TENDER DOCUMENT
FOR
ELEVATOR WORKS
Of
Volume - 1
Notice Inviting Tender , Instructions to Tenderers, Special
Conditions of Contract & Labour Welfare Rules
Institue of Liver & Biliary Sciences (Including Nurses & Intern’s Hostel) AT
ILBS,D-1,Vasant Kunj,Delhi-110070
VOLUME – 1
VOLUME – 2
1 Special Specifications
VOLUME – 4
1 Bill of Quantities
VOLUME – 5
1 Tender Drawings
VOLUME – 6
CONTENTS
SECTION 1
NOTICE INVITING TENDER
1.1 GENERAL
1.1.1 NAME OF WORK:
Delhi Metro Rail Corporation (DMRC) Ltd. invites sealed tenders in Two Packages
(Technical Package & Financial Package) from Pre-Qualified/Shortlisted Tenderers for
“Design ,Manufacturing , Supply , Installation & Commissioning of 24 nos. elevator
Works of ILBS Phase- 2 (Institute of Liver & Biliary Sciences) at D-1 , Vasant Kunj , New Delhi-
110070”( Including Elevators at Nurses & Interns Hostel).
Both Criteria i.e (a) & (b) as mentioned above , are Mandatorily required to be
separately qualified/passed by the Tenderer for becoming eligible to be
considered for evaluation.
Delhi Metro Rail Corporation (DMRC) Ltd. invites sealed tenders for the above
mentioned work (Clause 1.1.1).
Approximate cost of work Rs. 10.51 Crores (Ten Crores Fifty One
Lakhs only) (The estimated cost of the work
is inclusive of all taxes and duties). However
Custom Duty Exemption is available (
Annexure-C of ITT, ITT page 61 of 61) and
Tenderer is required to Follow Clause
10.6 of ITT in this regard.
Tender Security Amount Rs. 10.51 Lakhs (Rupees Ten Lakhs Fifty
One Thousand Only )
Cost of Tender Form Rs. 21,000/- (Rupees Twenty One
Thousands Only)
(Non-refundable) including 5%
DVAT
Completion period of the Work 12** Months from Issue of LOA (Letter of
Acceptance)
Tender Documents on Sale From 21/12/2010 to 28/12/2010 from 10:00
hrs to 17.00 hrs. on all Working Days except
Saturdays and On Saturday from 10:00 hrs
to 13:30 hrs
Date of Pre-Bid Meeting 14/01/2011 at 11:00 hrs
Date and Time of Submission of 27/01/2011 up to 11.00 hrs.
Tender
Date and Time of Opening of 27/01/2011 at 11.05 hrs.
Tender
** - The Completion Period of 6 nos. of Lifts ( including of 4 Lifts of Nurses &
Intern’s Hostel) will be 6 months from Date of Issue of LOA, while for the
Remaining 18 nos. of Lifts, Completion Period shall be 12 months from Date of
Issue of LOA .
The Tender Documents (One set, non-transferable) can be obtained from the Office of
Chief Electrical Engineer (IT & PD), CPM/C Office , Shastri Park Depot, New Delhi-
110053. Payment shall be made by Demand Draft drawn in favour of DMRC Ltd.
payable at New Delhi.
1.2 POINTS TO BE NOTED
1.2.1 Works envisaged under this contract are required to be completed in all respects
within the period of completion mentioned above.
1.2.2 Deleted
1.2.3 Deleted
1.2.4 Tender documents consist of
Volume 1-
- Notice Inviting Tender (NIT)
– Instructions to Tenderers (ITT)
– Special Conditions of Contract (SCC)
– Labour Welfare Rules
Volume 2
– Special Specifications
Volume 3
_ Not Used
Volume 4
– Bill of Quantities
Volume 5(Drawings)
– Tender Drawings
Volume 6
- Conditions of Contract on Safety , Health & Environment
- General Conditions of Contract
1.2.5 The Contract shall be governed by the documents listed in para 1.2.4 above and CPWD
specifications.
1.2.6 The Contract shall be governed by DMRC’ General Conditions of Contract (GCC) and the
documents listed in Para 1.2.4 above. GCC shall be deemed to be part of the Contract
Agreement.
1.2.7 The Tenderers may obtain further information in respect of these Tender Documents from
the Office of Chief Electrical Engineer (IT & PD), Shastri Park Depot, Shastri Park Delhi-
53.
1.2.8 All Tenderers are hereby cautioned that Tenders containing any material deviation or
reservation as described in Clause 24.0 of “Instructions to Tenderers” and/or minor
deviation without quoting the cost of withdrawal, shall be considered as non-responsive
and shall be summarily rejected.
1.2.9 DMRC reserves the right to accept or reject any or all proposals without assigning any
reasons, No tenderer shall have any cause of action or claim against the DMRC for
rejection of his proposal.
1.2.10 Late or Delayed Tenders shall not be accepted under any Circumstances.
SECTION- 2
SCOPE OF WORK
2.1 GENERAL
2.2.1.1 Deleted
2.2.1.2 Deleted
2.2.1.3 Deleted
2.2.1.4 SCOPE OF ELEVATOR WORKS
The Scope of Work under this contract shall include Design, Manufacture, Testing at
Manufacturer’s works, Supply, Transportation, Delivery, Storage, Erection, Site Testing
& Commissioning of Elevator Works & other provisions as stipulated in General
Conditions of Contract (GCC), Special Conditions of Contract (SCC), Specifications,
Drawings, Bill Of Quantities & other Tender documents comprising of but not
restricted to:-
IV) Integration with Building Management System & Fire Detection System.
V) All required Drawings preparation & its approval, Obtaining the Fire Clearance
Certificate from Fire authorities and all other Statutory approvals Sanction and
Lift Safety Certificate of Elevator Systems from Lift Inspectorate & other
authorities.
Scope of Work shall also include all Civil Works as indicated in the Bill of
Quantities and also not covered in Interface document ,Section 5 of NIT
associated with Elevator Works and making and painting the Civil Works as
required.
- Maintenance of the area during implementation stage for multi Storey Building
and surrounding area De-mobilisation, clearing of all Temporary Works and
Facilities after completion of job.
- Scope of Work shall also include obtaining all Statuary & Mandatory Permissions
/ Clearances / Approvals from the concerned authorities for Commissioning of the
Installations complete as stipulated is Para 6 of Special Conditions of Contract -
Part II.
- The Contractor shall include the Supply of entire material in accordance with
specification and whole of the work necessary for the complete installations as
set down in the specification and with the accompanying schedules & drawings .
Material & Components not specifically stated in the Specifications and / or
Bill of materials or not shown in the Drawings, but which are necessary for
satisfactory installation and Operations of the System, shall be deemed to
have been included in the Scope of Work.
- The contractor will have to suitably modify the Good for construction (GFC)
drawings and will prepare Shop drawings and all other drawings and will
put up for DMRC approvals at no extra cost. Where ever required the
contractor will carry out Design Calculation & will submit to DMRC for
approval.
-
- Any other item of work as may be required to be carried out for completing
the work under this Contract in all respects in accordance with the
provisions of the Contract and/or to ensure the safety of installation during
and after execution and its cost deemed to have been included in the
scope of work.
The Value of the Work shall be on Item Rates accepted in Letter of Acceptance
subject to such additions thereto or deductions there from as may be made under the
provisions of the Contract.
The Rates are inclusive of all Cost but not limited to the cost such as for Plants,
Equipments, Tools, All type of labours, Supervision, All materials from the source of
supplies as approved by Engineer/Employer including all lead and lifts, transport, all
temporary works, erection, maintenance, contractor’s profits & establishment /
overheads together with preparation of designs and drawings, all general risks, taxes,
royalties, duties, cess, octroi and other levies, insurance liabilities and all other
obligations set out or implied in the contract for completion of work except otherwise
specified in Bill of Quantities or elsewhere in the Tender documents.
2.2.1.4.4 Deleted
The Scope of Work for various interfacing works for other contracts shall be but not
limited to as described below:
2.2.2 Deleted
2.2.3 Deleted
2.2.4 Reference to the Standard Codes of Practice
2.2.4.1 The contractor shall make available at site all relevant Latest InternationaI and Indian
Standard Codes of practice, CPWD and MOST Specifications and IRS & IRC Codes
as applicable and other relevant British/German/American Standard.
Works to be performed shall also include all general works preparatory to the above
mentioned work for Elevator works and works of any kind necessary for the due and
satisfactory execution, completion and maintenance of the works to the intent and
meaning of the drawings adopted and technical specifications, to best Engineering
standards and orders that may be issued by the Engineer from time to time,
compliance by the agency with all Conditions of Contract, supply of all materials,
apparatus, plants, equipment, tools, fuel, water, transport, offices, stores, workshop,
staff, labour and the provision of proper and sufficient protective works, diversion,
temporary fencing, lighting and watching required for the safety of the public and
protection of works on adjoining land; first-aid equipment, sanitary accommodation for
the staff and workmen, effecting and maintenance of all insurances, the payment of
all wages, salaries, provident fund, fees, royalties, duties or the other charges arising
out of the erection of works and the regular clearance of rubbish, clearing up, leaving
the site perfect and tidy on completion.
2.2.7 Deleted
2.2.8 PRELIMINARY DRAWINGS
Preliminary drawings as listed in Volume -V represent Employer’s proposal based on
preliminary design. Detailed working drawings will be given for construction of
work subsequently
2.2.9 Deleted
2.3 TIME SCHEDULE
The agency shall submit with the tender "Time Schedule" for completion of various
portions of works. This schedule is to be within the overall completion period of 12
months from Letter of Acceptance. The Intermediate Milestones as mentioned in
Clause 28.0 of ‘Special Conditions of Contract’ are to be indicated specifically in the
Time schedule and these will have to be achieved. The Detailed Programme in the
form of a quantified bar chart or CPM Network shall include all activities from start to
completion for the Elevator Works as mentioned in clause 2.2.1 ,2.2.1.4, 2.2.1.4.1 &
2.2.1.4.2 above.
2.4 Deleted
SECTION 3
TENDER PRICES AND SCHEDULE OF PAYMENT
e. Deleted
f. Deleted.
g. Price variation for Elevator Works
Price variation is not applicable for this Tender of Elevator Works.
h. Deleted
3.1.3 Deleted
3.1.4 Deleted
3.1.5 Stage Payment for Elevator Works shall be made as per Clause 51.0 of Special
Conditions of Contract, Part-I, and Page 14 of 89 of SCC.
3.1.7 “In the event of exemption of custom duties and excise duties, sales tax/VAT or any other
cess /levy being granted by Government in respect of Works, the benefit of the same
shall be passed on to Employer. The Contractor shall maintain meticulous record of all
the taxes and duties paid and will provide the same as and when required by Employer,
so that the Employer is able to avail exemption/ reimbursement of same. Alternatively,
the Employer may direct the Contractor to get the reimbursements based on exemption
certificates/ Government’s order and it shall be obligatory on part of the contractor to
get the reimbursements from statutory authorities.” However , Custom Duty Exemption is
available for this Contract ( Annexure-C of ITT) , and hence Tenderer should quote
accordingly and further follow/comply Clause 10.6 of ITT , Vol.1
SECTION 4
SITE INFORMATION
4.1 WORK SITE
4.1.1 The project site is located in the National Capital Region of Delhi. The location of the
work and the general site particulars are shown in the General Arrangements
Drawings enclosed in the tender documents.
4.1.2 Instittute of Liver and Biliary Sciences (ILBS) is lacated at D-1 , Vasant Kunj, New
Delhi-110070
4.1.3 The contractor shall plan his works keeping in view restriction of approach and
availability of space and time.
4.2 GENERAL CLIMATIC CONDITIONS
4.2.1 The area in which the work lies is mostly plain terrain falling within latitudes 28°-20'
and 28°-45' North and longitudes 76°-56' and 77°-20' East.
4.2.2 The recorded highest and lowest temperatures in the past 10 years are 45.8 degree
Celsius and 2.4 degree Celsius respectively.
4.2.3 Summer season is from April to June and winter season is from November to March.
4.2.4 Mean average annual rainfall in the area over a five-year period is of the order of 735
mm, a good portion of which is concentrated during July to mid September, when
about 75% of the annual rainfall occur. The heaviest rainfall recorded during 24-hour
period is 191 mm.
4.3 SEISMIC ZONE
Delhi falls in Seismic Zone IV. Earthquake of Maximum Magnitude VIII on Modified
Mercalli scale has been experienced in the past, in the region.
4.4 FURTHER WORKS
4.4.1 Deleted.
4.4.2 Deleted
4.5 Deleted
SECTION 5
INTERFACE DOCUMENTS
(xii) The Elevator contractor shall issue their detailed construction schedule to the
Civil/Electrical contractor before start of the project with those activities
highlighted in red which cannot be taken up by Elevator contractor unless
Civil/Electrical contractor complete his work.
(xiii) The Elevator contractor shall critically go through detailed construction
schedule of Civil/Electrical/HVAC works in order to plan their work so that
activities of Civil/ Electrical/HVAC contractor do not lag behind their schedule.
The Elevator Contractor shall make the detailed work programme based on the
Access dates given by the Civil/Electrical/HVAC contractor.
(xiv) As per the requirement of Elevator Contractor for bringing the materials at Site,
Civil Contractor shall provide suitable Temporary Roads & Paths as necessary.
• Civil Contractor
• HVAC Contractor
• Electrical,LV System & Fire Fighting Contractor
• Plumbing Contractor
• Any other Contractor
a Deleted
c) The Contractor Shall interface with and co-ordinate activities with the other
contractors and his Sub-Contractors and shall keep the Employer’s representative
fully informed in respect of such interface, such information being given to the
Employer’s Representative in a manner and form at such intervals as required by
the Employer’s Representative.
i) The Contractor shall jointly with the other Contractors develop, update and
execute an Interface Management Plan in consultation with
Civil/Electrical,LV System/& Fire Fighting/HVAC Works Contractor after the
Commencement of work and throughout execution of the work to ensure
that.
ii) All interface issues with other Contractors are satisfactorily identified and
resolved and
e) All the Construction Tolerances at the Interface shall meet the requirements
of the Respective Specifications relating to Interface Points.
g) The Contractor has to Coordinate with Electrical,LV System & fire Fighting
Contractor for BMS Integration.
i) Each Software provided by the Contractor shall be Licenced & the Contractor
shall furnish the Valid Licence with Guarantee for free update at least for 10 years
from the Date of Commissioning.
Any Holes/Cutouts made in the Wall/Shaft etc. shall be furnished after completion
of work in an Approved Manner. Where-ever building portions are disturbed, they
shall be rectified and finished in a Manner as they were available before
commencement of the Work.
INSTRUCTIONS TO TENDERERS
INDEX
Clause Description Page
GENERAL………………………………………………………………………………… 3
1.0 Introduction……………………………………………………………………… 3
2.0 Post Qualification Requirements…………………………………………… 4
3.0 Cost of Tendering………………………………………………………………. 7
4.0 Site Visit…………………………………………………………………………. 7
TENDER DOCUMENTS………………………………………………………………… 7
5.0 Contents of Tender Documents………………………………………………. 7
6.0 Clarification on Tender Documents………………………………………….. 7
7.0 Amendment to Tender Documents………………………………………….. 8
PREPARATION OF TENDER………………………………………………………….. 8
8.0 Language of Tender…………………………………………………………… 8
9.0 Documents Comprising the Tender………………………………………… 8
10.0 Tender Prices…………………………………………………………………… 14
11.0 Currencies of the Tender……………………………………………………… 15
12.0 Tender Validity………………………………………………………………….. 15
13.0 Tender Security………………………………………………………………… 15
14.0 Not Used………………………………………………………………………… 16
15.0 Pre-Bid Meeting……………………………………………………………. 16
16.0 Format and Signing of Tenders………………………………………………. 16
SUBMISSION OF TENDERS………………………………………………………….. 17
17.0 Sealing and Marking of Tenders……………………………………………. 17
18.0 Submission of Tenders………………………………………………………… 18
19.0 Late Tenders……………………………………………………………………. 18
20.0 Not Used. ………………………………………………………………………. 18
TENDER OPENING AND EVALUATION……………………………………………. 18
21.0 Tender Opening………………………………………………………………… 18
22.0 Process to be Confidential…………………………………………………… 19
23.0 Clarification of Tenders………………………………………………………... 19
24.0 Determination of Responsiveness…………………………………………… 20
25.0 Evaluation of Tender………………………………………………… 21
26.0 Correction of Error…………………………………………………………… 22
AWARD OF CONTRACT……………………………………………………………… 23
27.0 Award Criteria………………………………………………………………….. 23
28.0 Employer's Right to Accept any Tender and to Reject any or All Tenders 23
29.0 Notification of Award…………………………………………………………… 23
30.0 Signing of Agreement…………………………………………………………. 23
31.0 Performance Security…………………………………………………………. 24
Appendix I………………………………………………………………………………. 25
Index on Proforma of Forms………………………………………………… 27
Form of Tender (Form-A) with Appendix……………………………………………… 28
Form of Bank Guarantee for Tender Security (Form-B) …………………………… 32
Proforma for Statement of Deviations (Form-C) …………………………………… 34
Form of Performance Security (Form-D) …………………………………………… 37
(Guarantee) by Bank
Form of Agreement (Form-E) ………………………………………………………… 39
General Information and Joint Venture Data (Form T-I) …………………………… 41
Experience Record of Sub-Contractors (Form T-II) ……………………………… 42
Resources Proposed for The Project-Personnel (Form T-III) ……………………… 44
Proposed Site Organisation (Form T-IV) …………………………………………. 47
Resources Proposed for the Project-Plant & Equipment (Form T-V)………………. 48
Financial Data (Form T-VI) …………………………………………………………… 50
Tender Index (Form T-VII) …………………………………………………………… 53
Annexure – A………………………………………………………………………….. 44
Annexure – B ………….………………………………………………………………. 55
Annexure- C - ……………………………………………………………………………… 61
Elevator Works of ILBS (Institute of Liver & Biliary Sciences) , D-1 Vasant Kunj ,
Delhi-110070
INSTRUCTIONS TO TENDERERS
(GENERAL)
1.0 INTRODUCTION
1.1 Delhi Metro Rail Corporation (DMRC) Ltd. invites sealed tenders in Two Packages (Technical
Package & Financial Package) from Pre-Qualified/Shortlisted Tenderers for “Design ,Supply
,Manufacturing , Installation & Commissioning of 24 no. elevator Works of ILBS (Institute of
Liver & Biliary Sciences) , D-1 Vasant Kunj ,Delhi-110070
The Delhi Metro Rail Corporation Limited, hereinafter called the ‘Employer’, for Works in
accordance with this Tender Package. The Scope of Work under this contract shall include
Drawing & Design, Manufacture, Testing at Manufacturer’s works, Supply, Transportation,
Delivery, Storage, Erection, Site Testing & Commissioning of Elevator Works & other provisions as
stipulated in General Conditions of Contract (GCC), Special Conditions of Contract (SCC) & other
Tender documents comprising of but not restricted to.
The tender papers consist of the following documents, along with their Annexures,
appendices, addenda and errata if any.
Volume 1
- Notice Inviting Tender (NIT)
- Instructions to Tenderers (ITT)
- Special Conditions of Contract (SCC)
- Labour welfare Rules
Volume 2
Special Specifications
Volume 3
- Not Used
Volume 4
- Bill of Quantities (Elevator Works)
Volume 5 (Drawings)
- Tender Drawings
Volume 6
- Safety Manual
- General Conditions of Contract
Tenderers should procure CPWD specifications referred from the market.
Tenders shall be prepared and submitted in accordance with the instructions given herein.
1.2 Relevant address for correspondence relating to this tender is given below:
Chief Electrical Engineer (IT&PD),
1.3 Some essential data/requirements pertaining to this Tender along with reference to Clause
Number of this Volume where full details have been given are detailed below :
a. Tender Security to be furnished by the Tenderer (Clause 13.0) -----Rs. 10.51 Lakhs
(valid for 150 days from date of submission of tender submittal)
b. Pre-Bid meeting – Pre-Bid meeting will be held at 11:00 hrs. on 14/01/11 at Office of
Chief Electrical Engineer (IT&PD), Shastri Park Depot, Shastri Park,
c-i. Last date for submitting letter of Query/clarifications regarding this tender -- 08/01/2011
.
c-ii. Last date for issuing addendum and replying clarifications if any ------ 18/01/2011 .
d. Tenders will be accepted in the Office of Chief Electrical Engineer (IT&PD), Shastri Park
Depot, Shastri Park, up to 11.00 hrs. on. 27/01/2011. Late or Delayed tenders will not
be accepted under any circumstances..
e. Date and Time of Opening of Technical Package (Clause 21.0) - 11:05 hrs. on 27/01/11
f. Period for which the tender is to be kept valid (Clause 12.0) - 120 days from the date of
submission of Tender.
g. Period of Commencement of Work (Form A) - 7 days from the date of issue of "Letter of
Acceptance".
j. Validity Period for Performance Security (Form D) -- within one month of issue of LOA
and up to 6 months beyond the date of expiry of “Maintenance period” as per GCC
condition.
** - The Completion Period of 6 nos. of Lifts ( including of 4 Lifts of Nurses & Intern’s
Hostel) will be 6 months from Date of Issue of LOA, while for the Remaining 18 nos.
of Lifts, Completion Period shall be 12 months from Date of Issue of LOA .
2.1.1 The Open Tender for this Work had been invited in two Packages (Technical Package and
Financial Package)
2.1.2 Each agency shall submit only one tender EITHER HIMSELF OR AS a Lead Partner /Lead
Constituents in a Joint Venture/ Consortium. The Tenderer who submits more than one tender for
the same work will be disqualified.
2.1.3 This Tender has been invited from reputed Indian Manufacturers/contractors/Joint Venturers/Consortiums
only and all Plants, Materials and Services shall be to the Satisfaction of the Employer and Engineer. The
Payments will be made in INR as well in foreign currency as indicated by the Tenderer in case of
imported equipments. However, exchange rate shall be taken as per clause 10.10 of the ITT. The
information on Plant & Material included in the Tenderer proposals and incorporated into the Contract
Document shall not be construed as a submission to Engineer under the Contract. However, the
Tenderer should note the requirements for Transfer of Technology.
2.2.1 General information on the Tender shall be furnished in Form T-1. Copies of Original Documents
defining the constitution and legal status, certificate of registration and ownership, principal place of
business of the company, corporation, firm or partnership or, if a joint venture including consortium, of
each party thereto constituting the tenderer will also be required to be furnished. All the group members
in a joint venture will be jointly and severally responsible for the performance under the contract.
2.2.2 In the case of tender by a joint venture of two or more firms or companies as partners or as members of a
consortium as the case may be, joint venture data must be furnished in the format prescribed (Form T-1)
along with the documents as mentioned therein. The following requirements shall also be complied with.
a) the tender, and, in the case of a successful tender, the Form of Agreement, shall be individually signed so
as to be legally binding on all partners/constituents as the case may be.
b) in case of the partnership, one of the partners shall be nominated as being Incharge as Lead or Prime
partner and this authorization shall be evidence by submitting a attested/notarized copy of Power of
Attorney signed by the partner and Board Resolution or legally authorized signatories of all the
partners. In case of consortium, it will similarly authorize a person to be in-charge and this authorization
shall be evidenced by a power of attorney in favour of that person.
c) The partner in-charge or the person in-charge as aforesaid, shall be authorized to incur liabilities and
receive instructions for and on behalf of any and all the partners of the joint venture or constituent of the
consortium and the entire execution of the contract including payment shall be carried out exclusively
through the partner in-charge or joint venture and person in-charge of a consortium.
d) All partners of the joint venture or constituents of the consortium shall be liable jointly and severally for the
execution of the contract in accordance with the Contract terms and a relevant statement to this effect
shall be included in the authorization mentioned under (b) above, as well as in the Form of tender and the
Form of agreement (in case of successful Tender).
e) In the event of default by any partner in the case of the joint venture and constituent in the case of a
consortium in the execution of his part of the Contract, the partner/person in-charge will have the authority
to assign the work to any party acceptable to the Employer to ensure the execution of that part of the
Contract.
f) A copy of the Agreement entered into by the joint venture/consortium partner shall be submitted along
with the Tender.
2.2.3 In case the Tenderer is an Association, Consortium or Joint Venture, the tenderer shall provide the
following:
a) Nomination of one of the members of Association, Consortium or Joint Venture to be in-charge or Lead
Member. This authorization shall be issued by the legally authorized signatories of all members of the
Association, Consortium or Joint Venture.
b) Details of the intended percentage participation given by each member, with complete details of the
proposed division of responsibilities and corporate relationships among the individual members.
c) Each member of the Association, Consortium or Joint Venture shall be jointly and severally liable for the
undertaking of this Contract.
2.2.4 The Tenderers to qualify for award of Contract, shall submit a written power of attorney and Board
Resolution authorizing the signatory(ies) of the tender to commit the tenderer or each member of the
partnership, consortium or joint venture. IN case of foreign partners, power of attorney and Board
Resolution for such action shall be submitted duly notarized by the Notary Public in the country of origin
and stamped by Indian Embassy/High Commission.
2.3 Each page of tender shall be signed by the authorized signatory of the tenderer. Attested/notarized
copy of Power of Attorney and Board Resolution in favour of the signatory will be required to be
furnished as detailed in Clause 16.0.
2.4 Cancellation or creation of a document such as Power of Attorney, Partnership deed, Constitution
of firm etc., which may have bearing on the tender/contract shall be communicated forthwith in
writing by the tenderer to the Engineer and the Employer.
2.5 Deleted
2.6 Each tenderer, or any associate will be required to confirm and declare in the tender submittal that
no agent, middleman or any intermediary has been, or will be, engaged to provide any services,
or any other items of work related to the award and performance of this contract. They will have to
further confirm and declare in the submittal that no agency commission or any payment which
may be construed as an agency commission has been, or will be paid and that tender price will
not include any such amount. If the Employer subsequently finds to the contrary, the Employer
reserves the right to declare the tender as non-compliant and declare any contract if already
awarded to the tenderer to be null and void.
3.1 The agency shall bear all costs associated with the preparation and submission of his tender and
the Employer will in no case be responsible or liable for these costs, regardless of the conduct or
outcome of the tendering process.
4.1 Any site information given in this tender document is for guidance only. The tenderer is advised to
visit and examine the Site of Works and its surroundings at his/their cost and obtain for himself on
his own responsibility, all information that may be necessary for preparing the tender and entering
into a Contract. The visit should cover complete study of the site and understand the interfacing
requirement.
4.2 The agency shall be deemed to have inspected the Site and its surroundings beforehand and taken
into account all relevant factors pertaining to the Site in the preparation and submission of the
Tender.
5.2 The Tenderer shall not make or cause to be make any alteration , erasure or obliteration to the text
of Tender Documents.
6.2 A prospective tenderer requiring any clarification of the tender documents may notify the Engineer
in writing or by tele-fax at the Engineer’s mailing address indicated in Clause 1.2. The Engineer will
respond in writing to any request for clarification which he receives prior to dead line mentioned in
Clause 1.3. Written copies of the Engineer’s response will be sent to all prospective tenderers who
have received the tender documents. Only written communications/clarifications can be considered
as valid. Notwithstanding the above a pre-tender meeting would be held for consultations as per
Clause 15.0.
7.2 The said amendment in the form of an addendum will be sent to all prospective tenderers who have
received the tender documents, on or prior to last date mentioned in Clause 1.3. This
communication will be in writing or by telefax and the same shall be binding upon them. Prospective
tenderers should promptly acknowledge receipt thereof by telefax to the Engineer.
7.3 In order to afford prospective tenderers reasonable time for preparing their tenders after taking into
account such amendments, the Engineer or the Employer may, at his discretion, extend the
deadline for the submission of tenders in accordance with Sub-clause 18.1.
PREPARATION OF TENDER
8.1 The tender prepared by the tenderer and all correspondence and documents relating to the tender
exchanged between the tenderer and the Employer/Engineer shall be in the English language.
9.1.1 The technical package, clearly labeled TECHNICAL PACKAGE, will comprise:
(b) Notarized certified copy of Power of attorney along with the Copy of Board Resolution (as
per Clause 16.4 of ITT) in favor of authorized signatory of the tender.
(c) Deleted
(d) Deleted,
(I) Total value of “Elevator Works” done for the last five financial years along with list of all on-
going contracts may be given in the format prescribed (Form T-VI)
(II) Attested copy of the Registration Certificate and Clearance Certificate under Delhi VAT Act,
2005 is required to be submitted. The foreign based contractors shall be required to
submit the necessary document as applicable to them according to Delhi VAT Act 2005.
As per Delhi VAT Act, the party who is executing work in Delhi has to have registration
with DVAT authority of Delhi. If a tenderer from outside of Delhi intends to participate in
DMRC tender, he can be permitted provided he gives an undertaking to the fact that he will
get himself registered with Delhi VAT authorities, in the event of issue of letter of
acceptance to the tenderer and shall submit registration number before claming initial
advance or first payment whichever is earlier. In the absence of registration detail with
Delhi VAT Department, EPF authority, first payment shall not be released.
If Tenderer fails to provide “DVAT Registration & Clearance Certificate” during the
Tender Stage , The Tenderer must submit a declaration in writing under clear
signature that “ We confirm that if we are considered to award this contract , we
shall submit the DVAT Registration & Clearance certificate to DMRC within one
month of issue of letter of acceptance.”
All these volumes duly signed and stamped (and duly filled where required) are to be
submitted with technical package along with other documents. The Bill of Quantity (BOQ)
volume - 4 is to be submitted without Rates with technical package.
All the documents of Financial package with prices left blank has to be submitted in support
of the Financial Bid with Technical Bid Submittal. While in Financial Package submittal
these will be filled accordingly.
i. The general approach and methodology proposed for carrying out the services
covered in the Scope of Work, including such detailed information as deemed
relevant. Also, tenderer shall submit the preliminary scheme of sequencing and
erection methodology of the work.
A detailed overall work programme and a bar chart indicating the duration and timing of all
major activities including intermediate milestones as mentioned in clause no. 28.0 of
Special Conditions of Contract (SCC) Pt-I. Bar chart shall be made showing the activity to
be performed for along with duration of each activity.
(a) An organization chart proposed to be deployed for this work with assignment of each key
staff member (identified by name) duration and timing together with clear description of the
responsibilities of each key staff member within the overall work programme. The minimum
level of supervision and qualification/experience of site-staff is given under Annexure – B.
(b) The name, background and professional experience of each key staff member to be
assigned to the project, with particular reference to his experience of a nature similar to that
of the proposed assignment. The majority of the key staff shall be regular members of the
firm for at least six months (Form T-III and T-IV).
(c) The details of the name, background and CV of any Sub-contracted staff who will be
employed on the project (Form T-III and T-IV). Alternatively, tenderer should submit the
undertaking for deployment of staff/engineer for the project in the format provided in Form
T-III.
(d) Names and addresses of Sub-contractors who are proposed to be engaged for execution
of different types of works as well as the details of the experience and past performance of
such Sub-contractors will be required to be furnished in the format prescribed (Form T-II).
This information shall be given for all critical items of works on/off site irrespective of the
status of the Sub-contractors in the Tender. In case of sub-contractors the complete details
as per the format prescribed (Form T-II) will be furnished.
The Tenderer should note that he is required to clearly indicate how Works are proposed to
be executed and integrated:
The Elevator Contractors can execute the work of Eleavtors, in house from their own
sources or can get this work executed through reputed sub-contractors who have
experience of carrying out similar works. For this purpose, the Tenderer will submit
proposal for appointment of sub-contractors for each activity proposed to be sub-
contracted along with Tender-Document, complete with details of similar works carried
out by the sub-contractor, his staff strength, Credentials etc.
In case, DMRC does not consider the proposed Sub-contractor acceptable, the Tenderer
will be asked to propose alternate firm acceptable to DMRC.
The Tenderer has to very clearly & unambiguously give the details of activities to be Sub-
contracted and proposed Sub-contractors for the same with requisite details.
If Tenderer fails to provide the above information & documents at tender stage, firm
must submit declaration in writing that ‘we confirm that if we are considered to
award this contract, we shall follow all terms and conditions of DMRC for
deployment of sub-contractor and no sub-contractor shall be deployed without prior
approval of DMRC. We also confirm that all the required data/details regarding sub-
contractor shall be submitted to DMRC within one month of issue of letter of
acceptance’.
(e) Details of Plant & Equipment assessed as required for the Tendered Work as well as those
available as on date in the format prescribed (Form T-V). Major Plant & Equipments are to
be provided as per the minimum scale indicated in Form T-V.
