Quality Assurance Requirements

Check List & ITPs (Inspection & Test Plans)


This page is going to be updated as & when certain check lists & ITPs are ready for the
assistance of those who intend to improve their QA skills.

By P Eng Suraj Singh

Setting Out & Excavations: Item # 1


Reference to project key plans & individual building plans:
Grids calculations in all directions:
Grid angles in all directions:
Level profiles conversion from GPS:
Are coordinates converted from real co ordinates?:
Third party certification (option):
Setting of offsets from building lines:
Margin for working areas:
In case way leave required:
Action on way leave requirement:
Record of running services:
Effect of running live services:
Programme for diversion if required:
Coordination with statutory bodies:
Whether or not NOC required?:
Whether or not excavation is Hot work?:
Safety measures to be adopted during excavations:
Traffic diversions to be adopted during excavations:
Whether or not method Statement approved?:
What equipments to be used?:
Are workers fully informed of site safety?:
Are shoring materials on site?:
Are ingress & egress to & from trench well planned?:
Shall work be done during night hours?:
If so, has police permission been obtained:
Is stockpiles area is readily available?:
Are environment protection measures intact?:
Is dumping area available?:
Definition of duration of excavation?:
Dewatering arrangement whether or not required?:
Are oxygen cylinders available if so required in confined areas?:
Are Aluminum ladders available?:
Are masks available for all personnel?:
Are safety glasses available?:
Has tool box talks been delivered?:
Has emergencies communication system been in place?:
Responsible personnel to be dedicatedly to be present on excavation?:
Is water tanker available for spreading water?:
Have neighbour existing buildings been checked of any adversity in case of deep
excavations or dewatering?

For excavations in certain areas, mechanical excavation cannot be applied


without ensuring about the live lines. Hand excavation is carried out for
resolution of the applicable method of excavation.
Hand Excavations: Item # 2
Location of relevant pits whether or not, in line to record drawings?:
Has these locations been discussed with relevant services authority?:
Has temporary permit been obtained?:
Has method statement for such excavation been approved?:
What is the indicative depth of excavation?:
Are the involved technician qualified for such significant operation?:
Is it the direct excavation method using hand tools?:
Or it is hydrojetting involvement?:
What precautionary methods have been adopted to protect unexpected
accident?:
Who shall supervise such delicate excavation?:
Is the follow up procedure well defined?:
Is the authority for live services discovering intimation known?:
Is the duration for diversion activity known?:
Is the method of maintaining services protection known?:
What measures to be adopted in case of failure to protect?:
Shall such services interruption impact the plant operation?:
Shall information to police be required?:

After the excavation progresses, further checks need be performed at various


stages. In deeper excavation requiring benching, additional checks would be
required.
Check List for Formation: Item # 3
Has the formation approximately reached which can be checked by reduced
level flying from the fixed datum bench mark RL?:
Is this RL applicable to formation level or to foundation blinding bottom
level?:
Has the factual SBC been confirmed either by plate load test or by some
other applicable load test?:
Whether the formation is in water or it is in moist condition?:
Does the soil show dry area conditions?:
Has dewatering activity been continuously working, if so applicable?:
Has the field density test at the formation level been conducted?:
Does soil need improvement either by replacement or by some other suitably
optimised method?:
Is soil improvement indicated on the project structural drawings?:
Has shoring been in place during excavation progress?:
Is the soil supporting system safe for the workers?:
Can formation compaction be conducted conveniently?:
Is soil condition indicating stronger soil than as specified?:
Is it economical to recommend redesign of foundation?:
Can equipment safely move to formation & work efficiently for various
purposes?:
Have various grids been erected in place temporarily for verification of
structures’ axii?:
If soil improvement is not required, can blinding preparatory works move?:

Regards

Check List for blinding Item # 4


Ensure formation is well prepared
Whether or not, anti termite treatment is specified?
If required apply the treatment through specialist
Marking of blinding areas
Batten forms of lines of areas duly fixed
Arrangement of blinding top profile
Whether or not, blinding pour is by RMC & if so, whether or not pump is required?
Ensure required strength of concrete pour gang
Ensure post concrete curing arrangement
Ensure tools for smooth finish are available
Plan sequence of pour
Plan pump locations
Plan concrete delivery frequency
Ensure that pour is not unreasonably delayed when anti termite treatment is applied
Ensure that area is constantly kept dry
Regards

Check List for Concrete Protection / Waterproofing Item # 5


Ensure that blinding is well cured for a minimum of three days
Ensure whether or not surface is smooth
Apply repairs if needed
Ensure all battens or forms removed
Whether it is cold or hot application?
Can specialist application be proceeded?
Regards

Check List for Foundation / Footings preparatory works Item # 6


Ensure whether or not, protection applied on concrete protection?
Ensure setting out for foundations in line with drawings
Ensure rebars are fabricated & assembled to specification requirements
Ensure formworks of footings match the designs
Ensure rebars are properly placed & fixed
Ensure formworks are true to plumb & lines
Ensure concrete spacers whether plastic or concrete mix, are placed well
Ensure whether or not, cathodic protection required
Provide if so required followed by continuity check
Check footings alignments better in grid references
Check the footing top levels
Check the supporting system for formwork sides
Ensure concrete protection is not damaged during preparatory works
Make sure that a safe access to all footings & strong working platform for workers &
vibrator is erected before inspection for pouring concrete
Check water hose pipe is available to all foundations
Check curing arrangements are made available
Specific for concrete covers: In certain cases, thicker cover is specified for the stub
column portion for which extra size of stub need executed. Ensure that care is taken
thereof. for construction joint.
Regards

