Kepada Yth.

Bp. Candra
PT. Suryacendra Puramegah

No. : 633/TEX/VIII/19 Proyek : Playground


Tanggal : 05 September 2019 Lokasi : Cikarang
Quotation Valid : 30 (tiga puluh) hari Luas Area : 503,72m²
QUOTATION
HARGA JUMLAH SUB JUMLAH
NO URAIAN SAT VOL SATUAN HARGA
( Rp.) ( Rp.) ( Rp.)
I. Pekerjaan Persiapan
1 Mobdemob material, peralatan dan pekerja ke lokasi proyek LS 1,0 5.000.000 5.000.000
2 Akomodasi LS 1,0 3.500.000 3.500.000
3 Pembersihan areal m2 503,7 3.000 1.511.160 10.011.160
II. Alternative Pekerjaan Flooring Playground
A. Sigma Polyurethane ex. USA with EPDM Rubber (t =20mm)
- Moisture Barrier
- Polyurethane Sealer Compound
- Polyurethane Black SBR Rubber (t = 15mm)
- Polyurethane EPDM Rubber (t = 5mm) m2 503,7 650.000 327.418.000 327.418.000
B. Sigma Polyurethane ex. USA with SBR Rubber (t= 20mm)
- Moisture Barrier
- Polyurethane Sealer Compound
- Polyurethane Black SBR Rubber (t = 15mm)
- Polyurethane Coloured SBR Rubber (t = 5mm) m2 503,7 525.000 264.453.000 264.453.000
Jumlah Pekerjaan I dan IIA 337.000.000
Note : Biaya di luar PPN
Jumlah Pekerjaan I dan IIB 274.000.000

Catatan :
1. Biaya pekerjaan termasuk biaya material dan pemasangan.
2. Penambahan atau pengurangan volume akan diopname bersama-sama di lapangan.
3. Gudang, listrik dan air bersih disediakan oleh pemberi kerja.
4. Mobilisasi material, peralatan dan pekerja 14 hari setelah DP diterima.
5. Lama pekerjaan + 45 hari setelah pekerja sampai di lokasi proyek.
6. Garansi Sigma Polyurethane berlaku untuk 2 (dua) tahun terhitung sejak serah terima, termasuk kerusakan seperti mengelupas atau retak,
diluar kerusakan akibat benda tajam, tersiram bahan kimia atau force majeure.

Term Pembayaran
40% DP dibayarkan setelah SPK ditandatangani.
Pembayaran selanjutnya by progress.

Hormat kami,
PT. TEXMURA

Marlon Nursalim
Direktur