(i) The tenderers shall submit their Corporate Quality Policy Document duly signed by the
corporate head or any other authorized person.
ii. The tenderers shall submit an OUTLINE Quality Plan, illustrating the intended means of
compliance with Volume 2, Special Specifications for the work including project quality
requirements and setting out in summary form an adequate basis for the development of
the more detailed document. The Outline Quality Plan shall contain sufficient information to
demonstrate clearly the proposed method of achieving the Tenderer’s Quality objectives
with regard to the requirements of the contract and shall, as a minimum, address the quality
system elements as required by ISO 9001– 1994 – “Model for Quality Assurance in Design,
Development Procurement, Installation and Servicing”.
Details of the quality assurance system and organization to enforce the same (Tenderer
may furnish the details in a narrative form).
iii. The contractor shall also associate for the checks conducted by DMRC / nominated
agencies for the QA and take necessary steps for improvement/ confirmation.
iv. If Tenderer fails to provide the above information/documents at tender stage, firm
must submit declaration in writing(as required in clause-11 of Form-A of ITT) that
“‘we confirm that if we are considered to award this contract ,the ‘Quality Assurance
Plan” adopted by us shall be in conformity with Quality Assurance Plan requirements
as detailed in Appendix-II of Pt-III of Special Condition Of Contract( Volume-1) and
required documents shall be submitted to DMRC within one month of receive of
Letter of Acceptance’.
i. The tender shall submit as part of his tender on Outline Environment Plan
illustrating the intended means of compliance with Appendix III and V of SCC –
Part III and setting out in summary form an adequate basis for the development
of the more detailed document to be submitted under sub clause (iv) of this
clause. The Outline Environmental Plan shall contain sufficient information to
demonstrate clearly the proposed method of achieving the tenderer’s
environmental objectives with regard to the requirement of the contract.
ii. The Outline Environmental Plan shall be headed with a formal statement of policy
in relation to Environmental Protection and signed by their corporate head or
authorized representative. The Outline Environmental Plan shall include the
methods and procedures for monitoring Environment Impact of works under the
contract.
iii. The Site Environmental Plan shall include detailed policies and procedures which when
implemented, will ensure compliance with Appendix III and V of SCC – Part III.
i. The tenderer shall submit as part of its tender, an OUTLINE Safety Plan which shall
contain sufficient information to demonstrate clearly the tenderer’s proposals for
achieving effective and efficient safety procedures. The Outline Safety Plan should
include an outline of safety procedures and regulations to be developed and the
mechanism by which they will be implemented for ensuring safety as required by
Appendix VI of SCC – Part III.
ii. The Outline Safety Plan shall be headed with a formal statement of [policy in relation to
safety and shall be sufficiently informative to define the tenderer’s safety plans and set
out in summary an adequate basis for development of Site Safety Plans.
iii. The form and content of Site Safety Plan shall be in accordance with Appendix VI of
SCC – Part III and shall include detailed policies, procedures and regulations which,
when implemented, will ensure compliance with Appendix VI of SCC – Part III.
iv) The contractor should associate themselves with any Safety checks undertaken by
DMRC or any agency nominated by DMRC for Safety and take necessary steps for
improvement / confirmation.
9.1.4 Deviation statement Form C-1 (Without Price), C-2 ,C-3 duly filled & signed.
9.1.5 The Bill of Quantity (BOQ) volume - 4 is to be submitted without Rates with technical
package.
9.1.6 Deleted
9.1.7 Tenderer shall also duly fill/submit the Mandatory Eligibility Criteria as listed in
Annexure-1 to ITT ( Page 56 of 61 ,ITT) & appendices thereof . Before Detailed
Technical Evaluation of the Tender, the Technical/Financial Criteria as laid down
in Annexure-1 to ITT & appendices thereof will be evaluated. Any Tenderer not
meeting the technical or financial requirements as indicated in Annexure-1 to
ITT& appendices thereof will not be considered eligible and further Evaluation
of Tenderer will not be done .
The financial package, clearly labeled FINANCIAL PACKAGE will contain the following:
ii. Deleted
iv Deviation statement Form C-1 With Price duly filled & signed.
9.2.2 The financial proposal should be separately completed and submitted in a separate
sealed envelope. The prices shall be entered in the Form of Tender and the BOQ
enclosed. These prices should include all costs associated with the contract All
Documents Should be in Duplicate and properly marked i.e. one original and one Copy.
9.3 Documents to be submitted by the tenderer under technical and financial packages have
been described under the respective Clauses 9.1 and 9.2. This list of documents has
been prepared mainly for the convenience of the tenderer and any omission on the part of
the Employer shall not absolve the tenderer of his responsibility of going through the
various clauses in the Tender
Documents including the specifications and to submit all the details specifically called for (or
implied) in those clauses.
9.4 All documents issued for the purposes of tendering as described in Clause 1.1, and any
amendments issued in accordance with Clause 7.0 shall be deemed as incorporated in the Tender.
9.5 Deleted
10.1 The tenderer is required to quote for all the items as per tender documents.
10.2 Rates / cost quoted should include all taxes , duties ,octroi , surcharges, cost of insurance
and other liabilities
10.3 The rate for each item shall be reasonable and not unbalanced. If the Engineer/ Employer come
across any unbalanced rates, he may require the tenderer to furnish detailed analysis to justify the
same. If after its examination, the Engineer/ Employer still feels the rates to be unbalanced, he may
ask the tenderer for additional Performance Security or other safeguards to protect Employer’s
interest against financial loss. Should the tenderer fail to comply with this, his tender shall be liable
to be rejected by the Employer, who may award the Contract to any other tenderer.
10.4 The tenderer shall keep the contents of his tender and rates quoted by him confidential.
10.5 The tenderer shall utilize Indian labour, staff and materials to the maximum extent possible in
execution of Works.
10.5.1 Rates/cost quoted should include all taxes , duties and surcharges insurances etc.
10.6 “In the event of exemption of custom duties and Excise duties, sales tax/VAT or any other
cess /levy being granted by Government in respect of Works, the benefit of the same shall be
passed on to Employer. The Contractor shall maintain meticulous record of all the taxes and
duties paid and will provide the same as and when required by Employer, so that the
Employer is able to avail exemption/ reimbursement of same. Alternatively, the Employer
may direct the Contractor to get the reimbursements based on exemption certificates/
Government’s order and it shall be obligatory on part of the contractor to get the
reimbursements from statutory authorities.”. However, Custom Duty Exemption is available
for this Contract in terms of Condition No. ‘77’ of Notification No. 21/2002-Cus. dated
01/03/2002 , issued by Customs Department ( Enclosed Annexure-C, ITT page 61 of 61) and
hence Tenderer will be mandatorily required to comply with the above provision, in case,
Tender is awarded .
10.7 Deleted
10.8 Deleted
10.9 Basic Amount is given in the summary sheet of Bill of Quantities. Tenderer has to quote a
single percentage Above / Below of the Basic Amount for Elevator Works
10.10 The Term CIF shall be governed by the rules in the current edition of Incoterms published by
the International Chamber of Commerce,38 Cours Albert Ier, 75008,Paris, France.
10.11 For the purpose of comparative evaluation of offers, all tender prices will be converted to Indian
Rupees by using the exchange (selling) rates for those currencies at the close of Business of the
State Bank of India 28 days before the latest date for submission of Tenders.
10.12 Deleted
10.13 Tender Price should be complete in all respect covering all activities and including Design , Drawing
, Supply , Erection , Testing , Commissioning & Overall Satisfactorily Operation of
Plant/Units/System, as mentioned in tender documents and If any Item Required for completion
of the work and not mentioned will be deemed to have been included in Scope of Work.
11.1 Tender prices shall be quoted in Indian Rupees only. In case of the Imported Equipments the
break-up of Tender Price in Freely convertible International Trading Currency and INR as per Bill of
Quantity shall be given.
12.1 The tender shall remain valid and open for acceptance for a period of 120 days from the Last date
of submission of tender.
12.2 In exceptional circumstances, prior to expiry of the original tender validity period, the Employer/the
Engineer may request the tenderers for a specified extension in the period of validity. The request
and the response thereto shall be made in writing or by telefax. A tenderer may refuse the request
without forfeiting his tender security. A tenderer agreeing to the request, shall not be required or
permitted to modify his tender but will be required to extend the validity of his tender security
correspondingly.
13.1 The tenderer shall furnish, as tender security, an amount as mentioned in Clause 1.3.
13.2 The tender security will be in the form of a Bank Guarantee from a Scheduled Commercial bank
based in India. The format of the Bank Guarantee shall be generally in accordance with the sample
form of tender security (Form B) included in this volume of tender documents. Other formats may
be permitted subject to the prior approval of the Employer. Bank guarantees shall be irrevocable
and operative for a period not less than 30 days beyond the validity of the tender ( 150 days from
the date of tender). The Tender Security shall be endorsed/pledged in favour of the Employer and
shall be submitted in a separate envelope superscribed “Tender security for----- ----(Name of Work
as mentioned under Clause 1.1.1 of NIT) --------------".
13.3 Any tender not accompanied by an acceptable tender security will be summarily rejected by the
Employer/Engineer as non-responsive.
13.4 The tender securities of unsuccessful tenderers shall be discharged/returned by the Employer as
promptly as possible but not later than 30 days after the expiration of the period of tender validity as
defined in Clause 12.0. In this connection, Clause 29.3 may also be referred to.
13.5 The tender security of the successful tenderer shall be returned upon the tenderer executing the
Contract Agreement after furnishing the required performance guarantee for performance, as
mentioned in Clause 31.0.
b. if the tenderer does not accept the correction of his tendered price in terms of Clause 26.0,
or
i. furnish the necessary performance guarantee for performance as per Clause 31.0
and/or
i. enter into the Contract within the time limit specified in Clause 30.0
13.7 No interest will be payable by the Employer on the tender security amount cited above.
15.0 PRE BID MEETING: - A Pre-Bid meeting ,open to all intending tenderers may be held to discuss
the issues referred in Clause 1.2 of Special Conditions of Contract.
16.1.1 If the tender is submitted by a proprietary firm it shall be signed by the proprietor above his full
name and the full name of his firm with its current address.
16.1.2 If the tender is submitted by a firm in partnership, it shall be signed by a partner holding the power
of Attorney for the firm. A certified copy of the Partnership deed and power of attorney shall
accompany the tender. Alternatively, it shall be signed by all the partners.
16.1.3 If the tender is submitted by a limited company or a limited corporation, it shall be signed by a duly
authorized person holding the power of attorney for the firm. A certified copy of the power of
attorney shall accompany the tender.
16.1.4 If a Tender is submitted by a Joint Venture or Consortium of two or more Firms, it shall submit
complete information pertaining to each Firm or Joint Venture or Consortium and state along with
the Tender as to which one of the firms shall have the responsibility for Tendering and for
Completion and due performance of the Contract. Full information & Satisfactory evidence
pertaining to participation of each Member of the Joint Venture or Consortium in the Tender shall be
furnished along with the Tender. All Members shall be jointly and severally responsible for all
aspects of the Tender and the Consequent Contract. Provision under Clause 2.2 may be referred to
in this connection.
16.2. The documents required to be submitted by the Tenderer will be as described under Clause 9.0
herein.
16.3 Entries to be filled in by the Tenderer shall be typed or written in indelible ink. Each page of such
document should be signed in full at the bottom by the person submitting the Tender along with the
date of signing. Each page of printed documents should be initialled at the bottom by the person
submitting the tender along with the date of initialling.
16.4 In case of all documents listed in Clause 9.0 above, the person signing/initialling the documents
shall be one who is duly authorized in writing by or for and on behalf of the Tenderer and/or by a
Statute Attorney of the Tenderer. Such authority in writing in favour of the person signing the tender
and/or notarially certified copy of the Power of Attorney as the case may be, shall be enclosed
along with the tender.
16.5 The complete tender shall be without alterations, overwriting, interlineations or erasures except
those to accord with instructions issued by the Employer, or as necessary to correct errors made by
the tenderer. All amendments/corrections shall be initialled by the person or persons signing the
tender.
16.6 All witnesses and sureties shall be persons of status and probity and their full names, occupations
and addresses shall be written below their signatures.
16.7 For the purpose of Clause 16.1.3 and 16.1.4, firm shall mean and include proprietary firm and
Partnership firm and company or Corporation.
SUBMISSION OF TENDERS
17.1.1 Tender will be submitted in Two sets. One marked “Technical Package”, and 2nd marked “Financial
Package”
17.1.2 Each set will further contain to Sets marked “Original” and “ COPY” and both will be sealed in
separate two envelopes and then both in one common large envelop marked TECHNICAL
PACKAGE or FINANCIAL PACKAGE as case may be.’. All the two envelopes shall be wrapped
in an outer envelope addressed to The Chief Electrical Engineer (IT&PD), DMRC duly super
scribing on top, tender number, name of work, time and date for submission and time and date for
opening. The envelope should also bear the name and address of the tenderer.
171.3 The contents of Technical Package and Financial Package shall be as detailed under Clauses 9.1 and
9.2 herein. Power of attorney and Tender Security shall also be submitted in separate envelops as
mentioned in Clause 9.1.1.
17.2 No responsibility will be accepted by the Employer/Engineer for the misplacement or premature
opening of a tender, not sealed or marked as per aforesaid instructions.
17.3 Two copy of all the tender documents one original & one Copy, including (i.e. Vol-1,2,4,5,6)
tender drawings and addenda thereto, with each page signed and stamped required to be
submitted with Technical Package to confirm Acceptance by tenderer of the contents.
Volume -4 (i.e. BOQ) is to be submitted unfilled without cost with technical submittal.
Chief Electrical Engineer (IT&PD), Office of CEE/IT&PD, Shastri Park Depot, Shastri Park,
Delhi – 110 053, on time, as mentioned in Clause 1.3.
The Employer/Engineer may, at his discretion, extend this date for the submission of tender by
amending the Tender Documents in accordance with Clause 7.0, in which case all rights and
obligations of the Employer and the tenderer previously subject to the original date shall thereafter
be subject to the new deadline as extended. If such nominated date for submission of tender is
subsequently declared as a Public Holiday by the Employer, the next official working day shall be
deemed as the date for submission of tender.
18.2 Tenders shall be submitted in person to Office of the Chief Electrical Engineer (IT&PD), DMRC.
The Engineer/Employer cannot take any cognizance and shall not be responsible for delay in
transit.
18.3 Tenders sent telegraphically or through other means of transmission (telefax etc.) which cannot be
delivered in a sealed envelope shall be treated as defective, invalid and shall stand rejected.
19.1 Any tender received in Office of the Chief Electrical Engineer (IT&PD) after the deadline prescribed
for submission of tenders in Clause 18.1 herein will be returned unopened to the tenderer and will
not be considered.
21.1 The Employer/ Engineer will open the Technical Package in the presence of tenderers or their
representatives who choose to attend on date & time as mentioned as per Clause 1.3 of ITT in the
Office of Chief Electrical Engineer (IT&PD), Shastri Park Depot, Shastri Park, Delhi – 110 053. If
such nominated date for opening of Tender is subsequently declared as a Public Holiday by the
Employer, the next official working day shall be deemed as the date of opening of Technical
Package. The Tender of any Tenderer who has not complied with one or more of the foregoing
instructions may not be considered.
21.2 On opening of the Main Tender envelopes, it will be checked if they contain Technical & Financial
Packages.
21.3 Technical Package of the Tender will thereafter be opened. They will be examined to see if they
are complete, whether the requisite Tender security has been furnished, whether the documents
are in order. If the documents do not meet the requirements of the Employer, a note will be
recorded accordingly by the Tender Opening Authority, and the said Tenderer’s Financial
Package will be considered only after Evaluation of Technical Bid by DMRC. Such Tender
may or may not be considered depending on nature of shortfall and the decision of DMRC
will be final.
21.4 The tenderers name, the presence or absence of the requisite tender security and such other
details as the Employer or his authorized representative, at his discretion, may consider
appropriate will be announced at the time of tender opening.
21.5 The sealed financial package will be kept in the safe custody of the Employer and will be opened
on a subsequent date after evaluation of technical packages. Financial packages of all technically
found suitable offers will be opened and the date for opening of financial package shall be
informed separately.
21.6 Deleted
22.1 Except the public opening of Tender, information relating to the examination, clarification,
evaluation and comparison of tenders and recommendations concerning the award of Contract
shall not be disclosed to tenderers or other persons not officially concerned with such process.
22.2 Any effort by a tenderer to influence the Employer/Engineer in the process of examination,
clarification, evaluation and comparison of tenders and in decisions concerning award of contract,
may result in the rejection of the tenderers tender.
23.1 Technical evaluation of technical packages submitted by tenderers shall be undertaken based on
details submitted in the technical package only. Tenderer shall not be required to submit on their
own, additional information or material subsequent to the date of submission and such material if
submitted will be disregarded. It is therefore essential that all the details are submitted by tenderer
accurately and specifically in their technical package avoiding vague answers. No
clarification/additional information in this regard will generally be sought from tenderer. However,
Employer reserve the right to ask any clarification (for technical Bid & financial bid) from tenderers
for details submitted with technical package if it so desires during the technical evaluation.
23.2 To assist in the examination, evaluation and comparison of Financial package, the Engineer/
Employer may ask tenderers individually for clarification of their tenders, including breakdowns of
prices. The request for clarification and the response shall be in writing or by telefax but no
change in the price or substance of the tender shall be sought, offered or permitted except as
required to confirm correction of arithmetical errors discovered by the Engineer during the
evaluation of tenders in accordance with Clause 25.0 herein.
24.1 Prior to the detailed evaluation of tenders, DMRC will determine whether each tender is
responsive to the requirements of the tender documents.
24.2.1 The Tenderer should submit his tender who conforms to the tender Documents, without material
deviations or reservations. Where, however, the Tenderer gives his financial offer subject to certain
Conditions, qualifications, deviations etc. He shall provide in a separate schedule (Form C1, C2 &
C3) the increase or decrease in the tender price for the unqualified withdrawal of each such
conditions qualifications/deviation,etc. Tenders not accompanied by such schedule are liable
to be rejected.
24.2.2 Tenderers shall further note that except for deviations listed in Form C1, C2 & C3 of Instructions to
tenderer (ITT) the tender shall be deemed to comply with all the requirements in the tender
documents including Employer’s Requirements, without any extra cost to the Employer irrespective
of any mention to contrary, anywhere else in the Tender.
24.2.3 The Employer may request the tenderer to withdraw any of the conditions, qualifications,
deviations, etc., if any, proposed by him at the cost stated in the tender . In case the Tenderer does
not withdraw the Conditions, Qualifications, deviations etc., if any, proposed by him at cost stated in
the Tender, his Tender is likely to be rejected and Tender Security forfeited.
24.3 If a tender is not substantially responsive to the requirements of the tender documents or if the
construction methods proposed by the tenderer are considered impracticable, it will be rejected by
the Employer, and will not subsequently be permitted to be made responsive by the tenderer by
correction or withdrawal of the non-conformity or infirmity. However minor clarifications if required
may be asked from tenderer at the time of evaluation of Technical or Financial Bid.
24.4 The decision of the Engineer/Employer as to which of the tenders are not substantially responsive
or have impractical / defective design or construction technology shall be final.
24.5 Cost of any item not quoted in financial package and also not clarified in deviation Form C1, C2 &
C3 in technical package but found shortfall in financial package, then it will be deemed to comply
with tender requirements, without any extra cost to the Employer.
24.6 Deleted
25.1.1 After Opening of Technical package and Preliminary scrutiny of the documents therein , the
Employer will, keeping in view the contents of Clause 9.1, carry out technical evaluation of
submitted technical proposals for experience/financial standing to determine that the tenderer has a
full comprehension of the work of the contract and he has requisite technical and financial capability
for executing the work. Where a tenderer’s technical submittal is found unsatisfactory or non-
compliant with the requirement of work, it may be rejected. This process is to assure that only
technically acceptable proposals are considered for the work. Procedure for evaluation is given in
clause 25.1.2 & 25.1.3 below.
25.1.2 Bidding Capacity :-
The Tenderers who meet the minimum qualification criteria will be qualified only if their
available Bid capacity is more than the 10.51 crore for this tender. He should furnish the
relevant data in the given formats. Available bid capacity will be calculated as under :-
Where ‘A’ = Maximum Turnover / Value of Works executed of any one year during the last 5
years.(updated to 31-03-2010 price level)
NOTE:
I) Adequacy of Bid Capacity will also be judged while evaluating the Tender from Pre
Qualified Contractors. Tenderer will have to furnish the requisite details for calculating the
bid capacity taking into account the New commitments if any.
II) In case of a group , the above formula will be applied to each member of the next extent of
his participation in the execution of the work. If the proposed % participation is not
mentioned then equal participation will be assumed.
25.1.3 Tenderer shall also duly fill/submit the Mandatory Eligibility Criteria as listed in Annexure-1
to ITT. Before Detailed Technical Evaluation of the Tender, the Technical/Financial Criteria
as laid down in Annexure-1 to ITT (ITT page 56 of 61) & appendices thereof will be
evaluated. Any Tenderer not meeting the technical or financial requirements as indicated
in Annexure-1 to ITT & appendices thereof will not be considered eligible and further
Evaluation of Tenderer will not be done .
25.2 All technically acceptable tenders will be eligible for opening of their financial proposals. DMRC will
notify all successful tenderers to attend the opening of the financial proposal. The financial proposal
will then be opened in front of attending tenderers and all prices recorded.
25.3 The evaluation of financial proposals by the Employer / Engineer will take into account, in addition
to the tender amounts, the following factors:
b. Such other factors of administrative nature as the Employer/Engineer may consider to have a
potentially significant impact on contract execution, price and payments, including the effect of
items or unit rates that are unbalanced or unrealistically priced.
25.4 Offers, deviations and other factors, which are in excess of the requirements of the tender
documents or otherwise will result in the accrual of unsolicited benefits to the Employer, shall not be
taken into account in tender evaluation.
25.5 The Tenderer is required to quote price including all taxes and duties etc in his financial offer as per
format in summary sheet of BOQ.
“In the event of exemption of custom duties and Excise duties, sales tax/VAT or any
other tax/ cess /levy being granted by Government in respect of Works, the benefit of the
same shall be passed on to Employer. The Contractor shall maintain meticulous record of
all the taxes and duties paid and will provide the same as and when required by
Employer, so that the Employer is able to avail exemption/ reimbursement of same.
Alternatively, the Employer may direct the Contractor to get the reimbursements based
on exemption certificates/ Government’s order and it shall be obligatory on part of the
contractor to get the reimbursements from statutory authorities.”
25.6 Deleted
26.1 Tenders determined to be technically acceptable after technical evaluation will be checked by the
Engineer/ Employer for any arithmetical errors in computation and summation during Financial
evaluation. Errors will be corrected by the Employer / Engineer as follows:
a. Where there is a discrepancy between amounts in figures and in words, the amount in
words will govern; and
b. Where there is a discrepancy between the unit price and the total amount derived from the
multiplication of the unit price and the quantity, the unit price as quoted will normally govern
unless in the opinion of the Employer / Engineer there is an obviously gross misplacement
of the decimal point in the unit price, in which event, the total amount as quoted will govern.
26.2 If a tenderer does not accept the correction of errors as outlined above, his tender will be rejected
and the tender security forfeited.
AWARD OF CONTRACT
27.1 Subject to Clause 25.0, the Employer will award, the Contract to the tenderer, whose tender has
been determined to be substantially responsive, complete and in accordance with the tender
documents, and whose Evaluated Price has been determined to be the lowest as per 3.1.1(d) of
Section 3 / NIT.
28.0 EMPLOYER'S RIGHT TO ACCEPT ANY TENDER AND TO REJECT ANY OR ALL TENDERS
28.1 Notwithstanding Clause 27.0, the Employer reserves the right to accept or reject any tender, and to
annul the tender process and reject all tenders, at any time prior to award of Contract, or to divide
the Contract between/amongst tenderers without thereby incurring any liability to the affected
tenderer or tenderers or any obligations to inform the affected tenderer or tenderers of the grounds
for the Employer's action.
29.1 Prior to the expiry of the period of tender validity prescribed by the Engineer/Employer, the
Engineer/Employer will notify the successful tenderer by telegram or telefax, to be confirmed in
writing by registered letter, that his tender has been accepted. This letter (hereinafter and in the
Conditions of Contract called 'the Letter of Acceptance') shall name the sum which the Employer
will pay to the Contractor in consideration of the execution, completion, maintenance and guarantee
of the works by the Contractor as prescribed by the Contract (hereinafter and in the conditions of
Contract called 'the Contract Price'). The "Letter of acceptance" will be sent in duplicate to the
successful tenderer, who will return one copy to the Employer duly acknowledged and signed by
the authorized signatory, within one week of receipt of the same by him. No correspondence will be
entertained by the Employer from the unsuccessful Tenderers.
30.1.1 The Employer shall prepare the Agreement in the Proforma (Form E) included in this Document,
duly incorporating all the terms of agreement between the two parties. Within 30 days from the date
of issue of the letter of acceptance the successful tenderer will be required to execute the Contract
agreement. The performance guarantee should be submitted immediately after issue of letter of
acceptance but not later than the agreement is signed between the parties. One copy of the
Agreement duly signed by the Employer and the Contractor through their authorized signatories,
will be supplied by the Employer to the Contractor.
30.2 Prior to signing of the Contract Agreement, the successful tenderer shall submit the following
documents within a period of 30 days from the date of issue of the Letter of Acceptance:
a. Performance Guarantee
b. Power of Attorney(s)
30.3 Upon "Agreement" being signed by the successful tenderer, the employer will promptly notify the
unsuccessful tenderers and discharge / return their tender securities.
30.4 Deleted
31.1 The successful tenderer shall furnish to the Employer a security in the form of a bank guarantee for
an amount of 10% of the Contract Price, in accordance with Clause 15.0 of the General Conditions
of Contract. The Bank Guarantee has to be from a Scheduled Commercial bank based in India and
the Form of Performance Security (Form D) provided in this Volume shall be used. The
Performance Security shall be furnished within the time limit specified in Clause 30.0.
31.2 Deleted
31.3 Failure of the successful tenderer to lodge the required Performance Security shall constitute
sufficient grounds for the annulment of the award of Contract and forfeiture of the tender security, in
which event the Employer may make the award to the next lowest evaluated tenderer.
32.0 Deleted
33.1 In case of Imported equipments (Partly/Fully) the Tenderer will be required to make credible
arrangements for ensuring availability of Critical Spares & Technical Support, during the Defect
Liability Period and also after the Contract Period, during the Service life of the
Equipments/Spares/M&P/Systems Commissioned.
33.2 To ensure proper availability of Technical Support, the Tenderer may be required to transfer
Technology in certain key areas to his Local associates/contractors/partners.
APPENDIX-I
4 Attested copy of Sales Tax Registration & latest (Original & Copy) 9.1.1(e-ii)
Clearance Certificate (STCC) / or Delhi Value Added
Tax Registration & latest Clearance Certificate
(DVATCC) or Declaration
5 Technical Package other Forms:
I)Form T- I (General Information Data) (Original & Copy) 2.2.1
II)Form T- II (Sub Contractor’s Data Along with 9.1.2 (d)
Declaration)) 9.1.2 (d)
III) Form T- III (For project Personals ) (Original & Copy)
9.1.2 (a)
IV) Form T- IV (For Site Organisation in chart form)
(Original & Copy 9.1.2(e)
V) Form T- V (For Plant & equipments)
(Original & Copy ---
VI) Form T- VII (Tender Index) (Original & Copy
1 Form of Tender and Appendix thereof (Form A) All in two sets 9.2
2 Bill of Quantities filled with cost (Original & Copy)
3 Deviation Form C-1 with Price
NOTE: Any other information or documents asked for in Tender Documents and not listed here
should also be submitted as this list is for assistance to contractors only.
INDEX ON
PROFORMA OF FORMS
FORM
v. Form of Agreement E
FORM
FORM A
PAGE 1 OF 4
FORM OF TENDER
ii. Tenderers are required to fill up all the blank spaces in this form of Tender and Appendix.
1. Having visited the site and examined the General as well as Special conditions of contract, CPWD
specifications, Special Specifications, Instructions to Tenderers, Preliminary Drawings and
Addenda for the execution of above named works, we the undersigned, offer to execute and
complete such works and remedy defects therein in conformity with the said Conditions of Contract,
Specifications, Preliminary Drawings and Addenda for the sum of Rs.___________________
_______________________________________________________________________________
(Amount in figures and words) for ‘Elevator Works of ILBS (Institute of Liver & Biliary Sciences) at
D-1 , Vasant Kunj , New Delhi-110070 ’ or such other sum as may be ascertained in accordance
with the said conditions.
3. We undertake, if our Tender is accepted, to commence the works within 7 days of issue of the
Engineer's order to commence and to complete the whole of the Works comprised in the Contract
by as indicated in the Appendix.
4. If our Tender is accepted, we will furnish a Bank Guarantee for Performance as security for the due
performance of the Contract. The amount and form of such guarantee or bond will be in
accordance with Clause 15.0 of the General Conditions of the Contract and as indicated in the
Appendix.
5. We have independently considered the amount shown Clause 57.5 of the General Conditions of
Contract as liquidated damages and agree that they represent a fair estimate of the damages likely
to be suffered by you in the event of the work not being completed in time.
6. We agree to abide by this Tender for a minimum period of 120 days from the date fixed for
receiving the same and it shall remain binding upon us and may be accepted at any time before the
expiry of that period or any extended period mutually agreed to.
FORM A
PAGE 2 OF 4
7. Unless and until a formal Agreement is prepared and executed, this Tender, together with your
written acceptance thereof, shall constitute a binding contract between us.
8. We declare that the submission of this Tender confirms that no agent, middleman or any
intermediary has been, or will be engaged to provide any services, or any other item of work related
to the award and performance of this Contract. We further confirm and declare that no agency
commission or any payment which may be construed as an agency commission has been, or will
be , paid and that the tender price does not include any such amount. We acknowledge the right of
the Employer, if he finds to the contrary, to declare our Tender to be non-compliant and if the
Contract has been awarded to declare the Contract null and void.
We understand that you are not bound to accept the lowest or any tender you may receive.
9. If our Tender is accepted we understand that we are to be held solely responsible for the due
performance of the Contract.
10. The Rates quoted by us are inclusive of all taxes, duties, fees, Octroi and other levies. Further We
will confirm compliance to follow Clause 10.6 of ITT in this regard.
11. We hereby confirm that information on our technical & financial Competence/ Credentials furnished
by us at the time of our participation are still valid. It is confirmed that there has been no adverse
change in availability of Liquid assets, line of credit & financial resources, availability of Technical
Competence (changes if any are to be indicated in the Statement of Deviations).
12. We hereby confirm that the ‘Quality Assurance Plan’ adopted by us shall be in conformity with
‘Quality Assurance Requirements’ detailed in Appendix II of, Part III of ‘Special Conditions of
Contract’ Volume I and shall be submitted as per Time Schedule laid therein, in case of our being
considered for Award.
13. We hereby confirm that the ‘Environmental Plan’ adopted by us shall be in conformity with
‘Environmental Protection Requirements’ detailed in Appendix III of Part III of ‘Special Conditions
of Contract’ Volume I and shall be submitted as per Time Schedule laid therein, in case our being
considered for Award.
FORM A
PAGE 3 OF 4
14. We hereby, conform that the ‘Safety Plan’ adopted by us shall be in Conformity with ‘Safety
Measures & Requirements for the outline Site Safety Plan, detailed in Appendix VI of Part III of
‘Special Conditions of Contract’, Volume-I and shall be submitted as per Time Schedule laid
therein, in case of our being Considered for Award.
Signature …………………………………
Address ……………………………………………………………………..………..
Name ……………………………………………..
Address ………………………………………………………………………………
Occupation ……………………………………………………………………………
FORM A
PAGE 4 OF 4
ii. Minimum amount of Third Party 23.0 of General Conditions Rs. 0.50 Million for any one
Insurance of Contract incident, with no. of incidents
unlimited.
iii Period for commencement of 7 days
work from the date of issue of
letter of acceptance
Iv Time for completion from the date 28.0 of Special Conditions 12 calendar months
of issue of the Letter of of Contract
Acceptance
v. Amount of liquidated damages in 57.5 of General Conditions 0.50% of Contract value of
case of extension of completion of Contract works for each week or part
date due to delays by the of week, Contractor is in
Contractor default, subject to maximum
of 10% of Contract value
vi Period of maintenance from the 80.0 of General Conditions 12 Calendar Months
date of issue of “Completion and 38.0 of Special
certificate” Conditions
FORM B
PAGE 1 OF 2
1. KNOW ALL MEN by these presents that we. ……………………………………... (Name of Bank)
having our registered office at ……………………… (Name of country) (hereinafter called “the
Bank”) are bound unto Delhi Metro Rail Corporation Limited (hereinafter called “the Employer”) in
the sum of for which payment will and truly to be made to the said Employer, the Bank binds itself,
its successors and assigns by these presents.