Check List for Stub Columns preparatory works Item # 7


Ensure setting out for stub columns in line with drawings’ requirements
Ensure rebars are fabricated & assembled to specification requirements
Ensure rebars are properly placed, fixed & cleaned
Ensure proper touch up paint applied on epoxy coated rebars, if so included
Ensure construction joint is correctly scabbled or chipped or hacked
Ensure proper concrete covers are installed duly tied up
Ensure formwork is in line in all directions
Ensure formwork is well secured
Ensure forms are all set in plumb on all sides to make a base for upper forms
Ensue whether or not, plinth or other beans preparatory works to be monolithic or
otherwise.
Make sure steel dowels are in place if separate casting programmed for beams
Ensure all supports are properly fixed at bottom & at top of stub if not more than 1200
mm height.
Ensure steel clamps are in place duly tightened or tie bolts are fastened well
Ensure whether or not pipe sleeve installed for tie bolts passing through column body
Ensure whether or not, cathodic protection required. If so required, whether or not, it is
critical? If it is non critical, whether, bosses & GI wires are available.
Check water hose pipe is available to all areas of stubs
Check curing arrangements are made available
Make sure that a safe access to all stubs & strong working platform or plates for workers
& vibrator are in place before inspection for pouring concrete
Regards

Check List for backfill works Item # 8


Make sure that selected fill or imported fill or desert fill materials are approved
Make sure that recommended additive materials are made available, if so required
Make sure that stocks of backfill materials are located in some reachable place
Make sure that screening of the larger particles is well done
Make sure that proper watering on the material is effected for initial mixing
Check whether or not all sub structural activities are completed including block or brick
works
Check that all rubbishes & debris are cleared from area
Ensure concrete protection applied on all surfaces & well protected
Ensure bottom portion of shoring removed
Ensure stages of shoring removal during backfill progression
Ensure backfill approvals
Ensure necessary equipment available (shovel, small roller, plate compactor etc)
Decide number of backfill layers
Decide number of field density tests required from every layer
Decide number of passes of small roller or plate compactor
Decide to use jumper in corners where, compactor otherwise, cannot work
Regards

Check List for grade slab (floating slab @ plinth level) works Item # 9
Ensure that backfill carried out properly to underside of grade slab blinding
Ensure requirement to comply with field density
Ensure all type of services required below grade slab, have been carried out duly tested
successfully for first fix
Ensure whether or not, pipes surroundings have been done in compliance with
specifications
Make an option whether or not, blinding shall be required & if so
Establish top of blinding levels
Ensure necessary block outs provision forms have been provided
Ensure waterproofing / concrete protection on plinth beams or plinth walls has been done
properly duly protected
Ensure proper profile of the proposed concrete for the blinding works
In case, blinding is not required, check for grade slab
Ensure that polythene isolation membrane is in place
Ensure that perimeter joints materials are placed properly
Ensure that either on blinding topped with polythene membrane or directly on polythene
membrane on compacted soil, welded fibre mesh is placed in
Ensure adequate supporting chairs are placed in
Ensure first fix of electrical, instrumentation, communication etc are completed
Ensure adequate area is available for a smooth pour
Ensure grade slab level profile is fixed correctly
Plan inspection as well as pour
Regards

Check List for RCC Columns works Item # 10


Ensure scaffolding with working platform is in position for access around columns for
preparatory works
Ensure rebar fixing is correct to requirement. Overlap should be fixed correct to
specifications. Lowest ring should start at half of spacing location from structural level.
Ensure rebars be well tightened & maintained in plumb.
Ensure rebars are clean & free from rust.
Ensure sacrificial anode is fixed, if so required
Ensure touch up paint is applied in case of epoxy coated rebars
Ensure electrical & other required inserts are fixed & approved
Ensure all concrete spacers are placed in position
Try to avoid excessive spacers within column main body, if not so required
Check that these spacers are fixed on top portion out of top of concrete
Ensure all inspection before closing the rebars by formwork
Check whether or not, starter or kicker is convenient.
Preferably, it should be avoided
Check forms are fixed in position correctly
Check sides supporting system intact
Check grid offset thread lines are available
Check from both axis reference to ascertain column location
Check tie bolts are fixed preferably outside of column section
Do not tighten them immediately but after ensuring location & plumb
Top inclined support is meant for keeping forms in position
Middle support located & fixed at one third from bottom is meant for resisting resultant
fluid pressure during pour
Bottom horizontal support is meant for holding form work foot
Check whether or not heavy plumb bobs are hung from top of forms on at least two sides
on both axis. Heavy plumb bob means either use heavy concrete piece or brick etc.
Binding wire can also be used to hang the heavy weight. Timber piece can be fixed on
top to hang bob
First check form location at bottom, then at top on both axis
Check the location somewhere at middle
After ensuring form location, check the plumbs on both directions at three locations
vertically in full height casting
Check for adjustments if so required, to bring the errors within permissible limits
Once, forms are checked for horizontal & vertical location, start fastening the ties &
ensure supports are well anchored
Having completed various columns preparatory works, move for working platform
operations & check the stability of the system
Plan for inspection & pour
Regards

