REKAPITULASI TOTAL BIAYA PEKERJAAN

PROGRAM : RANCANGAN PENGELOLAAN LAHAN DAN TATA AIR KP. LEMPAKE TAHUN 2019
PEKERJAAN : PEMBUATAN PARIT KELILING DAN PINTU AIR KP. LEMPAKE
LOKASI : JL. GUNUNG LINGAI KEL. LEMPAKE KOTA SAMARINDA
SUMBER DANA : APBN BPTP BALITBANGTAN KALTIM
TAHUN ANGGARAN : 2019

JUMLAH
NO. URAIAN PEKERJAAN
HARGA (Rp)
A REKAPITULASI I 255,203,300.00

B REKAPITULASI II 101,331,054.28

JUNLAH HARGA 356,534,354.28


PPn 10 % 35,653,435.43
JULAH HARGA SETELAH PAJAK 392,187,789.71

Samarinda, 14 Oktober 2019


Penawar
CV. BINTARAN TECHNIK

HARSONO
Direktur

1
HARGA KUANTITAS PENAWARAN BIAYA
PROGRAM : RANCANGAN PENGELOLAAN LAHAN DAN TATA AIR KP. LEMPAKE TAHUN 2019
PEKERJAAN : PEMBUATAN PARIT KELILING DAN PINTU AIR KP. LEMPAKE
LOKASI : JL. GUNUNG LINGAI KEL. LEMPAKE KOTA SAMARINDA
SUMBER DANA : APBN BPTP BALITBANGTAN KALTIM
TAHUN ANGGARAN : 2019

JUMLAH
NO. URAIAN PEKERJAAN
HARGA (Rp)
A PEKERJAAN PENDAHULUAN 31,000,000.00

B PEKERJAAN GALIAN TANAH DAN PEMBENTUKAN TANGGUL 224,203,300.00

JUNLAH HARGA 255,203,300.00

1
HARGA KUANTITAS PENAWARAN BIAYA
PROGRAM : RANCANGAN PENGELOLAAN LAHAN DAN TATA AIR KP. LEMPAKE TAHUN 2019
PEKERJAAN : PEMBUATAN PARIT KELILING DAN PINTU AIR KP. LEMPAKE
LOKASI : JL. GUNUNG LINGAI KEL. LEMPAKE KOTA SAMARINDA
SUMBER DANA : APBN BPTP BALITBANGTAN KALTIM
TAHUN ANGGARAN : 2019

HARGA JUMLAH
NO. URAIAN PEKERJAAN SAT VOL
SATUAN (Rp) HARGA (Rp)
A PEKERJAAN PENDAHULUAN
1 pembersihan lokasi pekerjaan ls 1.000 5,000,000.00 5,000,000.00
2 dewatering ls 1.000 16,000,000.00 16,000,000.00
3 mobilisasi dan demobilisasi alat excavator ls 1.000 10,000,000.00 10,000,000.00
JUMLAH HARGA A (PEKERJAAN PENDAHULUAN) 31,000,000.00
B PEKERJAAN GALIAN TANAH DAN PEMBENTUKAN TANGGUL
Galian tanah dan pembentukan tanggul dari galian (tinggi 2 m dan
1 m3 4,960.250 45,200.00 224,203,300.00
lebar atas 3 m & lebar bawah 2.5 m)

JUMLAH HARGA B (PEMBUATAN PINTU AIR) 224,203,300.00

1
HARGA KUANTITAS PENAWARAN BIAYA
PROGRAM : RANCANGAN PENGELOLAAN LAHAN DAN TATA AIR KP. LEMPAKE TAHUN 2019
PEKERJAAN : PEMBUATAN PARIT KELILING DAN PINTU AIR KP. LEMPAKE
LOKASI : JL. GUNUNG LINGAI KEL. LEMPAKE KOTA SAMARINDA
SUMBER DANA : APBN BPTP BALITBANGTAN KALTIM
TAHUN ANGGARAN : 2019

JUMLAH
NO. URAIAN PEKERJAAN
HARGA (Rp)
A PEKERJAAN PENDAHULUAN 21,000,000.00

B PEMBUATAN PINTU AIR 80,331,054.28

JUNLAH HARGA 101,331,054.28

1
HARGA KUANTITAS PENAWARAN BIAYA
PROGRAM : RANCANGAN PENGELOLAAN LAHAN DAN TATA AIR KP. LEMPAKE TAHUN 2019
PEKERJAAN : PEMBUATAN PARIT KELILING DAN PINTU AIR KP. LEMPAKE
LOKASI : JL. GUNUNG LINGAI KEL. LEMPAKE KOTA SAMARINDA
SUMBER DANA : APBN BPTP BALITBANGTAN KALTIM
TAHUN ANGGARAN : 2019

HARGA JUMLAH
NO. URAIAN PEKERJAAN SAT VOL
SATUAN (Rp) HARGA (Rp)
A PEKERJAAN PENDAHULUAN
1 dewatering ls 1.000 16,000,000.00 16,000,000.00
2 pasangan bouwplank ls 1.000 5,000,000.00 5,000,000.00
JUMLAH HARGA A (PEKERJAAN PENDAHULUAN) 21,000,000.00
B PEMBUATAN PINTU AIR
1 Galian tanah sloof dan pasangan batu gunung m3 9.120 724,600.00 6,608,352.00
2 bekisting (bekisting sloof 1 x pakai pintu air) m2 6.360 532,400.00 3,386,064.00
3 bekisting ( bekisting kolom dan balok 1 x pakai pintu air) m2 9.200 482,600.00 4,439,920.00
4 pembesian (pembesian sloof pintu air) kg 275.220 17,000.00 4,678,740.00
5 pembesian (pembesian kolom dan balok pintu air) kg 143.330 17,000.00 2,436,610.00
6 cor beton m3 2.960 4,587,118.00 13,577,869.28
7 pasangan batu gunung m3 4.310 446,500.00 1,924,415.00
8 plesteran dan acian (sudah termasuk plesteran + acian beton) m2 36.520 226,700.00 8,279,084.00
9 pasangan pintu air papan ulin 100 cm x 120 cm + rangka besi unit 2.000 17,500,000.00 35,000,000.00
JUMLAH HARGA B (PEMBUATAN PINTU AIR) 80,331,054.28