QUANTITY TAKE-OFF:

COLOR CODE:
Supply the values:
Computed values:
Quntity Required:
Factors:
Data available:
CODE Requirements

ITEM PARTICULARS Unit Qty.

A BATTERBOARD:

Measure:
Total Perimeter m 18
Number of Outer Corner units 4
Number of Inside Corner units 0

Computed Length
CL = TP + OC*2m - IC*2m m 26

Batterboard: using 2"x2"x12' wood


Reqd No. 2"x 2" x 12' wood pcs 7
Formula = CL *3.28 / 12

Stake: using 2"x2"x4' wood @ 1.20m o.c.


Reqd No. 2"x 2" x 12' wood pcs 7
Formula = (CL / 1.2)/3

CWN = (BF/1000)x45 kgs 2.6


#16 GI Wire = (BF/4000)x45 kgs 0.2

B EXCAVATION:

B.1 Wall Footings WF-1

width m 0.30
depth m 0.45
length m 20.00
volume = w x d x L m³ 2.70

Total Volume m³ 5.40

B.2 Column Footings CF-1

width m 1.00
length m 1.00
depth m 0.90
number units 4.00
volume = w x L x d x n m³ 3.60

Total Volume m³ 16.92

C CONCRETE WORKS - FOOTINGS

C.1 Wall Footings WF-1

width m 0.30
thickness m 0.15
length m 20.00
area = w x L m² 6.00
volume = w x t x L m³ 0.90

Total Volume m³ 1.80

Materials:
Gravel bed - 3/4" = [(A1+A2+An)x0.05]+10% m³ 0.66
Concrete Mixture: Class B - 2000 to 2500 psi
Portland Cement = Vol x 7 bags/cu.m. bags 13
White Sand = Vol x 0.50 cu.m. / cu.m. m³ 0.900
Gravel bed - 3/4" = Vol x 0.99 cu.m. / cu.m. m³ 1.782

C.2 Column Footings CF1

width m 1.00
length m 1.00
thickness m 0.25
number units 4
area = w x L x n m² 4.00
volume = w x L x d x n m³ 1.00

Total Volume m³ 3.70


Materials:
Gravel bed - 3/4" = [(A1+A2+An)x0.05]+10% m³ 0.88
Concrete Mixture: Class B - 3000 to 3500 psi
Portland Cement = Vol x 8.5 bags/cu.m. bags 31
White Sand = Vol x 0.48 cu.m. / cu.m. m³ 1.776
Gravel bed - 3/4" = Vol x 0.96 cu.m. / cu.m. m³ 3.552

D CONCRETE WORKS - COLUMNS C1

dim 1 m 0.30
dim 1 m 0.30
length m 3.00
number units 4
volume = d1 x d2 x L x n m³ 3.60

Total Volume m³ 12.00

Materials:
Concrete Mixture: Class B - 3000 to 3500 psi
Portland Cement = Vol x 8.5 bags/cu.m. bags 102
White Sand = Vol x 0.48 cu.m. / cu.m. m³ 5.760
Gravel bed - 3/4" = Vol x 0.96 cu.m. / cu.m. m³ 11.520

E CONCRETE WORKS - FLOOR BEAMS FB-1

dim 1 m 0.20
dim 1 m 0.30
length m 30.00
volume = d1 x d2 x L x n m³ 1.80

Total Volume m³ 3.96

Materials:
Concrete Mixture: Class B - 3000 to 3500 psi
Portland Cement = Vol x 8.5 bags/cu.m. bags 34
White Sand = Vol x 0.48 cu.m. / cu.m. m³ 1.901
Gravel bed - 3/4" = Vol x 0.96 cu.m. / cu.m. m³ 3.802

F CONCRETE WORKS - SHORED SLAB S-1

length m 4.00
width m 3.00
thickness m 0.10
volume = L x W x t m³ 1.20

Total Volume m³ 2.19

Materials:
Concrete Mixture: Class B - 3000 to 3500 psi
Portland Cement = Vol x 8.5 bags/cu.m. bags 19
White Sand = Vol x 0.48 cu.m. / cu.m. m³ 1.051
Gravel bed - 3/4" = Vol x 0.96 cu.m. / cu.m. m³ 2.102

G CONCRETE WORKS - ON-GRADE SLAB S-1

length m 4.00
width m 3.00
thickness m 0.10
area = L x W m² 12.00
volume = L x W x t m³ 1.20