Check List for RCC Walls works Item # 11


Ensure scaffolding with working platform is in position for access on both sides of walls
for preparatory works
Ensure rebar fixing is correct to requirement. Overlap should be fixed correct to
specifications. Lowest links should start at half of spacing location from structural level.
Ensure rebars be well tightened & maintained in plumb.
Ensure that all U shape bars or even if so required, rings are rightly fixed in position &
well secured or anchored
Ensure rebars are clean & free from rust.
Ensure sacrificial anode is fixed, if so required
Ensure touch up paint is applied in case of epoxy coated rebars
Ensure electrical & other required inserts are fixed & approved
Ensure all concrete spacers are placed in position on both sides
Try to avoid excessive spacers within wall main body, if not so required
Check that these spacers are fixed on top portion out of top of concrete
Ensure all inspection before closing the rebars by formwork
Check whether or not, starter or kicker is convenient.
Preferably, it should be avoided
Check forms are fixed in position correctly
Check sides supporting system intact at one side when bolts are used
Check grid offset thread lines are available
Check from both axis reference to ascertain wall location
Check tie bolts are fixed preferably inside of wall section
Check that these bolts pass through plastic sleeve with bosses at ends
Do not tighten them immediately but, after ensuring location & plumb
Top inclined support is meant for keeping forms in position
Middle support located & fixed at one third from bottom is meant for resisting resultant
fluid pressure during pour
Bottom horizontal support is meant for holding form work foot
Check whether or not heavy plumb bobs are hung from top of forms on at least three or
more locations depending on length of RCC wall. Heavy plumb bob means either use
heavy concrete piece or brick etc. Binding wire can also be used to hang the heavy
weight. Timber piece can be fixed on top to hang bob. In case, proprietary system is used
in place of site fabricated, check the system is in line with system manufacturer drawings.
First check form location at bottom, then at top
Check the location somewhere at middle
After ensuring form location, check the plumbs on all locations vertically in full height
casting
Check for adjustments if so required, to bring the errors within permissible limits
Once, forms are checked for horizontal & vertical location, start fastening the ties &
ensure supports are well anchored
Having completed various walls preparatory works, move for working platform
operations & check the stability of the system
Plan for inspection & pour
Check adequate working space is available within wall preparatory works about passage
of pump pipe down to at least 1.5 to 2 m above lowest starting point
Remember that wall pour is slow but steady as it has to be poured in rotations of heights
not more than depth of nozzle
It would risk opening forms in case, pour is allowed fast
Wall is not an element like columns or beams & therefore, imports a good check &
attention
Regards

Check List for RCC Lift Well Walls works Item # 12


Ensure scaffolding with working platform is in position for access on both sides of
internal & external side of walls for preparatory works
Ensure safe ingress & egress to & from inside of lift well
Ensure all other safety measures such as green tags are installed
Ensure rebar fixing is correct to requirement. Overlap should be fixed correct to
specifications. Lowest links should start at half of spacing location from structural level.
Ensure rebars be well tightened & maintained in plumb.
Ensure that all U shape bars or even if so required, rings are rightly fixed in position &
well secured or anchored.
Ensue in particular corner U bars in both directions making a perpendicular
Ensure rebars are clean & free from rust.
Ensure sacrificial anode is fixed, if so required
Ensure touch up paint is applied in case of epoxy coated rebars
Ensure electrical & other required inserts are fixed & approved
Ensure all concrete spacers are placed at appropriate locations & position on both sides
Try to avoid excessive spacers within wall main body, if not so required
Check that these spacers are fixed on top portion out of top of concrete
Ensure all inspection before closing the rebars by formwork
Check whether or not, starter or kicker is convenient.
Preferably, it should be avoided
In case, proprietary system is used in place of site fabricated, check the system is in line
with system manufacturer drawings.
In case, self designed system is being followed, ensure the followings:
Check lift well door forms are additionally fixed to be concealed within main forms
Check both internal & external forms are fixed in position correctly
Check sides supporting system intact at one side when bolts are used
Check grid offset thread lines are available
Check from both axis reference to ascertain all walls locations
Check tie bolts are fixed preferably inside of wall sections in all walls
Check that these bolts pass through plastic sleeve with bosses at ends
Do not tighten them immediately but, after ensuring true locations & accurate plumb
Top inclined support is meant for keeping forms in position
Middle support located & fixed at one third from bottom is meant for resisting resultant
fluid pressure during pour
Bottom horizontal support is meant for holding form work foot
More supports can also be added depending on the height of proposed pour. Also, the
spacing of tie bolts would require number of added supports.
Check whether or not, tie bolts have been designed to withstand the forces imposed by
liquid concrete safely.
Check all corners of the forms are well anchored without causing any worry for opening
or relocation of forms or getting twisted
Also, check internal forms that should be provided with adequate cross inclined supports
though located in the middle of forms at various locations
Check whether or not, heavy plumb bobs are hung from top of forms on at least three or
more locations depending on length of RCC wall. Heavy plumb bob means either use
heavy concrete piece or brick etc. Binding wire can also be used to hang the heavy
weight. Timber piece can be fixed on top to hang bob..
First check form location at bottom, then at top
Check the location somewhere at middle
After ensuring form location, check the plumbs on all locations vertically in full height
casting
Check for adjustments if so required, to bring the errors within permissible limits
Once, forms are checked for horizontal & vertical location, start fastening the ties &
ensure supports are well anchored
Having completed all walls preparatory works, move for working platform operations &
check the stability of the system
Plan for inspection & pour
Check adequate working space is available within walls preparatory works about passage
of pump pipe down to at least 1.5 to 2 m above lowest starting point
Check for raising a strong temporary platform internally as well for working
Remember that walls pour is slow around the walls but, steady as it has to be poured in
rotations of heights not more than depth of nozzle
It would risk opening forms in case, pour is allowed fast
Wall is not an element like columns or beams & therefore, imports a good check &
attention. Lift well walls are a complicated pour that should be taken due care of.
Regards

Check List for RCC Longitudinal Stair works Item # 13


Conduct In depth Coordination on drawings for relevant involved activities.
Actual details pertaining following settings should be charted out clearly for
communication to site. Any error may mar site work in stair case.

