November 9, 2010
Citizens are very concerned with the preponderance of irregularities that exist with respect to
LCPS’ selection of school sites. Citizen support of LCPS’ operating and CIP budgets requires
tremendous trust that our tax dollars are being wisely spent to advance a single agenda, that is to
provide the best possible education for students in Loudoun County for the available budget.
Therefore, citizens request that these irregularities be reconciled immediately to build citizen trust
in LCPS’ fiduciary responsibility. We recognize past events are just that, the past, however, we
believe in the role and importance of history lessons. Because looking at history is perhaps the
best way to fix problems we don’t want repeated in the future. Therefore we submit the following
partial list of questions that have been raised on western Loudoun site acquisitions.
1. McDonough Assemblage
a. Why were tens of thousands of dollars paid to consultants for continuing studies on
Wheatland Farm after the May 2009 rejection of that site by the Board of Supervisors?
(see page C-3) 1
b. Why were funds available for continued study in Wheatland but not on the McDonough
Assemblage? (see page C-3) 1
c. Why did LCPS wait until April 2010 (expiration date of McDonough Assemblage
contracts) before asking Supervisors for more money to study options, when the
advertisement for land closed 5 months prior, in October 2009?
d. Why were detailed costs presented for McDonough Assemblage-associated traffic
improvements but no equivalent cost estimates were shared with the public for
infrastructure and mitigating measures anticipated for the Wheatland Farm school
complex?
e. Does LCPS include estimating costs for site improvements in their due diligence study
scopes of work and fully disclose results to Board members?
f. Did due diligence studies conducted for the proposed Wheatland Farm schools
recommend upgrades to interstate thoroughfare Route 9?
g. Why did LCPS’ cost analysis of the McDonough Assemblage exclude cost savings
associated with the Town providing sewer service? i.e., LCPS-constructed and
operated wastewater treatment plants would not be required.
h. Staff from State and County Transportation Departments (VDOT and Loudoun) were
consulted during evaluation of HS-3 sites. (Attachment A) Therefore, why were these
agencies not consulted during analysis of HS-10 sites?
i. Other co-located schools in the County share a single access road. Why did LCPS
assume, and present costs for, separate access roads serving MS/HS-10 on the
McDonough Assemblage?
j. Did LCPS inform the School Board of previous offers made by Mr. McDonough to
negotiate assemblages for secondary school sites in the Lovettsville area?
k. What correspondence exists between LCPS and landowners in the McDonough
Assemblage since the Assemblage was first presented to LCPS in 2009?
4. 2008 RFP
a. Have 2-week RFP response timeframes been specified for any other LCPS or County
procurement? Why such a short fuse when LCPS’ CIP did not reflect an accelerated
schedule for opening those schools?
b. When did LCPS staff first advise the School Board that a RFP response was received
for a site contiguous to Hillsboro Elementary school (i.e., the Crim/Moler property)?
c. Why was that RFP response never included in presentations to Supervisors or the
public when presenting the list of RFP responses?
6. 2006 Contracts
a. Did anyone at LCPS, including their legal counsel, consultants or agents, have any
contact whatsoever (implied or documented) with Mr. Cangiano or his representatives
regarding LCPS’ interest in Wheatland Farm prior to Mr. Cangiano initiating his
acquisition of that property?
b. Why did LCPS fail to respond to Mr. Miller’s letter first letter dated November 2, 2005 in
which Mr. Miller offered his 156-acre farm situated at the intersection of (with frontage
on) two paved roads immediately adjacent to the Town of Lovettsville?
c. Why did LCPS’ letter to Mr. Miller dated January 27, 2006 include two specific
references to the School Board’s authority to invoke eminent domain; and, fail to
acknowledge either of the two prior letters submitted to LCPS by Mr. Miller/ agent,
including the Miller’s offer of their farm for $29.8k/acre dated January 4, 2006?
d. Why did it require several follow-on FOIA requests to obtain all correspondence on this
matter?
e. How does LCPS believe that during initial contact with landowners submitting offers to
sell their land for schools that multiple assertions of the School Board’s authority to use
eminent domain effectively demonstrates LCPS’ willingness to negotiate in good faith,
and in the best interests of Loudoun citizens?
f. The School Board has stated on numerous occasions that condemning land is to be
avoided whenever possible. Therefore, did LCPS staff obtain permission from the
School Board prior to asserting their authority to condemn Mr. Miller’s land?
g. Were School Board members consulted when LCPS rejected a LCPS contract modified
and signed by both Mr. and Mrs Miller on April 7, 2006 for $31,730 per acre, which was
submitted to LCPS by the Miller’s attorney (Attachment G)?