Total Volume m³ 2.19

Materials:
Gravel bed - 3/4" = [(A1+A2+An)x0.05]+10% m³ 1.20
Concrete Mixture: Class B - 2000 to 2500 psi
Portland Cement = Vol x 7 bags/cu.m. bags 15
White Sand = Vol x 0.50 cu.m. / cu.m. m³ 1.095
Gravel bed - 3/4" = Vol x 0.99 cu.m. / cu.m. m³ 2.168

H FORM WORKS:

Columns:
Facing Area (Manually computed) m² 25.00
Facing Member (2"x2") = FA x 10.76BF/m² BF 269.00
Support & Brace (2"x2" & 2"x3") = FA x 18.83BF/m² BF 470.75

Beam Bottoms: (Height from Floor = 3 to 4 m)


Facing Area (Manually computed) m² 30.00
Facing Member (2"x2") = FA x 21.52BF/m² BF 645.60
Support & Brace (2"x2" & 2"x3") = FA x 29.60BF/m² BF 888.00
Beam Sides: (Height from Floor = 3 to 4 m)
Facing Area (Manually computed) m² 25.00
Facing Member (2"x2") = FA x 10.76BF/m² BF 269.00
Support & Brace (2"x2" & 2"x3") = FA x 18.83BF/m² BF 470.75

Slabs: ( Thickness = 4" to 6" & Height = 3.0m fr Flr)


Facing Area (Manually computed) m² 50.00
Facing, Bracing & Supports = FA x 32.28BF/m² BF 1614.00

Totals:
Facing Members (2" x 2" wood) BF 1716.22
Supports & Braces (2" x 3" & 2" x 4" wood) BF 2910.88

Other Materials:
Total Facing Area m² 130.00
Number of Uses uses 3
Reqd Area = TFA / NU m² 43.33
Plywood 4' x 8' x 1/4" ordinary = RA / 2.98 shts 15

Lumber:
Facing Members = Total BF / NU BF 572.07
Supports & Braces = Total BF / NU BF 970.29
Total = BF 1542.37

Consumables:
CWN = TBF x 45 / 2500 kgs 28
#16 GI Wires = TBF x 45 / 4000 kgs 17

I CHB WALLS:

CONCRETE HOLOW BLOCKS 150 mm (6 inches)


A6 = 6" CHB Wall Area (Computed Manually) m² 30

Materials Required:
6" CHB = A6 x 12.5 pcs 38

Mortar: Mixture = 1:4 Class = C


Portland Cement = A6 x 0.759 Bags/sqm Bags 23
White Sand = A6 x 0.08438 cu.m./sqm m³ 2.53

Plaster: Mixture = 1:3 Class = B


Plaster Area = A6 x 2 m² 60
Portland Cement = PA x 0.225 Bags/sqm Bags 14
White Sand = PA x 0.05 cu.m./sqm m³ 3.00

CONCRETE HOLOW BLOCKS 100 mm (4 inches)


A4 = 4" CHB Wall Area (Computed Manually) m² 28

Materials Required:
4" CHB = A64x 12.5 pcs 35

Mortar: Mixture = 1:4 Class = C


Portland Cement = A4 x 0.394 Bags/sqm Bags 11
White Sand = A4 x 0.04375 cu.m./sqm m³ 1.23

Plaster: Mixture = 1:3 Class = B


Plaster Area = A4 x 2 m² 56
Portland Cement = PA x 0.225 Bags/sqm Bags 13
White Sand = PA x 0.025 cu.m./sqm m³ 1.40

J CHB REBARS:

Area (Specify) m² 28

Vertical Bars: factor


Spacing: 0.40 m m/m² 2.93
0.60 m m/m² 2.13
0.80 m m/m² 1.60

Total Length = A x factor m 59.64


Required: (specify diameter)
10mm dia x 6.0m long = TL / 6.0 pcs 10

Horizontal Bars: factor


Spacing: every 2 layers m/m² 3.30
every 3 layers m/m² 2.15
every 4 layers m/m² 1.72

Total Length = A x factor m 60.20


Required: (specify diameter)
10mm dia x 6.0m long = TL / 6.0 pcs 10
Total Number of 10mm dia x 6.0m rebars pcs 20
Weight = N x 3.70kg/pc kgs 73.90
Weight of #16 GI Wire = Wt *45 / 3000 kgs 1.11

K WALL FOOTING REBARS:


WF-1
Longitudinal Rebars:
Number of Logitudinal Bars pcs 3
Total length m 20.00
Reqd 6.0m long Rebars = (L x N)/5.70m pcs 11
(note: 0.30m for splicing allowance)