Setting of lowest beam- can be carried out in one go easily whether or not, it is monolithic
with grade slab
Setting of columns – it is a little tedious as a decision has to be taken about whether stage
casting of column or full casting allowing dowels
Setting of first waist slab-waist slab requires dimensions of waist soffit
Setting of landing beams-landing slab requires dimensions of soffit + beam soffit ( up
stand or down stand)
Setting of mid landing- requires dimensions of soffit
Setting of second waist slab - waist slab requires dimensions of waist soffit + beams / slab
Setting of floor portion landing- requires slab dimensions in line with main slab
Setting of floor beams- requirement of surrounding beams
Ensure the riser & tread dimensions- very significant
Ensure the structural floor height to structural floor height, matches with the riser size
summations or number of risers multiplied by size of riser
In general, calculation & setting dimensions is a cumbersome process for stair work on
site. Working carpenter requires full details that either junior supervisors or surveyor on
site may not rightly communicate.
Check whether or not, all required dimensions are indicated. In case, of some important
dimension missing, use Autocad sot copy for charting out the required dimension. It is
not a tedious job by Autocad. Calculating using formula, shall not be much supportive.
It is significant to note that carpenter shall require relevant dimension necessary for
setting out formwork in three axis dimensions.
Check whether or not, supporting system scaffolding for the stair is easy as supplied by
the proprietary manufacturer or it requires to be designed on site using traditional
methods. It has been observed that many adjustments are made on site for such purposes.
Check whether or not, complete stair can be poured in one go or in two stages.
Check all rebars & have those placed in right locations.
Check all electrical inserts that are in place
Check all risers are in right locations & well anchored using middle anchorage supporting
system.
Check whether or not, railing inserts require at this stage or preferably, not required as
embedment.
Check all forms are fixed properly & well secured.
Inspection to be conducted.
Plan for pour whether first portion separately & second portion with the slab or
Plan pour all with the slab as an option.
Regards

Check List for RCC Suspended Slabs works Item # 14


Conduct In depth Coordination on drawings for relevant involved activities.
Ensure that all structural & coordinated services drawings are ready for construction.
Actual details pertaining following settings should be charted out clearly for
communication to site. Any error may mar site work in suspended slab case.
Setting of all grids in both directions are accurate.
All supporting system scaffolding drawings are ready duly approved or certified by
designer of manufacturer.
All access scaffolding details are ready.
All stepping type ladders are ready wherever required.
Materials for all areas ready for safe working in & around of the pourable area.
Materials for all areas are ready for preparatory works..
All rebars are ready duly tagged.
Ensure all columns & RCC walls are poured.
Ensure construction joints are made on column tops.
Ensure datum level lines are marked on columns surfaces.
Ensure datum level lines are marked on RCC wall surfaces.
Ensure erection of supporting either mechanical system or other system, is well handled
by the specialist trained team of riggers.
Ensue that erection or installation of system provides a good space to circulate within.
Ensure fixing of all beam bottoms of down stands are commenced with at the right
locations all over area. This is an important activity & must be ensured for correctness by
land surveyor or an experienced foreman.
Leveling of beam soffit is significant but should be within approximation at this stage for
it would be corrected by adjustments at final level check.
Ensure that beam sides are able to be stripped out conveniently while beam soffit is in
place. Soffit may be in place for defined duration of form strike.
Ensure slab soffit levels are correct & system is installed accordingly.
Ensure safety rail is available duly installed around the working area from safety reasons.
Ensure correct alignment is marked on the slab exteriors for slab sides formwork.
Ensure location of construction joint if so required, for a major pour.
Ensure that grid locations are correctly transmitted on the slab beam lines.
Ensure that beam sides could be struck easily prior to slab soffit forms.
Make sure correctness by checking levels on the slab.
Make sure correctness of the dimensions of the beam sections.
Make sure if so required, timber fillets are fixed on beam corners for the exposed faces.
Make sure that the form strike oil applied & dried out prior to placing rebars.
Ensure that rebars are centred & fixed to meet requirement. Beams may be prefabricated
on ground if so convenient, otherwise, these could be on location assembled.
Ensure that all bars are tightly bound & concrete or plastic spacers fixed uniformly.
Ensure that all services block outs are marked & fixed wherever shown.
Ensure bottom reinforcement is placed as required.
Ensure that electrical first fix conduit work is done satisfactorily & inspected by
competent electrical engineer.
Ensue adequate overlaps are available for the next floor if, that being the case.
Make sure that all overlaps or extending bars are well held by rings or stirrups.
Make sure that all mechanical connectors if used in place of overlaps, are well placed &
tightened well. Ensure that adequate space is available after mechanical connectors are
used for passage of vibrator needle.
In case, epoxy coated bars are included, ensure continuous activity of epoxy touch up
paint is made.
Make sure all previous concrete joints are well cleaned by scabbling or hacking.
Ensure that no dirt & timber piece etc. is available after cleaning by air compressor is
done.
If it is hot keep the form cool by allowing water.
Every care is required to check that flash setting would be avoided.
Ensure that stair portion to be poured with slab is well scabbled at joint locations &
rebars are cleaned properly.
Ensure cleaning of the lift well rebars.
Ensure all block outs or inserts are in place.
Make sure if so required, scaffolding manufacturer certification is obtained for
scaffolding supporting system being sound.
Make sure that all portions of beam down stands are well secured by fixing tie bolts
wherever required.
Ensure that all column caps forms are in plumb & well secured.
Ensure a thorough inspection is conducted for all preparatory as well as temporary works.
No doubt should remain unattended.
Plan pouring activity in all respects defining locations of pumps & truck mixers.
Make sure that certain formwork strips for emergency provision of construction joint is
readily available.
Chart out concrete start timing.
Chart out truck arrival sequences.
Define concrete date.
Define concrete duration.
Define curing procedures.
Check all equipment availability.
Make sure that testing laboratory technicians would attend in time.
Prior to concrete pour, check all supports & system again.
Make sure that adequate workers strength would be available during pour.
Make sure that concrete pour timings match with temperature range.
Do not work in haste as work must be safely carried out.
Make sure that responsible supervising engineer would be available during pouring.
In case, there is already one slab below the system, ensure that additional supporting
system is installed there, depending on the day of previous concrete below slab.
Once safety is overlooked, site shall be prone to untoward accident.
Regards