AND WHEREAS the Tenderer is required to furnish a Bank Guarantee for the sum of Rs.10.51
Lakhs (Rupees Ten Lakhs Fifty One Thousands only) as Tender Security against the Tenderer’s
offer as aforesaid.
a. That the Employer may without affecting this guarantee grant time or other indulgence to or
negotiate further with the Tenderer in regard to the conditions contained in the said tender
and thereby modify these conditions or add thereto any further conditions as may be
mutually agreed upon between the Employer and the Tenderer.
b. That the guarantee hereinbefore contained shall not be affected by any change in the
constitution of our Bank or in the constitution of the Tenderer.
c. That any account settled between the Employer and the Tenderer shall be conclusive
evidence against us of the amount due hereunder and shall not be questioned by us.
d. That this Guarantee commences from the date hereof and shall remain in force till---------
(date to be filled up) (up to 150 days from the date of tender submission).
e. That the expression ‘the Tenderer’ and ‘the Bank’ herein used shall, unless such an
interpretation is repugnant to the subject or context, include their respective successors and
assigns.
FORM B
PAGE 2 OF 2
a. If the Tenderer withdraws his Tender during the period of Tender validity specified in the
Form of Tender, or
b. If the Tenderer does not accept the correction of his tender price in terms of Clause 26.0 of
the “Instructions to Tenderers”.
c. If the Tenderer having been notified of the acceptance of his tender by the Employer during
the period of tender validity:
i. Fails or refuses to furnish the Performance Security in accordance with Clause 31.0 of the
“Instructions to Tenderers” and/or
ii. Fails or refuses to enter into a Contract within the time limit specified in Clause 30.0 of the
“Instructions to Tenderers”.
We undertake to pay to the Employer upto the above amount upon receipt of his first written
demand, without the Employer having to substantiate his demand provided that in his demand the
Employer will note that the amount claimed by him is due to him owing to the occurrence of any one
or more of the conditions (a), (b), (c) mentioned above, specifying the occurred condition or
conditions.
Signature of ………………………….
Authorized Official of the Bank
…………………………………….
Page 1 of 3
Form C - 1
To………………………….
Dear Sir,
Our prices given in Statements 1 to 8 are subject to the following deviations, conditions, qualifications
etc. These deviations, conditions, qualifications etc. are exhaustive. Except for these deviations,
conditions, qualifications, etc., the entire work shall be performed as per the Tender Documents. We
are also furnishing below the cost of unconditional withdrawal for the deviations, conditions,
qualification, etc. proposed by us. We confirm that we shall withdraw the deviations, conditions,
qualifications etc. at the cost of withdrawal indicated in this statement failing which our Tender may be
cancelled and the Tender Guarantee forfeited.
(- To be included in the Technical Package without Price and in Financial package with Price)
- Where there is No Deviation , the statement should be returned duly signed with an
endorsement indicating – ‘No Deviation’
Note:-
1. We hereby confirm that the pricing for unconditional withdrawn of above deviations has been given
in the financial bid.
2. We hereby confirm that all implicit and explicit deviations, comments and remarks mentioned
elsewhere in our proposal shall be treated as NULL and VOID and stand withdrawn.
3. No additional Deviations/Conditions/Qualifications, etc has been included with Financial Offer.
(This note is to be included in case of Technical Package only and not in Financial Package)
4. We hereby confirm that for the deviations, comments, remarks, conditions, qualifications, etc.
noted in this Form, our proposal is fully and truly Compliant.
5. Any additional deviations / comments/ remarks / conditions,/qualifications, etc. if included in
Financial Offer shall be treated as NULL and VOID and stand withdrawn.”
Date…………….. (Signature) …………………………………
Place …………… (Printed Name) ……………………………
(Designation) ……………………………….
(Common Seal) …………………………….
Form C-2
Page 2 of 3
Proforma for Statement of Deviations
Refer Clause 24.0 of ITT , Volume-1
GENERAL SPECIFICATIONS
(Where there is no deviation, the statement should be returned with an endorsement indicating ‘ No
Deviation )
Note:-
1. We hereby confirm that the pricing for unconditional withdrawn of above deviations has
been given in the financial bid.
2. We hereby confirm that all implicit and explicit deviations, comments and remarks
mentioned elsewhere in our proposal shall be treated as NULL and VOID and stand
withdrawn.
3. We hereby confirm that but for the deviations noted in this Form – C our offer is fully
and truly compliant.
4. No additional Deviations/Conditions/Qualifications, etc has been included with Financial
Offer. (This note is to be included in case of Technical Package only and not in Financial
Package)
5. “Any additional deviations/ comments/remarks/ conditions/qualifications, etc. if included
in Financial Offer shall be treated as NULL and VOID and stand withdrawn”.
FORM C-3
Page 3 of 3
(Where there is no deviation, the statement should be returned with an endorsement indicating ‘ No
Deviation )
Note:-
1. We hereby confirm that the pricing for unconditional withdrawn of above deviations has
been given in the financial bid.
2. We hereby confirm that all implicit and explicit deviations, comments and remarks
mentioned elsewhere in our proposal shall be treated as NULL and VOID and stand
withdrawn.
3. We hereby confirm that but for the deviations noted in this Form – C our offer is fully
and truly compliant.
4. No additional Deviations/Conditions/Qualifications, etc has been included with Financial
Offer. (This note is to be included in case of Technical Package only and not in Financial
Package)
5. Any additional deviations/ comments/ remarks/ conditions/qualifications, etc. if included
in Financial Offer shall be treated as NULL and VOID and stand withdrawn”.
FORM D
PAGE 1 OF 2
FORM OF PERFORMANCE SECURITY (GUARANTEE) BY BANK
(Refer Clause 31.0 of “Instructions to Tenderers”)
1. This deed of Guarantee made this day of_________ between Bank of________________(hereinafter called
the “Bank”) of the one part, and Delhi Metro Rail Corporation Limited (hereinafter called “the Employer”) of the
other part.
2. Whereas Delhi Metro Rail Corporation Limited has awarded the contract for ----------(Name of work
as mentioned under Clause 1.1.1 of NIT) (hereinafter called the contract) to ______________
(hereinafter called the Contractor).
(Name of the Contractor)
3. AND WHEREAS the Contractor is bound by the said Contract to submit to the Employer a Performance
Security for a total amount of Rs.____________________________________(Amount in figures and
words).
FORM D
PAGE 2 OF 2
7. At any time during the period in which this Guarantee is still valid, if the Employer agrees to grant a time
extension to the Contractor or if the Contractor fails to complete the Works within the time of completion as
stated in the Contract, or fails to discharge himself of the liability or damages or debts as stated under Para 5,
above, it is understood that the Bank will extend this Guarantee under the same conditions for the required
time on demand by the Employer and at the cost of the Contractor.
8. The Guarantee hereinbefore contained shall not be affected by any change in the Constitution of the Bank or
of the Contractor.
9. The neglect or forbearance of the Employer in enforcement of payment of any moneys, the payment whereof
is intended to be hereby secured or the giving of time by the Employer for the payment hereof shall in no way
relieve the bank of their liability under this deed.
10. The expressions “the Employer”, “the Bank” and “the Contractor” hereinbefore used shall include their
respective successors and assigns.
In witness whereof I/We of the bank have signed and sealed this guarantee on the ---------- day of --
--------- (Month) 2011 being herewith duly authorized.
Name : ……………………………..
Designation : ………………………
Stamp/Seal of the Bank: ………..
Witness 1.
Signature ……………………….
Name ……………………………
Address …………………………
Witness 2.
Signature ………………………
Name …………………………..
Address ………………………..
FORM E
PAGE 1 OF 2
∗ FORM OF AGREEMENT
(Refer Clause 30.0 of “Instructions to Tenderers”)
This Agreement is made at New Delhi on the ___________ day of _____________ 2011 Between Delhi
Metro Rail Corporation Limited, Fire Brigade Lane, Barakhamba Road, New Delhi – 110001 hereinafter
called “the Employer” of the one part and _________________ (Name of Contractor) (Address of
Contractor) ______________________________________ ____________________ of ____________
hereinafter called “the Contractor” of the other part.
Whereas the Employer is desirous that (*** certain Goods and Services should be provided and) certain
Works should be executed, viz. ----------(Name of work as mentioned under Clause 1.1.1) hereinafter called
“the Works” and has accepted a Tender by the Contractor for the execution and completion of such works
(*** as well as guarantee of such works) and the remedying of defects therein. NOW THIS AGREEMENT
WITNESSETH as follows:
1. In this Agreement words and expression shall have the same meanings as are respectively
assigned to them in the Conditions of Contract hereinafter referred to.
2. The following documents shall be deemed to form and be read and construed as part of this
Agreement, viz:
(a) General Conditions of Contract
(b) Special Conditions of Contract(SCC)
(c) Special Specifications
(d) Notice Inviting Tender & ITT
(e) Drawings and Specifications submitted by the Contractor.
(f) Bill of Quantities
(g) Form of Tender with Appendix
(h) Letter of acceptance
(i) Addendums, if any
(j) Other conditions agreed to and documented as listed below
(i) Tenderer’s Work Schedule as amended if required
(ii) Details of Quality assurance system and organization
(iii) Alternative designs (if applicable)
(iv) Statement of deviations (if applicable)
(v) Guarantee for the system offered (if applicable)
(vii) Any other item as applicable
(k) Safety Manual
3. In consideration of the payments to be made by the Employer to the Contractor as hereinafter
mentioned, the Contractor hereby covenants with the Employer to execute and complete the
works by **________ and remedy any defects therein in conformity in all respects with the
provisions of the Contract.
FORM E
PAGE 2 OF 2
4. The Employer hereby covenants to pay the Contractor in consideration of the execution and
completion of the works and the remedying of defects therein, the Contract Price of
**Rs__________ being the sum stated in the letter of acceptance subject to such additions
thereto or deductions there from as may be made under the provisions of the Contract at the
times and in the manner prescribed by the Contract.
The contractor shall ensure full compliance with tax laws of India with regard to this contract and
shall be solely responsible for the same. The contractor shall submit copies of acknowledgements
evidencing filing of returns every year and shall keep the Employer fully indemnified against liability
of tax, interest, penalty etc. of the contractor in respect thereof, which may arise.
6. JURISDICTION OF COURT
The Courts at Delhi/ New Delhi shall have the exclusive jurisdiction to try all disputes arising out of
this agreement between the parties.
IN WITNESS WHEREOF the parties hereto have caused their respective Common Seals to be hereunto
affixed / (or have hereunto set their respective hands and seals) the day and year first above written.
For and on behalf of the Contractor For and on behalf of the Employer
Note :
* To be made out by the Employer at the time of finalization of the Form of Agreement.
** Blanks to be filled by the Employer at the time of finalization of the Form of Agreement.
*** to be deleted if not applicable
FORM T- I
FORM-TI PAGE 1 OF 1
NOTES:
(i) Attach an attested/notarized photo copy of certificate of Registration and Ownership as well as
of constitution and legal status.
a)……………………………………………………………….
b)……………………………………………………………….
c)……………………………………………………………….
a)……………………………………….. ………………………………………….
…………………………………………. …………………………………………….
b)……………………………………….. ……………………………………………
…………………………………………. …………………………………………..
c)……………………………………………… ……………………………………………
………………………………………………… ……………………………………………
FORM T-II
PAGE 1 OF 2
EXPERIENCE RECORD OF SUB-CONTRACTORS
(Refer Clause 9.1)
Note:
(i) The Elevator Contractors can execute some part of Elevator Works through reputed Sub-
Contractors who have experience of carrying out similar works.
The tenderer shall indicate whether Some part of Elevator works are proposed to be executed by
them or through sub-contractor. In case these works are to proposed to be executed through sub-
contractor, the requisite information shall be submitted as per the performa given below, at this
stage & all the details pertaining to proposed Sub-Contractors shall be submitted on separate
sheets in the similar manner.
(ii) In para 2 furnish experience record of each sub-contractor by way of works executed during the last
five years and of works in progress now. Details may be furnished of only works similar in nature to
the work proposed for Sub-contracting.
(iii) In para 2 col.3 “Employer” means the organization which paid for the works and the “Engineer”
means the consulting Engineer for the project.
FORM T-II
PAGE 2 OF 2
Sl. Name Name of work Total Value for Contract Period Certificates Placed
No. of Sub- executed by the value of which the at
contract pro-posed sub- the proposed
Stipulated Actual Annexure Page
or contractor with work subcontractor
(Years) No. No.
location and (Rs. was
name & address Millions) responsible Start Completion
well as
“Engineer”
1 2 3 4 5 6a 6b 6c 7a 7b
Notes :
(ii) All the details should be supported by attested copies of certificates from clients for
each entry otherwise it will not be considered.
(iv) All the pages must be signed by the authorized signatory of the tenderer.
5 Others
Note:
1) Only Regular employees of the Tenderer, who have been with the Tenderer for at least 6
months, are to be listed out.
Form T-III
(Page 2 of 3)
6) A summary of the qualification and work experience of each key staff, to be attached. If personnel
of collaborator are involved, the same may be indicated separately.
7) Value of similar projects executed by the key personnel proposed for general management and
administration of the Contract, within the past five years, should be furnished as a supplement to
this form. Project Manager who will be in overall in charge at site, must have a minimum experience
of at least 15 years in execution of works.
8) The minimum level of qualification/experience of site-staff is given under Annexure–B
9) Employees required above are for Work Execution at Site while those required against ‘Safety ,
Health and Environment (SHE)’ shall be deputed as per DMRC General Instructions No.
DMRC/SHE/001/MPR/200106 ( Page 93 of 117 , Volume-6).
10. The Safety for Supply Part (SHE) will be taken care of by the Manufacturer at the Factory itself.
Tenderer /Contractor has to depute the shaft for erection, Testing and Commissioning part of the
Contract Value ; as per SHE Guidelines reference in Item 9 above.
11. Alternatively, Undertaking should be submitted for Deployment of Staff / Engineers in the
Enclosed Format on next page :-
Form T-III
(Page 3 of 3)
LETTER OF UNDERTAKING
(On Tenderer’s Letter Head to be submitted with Form T-III )
Date
…………………
To
The Managing Director
Delhi Metro Rail Corporation Limited
13,Fire brigade lane,
Barakhamba Road,
New Delhi-110001
2. We Confirm that minimum requirement of Project Personals as mentioned in ITT Form T-III
will be deployed and staff will be experts of requisite experience & qualification ( minimum
graduate in engineering with minimum 15 years experience as project Manager for Project
Manager s and minimum 5 years experience of relevant discipline for other engineers) will
be mobilized by us for the work in addition to semiskilled & skilled staff.
3. We also confirm that this is minimum project specific organization and these will be
suitably augmented , as required for achieving the tender requirements and key dates.
Signed-------------------------
For and on behalf of
FORM T-IV
PAGE 1 OF 1
PROPOSED SITE ORGANISATION
* Indicate clearly distribution of authority and responsibility between Head Office and Site
Management.
FORM T-V
PAGE 1 OF 2
S. Type of equipment required No. of Units Details of equipment Available for work Remarks
No. for the work of if any
equipment Make Distingui- Capacity Year of Present Present Owned
required for shing /Size manufa- condition location or
the work number cture leased
2. Multimeters (5)
FORM T-V
PAGE 2 OF 2
NOTE: -
1. The figure indicated in the bracket are the minimum number of Equipments required.
2. Major plants & Equipments are to be provided as per the minimum scale indicated in
Form T-V. Any proposal with Major plant & Equipment lesser than specified will not be
acceptable.
3. It is confirmed that minimum Plant & Equipment as per Tender requirement will
be deployed and if required the Plant & Equipment will be augmented to meet the
work schedule.
Signature of Tenderer
Name----------------------
Seal-----------------------
FORM T-VI
PAGE 1 OF 3
The Tenderer should have bidding capacity more than 10.51 crores . For this, he should furnish the
relevant data in the formats given below. The Bid Capacity shall be calculated as follows
Where ‘A’ = Maximum Turnover / Value of Works executed of any one year during the last 5
years.(updated to 31-03-2010 price level)
NOTE:
i) Adequacy of Bid Capacity will also be judged while evaluating the Tender from Pre Qualified
Contractors. Tenderer will have to furnish the requisite details for calculating the bid capacity
taking into account the New commitments if any.
ii) In case of a group , the above formula will be applied to each member of the next extent of
his participation in the execution of the work. If the proposed % participation is not
mentioned then equal participation will be assumed
iii) Tenderer should submit full detail of works in hand and anticipated during
completion period and should also submit their own calculation for Bid
Capacity being important criteria.
FINANCIAL DATA
(Cost in Million of Rs.)
* Total Value of Works/Sales & Services (in terms of Rupee equivalent
adjusted to 31.03.2010 level by assuming 5 % escalation for Indian Rupees
Year and 2 % for foreign currency portion per year)
* Attach attested copies of the Audited Financial Statement of last five financial years as Annexure. Financial
Value to be given in Million of Rupees. In case latest audited Financial Statement for year2009-10 is not readily
available then firm should submit latest relevant statement duly certified by Chartered Accountant .
2. Value of Work in Hand (B) - Applicants or each group member should indicate. in the form below ,
details for each contract/commitment which is anticipated to be in hand as on 24/11/2010 and the expected
year wise value of the balance works in the next four year. (Applicants are to present this information in the
format given below:.
FORM T- VI
Page 2 of 3
FINANCIAL DATA
(Refer Clause 9.2)
List of Ongoing Contracts
Amount –INR (Lacs)
Name of the Applicant :-
Applicant should provide information on their current commitments or all contracts that have been
awarded or for which a letter of intent of acceptance has been received or for contracts approaching
completion but for which a completion certificate is yet to be issued. (Give only the value of work
assigned to the applicant(s)). (Assume inflation as 5% for Indian Rupees and 2% for foreign
currency for year).
value of work assigned
telephone number and
Estimated completion
part of work assigned
Rupees equivalent (
Value of Work to be
Value of Work to be
Value of Work to be
(clearly indicate the
Original completion
Name of client with
Contract value in
yet to be done in
done in 2010-11
done in 2011-12
done in 2012-13
Name and brief
to applicant )
to applicant)
fax number
reason
Rupee
date
date
FORM T-VI
Page 3 of 3
FINANCIAL DATA:
Name of Applicant
Amount –INR (Lacs)
No. Financial Information Actuals for previous five years ending 2009-2010 Projection
in Rupee equivalent for the
with exchange rate at 2010-2011
the end of concerned
2005-2006 2006-2007 2007-2008 2008-2009 2009-2010
year
1 Total Assets
2 Current Assets
4 Total Liabilities
5 Current Liabilities
6 Current Liabilities+
Provision
10 Net worth
Note:
1. Please provide Audited Balance sheets / Profit & Loss Accounts in support of
information given above .
2. Financial Data submitted by the applicant in the above format earlier than 2005-2006 will not
be considered. Submitted Financial Data shall be duly certified by Chartered Accountant.
3. Also indicate contingent liabilities not provided for and any post balance sheet developments
having financial impact in relation to the financial statements of 2009-2010.
FORM T-VII
PAGE 1 OF 1
TENDER INDEX
The Tenderer shall include with his tender an index which cross refers all of
the Employer’s tender requirements elaborated in these documents to all the
individual sections within tender Package-1 (Technical Package) & tender
Package-2(Financial Package) which the Tenderer intend to be the responses
to each and every one of those requirements.”
Annexure-A
Deleted
Annexure –B
1. Project Manager (Team Leader) Graduate in Electrical/ Mechanical Minimum 3 years as In-
Engg. charge of similar works
and Minimum total
experience 15 yrs.
2. System Co-ordinator for System Graduation in Engineering Minimum 5 years relevant
Integration ,Safety ,Quality Experience.
Assurance & Environment
Control (Minimum 1)
Note :- For other SHE Staff , Instructions given in ‘ Condition of contract on Safety ,
Health & Environment ‘ at Page 95 of 117 of Voulme-6 ( General Instructions of
DMRC : DMRC/SHE /GI/002/QE /281105) will apply.
ANNEXURE- 1 to ITT
1. Work Experience :-
a) The Tenderer should have Annual Manufacturing Capability of at least 800 elevators (out of
which atleast 500 elevators should be with Machine Room Type & 300 elevators should be
without machine room/ machine room less type) . The above Information should be
submitted in Appendix-1 of ‘’Annexure-1 to ITT”.
b) The Tenderer should have Designed, Manufactured & Commissioned 2000 Elevator systems
in last 10 years (out of which alteast 1750 elevators should be with Machine Room Type &
250 elevators should be without machine room/ machine room less type). The above
Information should be submitted in Appendix-2 of ‘’Annexure-1 to ITT”.
c) The Tenderer should have experience of Installation, Testing & Commissioning of alteast
2000 nos. Elevators in last 10 years ( out of which alteast 1750 elevators should be with
Machine Room Type & 250 elevators should be without machine room/ machine room less
type). to be submitted in Appendix-3 of ‘’Annexure-1 to ITT”.
IF Tenderer has compliance in only (a) & (b) above , , he would be required to clearly explain
the sub-contractor proposal for item (c) above along with proof of his meeting the above
requirement in the relevant field, in the Technical Package. The Documentary Evidence
(such as Completion Certificate/Acceptance Certificate, Work Order etc.) for experience in
all the core areas mentioned above (a) to (c) shall be submitted in Technical Package.
It may also be noted that If Tenderer is not meeting the requirements as listed in (a) to
(c) , then his Tender will not be considered eligible and will not be considered for further
technical evaluation.
2. Financial Capability :
The Tenderer should have bidding capacity more than 10.51 crores . For this, he should furnish
the relevant data in the formats as per Form TVI , Page 1 of 3 & Page 2 of 3. The Bid Capacity
shall be calculated as follows
Where ‘A’ = Maximum Turnover / Value of Works executed of any one year during the last 5
years.(updated to 31-03-2010 price level)
of LOA plus approx. one month anticipated period for issue of LOA from date of Tender
Submission).
Both Criteria i.e (1) & (2) as mentioned above , are Mandatorily required to be
separately qualified/passed by the Tenderer for becoming eligible to be
considered for evaluation.
Summary for information for completed works year wise for last ten years
To be given separately by each member
31.03.2010
31.03.2009
31.03.2008
31.03.2007
31.03.2006
31.03.2005
31.03.2004
31.03.2003
31.03.2002
31.03.2001
Signature of Tenderer
Summary for information for completed works year wise for last ten years
31.03.2010
31.03.2009
31.03.2008
31.03.2007
31.03.2006
31.03.2005
31.03.2004
31.03.2003
31.03.2002
31.03.2001
Signature of Tenderer
Summary for information for completed works year wise for last ten years
31.03.2010
31.03.2009
31.03.2008
31.03.2007
31.03.2006
31.03.2005
31.03.2004
31.03.2003
31.03.2002
31.03.2001
Signature of Tenderer
CONTENTS
PART I
SPECIAL CONDITIONS OF CONTRACT
(General)
1.0 SPECIAL ATTENTION
1.1 Deleted
1.2 On receipt of tender documents, if any clarification or additional information is desired, the Tenderer
may submit a written request to that effect immediately. Clause 6.2 of “Instructions to Tenderers”
may be referred to in this regard.
1.3 The Contract will be awarded to the Tenderer whose responsive tender is determined to be the
lowest evaluated tender and who satisfies the appropriate standards of capacity and financial
resources. Clause 27.0 and 28.0 of “Instructions to Tenderers” may be referred to in this
connection.
2.0 PRE-BID MEETING
2.1 A Pre-Bid Meeting, open to all intending tenderers, may be held to discuss the issues referred in
Sub-Clause 1.2 above. Clause 15.0 of “Instructions to Tenderers” gives full details on “Pre – Bid
Meeting”.
3.0 RIGHT OF WAY (Supplemental to Clause 56.0 of “General Conditions of Contract”)
3.1 Right of way (within DMRC land) to the work site will be provided to the Contractor.
4.0 COORDINATION WITH OTHER CONTRACTORS
4.1 The contractor for this package shall plan and execute work in coordination and in co-operation with
other contractors working for adjacent/other packages, so that on completion, the proposed work
becomes an integral part of the ILBS (Institute of Liver & Biliary Sciences) at D-1, Vasant Kunj ,
New Delhi-110070
5.0 RULES AND REGULATIONS
5.1 The Tenderers are advised to familiarize themselves with rules, regulations and by – laws
applicable to them as indicated in Clause 9.0 of “General Conditions of Contract”. Ignorance of
rules, regulations and bye – laws shall not constitute a basis for any claim at any stage of work.
6.0 SUFFICIENCY OF TENDER
6.1 The Tenderer shall be entirely responsible for sufficiency of rates quoted by him in his tender.
6.2 The Contractor (Successful Tenderer) shall be paid for only at quoted/accepted rates for finished
works as per approved construction drawings. Where such agreed/accepted rates are not available,
the contractor shall be paid at rates to be decided in accordance with Clause 64.0 of “General
Conditions of Contract”.
7.0 NOTICES AND INSTRUCTIONS
7.1 The Contractor shall furnish to the Employer/Engineer the postal address of his site office. Any
notice or instructions to be given to the Contractor under the terms of the contract shall be deemed
to have been served on him if it has been delivered to his authorized agent or representative at site
or if it has been sent by registered post to the site office, or to the address of the firm last furnished
by the Contractor. Clause 86.0 of “General Conditions of Contract” may be referred to in this
connection.
8.0 RESPONSIBILITY FOR SPECIFICATIONS, DESIGN AND DRAWINGS (Supplemental to Sub-
Clauses 8.2, 8.4 and Clause 18.0 of General Conditions of Contract.)
8.1 SPECIAL SPECIFICATIONS
One copy of Special specifications shall be supplied to the Contractor. CPWD specification/other
Specifications viz. IS, IRS, IRC, DSR,IEC etc. shall be procured by the Contractor from the market.
8.2 DRAWINGS FOR PERMANENT WORKS.
Preliminary Drawings showing general dimensions & details elaborating the scope of work (not
based on detailed design) will be supplied along with the tender documents. Detailed working
drawings will be supplied during execution of work well in time including one soft copy of the
drawings.
8.3 DESIGN, DRAWINGS AND SPECIFICATIONS.
8.3.1 The contractor will submit the Shop Drawings for approval by the Engineer. After approval the
contractor would supply 6 sets of these drawings including one soft copy of the Drawings to the
Engineer for the latter’s use.
8.3.2 On completion of the Works, the Contractor shall arrange to furnish to the Employer six bound
sets of all “As-Constructed” Working Drawings and 2 sets of Soft Copy of the same for every
component of the Works, All such copies being on polyester film of quality to be approved by the
Engineer or his authorized Representative. The Certificate of Completion of Works as per the
provisions of Clause 78 of General Conditions of Contract shall not be issued by the Engineer in
the event of Contractor’s failure to furnish aforesaid “As-Constructed” drawings for the entire
works.
8.3.3 The Contractor shall promptly inform the Engineer of any error, omission, fault and other defects
in the Specifications, Drawings for the Works which are discovered when reviewing the Contract
Documents or in the process of execution of the Works.
9.0 NOT USED.
10.0 PLANS AND DRAWINGS FOR LAYOUT OF PLANT AND EQUIPMENT
10.1 The Contractor shall submit the following information, in triplicate, to the engineer for approval,
within the time stipulated against each item given below :-
a. A General layout plan for construction plant and equipment required for execution of work,
within thirty days from the date of issue of “ Letter of Acceptance.”
b. Drawings or prints showing the locations of major facilities which he proposes to put up at
site, at least fourteen days prior to the commencement of the respective work; and
c. Any other details and drawings as required under the contract, within the time as specified in
the contract.
11.0 REFERENCE POINTS AND BENCH MARKS
11.1 Deleted
11.2 The Contractor shall establish at his cost, at suitable points, additional reference lines and
bench marks as may be necessary. The Contractor shall remain responsible for the
sufficiency and accuracy of all his benchmarks and reference lines. He shall take
precautions to see that lines, points and bench marks fixed by the Engineer are not
disturbed by his work and shall make good any damage thereto.
12.1 No material, tools, plant and equipment shall be supplied by the Employer. The Contractor has
to arrange all tools, plant, equipment as well as materials required for the work. The Contractor
shall have to identify sources for supply of all such materials and get them approved by the
Engineer before the supply starts. The Contractor shall submit the sample to the Engineer and
shall arrange for supply only after the sample is approved. Nothing extra shall be payable to the
Contractor on this account. List of the Approved Makes/Manufacturers/Suppliers has been given
in the Special Specifications. Items are to be supplied of Approved Makes only after obtaining
the Approval of Engineer. Where Make has not been Specified, Contractor shall give a proposal
for a ‘Reputed Make’ and obtain Engineer’s Approval.
13.0 USE AND CARE OF SITE (Supplemental to Clauses 33.0 and 44.0 of “General Conditions
of Contract”).
13.1 The Contractor shall not demolish, remove or alter structures or other facilities on the site without
prior approval of the Engineer.
13.2 All garbage shall be burnt or removed from site daily or as they accumulate. All surface and sub-
soil drains shall be maintained in a clean, sound and satisfactory state of performance.
14.0 NOT USED.
25.1 Where night working is permitted by the Engineer to facilitate the Contractor’s Work operations,
temporary lighting equipment as per approved layout shall be provided, installed, maintained for
the duration of the contract and removed after completion of work by and at the expense of the
Contractor.
25.2 The Contractor shall provide and maintain adequate fire fighting equipment and take adequate
fire precautions for the safety of all personnel and temporary and permanent works and shall take
action to prevent damage to or destruction by fire of trees, shrubs and grasses.
25.3 No extra payment will be made for the provision of temporary lighting and fire prevention
measures and entire cost of all such work shall be deemed to have been included in the costs of
items of Bill of Quantities.
26.0 ERRORS, OMISSIONS AND DISCREPANCIES IN SPECIFICATIONS AND DRAWINGS
(Supplemental to Clause 8.0 of “General Conditions of Contract)
26.1 It shall be the responsibility of the Contractor to promptly bring to the notice of Engineer any error
or discrepancy in the contract documents and obtain his orders thereon. Only stated dimensions
are to be taken and not those obtained from scaling drawings. In case any feature of the work is
not fully described and set forth in the drawings and specifications, the Contractor shall forthwith
apply to the Engineer for further instructions, drawings or specifications.
26.2 In case of errors, omissions and/or disagreement on the drawings or between the drawings and
specifications the following principles shall be followed:
26.2.1 As between the written description or written dimensions on the drawing and the
corresponding one in the specifications, the former shall apply.
26.2.2 As between the written description of the item in Bill of Quantities and the detailed
description in the specification of the same item, the former shall prevail.
26.2.3 The drawings on a large scale shall take precedence over those on a smaller scale; and
26.2.4 Drawings approved as construction drawings from time to time shall supersede
corresponding drawings previously approved.
26.2.5 As between the written description or terms or conditions given in Special Conditions Of
Contract(SCC),or NIT or ,ITT and the description or terms or conditions given in General
Conditons Of Contract (GCC) of same items the former(i.e. SCC,NIT,ITT) shall prevail.
27.0 DEDUCTIONS TO BE MADE FROM CONTRACTOR’S BILL (Supplemental to Clause 75 of
“General Conditions of Contract)
27.1 Calculations for interest and deductions towards recovery of advances and interest thereon shall
be made from Contractor’s bills as provided hereunder:
27.1.1 The following shall be calculated on the first day of every month separately:
(a) amounts of mobilisation advance, advances for plant and machinery required for work and
brought to site and advance on construction material, outstanding on the last day of the
preceding month;
(b) amounts of interest remaining to be recovered on the last day of the preceding month. All
advances shall carry a simple interest at 10%.
27.1.2 Recovery on account of advances and interest thereon shall be made as per Clause 75.0 of
General Conditions of Contract and shall not exceed 30% of each bill.
27.1.3 Amount due for recovery on account of hire charges of Employer’s Machinery and other facilities
(if provided) as also for other services and electricity charges and expenditure, if any, incurred by
the Employer on Contractor’s behalf on labour, materials and equipment which may become due
from the Contractor as per terms of this contract as well as under any other prevailing laws will be
recovered from the payments to the Contractor as and when due.
27.1.4 Tax Deduction at source from each on-account progress bill shall be made by the Employer as
per the provisions of the statutes / act of statutory bodies / local Authorities. Etc.