h. How does LCPS justify repeated rejection of Mr. Miller’s multiple offers, ranging from
$29k-32k/acre for his farm, (a site that offered potential access to Town-supplied
water/sewer) at the same time that LCPS simultaneously submitted offers of $57k/acre
7. To demonstrate LCPS’ efforts to find near Town sites, what correspondence exists between
LCPS and owners of properties listed by LCPS as possible HS-10 sites that offer existing
paved road frontage and are located near the Town of Lovettsville, including these properties,
Shoene, O’Brien/Athey Assemblg, Opeka, and Mercker; and, owners of contiguous parcels?
GENERAL QUESTIONS
8. What is LCPS’ rationale against taping School Board Executive Sessions involving real estate
so incoming School Board representatives can objectively understand past decisions?
9. Why are current student distribution maps (readily available using LCPS’ existing GIS-based
software) not a tool used by LCPS during the site acquisition and boundary zone processes?
10. Has LCPS ever used their Edu-log software to develop attendance boundary alternatives and
predict student enrollment?
11. The MacKenzie Group reported in 2003 that, “When sites are being sought, the [Loudoun
County] school district either advertises publicly that they are looking for land for a new school,
or they use "scouts" to search out land.” If this is correct, does LCPS believe that driving
around scouting potentially available properties is an effective use of staff’s time?
12. Why does LCPS continue to resist using a siting process where early public input is solicited on
proposed school sites, as requested by citizens during the February 2009 public hearing on the
topic? (see process presented to the Joint Committee in 2008 – Attachment H)
13. Why did LCPS reject assistance offered by two experts (through a citizen advocate) on
resolving recalcitrant school siting issues, specifically a school siting expert with the USEPA
Smart Growth Initiative and a land acquisition expert with the Commonwealth of Virginia?
14. Does LCPS reserve rights to resubmit their proposal for siting HS/MS-10 at Wheatland Farm?
15. To build trust, would officials involved in any way with LCPS site acquisitions be willing to
submit, for a confidential audit, detailed personal financial statements, including funding
sources for recent personal travel, home improvements or other major
purchases/expenditures?
16. Will these same public officials formally disclose all previously undocumented conversations
and correspondence regarding possible land acquisitions (or study of sites) shared with
contractors and landowners who have any interest (profit or advantage) in the acquisition?
$67,000/acre:
2009 $62,000/acre Cangiano contract $54,000/acre McDonough Assemblage contracts
+ $147,000/acre Burgess contract 108 acres for $5.87M
= 170 acres for $11.4M
ATTACHMENT A
A-1
A-2
by moving the round-about north to Loudoun St, the need to align the
school access road through (and condemn) the Moore home is eliminated.
This suggestion was never considered in subsequent presentations.
ATTACHMENT B
B-1
Aprll}7,2009
Dear Dennis,
The maximum combined potable water supply requirements of the Elementary, Middle,
and High Schools at this project site are estimated tobe 65,490 gpd (a5.5 gpm). These estimates
are based on the following Virginia Health Department guidelines:
Elementary School 875 students + x l0 gallons per day per 9,650 gallons per day
90 staff: 965 Derson
Middle School 1,350 students + 140 x 16 gallons per day per 23,840 gallons per day
staff:1.490 nerson
High School 1,800 students + 200 x l6 gallons per person per 32,000 gallons per day
staff :2.000 day
We anticipate, based upon historic water use recorded at the other Loudoun Counfy
Public Schools, that actual average daily water use will be reduced to the following:
B-2
Elementary School 875 students + x 3.1 gallons per day per 2,992 gallons per day
90 staff:965 Del'son
Middle School 1,350 students + 140 x 2.9 gallons per day per 4,321 gallons per day
staff :
1,490 Derson
High School 1,800 students + 200 x 5.0 gallons per day per 10,000 gallons per day
staff :2,000 Derson
The demand for potable water is to be met by three (or possibly four) proposed
Community Supply Wells. These wells are identified as Wells WLS-2B2, WLS-10, and WLS-
l6 (and possibly Well WLS-I) (Figures I and 2). Water Well Completion Reports (GW-2s) for
these wells are included with this document.
During the proposed yield and quality testing program, all Community Supply Wells will
be pumped simultaneously to create a maximum stress on the local bedrock aquifer(s). We
anticipate pumping each well between 10 and 20 gpm. Each community supply well will be
pumped for a minimum of 72 hours. All discharge water will be directed a minimum of 200 feet
away from each well to the streams draining the site. Preventative measures will be taken to
minimize bank erosion at each discharge point.