Check List for RCC Pedestal Footings For Steel Frames works Item # 15
Used term pedestal for approximate cubical size of footing.
Ensure setting out on blinding is OK.
Ensure reinforcement in the form of cage is rightly fabricated in all directions.
Ensure concrete covers are provided to meet requirement.
Ensure void or pocket for bolts portion is provided within top of cage.
Ensure pocket blockout is fabricated correct to truncated dimensions.
In case, anchor bolt plate needs be provided, block out shall not be required.
Have the formwork erected to required dimensions on all sides.
Have it be well secured & supported.
Have rebar cage placed in.
Ensure pocket block out placed by approved supports to hang within the pad volume.
Check grids & grid measurements.
Check dimensions of forms.
Check top of concrete levels fixing arrangement.
Regards,

Check List for RCC Footings Blocks For Steel Frames works Item # 16
For footings of long span steel frames.
In plan it s rectangular shape with considerable depth block
Ensure setting out on blinding is OK.
Ensure reinforcement in the form of cage is rightly fabricated in all directions.
Ensure concrete covers are provided to meet requirement.
Ensure void or pocket for bolts portion is provided within top of cage.
Ensure pocket blockout is fabricated correct to truncated dimensions.
In case, anchor bolt plate needs be provided, block out shall not be required.
Have the formwork erected to required dimensions on all sides.
Have it be well secured & supported.
Have rebar cage placed in.
Ensure dovels for beams if so required, are fixed.
Ensure pocket block out placed by approved supports to hang within the pad volume.
Check grids & grid measurements.
Check dimensions of forms.
Check alignment & plumb.
Check supports of forms.
Check top of concrete levels fixing arrangement.
If demanded, grade beams can also be provided monolithic.
Regards,

Check List for RCC For DC Generator & Alternator Foundation works
Item # 17
Components Involved are raft, alternator foundation in thick column form, isolation
between generator foundation & raft & generator foundation on isolation on raft.
Ensure setting out on blinding is OK.
Ensure reinforcement of raft is correctly fabricated & placed within layout.
Ensure proper concrete covers are fixed.
Ensure cathodic protection is carried out if so required.
Ensure forms are erected rightly in plan to alignment.
Ensure concrete top levels.
Ensure alternator foundation rebars are placed in correct positions.
Pouring concrete & suring activities for defined period.
Ensure steel plate mounted Neoprene pads are fixed to raft using steel made concrete
nails. These nails must do proper fixing of plates to concrete.
Check that polystyrene rolls are spread on the areas of raft but pads so that the
prefabricated plate rests on polystyrene.
Provide a rubber sheet on the whole system.
Place the following fabricated plate on laid system.
Fabrication of steel lamina frame.
Check defined guage.
Check sections of RS to be included for frame fabrication.
Ensure proper setting out of lines for RS sections.
Ensure proper marking on plate for welding.
Ensure welding operation is rightly carried out.
Ensure provisions of lifting hooks & their locations.
This plate should be placed such that lamina faces down & RS upwards to allow grip to
upper concrete foundation.
RCC works of generator foundation
Make sure reinforcement of generator block is placed in right locations in the form of
multilayer meshes.
Ensure that rebars are placed inline with design details whatsoever.
Make sure that vertical forms are erected on all sides of block.
Make sure their good fixing arrangements.
Make sure concrete covers are fixed correctly.
Check top alignment & plumbs.
Check setting out for the anchor bolts locations for blockouts.
Check block out truncated formworks.
Check these blocks outs are fixed in position & are truly vertical.
Make sure about cathodic protection if so required.
In case of cathodic protection, continuity test shall be required to be conducted.
Activity of pouring & curing
Alternator foundation works.
Follow all operations as are required for a column with addition of provision of pockets
for blockouts.
Regards,

Check List for RCC Fair Face Structural works Item # 18


Fairface does not require any plastering on the formed surfaces.
Checks for all items should be made for various vertical members as described earlier.
Ensure that quality of plywood to be used does not degrade.
Ensure that no more than 3 or 4 uses are made out of new marine plywood.
Ensure that plywood thickness be 18 mm, if feasible.
Make sure the pattern of form ply is intact as required.
Ensure that ties are provided at the designed locations.
Ensure that plastic conduits are medium to heavy duty, which do not twist.
Ensure that the plumb does not exceed out of line by 1 mm in 100 mm.
No opening of sides is allowed in fair face forms.
No unrequired joints are allowed.
Make sure all supports are well anchored.
Make proper concreting pouring arrangements.
During concreting, no voids or honeycombing are acceptable.
Regards