28.0 EXECUTION PROGRAMME (Supplemental to Clause 53.0 of “General Conditions of
Contract”)
28.1 The Contractor shall prepare and submit his detailed construction programme in accordance with
Clause 53.0 of “General Conditions of Contract” and Clause 45.0 of “Special Conditions of
Contract”. The Contractor may also be asked to complete the work in a phased manner fixing
priorities to the different stretches of the work to give access to other Interfacing Contractors such
as Civil, HVAC, Plumbing, Lift Contractors etc as per requirement of Project from time to time.
Contractor will complete the work meeting and as per access of civil woks and will over all finish
the works within one year completion period of this tender.
Penalty
If contractor do not meet the targets along with civil works, Employer reserves the right to impose
intermediate penalty over and above as mentioned in clause 57.5 of GCC.
The Contractor shall co-ordinate his programme to the extent feasible with the programmes of other
contractors to be engaged at the site or in the vicinity of the site, as furnished by the Engineer so
that the project can be completed in time as per the overall programme
28.2 As regards Project Monitoring and updating of construction programme, Clause 45.0 may be referred to.
29.0 NOT USED
30.0 LAND FOR CONSTRUCTION
30.1 The Employer will acquire and provide land for permanent works and right of way (within DMRC
land) for access thereto over routes established by the Contractor. Any additional right of way to
the land, desired by the Contractor, for Execution purpose shall be arranged by the Contractor
without any expense to the owner as provided in Clause 55.0 of the “General Conditions of
Contract”.
31.0 SECURITY MEASURES
31.1 Security arrangements for the work shall be in accordance with general requirements and the
Contractor shall conform to such requirements and shall be held responsible for the action or
inaction on the part of his staff, employees and the staff and employees of his sub contractors.
31.2 Contractors’ as well as Sub contractor’s employees and representatives shall wear Identification
Badges (cards), uniforms, helmets, gum boots & other safety/protection wear as directed by
Engineer, and to be provided by the Contractor. Badges shall identify the Contractor and show
the employee’s name and number and shall be worn at all times while at site.
31.3 All vehicles used by the Contractor shall be clearly marked with the Contractor’s name or
identification mark.
31.4 The Contractor shall be responsible for security of works for the duration of the contract and shall
provide and maintain continuously adequate security personnel to fulfill these obligations. The
requirements of security measures shall include, but not be limited to, maintenance of Law and
order at site, provision of all lighting, guard, flagmen, and all other measures necessary for
protection of works within the colonies, camps and elsewhere at site, all materials delivered to the
site and all persons employed in connection with the works continuously throughout working and
non-working periods including nights, Sundays and holidays, for the duration of the Contract.
However, at work sites in close proximity of traffic corridors where public and traffic are likely to
come close to the work area, suitable barricading as directed by Engineer shall be provided.
31.5 Separate payment for provision of security services will not be made and deemed to be included
in the item of Bill of Quantities.
32.0 ANCILLARY AND TEMPORARY WORKS
32.1 The Contractor’s proposals for erection of all ancillary and temporary works shall be in conformity
with the proposals submitted along with the tender and modifications thereto as approved by the
Engineer.
32.2 The Contractor shall submit drawings, supporting design calculations where called for by the
Engineer and other relevant details of all such works to the Engineer for approval at least one
month before he desires to commence such works. Approval by the Engineer of any such
proposal shall not relieve the Contractor of his responsibility for the sufficiency of such works.
32.3 No extra payment will be made for complying with the provisions of this clause and the cost of the
work under this element shall be deemed to be included in the Bill of Quantities.
37.1 The Engineer may, if he considers it necessary or desirable, order in writing that any additional or
substituted work shall be executed on a day work basis. The Contractor shall then be paid for
such work in terms of provision contained in Sub-Clause 64.5 of General Conditions of Contract
on payment for extra items of Works not included in the Bill of Quantities.
37.2 The Contractor shall furnish to the Engineer such receipts or other vouchers as may be
necessary to prove the amounts paid and, before ordering materials, shall submit to the Engineer
quotations for the same for his approval.
37.3 In respect of all works executed on a day work basis, the Contractor shall, during the continuance
of such work, deliver each day to the Engineer an exact list in duplicate of the name, occupation
and times of all workmen employed on such works and a statement, also in duplicate, showing
the description and quantity of all materials and plant used thereon or therefore. One copy of
each list and statement, after verification, shall be signed by the Engineer and returned to the
Contractor.
37.4 At the end of each month the Contractor shall deliver to the Engineer a priced statement of
labour, material and plant, used and the Contractor shall not be entitled to any payment unless
such lists and statements have been fully and punctually rendered. Provided always that if the
Engineer shall consider that for any reason the sending of such lists or statements by the
Contractor, in accordance with the foregoing provision, was impracticable, he shall be entitled to
authorize payment for such work, on being satisfied as to the time employed and plant and
materials used on such work, either as day work at such value therefore as shall, in his opinion,
be fair and reasonable.
38.0 MAINTENANCE PERIOD (Supplemental to Clause 80.0 of “General Conditions of
Contract”)
38.1 Maintenance period shall be as mentioned in Clause 1.3 of ‘Instructions to Tenderers’.
39.0 This contract is a fixed rate contract and hence provisions contained in price variation
clauses (GCC clause no. 66 and 67) are not applicable.
40.0 BRIEF SCOPE OF WORK
Brief scope of work is included in Sub-Clause 2.2 of Notice Inviting Tender issued with the tender
documents.
41.0 PROGRAMME OF WORK (Supplemental to Clause 53.0 of “General Conditions of
Contract”)
41.1 The programme of work is included in Clause 2.3 of the Notice Inviting Tender issued with the
tender documents.
42.0 METHOD OF MEASUREMENT AND PAYMENT
42.1 For the purpose of On-account payment, the contractor shall submit detailed measurements,
recorded in Measurement sheets, Abstract sheets along with recorded bill for the item actually
executed for checking and payment. Measurement shall be witnessed by Employer’s
representative. Payment will be effected based on unit rates as approved in the Bill of Quantities.
42.2 Deleted.
43.0 NOT USED
44.0 CONTRACTOR’S OFFICE
44.1 The Contractor shall establish an office in the National Capital Region of Delhi in consultation
with the Engineer for planning, design, co-ordination and monitoring the progress of the Work and
intimate the same in writing to Engineer. The office shall be headed by a qualified person whose
credentials shall be approved by the Engineer. In addition, the Contractor may set up field
construction offices at convenient and approved locations for co-ordination and for monitoring the
progress of fieldwork. The entire cost shall be borne by the contractor.
45.0 PROJECT MONITORING (Supplemented by Appendix-I)
45.1 Activities in the works programme would be arranged as per the Works Break Down Structure
(WBS) of the work .The WBS Structure of the work would be developed by the contractor in
consultation with the Engineer. Contractor would get WBS structure approved by the Engineer.
45.2 The contractor will prepare an Execution Programme based on Computerized CPM network
using the Precedence Diagramming Method. The tentative Execution Programme shall be
submitted within 15 days of award for approval as ‘Baseline Programme’. The Baseline Program
shall clearly reflect Interface & Access dates for civil/system contracts.
45.3 After the work has started, the Contractor shall deliver in the first week of every month to the
Engineer an update of the Execution Programme showing changes, if any, in planning or
progress scheduling and reflecting the progress of all the activities of the network and the project
status as at the end of previous month.
45.4 If the Contractor falls behind the approved Execution Programme by more than one month, he
shall, within fourteen days of the date of such information, submit for approval, a revision of the
execution programme showing the proposed measures, including augmentation of plant, labour
and material resources to complete the works on time.
45.5 Whenever the Contractor proposes to change the execution programme he shall immediately
advise the Engineer in writing and, if the Engineer considers the change a major one, the
Contractor shall submit a revised programme for approval.
45.6 Detailed Network Plan (Works Programme)
Detailed Network Plan shall be prepared by the Contractor for each and every activity within the
same time frame and in the same sequence as indicated in the master network plan. Activity at
this level shall not be more than 15 days duration, except for summary items like procurement/
mobilization etc.
45.7 The Contractor shall select a PC-based broad planning and control software on which the two
networks shall be implemented. Software selected shall be Microsoft Project ,Version-2002
(MSP-2002) or higher version. If any other compatible software is used, approval of the Engineer
will be required. The Contractor shall supply one licensed copy of the software selected along
with the Baseline program network and detailed network plan free of cost and load it on the PC
system of the Engineer so that uniform monitoring of the project is done and any slippages are
identified well in time and corrective action taken.
45.8 The following reports, in agreed formats and frequency, shall be submitted by the Contractor at
his own cost:
(a) Progress Reports
(b) Material Status Reports
(c) Equipment and Manpower Development Reports
(d) Any other Report desired by the Employer or the Engineer
45.9 The Engineer’s monitoring team will have access to all the data/information of the Contractor,
required for the assessment of the progress and monitoring. If necessary, the monitoring team
will visit the Vendor/Contractor’s works in order to assess the status of critical activities.
45.10 Periodic Project Status Review Meetings will be held by the Employer or the Engineer. The
Contractor shall depute his Engineers/Managers at appropriate level as decided by the Engineer
to attend the Review Meetings.
45.11 Progress photographs of the major events shall be submitted by the Contractor along with the
Progress Reports. Video Recording of the progress of works shall be maintained from beginning
till completion of work as directed by the Engineer. Cost shall be borne by the Contractor.
45.12 The Contractor shall provide additional inputs whenever the PERT-CPM diagram indicates a
possible slippage in the completion schedule. Such additional inputs may require supplementing
of equipment, personnel, work in excess of the normal work per day, work in excess of the normal
work per week or other resources. Provisions under Sub-Clause 57.5 of General Conditions of
Contract will be applicable in cases of delays due to Contractor.
46.0 CASH FLOW ESTIMATE
The Contractor shall furnish to the Engineer the detailed cash flow estimate in respect of the
works within 3 months of the award of the Contract. This shall be up-dated and submitted every
three (3) months thereafter till the completion of the works.
47.0 NOT USED
51.5 The On-account payment will be made against indemnity bond of a format acceptable to the
engineer.
52.1 The whole of the Performance Security, amount, shall be liable to be forfeited to the employer at
the discretion of the Employer, in the event of any breach of Contract on the part of the
Contractor or if the Contractor fails to perform or observe any of the conditions of the Contract.
The Performance Security amount, shall become due and shall be paid to the Contractor, after
the expiry of the period of the maintenance specified in the Contract, reckoned from the date on
which the engineer shall have issued the Certificate of Completion comprising the whole of the
Works, and after all failures, defects and faults have been rectified by the Contractor, to the
satisfaction of the Engineer.
Provided always that, no Performance Security amount shall become due nor payable to the
Contractor, unless all the stipulations of the Contract have been fulfilled by the contractor and all
claims and demands made by the Employer for and in respect of damage or loss by, from or in
consequence of the Works, but excluding the claims made by the Contractor on the Employer,
have been finally satisfied.
(PART -II)
1.1 GENERAL
1.2 Work under this contract shall be executed as given in this tender document and as required at
site whether specifically shown or not. The Contractor shall carry out and complete the work
under this contract in every respect in conformity with the contract documents, as per directions
of and to the satisfaction of the Employers' Representative.
1.3 The tenderer shall constitute a competent qualified team to execute the Elevator in strict
compliance to statutory rules and specifications, drawings and relevant standards, whether
specifically mentioned in Tender or Drawings or BOQs or not.
1.3.1 In case the any part of Elevator Works are planned to be executed through Sub Contractors, the
tenderer shall assess the capabilities of the Subcontractors and satisfy himself as regard to
suitability, time schedule of work and quality standards of sub-contractors and furnish complete
credentials viz. Willingness to quote, legal status, registration, owners /partnership, IT return,
sales tax registration, past experience, solvency certificate and other information asked in ITT
regarding the proposed sub contractor/s which shall not be changed except in the cases where
the change is approved by Employer’s Representative to control the quality and timely completion
of work. The main bidder shall make available all the tender documents, specifications and
drawings to the Sub-contractors prior to bidding to ensure quality, timely completion and under
standing of work by Sub Contractors.
1.3.2 An undertaking from such sub contractors for having received above information and related
documents, having understood the Scope of Work and willing to execute the work shall be
submitted at the time of submission of tender, however the employer reserves the right to reject
/change the sub contractor at any stage. Sub contractor shall be deemed to be aware of the Site
Conditions, contractual conditions, nature of work, and all the risks associated with the work. Sub
contractors shall at all times keep upon work site competent and experience personnel with
communication and transport facility. Any instruction given to the representative shall be deemed
as given to Contractor and Sub contractor. No Sub Contractor shall be Engagement by Main
contractor without getting Prior approval from DMRC and no work shall be given to subcontractor
till approval.
1.3.3 No Sub letting by the contractor shall be permitted except for specific items such as the
Distribution Panels/Board Manufacture, subject to approval of Employer’s Representative.
1.4 In case of any contradiction between Part I and Part II of Special Conditions of Contract, the
order of Preference shall be as follows: -
2.1 Technical specifications forming a part of this contract are intended to cover work referred above.
It is not the intent to specify completely herein all aspects of design, constructional features of
equipment and details of the work to be carried out, but nevertheless the intent of the
specification is to ensure that the equipment and work shall conform in all respects to the relevant
Bureau of Indian Standard Specifications, Codes of Practice, Relevant International Codes &
Standards, Indian Electricity Act, Indian Electricity Rules ,The Bombay Lift Rules and other
Statutory Regulations as may be applicable and to high standards of engineering, design and
workmanship. The equipment and work shall perform in continuous operation in a manner
acceptable to the Employers' Representative who will interpret the meaning of the specifications
and drawings and shall have the right to reject or accept any equipment or work which in their
assessment is not complete to meet the requirements of this specification and/or applicable
Codes and Standards.
2.2 The work shall conform to all provisions of the relevant Government Legislation, Regulations and
Bye- laws of the Central/State/Local Authorities and of any State Electricity Boards/Companies to
whose system the installation is proposed to be connected. The Contractor shall give all
necessary notices required under the said Acts, Regulations and/or Bye- laws.
2.3 The contractor shall examine the installations' specifications, drawings & schedule of quantities
for feasibility & safety and may suggest or ask for change required if any to provide satisfactory &
safe services of the equipment designated for the Project.
3.1 The technical specifications and schedule of quantities shall be considered as part of this contract
and any work or materials shown in schedule and not called for in the specifications or vice versa,
shall be executed as if specifically called for in both. The drawings are for the guidance of the
contractor. Exact locations, distances and levels will be governed by the site conditions.
3.2 Special conditions of contract shall be read in conjunction with the General Conditions of the
Contract, Technical Specifications, Bill of Quantities, drawings and any other document forming
part of this contract. For any discrepancy between the General Conditions and Special
Conditions, provisions of Special Conditions shall prevail. For any discrepancy between
Technical Specifications and Bill of Quantities, the provisions of Bill of Quantities shall prevail.
3.3 Wherever it is mentioned in the specifications that the Contractor shall perform certain work or
provide certain facilities, it is understood that the Contractor shall do so at his own cost.
3.4 Where the Contract Technical Specifications stipulate requirements in addition to those contained
in the applicable Indian Standard Codes Relevant International Codes & Standards and
Specifications, these additional requirements shall also be satisfied.
3.5 The Contractor must get acquainted with the proposed site for the works and study specifications
and conditions carefully before tendering. The work shall be executed as per programme
approved by the Employers' Representative. If part of site is not available for any reason or there
is some unavoidable delay in supply of materials stipulated to be supplied by the Employers'
Representative, the programme of construction shall be modified accordingly and the Contractor
shall have no claim for any extras or compensation on this account.
3.6 Should the tenderer wish to depart from the provisions in these technical specifications, such
departure shall be listed in a separate schedule with full particulars and reasons for the same.
3.7 Contractor shall get the arranged material inspected/tested as required before use and shall not
move/ dispose off the material so arranged without the written permission of authorized
representative of Employer.
4.1 Tenderers, if they so desire, can, before submitting the tender, inspect the site of the work after
obtaining prior approval from Employers' Representative in order to familiarize themselves of the
conditions of work prevailing at site as also quantum of statutory levies (taxes, duties etc.)
applicable. No extra claim on account of lack of such knowledge shall be entertained after award
of contract.
4.2 All equipment and work covered by this contract shall be capable of operating continuously and
delivering the rated output at ambient conditions prevailing at site. The anticipated maximum and
minimum extremes at site are as below.
Location - Delhi
Contractor shall order for the approved make of material only and shall progressively forward the
copy of order placed and test certificates of the material to the Engineer/Employer’s
Representative. Contractor shall propose the make of the material as per List of approved make
available in Tender Document & obtain vendor approval from the Employer before ordering the
material. It may so happen, where particular material does not appear in list of Approved Makes of
the Tender Document / Bill of Quantities or Else where in the Tender Document. In such case,
Tenderer shall propose a reputed make and obtain Employer’s approval before Ordering.
5.2 MAKE
5.2.1 Contractor shall use the material of approved make as per approved list unless specified in
BOQ or as approved by the Employer’s representative.
5.2.2 The contractor shall ensure the correct selection of the approved make meeting the
specifications and application duties. Before placing order for procurement, the sample of
approved make shall be got verified for its suitability to the specification and application duty.
However in case Employer’s representative/ engineer, whose decision will be final and
binding on both parties, considers that the make/ model proposed by the contractor does not
meet the requirement, the contractor will be required to propose an alternative make
acceptable to the Employer’s Representative.
5.2.3 The Contractor shall quote the rates for material and equipments as per the list of approved
makes. In the event of contractor wanting to use alternate makes other than those stipulated
for any reason, the contractor can send a proposal after ensuring that what he proposes at
least meets both the quality, and safety standard of the stipulated makes, and the financial
benefit that will accrue to the Employer. He shall also stand full guarantee to his alternate
proposal. The alternate makes can be used only after an approval accorded by the
Employer, whose decision will be final in the matter.
• Assessment of the financial and functional strength of the Vendor to supply the
requisite quantity of equipment and product as per delivery schedule acceptable to
contractor.
(b) In the second stage, called as Technical Submission Approval Stage, selection of
Equipment or product from the equipment / products manufactured / supplied by the
approved vendor will be done. This stage includes thorough technical assessments about
the conformance of the offered equipment / product to the Specifications and other
requirements.
(c) To obtain Vendor Approval the Contractor must apply with the five sets of the following
documents to the Engineer
(ii) Details of the facilities available at the Works / Manufacturing Unit where the
proposed equipment / product shall be manufactured.
(iii) ISO 9000 Certification for the Works / Manufacturing Unit where the
proposed equipment / product shall be manufactured (The Works /
Manufacturing Unit where the proposed equipment / product shall be
manufactured must have ISO 9000 Certification)
(v) Audited Financial Statements of the Vendor for the last three years.
(vi) Type test certificates from accredited laboratories for the proposed type of
equipment / products to establish the technical capability of the vendor (In
case, specific requirements are mentioned in the relevant sections of
Specifications with regard to type testing, same shall also be complied
additionally). Proposal received without the type tests certificates as
mentioned above, shall not be considered as a Vendor Proposal and
summarily rejected.
(viii) Details of supplies / orders executed in last ten years for the type of
equipment / product offered. Any other item as required by Employer /
Employer’s Representative.
(d) Contractor must check and certify that vendor Proposal is complete and all the above
documents are available in the Vendor Proposal. In addition, the Contractor must check /
certify compliance to the Specifications before forwarding the same.
(e) Incomplete Vendor Proposal will not be treated as a submission and will be returned.
(f) Engineer will give Approval to the Vendor Proposal (received complete with all the
documents mentioned above) within ten working days from the date of receipt.
(g) Technical submission shall be accompanied with the calculations / other technical
documents to justify the selection of any particular model of equipment / product, detailed
technical features / parameters of the selected product, type test certificates from the
accredited laboratories for the offered products, any other document required by the
Engineer.
(h) Engineer will give Approval to the Technical Proposal (received complete with all the
documents mentioned above) within ten working days from the date of receipt.
5.2.5 It may be noted that Approval of Vendors above shall only be done by Employer / Engineer
after the award of this work. Vendor Approval Submissions shall not be included in the Tender
Packages. Conditional Tender offers received from Tenderers with particular Vendors for
supply of equipment / products shall not be considered.
5.2.6 It may further be noted that Employer / Engineer shall be under no obligation to accept
equipment / products manufactured by the successful Tenderer, unless it meets the entire
criterion mentioned above.
5.3 SAMPLES
A list of items of materials and equipment together with samples, as required, shall be submitted
to 'Engineer' as per agreed schedule, for approval, before being used on work. No change in
samples and deviations from drawings of equipments shall be made from without the written
instructions of the Employers' representative. Approvals given by the Employers' representative
to any samples or drawings submitted by the Contractor shall not in any way exonerate the
Contractor from his liability to carry out the work in accordance with the terms of the contract and
Any item, which is proposed as a substitution, shall be accompanied by all technical data giving
sizes, Performance Data, Utilization Data, Technical Specifications, Technical Literature,
Particulars of Materials, Rate Analysis and the Manufacturer's name. At the time of the
submission of proposed substitution the Contractor shall state the credit, if any, due to the owner,
in the event the substitution is approved. All changes and substitutions shall be requested in
writing and approvals obtained in writing from the Employers' Representative. Any Proposed
substitute material shall be of Reputed make.
If manufacturers furnish specific instructions relating to the materials used in this contract covering
points not specifically mentioned in this document, manufacturer’s instructions shall be brought to
the notice of Employers' Representative for further instructions in the matter. Such instructions
from the manufacturer shall be complied by the Contractor.
5.6 INTERCHANGEABILITY
All similar parts and/or equipments shall be interchangeable with one another.
The Employers' representative shall have full powers to require any material used in work to be
tested by an independent agency at the Contractor's expense in order to prove its soundness and
adequacy.
a. Shop assembly of all component parts shall be made to ensure that all parts are
properly fitted to minimize installation problems.
b. The Employer reserves the right to inspect any machinery, material and component
(hereinafter collectively called “apparatus”) finished or used by the contractor under this
contract and may reject which is defective in workmanship or design or otherwise
unsuitable for the use and purpose intended or which is not in accordance with the
intent of this contract. The contractor shall on demand by the Employer, remedy/replace
at the contractor’s expenses any such defective or unsuitable apparatus at No cost to
the Employer. The contractor shall advise the Employer in advance when apparatus is
ready for inspection in the contractor’s workshop and/or in his sub Contractor’s
workshop.
c. The Employer’s Representative shall at all times have access to all parts of shops
where apparatus are being manufactured and also shall be provided with all reasonable
inspection facilities by the contractor and his Sub Contractor.
d. None of the apparatus to be furnished or used in connection with this contract will be
supplied until shop inspection and performance testing, wherever possible, satisfactory
to the Employer’s Representative has been made. Such shop inspection of the
apparatus shall not however, relieve the contractor from full responsibility for furnishing
the apparatus confirming to the requirements of this contract not prejudice any claim,
right or privilege which the Employer may have because of the supply of defective or
unsatisfactory apparatus. Should the Employer waive the right to inspect any
apparatus, such waiver shall not relieve the contractor from his obligation under this
contract.
e. The above clauses are in addition to the provisions available in the Tender Document,
elsewhere which are applicable.
f. In addition to the above, the provisions as per Specifications, Codes, Standards &
Tender Documents are to be followed.
a. The contractor shall carry out the complete installation and commissioning. All work
shall commence on previously prepared locations for the main and sub systems. All the
materials shall be moved from their place of storage into the plant by the contractor.
The contractor shall make his own arrangement to off load materials received at various
points, dispatch to site and to store all material received at site. The Employer shall
provide clear storage and installation space only. All installation tools and tackles as
and when required to suit the installation programme shall be provided by the
contractor.
b. The above clauses are in addition to the provisions available in the Tender Document
elsewhere which are applicable.
In addition to the above, the provisions as per Specifications, Codes, and Standards &
Tender Documents are to be followed.
a. On completion of the installation, the contractors shall arrange to carry out various initial
tests as detailed below, in the presence of and to the complete satisfaction of the
Engineer. Any defects or shortcomings found during the tests shall be speedily rectified
or made good by the contractor at his own expenses.
b. Contractor shall prepare Elaborate Installation & Testing Procedure (ITP) & shall
submit the same for Employer’s approval prior to installation & testing .
c. The Testing & commissioning of Elevator System is to be carried out as per applicable
National / International Standards, Statutory requirements etc.
d. Lift Management System its compatibility with Building Management System (with
BACNET Protocol) & interface with Building Management & Fire detection System,
shall also be tested & certified.
The contractor shall provide all necessary tools, Instruments, gauges, flow meter,
Manometer, ammeter etc. As may be required for conducting the various tests.
e. The above clauses are in addition to the provisions available in the Tender Document,
elsewhere which are applicable.
f. In addition to the above the provisions as per Specifications, Codes, Standards &
Tender Documents are to be followed.
6.1 The Contractor shall submit the required applications, drawings, etc., to the concerned statutory
authorities and obtain their approval, license, permission, clearance and/or sanction. All the workmen
and supervisory staff shall be qualified and certified license holders or have competency from National /
Internationally recognized agency empowered to issue, to carry out similar work or authority.
6.1 The final completion certificate shall be obtained by the Contractor from all statutory authorities to
enable the Employers' representative to commission the equipments/installation for utilization. The
Contractor shall bear all expenditure to be incurred for getting the installations approved and obtaining
the statutory approvals. The work shall not be deemed to have been completed until all the approvals
etc., have been obtained by the Contractor. All Legitimate Fees paid by the Contractor to the statutory
authorities shall be reimbursed by the Employers' representative on production of receipts. However, all
other charges and liasoning work expenses shall be borne by the Contractor. Obtaining statutory
approvals by the Contractor shall form a part of the Contractor’s scope of the contract work. The
Contractor shall obtain all the required statutory approvals including but not restricted to the following.
a) ELEVATOR WORKS: -
Approval from Electrical Inspector to Govt. of India for DMRC & Lift Inspector including
approval on submittal and of works before energisation , clearance from Statutory
Authorities for Energising the System after Completion of Work as required.
b) Approval of Elevator system layout from Delhi Fire Service for getting Design clearance/
Fire Clearance.
Clearance from Delhi Fire Service for energizing the systems after completion of work
and to obtain No Objection Certificate from Delhi Fire Services.
The Contractor shall work in co-ordination and co- operation with the Building Contractor and/or
any other agencies at site and shall arrange to place the pipes/ conduits/inserts etc in the
masonry and concrete as required, along with the progress of building works. Any hold up of the
building or other works because of delay in placing the pipes/Conduits/ inserts etc or otherwise
shall be the responsibility of the Contractor and shall make him liable for damages as may be
considered and levied by the Employers' representative.
Tenderer is expected to go through technical specifications, drawings and other details carefully
and confirm full compliance to the same. Whenever technical specifications are not mentioned,
contractor is required to follow latest national/ international standards to ensure highest quality of
work.
In case the Tenderer finds himself unable to adhere to any of the specification/parameter, ha
should clearly indicate the reasons for the same in schedule of deviations and propose alternative
standards as per the International/National practice.
The scope of work under this contract shall include the Design, Manufacture, Testing at
Manufacturer’s works, Supply, Transportation, Delivery, Storage, Erection, Site Testing &
Commissioning, shop drawings, approvals from relevant authorities of Electrical, LV system
& Fire Fighting Works including co-ordination & visioning with other Contractors/Agencies &
DDC as required to complete the work, & other provisions as stipulated in General
Conditions of Contract (GCC), Special Conditions of Contract (SCC), Special
Specifications, Bill of Quantities & other Tender documents comprising of but not restricted
to :
V) All required Drawings preparation & its approval, Obtaining Statutory approvals
Sanction and Lift Safety Certificate of Elevator Systems from Lift Inspectorate &
other authorities.
Scope of work shall also include all Civil works as indicated in Bill of Quantities and
also not covered in Interface Document, Section 5 of NIT associated with Electrical,
LV system and Fire Fighting works and making and painting the Civil works as
required.
- Maintenance of the area during implementation stage for Multy Storey Building
consisting of 2 Basements.
- Scope of work shall also include obtaining all Statuary & Mandatory Permissions /
Clearances / Approvals from the concerned authorities for Commissioning of the
Installations complete as stipulated is Para 6 of Special Conditions of Contract -
Part II.
- The Contractor shall include the Supply of entire material in accordance with
specification and whole of the work necessary for the complete installations as
set down in the specification and with the accompanying schedules & drawings.
Material & Components not specifically stated in the Specifications and / or Bill of
materials or not shown in the Drawings, but which are necessary for satisfactory
installation and Operations of the System, shall be deemed to have been
included in the Scope of Work.
- Any other item of work as may be required to be carried out for completing the
work under this Contract in all respects in accordance with the provisions of the
Contract and/or to ensure the safety of installation during and after execution.
The value of the work shall be on Item Rates accepted in Letter of Acceptance
subject to such additions thereto or deductions there from as may be made under the
provisions of the Contract.
The Rates are inclusive of all Cost but not limited to the cost such as for Plants,
Equipments, tools, all type of labours, supervision, all materials from the source of
supplies as approved by Engineer/Employer including all lead and lifts, transport, all
temporary works, erection, maintenance, contractors profits & establishment /
overheads together with preparation of designs and drawings, all general risks, taxes,
Confidential SCC 22 of 93 ` December 2010
Contract DMRC/ELECT./IT&PD/ILBS/ELEVATOR/03 Special Conditions of Contract
royalties, duties, cess, octroi and other levies, insurance liabilities and all other
obligations set out or implied in the contract for completion of work except otherwise
specified in Bill of Quantities or elsewhere in the Tender documents.
10.1 Working drawings (Shop Drawings) and Particulars to be furnished by the Contractor
before Commencement of Work
The Contractors shall submit Six sets of following drawings and technical particulars along with
Two soft copies (CDs) after the award of contract for approval of Employers’ representative
before commencement of work at site/fabrication at manufacturer’s work. The mode of
submission and procedure for incorporations of comments by Employers on such drawings,
resubmission and final approval shall be as finalized at site by the Employer.
Obtaining the Fire Clearance Certificate from Fire authorities and all other Statutory
including Lift Inspectorate Approval and getti9ng issued License for Lift Operation. Scope of
Work shall also include all Civil Works as indicated in the Bill of Quantities and also not
covered in Interface document, Section 5 of NIT associated with Elevator Works and
making and painting the Civil Works as required & other authorities.
c) Elevator Plans
d) Sub-System Drawings
f) Elevator Drive
i) Schematic Diagrams
m) Earthing Layouts
p) Conduiting Layosuts
t) Manufacturing Schedule
v) Interface Drawings
10.2.1 MANUALS
The contractor shall provide/produce 6 copies of Manuals along with Two Soft copies in bound
term as approved by the Employer for all Contractor-supplied equipment and systems. The
following Set of Manuals are to be provided separately for Electrical, LV System & Fire Fighting
Works:
Each and every manual shall be divided kinto indexed sections explaining the subject matter in
logical steps. Most manuals shall consist of A4 size printed sheets bound in stiff cover, wear-
resistant binders clearly and uniformly marked with the subject matter and reference number.
Where alternative sizes are proposed, (e.g. A5/A6 pocket books of schematic wiring diagrams)
these shall be submitted for review of Employer representative. The binding shall allow for all
subsequent changes and additions to be readily effected.
Information shall be provided in pictorial form wherever possible and shall include step-by-step
instructions and views of the particular equipment including exploded views. Programmable
equipment shall be supplied with sufficient flow charts and fully documented programmes to
enable faults to be quickly identified and system modification to be undertaken at any time.
The Contractor shall provide clarifications and amendments to the Manuals as necessary during
the Defects Liability Period. Updates shall be provided for the originals and all copies.
The Contractor shall provide/produce 6 copies of Manuals along with Two Soft copies approved
by the Employer for all Contractor-supplied equipment and systems. The following Set of Manuals
are to be provided separately for Elevator Works.
i) Part number
ii) Description
iii) Name of manufacturer
iv) Quantity and unit
v) Part number of next higher assembly (usually a line replaceable unit).
vi) Cross-reference to figure number.
vii) Category: e.g. consumable, line replaceable unit, repairable.
viii) Life-expected life, Mean time between failure or mean distance between failure
where available.
ix) General or specific purpose.
x) The second is a series of illustrations to indicate the location of each replaceable
item which shall be clear and progressive with exploded views to enable parts to be
identified easily by cross-reference with the alpha-numeric list.
xi) Maintenance Manual shall include the following:
i) Infrastructure required for the maintenance.
ii) Maintenance check sheets for I line, II line & III line maintenance.
iii) Illustration of lift’s components, sub-assemblies, assemblies etc. with a sketch.
iv) Detailed explanation of safety items.
v) Detailed overage of trouble shooting.
vi) Reliability Centered maintenance (RCM), Maintenance Requirement Analysis,
Condition Monitoring based Maintenance & Reliability, Availability & Maintainability
datas.
vii) Check Sheets & Scope of Work for Comprehensive Annual Maintenance.
