A PEKERJAAN PERSIAPAN 11,690,000
1 Papan Proyek 1 unt 500,000 500,000
2 Pek. Pengukuran dan Bowplank 52 m' 157,500 8,190,000
3 Pek. Listrik & Air Kerja 1 ls 2,500,000 2,500,000
4 Pek. Laporan & Dokumentasi 1 ls 1,000,000 1,000,000
B PEKERJAAN PONDASI & TANAH 74,489,747
1 Pek. Galian Tanah Pondasi 77.38 m3 36,740 2,842,941
2 Pek. Urug Tanah Kembali 25.79 m3 13,400 345,586
. =
3 19.55 m3 183,900 3,595,245
4 Pek. Pasir Urug -
Bawah Pondasi 11.9 m3 11
110,000 1,309,000
Bawah Lantai 19.9 m3 110,000 2,189,000
5 Pek. Pondasi Tapak P1 (100x100x20- 40) -
Beton K-225 3.92 m3 1,230,825 4,824,834
Bekisting 0.69 m2 295,290 203,750
6 Rek Kolom Sopi 60/60 -
 beton K-225 0.75 m3 1,230,825 923,119
Pembesian 84.12 kg 11,316 951,902
Bekisting 9.96 m2 295,290 2,941,088
7 Pek, Ring Balok Praktis Sopi-sopi -
Beton K-175 0.96 m3 1,124,383 1,079,408
Pembesian 194.91 kg 11,316 2,205,602
Bekisting 12.81 m2 295,290 3,782,665
8 Pek. plat Beton Topi-topi -
Beton K-225 0.86 m3 1,230,825 1,058,510
Pembesian 182.42 kg 11,316 2,064,265
Bekisting 12.24 m2 295,290 3,614,350
D PEKERJAAN ATAP & PLAFOND   83,777,760
D.1 PEKERJAAN ATAP 62,644,900
1 Rangka Atap baja Ringan 205.53 m2 165,000 33,912,450
2 Atap Spandek t=0,35 205.53 m2   65,000 13,359,450
3 Lisplank GRC 73.8 M' 85,000 6,273,000
4 Pasang Aluminium foil, Glaswool, Roofmesh 140 m2 65,000 9,100,000
D.2 PEKERJAAN PLAFOND 21,132,860
1 Plafond Gipsum +Rangka hollow 4/4; t= 136.49 m2 97,000 13,239,530
2 Plafond Calsiboard 4,5 mm + Rangka 53.31 m2   68,000 3,625,080
3 List Gipsum 5 cm 94.85 m2   45,000 4,268,250
E PEKERJAAN PASANGAN 110,064,060
1 P Di di B 250 73 2 66 440 16 658 501
3 Pek. Pengecatan Plafond 189.8 m2 21,360 4,054,128
4 Pek. Pengecatan Listplank 22.14 m2 21,360 472,910
H PEKERJAAN PLUMBING & SANITAIR 15,670,043
1 Instalasi Pipa PVC AW 4" 16 m' 180,519 2,888,304
2 Instalasi Pipa PVC AW 2" 12 m' 103,218 1,238,616
3 Instalasi Pipa PVC AW 3/4" 20 m' 98,180 1,963,600
4 Instalasi Pipa PVC AW 1/2" 15 m' 79,323 1,189,845
5 Septic Tank dan Rembesan 1 unt 4,407,413 4,407,413
6 Pemasangan Closed Jongkok 1 bh 627,947 627,947
7 Pemasangan Kran Air 2 bh 216,452 432,904
8 Pemasangan Wastafel + Kran 2 bh 875,074 1,750,148
9 Pemasangan Cermin Wastafel 100x200 1 unt 1,171,266 1,171,266
I PEKERJAAN LISTRIK 67,667,437
1 Penyambungan Daya Listrik 5.500 VA ## VA 1,000 5,500,000
.
2 ## VA 1,000 5,500,000
3 Panel Listrik 1 unt 467,280 467,280
4 Pek. Instalasi Kabel Feeder NYY 4x10 mm2 2 m' 1,506,600 3,013,200
.
5 66 ttk 241,760 15,956,160
6 Pek. Instalasi Power AC 2 ttk 1,800,000 3,600,000
7 Pemasangan Lampu TKI 2x36W 16 bh 317,400 5,078,400
8 Pemasangan Lampu Baret Kotak 22W 7 bh 95,274 666,918
9 Pemasangan Lampu E27ESS 8 Watt + Fitting 3 bh 2,908,080 8,724,240
10 Pemasangan Saklar Engkle 5 bh 105,360 526,800
11 Pemasangan Saklar Double 4 bh 118,440 473,760
12 P S K k Si l 9 bh 198 240 1 784 160
RENCANA ANGGARAN BIAYA
PEMBANGUNAN GEDUNG WORKSHOP
PEKERJAAN :
KOMPUTER - BLK KOMUNITAS
PEMBERI TUGAS : KEMENTERIAN KETENAGAKERJAAN RI
TAHUN ANGGARAN : 2018

NO ITEM PEKERJAAN TOTAL

A PEKERJAAN PERSIAPAN 11,690,000


B PEKERJAAN PONDASI & TANAH 74,489,747
C PEKERJAAN STRUKTUR 120,307,947
D PEKERJAAN ATAP & PLAFOND 83,777,760
E PEKERJAAN PASANGAN 110,064,060
F PEKERJAAN KUSEN PINTU & JENDELA 64,473,180
G PEKERJAAN PENGECATAN 16,125,026
H PEKERJAAN PLUMBING & SANITAIR 15,670,043
I PEKERJAAN LISTRIK 67,667,437
J LAIN - LAIN 15,000,000
TOTAL 511,597,764
PEMBULATAN   500,000,000
TERBILANG : Lima Ratus Juta Rupiah

Sukabumi, 17 Juli 2018


Pimpinan Pondok Pesantren Ketua Unit Ketua Unit
 Nurul Hasanah Pengelola Kegiatan Pengelola Kuangan

Nurhayat, S.Pd.I.,SE. Ade Yunus, S.Pd.I. Yuswandi, S.Pd.I