Cycle Management.
C. Coulthard, B.A.
D. S. Evans Ph.D., P. Geol.
I. Henderson M.Sc., P. Eng.
(5) Summary
CSC
Excellence In Risk Management April 2005
Mining Issues and Problems - Mining Life Cycle Activities
CSC
Excellence In Risk Management April 2005
Mining Issues and Problems – Key Uncertainties
(5) Summary
CSC
Excellence In Risk Management April 2005
Project Management Mantras
+ =
Continuous Breakthrough
Cost Quality Improvement Thinking
CSC
Excellence In Risk Management April 2005
Three Techniques are available that address different levels of
Risk Management
Qualitative Range Estimating Quantitative Analysis
Identify key project risks Calculate Appropriate Optimize project configuration
Contingency Targets and shareholder value.
CSC
Excellence In Risk Management
Objective April 2005
Three Techniques are available that address different levels of
Risk Management
Qualitative Range Estimating Quantitative Analysis
Identify key project risks Calculate Appropriate Optimize project configuration and
Contingency Targets shareholder value.
Large Group – Consensus Based Small group Consensus based Broad Expert Group with
or individual interviews judgment based assessment.
(Template driven).
CSC
Excellence In Risk Management
Assessment April 2005
Three Techniques are available that address different levels of
Risk Management
Qualitative Range Estimating Quantitative Analysis
Identify key project risks Calculate Appropriate Optimize project configuration and
Contingency Targets shareholder value.
Large Group – Consensus Based Small group Consensus based or Broad Expert Group with judgment
individual interviews (Template based assessment.
driven).
Considers the fixed execution Considers the project execution Considers all strategic options,
plan, assumptions and some plan and assumptions. execution plans and external
risks.
external risks.
CSC
Excellence In Risk Management
Scope April 2005
Three Techniques are available that address different levels of
Risk Management
Qualitative Range Estimating Quantitative Analysis
Identify key project risks Calculate Appropriate Optimize project configuration and
Contingency Targets shareholder value.
Large Group – Consensus Based Small group Consensus based or Broad Expert Group with judgment
individual interviews (Template based assessment.
driven).
Considers the fixed execution Considers the project execution Considers all strategic options,
plan, assumptions and some plan and assumptions. execution plans and external risks.
external risks.
No Modeling Tool-Driven Modeling focusing Custom Integrated modeling
on one aspect of project (Cost, highlighting cross impacts from
Schedule or Economics). project areas.
CSC
Excellence In Risk Management
Modeling April 2005
Three Techniques are available that address different levels of
Risk Management
Qualitative Range Estimating Quantitative Analysis
Identify key project risks Calculate Appropriate Optimize project configuration and
Contingency Targets shareholder value.
Large Group – Consensus Based Small group Consensus based or Broad Expert Group with judgment
individual interviews (Template based assessment.
driven).
Considers the fixed execution Considers the project execution Considers all strategic options,
plan, assumptions and some plan and assumptions. execution plans and external risks.
external risks.
No Modeling Tool-Driven Modeling focusing Custom Integrated modeling
on one aspect of project (Cost, highlighting cross impacts from
Schedule or Economics). project areas.
CSC
Excellence In Risk Management
Correlation April 2005
Three Techniques are available that address different levels of
Risk Management
Qualitative Range Estimating Quantitative Analysis
Identify key project risks Calculate Appropriate Optimize project configuration and
Contingency Targets shareholder value.
Large Group – Consensus Based Small group Consensus based or Broad Expert Group with judgment
individual interviews (Template based assessment.
driven).
Considers the fixed execution Considers the project execution Considers all strategic options,
plan, assumptions and some plan and assumptions. execution plans and external risks.
external risks.
No Modeling Tool-Driven Modeling focusing Custom Integrated modeling
on one aspect of project (Cost, highlighting cross impacts from
Schedule or Economics). project areas.
Project Team, Constructors, and Project Team, Constructors, and Project Team, Owners,
EPCM Contractors. EPCM Contractors Stakeholders, Constructors &
EPCM Contractors.
CSC
Excellence In Risk Management
Audience April 2005
Properly conducted risk analysis builds on the early tools used for
qualitative analysis (KT, SWOT) and range estimation to include all the
risk and opportunity impacts on a project or decision.