Training Manuals are a convenient source document for use ins the field. The Contractor may
prepare Training Manuals as per requirement of the project.
The Contractor shall prepare Training Manuals and submit them to the Employer for review and
approval at least 3 months prior to Date of Completion of Elevator Works.
Throughout the Contract and DLP, it shall be the responsibility of the Contractor to supply the
Employer with all changes and revisions to the Training Manuals.
The Contractor shall provide Six Hard Copies + Two Soft Copies of the Training Manual as
directed by Employer’s representative.
The Employer reserves the right to copy all Training Manuals for use in Training Courses.
System Manuals shall cover a Comprehensive Description of all Systems & Sub-Systems,
Principles at Block Diagram Level, Colour Photographs of Systems & Sub-Systems etc.
All wiring diagrams and circuits, protection scheme, equipment layout, terminal and cable listing
and including such external equipment as may be necessary for completeness. This shall cover all
equipments provided in Machine Room.
Shall cover commissioning test procedures for all the equipment and the final test values of the
equipment on load, without load, protective earthing and measures taken to avoid surprise failures.
Installations, Testing & Commissioning procedure shall be made and got approved before
Installation for all Equipments & Systems.
Shall cover the condition monitoring procedures, yardsticks, equipment wise condition norms etc. to
facilitate monitoring of equipment and avoid surprise failures.
Wherever applicable, Software Manuals covering details regarding Software, Usage, System
Administration etc. will be provided. This will cover details of Lift Monitoring System also.
Contractor shall submit all Manuals for review by the Employer’s representative prior to installation
and the Contractor provide 3 copies of all Manuals well in advance and explain so as to understand
the Manuals by the user prior to commissioning.
a) Manufacturing Drawings
c) Elevator Plans
d) Sub-System Drawings
f) Elevator Drive
i) Schematic Diagrams
m) Earthing Layouts
p) Conduiting Layosuts
t) Manufacturing Schedule
v) Interface Drawings
10.3.1.2 Results of installation and commissioning test and other tests as required and specified. The
Contractor shall be required to carry out all tests required as per specification with his own
equipment and at his own cost and in case the test results are not within permissible value,
take necessary remedial action at his cost to bring them to desired level.
10.3.1.3 Technical literature and test certificates as required together with field test results and
manufacturer test certificates.
Contractor has to carryout all type tests, acceptance tests, special tests, routine tests and
commissioning tests as per IS / CPWD specifications, other codes, specifications, etc., as required
by Engineer. Contractor shall furnish 6 copies (bound, as approved by the Engineer) of certificates
for the type-tests, routine-tests carried out as per the relevant Standard Specification for every
equipment / component/ fitting either at the manufacturer’s works or in a laboratory approved by the
Engineer, and the cost thereof shall be borne by the Contractor. Test certificates of successful
prototype tests shall be furnished within a month of completion of the prototype test and routine test
certificates after passing of the equipment /component/ fitting by the Engineer’s Representative on
inspection. The type test to be witnessed will be on the sole discretion of the Engineer. Type tests
may not be required in those cases where the Contractor can produce certified evidence
that the required Type Test has been performed successfully on identical equipment and
produced in a factory where the equipment to be supplied under the contract is to be
manufactured, provided the Type Test has been carried out and witnessed by recruiting Test
agencies. The final decision regarding acceptability and acceptance of the Type Test,
certificate produced shall rest with Employer’s representative.
(a) The Tests have been included at the appropriate places in the Specifications.
i. The Type Test Tests which will be witnessed by Employer’s representative will be
decided solely by the Representative.
ii. The Costs of all Testing is to be included in the rates except for expenses of travel
and boarding of Employer’s Representative.
The Test certificates for Acceptance Tests, Special Tests, Routing Tests and Commissioning
Tests, which will be performed in the presence of Employer’s Representative, has to be
submitted in 6 copies. However, this will not absolve the Contractor of the Complete System to
be made functional in all respects. An Integrated Testing & Commissioning shall be done for the
complete Elevator system specified.
11.1 The Contractors shall, at his own expense, arrange for safety provisions as per safety codes of
Indian Standards Institution, Indian Electricity Act and such other Rules, Regulations and Laws as
may be applicable, as indicated below, in respect of all labour, directly or indirectly employed in
the work for performance of the Contractors’ part of this agreement.
11.2 While the Indian Electricity Rules 1956, as amended up to date, are to be followed in their
entirety, particular attention is drawn to the variation clauses indicated in Appendix ‘C’. Any
installation or portion of installation which does not comply with these rules should be rectified
immediately.
11.3 It shall be ensured that the control switches and distribution boards are duly marked , the
distribution diagrams of sub-stations are prominently displayed, and the sub-station premises,
main switch rooms and D.B enclosure are kept clean. Particular care should be taken to prevent
the sub-station being used as store for inflammable materials, broken furniture, waste materials
etc.
11.4 No inflammable materials shall be stored in places other than the rooms specially constructed for
this purposes in accordance with the provisions of Indian Explosives Act. If such storage is
unavoidable, it should be allowed only for a short period and in addition, special precautions,
such as cutting off the supply to such places at normal hours, storing materials away from wring
and switch boards, giving electric supply for a temporary period with due permission of Engineer
shall be taken.
11.5 Rubber or insulating mats should be provided in front of the main switch boards or any other
control equipment of medium voltage and above.
11.6 Protective and safety equipments such as portable fire extinguishers rubber gauntlets or gloves,
earthing rods, linemen’s belt, portable artificial respiration apparatus etc. should be provided in
easily identifiable locations. Where electric welding or such other nature of work is undertaken,
goggles shall also be provided.
11.7 Necessary number of caution boards such as “Man on Line, Don’t switch on” should be readily
available in easily identifiable locations.
11.8 Standard first aid boxes containing materials as prescribed by the St. John Ambulance Brigade or
Indian Red Cross should be provided in easily identifiable locations and should be readily
available.
11.9 Periodical examination of the first aid facilities and protective and safety equipments provided
shall be undertaken and proper records shall be maintained for their adequacy and effectiveness.
11.10 Charts (one in English and one in regional language ) displaying methods of giving artificial
respiration to any recipient of electrical shock shall be prominently displayed at appropriate
places.
11.11 A chart containing the names, addresses and telephone numbers of nearest authorized medical
practitioners, hospitals, Fire Brigade and also of the officers in charge shall be displayed
prominently along with the First Aid Box.
11.12 Steps to train supervisory and authorized persons of the Engineering staff in the First aid
Practices, including various methods of artificial respiration with the help of local authorities such
as Fire Brigade, St. John’s Ambulance Brigade, Indian Red Cross or other recognized institutions
equipped to impart such training shall be taken, as prompt rendering of artificial respiration can
save life at time of electric shock.
11.13 All new recruits should be given such First Aid Training immediately after appointment.
11.14 All supervisory and authorized persons of the Engineering staff should be deputed for refresher
course in First Aid Training periodically.
11.15 Electrical wiring and control switches should be periodically inspected and any defective wiring,
broken parts of switches, which will expose live parts, should be replaced immediately to make
the installations safe.
11.16 No work shall be undertaken on live installations, or on installations, which could be energized
unless another person is present to immediately isolate the electric supply in case of any accident
and to render first aid, if necessary.
11.17 No work on live HT/ L.T. bus bar or pedestal switchboards should be handled by a person below
the rank of a licenced Wireman and such a work should preferably be done in the presence of the
Contractor’s Engineer .
11.18 When working on or near live installations, suitably insulated tools should be used, and special
care should be taken to see that those tools accidentally do not drop on live terminals causing
shock or dead short.
11.19 The electrical Switchgear and distributions boards should be clearly marked to indicate the area
being controlled by them.
11.20 Before starting any work on the existing installation, it should be ensured that the electric supply
to that portion in which the work is undertaken is preferably cut off. Precautions like displaying
“Men at Work” cautions boards on the controlling switches, removing fuse carrier from theses
switches and these fuse carriers being kept with the person working on the installation, etc.
should be taken against accidental energisation. “Permit to Work” should, be obtained form the
Engineer. No work on H.T. main should be undertaken unless it is made dead and discharged to
earth with an earthing lead of appropriate size. The discharge operation shall be repeated several
times and the installation connected to earth positively before any work is started.
11.21 Before energizing an installation after the work is completed, it should be ensured that all tools
have been removed and accounted, no person is present inside any enclosure of the switch
board etc. any earthing connection made for doing the work has been removed, “Permit to Work”
is received back duly signed by the person to whom it was issued in token of having completed
the work and the installation being ready for re-energizing and “Men at Work” caution boards
removed.
11.22 In case of electrical accidents and shock, the electrical installation on which the accident occurred
should be switched off immediately and the affected person should be immediately removed from
the live installation by pulling him with the help of his coat, shirt, wooden rod, broom handle or
with dry cloth or paper. He should be removed from the place of accident to a nearby safe place
and artificial respiration continuously given as contained in BIS. Code and Standard prescribed
by St. John Ambulance Brigade or Fire Brigade.
11.23 While artificial respiration on the affected person is started immediately, help of Fire Brigade and
Medical Practitioner should be called for and artificial respiration should be continued
uninterrupted until he recovers or medical help is availed.
11.24 Deleted
11.25 Deleted
(a) Debris and wastes like cable cut copies, conduit pieces etc. shall be stored only in an
identified and approved location at site.
(b) There shall be periodically disposed, so that the site is maintained clean and tidy.
13.0 WORKMANSHIP
Good workmanship is an essential prerequisite to be complied for this work. Skilled workers under
competent supervision shall carry out entire work in the most workmanlike manner by skilled
workers under competent supervision.
14.1 The methodology shall be framed mutually agreed to certify the work, through checklists,
standards progressively. Installation, Testing & Commissioning procedure shall be made and got
approved well before Installation. The installations shall be checked by a quality assurance team
of the contractor, Employer’s Representative.
14.2 The Contractor shall enlist the equipment assemblies/ sub assemblies/ components accessories
and other movable components on successful installation and commissioning of the equipment.
14.3 The prior approval for energisation from the competent authority shall be obtained as per the
statutory regulations in force. The Contractor shall be responsible for all safety aspects included
and approved.
15.2 Contractor shall establish an office for the purpose with communication facility so as to facilitate
communication for reporting failures and liaison with DMRC’ maintenance staff manning Sushant
Lok PD Area round the clock .The supervisor in-charge of contractor should be provided with
mobile communication facility to ensure his presence at the site within 1 hours of reporting.
Contractor shall ensure restoration /rectification/replacement within 3 hrs. for attending to
Defects / Failures of Minor Nature and 8 hrs. for attending Defects / Failures of Major Nature to
the satisfaction of Employer’s Representative. The Employer’s Representative in case of the
delay as deem fit shall be empowered to carry out the maintenance at the risk and cost of the
Contractor.
The Contractor shall carryout Corrective Maintenance at any time during 24 hrs. X 365 days
based on the occurrence of failures / breakdowns.
15.3 Deleted
15.4 The work of Full Service Maintenance shall be carried out as follows:-
15.4.1 Full Service Maintenance of the Elevator Works executed by the Contractor under this contract
during the Defects Liability period, during which, the Contractor shall be responsible for
maintenance of the installation to achieve the Uptime stipulations including providing all
consumables and spares as described hereunder. This shall be provided by the contractor at no
extra cost and is deemed to be included in the quoted rates for the installation.
15.5.1 Submit a schedule for routine maintenance which shall include the Manufacturer’s
recommendations and / or common engineering practice (for all plant and equipment). Any
comment / instruction given by the Engineer – in – Charge vis – a – vis the maintenance
schedule shall not absolve the contractor of his obligation to properly and fully maintain all the
Elevator Systems at all times.
15.5.2 Plant and equipment history card shall be maintained by the Contractor which shall give full
details of equipment and frequency of checks and overhaul.
15.6 REPAIRS
15.6.1 All equipment that require repairing shall be immediately serviced and repaired. All replacement
parts and labour shall be supplied promptly.
15.7 Deleted
15.8 MANPOWER
15.8.1 Adequate number of persons shall be provided including relief personnel for satisfactory
maintenance.
15.8.2 Duty allocation and Roster control shall be the contractor’s responsibility but shall be subject to
the approval of the Engineer – in – Charge.
15.8.3 The Contractor shall furnish the bio-data of all the personnel whom he proposes to deploy for the
maintenance work for the approval of the Engineer – in – Charge. The Contractor shall deploy
only those personnel who are approved by the Engineer – in – Charge. Such approval shall not
absolve the Contractor of his obligations of proper conduct and performance of his personnel.
The Engineer – in – Charge shall have the right, without assigning any reason whatsoever, to ask
the Contractor to remove from the Site any person, regardless of his having been approved
earlier by the Engineer – in – Charge, and replace with another suitable person approved by the
Engineer – in – Charge. The contractor shall expeditiously comply with all such instructions.
15.9.2 Contractor shall carry out Preventive Maintenance during Non-Operational hours with prior
permission of the Engineer – in – Charge. Corrective Maintenance is to be carried out as and
when failures/ defects occur any time during 24 Hrs. X 365 days.
15.10 Deleted
During the Defects Liability Period, the Contractor shall provide free of cost all materials
including consumables, unit exchange spares and emergency spares required for
maintenance (routine and breakdown) of the Elevator System provided under the Contract.
The provision of spares during the DLP excludes any spares / consumable required for
routine / breakdown maintenance of operation. Before the commission of Works the
contractor shall supply the spares, jigs and fixtures materials not later than 6 weeks before
the commissioning of the services. A list of such spares and materials required for
maintenance during the Defects Liability Period and to be provided free of cost by
the Contractor and if list is found insufficient then the same need to be
augmemented for preventive and corrective maintenance of all the equipments
supplied under the contract.
If these spares are not consumed during the Defects Liability Period, these shall become
the property of the Employer at the end of Defects Liability Period.
16.0 Training
The contractor shall arrange for theoretical as well as practical training to both supervisors and staff
adequately. Any training can be arranged in Delhi as well as outside Delhi within India with a
minimum duration of 3 days. Separate Training will have to be arranged for Different Systems. The
cost of Training except for Travel & Boarding Expenses of Employer’s Personal is to be borne by
the Contractor. Training manual shall be submitted for DMRC’ approval. At the end of training,
competency certificate should be issued to trained personnel by contractor.
16.2.1 This covers the requirements for a Training Program to train the Employer’s O&M personnel. The
training Program shall enable the staff to operate, service, enhance, maintain and interact with, the
hardware, software, and firmware, such that the elevator systems and associated equipment will
perform in accordance with the specifications of this contract.
The Contractor shall provide comprehensive training to the Employer’s O&M personnel. The
Contractor shall provide competent training instructors, training manuals, all necessary aids and
materials in support of all training courses. The training manuals shall be submitted in original plus
five hard copies and in Two Soft Copies.
The training instructors shall be qualified, competent, with sufficient years of practical experience in
the relevant fields and possesses good communication skills.
The training instructors shall be competent staff of the Contractor, or the sub-contractors or the
equipment manufacturers.
16.2.2 The training shall be carried out at such locations where the greatest benefit for trainees may be
gained. This may be in any place in India, at place of manufacture assembly or testing, or at such
other locations as may be necessary. All places of training shall be subject to review by Employer’s
Representative.
16.2.3 The training courses and/or sessions shall include system performance requirements and all major
equipment and works designed, by the Contractor.
16.2.4 The Contractor shall provide full-time on-Site management and co-ordination of the entire training
programme to ensure the continuity of classes, and proper distribution of training materials, and be
responsible for interfacing with the instructors.
Confidential SCC 32 of 93 ` December 2010
Contract DMRC/ELECT./IT&PD/ILBS/ELEVATOR/03 Special Conditions of Contract
16.2.5 The traindsing courses shall be delivered to all relevant Employer’s O&M personnel.
The training shall be provided by the Contractor to the Employer’s personnel in Design,
Manufacturing, testing, system architecture and installation practices related to Elevators.
Contractor shall submit a training programme for 4 Trainer’s Weeks. There will be number of
courses with duration varying form half to one full week. The number of trainees in each course
may vary from 5 to 10. The areas of training will be including the following:
S.No. Description
a) The Contractor shall provide Training Courses on all facilities, systems, equipment, hardware,
and firmware, software. Each Course shall be specific, and shall consist of classroom, hands-
on, or site training as necessary to accomplish the Course Objectives specified in the Training
Program Plan.
b) All Concerend O&M & Security staff would need to be trained in emergency handling.
c) All trainsding aids shall be used during training followed by practical & demonstrations.
d) Trainer’s kit may be used for imparting training in trouble shooting.
e) The Contractor shall provide training courses for each of the sub-systems, including but not
limited to:
The Contractor shall arrange all Training Aids, Training Materials, Training Devices, Special Tools,
Fixtures, Models, or other Equipment required to train Course Participants.
The Contractor shall arrange to provide all equipment/ accessories as required for the work as per
the approved list of the makes as specified in the specifications unless the change is approved by
the Engineer in case of non availability or better substitute in writing.
Deleted
19.0 ORGANISATION
The Contractor/Sub contractor shall provide at his own cost Qualified Site Engineer with minimum
staff as approved by the Engineer at site and maintain an all time team at its headquarter office
for prompt liason. Necessary details as asked in formats be furnished regarding Electrical
contractor team and the sub contractors team proposed for the work
20.0 TIME SCHEDULE
20.1 It is desirable that all the Elevator works are completed one Month prior
to the Date of Completion except those Items mentioned for Intermediate Milestones which are to
be completed accordingly.
The submittals of Contractor/sub-contractor at construction stage shall include the following but
not limited to:
Submittal Tentative schedule
T Hand over of the utilities and manuals, drawings, Prior to completion date
warranty/guarantee papers and deployment of
maintenance staff for defect liability
20.2 The Contractor shall within 15 days of award of Contract submit his time schedule, which shall be
binding on him. However employer reserves the right to amend /modify any of the dates in the
interest of the work. Contractor/sub contractor shall propose the inspection/delivery dates as per
mutual agreement. Contractor/ sub-contractor shall take in to account all such considerations
while quoting for the offer.
21.1 Power supply is available at 415/240V 3 Phase 4 wire 50 Hz earthed neutral system and all
equipment shall be suitable for the above power supply with a variation of + 10% to – 15 %. All
equipment shall operate at these voltages and any equipment or component operating at other
than the above power supply shall be provided with necessary transformer.
All tools, tackle, scaffolding and staging required for erection and assembly of the equipment and
installation covered by the contract shall be obtained by the contractor himself. All other
materials such as foundation bolts, nuts etc. are required for the installation of the plant shall also
be supplied and included in the contract.
23.1 The contractor shall carry out tests on different equipment as specified in various section in the
presence of the Engineer in order to enable them to determine whether the plant, equipment and
installation in general comply with the specifications.
23.2 All equipment shall be tested after carrying out the necessary adjustments and balancing to
establish equipment ratings and all other design conditions, the test data shall be submitted in the
Acceptance Test Forms in an approved format. At least four sets of reading shall be taken for
each item tested and submitted. Instruments required for testing shall be furnished by the
contractor for testing with initial requirements of all consumables.
23.3 The plan shall be handed over after satisfactory testing along with six sets of hard copies & two
sets of soft copies (CDs) each consisting of :
iii) Set of as-built drawings, showing plant layouts, piping, ducting etc.
v) Certificates of approval from Statutory or Local Authorities for the operation and
maintenance of the installation and equipment, wherever such approval or certification is
required.
vii) Certificate from the contractors that they cleared the site of all debris and litter caused by
them during the construction.
viii) Manuals & other Documents as per S.C.C. Part-II Clause 10.2 & 10.3.
x) List of Spares, Consumables, T&P, M&P, Material Handling equipments, Test Instruments,
Jigs & Fixtures etc. along with Quantities to be kept by Contractor in Delhi Metro premises
during Defects liability Period for maintenance.
xii) Completion of all Electrical, LV System and Fire Fighting Works in all respect.
24.1 All designs for temporary work shall confirm to and comply with all requirements given in the
latest editions of the relevant Indian Standard specifications and codes of practice and other
technical Specifications as detailed in this tender.
24.2 For all work for which the contractor has to submit design for approval of the Employer, the same
shall be got prepared by the contractor from approved consultants who are specialized in this
field. For particular item of scaffolding, staging and shuttering, use of any proprietary method of
staging should be supplemented with proper designs of such system after getting approval from
the Engineer.
a) Operating and Maintenance Instructions which describe the procedures for operating and
maintaining each item, unit / equipment and which will include all technical data for its
operation, routine inspection/survey, routine maintenance, procedures for removal and
replacement of components and test running.
b) Parts catalogue along with Pricelist and Recommended List of Spares for One Year’s
operation and for 10 Years of Operation after Defects Liability Period along with Vendor’s
Addresses.
c) A List of Special Tools, Material Handling Equipments, Jigs and Fixtures required for
dismantling & assembling and test/diagnostic equipment for Performance
Monitoring/Maintenance.
d) List of M&P, T&P, Testing Instruments, Material Handling Equipments, Jigs & Fixtures etc.
required for Maintenance to be submitted.
e) Training requirements.
After commissioning & service trials, contractor will deliver to the Employer copies of all
such Drawing, Schedules and software for all components.
26. DOCUMENTATION
Separate set of Manuals are to be given for Elevator Works as mentioned in Clause 10.2 .
Contractor will submit all Manuals for review by DMRC prior to Commissioning of Systems well in
advance.
Six controlled Hard copies & Two soft copies of all Manuals will be supplied to DMRC.
Contractor will maintain all Manuals in an up-to-date condition throughout the Contract Period.
Documentation to be provided will also include:
• Test Procedures
• Test Reports
• Inspection records
• Assembly drawings
• Schematic diagrams
• O & M Manuals
Recommended spares
A Soft Copy, in CD, shall also be submitted for all the documents.
Any plant and equipment that has been installed prior to completion of the whole works but not
required for immediate use will be protected to ensure that there will be no deterioration to its
condition.
In case of imported Elevator or its Systems (Fully or Partly), Tenderer shall submit a detailed Pain
of transfer of Technology along with memorandum of Understanding with suitable Indian
Companies having proven Track Record and are working in related areas for all Major
Systems/Sub-Systems.
Transfer of technology shall be essential & shall include System assembly, installation,
Maintenance and Software Modification/Customization & Training of Indian Company’s Personnel
to cover.
The Transfer of Technology, may require involvement of Indian Company’s Personnel in Design,
Manufacturing, testing & Installation of Elevator Sub-Systems during the Contract Period. The
Contractor shall undertake to supply or make arrangement to supply additional equipment required
for replacement or upgradation of Elevator Systems in future. The Contractor shall undertake to
provide to the above Indian Company, during the Life of the equipment ordered Technical
Assistance in the form of Additional drawings, maintenance practices & Technical Advice.
Transfer of Technology is not required where the Elevators or its Systems are indigenous or where
Contractor himself can undertake for the above.
The Cost of transfer of Technology where applicable is assumed to be included in the Cost of
Elevators as indicated in the Bill of Quantities.
PART III
ADDITIONAL SPECIAL CONDITIONS OF CONTRACT
1.0 DELETED
2.0 OBTAINING CLEARANCES/CERTIFICATES FROM AUTHORITIES
2.1 The contractor shall arrange stage wise as may be required, submission of all the required
documents and drawings for execution and installation of the works and their inspection and
obtain approval/completion certificates with respect to his work as required for use and
connection of the utilities and occupation of the building from the Statutory Authorities. The
Contractor shall obtain and deliver to the Engineer, on completion of the works, the final
Inspection Report and approval from the Authorities.
2.2 The Contractor shall warrant that all actions taken by him in the execution of the Contract shall
conform to all applicable City, State and Central Laws, Ordinances and Regulations. The
Contractor shall defend and keep Employer harmless from loss, cost of damage by reason of any
actual or alleged violation of any statutory requirements.
3.0 DRAWINGS FOR PERMANENT WORKS
(Supplemental to Sub-Clause 8.2 of SCC Part - I)
3.1 For guidance of the bidder, drawings as listed, are enclosed with the tender documents. These
drawings are broadly indicative of the work to be carried out. These drawings are not
“Construction Drawings” and details indicated therein are for general guidance only and shall be
modified by the Engineer, to incorporate additional details as per design, and as described in the
Specifications and the Schedule of Quantities.
No claim whatsoever shall be admissible on account of any changes that may be introduced by
the Engineer.
3.2 The "Good for Construction" drawings which shall be issued to the Contractor by the Engineer
after the award of work, shall delineate the extent of work to be done by the Contractor.
No deviation shall be made from these drawings without a written authorization from the
Engineer.
4.0 DESIGN, DRAWINGS BY CONTRACTOR
(Supplemental to Sub-Clause 8.3 of SCC Part – I)
4.1 Shop drawings by Contractor.
(a) Based on "Good for Construction" drawings issued by the Engineer the Contractor shall
prepare shop/fabrication drawings to scale as specified, indicating the required details. The
shop drawings shall be prepared before execution of work, after taking actual site
dimensions and all existing and proposed services/structures etc
(b) Shop drawings submitted by the Contractor shall be in sufficient detail to indicate the type,
size, arrangement, breakdown for packing and shipment, the external connections, fixing
arrangements required, the dimensions required for installation and interconnections with
other equipment and materials, clearances and spaces required between various portions
and any other information specifically called for.
(c) All reference points shall be in relation to the levels and locations, given in the Architectural
and Services drawings duly cross-checked on site and confirmed. All locations and levels
should be indicated with respect to grid and reduced levels with respect to the Bench Mark
adopted for the Project and indicated in the drawings issued by the Engineer.
(d) The Contractor shall verify the dimensions of all the necessary structural, architectural,
Mechanical, Electrical & Plumbing (MEP) Services and other elements, relevant to the
system being done, before proceeding with the preparation of the shop drawings and
proceeding with the physical work at site and make suitable adjustments to accommodate
within the spaces available.
(e) The Contractor shall submit all drawings only after they have been duly detailed, checked
and verified within the Contractor's organization ensuring that the details and data
shown/furnished on the drawings are correct and that the requirements of other disciplines
have been taken care. The names and complete signatures of the Contractor's personnel
Confidential SCC 39 of 93 ` December 2010
Contract DMRC/ELECT./IT&PD/ILBS/ELEVATOR/03 Special Conditions of Contract
responsible for the drawings shall be contained on each drawing. Any drawing which does
not contain the above names and signature’s shall be summarily returned to the Contractor
and treated as not having been submitted.
(f) The drawings submitted for approval shall be in any one of the standard sizes - AO, Al, A2,
A3 or A4, in accordance with Indian standards.
(g) All drawings shall show the following particulars in the lower right hand corner in addition to
the Contractor's name.
• Name of the Owner.
• Project Title.
• Contract No.
• Name of the System /Work (i.e LV Works)
• Title of Drawing.
• Scale
• Date of Drawing.
• Contractor's Drawing Number.
• Space for the Engineer’s drawing number.
• Name of the Engineer.
• Name of Review Consultant.
• This drawing is based on Drawing No.(s).
• Further detail is given on Drawing No.(s).
(h) Each drawing shall carry a revision number, date of revision and brief details of revisions
carried out. Whenever any revision is carried out, the revision number must be updated.
The revisions carried out on the drawing shall be clearly marked by clouding and each
cloud revision numbered by marking the revision number in triangle. The clouding shall be
done on the backside of the tracing by pencil.
(i) All dimensions on drawings shall be metric units, unless otherwise specified. However, all
levels shall be in meters.
j) All shop drawings shall be prepared on CAD using AutoCAD release 14.
4.2 Revision of Approved Shop drawings.
If, at any time before the completion of the Work, changes are made necessitating revision of
approved shop drawings, the Contractor shall make such revisions and proceed in the same
manner and observe procedure for obtaining approval of the Engineer as for the approval of the
original shop drawing.
4.3 Documents by Contractor.
The contractor shall submit to the Engineer, for approval, Quality Assurance plans, Design
Calculations, Material specifications for each item and system, samples, as may be called for in
the Specifications or as the Engineer may reasonably require. Wherever necessary, the
Contractor shall provide As Built dimensions to facilitate proper Good for Construction drawings
being prepared for various construction detailing.
4.4 Number of Copies of Shop drawings and documents.
All shop drawings, documents, schedules etc. and revisions thereof shall be submitted by the
Contractor to the Engineer in 6 Hard copies and one Soft copy as per the requirement of the
Engineer. Copies required in excess of' these shall be paid for by the Engineer at a reasonable
rate, which shall include the direct cost of the documents, together with a reasonable amount to
cover the Contractor's overheads associated therewith.
4.5 Completion Drawings.
On completion of the work in all respects the contractor shall submit the following.
• Six number portfolios (300 mm x 450 mm) each containing complete set of drawings on
approved scale indicating the work "As Built". Each portfolio shall also contain technical
literature.
These drawings shall be prepared on CAD using Auto-Cad release 14 and shall be
recorded on CDs and one set of these CDs shall also be submitted.
• Six sets of catalogues & manuals of all manufactured materials with the name and
addresses of the manufacturers for all equipment provided by him.
• The Contractor shall also submit one set of original "AS Built" drawings on tracing.
The Certificate of Completion of Works as per the provisions of Clause 78 of General
Constructions of Contract shall not be issued by the Engineer in the event of Contractor's failure
to furnish aforesaid "As-Constructed" drawings for the entire works.
4.6 The Contractor shall promptly inform the Engineer of any error, omission, fault and other defects
in the Specifications, Drawings for the Works which are discovered when reviewing the Contract
Documents or in the process of execution of the Works.
5.0 DRAWING MANAGEMENT AT SITE
5.1 The Contractor shall ensure that all drawings meant for further engineering, fabrication, erection
and field work are issued to his personnel in a controlled manner - a proper record shall be
maintained to show to whom the drawing is issued and to ensure that the latest revisions of the
drawing is being followed for further work. All superseded drawings shall be promptly withdrawn
from the personnel to whom they are issued and stamped "SUPERSEDED" in RED. The
Contractor shall maintain a register of drawings, with their revision/issue number, as received
from the Engineer and a record of their distribution to the designated personnel within their
organization.
5.2 The Contractor shall maintain at Site a set of the drawings issued by the Engineer on which
changes shall be progressively marked and initialed by the Engineer so that "As-Built" drawings
can be made correctly and expeditiously at the end of their Work at Site.
6.0 COOPERATION WITH OTHER CONTRACTORS
(Supplemental to Clause 4.0 of SCC Part- I)
6.1 Agencies other than the Contractor shall also simultaneously execute works other than those
covered under this Contract in connection with the Project. The Contractor shall cooperate with all
such other agencies and allow full access to them to places of work.
6.2 During course of the Works the Contractor shall extend his facilities to other agencies working on
the same Project and shall enable incorporation of their works into his work. He shall provide
levels, grid alignments, thickness of finishing items, clearances etc. as may be required by the
Engineer, to enable other contractors to coordinate their work. The Contractor shall bring to the
notice of the Engineer, works to be carried out by others which would hold up the execution of his
work.
7.0 Deleted
8.1 The Contractor shall schedule his work to complete the same block-wise/area-wise/system wise,
should the Engineer so decide. Nothing extra shall be payable on this account.
9.1 The Contractor shall not display any name board for the works without the written permission of
the Engineer.
10.0 Deleted
11.0 Deleted
15.0 ACCOMMODATION, EQUIPMENT AND TRANSPORT FOR ENGINEER – (See Appendix IV)
17.0 SAFETY MEASURES AND REQUIREMENTS FOR THE OUTLINE SITE SAFETY PLAN -
(Appendix VI)
Appendix I
PROGRAMME REQUIREMENTS
1.1 GENERAL
(1) Purpose of Programme
The purpose for the requirement of Programme (Scheduling) information described in this
document is to provide the Engineer with status reports for managing, monitoring and
coordinating the awarded contract during the execution within the overall multi-contract
project schedule. It describes a series of reports to be submitted by the Contractor to the
Engineer during the execution of the contract, following the award of Contract.
(2) The Tenderer/ Contractor shall programme his work at all times to meet the Key
Dates and the Works Area Hand-over Dates specified in the tender documents and
the specified interface periods for the design and installation of the Works with
those of the Designated Contractors and shall during the progress of the Works
constantly monitor his progress against the programmes described below.
(3) The Tenderer/ Contractor shall include in all programmes his work obligations
towards shared access, shared Site areas and other coincident or adjacent Works
Areas.