Check List for RCC Architectural Finish works Item # 19


Architectural finish means a selected texture to be embossed on concrete vertical surface.
Checks for all items should be made for various vertical members as described earlier.
Ensure good quality of timber planks of required length, width & thickness are procured.
Ensure the edges of planks are straight for joint formations without any cavity opening.
Arrange for the approved texture by arranging planks on a standard size of panel of wall.
Decide locations of the tie arrangements.
Decide for the support locations.
Check that arrangement of texture is symmetrical on both sides of wall.
Ensure that ties are provided at the designed locations.
Ensure that plastic conduits are medium to heavy duty, which do not twist.
Ensure that the plumb does not exceed out of line by 1 mm in 100 mm.
No opening of sides is allowed in fair face forms.
No unrequired joints are allowed.
Make sure all supports are well anchored.
Make proper concreting pouring arrangements.
During concreting, no voids or honeycombing are acceptable.
Regards

Check List for RCC Hourdy Slab works Item # 20


Hourdy precast concrete trapezoidal blocks are used at low spacing.
Checks for all items should be made for various vertical members as described earlier.
Ensure good quality Hourdy blocks of defined dimensions, are procured.
Ensure cut size blocks to suit the site, are procured.
Ensure slab form is fixed on the scaffolding system as usual.
Ensure whole slab area is in one level without beams form works.
Check the setting out of beams in both directions.
Check Hourdy block works are carried out correctly on lines.
Check vertical space availability for receiving thin slab cast in situ concrete.
Check rebars for the beams are placed correctly.
Check rebars for the slabs are placed correctly.
Check all services embeds that run through the beams as well as through the Hourdy
block void cavities.
Be careful for Hourdy slab works as coordination of services works is a little bit
cumbersome & complicated activity.
It is to be noted that slab is too thin say about 60 mm & therefore, services embeds may
not find any room through or within slab portion.
Regards

Check List for RCC Sloping Portion Floor Slab works Item # 21
Check that all operations would be done as defined within other operations of grade
slabs. Whatever sections are shown, would have been provided accordingly.
Ensure that the sloping portion is rightly carried out to specifications.
For slope exceeding 30 to 45 degrees, special formwork requirement is made.
Ensure that top forms are provided & would not move from its position during pouring.
Ensure that these forms do have square shaped openings at suitable spacing in both
directions of sloping surface forms.
These openings should cover whole area of the slope to avoid any honeycombing or any
voids in the hardened concrete.
Ensure that the sloping form is strong enough to be accessed & working.
Check these openings do allow cleaning & concreting pouring operations easily.
Make sure that vibrator would be applicable easily.
Make sure that slope would be cast monolithic with upper & lower flat concrete.
Make sure that curing would be conveniently effected.
Regards

Check List for RCC Sloping Portion Suspended Slab works Item # 22
Check that all operations would be done as defined within other operations of slabs.
Whatever sections are shown for preparatory works, would have been provided
accordingly.
Ensure that the sloping portion is rightly carried out to specifications.
Ensure that supporting system is well carried out to scaffolding effective fitness.
For slope exceeding 30 to 45 degrees, special formwork requirement is made.
Ensure that top forms are provided & would not move from its position during pouring.
Ensure that the sloping supports are well anchored & if so required, well braced.
Make sure that temporary platforms are available for the sloping portion as well.
Ensure that these forms do have square shaped openings at suitable spacing in both
directions of sloping surface forms.
These openings should cover whole area of the slope to avoid any honeycombing or any
voids in the hardened concrete.
Make sure that required services inserts are duly embedded in the prepared sloping forms.
Ensure that the sloping form is strong enough to be accessed & working.
Check these openings do allow cleaning & concreting pouring operations easily.
Make sure that vibrator would be applicable easily.
Make sure that slope would be cast monolithic with upper & lower flat concrete.
Make sure that curing would be conveniently effected.
Regards

Check List for RCC Heavy Compressor Foundation works Item # 23


May apply to Cracked Gas / Propane / Ethane etc. gas compressors foundation to be
installed within process areas of plants. Dimension of foundation could be 25 m long x 8
to 10 m wide x 2 m deep
Ensure the formation level is achieved by required fill or otherwise.
Ensure that the formation level is duly tested & approved.
Ensure all precaution required for such area for ingress & egress & other safety measures
are adopted.
Ensure blinding is well laid & concrete protection applied accordingly.
Ensure protection of concrete protection mechanism if so required, is applied.
Ensure shop fabricated rebars of course uncoated are received for installation.
Ensure that these cut & bent rebars are rightly tagged.
Check about the on site fabrication of forms smoothly going on for vertical sides.
Ensure whether or not, vacuum test is conducted for the concrete protection membrane
applied.
Should it be propriety form, it should be complied with manufacturer’s drawings.
Check that marking is made on prepared foundations for the location of rebars.
Ensure that delivered rebars are placed properly using required strong chairs of
considerable size rebar say 25 mm.
Ensure that heavy columns or walls if so designed, are well placed intact into the
foundation portion. Mind that these bars are always heavy as well. Sometimes bending of
these rebars is not permitted. It requires special positioning of these rebars.
Since heavy quantity of rebars are required for such foundations, heavy deeper chairs are
required at various locations depending on expected working loads.
Ensure that workers do work safely within space available.
Check fabricated forms are in compliance with the dimensions of the foundation.
Ensure that forms are erected in sequence & well supported.
Ensure sequential panel edges are well secured.
Ensure corner panels are well secured.
Ensure the access to the inside of forms being safe.
Ensure alignment & plumb for the forms.
Ensure inclined supports are fixed to necessary requirement.
Ensure concrete spacers are installed to meet rebars requirement.
Ensure certain bars on top are allowed to be fixed later so that entry is allowed to descend
to the lower bars.
Ensure that the sacrificial anodes are arranged & their interface connections to the
foundation rebars are tied up using the galvanized wires or cables clamped with SS C
clamps,
Ensure that sacrifical anodes to be inserted doen is duly welded.
Inspection of this anode/s has/have to be done by going to the lower reinforcement mesh.
Ensure electrical continuity testis conducted properly on all rebars.
Plan for the pouring method that has to be approved.
Plan for the concrete ordering sequence.
Plan for pouring working hours.
Plan for curing arrangements.
Plan for the workers deployment.
Plan for stepping management of pouring.
Plan for thermal controls.
Plan for working access on to the top area.
Plan for a stand by construction joint formwork or stop arrangement to meet any damn
emergency.
Regards

