COLOR CODE:
Supply the values:
Computed values:
Quntity Required:
Factors:
Data available:
CODE Requirements
A BATTERBOARD:
Measure:
Total Perimeter m 18
Number of Outer Corner units 4
Number of Inside Corner units 0
Computed Length
CL = TP + OC*2m - IC*2m m 26
B EXCAVATION:
width m 0.30
depth m 0.45
length m 20.00
volume = w x d x L m³ 2.70
width m 1.00
length m 1.00
depth m 0.90
number units 4.00
volume = w x L x d x n m³ 3.60
width m 0.30
thickness m 0.15
length m 20.00
area = w x L m² 6.00
volume = w x t x L m³ 0.90
Materials:
Gravel bed - 3/4" = [(A1+A2+An)x0.05]+10% m³ 0.66
Concrete Mixture: Class B - 2000 to 2500 psi
Portland Cement = Vol x 7 bags/cu.m. bags 13
White Sand = Vol x 0.50 cu.m. / cu.m. m³ 0.900
Gravel bed - 3/4" = Vol x 0.99 cu.m. / cu.m. m³ 1.782
width m 1.00
length m 1.00
thickness m 0.25
number units 4
area = w x L x n m² 4.00
volume = w x L x d x n m³ 1.00
dim 1 m 0.30
dim 1 m 0.30
length m 3.00
number units 4
volume = d1 x d2 x L x n m³ 3.60
Materials:
Concrete Mixture: Class B - 3000 to 3500 psi
Portland Cement = Vol x 8.5 bags/cu.m. bags 102
White Sand = Vol x 0.48 cu.m. / cu.m. m³ 5.760
Gravel bed - 3/4" = Vol x 0.96 cu.m. / cu.m. m³ 11.520
dim 1 m 0.20
dim 1 m 0.30
length m 30.00
volume = d1 x d2 x L x n m³ 1.80
Materials:
Concrete Mixture: Class B - 3000 to 3500 psi
Portland Cement = Vol x 8.5 bags/cu.m. bags 34
White Sand = Vol x 0.48 cu.m. / cu.m. m³ 1.901
Gravel bed - 3/4" = Vol x 0.96 cu.m. / cu.m. m³ 3.802
length m 4.00
width m 3.00
thickness m 0.10
volume = L x W x t m³ 1.20
Materials:
Concrete Mixture: Class B - 3000 to 3500 psi
Portland Cement = Vol x 8.5 bags/cu.m. bags 19
White Sand = Vol x 0.48 cu.m. / cu.m. m³ 1.051
Gravel bed - 3/4" = Vol x 0.96 cu.m. / cu.m. m³ 2.102
length m 4.00
width m 3.00
thickness m 0.10
area = L x W m² 12.00
volume = L x W x t m³ 1.20
Materials:
Gravel bed - 3/4" = [(A1+A2+An)x0.05]+10% m³ 1.20
Concrete Mixture: Class B - 2000 to 2500 psi
Portland Cement = Vol x 7 bags/cu.m. bags 15
White Sand = Vol x 0.50 cu.m. / cu.m. m³ 1.095
Gravel bed - 3/4" = Vol x 0.99 cu.m. / cu.m. m³ 2.168
H FORM WORKS:
Columns:
Facing Area (Manually computed) m² 25.00
Facing Member (2"x2") = FA x 10.76BF/m² BF 269.00
Support & Brace (2"x2" & 2"x3") = FA x 18.83BF/m² BF 470.75
Totals:
Facing Members (2" x 2" wood) BF 1716.22
Supports & Braces (2" x 3" & 2" x 4" wood) BF 2910.88
Other Materials:
Total Facing Area m² 130.00
Number of Uses uses 3
Reqd Area = TFA / NU m² 43.33
Plywood 4' x 8' x 1/4" ordinary = RA / 2.98 shts 15
Lumber:
Facing Members = Total BF / NU BF 572.07
Supports & Braces = Total BF / NU BF 970.29
Total = BF 1542.37
Consumables:
CWN = TBF x 45 / 2500 kgs 28
#16 GI Wires = TBF x 45 / 4000 kgs 17