(4) The Works Programme, and all more detailed or revised versions, shall be submitted
to the Engineer for his consent.
1.2 METHODOLOGY
(1) The computerized Critical Path Method (CPM) network using the Precedence Diagramming
Method (PDM), has been selected by the Employer as the technique for contract
management system and in coordinating the multi-contract project. This technique shall
also be employed by the Tenderer in preparing their Tender submissions and by the
Contractor in their Construction Stage submissions.
(2) Unless otherwise agreed by the Engineer, all programmes submitted by the Contractor
shall be produced using computerized Critical Path Method (CPM) Networks developed
implementing the Precedence Diagramming Method (PDM) with Cost Loaded Charts and
Tables.
(3) The Contractor shall implement and use throughout the duration of the Contract, a
computerized system to plan, execute, maintain and manage the planning, design, pre-
construction, construction, and sub-contracts in executing the CPM scheduling by PDM.
The reports, documents and data provided shall be an accurate representation of the
current status of the Works and of the work remaining to be accomplished; shall provide a
sound basis for identifying problems, deviations from the planned works, and for making
decisions; and shall enable timely preparation of the same for presentation to the Engineer.
1.3 PROGRAMME MANAGEMENT SOFTWARE
(1) CPM programming software used shall be Microsoft Project ,Version-2002 (MSP-
2002) or later. Any other compatible system capable of direct file interchange
capability with software program used by the Employer – can be used with
Engineer’s consent. Scheduling software and relevant instruction manuals, licensed
for use in connection with the contract, shall be provided by the Contractor
according to the Employer’s specifications for Engineer’s use.
(2) The Tenderer may use a system other than MSP-2002 but will be required to
demonstrate that full electronic data transfer to be available and that the various
(3) The Contractor shall supply the Engineer with an original licensed copy, including
manuals and approved training of the software and any subsequent versions thereof
at no extra cost.
1.4 SUBMISSIONS
1.4.0 The Contractor shall develop his Tender Programme into the Initial Works Programme including
an outline Narrative Statement and submit within 15 days of the date of issue of Letter of
acceptance and its more detailed version within 30 days of receiving the Engineer’s consent to
the proposed Initial Works Programme.
1.4.1 Activity in the initial works program should be arranged as per the Works Break Down Structure
(WBS) of the work. The WBS structure of the work would be developed by the contractor in
consultation with the Engineer .Contractor would get the WBS structure approved by the
Engineer.
1.4.2 The first Three Month Rolling Programme shall be submitted within 15 days of the date of issue
of Letter of acceptance and all subsequent editions shall accompany the Monthly Progress
Report. The Monthly Progress Reports shall also include a Programme Update as described
below. These programmes shall subsequently be updated as described below.
1.4.3 Following the Contractor’s Initial Works Programme submission but in any case no later than one(1)
months from the date of award of contract, the contractor shall make submissions of the detailed
Works Programme suitably amended to take into account the programmes of Designated
Contracts. It is the Contractor’s responsibility to ensure timely co-ordination with the Designated
Contractors to review, revise and finalize his Initial Work Programme so as not to affect the progress
of Works/ and or the works of the Interfacing Contractors. The resubmitted programme when
approved by the Engineer shall form the Baseline Programme against which actual progress of the
Contract shall be reckoned. As the work progresses, it may be necessary to update/ revise the
Baseline programme but such updating shall only be carried out with the prior consent of the
Engineer or when directed by them.
1.4.4 For Initial & Detail Work Programme submission, one (1) original and six (6) copies each of the
following Programmes and Reports shall be submitted to the Engineer:
a) Programme: Baseline CPM Network
b) Programme: Baseline Milestone based Cost Activity Schedule
c) Baseline Schedule Report
d) Narrative
e) Baseline Physical Progress ‘S’ curve
f) Baseline Resource Charts
1.4.5 The Engineer shall review and comment on the Contractor’s programmes and information submitted.
The Engineer will confirm his consent or otherwise of the submissions within thirty (30) calendar
days.
1.4.6 The Employer’s Representative shall require the Contractor to re-submit within thirty (30) calendar
days if he is of the opinion that the programmes and information submitted by the Contractor is
unlikely to meet the Contract key dates.
1.4.7 If in the opinion of the Engineer, any of the Contractor’s revised programmes or Baseline Schedule
Report is not acceptable, it shall be construed as a failure of the Contractor to meet a Milestone.
1.4.8 Notwithstanding the above, the Engineer may at any time during the course of the Contract require
the Contractor to reproduce the computer-generated Baseline Schedule Report described above to
reflect actual activity dates and generate schedules based upon “what if” statements. The initial
computer-generated report after receiving the Engineer’s consent will serve as the base against
which the contract progress will be measured. Any changes to the Report reflected in subsequent
Baseline Schedule Reports shall also require the Engineer’s consent.
1.4.9 Failure to include any element of work required for performance of the Contract shall not relieve the
Contractor from completing all works required under the Contract to achieve the original or any
extended key completion date.
1.5 WORKS PROGRAMME
(1) The Works Programme shall show the Contractor’s plan for organizing and carrying
out whole of the Works.
(2) The Works Programme shall be a computerized Critical Path Method (CPM) network
developed using the Precedence Diagramming Method (PDM) and shall be present in
bar chart and time-scaled network diagram format to a weekly or monthly time scale.
(3) Tasks in the Works Programme shall be sufficiently detailed to describe activities
and events that include, but are not limited to, the following:
(4) The Works Programme shall show achievement of all Key Dates. The Works
Programme shall also show all Milestones, but the Milestones shall not be taken as
imposing any constraints that in any way affect the logic or limit any other dates in
the programme.
(5) Activity descriptions shall be unique, describing discrete elements of work. Any
activity creating an imposed time or other constraint shall be fully defined by the
Contractor.
(7) Activity duration shall not exceed 15 days, unless otherwise consented to by the
Engineer, except non-construction activities such as submittals, submittal reviews,
procurement and delivery of materials or equipment. The Contractor shall submit
(9) Activity Report shall list all activities, and events in the Works Programme, sorted by
activity identification number.
The Activity Report shall include the following for each activity and event:
(a) Activity identification number and description,
(c) Early and late start, & early and late finish dates. Planned start and finish dates,
(g) Calendar.
The Narrative shall be a comprehensive statement of the Contractor’s plan and approach for
the execution of the Works and the achievement of key dates, handover dates, submission
dates and any intermediate dates. It shall incorporate outline method statements in respect of
major items of work. It shall fully explain the reasons for the main logic links in the Programme
and include particulars of how activity duration are established. This shall include estimated
quantities, production rates, hours per shift, work days per week and a listing of the major
items of Construction Equipment planned for use on the project. Activities, which may be
expedited by use of overtime or additional shifts, shall be identified and explained. A listing of
holidays, and other special non-work days being used for the computer reports shall be
included.
(11) Baseline Physical Progress ‘S’ Curve
The Contractor shall also submit a forecast Cumulative Physical Progress ‘S’ curve based on
the time-phased distribution of cost in the CPM Network Logic Diagram, expressed in
percentage terms. This ‘S’ curve shall be generated from the computerized CPM Network
Logic Diagram.
(12) Baseline Resource Charts
The Contractor shall also submit a Resource Charts, generated from the Contractor’s CPM
Network Diagram, showing the anticipated manpower and main Construction Equipment
usage during the execution of the Project.
All submissions of proposed Works Programmes subsequently, after approval of the Initial
Works Programme, shall include the actual physical progress of work and forecast of the
remaining work . Actual progress shall be stated in percent complete, remaining duration,
and actual start and finish dates for each activity in the Works Programme.
1.5 INITIAL WORKS PROGRAMME
(1) The Initial Works Programme submitted as under Clause 4.1 need not include the full
details given under Clause 1.5 above. It should be a condensed version with combined
activities of longer duration but must show clearly how the requirements of the Contract are
to be achieved in the initial work program should be arranged as per the Works Break
Down Structure (WBS) of the work. The WBS structure of the work would be developed by
the contractor in consultation with the Engineer. Contractor would get the WBS structure
approved by the Engineer . The outline Narrative Statement shall be in sufficient detail to
clearly show the Contractor’s intention.
(2) Within 30 days of the Engineer’s consent to the Initial Works Programme, the Contractor
shall submit to the Engineer an expanded and more detailed version of the Initial Works
Programme containing all of the information and detail required under Clause 1.4 above.
(3) Such submission shall make use of the Tender Programme submitted earlier but refined to
include the best estimates of dates for the work of Designated Contracts which has impact
on the Contractor’s programme. Such programmes shall be amended subsequently to
incorporate the actual dates/ schedule of the affecting contracts. It is the Contractor’s
responsibility to ensure timely co-ordination with the Designated Contractors to finalize the
Initial Programme, without affecting progress of the work.
1.6 WORKS PROGRAMME REVISIONS
(1) The Contractor shall immediately notify the Engineer in writing of the need for any
changes in the Works Programme, whether due to a change of intention or of
circumstances or for any other reason. Where such proposed change affects timely
completion of the Works or any other Key Date the Contractor shall within fourteen (14)
days of the date of notifying the Engineer submit for the Engineer’s consent its proposed
revised Works Programme and accompanying Narrative Statement. The proposed
revised Works Programme shall show the sequence of operations of any and all works
related to the change and the impact of changed work or changed conditions.
(2) If at any time the Engineer considers the actual or anticipated progress of the work
reflects a significant deviation from the Works Programme, he may request the
Contractor to submit a proposed revised Programme which together with an
accompanying Activity Report and Narrative Statement, shall be submitted by the
Contractor within fourteen (14) days after the Engineer’s instruction. The proposed
revised Works Programme shall show the sequence of operations of any and all work
related to the change and the impact of changed work or changed conditions.
(3) All activities that have negative float must be analyzed by the Contractor to identify the
impact on the timely completion of the Works or on the achievement of Key Dates.
(1) The Three Month Rolling Programme shall be an expansion of the current Works
Programme, covering sequential periods of three months. The Three Month Rolling
Programme shall provide more detail of the Contractor’s plan, organization and execution
of the work within these periods. In particular, the Contractor shall expand each activity
planned to occur during the next three (3) month period, if necessary to a daily level of
detail.
(2) The Three Month Rolling Programme shall be developed as a Critical Path Method (CPM)
network, and shall be presented in bar chart and time-scaled network diagram format. Bar
charts shall be presented on an A4 and time-scaled networks diagrams on an A1 size
reproducible media. Tasks in the programme shall be derivatives of and directly related to
tasks in the approved Works Programme.
(3) The Contractor shall describe the discrete work elements and work element inter-
relationships necessary to complete all works and any separable parts thereof including
work assigned to sub-contractors.
(4) Activity duration shall not exceed two (2) weeks unless otherwise consented to by the
Engineer.
(5) Each activity in the Three Month Rolling Programme shall be coded, or described so as
clearly to indicate the corresponding activity in the Works Programme.
(1) The Three Month Rolling Programme shall be extended forward each month as described
under Clause 1.5(1) above. Each submission of the Three Month Rolling Programme shall
be accompanied by a Programme Analysis Report, describing actual progress to date, and
the forecast for activities occurring over the next three-month period.
(2) If the Three Month Rolling Programme is at variance with the Works Programme, the
Programme Analysis Report shall be accompanied by a supporting Narrative Statement
describing the Contractor’s plan for the execution of the activities to be undertaken over the
three month period, including programme assumptions and methods to be employed in
achieving timely completion.
(3) The Contractor shall revise the Three Month Rolling Programme or propose revisions of the
Works Programme, or both, from time to time as may be appropriate to ensure consistency
between them.
Once a week, on a day mutually agreed to by the Engineer and the Contractor, a meeting will be
held to assess progress by the Contractor during the previous week. The Contractor shall submit
a construction schedule listing activities completed and in-progress from the previous week and
the activities scheduled for the succeeding two weeks based on the detailed Works Programme.
Copies of the schedule shall be submitted on A3 sized papers.
1.10 PROJECT CALENDAR
For the Project, the Contractor shall adopt 7 days a week calendar, identical calendar for the
purpose of programming and Execution of Works. Official documents shall be transacted during 5
days week – Monday through Friday, except for National (Govt. of India) Holidays. For Project
purposes, a week begins at 0001 hours on a Monday and ends at 2359 hours on a Sunday. The
completion of an activity or the achievement of an event when given a week number shall be
taken to mean midnight on the Sunday at the end of the numbered week. An access date or
activity start date when given as a week number shall be taken to mean 0001 hours on a Monday
of the Numbered week.
The Contractor shall submit, as part of its Staff Organization Plan, the names and required
information for the staff to be employed on Works Programming. The principal Works
Programmer shall hold reputable professional qualifications acceptable to the Engineer including
at least five (5) years relevant experience in programming civil engineeringconstruction works.
Others in the group shall have at least three (3) years experience in such work. The
programmers shall be employed by the Contractor full time on the Contract until the completion or
such earlier time the Engineer may give his consent.
The Contractor shall submit one (1) original and six (6) copies and one (1) reproducible (for
Programmes) of all submissions to the Engineer. All submissions shall be in A0, A1, A3 or A4 size,
as appropriate except as may otherwise be agreed by the Engineer. In addition, the computerized
programme and report shall be submitted in Compact Discs (CDs) (similarly for submissions required
under Clause 5.4).
The format for all Programme and Report submissions shall be strictly in accordance with the format
as stated herein or as requested by the Engineer.
2.0 MONTHLY PROGRESS REPORTS
2.1 GENERAL
(1) The Contractor shall submit to the Engineer, a Monthly Progress Report. This Report shall
be submitted by the end of each calendar month and shall account for all work actually
performed from 26th day of the last month and up to and including the twenty-fifth (25th) day
of the month of the submission. It shall be submitted in a format to which the Engineer
shall have given his consent and shall contain sections/sub-sections for, but not be limited
to, the topics listed in clauses below.
(2) A spreadsheet summarizing each Cost Center, the budget, costs incurred during the
period, costs to date, costs to go, cost forecast (total of costs to date and costs to go) and
cost variance (difference between cost forecast and budget).
(3) A spreadsheet indicating the status of all payments due and made.
(4) A report on of the status of any outstanding claims. The report shall in particular provide
interim updated accounts of continuing claims.
(a) The monthly Programme Update which shall be prepared by recording actual activity
completion dates and percentage of activities completed up to the twenty-fifth (25th ) of the
month together with estimates of remaining duration and expected activity completion
based on current progress. The Programme Update shall be accompanied by an Activity
Report and a Narrative Statement. The Narrative Statement shall explain the basis of the
Contractor’s submittal:
(i) Early Work and Baseline Submittals – explains determination of activity duration and
describes the Contractor’s approach for meeting required Key Dates as specified in
the Contract.
(ii) Updated Detail Programme Submittals – state in narrative the Works actually
completed and reflected along Critical Path in terms of days ahead or behind
allowable dates. Specific requirements of narrative are:
A report on the status of all Milestones due to have been achieved during the month and
forecasts of achievement of any missed Milestones, and those due in the next month.
2.7 In case of failure of the contractor to make submissions as per section 1.4 herein above, the
Employer/ Engineer shall retain 5% of the due progress payment till the submissions. For non-
submission of Monthly Update and Progress Reports as per Clause 2.0 herein above, the
Employer/ Engineer shall retain 5% of the due progress payment in each case which shall be
released upon submission o the same. In case the submissions are not made in the month it is
due, the retained payment would be released only in the next Monthly Running Bill.
(1) A review of all safety aspects during the month including reports on all accidents
and actions proposed to prevent further occurrence.
2.11 ENVIRONMENTAL
(1) A review of all the environmental issues during the past month to include all
monitoring reports, mitigation measures undertaken, and activities to control
environmental impacts.
Appendix II
QUALITY ASSURANCE
1.1 General
The Contractor shall implement a Project Quality Management Plan in accordance with ISO-9001
“Quality System – Model for Quality Assurance in Design/Development, Production, Installation
and Servicing” or any other system as approved by Engineer to ensure that all materials,
workmanship, plant and equipment supplied and work done under the contract meets the
requirements of the contract. This plan shall apply to all activities related to the quality of items,
including designing, purchasing, inspecting, handling, assembling, testing, storing, and shipping
of materials and equipment and different elements of construction work and installations of
system components.
The Quality Plan to be prepared by the Contractor and submitted to the Engineer shall follow the
requirements of ISO 9001 and address each element therein. This Quality Plan / QA manual,
specific to this work must be submitted with in one month of award of contract.
Running on account payment will be released after the following milestones are achieved and
Engineer has issued a ‘Notice of No Objection’ or a Notice of No Objection subject to
……(specifying the condition)’.
a. Release of on-account payment after two months of signing the contract agreement – On
submittal of QA Manual duly approved by Engineer (ER). Otherwise 10% of the running bill
be withheld till compliance.
b. Closure of Non-conformance Report – Action taken on non-compliance and its closure to
be ensured within 15 days of issue of non conformance report. In case of non closure of
report, running on-account bill will be with held @ 1 % of amount for every non closure, till
the same are closed satisfactorily.
c. Release of on-account payment after four months and thereafter every 3 months from the
date of start of work – On submittal of Internal Quality Audit Report duly reviewed by
Engineer and Action Taken Report. Otherwise 10% of the running bill be withheld till
compliance.
d. Release of Final bill – i. Closure of all non-conformance reports
ii. Submittal of all quality documented record pertaining
to monitoring and accountability including QA Manual
& Procedures
Registration of the Contractor’s organization, or subcontractors or sub-consultants is not required
for this Project but the Project Quality Management Plan as submitted shall meet the intent of the
ISO 9001 requirement in that there is a comprehensive and documented approach to achieving
the project quality requirements.
1.2 Quality Assurance Management Plan
The Project Quality Management Plan (PQMP) shall as a minimum address the quality system
elements as required by ISO 9001, generally noting the applicability to the Contractor’s Works
Programme for the Project. Procedures or Quality Plans to be prepared by others (Suppliers,
Subcontractors, Sub-consultants) and their incorporation in the overall PQMP shall be identified.
The Contractor shall provide and maintain a Quality Assurance Plan (QA) to regulate methods,
procedures, and processes to ensure compliance with the Contract requirements. The QA Plan,
including QA written procedures, shall be submitted to the Engineer for his review.
Adequate records shall be maintained in a readily retrievable manner to provide documented
evidence of quality monitoring and accountability. These records shall be available to Employer
at all times during the term of the Contract and during the Defects Liability Period and for a five
year period thereafter.
The Plan shall identify:
• Design Process: that control, check and verify the accuracy, completeness and integration
of the design shall be performed by certified personnel and in accordance with documented
procedure that have the written consent of the Engineer.
• Special Processes: that control or verify quality shall be performed by certified personnel
and in accordance with documented procedures that have the written consent of the Engineer;
• Inspection and Test: Inspection and testing instructions shall provide for reporting non-
conformances or questionable conditions to the Engineer; Inspection shall occur at appropriate
points in the installation sequence to ensure compliance with drawings, test specifications, process
specifications, and quality standards. The Engineer shall designate, if necessary, inspection hold
points into installation or inspection planning procedures;
• Receiving Inspection: These procedures shall be used to preclude the use of
nonconforming materials and to ensure that only correct and accepted items are used and installed;
• Identification and Inspection Status: a system for identifying the progressive inspection
status of equipment, materials, components, subassemblies, and assemblies as to their
acceptance, rejection, or non-inspection shall be maintained;
• Identification and Control of Items: an item identification and tractability control shall be
provided;
• Handling, Storage, and Delivery: provide for adequate work, surveillance and inspection
instructions.
The Plan shall ensure that conditions adverse to quality such as failures, malfunctions,
deficiencies, deviations, and defects in materials and equipment shall be promptly identified and
corrected.
The Plan shall provide for establishing, and maintaining an effective and positive system for
controlling non-conforming material including procedures for the identification, segregation, and
disposal of all non-conforming material. Dispositions for the use or repair of non-conforming
materials shall require the Engineers consent.
1.3 Plan Implementation and Verification
The Plan shall clearly define the QA Organization. Management responsibility for the QA shall be
set forth on the Contractor’s policy and organization chart. The Plan shall define the
requirements for QA personnel, their skills and training. Records of personnel certifications shall
be maintained and monitored by the QA personnel. These records shall be made available to the
Engineer for review, upon request.
The QA operations shall be subject to the Engineers, Employer or Employer’s authorized
representative’s verification at any time, including: surveillance of the operations to determine that
practices, methods and procedures of the plan are being properly applied; inspection to measure
quality of items to be offered for acceptance; and audits to ensure compliance with the Contract
documents.
The contractor’s Quality Audit Schedule shall be submitted to the Engineer for consent every
three months or more frequently as required.
The results of Quality Audits shall be summarized in the Contractor’s Monthly ---- reports.
The Contractor shall provide all necessary access, assistance and facilities to enable the
Engineer to carry out on-site and off-site surveillance of Quality Assurance Audits to verify that
the quality system which has the consent of the Engineer is being implemented fully and properly.
Appendix III
ENVIRONMENTAL PROTECTION REQUIREMENTS
1.1 GENERAL
(1) The Contractor shall conform to the Indian Environmental Laws and codes as applicable.
The current national standards established by the Ministry of Environment and Forest,
Government of India and other government agencies for control of environmental pollutants
such as air, water, noise and visual impacts/aesthetics shall be followed for compliance
during project construction.
(2) The Contractor shall comply with all enactments which shall include but are not limited to:
a. Environment Protection Act,1986
b. Air (Prevention and control of Pollution) Act,1981
c. Water (Prevention and Control of Pollution) Act,1974
d. Requirements of Delhi Urban Arts Commission and Central Vista Committee
(3) The provisions listed herein regarding Environmental Protection shall apply to and be
binding upon the Contractor for any works on the site and the persons employed by sub-
Contractors. The Contractor shall ensure that proper and adequate provisions to this end
are included in all sub-contracts placed by him.
(4) The provisions of this Appendix however, shall not be applicable in the case of emergency
works necessary for saving of life and property or safety of the Works.
(5) The Contractor has been issued with the Employer’s Environmental Quality Management
Manual. Within 4 weeks of notification of acceptance of the Tender, the Contractor shall
submit for review by the Engineer, his own contract specific Site Environmental Plan based
on the Employer’s Environmental Quality Management Manual and his construction
methodology
(6) This contract specific Site Environmental Plan of the Contractor shall be consistent with the
provisions of the Environmental Management Plan outline, as given in the Employer’s
Environmental Quality Management Manual.
(7) The Contractor shall undertake environmental monitoring as required under the contract,
including setting up of monitoring stations. The monitoring locations, frequency, and
reporting are given in the Employer’s Environmental Quality Management Manual.
(8) The Contractor shall ensure that audits of all the activities detailed in his Site Environmental
Plan are carried out at weekly intervals or at such intervals as the Engineer may require to
ensure the continuing effectiveness and compliance with the Site Environmental Plan. The
Contractor shall make available on request any document, which relates to his recent
internal audits.
(9) The Engineer may conduct quarterly Audits of the Contractor’s Site Environmental Plan
and its effective implementation on the works site. Not less than 2 weeks notice will be
given by the Engineer. During the audit by the Engineer, the Contractor shall provide
suitably qualified staff to accompany the auditor.
(10) Running on account payment will be released after the following milestones are achieved
and Engineer has issued a ‘Notice of No Objection’ or a Notice of No Objection subject to
……(specifying the condition)’.
a. Release of on-account payment after two months of signing the contract agreement –
On submittal of Site Environment Plan duly approved by Engineer Otherwise 10% of
the running bill be withheld till compliance.
b. Closure of Non-conformance Report – Action taken on non-compliance and its
closure to be ensured within 15 days of issue of non conformance report. In case of
non closure of report, running on-account bill will be with held @ 1 % of amount for
every non closure, till the same are closed satisfactorily.
c. Release of on-account payment after four months and thereafter every 3 months
from the date of start of work – On submittal of Environment Audit Report duly
Confidential SCC 54 of 93 ` December 2010
Contract DMRC/ELECT./IT&PD/ILBS/ELEVATOR/03 Special Conditions of Contract
reviewed by Engineer and Action Taken Report. Otherwise 10% of the running bill
be withheld till compliance.
d. Release of Final bill – i. Closure of all non-conformance reports
ii. Submittal of all environment documented record
pertaining to monitoring and accountability including
Environment Manual & Procedures
(11) Requirements established in this Appendix shall apply to all sites and all activities of the
Contractor, and shall supplement the Employer’s Requirements – Construction.
1.2 AVOIDANCE OF NUISANCE
The Contractor shall take all precautions to avoid any nuisance arising from his operations. This
shall be accomplished, wherever possible by suppression of nuisance at source rather than
abatement of the nuisance once generated.
(1) Following site clearing and before construction, the Contractor shall remove all trash, debris
and other weeds.
(2) The Contractor shall ensure that the work place is free of trash, garbage, debris and
weeds. He shall provide and ensure proper uses of refuse containers to ensure that
rodents, flee and other pests are not harbored and attracted.
(3) The Contractor shall provide at site, metal or heavy-duty plastic ‘Refuse Containers’ with
tight fitting lids for disposal of all garbage or trash associated with food. The containers
shall not have openings that allow access by rodents.
(4) To keep the area free of litter and garbage, specific locations shall be designated for
consuming food and snacks to prevent random disposal of waste. All waste shall be
deposited in the refuse containers described in (3) above. Suitable notice shall be
deployed prominently for strict compliance of these requirements.
(5) The refuse containers shall be kept upright with their lids shut tight. These containers shall
be emptied at least once daily by the Contractor to maintain site sanitation.
1.3 AIR QUALITY
(1) The Contractor shall take all necessary precautions to minimise fugitive dust emissions
from operations involving excavation, grading, clearing of land and disposal of waste. He
shall not allow emissions of fugitive dust from any transport, handling, construction or
storage activity to remain visible in atmosphere beyond the property line of emission source
for any prolonged period of time without notification to the Engineer.
(2) The Contractor shall use construction equipment designed and equipped to minimise or
control air pollution. He shall maintain evidence of such design and equipment and make
these available for inspection by Engineer.
(3) If after commencement of construction activity, Engineer believes that the Contractor’s
equipment or methods of working are causing unacceptable air pollution impacts then
these shall be inspected and remedial proposals shall be drawn up by the Contractor,
submitted for review to the Engineer and implemented.
(4) In developing these remedial measures, the Contractor shall inspect and review all dust
sources that may be contributing to air pollution. Remedial measures include use of
additional/ alternative equipment by the Contractor or maintenance/modification of existing
equipment of the Contractor.
(5) Dust generating materials shall be:
(i) Transported in closed containers or covered trucks.
(ii) Loaded and unloaded in closed systems or wind protected areas.
(iii) Watered as appropriate to minimise dust production.
(6) Contractor’s transport vehicles and other equipment shall conform to emission standards
fixed by Statutory Agencies of Government of India from time to time at Delhi. The
Contractor shall carry out periodical checks and undertake remedial measures including
replacement, if required, so as to operate within permissible norms.
(7) In the event that approved remedial measures are not being implemented and serious
impacts persist, the Engineer may direct the Contractor to suspend work until the measures
are implemented, as required under the Contract.
(8) The Contractor shall cover loads of materials, debris and soil transported from construction
sites. All trucks carrying loose material should be covered and loaded with sufficient free-
board to avoid spills through the tail board or side boards.
(9) The Contractor shall be responsible for ensuring that no earth, rock or debris is deposited
on public or private right of way as a result of his operations, including any deposits arising
from the movement of loaded/unloaded trucks and/or other construction vehicles.
(10) The Contractor shall make his own arrangements for water for purposes stated in above
clauses and wherever it may be required to control air pollution, dust and debris.
(11) The Contractor shall establish and maintain records of routine maintenance program for
internal combustion engine powered vehicles and equipment used on this project. He shall
keep records available for inspection by Engineer.
(12) The Contractor shall promptly transport all excavation disposal materials of whatever kind so
as not to delay work on the project. Stockpiling of materials will only be allowed at sites
designated by the Engineer.
(13) The Contractor shall protect structures, utilities, pavements and other facilities from
disfiguration and damage.
(14) The Contractor shall place excavation materials in the dumping/disposal areas designated in
the plans as given in the specifications.
(15) The temporary dumping areas shall be maintained by the Contractor at all times until the
excavate is re-utilized for backfilling or as directed by Engineer.
(16) The Contractor shall place material in a manner that will minimise dust production. Material
shall be stabilized each day and wetted, to minimise dust production.
(17) During dry weather, dust control methods must be used daily especially on windy, dry days to
prevent any dust from blowing across the site perimeter.
(18) The Contractor will make water sprinklers, water supply and water delivering equipment
available at any time that it is required for dust control use.
(19) Dust control activities shall continue even during any work stoppage.
(20) The Contractor shall water down construction sites as required to suppress dust, during
handling of excavation soil or debris or during demolition.
(21) At each construction site, the Contractor shall provide storage facilities for dust generating
materials and shall be:
(i) Closed containers/bins or;
(ii) Wind protected shelters or;
(iii) Mat covering or;
(iv) Walled.
Or any combination of the above to the satisfaction of the Engineer.
(22) The Contractor shall submit to the Engineer an Air Monitoring and Control Plan (AMCP)
under contract specific Site Environmental Plan to guide construction activity insofar as it
relates to monitoring, controlling and mitigating air pollution.
(2) The Contractor shall provide adequate precautions to ensure that no spoil or debris of any
kind is pushed, washed, falls or deposited on land adjacent to the site perimeter.
(3) In the event of any spoil or debris from construction works being deposited on adjacent
land any silt washed down to any area, then all such spoil, debris or material and silt shall
be immediately removed and the affected land and areas restored to their natural state by
the Contractor to the satisfaction of the Engineer.
(4) Due to lowering of potable water supplies in Delhi and subsequent contamination of ground
water, the Contractor is not allowed to discharge water from the site without the approval of
the Engineer. The Contractor must comply with the requirements of the Central Ground
Water Board for discharge of water arising from dewatering. Any water obtained from
dewatering systems installed in the works must be either re-used for construction purposes
and this water may subsequently be discharged to the drainage system or, if not re-used,
recharged to the ground water at suitable aquifer levels. The Contractor must submit his
proposals for approval of Engineer, on his proposed locations of dewatering of excavation
and collection of water for either construction re-use or recharge directly to aquifers. The
Contractor’s recharge proposals must be sufficient for recharging of the quantity of water
remaining after deduction of water re-used for construction. The Contractor will not be
permitted to directly discharge, to the drainage system, unused ground water obtaining
from the excavation without obtaining approval of Engineer or the Agency controlling the
system.
(5) The Contractor shall prevent soil particles and debris from entering the wells or water
discharge points by use of filters and sedimentation basins as required.
(6) The Contractor shall provide treatment facilities as necessary to prevent the discharge of
contaminated ground water.
(7) The Contractor shall at all times ensure that all existing stream courses and drains within,
and adjacent to the site are kept safe and free from any debris and any excavated
materials arising from the Works. The Contractor shall ensure that earth, chemicals and
concrete agitator washings etc. are not deposited in the watercourses but are suitably
treated and effluents and residue disposed off in a manner approved by local authorities.
(8) All water and waste products (surface runoff and wastewater) arising on the site shall be
collected and removed from the site via a suitable and properly designed temporary
drainage system and disposed off at a location and in a manner that will cause neither
pollution nor nuisance.
(9) Any mud slurry from drilling, grouting etc. shall not be discharged into the drainage system
unless treatment is carried out that will remove silt, mud particles, etc.
(10) The Contractor shall discharge wastewater arising out of site office, canteen or toilet
facilities constructed by him into sewers after obtaining prior approval of agency controlling
the system. A wastewater drainage system shall be provided to drain wastewater into the
sewerage system.
(11) Oil removal / interceptors shall be provided to treat oil waste.
(12) The Contractor shall take measures to prevent discharge of oil and grease during spillage
from reaching drainage system or any water body through Spill Prevention and Control
Plan.
1.5 NOISE
1.5.1 General
(1) The Contractor shall consider noise as an environmental constraint in his design, planning
and execution of the Works. The Contractor shall, at his own expense, take all appropriate
measures to ensure that work carried out by the Contractor and by his sub-Contractors,
whether on or off the Site, will not cause any unnecessary or excessive noise which may
disturb the occupants of any nearby dwellings, schools, hospitals, or premises with similar
sensitivity to noise.
(2) Without prejudice to the generality of the foregoing, noise level reduction measures shall
include the following:
(a) The Contractor shall ensure that all powered mechanical equipment used in the
Works shall be effectively sound reduced using the most modern techniques
available including but not limited to silencers and mufflers.
(b) The Contractor shall construct acoustic screens or enclosures around any parts of
the Works from which excessive noise may be generated.