Qualitative Range Quantitative
Comprehensive Risk Envelope for decision making
Outcome Uncertainty
(Cost, Schedule or Economic)
CSC
Excellence In Risk Management April 2005
Five Levels of Risk Management Maturity*
Level 1:
Success depends on the competencies and heroics of individuals
Ad Hoc
CSC
Excellence In Risk Management April 2005
A rigorous process is applied consistently to evaluate all projects
Recycle to Focus on
Most Important Risks
Tactical
Strategic
CSC
Excellence In Risk Management April 2005
Presentation Agenda
(5) Summary
CSC
Excellence In Risk Management April 2005
Risk Analysis is the centerpiece of a Risk Management Process
Base Design
& Operating Plans
Risk
Monitoring
System
Tornado Diagrams
Probability Step Diagrams
Distributions Interview Issues Model and Test Options
Project Targets Immediate Risk Contingency Plans
Control Measures
CSC
Excellence In Risk Management April 2005
Project Targets
The probability distribution illustrates the full
range of project uncertainty and is used to set the
project targets at appropriate confidence levels.
90% Note:
Confidence Level 1. Each point on the curve is a result from
P80 (?)
a single Monte Carlo trial. The expected
value represents the average value of all
Probability
the trials.
Expected
50% Value * 2. The slope of the 10/90 range represents
Downside the uncertainty, the flatter the curve, the
Risk
Upside more uncertainty.
Opportunity
3. The curve below the expected value
indicates upside opportunity, the
10% portion above shows the downside risk.
10/90 Range
CSC
Excellence In Risk Management April 2005
Project Targets
Probability distributions illustrate opportunity and risk trade-
offs, and can be used to select the best project option.
Option A
90%
Option B
Upside
Expected
Opportunity
Value
Probability
50% *
Option B has slightly more risk
Downside
Risk with a much greater upside
opportunity.
10%
Days
Start Date -60 -40 -20 0 20 40 60
Road Preparation Duration 3 6
Labour Productivity Delays -1.25 1.75
Plant Pad Preparation Duration 3 6
Labour Unrest Delays 0 2.3
Execution Organization Performance Best Worst
Regulatory Duration 11.3 16.5
Competing Project Environment Low Heated
Start-up & Commissioning Duration (Early Steam) 1.5 2.4
Terms of Reference - Duration 3 4
Regulatory Environment Relaxed Stringent
Terms of Reference - Application Date 1-Aug-02 1-Oct-02
Labour Availability Delays 0 1.4
OTSG Manufacture & Delivery Duration 12 16
Weather Delays 0 0.5
Long Lead Equipment Delays -1 2
EV = 20-Dec-07
CSC
Excellence In Risk Management April 2005
15-Aug-07
15-Nov-07
01-Dec-07
15-Dec-07
CSC
15-Sep-07
15-Oct-07
01-Jan-08
1-Nov-07
1-Sep-07
1-Oct-07
Excellence In Risk Management
+6
AFE Approval
Base= 03-Sep-07
+13
Engineering to 60%
+7
Preliminary Vendor Data
Module Assembly
Last Process Area Module
0
On-site to Construction
Complete
Start Date
Evaporator Units
0
Vapour Compressors
0
Piling
+14
Commissioning Duration
-3
Start-up Duration
+31
Construction Duration
+5
Materials Delivery
+5
Weather Delay
+12
Labour Issues
+14
Long Leads
EV= 20-Dec-07
Complete to MC
+5
Labour Productivity
April 2005
+3
Reworks
Immediate Risk Control Measures
A complete risk register considers all sources of information
available for the project uncertainties.
Risk Register
CSC
Excellence In Risk Management April 2005
Contingency Plans
The analysis can be used to evaluate impacts of schedule
risks, and test mitigation steps to show the potential for
schedule advancement. Incremental mitigation can be
applied to reach an acceptable target date.
100%
90%
80% Mitigated
EV = 21-Feb-04
70%
Base
60% EV = 1-Nov-04
50%
40%
Unconstrained
30% Fix Filing Date (-120 days)
20% Early Application (-40 days)
10% No JV Delays (-60 days)
No Staffing Delays (-30 days)
0%
1-Jan-03 1-Jan-04 1-Jan-05 1-Jan-06 1-Jan-07
CSC
Excellence In Risk Management April 2005
Risk Monitoring System
Use of risk analysis throughout the project life helps the
project team to focus on the most important risks for each
stage of development, resulting in a better defined project
(i.e. less risk).
