Ascertain the net present value of the projects with 12 cost of capital.
Solution:
NPV
Working notes 2: Depreciation: Original cost + Survey cost – Scrap value ÷ Life of machinery
= (40,00,000 + 2,00,000 – 5,00,000)/5 = Rs. 7,40,000
Depreciation should be added to PAT of every year to get CFAT
ake a project for placing a new product on
at the project would cost Rs.40,00,000 in
crap value of plant and machinery at the
tion on straight-line basis, profits after tax
4 5
5,00,000 4,00,000
Present
Values
(Rs.)
9,28,720
12,27,380
14,52,480
7,88,640
6,46,380
50,43,600
5,67,000
2,83,500
58,94,100
52,00,000
6,94,000
e ÷ Life of machinery
A firm has two investment opportunities, each costing Rs.1,00,000 and
2 eachhaving an expected profit as shown below:
Year 1 2 3 4
Project 50,000 40,000 30,000 10,000
X (Rs.)
Project 20,000 40,000 50,000 60,000
Y (Rs.)
After giving due consideration to the risk criteria in each project the
management has decided that project A should be evaluated at a 10 per
cent cost of capital and project B, a risky project with a 15 per cent cost
of capital.
Compare the NPV and suggest the course of action for the management
if
a) Both the projects are independent,
b) Both are mutually exclusive
Solution:
Calculation of NPV
Year CFAT (Rs.) DF % PVs (Rs.)
Project Project 10 15 Project Project
A B A B
1 50,000 20,000 0.91 0.78 45,450 17,400
2 40,000 40,000 0.83 0.76 33,040 30,240
3 30,000 50,000 0.75 0.66 22,530 32,850
4 10,000 60,000 0.68 0.57 6,830 34,320
Present Value of cash inflows 1,07,850 1,14,810
Less: Cash outflows 1,00,000 1,00,000
Netindependent,
a) If both the projects are Present Values (NPV)
accept 7,850 as14,810
both the projects, NPV
of both projects are positive.
b) If both the projects are mutually exclusive, accept project B as its
NPV is higher than that of Project A.
X Ltd., is considering the purchase of a new machine, which will carry out some
operations at present performed by labour. Two alternative models A and B are
available for the purpose. From the following information prepare a profitability
3 statement for submission to management and calculate PBP.
Machine A Machine B
Rs. Rs.
Estimated life (Years) 5 6
Cost of Machine (Rs.) 80,000 1, 50,000
Estimated additional cost (Rs.)
Indirect material (p.a) 2,000 3,000
Maintenance (p.m) 500 750
Supervision (per quarter) 3,000 4,500
Estimated savings in scrap (p.a.) 8,000 12,000
Estimated savings in direct wages
a. workers not required 10 15
b. wages per worker p.a. 7,200 7,200
(a) PBP (b) ARR (c) NPV at 10 per cent and (d) PI at 10 per cent
1 10,000 - -
2 11,000 1,000 500
3 14,000 4,000 2,000
4 15,000 5,000 2,500
5 25,000 15,000 7,500
PI indicates that for every one rupee of investment the project will generate only 0.92
paise, in other words the project will incur a loss of 0.08 paise for every one rupee of
investment.
. The project will cost Rs. 50,000 and will
s straight-line method of depreciation. The
4 5
15,000 25,000
CFAT Cumulat
(Rs.) ive
(EAT+D CFAT
ep.) (Rs.)
10,000 10,000
10,500 20,500
12,000 32,500
12,500 45,000
17,500 62,500