(3) The Contractor shall ensure that noise generated by work carried out by the Contractor and
his sub-Contractors during day time and night time shall not exceed the maximum
permissible noise limits, whether continuously or intermittently, as given in the Employer’s
Environmental Quality Management Manual. The same may be varied from time to time by
and at the sole discretion of the Engineer, In the event of a breach of this requirement, the
Contractor shall immediately re-deploy or adjust the relevant equipment or take other
appropriate measures to reduce the noise levels and thereafter maintain them at levels
which do not exceed the said limits. Such measures may include without limitation the
temporary or permanent cessation of use of certain items of equipment.
(4) The noise monitoring requirements including monitoring locations are given in the
Employer’s Environment Quality Management Manual.
1.5.2 Control Requirements
Construction material should be handled and transported in such a manner as not to create
unnecessary noise as outlined below.
Under the Contract, the Contractor shall:
(1) Perform Work within the procedures outlined herein and comply with applicable codes,
regulations, and standards established by the Central and State Government and their
agencies.
(2) Keep noise to the lowest reasonably practicable level. Appropriate measures will be taken to
ensure that construction works will not cause any unnecessary or excessive noise, which
may disturb the occupants of any nearby dwellings, schools, hospitals, or premises with
similar sensitivity to noise. Use equipment with effective noise-suppression devices and
employ other noise control measures as to protect the public.
(3) Schedule and conduct operations in a manner that will minimize, to the greatest extent
feasible, the disturbance to the public in areas adjacent to the construction activities and to
occupants of buildings in the vicinity of the construction activities.
(4) The Contractor shall submit to the Engineer a Noise Monitoring and Control Plan (NMCP)
under contract specific Site Environmental Plan. It shall include full and comprehensive
details of all powered mechanical equipment, which he proposes to use during daytime and
nighttime, and of his proposed working methods and noise level reduction measures. The
NMCP shall include detailed noise calculations to demonstrate the anticipated noise
generation by the Contractor.
(5) The NMCP prepared by the Contractor shall guide the implementation of construction activity.
The NMCP will be reviewed on a regular basis and updated as necessary to assure that
current construction activities are addressed. It shall appear as a regular agenda item in
project coordination meetings.
1.6 WASTE
(1) The Contractor shall handle waste in a manner that ensures they are held securely without
loss or leakage thus minimizing potential for pollution.
(2) The Contractor shall remove waste in a timely manner. Scrap and waste material shall be
removed and disposed off at landfill sites after obtaining approval of Conservancy and
Sanitation Engineering Department of Municipal Corporation of Delhi for its disposal.
(3) Burning of wastes is prohibited. The Contractor shall not burn debris or vegetation or
construction waste on the site but remove it in accordance with (2) above.
(4) The Contractor shall maintain and clean waste storage areas regularly.
(5) If encountered or generated as a result of Contractor’s activity, then waste classified as
hazardous under the “Hazardous Wastes (Management & Handling) Rules, 1989” and
chemicals classified as hazardous chemicals under “Manufacture, Storage and Import of
Hazardous Chemical Rules,1989 of Environment (Protection) Act,1986 `shall be disposed
off in a manner in compliance with the procedure given in the rules under the aforesaid act.
1.7 PREVENTION OF MOSQUITO BREEDING
(1) Measures shall be taken to prevent mosquito breeding at site. The measures to be taken
shall include:
(a) empty cans, oil drums, packing and other receptacles which may retain water shall be
deposited at a central collection point and shall be removed from the Site regularly;
(b) still waters shall be treated at least once every week with oil in order to prevent mosquito
breading;
(c) Contractor’s Equipment and other items on the Site which may retain water shall be stored,
covered or treated in such a manner that water could not be retained.
(d) Water storage tanks shall be suitably provided.
(2) Posters in both Hindi and English which draw attention to the dangers of permitting
mosquito breeding shall be displayed prominently on the Site.
Appendix IV
Deleted
Appendix V
ENVIRONMENTAL QUALITY MANAGEMENT MANUAL
1.0 INTRODUCTION
1.1 The Environmental Quality Management Manual (EQM) forms an essential part of the overall
Environmental protection system employed by DMRC for the construction of Delhi MRTS project.
1.2 This manual is set out as follows:
• Section 2 highlights the purpose and scope of this Manual
• Section 3 outlines the objectives of the manual which will form a basis for Environmental
Management System
• Section 4 specifies the domain or contract application of this manual
• Section 5 lists the definitions and abbreviation of terms used in the manual
• Section 6 sets out the responsibilities for application of the procedures
• Section 7 provides guidance to the Contractor for preparation of his contract specific Site
Environmental Plan
• Section 8 focuses on the Environmental Performance Review of Contractor’s activities through
Environmental Audits
• Section 9 specifies the submittals as required in the manual
• Section 10 details the measures to control Air Pollution that shall be implemented by the
Contractor during construction phase
• Section 11 details measures to control water pollution
• Section 12 details measures that shall be implemented by the Contractor to control construction
noise
• Section 13 deals with waste pollution
• Section 14 details issues on landscape and aesthetics
• Section 15 on Environmental Monitoring lists the relevant impact monitoring equipment,
compliance criteria and monitoring programme to be undertaken by the Contractor during
construction
• Section 16 highlights the purpose of Event Contingency Plan which shall be prepared by the
Contractor for exceedance of limiting values
• Section 17 details requirements for impact monitoring for air quality including Air Monitoring and
Control Plan
• Section 18 details requirements for impact monitoring for noise including Noise Monitoring and
Control Plan
• Section 19 describes the Environmental Site Inspection process to be implemented by the
Contractor
• Section 20 details the Reporting requirements under this manual
• Section 21 sets out the Complaint response process
• Section 22 details when the Environmental Quality Management programme shall be
completed
2.0 PURPOSE & SCOPE
2.1 The purpose of this Environmental Quality Management Manual (EQM), is to make the Contractors
aware of the environmental concerns of DMRC, and to establish guidelines for the application of
environmental controls during the construction phase of the project.
2.2 This manual is intended to translate into practice, three important principles of DMRC's mandate --
that construction activities should not:
5.5 Monitoring is the use of direct or indirect reading field instrumentation to provide information
regarding the levels of pollutants released during construction.
5.6 Construction Site is the contract limits for construction. It shall be all the area within the limits of the
work as shown on the Plans. Construction site shall also include staging, and debris disposal areas
and transportation routes to and from these areas.
5.7 Noise is any unwanted sound disturbance of the environment around the area of construction
operations.
5.8 Decibel is a measure on a logarithmic scale of the magnitude of a particular quantity (such as
sound pressure, sound power) with respect to a standardized reference quantity).
5.9 A - weighted Noise levels in Decibels (referenced to 20 micro-Pascal) as measured with A-
weighting network of standard sound level meter, abbreviated dB(A).
5.10 Energy Equivalent Level (Leq) is the level of a steady noise, which has the same energy as the
fluctuating noise level integrated over the period of measurement. Lmax is the maximum Noise Level
during the period of measurement. L10 and L90 are the are the percentile exceeding levels of sound
which is exceeded 10% and 90% of the time of measurement.
5.11 Waste is unwanted surplus substances arising from the application of all construction operations
and any substance or article which is required to be disposed.
5.12 Suspended Particulate Matter is abbreviated as SPM and measured in µg/m3 .
5.13 Environmental Quality Management Manual is abbreviated as EQM.
5.14 Air Monitoring and Control Plan is abbreviated as AMCP.
5.15 Noise Monitoring and Control Plan is abbreviated as NMCP.
5.16 Ministry of Environment and Forest, Government of India is abbreviated as MOEF.
5.17 Central Pollution Control Board, New Delhi is abbreviated as CPCB.
6.0 RESPONSIBILITIES
6.1 The Employer or Engineer will monitor Contractor's performance of tasks specified, and will inspect
necessary records, reports and procedures as defined in this manual.
6.2 The Engineer will ensure that this procedure is followed by the institution of a monitoring and
reporting system that provides information about the environmental performance of the construction
contractor throughout the duration of the contract.
7.0 SITE ENVIRONMENTAL PLAN
7.1 To effectively implement mitigation, monitoring and remedial requirements, an appropriate
contractual and supervisory framework needs to be established.
7.2 This document, the EQM Manual, provides the scope for construction monitoring, the parameters to
be measured, the frequency of monitoring and the actions to be taken in the event of the
environmental parameters being exceeded.
7.3 The basis of framework within which implementation will be managed is through the preparation of
contract-specific Site Environmental Plans by the Contractor. The Engineer will audit the contract-
specific and advise the necessary remedial actions required through contractual means.
7.4 The Site Environmental Plan shall provide details of the means by which the Contractor (and all
subcontractors working for the Contractor) will implement the recommended mitigation measures
and achieve the environmental performance standards defined both in Indian environmental
legislation and in the Employer’s Requirements.
7.5 The primary reason for adopting the EQM Manual approach is to make the Contractor aware of his
environmental responsibilities and to ensure his commitment to achieving the standards specified.
7.6 Based on Environmental Management Plan outline given in this document, each Tenderer shall
prepare an Outline Environmental Plan for submission as part of the tender process.
7.7 The Outline Environmental Plan will demonstrate the determination and commitment of Contractor’s
organization towards environment and indicate how the environmental performance requirements
laid out in the Employer’s requirements documentation will be met and, where appropriate
exceeded.
7.8 Within 20 weeks of the date of Notice to Proceed, the Contractor shall submit a draft contract -
specific Site Environmental Plan for the approval of the Engineer and a final version prior to the
at the exits from each site. At such facility, high-pressure water jets will be directed at the
wheels of vehicles to remove all spoil and dirt. Wheel washing facilities will be provided with
efficient drainage, incorporating silt traps to prevent any excessive build up of water. These
facilities could include water re-circulation apparatus to minimise water consumption.
(3) The Contractor shall ensure that vehicles with an open load carrying area used for moving
potentially dust-producing materials shall have properly fitting side and tailboards. Materials
having the potential to create dust shall not be loaded to a level higher than the side and
tail boards, and shall be carried in vehicles fitted with cover lids or clean tarpaulin cover in
good condition. The tarpaulin shall be properly extended beyond side / tail board and
secured properly.
(4) Should dust problems continue to occur, the Contractor must be able to have controls in
place on 24-hour basis.
10.2 CONTROL REQUIREMENTS AT DUMPING SITES
(1) The Contractor shall place excavated materials in the dumping/disposal areas designated in
the drawings.
(2) The Contractor shall place material in a manner that will minimise dust production. Material shall be
stabilized each day by watering or other accepted dust suppression techniques.
(3) The heights from which materials are dropped shall be the minimum practical height to limit
fugitive dust generation.
(4) The Contractor shall stockpile the material in the locations designated by Engineer, with
suitable slopes. The area shall be enclosed on three sides with walls extending above the
height of stockpile. The fourth side shall be progressively covered even as material is being
placed at that site to required quantity. Thereafter, the site shall be accessible through a
lockable gate that shall allow for easy entry and exit of men, material and machines.
(5) During dry weather, dust control methods must be used daily especially on windy, dry days to
prevent any dust from blowing.
(6) The Contractor shall provide water sprinklers at any time that they are required for dust
control use.
(7) Sufficient equipment, water, and personnel shall be available on dumping sites at all times to
minimise dust formation and movements to prevent nuisance.
(8) Dust control activities shall continue during work stoppages.
10.3 CONTROL REQUIREMENTS AT CONSTRUCTION SITES
(1) The Contractor shall spray water at construction sites as required to suppress dust, during
handling of excavation soil or debris or during demolition.
(2) The Contractor shall implement dust suppression measures, which shall include, but not be
limited to the following:
(3) Stockpiles of sand and aggregate greater than 20 m3 for use in concrete manufacture shall
be enclosed on three sides, with walls extending above the pile and two (2) metres beyond
the front of the pile.
(4) Effective water sprays shall be used during the delivery and handling of all raw sand and
aggregate and other similar materials, when dust is likely to be created and to dampen all
stored materials during dry and windy weather.
(5) Areas within the Site where there is a regular movement of vehicles shall have an approved
hard surface that is kept clear of loose surface material.
(6) If conveyors are used, conveyor belts shall be fitted with windboards, and conveyor transfer
points and hopper discharge areas shall be enclosed to minimise dust emission. All
conveyors carrying materials that have the potential to create dust shall be totally enclosed
and fitted with belt cleaners.
(7) Unless the Engineer has given consent otherwise, the Contractor shall restrict all motorised
vehicles on the Site to a maximum speed of 15 kilometers per hour and confine haulage
and delivery vehicles to the designated roadways inside the Site.
(8) At the Batching plant the following additional conditions shall be complied with:
• The Contractor shall undertake at all times the prevention of dust nuisance as a result
of his activities.
• The Contractor shall frequently clean and water the concrete batching plant and
crushing plant sites and ancillary areas to minimise any dust emissions.
• Dry mix batching shall be carried out in a totally enclosed area with exhaust through
suitable fabric filters.
(9) The Contractor shall erect boarding at least 2 m high, securely around all construction work
sites during the main construction activity, when reasonably practicable, to contain dust
within the site area and also to reduce air turbulence caused by passing traffic.
10.4 CONTROL REQUIREMENTS DURING DRILLING AND BLASTING
(1) Watering should be undertaken to control dust during breaking of rock/concrete.
(2) During blasting operations, appropriate precautions should be taken to minimise dust such
as the use of blast nets, canvas covers and watering.
(3) Wire mesh, gunnysacks and sand bags should be used over blast area on each shot to
prevent flying rock and reduce dust.
(4) Fitting of blast doors at the portals may be used to control dust and debris from tunnel
works.
11.0 WATER POLLUTION CONTROL
11.1 A drainage system should be constructed at the commencement of the Works to drain off all
surface water from the work site into suitable drain outlet. Temporary drainage works should be
maintained, removed and reinstated as necessary, and all other necessary precautions should be
taken for avoidance of damage by flooding and silt.
11.2 Sedimentation tanks or other acceptable measures, of sufficient capacity to trap silt laden water
before discharge into the outlet drain should be provided. The system should be flexible and be
able to handle multiple inputs from a variety of sources.
11.3 Temporary open storage of excavated materials from cut and cover tunneling work used for backfill
on site should be covered with tarpaulin or similar fabric during rainy season or at any time of the
year when rainstorms are likely. Washout of construction or excavated materials should be
diverted to drainage system through appropriate sediment traps.
11.4 Bentonite slurries or other grouts used in diaphragm wall construction should be collected in a
separate slurry collection system. If reuse is not practicable then it should be disposed off at
nearest landfill site after obtaining permission from agency owning the landfill and under the
conditions imposed by the agency concerned.
11.5 The Contractor shall discharge wastewater arising from site offices, canteens or toilet facilities
constructed by him into sewers after obtaining prior approval of agency controlling the system. A
wastewater drainage system shall be provided by the Contractor to drain wastewater into the
sewerage system.
11.6 Oil separator / interceptors shall be provided to prevent the release of oils and grease into the
drainage system. These shall be cleaned on a regular basis.
11.7 A Spill Prevention and Control Plan (SPCP) in the site Environmental Plan shall be prepared to
identify project components such as storage areas, storage tanks that could allow discharge of oil
or grease or hazardous materials to the drainage system or ultimately in any water body during
spillage. The volume of spill should be calculated as well as storage volume to contain spill within
the materials storage containment areas. The Plan shall contain a written description of the actions
that will be taken in order to prevent, contain and mitigate transportation of oil, grease or hazardous
materials to the drainage system or any water body.
12.0 NOISE CONTROL
12.1 To the extent required to meet the noise limits the Contractor shall use reasonable efforts to include
noise reduction measures listed below to minimize construction noise emission levels. Noise
reduction measures – Include, but not be limited to the following:
(a) Scheduling truck loading, unloading, and hauling operations so as to minimize noise impact
near noise sensitive locations and surrounding communities.
(c) Locating stationary equipment so as to minimize noise impact on the community.
(c) Equipment and plant are not to be kept idling when not in use.
(d) Use only well maintained plant at site, which should be serviced regularly.
(e) Plant and equipment known to emit noise strongly in one direction should, where possible, be
oriented in a direction away from noise sensitive receptor
(f) Silencers and mufflers on construction equipment should be properly fitted and maintained.
(g) Reducing the number of plant and equipment operating in critical areas close to noise
sensitive receptors.
(h) Limiting the use of enunciators or public address systems, except for emergency notifications.
(i) Maintaining equipment such that parts of vehicles and loads are secure against vibrations
and rattling.
(j) Limit the time that temporary street decking or covered excavated areas are in use.
(k) Maximize physical separation between noise generators and noise receptors
(l) Grading of surfaced irregularities on construction sites to prevent the generation of impact
noise and ground vibrations by passing vehicles.
(m) Schedule work to avoid simultaneous activities that both generate high noise levels.
(n) The construction of temporary physical noise barriers
(o) If back-up alarms are used on construction equipment, their noise emission level near
noise sensitive receptors such as residences, schools, hospitals and similar areas where
quiet is essential, should be regulated, especially at night time.
13.0 WASTE CONTROL
13.1 The transportation and disposal of all waste shall be strictly managed.
13.2 The transportation of construction spoil shall be allowed only to officially designated dumpsites after
obtaining necessary permission from appropriate authority.
13.3 A procedure to facilitate tracking of loads should be developed to prevent illegal disposal of waste.
13.4 Careful design, planning and good site management can minimise waste of materials such as
concrete, mortars and cement grouts.
13.5 The design of formwork should maximise use of wooden panels so that high reuse levels can be
achieved.
13.6 Construction waste should be segregated as much as possible at site to increase the feasibility of
recycling. Concrete and masonry can be used for filling material while steel bars can be used by
scrap steel mills.
13.7 Litter disposal and collection points should be established around all construction work sites.
14.0 LANDSCAPE AND AESTHETICS
14.1 The construction of the railway line will have negative but temporary impacts on the landscape and
aesthetics due to loss of amenities and trees. Large scale construction activity will impact
negatively on roadside areas and residential communities immediately adjacent to the construction
sites.
14.2 However, transplanting, replanting of trees and additional landscape treatment along the rail
corridor is likely to result in long-term beneficial impacts.
14.3 Lights used for construction lighting can illuminate adjacent areas in undesired ways. Such lighting
and glare shall be prevented from striking adjacent areas, where feasible, through directional
shielding.
14.4 The other measures include but not limited to:
(1) Erection of decorative screen hoarding prominently displaying the logo of Delhi Metro Rail
Corporation and other suitable things.
(2) Minimizing height of temporary buildings.
(3) Careful positioning of construction equipment.
15.0 ENVIRONMENTAL MONITORING
15.1 The Contractor’s Environmental Team shall carry out the monitoring of environmental impacts
during construction. Representative sensitive receivers in the vicinity of the works shall be
monitored for noise and air quality impacts.
15.2 For carrying out impact monitoring for noise and air, equipment shall be provided, operated and
maintained by the Contractor. The equipment shall be kept in a good state of repair in accordance
with the manufacturer’s recommendations and maintained in proper working order with sufficient
spare equipment available in the event of breakdown to maintain the planned monitoring
programme.
15.3 The calibration of monitoring instruments and their respective calibrators shall be carried out in
accordance with the manufacturer’s requirements to ensure they perform to the same level of
accuracy as stated in the manufacturer’s specifications.
15.4 Suspended Particulate Matter (SPM) levels shall be measured by following the standard high
volume sampling method as set out in High Volume Method for Suspended Particulate, BIS: 5182-
1981
15.5 24-hour average SPM concentration shall be measured by drawing air through a High Volume
Sampler (HVS) fitted with pre-weighted Glass Fiber filter paper at an average flow rate not less than
1.1m3 per minute.
15.6 The minimum requirements to the specifications of sound level meter are given in IS: 9779-1981
15.7 Engineer will undertake baseline monitoring to establish background levels. Action Level of the
Contractor shall be based on the results of baseline monitoring programme, which will be made
available to him prior to start of construction.
15.8 The Contractor’s monitoring programme is summarized in Table –1.
TABLE-1
17.13 Where the recorded baseline levels exceed the ambient air quality standards, then at such
locations the action level is the recorded base line. Contractor shall take all effective remedial
measures to contain the levels to their baseline value as a result of his activities. The action level
may be varied by and at the sole discretion of the Engineer.
17.14 The Contractor shall inform the Engineer of all steps taken to investigate cause of exceedance and
immediate action taken to avoid further exceedance through written reports and proposals for
action under an Event Contingency Plan.
18.0 NOISE MONITORING
18.1 The activities which are expected to cause noise during the construction of MRTS, Delhi include
noise from construction equipment, construction activities such as portal construction, earthwork
excavation, concreting, viaduct construction and removal of spoil and movement of construction
vehicles and delivery vehicles traveling to and from the construction and disposal sites.
18.2 The level of impact of these noise sources depends upon the noise characteristics of the equipment
and activities involved, the construction schedule, and the distance from noise sensitive receptors.
18.3 The Noise Monitoring and Control Plan (NMCP) in contract specific site Environmental Quality
Management Plan prepared by the Contractor shall establish procedures to monitor construction
noise and determine when to apply measures to control noise pollution due to construction activities
at work sites.
18.4 The NMCP will provide site description, define acceptable noise monitoring equipment, provide siting
and operating procedures for noise equipment, indicate reports and record keeping on noise
monitoring data.
18.5 The NMCP will provide guidance for construction activity. It shall also address noise performance
criteria used in the selection of construction equipment.
18.6 The Noise Monitoring and Control Plan shall provide for:
a) Definition of noise-sensitive uses in the zones affected by construction.
b) Calculation of future noise levels at the closest noise-sensitive receptors to the construction
activity based on construction activity and ambient noise levels.
c) Evaluation and specification of the noise abatement measures that can be applied to meet
the noise objectives.
d) Monitoring construction activity and providing adjustments to noise abatement controls that
may be required to increase their effectiveness
e) Regular reporting
f) Requirements of NMCP:
(i) It shall specify the nighttime and daytime construction activities, monitoring locations,
equipment, procedures, and schedule of measurements and reporting methods to be
used.
(ii) It shall contain a scaled plan indicating monitoring locations, including measurements
to be taken at construction site boundaries and at nearby residential zones.
(iii) A record of the noise characteristics of powered mechanical equipment proposed to
be used during day time and night time and of proposed working methods and of
potential noise level reduction measures.
(iv) Provisions for immediate notification when measured noise levels exceed allowable
limits,
(v) Provide a reporting procedure whereby noise-monitoring data is furnished to the
Engineer on a weekly basis.
18.7 In defining the requirements of the NMCP, available measures for noise control, such as, the use of
equipment with special exhaust silencers or enclosures, and the construction of temporary enclosures
or noise barriers around specific construction site activity areas shall be considered.
18.8 If the measured noise levels exceed the noise limits, the noise levels shall be reduced by appropriate
abatement measures.
18.9 The NMCP will be reviewed on a regular basis and updated as necessary to assure current
construction activities are addressed.
18.10 The Engineer shall monitor Contractor’s performance of tasks specified, and will inspect necessary
records, reports and procedures related to the control of noise.
18.11 Impact monitoring shall be carried out at noise sensitive receptor locations within 200 feet of the
construction site once each week and after a change in construction activity. Construction noise
measurements shall coincide with daytime and nighttime periods of maximum noise generating
construction activities.
18.12 Noise monitoring data will be submitted in a Noise Measurement Report Form. It will contain the
type of measurement, duration of measurement, distance of monitoring from construction site, and
construction equipment working during monitoring period.
18.13 The appropriate parameter for measuring construction noise impacts shall be the equivalent A-
weighted sound pressure level (Leq) measured in decibels (dB). The two statistical sound levels L10
and L90 ; the level exceeded for 10 and 90 percent of the time respectively, shall also be recorded
during monitoring. The L90 may be considered as the ambient level into which the L10 as average
peak level intrudes. The Lmax, Leq, L10 and L90 values will be reported in the noise measurement
form along with allowable noise limit. The duration of monitoring shall be for a minimum of 30
minutes.
18.14 In no case shall the Contractor expose the public to construction noise levels exceeding
90dBA(slow) or to impulsive noise levels with a peak sound pressure level exceeding 140dB as
measured on an impulse sound level meter.
18.15 Limit for construction noise is based on the existing ambient noise levels in areas adjoining the
construction sites.
18.16 The noise levels emanating from any source during construction, shall not exceed 5 dB(A) or more
above existing ambient pre-construction noise levels when measured at a point outside the
premises of the location of source. The same may be varied from time to time by and at the sole
discretion of the Engineer.
18.17 Where there are no ambient noise measurements, the construction activities shall be limited to
levels measured at a distance of 200 feet from the construction limits or at the nearest affected
building, whichever is closer, as given in Table-2.
TABLE-2
ALLOWABLE CONSTRUCTION NOISE
LAND USE MAXIMUM NOISE LEVELS- Lmax dB(A)
Day Time Night Time
Residential 75 65
At all Times
Commercial 85
Industrial 90
18.18 The ground borne noise levels within building structures due to tunnel boring machine and any
other underground and tunneling construction activities shall not cause interior noise levels to
exceed the levels given below as measured in the inside of the affected noise sensitive structure:
Residential: Lmax 55dB(A)
Commercial: Lmax 60dB(A)
18.19 At the surface of the construction site during night time hours, the Contractor shall use only
equipment that operating under full load meets the noise limits specified in Table-3, if a sensitive
receptor would be affected.
TABLE-3
NOISE EMISSION LIMITS FOR CONSTRUCTION EQUIPMENT USED DURING
NIGHTTIME HOURS; MEASURED AT 50 FEET FROM CONSTRUCTION EQUIPMENT*
Backhoe 80
Bar Bender 75
Chain Saw 81
Compactor 80
Compressor 80
Concrete Mixer 85
Concrete Pump 82
Crane 85
Dozer 85
Front End Loader 80
Generator 82
Gradall 85
Grader 85
Paver 85
Pneumatic Tools 85
Scraper 85
Tractor 84
Noise emission limits apply to equipment used at surface of the construction site during
night time hours of 9 p.m. to 6 a.m.
18.20 The adjustments for close in equipment noise measurement shall be made in accordance with Table-
4.
TABLE – 4
ADJUSTMENTS FOR CLOSE-IN EQUIPMENT NOISE MEASUREMENTS
(Measurement Values to be subtracted from Measured Sound)
18.21 When Diesel Generator (DG) Sets are used for operation of equipment and machinery, then
‘Standards and Guidelines for control of Noise Pollution from Stationery DG Sets’, under
Environment (Protection) Act, 1986 shall apply.
18.22 Should the impact monitoring record noise levels which are:
• Indicative of a deteriorating situation such that closer monitoring is reasonably
indicated, or
• When in the opinion of the Engineer additional measurements are required in
view of deteriorating noise environment,
then, the Engineer may require the Contractor to increase the frequency of impact monitoring at
any one or more of the monitoring stations until the results indicate an improving and acceptable
level of noise.
18.23 The Contractor shall submit a copy of monitoring results. The results should represent a statistical
evaluation of data for evaluation of trends and comparison with noise emission standards.
18.24 Where the Engineer determines that the recorded Noise level is significantly greater than the
acceptable levels, the Engineer may direct the Contractor to take effective remedial measures
including, but not limited to, reviewing noise sources and modifying working procedures.
18.25 The Contractor shall inform the Engineer of all steps taken to investigate cause of exceedance and
immediate action taken to avoid further exceedance through written reports and proposals for
action under an Event Contingency Plan.
19.0 ENVIRONMENTAL SITE INSPECTION
19.1 As indicated earlier in this Manual, the Engineer shall undertake regular audits at quarterly
intervals, of the Contractor’s onsite practices and procedures as a means of assessing the ongoing
performance of the Contractor.
19.2 The criteria against which the audits will be undertaken shall be derived from the clauses within the
Employer’s Requirements – Appendix III, contract-specific Site Environmental Plan and previous
site inspection results as given in 6.0 of this manual.
19.3 In addition to the quarterly audits by the Engineer, site inspection shall be undertaken by the
Contractor’s staff to inspect the construction activities in order to ensure that appropriate
environmental protection and pollution control measures are properly followed and implemented.
19.4 The frequency of site inspection shall be at least once a week.
19.5 The Contractor shall prepare an ‘Environmental Inspection and Action Reporting System’ and
submit to the Engineer for approval and make amendments as suggested. It shall contain a
contract specific comprehensive Environment Inspection checklist as requirement of Site
Environmental Plan.
19.6 The area of inspection shall not be limited to environmental compliance within the site but areas
outside the site which are likely to be affected, directly or indirectly by activities at site.
19.7 Results of inspection shall be discussed with Resident Engineer and his recommendations on
better environmental protection shall be notified to the Contractor for taking immediate action and
rapid resolution of identified non-compliance.
19.8 If significant environmental problems are identified or if there is an environmental complaint or as a
part of investigation work, then the Engineer shall also carry out Ad hoc site inspection which shall
be attended by Contractor’s Representative.
20.0 REPORTING SYSTEM
20.1 Reporting under the Environmental Management System will contain results of monitoring and
inspection programmes.
20.2 In Site Environmental Plan, the Contractor shall prepare and submit monthly Environmental Quality
Management Reports in accordance with Employer’s Requirements.
20.3 The monthly report shall include (but not limited to) the following:
• Executive Summary
• Brief mention of construction activities
• Monitoring results under AMCP, and NMCP
• Interpretation of monitoring results, significance and influencing factors
Appendix VI
SAEFETY MEASURES AND REQUIREMENTS FOR THE OUTLINE SITE SAFETY PLAN
(1) The Contractor shall comply with all safety and industrial health legislation including, without limitation,
the Rules and Regulation of the National Safety Council of India.
(2) The Contractor shall keep on the Site copies of safety and industrial health regulations and documents.
All regulations and documents referred in this Clause 6(5) shall be translated into languages which are
understood by the operators engaged by the Contractor or sub-contractors (unless the Engineer
consents to the contrary) and such translations shall be displayed or kept alongside those in Hindi and
English languages.
(1) The Contractor shall, within 112 days of the date of Notice to Proceed, prepare and submit to the
Engineer for review his proposed safety plan which shall contain as a minimum those items set out
in Project Safety Manual and as detailed in Appendix 20 of the Employer’s Requirements.
Safety Personnel
(1) The Contractor shall appoint a Safety Officer whose duties throughout the period of the Contract shall
be entirely connected with the safety and industrial health aspects of the Contractor's activities on the
Site. The Safety Officer shall be a suitably qualified and experienced person who shall supervise and
monitor compliance with the Site Safety Plan. The Safety Officer shall, in particular but without
limitation, carry out auditing of the operation of the Site Safety Plan in accordance with a rolling
programme to be submitted, from time to time, to the Engineer for his consent. The Safety Officer's
appointment shall be within twenty eight (28) days of the date of acceptance of Tender and shall be
subject to the Engineer's written consent.
(2) The Contractor shall not undertake any works on the Site until the Safety Officer has commenced
duties in Delhi and unless the Engineer has specifically consented in writing.
(3) The Contractor shall not remove the Safety Officer from the site without the express permission of the
Engineer. Within fourteen (14) days of any such removal or notice of intent of removal, the Contractor
shall nominate a replacement Safety Officer for the Engineer's consent.
(4) The Contractor shall provide the Safety Officer with supporting staff in accordance with the staffing
levels set out in the Site Safety Plan. The supporting staff shall include at least one (1) Deputy Safety
Officer whose appointment(s) shall be subject to the Engineer's consent under similar criteria to those
contained under Clause 6(8) above. The Deputy Safety Officer(s) shall be capable of assuming the
duties and functions of the Safety Officer as contained in the Site Safety Plan whenever necessary.
(5) The Contractor shall empower the Safety Officer and safety staff to instruct employees of the
Contractor or of its sub-contractors of any tiers to cease operations and take urgent and appropriate
action to make safe the Site and prevent unsafe working practices or other infringements of the Site
Safety Plan or the statutory regulations.
(6) The Contractor shall ensure that the Safety Officer maintains a daily site safety diary, such diary
comprehensively recording all relevant matters concerning site safety, safety inspections and audits,
safety related incidents and the like. The site safety diary shall be reviewed and signed on a weekly
basis by the site agent and shall be available at all times for inspection by the Engineer.
(7) The Contractor's Staff Organization Plan shall show direct lines of communication and reporting
between the Safety Officer and the site agent and between the Safety Officer and the director
responsible for the Contract. The Contractor shall instruct and require the Site Agent and the Director
responsible to be directly accountable in all matters concerning site safety.
(1) The Contractor will conduct site safety inspections at a regular frequency. The findings of
the inspections shall be recorded on suitable forms which shall be kept available for
inspection by the Engineer.