90%
70%
Probability
Definition
EV = 528 $MM Project AFE
50% EV = 697 $MM
Planning
EV = 460 $MM
Mid-Construction
EV = 669 $MM
30%
Start Up
EV = 695 $MM
10%
CSC
Excellence In Risk Management April 2005
Presentation Agenda
(5) Summary
CSC
Excellence In Risk Management April 2005
Mining Issues and Problems – Key Uncertainties
CSC
Excellence In Risk Management April 2005
Strategy Table for Country Risk Analysis
Decisions
Strategy Country Commodities Mining Processing Smelting Markets
Extraction &
Refining
Increasing Canada Polymetallic Open Pit Heap Leach In Country
Reserves In Country:
onsite
CSC
Excellence In Risk Management April 2005
Portfolio Management to select best mining project
Environmental
Performance
Exploration/ Mech.
Acquisition
AFE Duration Duration
Socio-Cultural Duration
Environment
Pre- Project First
Acquisition
Acquisition Execution Production
Discount
Political Local Labour
Extraordinary Rate
Climate Benefits Productivity
Costs CAPEX
Project
Infrastructure
Acquisition/ Labour NPV
Material Bulks Costs
Exploration & Equipment Costs
Costs Costs Fixed OPEX
Energy & Costs
Utility Costs
Smelting &
Refining Costs Variable Revenue
Chemical Costs
Environmental
Performance Costs
Commodity
Expropriate Price
Taxes & Fiscal Closure
Royalties Terms
Closure
Cost
CSC
Excellence In Risk Management April 2005
Portfolio Management
100%
90%
80%
Canada
Probability
70% Russia
EV = $147 MM
EV = -$415 MM
60%
50%
40%
30% Indonesia
EV = $48 MM
20%
10%
0%
-1500 -1000 -500 0 500 1000 1500
CSC
Excellence In Risk Management April 2005
Portfolio Management
1000
Indonesia Payout
EV = 2014
-500
-1000
2000 2005 2010 2015
CSC
Excellence In Risk Management April 2005
Portfolio Management
The Tornado Diagram highlights the key drivers for the option
and identifies areas to focus mitigation efforts to ensure success
$MM NPV @ 12%
-100 0 100 200 300 400
Political Climate
Daily Production
Socio-Cultural Environment
Taxes & Royalties
Au Grade
Cu Price
Acquisition / Exploration Costs
Environmental Performance
Au Price
Labour Costs
Zn Recovery Rate
Zn Grade
Chemical Costs
Ramp-up Duration
Local Benefits
EV = $147 MM
CSC
Excellence In Risk Management April 2005
Development – capital cost for a mining project
Bid
Rate
$ 5 MM
Shaft
Excavation $ 60 MM
Competing
Materials/ Mine
Projects $ 40 MM
Estimate
Variance Level
Excavation
Labour $ 15 MM
Rate
Subsurface
Equipment
Scope
Variance $ 60 MM $ 160 MM
Used Mill Total
Equipment Project
Labour CAPEX
Productivity $ 5 MM
Roads $20 MM
Organization
Performance Infrastructure Exchange
Rate
Local
Benefits Water Miscellaneous
Cost
Variance $ 5 MM $ 10 MM
$1.5 MM/yr $3 MM
Engineering
Cost Sustaining
Capital Administration $ 20 MM
Variance $ 15 MM
EPCM Indirects
CSC
Excellence In Risk Management April 2005
Development - CAPEX
Expected Value
60% CAPEX = $175 MM
CAPEX ($MM)
CSC
Excellence In Risk Management April 2005
Development - CAPEX
$175 MM
CSC
Excellence In Risk Management April 2005
Presentation Agenda
(5) Summary
CSC
Excellence In Risk Management April 2005
Modern Day Applications of Risk Analysis
to Mining Issues and Problems
• Risk management is fundamental for accountability on corporate
governance and on maximizing shareholder value.
It begins with strategic definition and continues in a consistent manner throughout
the project life cycle. The earlier risk management starts, the earlier you can avoid
or mitigate risks and capture opportunities.
CSC
Excellence In Risk Management April 2005