Transverse Rebars:
Spacing of Bars m 0.30
Total length of WF1 m 20.00
Width of Wall Footing m 0.30
Effective Cut Size of Transbars = W-2x0.05 m 0.20
Number of WF1 units 4
Reqd Number of Cut Size = (L / S) + (1 x units) pcs 71
Number of cut size in 1-6m long rebars = 6.0/ECS pcs 30
Reqd 6.0m long Rebars = RN / NCS pcs 2

L COLUMN FOOTING REBARS:


CF-1
Dimensions:
Width m 1.00
Length m 1.00
Thickness m 0.25
N Number units 4

Longitudinal Rebars:
Number of Logitudinal Bars pcs 5
TNB Total number of bars pcs 20
CC Concrete Cover m 0.075
H If HookS are required, choose for bar dia:
for 12 mm (1/2") , add this length 0.33
for 16 mm (5/8") 0.43
for 20 mm (3/4") 0.51
for 25mm (1") 0.67

Ø Bar diameter mm 16
LB Length of one bar = L - (CC x 2) + H m 1.28
NCS No. of cut size in one-6.0m standard length pcs 5
Reqd 6.0m long Rebars = TNB / NCS pcs 4
(note: 0.30m for splicing allowance)
Required: 16mm Ø x 6.0 m Deformed Bars pcs 20

Transverse Rebars:
Number of Transverse Bars pcs 5
TNB Total number of bars pcs 20
CC Concrete Cover m 0.075
H If HookS are required, choose for bar dia:
for 12 mm (1/2") , add this length 0.33
for 16 mm (5/8") 0.43
for 20 mm (3/4") 0.51
for 25mm (1") 0.67

Ø Bar diameter mm 16
LB Length of one bar = L - (CC x 2) + H m 1.28
NCS No. of cut size in one-6.0m standard length pcs 5
Reqd 6.0m long Rebars = TNB / NCS pcs 4
(note: 0.30m for splicing allowance)
Required: 16mm Ø x 6.0 m Deformed Bars pcs 14

M COLUMN REBARS:

Ground Floor Column (fr Footing to 2nd Floor Line) C1


Dimensions:
dim 1 m 0.30
dim 2 m 0.30
L1 Length (ground floor line to 2nd floor line) m 3.00
L2 Depth from ground floor line to bottom of footing m 0.90
CC Concrete Cover + 2 x Diameter of Footing Rebars m 0.08
N Number units 4

Main Bars:
Number of Bars pcs 8
TNB Total number of bars pcs 32
H Required L Hook, choose for bar dia:
for 12 mm (1/2") , add this length 0.153
for 16 mm (5/8") 0.203
for 20 mm (3/4") 0.254
for 25mm (1") 0.318
Ø Bar diameter mm 16
LB Length of one bar = L1+L2 - CC + H m 4.03
NCS No. of cut size in one-6.0m standard length pcs 1.49
Reqd 6.0m long Rebars = TNB / NCS pcs 21

Required: 16mm Ø x 6.0 m Deformed Bars pcs 59


WF-2 WF-3

0.40
0.45
15.00
2.70 0.00

CF-2 CF-3

1.00 1.50
1.20 1.50
0.90 1.50
4.00 4.00
4.32 9.00

WF-2 WF-3

0.40
0.15
15.00
6.00 0.00
0.90 0.00

CF2 CF3

1.00 1.20
1.20 1.50
0.25 0.25
4 4
4.80 7.20
1.20 1.50
C2 C3

0.40 0.25
0.40 0.30
3.00 3.00
4 4
4.80 3.60

FB-2 FB-3

0.20 0.20
0.40 0.40
12.00 15.00
0.96 1.20

S-2 S-3

3.00 2.00
2.50 1.20
0.10 0.10
0.75 0.24

S-2 S-3

3.00 2.00
2.50 1.20
0.10 0.10
7.50 2.40
0.75 0.24
WF-2 WF-3

3 3
15.00 0.00
8 0

0.30 0.30
15.00 0.00
0.30 0.30
0.20 0.20
4 0
54 0
30 30
2 0

CF-2 CF-3

1.00 1.20
1.20 1.50
0.25 0.25
4 4

6 8
24 32
0.075 0.075

0.33 0.33
0.43 0.43
0.51 0.51
0.67 0.67

16 16
1.48 1.78
4 3
6 9

5 6
20 24
0.075 0.075

0.33 0.33
0.43 0.43
0.51 0.51
0.67 0.67

16 16
1.28 1.48
5 4
4 6

C2 C3

0.40 0.25
0.40 0.30
3.00 3.00
0.90 0.90
0.08 0.08
4 4

8 6
32 24

0.153 0.153
0.203 0.203
0.254 0.254
0.318 0.318
20 16
4.08 4.03
1.47 1.49
22 16