I CHB WALLS:
Materials Required:
6" CHB = A6 x 12.5 pcs 38
Materials Required:
4" CHB = A64x 12.5 pcs 35
J CHB REBARS:
Area (Specify) m² 28
Transverse Rebars:
Spacing of Bars m 0.30
Total length of WF1 m 20.00
Width of Wall Footing m 0.30
Effective Cut Size of Transbars = W-2x0.05 m 0.20
Number of WF1 units 4
Reqd Number of Cut Size = (L / S) + (1 x units) pcs 71
Number of cut size in 1-6m long rebars = 6.0/ECS pcs 30
Reqd 6.0m long Rebars = RN / NCS pcs 2
Longitudinal Rebars:
Number of Logitudinal Bars pcs 5
TNB Total number of bars pcs 20
CC Concrete Cover m 0.075
H If HookS are required, choose for bar dia:
for 12 mm (1/2") , add this length 0.33
for 16 mm (5/8") 0.43
for 20 mm (3/4") 0.51
for 25mm (1") 0.67
Ø Bar diameter mm 16
LB Length of one bar = L - (CC x 2) + H m 1.28
NCS No. of cut size in one-6.0m standard length pcs 5
Reqd 6.0m long Rebars = TNB / NCS pcs 4
(note: 0.30m for splicing allowance)
Required: 16mm Ø x 6.0 m Deformed Bars pcs 20
Transverse Rebars:
Number of Transverse Bars pcs 5
TNB Total number of bars pcs 20
CC Concrete Cover m 0.075
H If HookS are required, choose for bar dia:
for 12 mm (1/2") , add this length 0.33
for 16 mm (5/8") 0.43
for 20 mm (3/4") 0.51
for 25mm (1") 0.67
Ø Bar diameter mm 16
LB Length of one bar = L - (CC x 2) + H m 1.28
NCS No. of cut size in one-6.0m standard length pcs 5
Reqd 6.0m long Rebars = TNB / NCS pcs 4
(note: 0.30m for splicing allowance)
Required: 16mm Ø x 6.0 m Deformed Bars pcs 14
M COLUMN REBARS:
Main Bars:
Number of Bars pcs 8
TNB Total number of bars pcs 32
H Required L Hook, choose for bar dia:
for 12 mm (1/2") , add this length 0.153
for 16 mm (5/8") 0.203
for 20 mm (3/4") 0.254
for 25mm (1") 0.318
Ø Bar diameter mm 16
LB Length of one bar = L1+L2 - CC + H m 4.03
NCS No. of cut size in one-6.0m standard length pcs 1.49
Reqd 6.0m long Rebars = TNB / NCS pcs 21
0.40
0.45
15.00
2.70 0.00
CF-2 CF-3
1.00 1.50
1.20 1.50
0.90 1.50
4.00 4.00
4.32 9.00
WF-2 WF-3
0.40
0.15
15.00
6.00 0.00
0.90 0.00
CF2 CF3
1.00 1.20
1.20 1.50
0.25 0.25
4 4
4.80 7.20
1.20 1.50
C2 C3
0.40 0.25
0.40 0.30
3.00 3.00
4 4
4.80 3.60
FB-2 FB-3
0.20 0.20
0.40 0.40
12.00 15.00
0.96 1.20
S-2 S-3
3.00 2.00
2.50 1.20
0.10 0.10
0.75 0.24
S-2 S-3
3.00 2.00
2.50 1.20
0.10 0.10
7.50 2.40
0.75 0.24
WF-2 WF-3
3 3
15.00 0.00
8 0
0.30 0.30
15.00 0.00
0.30 0.30
0.20 0.20
4 0
54 0
30 30
2 0
CF-2 CF-3
1.00 1.20
1.20 1.50
0.25 0.25
4 4
6 8
24 32
0.075 0.075
0.33 0.33
0.43 0.43
0.51 0.51
0.67 0.67
16 16
1.48 1.78
4 3
6 9
5 6
20 24
0.075 0.075
0.33 0.33
0.43 0.43
0.51 0.51
0.67 0.67
16 16
1.28 1.48
5 4
4 6
C2 C3
0.40 0.25
0.40 0.30
3.00 3.00
0.90 0.90
0.08 0.08
4 4
8 6
32 24
0.153 0.153
0.203 0.203
0.254 0.254
0.318 0.318
20 16
4.08 4.03
1.47 1.49
22 16