Check List for RCC Tabletop Columns works Item # 24


Ensure curing for foundation concrete is accomplished.
Ensure construction joint is scabbled properly.
Ensure setting out locations are correct.
Ensure column reinforcement is placed correctly to drawings.
Ensure sacrifical anode are fixed to required height well anchored.
Ensure Tanged GI steel plate inserts are available duly fabricated from workshop.
Check proper holes are available for fixing by fastening to forms using bolts.
Ensure all form sides are fixed with inserts properly & inspected.
Make sure that tangs of plates should be embedded in concrete.
Make sure that all sides of forms are erected after rebar inspections.
Have closure of forms & carry out all column form operations.
Check out concrete pouring levels.
Check form supporting arrangements.
Make sure a temporary platform is available for casting.
Suggested pour in full height if feasible.
Two stages of pour can also be allowed depending on column height limits.
Regards
Check List for RCC Tabletop works Item # 25
Make sure the axis of rotation of the machine.
Ensure grids in both directions are indicated on drawing.
Ensure that shop drawings is produced & approved.
Check whether or not, the table tope is to be produced by one casting.
Certainly, the beams of top are quiet deep & construction joint shall cause practical
problems. Have a discussion with responsible authority in this regard.
According to engineering requirement, one go for pouring is appreciable.
Check that column construction joints are well scabbled.
Check columns are rightly marked with datum levels.
Check formwork is completely erected.
Ensure fitness of formwork preferably by the formwork manufacturer expert.
Check all access scaffolding is installed for ease of working.
Check setting out profiles on the forms of slabs.
Check all deep beams are correctly marked.
Check all block outs are rightly inspected.
Ensure rebars are delivered duly fabricated from workshop or yard.
Ensure that delivered rebars are placed properly.
Keep close watch on works since, the rebars on such works are complicated in design.
Make sure rebar arrangement of placing is rightly followed without causing any
complications.
Check all preparatory works in all respects.
Make sure cathodic protection arrangements are rightly installed.
Make sure that level of top of concrete are seen.
It is significant to note that level should be within tolerable limits as space between the
top of concrete & the machine support bottom shall be required to be epoxy grouted.
All temporary & preparatory works require detailed checking horizontally as well as
vertically.
All locations of defined inserts to be checked accurately.
Plan about method of pouring as pouring requires a good thought out sequence.
Have inspections of all items involved.
Regards

Check List for Below Ground RCC Swimming Pool works Item # 26
Pool size 25 x 13 M say & meant for local competition. Shallow end depth 1M. Deep end
depth 2.5 M. RCC base. RCC walls. Construction Joints. Open surface drains.
Submerged pool lights. Internal tiling on shelf surface. Pool carpet. Changing room.
Pergola.

Structural Items are defined herein.


Base Slab
Check setting out of the pool coordinates & their alignments.
Check working area meant for excavation as well as no clash situation with other
required buildings such as water supply & service area.
Check safety proposals to be installed during excavation.
Check coordinated services drawings duly approved or approve it.
Check internal tiling location setting out in the isometric view probably.
Check location of open drains around pool for overflowing water.
Check process plant room drawings & locations.
Check all coordination for all such minor structures for services meeting purpose.
Check all details duly coordinated with the balance tank monolithic with the shelf.
Check balance tank drawings are ready & coordinate these with other drawings.
Make sure slope portion between the shallow & deep end is done rightly.
Make sure that all forms & rebar fabricated are available or are being fabricated
according to given details.
Check that excavations being progressed in line with the setting out & under constant
check for alignment as well as levels.
Check formation is reached & prepared to requirement.
Make sure blinding works are done to requirement.
Make sure concrete protection is carried out to specifications.
Make sure that water bars are available for the CJ for both vertical & horizontal locations.
Make sure that these joints are correctly welded by the required tool to suit site
dimensions.
Check if any underground services if so required, under compelling situation otherwise,
not preferred as such.
Check all raft rebars to be true to design requirements.
Check all side forms are erected rightly.
Make sure slope portion between the shallow & deep end is done rightly.
Check welded piece of PVC CJ ring is available & fixed correctly being kept half in the
raft & half in the walls portion.
Check for electrical first fix conduits are inserted to shop drawings within the raft work.
Plan for raft pouring in one go.
Check for CJ are correctly produced rough during concrete pour.
Walls
Proceed for curing of base slab as well as for wall forms erection.
Check that walls are carried out in alternate bays of CJ.
Check for walls reinforcement being done correctly.
Check for all services first fix are inserted for walls.
Check vertical CJ bars are inserted correctly.
Check all walls are closed by forms after inspections.
Check that bolts & supports would not slacken during pour.
Check working platform are ready & erected.
Check pour being done rightly.
Check all walls are completed.
Check curing procedures are complied with.
Balance Tank
Make sure base slab, walls & roof of balance tank are carried out according to drawings
with all inserts placed in.
All repetitive operations’ checks are required as defined on other check lists.
Regards

Check List for Firing or Shooting Range works Item # 27


300 M long, 25 M wide Range.
Components
Main building. RCC Framed structure.
Indoor Pistol Range. RCC Framed structure.
Outdoor Shooting Range. RCC Framed structure.
Bullet Trap Chamber. RCC Framed structure.
Target Pits every 100 M.. RCC Framed structure.
Underground passages Pits every 100 M. RCC Framed structure.
Baffle walls. RCC ordinary thick walls 6 to 4 m high.
Gantries supported on PTFE bearing mounted on Corbels.. Structural Steel armoured
plate with water proof board covering.
Sand Trap.