(1) The Contractor shall submit regular site safety reports to the Engineer in accordance with
the Site Safety Plan. Such reports shall be submitted as part of the Monthly Progress
Report. Prior to submission, the site safety report shall be endorsed by the director
responsible for the Contract and the site agent. Site safety reports shall comprehensively
address all relevant aspects of site safety and industrial health regulation and, in particular,
report on all site safety audits undertaken during the period covered by the report.
(2) The Engineer shall be notified by the Contractor immediately of occurrence of any
accidents whether on-site or off-site in which the Contractor, its personnel or plant, or those
of its sub-contractors are directly or indirectly involved and which results in any injuries to
any persons. Such initial notification may be verbal and shall be followed by a written
comprehensive report within 24 hours of the accident.
Additionally the Contractor shall notify the Engineer in writing within twenty-four (24) hours
of any incident occurring whether on-site or off-site at which the Contractor or any sub-
contractors are involved and could have resulted in serious injuries to persons or significant
damage to the Works.
1.5 Sub-Contractors
(1) The Contractor shall provide its sub-contractors with copies of the Site Safety Plan and
shall incorporate into all sub-contract documentation provisions to ensure the compliance
with such plan at all tiers of the sub-contracting.
(2) The Contractor shall, unless the Engineer's consent in writing is given; require all sub-
contractors to appoint a safety representative who shall be available on the Site throughout
the operational period of the respective sub-contract. In the event of the Engineer's
consent being given, the Safety Officer or safety staff, without prejudice to their other duties
and responsibilities, shall ensure, as far as is practically possible, that employees of sub-
contractors of all tiers are conversant with appropriate parts of the Site Safety Plan and the
statutory regulation.
(1) The Contractor shall convene regular safety meetings in accordance with the Safety Plan
and shall require attendance by the Safety Officer and safety representatives of sub-
contractors unless otherwise agreed by the Engineer. All safety meetings shall be notified
in advance to the Engineer who may attend in person or by representative at his discretion.
The minutes of all safety meetings shall be taken and sent to the Engineer within seven (7)
days of the meeting.
(2) A site safety management committee may be established by the Engineer to monitor the
implementation of the safety plan and for the purpose set out in the Project Safety manual.
The Engineer or his representative will be chairman of this committee and the members
shall include the Contractor's agent or representative, Safety Manager and Safety Officers,
sub-contractors' Safety personnel.
(1) The Contractor shall ensure that safety equipment and protective clothing as described in
the Safety Plan is available and used on the site at all material times and that measures for
the effective enforcement of proper utilization and necessary replacement of such
equipment and clothing is incorporated into the Site Safety Plan.
(2) The Contractor shall regularly inspect, test and maintain all safety equipment,
scaffolds, guard-rails, working platforms, hoists, ladders and other means of access and
egress, lifting, lighting, signage and guarding equipment. Lights and signs shall be kept
clear of obstructions and legible to read. Equipment that is damaged, dirty, incorrectly
positioned or not in working order shall be repaired or replaced immediately.
(1) The Contractor shall establish, maintain, staff, and fully equip a first aid base as detailed
below:
(i) The first aid base shall be located at the Contractor’s principal works Area. The
base shall consists of a treatment room fitted with two treatment couches, a hand
basin, sterilizing equipment and lockable cupboards to contain sufficient medical
supplies for first-aid for the Contractors workforce, the Engineer’s site supervisory
staff, the Designated Contractors work force in the area and any visitors to the site.
In addition, six stretchers shall be stored, available for instant use. The first aid
base shall contain a recovery room that shall be furnished with six chairs and six
footrests. The first aid post shall be air-conditioned, with cooling capability sufficient
to maintain the temperature of the inside of building at 20oC.
(ii) Portable first aid boxes will be maintained fully equipped at each of local site offices
and work location where 20 or more persons work at a time. In each site office and
location at least one employee of contractor trained in first aid should be available
at all working hours for purpose of attending to emergencies.
(iii) The contractor shall maintain necessary tie up with near by hospital to attend and
give medical attention during emergencies.
(1) The Contractor shall ensure that safety, rescue and industrial health matters are given a
high degree of publicity to all persons regularly or occasionally on the Site. Posters, in both
Hindi and English, drawing attention to site safety, rescue and industrial health regulation
shall be made or obtained from the appropriate sources and shall be displayed prominently
in relevant areas of the Site. These posters shall be changed on a monthly basis in order
to ensure their continued impact.
1.10 Training
(1) The Contractor shall conduct regular safety training and rescue training drills, the
frequency, coverage and application of which shall be in accordance with the Site Safety
Plan, and in any case shall not be more than every six months. The Contractor shall
require that all sub-contractors' employees participate in relevant training courses
appropriate to the nature, scale and duration of the sub-contract works.
(1) Any employees of the Contractor or sub-contractor of any tiers who commit a serious
breach of the safety regulations shall be liable to summary dismissal and shall not be re-
employed on the Contract or allowed on any of the Sites. The due notice of this sanction
shall be prominently displayed on the Site.
(1) All plant and equipment used on or around the Site shall be fitted with appropriate safety
devices which shall be operational at all times and shall be regularly inspected and tested.
These shall include amongst others:
(i) Effective safety catches for crane hooks and other lifting devices.
(ii) Functioning automatic warning devices and, where applicable, an up-to-date test certificate,
for cranes and hoists.
(iii) All plant and equipment used on or around the Site shall be operated by suitably trained
and qualified personnel.
(1) The Contractor shall provide and maintain safe mechanical cranes, hoists and conveying
facilities for the lifting and transport of materials and shall comply with all relevant
requirements of BS 7121, Code of Practice for Safe Use of Cranes. All cranes, hoists and
the like shall be fitted with audible overload warning devices. All such equipment shall be
regularly maintained in accordance with manufacturers' recommendations and standards
having regard to local legislation and recommendations from the appropriate statutory
authority.
(2) Prior to use on Site, all lifting appliances and lifting gear shall be tested to an approved
safety margin and suitably identified in accordance with the requirements of the current
legislation. The test certificate shall be submitted to the Engineer for review prior to the use
of such equipment on Site.
(3) The safe working load shall be clearly and indelibly marked on all lifting appliances and
lifting gear either by stamping or by the addition of permanently secured tag labels.
Stamping shall not be permitted on any stress-bearing part.
(4) The Contractor shall prepare and maintain an up-to-date register containing test certificates
of all lifting and hoisting equipment used on the Works. The Contractor shall notify the
Engineer of the person responsible for maintaining this register. The register shall, from
the commencement of construction, be available on Site for inspection by the Engineer and
Relevant Authorities.
(5) Heavy plant or equipment which does not come under the jurisdiction of any local statutory
legislation shall be subject to the testing and examination requirements as recommended
by its manufacturer or in the absence of such, it shall be the responsibility of the Contractor
to submit a standard or method of testing and examination to the Engineer for review.
(6) Competent operators with certificates certifying that the proposed operator has received
training in the general principles of crane operation and specific training in the type of lifting
or hoisting equipment he is required to operate shall be provided for the control of all lifting
and hoisting equipment. At least one trained banksman shall be in attendance at each
lifting or hoisting installation.
(7) The Contractor shall provide and maintain all necessary temporary fire protection and fire
fighting facilities on the Site during the construction of the Works, and shall comply with all
requirements of the Delhi Fire Services Department. These facilities may include, without
limitation, sprinkler systems and fire hose reels in temporary site buildings, raw water
storage tanks and portable fire extinguishers suitable for the conditions on the Site and
potential hazards.
(8) The Contractor shall submit details of these facilities to the Engineer for review prior to
commencement of work on the Site.
(9) If, in the Engineer's opinion, the use of naked lights may cause a fire hazard, the Contractor
shall take such additional precautions and provide such additional fire fighting equipment
(including breathing apparatus) as the Engineer considers necessary. The term "naked
light" shall be deemed to include electric arcs and oxyacetylene or other flames used in
welding or cutting metals.
(10) Oxyacetylene burning equipment will not be permitted in any confined space. Burning
equipment of the oxypropane type shall be used.
(1) The Contractor shall ensure that all gases, fuels and other dangerous goods are stored and
handled in a safe manner and in accordance with the statutory regulations and as required
by the Engineer. The Contractor shall be responsible for obtaining the requisite licenses
and permission to store and handle such substance
(2) No use of radioactive substances and radiating apparatus or operation involving ionizing,
electromagnetic radiation or X-rays shall be carried out without the prior consent of the
Engineer. The Contractor shall ensure that all personnel and members of the public are
properly protected from the effects of any such radiation. Each radiation area shall have
conspicuous signs and barriers.
(3) The Contractor shall submit for review by the Engineer details of the training given to
nominated employees on the safe use, handling, transport and storage of dangerous
goods, radioactive substances, radiation and X-ray equipment prior to their introduction on
Site. Such training shall include the necessary measures to be taken in case of
emergency.
(2) The Contractor shall, prior to the commencement of any operation carry out a detailed
hazard and risk assessment. The results of such assessments shall be recorded and the
records kept for inspection by the Engineer.
(3) The Contractor shall produce detailed method statements for all medium and high risk
operations and shall submit them to the Engineer for his consent prior to commencement of
any task to which they relate.
(4) The Contractor shall produce and implement a Permit to Work system for all high-risk
operations. The Permit to Work system shall be submitted to the Engineer for consent
before application.
1.17 Explosives
(1) Explosives shall not be used without prior written consent of the Engineer. Before consent
to blasting is granted, the Contractor shall prepare a Specification as to the size of charge,
the method of firing and any other restrictions that may be imposed from time to time.
(2) Where the Engineer has consented to the use of explosives, the Contractor shall be
responsible for obtaining the requisite licenses and permits for complying with all statutory
requirements for blasting.
(3) The storage, transportation and use of explosives shall at all times be governed by the
Explosives Acts and such other statutory regulations, which may be applicable, and as
imposed by the Statutory Authorities.
(1) The Contractor shall provide adequate stand-by equipment to ensure the safety of
personnel, the Works and the public. These measures shall include as a minimum the
following:-
(a) Stand-by pumping and generating equipment for the control of water;
(b) Stand-by equipment and spares for illumination of the Works; and
(c) Stand-by generating equipment and equipment for the lighting and ventilation of
underground works.
1.20 Co-operation
(1) The Contractor shall provide full co-operation and assistance in all safety surveillance
carried out by the Engineer or the Employer. Any breaches of the Site Safety Plan or the
statutory regulations or others disregard for the safety of any persons may be the reason
for the Engineer to exercise his authority to require the site agent’s removal from the Site.
2.1. GENERAL
(1) The Contractor shall, within 30days of the date of issue of letter of acceptance , prepare and submit
to the Engineer for review his proposed safety plan which shall contain as a minimum those items
set out in Project Safety Manual and details of the following:-
(2) The Contractor shall produce a policy statement signed by the managing director of the Contractor
or other senior officer acceptable to the Engineer, or the managing directors or other senior officers
acceptable to the Engineer of each company of the consortium, partnership or joint venture
comprising the Contractor, declaring that the Contractor shall ensure that safety and industrial
health are given priority consideration in all aspects of the Works and by the Contractor in
discharging his contractual obligations;
(3) An understanding of and means of ensuring due compliance with the statutory regulations and
standards relating to construction work in India;
(4) The statutory contractual obligations regarding safety and industrial health applying to the
Contractor, and the means by which the Contractor will supervise, monitor and audit his Site safety
to ensure due compliance with these obligations.
(5) The statutory and contractual obligations regarding safety, rescue and industrial health imposed on
the Contractor; and the means by which the Contractor will supervise, monitor and audit his site
safety assurance system to ensure due compliance with these obligations;
(6) The name(s) and experience of person(s) within the Contractors proposed management structure
who would be responsible for coordinating and monitoring the overall safety performance of the
Contractor, all Sub-contractors and Safety Officers.
(7) The safety staff and organizational structure, which should identify the personnel to be engaged
solely for site safety assurance, the responsibilities of the participants and the subdivision of the site
safety assurance tasks into elements which can be effectively controlled, technically and
managerially. Names, addresses, telephone and facsimile numbers of all participants shall be
listed where known (Supplements to the Site Safety Plan will update and complete this information);
(9) The powers vested in the safety staff, which shall be sufficient to enable them to take urgent and
appropriate action to make safe the Site and prevent unsafe working practices or other
infringements of the safety plan or statutory regulations;
(10) The proposed interaction and communication procedures between the Contractor's construction
personnel and safety staff, including proposals for radio communication facilities. In particular, the
establishment of a regular communication and reporting system between the Safety Officer and the
director responsible for the Contract and the Safety Officer and the Site Manager shall be
demonstrated;
(11) The frequency, coverage and intent of regular site safety reports;
(12) The means by which the site safety assurance system will be supervised, monitored and audited by
the Safety Officer to ensure due compliance with the principles and objectives of the Site Safety
Plan at all levels of construction. Procedures for updating the Site Safety Plan and associated
assurance system shall be given;
(13) The records to be prepared and maintained by the Safety Officer and safety staff and
communication procedures to be adopted by the Safety Officer such that the Engineer, Employer
and others associated with the Works (e.g. sub-contractor) are kept fully informed on matters
relating to site safety and industrial health regulations throughout the period of the Contract;
(14) The means by which the Contractor will identify hazards, assess the risks and develop procedures
and method statements to minimise the risk for those risks which will occur during the works;
(15) The aspects of the Temporary Works design which should be communicated to the Engineer and
others directly or indirectly associated with the Works if the installation of the associated works has
a particular significance on the site safety of the Works;
(16) The Contractor shall produce a list of safety and health hazards identified for this contract and the
procedures and method statements for achieving effective and efficient minimization of the risks
associated with such hazards.
(17) The means of minimization of the effects of climatic exposure (heat, wind and moisture) and an
exposure to noxious substances;
SAFETY TRAINING
(18) The Contractor shall produce a description of the safety training courses that are to be provided.
The syllabus, frequency, coverage and application of training courses shall be included together
with the means of attaining the objective that all workmen shall be required to attend a safety
induction course within their first week on Site and thereafter at times appropriate to their
prospective duties and at intervals of not more than 6 months;
SAFETY EQUIPMENT
(19) The Contractor shall identify the safety equipment, rescue apparatus and protective clothing which
will be required for the Works, including the quantity, sourceing, standards of manufacture, storage
provisions and means of ensuring proper utilization by all workmen and staff employed directly or
indirectly by the Contractor and repair to or replacement of damaged equipment. Such equipment
shall include, but not be limited to: site helmets, goggles and other eye protectors, hearing
protectors, safety harnesses, safety equipment for working underground and in confined spaces
(e.g. sewers, drains etc.), rescue equipment, equipment to rescue persons from drowning (if
applicable), fire extinguishers, first aid equipment, and, where appropriate, suitable fall arrest
equipment;
(20) The means by which safety equipment, scaffolds, guard-rails, working platforms, hoists, ladders
and other means of access, lifting, lighting, signing and guarding equipment shall be inspected,
tested and maintained and the standards below which such items will be removed from the Site and
replaced;
CONTRACTORS EQUIPMENT
(21) The Contractor shall produce policy and procedures for ensuring that all his Plant and Equipment
used on the works site is maintained in a safe condition and is operated in a safe manner;
(22) Also regulations and procedures covering all safety and health aspects of the Works, including
where appropriate but not limited to the following:-
(i) housekeeping
(ii) traffic control and transportation
(iii) fire prevention precautions and fire fighting equipment
(iv) working in confined spaces
(v) excavation
(vi) diving
(vii) hot working
(viii) electrical equipment
(ix) welding/cutting operations and equipment
(x) personal protection clothing and equipment
(xi) conveyance, handling and use of explosives
(xii) cranes
(xiii) hoists
SUB-CONTRACTORS
(23) The means by which safety, rescue and industrial health matters and requirements will be
communicated to sub-contractors of all tiers and their due compliance with the Site Safety Plan and
all relevant statutory regulations is ensured;
(24) The method by which the safety procedures and practices proposed by sub-contractors will be
reviewed for compliance with the Site Safety Plan and statutory regulations including the provision
of hazard and risk assessments and method statements.;
DISCIPLINARY PROCEDURES
(25) The Contractor’s disciplinary procedures with respect to dealing with safety related matters both
with his own staff and that of sub-contractors;
ACCIDENT REPORTING
(26) The Contractor’s procedure for reporting and investigating accidents, dangerous occurrences or
occupational illness;
(27) The Contractor’s proposals for statistical measurement and monitoring of the safety and health
performance of the Contractor and sub-contractors of all tiers and how such proposals reflect
responsible practice in the construction industry. The means by which the site safety and industrial
health performance of the Contractor and sub-contractors of all tiers can be compared with local
and international norms shall be given together with the suggested rationale for establishing such
norms;
SAFETY PROMOTION
(29) The Contractor shall provide details of the frequency, coverage and intent of site safety meetings
together with the rationale for attendance;
(30) The methods of promoting an awareness of site safety and site rescue procedures, and industrial
health amongst all persons directly or indirectly associated with the Works.
(31) This shall include proposals for on-site publicity, training courses for all workmen on the Site and at
all levels of supervision and management, incentive schemes for the promotion of compliance with
safety measures, etc.
GENERAL
(32) The Contractor’s system for the protection of authorized and unauthorized visitors to the site;
(33) The Contractor’s proposals to ensure that construction methods do not compromise the
Contractor's commitment to the Site Safety Plan or its compliance with the statutory regulations.
(34) Running on account payment will be released after the following milestones are achieved and
Engineer has issued a ‘Notice of No Objection’ or a Notice of No Objection subject to
……(specifying the condition)’.
a. Release of on-account payment after two months of signing the contract agreement – On
submittal of Site Safety Plan duly approved by Engineer (ER). Otherwise 10% of the
running bill be withheld till compliance.
b. Closure of Non-conformance Report – Action taken on non-compliance and its closure to
be ensured within 15 days of issue of non conformance report. In case of non closure of
report, running on-account bill will be with held @ 1 % of amount for every non closure, till
the same are closed satisfactorily.
c. Release of on-account payment after four months and thereafter every 3 months from the
date of start of work – On submittal of Safety Audit Report duly reviewed by Engineer (ER)
and Action Taken Report. Otherwise 10% of the running bill be withheld till compliance.
d. Release of Final bill – i. Closure of all non-conformance reports
ii. Submittal of all environment documented record pertaining to
monitoring and accountability including Safety Manual &
Procedures.
Appendix VII
GENERAL REQUIREMENTS-CONSTRUCTION
(1) Any error in the execution of work leading to redesign work shall be duly compensated by
the contractor as per the decision of Engineer. Any error attributable to the construction
including failure to locate underground utilities shall attract penalties.
(2) Unless otherwise permitted by the Employer's Representative all works shall be carried out
in dry conditions.
(3) The Works, including materials for use in the Works, shall be protected from damage due
to water. Water on the Site and water entering the Site shall be promptly removed by
temporary rainage or pumping system or by other methods capable of keeping the Works
free of water. Silt and debris shall be removed by traps before the water is discharged and
shall be disposed of at a location or locations to which the Engineer has given his consent.
(4) The discharge points of the temporary systems shall be as per the consent of the Engineer.
The Contractor shall make all arrangements with and obtain the necessary approval from
the relevant authorities for discharging water to drains, watercourses etc. The relevant
work shall not be commenced until the approved arrangements for disposal of the water
have been implemented.
(5) The methods used for keeping the Works free of water shall be such that settlement of, or
damage to, new and existing structures does not occur.
(6) Measures shall be taken to prevent flotation of new and existing structures.
(1) Work shall not be carried out in weather conditions that may adversely affect the Works
unless proper protection is provided to the satisfaction of the Engineer.
(2) Permanent Works, including materials for such Works, shall be protected from exposures
of weather conditions that may adversely affect such Permanent Works or materials.
(3) During construction of the Works storm restraint systems shall be provided where
appropriate. These systems shall ensure the security of the partially completed and on
going stages of construction in all weather conditions. Such storm restraint systems shall
be installed as soon as practicable and shall be compatible with the right of way, or other
access around or through- out the Site.
(4) The Contractor shall at all times programme and carry out the work duly ensuring protective
arrangements such that the Works can be made safe in the event of storms.
(1) The finished Works shall be protected from any damage that could arise from any activities
on the adjacent site/ works.
(1) Work shall be carried out in such a manner that there is no damage to or interference with:
(b) Utilities;
(c) Structures (including foundations), roads, including street fixtures, or other properties;
(e) Monuments, graves or burial grounds other than to the extent that is necessary for them to
be removed or diverted to permit the execution of the Works. Heritage structures shall not
be damaged or disfigured on any account. The Contractor shall inform the Engineer as
soon as practicable of any items which are not stated in the Contract to be removed or
diverted but which the Contractor considers necessary to be removed or diverted to enable
the Works to be carried out. Such items shall not be removed or diverted until the consent
of the Engineer to such removal or diversion has been obtained.
(2) Items which are damaged or interfered with as a result of the Works and items which are
removed to enable the Works to be carried out shall be reinstated to the satisfaction of the
Engineer and to at least the same condition as existed before the Work started. Any claims
by Utility Agencies due to damage of utilities by the Contractor shall be borne by the
Contractor.
(1) The Contractor shall immediately inform the Engineer of any damage to structures, roads
or other properties.
6 ACCESS
(1) Alternative access shall be provided to all premises if interference with the existing access,
public or private is necessary to enable the Works to be carried out. The arrangements for
the alternative access shall be as agreed by the Engineer and the concerned agency.
Unless agreed otherwise, the permanent access shall be reinstated as soon as practicable
after the work is complete and the alternative access shall be removed immediately it is no
longer required, and the ground surfaces reinstated to the satisfaction of the Engineer.
Proper signage and guidance shall be provided for the traffic / users regarding diversions.
7 TREES
(1) The felling of trees in the National Capital Territory of Delhi is governed by the Delhi
Preservation of Trees Act 1994 (Delhi Act No. 11 of 1999). The Contractor is not permitted to
cut any trees in terms of the provisions of the aforementioned act. The Employer has
assessed the number of trees existing within the right-of-way and has arranged for cutting and
removal of trees, which are likely to be affected by the right of way (i.e., within the limits of
permanent works) construction works. The trees requiring to be felled, will be removed from
ground level up by the Employer prior to commencement of the works. If for the purposes of
the works additional trees are required to be cut/trimmed or removed, the Contractor must
notify the Engineer of such requirements. Subject to compliance with the aforementioned act,
arrangements for tree felling may be made by the Employer under separate contract and
compensatory replacement of felled trees will also be made by the Employer. If the Contractor
is able to obtain permission for tree cutting from the concerned authority then such trees can
be cut by the Contractor and any replacement carried out by the Contractor.
(1) If any graves and other obstructions are required to be removed in order to execute the
Works and such removal has not already been arranged for, the Contractor shall draw the
Engineer's attention to them in good time to make necessary arrangement for
authorizations for such removal. The Contractor shall not itself remove them unless the
Engineer has given consent.
(1) The Contractor shall take all necessary precautions to protect the structures or works being
carried out by others adjacent to and, for the time being, within the Site from the effects of
vibrations, undermining and any other earth movements or the diversion of water flow
arising from its work.
10 Deleted
11 SITE ESTABLISHMENT
11.1 Deleted
(1) The Contractor shall provide and maintain its own site accommodation at locations
consented to by the Engineer. Offices, sheds, stores, mess rooms, garages, workshops,
latrines and other accommodation on the Site shall be maintained in a clean, stable and
secure condition. Living accommodation shall not be provided on the Site.
(1) The Contractor shall provide latrines and washplaces for the use of its personnel and all
persons who will be on the Site. The size and disposition of latrines and washplaces shall
accord with the numbers and dispositions of persons entitled to be on the Site. There shall
be separate facilities for males and females. The capacities and layout shall be subject to
approval of the Engineer. The Contractor shall arrange regular disposal of effluent and
sludge in a manner that shall be in accordance with local laws/ regulations.
(2) The Contractor shall be responsible for maintaining all latrines and washplaces on the Site
in a clean and sanitary condition and for ensuring that they do not pose a nuisance or a
health threat. The Contractor shall also take such steps and make such provisions as may
be necessary or directed by the Engineer to ensure that vermin, mosquito breeding etc. are
at all times controlled.
11.4 SITE UTILITIES AND ACCESS
(1) (a) The Contractor shall be responsible for providing water, electricity, telephone, sewerage and
drainage facilities and all such services that are necessary for satisfactory performance of
the Works for all site accommodation, structures and buildings in accordance with Appendix
5 to these Employer's Requirements. The Contractor shall make all arrangements with and
obtain the necessary approval from the relevant civil and utility authorities for the facilities.
(b) The Contractor shall be responsible for provision of power supply for his works including for
tunneling machines and the like .The Employer can not guarantee to the Contractor
provision of adequate, continuous power supply. However, assistance will be given by the
Employer in obtaining the necessary permissions for installation of site generators and the
like.
(3) Deleted
12 SUBMISSION OF PARTICULARS
(1) The following particulars shall be submitted to the Engineer for his consent not more than
fifty-six (56) days after the date of commencement of the Works:
(a) Drawings showing the formation works and the layout within the Site of the Engineer's
accommodation, the Contractor's offices, project signboards, principal access and other
major facilities required early in the Contract, together with all service utilities;
(b) Drawings showing the layout and the construction details of the Engineer's
accommodation; and
(c) Drawings showing the details to be included on the project signboards and diversion
boards.
(2) Drawings showing locations of stores, storage areas, concrete batching plants and other
major facilities as well as the access roads/paths shall be submitted to the Engineer for his
consent as early as possible but in any case at least twenty eight (28) days prior to the date
when such facilities are intended to be constructed on the Site.
13. SECURITY
(1) The Contractor shall be responsible for the security of the Site for the full time the Site is in
his possession. The Contractor shall set up and operate a system with the consent of
Engineer to ensure proper arrangements for security.
(2) During the progress of the Works the Contractor shall maintain such additional security
patrols over the areas of the Works as may be necessary to protect its own and its sub-
contractor's work and equipment. The Contractor shall co-ordinate and plans the security of
both the work under this Contract and the work of others engaged in adjacent and
interfacing contractors and requiring access to the site.
3) The Contractor shall liaise with the Designated Contractors and the contractors responsible
for the adjacent and other interfacing contracts and ensures that coordinated security
procedures are operated, in particular in respect of vehicles permitted to pass through the
Site and/or the adjacent sites.
(4) Security and checking arrangements, as felt necessary shall be provided with advice and
help of the Police.
(1) The Contractor shall keep monthly records of the average, high and low wage rates for
each trade/tradesman employed on the Site and records shall be made available to the
Engineer during inspection.
15. MATERIALS
(1) Materials and goods for inclusion in the Permanent Works shall be new unless the
Engineer has consented otherwise. Preference shall be given to local materials where
available.
(2) Certificates of tests by manufacturers, which are to be submitted to the Engineer, shall be
current and shall relate to the batch of material delivered to the Site. Certified true copies of
certificates may be submitted if the original certificates could not be obtained from the
manufacturer.
(3) Parts of materials, which are to be assembled on the Site, shall be marked to identify the
different parts.
(4) Materials which are specified by means of trade or proprietary names may be substituted
by materials from a different manufacturer which has received the consent of the Engineer
provided that the materials are of the same or better quality and comply with the specified
requirements.
(5) Samples of materials submitted to the Engineer for information or consent shall be kept on
the Site and shall not be returned to the Contractor or used in the Permanent Works unless
permitted by the Engineer. The samples shall be used as a mean of comparison, which the
Engineer shall use to determine the quality of the materials subsequently, delivered.
Materials delivered to the Site for use in the Permanent Works shall be of the same or
better quality as the samples, which have received cons
16. Deleted
17. Deleted
Unless otherwise directed by the Engineer, any areas disturbed by the construction activity, either
inside or outside the Project Right of Way, shall be reinstated as follows:
All areas affected by the construction work shall be reinstated to their original condition, with new
materials, including but not necessarily limited to, sidewalks, parking lots, access roads, adjacent
roads, properties and landscaping. Grass cover shall be provided for any bare earth surface areas,
along with proper provisions for surface drainage.
19.1 The Employer will not provide living accommodation for the use of the Contractor or any of his staff
or labour employed on the Works. Living accommodation shall not be established on any land
provided to the Contractor by the Employer for the Works.
The Contractor, shall, at his own expense, make adequate arrangements for the housing, supply of
drinking water and provision of bathrooms, latrines and urinals, with adequate water supply, for his
staff as well as for workmen employed on the Works directly or through sub-contractors at the
location authorized by Engineer. No labour camp shall be allowed at work site or any unauthorized
place.
The Contractor at his own cost shall maintain all campsites in a clean and sanitary condition. The
Contractor shall obey all health and sanitary rules and regulations, and carry out at his cost all
health and sanitary measures that may from time to time be prescribed by the Local/Medical
Authorities and permit inspection of all health and sanitary arrangements at all times by the
Employer, the Engineer and the staff of the local municipality or other authorities concerned.
Should the Contractor fail to provide adequate health and sanitary arrangements these shall be
provided by the Employer and the cost recovered from the Contractor.
The Contractor shall at his own cost, provide First Aid and Medical facilities at the Labour Camp
and at work sites on the advice of the Medical Authority consistent with the strength of the
Contractor’s staff and workmen, employed directly or through sub-contractors.
The Contractor shall at his own cost, provide the following minimum requirements for meeting the
fire hazards:
The Contractor at his own cost shall provide necessary arrangements for keeping the camp area
sufficiently lighted to avoid accidents to the workers. He should also ensure that electrical
installations are done by Trained Electricians. These installations shall be maintained and daily
maintenance records must be made available for inspection by the Engineer.
The Contractor shall take requisite precautions, and use his best endeavours to prevent any
riotous or unlawful behaviour by or amongst his workmen, and others, employed directly or
through sub-contractors. These precautions shall be for the preservation of the peace and
protection of the inhabitants and security of property in the neighbourhood of the Works. In the
event of the Employer requiring the maintenance of a Special Police Force at or in the vicinity of
the site, during the tenure of the work, the expenses thereof shall be borne by the Contractor and
if paid by the Employer, shall be recoverable from the Contractor.
The sale of alcoholic drinks or other intoxicating drugs or beverages upon the work, in any labour
camp, or in any of the buildings, encampments or tenements owned or occupied by, or within the
control of, the Contractor or any of his personnel employed on the work directly or through sub-
contractors shall be forbidden, and the Contractor shall exercise his influence and authority to
secure strict compliance with this condition. The Contractor shall also ensure that no labour or
employees are permitted to work at the site in an intoxicated state or under the influence of drugs.
The Contractor shall remove from his camp such labour and their families, as refuse protective
inoculation and vaccination when called upon to do so by the Engineer on the advice of the
Medical Authority. Should Cholera, Plague or any other infectious disease break out, the
Contractor shall at his own cost burn the huts, bedding, clothes and other belongings of or used
by the infected parties. The Contractor shall promptly erect new huts on healthy sites as required
by the Employer, within the time specified by the Employer, failing which the work may be done by
the Employer and the cost recovered from the Contractor.
The Contractor shall provide living accommodation that is equal to or exceeds the minimum criteria
established in the following sub-sections, needed to house his staff as well as workers employed
directly or through sub-contractors. The buildings shall be constructed so as to have a minimum life
of not less than the length of the Contract.
(a) The roofs shall be watertight and laid with suitable non-flammable materials permissible for
residential use under local regulations and for which the consent of the Engineer has been
obtained.
(b) Each hut shall have suitable ventilation. All doors, windows, and ventilators shall be
provided with security leaves and fasteners. Back to back units may be avoided.
(c) The minimum height of each unit shall be 2.10m and shall have separate cooking place.
The Contractor shall provide an adequate supply of water for the use of labourers in the Camp.
The provision shall not be less than two gallons of pure and wholesome water per head per day for
drinking purposes and three gallons of clean water per head per day for bathing and washing
purposes. Where piped water supply is available, supply shall be at stand posts and where the
supply is from wells or river, tanks that may be of metal or masonry shall be provided. The
Contractor shall also at his expense make arrangements for the provision and laying of water pipe
lines from the existing mains wherever available and shall pay for all the fees and charges
therefore.
19.6 DRAINAGE
The Contractor shall provide efficient arrangements for draining away sullage water so as to keep
the camp neat and tidy. Surface water shall be drained away from paths and roads and shall not
be allowed to accumulate into ditches or ponds where mosquitoes can breed.
19.7 SANITATION
The Contractor shall make arrangements for conservancy and sanitation in the labour camps
according to the rules and regulations of the Local Public Health and Medical Authorities.
The Contractor shall provide a sewage system that is adequate for the number of residents in the
camp, and which meets the requirements of the Municipal Authorities.