The pumping test program is scheduled to begin sometime between May 7th and May
131h,2009. The start of pumping for each Production Well will be sufficiently staggered so that
potential pumping interference between wells (if any) can be recorded. The pumping of all the
wells will be terminated at the same time.
EGGI has contacted 26 nearby property owners to determine if they have a well on their
propeffy and if they are interested in participating in the groundwater monitoring program
(Figures I and 2). EGGI hopes to monitor approximately l5 to 25 off-site wells, dependent upon
the response of nearby well owners and the ability to install monitoring equipment into each
available domestic well. In addition to the off-site wells, EGGI will monitor changing water
levels in approximately l0-15 on-site wells. All locations will be monitored every 30 minutes
using automated water level recorders accurate to within 0.01 feet. The monitoring of
groundwater levels will take place for approximately one week prior to the testing period,
throughout the pumping period, and one week after the pumping period is concluded.
' Please note that the majority of potable water used on site will be returned into the groundwater system vra on-site
septic drainfields.
2
well wLS-28 is intended to be drilled adjacent to existing well wLS-2, which is only 35 feet from the nearby
stream. This Well will be drilled during the week of April 27 ,2009. It will be located 53 feet fiom the stream. A
walver request has been submitted to the County Health Department to allow a 5O-foot setback from the stream for
this proposed communily supply well. This proposed 5O-foot setback is consistent with VDOH requirements.
Near the conclusion of pumping, water samples willbe collected from each Community
Supply Well and delivered to the Virginia Division of Consolidated Laboratory Scrvices (State
Laboratory), and Joiner Micro-Labs for all analyses required by the State Department of Health
and Loudoun County Department of Health for new community water supply rvells.
EGGI will also install three piezometers within the streambed located along the northem
property boundary and water levels will be monitored every 30 minutes to assess potential
impacts to the fluvial plain area. We will also be installing staff gages in on-site ponds to assess
possible changes in surface water levels.'
I hope you find this information responsive to your needs. If you have any questions
regarding the proposed pumping test plan please do not hesitate to contact me.
Sincerely,
lhL6 $u-^-
Mark Wingsted John Brooks, Ph.D., PG
Projegt Manager Senior Hydrogeologist
' We are not intending to measure the flow of the norlhem stream due to its significant flow rate, which was
estimated to be in excess of I ,500 gpm during the rveek of April I 5. 2009.
D-1
ATTACHMENT E E-1
E-2
Lovettsville Park option requires additional acreage from both Moore and Miller
Effect on Park and its program requires additional examination. Impacts are dependent upon the option
selected
Property and Right-of-Way needs would likely require condemnation of multiple properties
Town of Lovettsville would have to amend its comprehensive plan to reflect addition of
public schools to the town utility grid
Additional treatment module approximately $2,500,000, infiltration and inflow issues need
to be resolved
Without utilities from Lovettsville, hydro geologic and soils analyses have to be performed to determine if
water and sewer capacities exist on the above properties and a larger area would be required for drainfield
locations
In order to locate a school in areas outside of the towns, villages and/or their JLMAs, the BOS must provide
support for an alternative location
ATTACHMENT G
G-1
G-2
G-3
G-4
G-5
G-6
G-7
G-8
G-9
G-10
Co*tRACror So""
I'
Between
and
-
G-11
CONTRACT,OF SAIjB
into this day of February, 2006, by and between the county school Board of Loudoun
County, a body politic (hereinafter referred to as the "Buyer"), and Herbert J. Miller, Jr. and
Carey K. Miller, his wife (although more than one, they are hereinafter referred to as the
"SeUerr').
