018 10.95 55.54
30/11/2018 11.35 55.74 1.00 1.00 0.75 0.30
01/12/2018 11.75 55.94
02/12/2018 - - - - 64.50 332.64 - - - - - 1.00 1.00 0.75 0.30
03/12/2018 0.80 2.00 2.00
04/12/2018 0.96 2.20 2.40
05/12/2018 1.12 2.40 2.80
18 06/12/2018 1.28 2.60 3.20
07/12/2018 1.44 2.80 3.60
08/12/2018 1.60 3.00 4.00
09/12/2018 - - - 7.20 - - - - - 15.00 18.00 - - - -
ORGANISASI : DINAS PERUMAHAN DAN KAWASAN PERMUKIMAN KABUPATEN SORONG
PROGRAM : PROGRAM SARANA DAN PRASARANA SANITASI LINGKUNGAN BERBASIS MASYARAKAT
KEGIATAN : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL
LOKASI : KELURAHAN KLASULUK
SUMBER DANA : DAK-PENUGASAN
JUMLAH : 54 UNIT
TAHUN ANGGARAN : 2018 HARI : ................
CATATAN / LAPORAN HARIAN PELAKSANAAN PEKERJAAN TANGGAL : ................
TENAGA KERJA TIBA / MUTASI BAHAN KONSTRUKSI PEMAKAIAN PEKERJAAN YANG DILAKSANAKAN HARI INI
Jumlah Keahlian Jenis Bahan Jumlah Diterima Ditolak PERALATAN Uraian Pekerjaan Satuan Volume

Orang Pelaksana
Orang Mandor
Orang Kepala Tukang
Orang Tukang Batu
Orang Tukang Besi
Orang Pekerja

CERAH
CUACA PEKERJAAN DI MULAI DARI PUKUL : s/d WIT.
HUJAN

Dibuat Oleh : Di Periksa Oleh :


KSM KELURAHAN MARIYAI TENAGA FASILITATOR LAPANGAN

HARTONO IRVAN BONGI, ST JULES D. ANTOH, SE


Ketua TFL Teknis TFL Pemberdayaan
ORGANISASI : DINAS PERUMAHAN DAN KAWASAN PERMUKIMAN KABUPATEN SORONG
PROGRAM : PROGRAM SARANA DAN PRASARANA SANITASI LINGKUNGAN BERBASIS MASYARAKAT
KEGIATAN : PEMBANGUNAN TANGKI SEPTIC INDIVIDUAL
LOKASI : KELURAHAN KLASULUK
SUMBER DANA : DAK-PENUGASAN
JUMLAH : 54 UNIT
TAHUN ANGGARAN : 2018 HARI : ................
CATATAN / LAPORAN HARIAN PELAKSANAAN PEKERJAAN TANGGAL : ................
TENAGA KERJA TIBA / MUTASI BAHAN KONSTRUKSI PEMAKAIAN PEKERJAAN YANG DILAKSANAKAN HARI INI
Jumlah Keahlian Jenis Bahan Jumlah Diterima Ditolak PERALATAN Uraian Pekerjaan Satuan Volume

Orang Pelaksana
Orang Mandor
Orang Kepala Tukang
Orang Tukang Batu
Orang Tukang Besi
Orang Pekerja

CERAH
CUACA PEKERJAAN DI MULAI DARI PUKUL : s/d WIT.
HUJAN

Dibuat Oleh : Di Periksa Oleh :


KSM KELURAHAN KLASULUK TENAGA FASILITATOR LAPANGAN

Nyujiantoro IRVAN BONGI, ST JULES D. ANTOH, SE


Ketua TFL Teknis TFL Pemberdayaan
KELOMPOK SWADAYA MASYARAKAT
KELURAHAN KLASULUK DISTRIK MARIAT

LAPORAN PROGRESS PEKERJAAN FISIK

PAKET :
PROGRAM KEGIATAN
PENYEDIAAN SARANA DAN PRASARANA
SANITASI LINGKUNGAN K

JENIS KEGIATAN:
PEKERJAAN PEMBANGUNAN BARU/
PEREMAJAAN KEMBALI TANGKI SEPTIK
INDIVIDUAL

LOKASI:
KELURAHAN KLASULUK

TAHUN ANGGARAN 2018