I
RECITALS:
A. Seller is tfre owner of twelve (12) contiguous tracts of land located in Loudoun
County, Virginia, containing in the aggregate approximately 155 acres of land and identified as
more particularly described on Exhibit "A" attached hereto and incorporated herein by
reference (the twelve (12) tracts of land, together with all improvements and fixtures thereon and
all rights, privileges, easements, benefits and agreements appurtenant thereto are hereinafter
AGREEMENT:
*r,t:l ( NOw, THEREFORE, in consideration of the ,u* off/rhousand and no/t00 Dollars
Lli-lilF
fotfilooo o0) paid by Buyer (the "Deposit") to be paid in the fbrm of a check to Loudoun
Comrnercial Title, LLC (the "Escrow Agent"), to be held by Escrow Agent and disbursed by
Escrow Agent in accordance with the terms of the Escrow Agreement attached hereto as Erhibit
G-12
"8" and incorporate.d herein by reference to be executed by Seller, Buyer and Escrow Agent
contemporaneousiy with the execution of this Contract, the receipt of which by Escrorv Agent is
acknowledged hereon, Buyer hereby agrees to buy and Seller hereby agrees to sell the property
l. Purchase Price: Paymen(. The purchase price for the Property (the "Purchase
(rice") shall be the sum of Four Millio/H H""dfJffousand and no/100 Dolars
(!4,2eS,000.00). Ttris is a sale in gross and not by the icre. The entire Purchase Price shall be
payable by Buyer to Seiler in cash, certified or bank cashier's check, or by wired funds at closing
2. StudY-.Period- For the period commencing on the date of full execution hereof
and continuing for 120 days (the "Study Period"), Buyer, at its sole cost and expense, shall
have complete access to the Property for the purpose of conducting such appraisals, soil borings,
soil analyses, engineering tests and studies, topographic tests, studies, and/or investigations with
respect to the Property as Buyer may deem necessary or appropriate in order to determine
whether the Property is suitable for Buyer's intended use; provided that Buyer shall repair any
damage to the Property caused in connection with such tests and studies. In the event that Buyer
determines, in its sole discretion, that the Property is not suitable for Buyer's intended use
thereof, the appraisal results are unsatisfactory, or for any other reason, then Buyer may
terminate this Contract by delivery of written notice thereof to Seller prior to the expiration of
the Study Period, and thereupon the parties hereto shall have no further rights or obligations one
to the other hereunder, and the Deposit shall be retumed to Buyer. To the extent permitted by
law Buyer shall indemnify and hold Seller harmless frorn and against all costs, expenses, and
liabilities incuned by Seller in connection with the tests and studies conducted by Buyer and
J
G-13
SELLER:
Ay"il 7,Joa6
A
Date
t9
G-14
COMMONWEALTH OF VIRGINIA
COTJNTY OF to wlt:
COMMON\I/EALTH OF VIRGINIA
COLNTY OF Loccrlrt r'**
. to wit:
[, the undersigned Notary Public, in and for the jurisdiction aforesaid, do hereby certify
that HERBERT J. MILLER, JR., whose name is signed to the foregoing instrument, appeared
before me and personally acknowledged the same in my jurisdiction aforesaid.
tu
GIVEN under my hand and seal rni, . V aay or *{ r t I, 2006.
My conrmissionexpires,
44 30, un?
COMMONWEALTH OF VIRGTNIA
COUNTY AF I r'tu,-clo "n*
-,to wit:
[, the undersigned Notary Public, in and for the jurisdiction aioresaid, do hereby certify
that CAREY K. MILLER, whose name is signed to the foregoing instrumenl appeared before
me and personally acknowledged the same in my jurisdiction aforesaid-
tu
GIVEN under my hand and seal tni" day of
-7
My commission expires: fi1r;l 3a, Zacl
20
G-15
April28, 2006
VIA FASCIMILE
Dear David,
Sam Adamo has asked that I respond to your letter of April 7 , 2006. He has talked with the
Instead of marking up your "mark-ups", I thought the better course would be to set forth in letter
form the changes acceptable to Loudoun County Public Schools and if we agree, put it then in a clean
contract.
l. Purchase Price. Loudoun County Public Schools will agree to a purchase price
2. study Period. Loudoun county Public schools will agree that the a"porit i! to be
increased. Further, Loudoun County Public Schools will agree that in the event closing
does not occur, ten thousand dollars ($10,000) of the deposit will be forfeited to Seller.
4 (A) Loudoun county Public Schools will agree to the proposed closing date, provided it
has the option to extend closing for up to 120 days if it is caught/bogged down in the
approval process. Of course, Loudoun County Public Schools agrees to promptly initiate
9 (B) Loudoun County Public Schools agrees that any required compliance may be
accomplished after the conclusion of the Study period. Loudoun county public
Please promptly let me know if these are acceptable to your clients. If they are, I will revise the
&u
E. William Chapman
{:
formerly
represented Sal
Cangiano
Proposals
Develop Criteria & Prepare &
Bidding Received and
Weighting Advertise RFP
Evaluated
*Criteria examples:
» Projected Student Population Location (proximate) » Physical characteristics (size, topography, floodplain, wetlands, etc…
» Length of bus ride » Compatibility with surrounding land use
» Proximate to other schools (clusters) » Conformance with Plan Policies, Zoning
» Access (vehicular and pedestrian) » Cost
» Availability of Public Utilities » Willing seller