Refer to attached sketches about Firing Range.


Components defined above
Special structures are:
Bullet Trap Chamber. RCC Framed structure.
Target Pits every 100 M.. RCC Framed structure.
Underground passages Pits every 100 M. RCC Framed structure.
Baffle walls. RCC ordinary thick walls 6 to 4 m high.
Gantries supported on PTFE bearing mounted on Corbels.. Structural Steel armoured
plate with water proof board covering.
Regards

Check List for Foundation / Footings Concrete Pour


Item # 6 previous (preparatory Works) / # 28 this (Concrete Pour)
Plan adequate number of foundations in one go to meet RMC delivery requirement.
Book concrete in advance to facilitate RMC supplier to chart out RMC plans schedule.
Book concrete pump of required boom length.
Have site appraised by RMC representative for assessment of timings.
Footings pouring is fast activity which point has to be considered.
Prepare pouring platforms wherever required.
Ensure pouring inspection is over & ITP is signed off.
Concrete temperature should not exceed 32 deg celcius.
In hot weather plan for concrete pouring either in early morning hours or late evening or
at night hours.
Make sure that supporting arrangements should not disturb during pour.
Make sure vibrator & standby vibrators are available.
Make sure Masons tools are available.
Make sure adequate number of carpenters & steel fixers are in attendance for meeting
certain low profile emergency.
Make sure all arrangements regarding curing are available.
Make sure concrete testing equipments are available either directly or by laboratory.
Make sure that these equipment include slump cone, cube moulds, thermometers, air
voids measuring instrument,
Make sure that a qualified technician is available to test & record all observations.
Make sure RMC delivery timings are correctly recorded.
Make sure that no RMC truck starts pouring delivery at site without clearance from
testing position is given.
Make sure that trained group or gang to receive pumped concrete is available at location
of concrete.
Prior to commence with pouring, have vibrator checked for operations.
Make sure that location is cleaned well prior to pouring commences with.
Check that concrete location is watered well to avoid flash setting.
Receive RMC truck after testing clearance & start pouring from the pump station.
Footings can be poured in one go should the depth not exceed 400 to 450 mm.
Footings can be continuous in case beams are cast monolithic.
Make sure that no started bars are displaced during pouring.
Make sure that concrete occupies all space around rebars & the forms.
Immediately, after the top of concrete is leveled & say half an hour is over, curing
compound could be sprayed depending on the site situation & the weather temperature.
No gap should be allowed during pouring for a better pour quality.
It is a common practice not to order last truck since exact quantity of mix is not known.
Therefore, hold the last truck to replace its order after major pour is over.
Make sure that construction joint is correctly formed by roughening or scabbling.
Testing technician must collect cube samples & record all testing observations.
Apply Hessian or gunny rolls & polythene sheets over the unformed surfaces & cure with
water all times for at least 7 to 10 days depending on weather temperature.
Make sure that curing arrangement is not thrown away by fast winds.
Hardened concrete should not be allowed to dry any time till curing is over.
Side forms can be removed after 24 hours to 36 hours.
Regards

Check List for Stub Columns Concrete Pour.


Item # 7 previous (preparatory Works) / # 29 this (Concrete Pour)
Plan adequate number of stubs to be poured in one go to meet RMC delivery
requirement.
Book concrete in advance to facilitate RMC supplier to chart out RMC plans schedule.
Factually, it would be inconvenient for RMC supply too small quantity.
Book concrete pump of required boom length in case, stubs pour is required by pump but,
stubs may also be done using pumpless pour.
Check that stubs are not more than 2 M high in general.
Check that site provided means are feasible for pouring RMC.
Check if site pour means are utilized, RMC should not be delayed excessively during
pouring.
Check that all stubs planned for pouring are safely accessible for pour gang.
Make sure Masons tools are available.
Make sure adequate number of carpenters & steel fixers are in attendance for meeting
certain low profile emergency.
In case of concrete pump being used, make sure that only required quantity of mix is
poured into stub to prevent concrete from dropping around stub preparatory works.
Ensure vibrator is applied rightly into stub portion without touching reinforcing bars or
forms. In case, vibrator touches forms, chances of form opening are not acceptable.
Check all curing materials required for stubs are available on site including curing
compound.
While concrete truck arrives, collect the sample for slump, air voids etc.
Check loading & delivery times & also check RMC dockets.
Allow truck to move in to location station for delivery.
Check site prepared open chutes are available in case of pumpless concrete so that
concrete can be easily transported to the stubs.
In certain cases, steel wheel barrows can also be used for transporting concrete from
truck. Small buckets can also be used for collection of concrete & pouring into stubs.
Mobile or tower crane can also be used for pouring stubs, if available.
Make sure that stub is concreted in layers not exceeding 400 to 500 mm deep.
Make sure that vibrator is efficiently used after the layer pouring.
Make sure that after pouring the stubs, to their marked top level, top is covered with
polythene or Hessian as convenient.
Make sure that no supports are slackened during pouring.
While using pumpless pour, there are remote chances of forms opening but with pump,
chances are more.
Makw sure that foreman or chargehand type supervisors do not allow water to be added
to concrete during pouring. It often happens that during long pour & concrete truck
getting delayed, concrete stuff is stiffened causing hardship to workers. To svoid that,
they tend to add water to mix which is not acceptable in any case.
Start curing after few hours depending on the temperature but sides of forms externally
can be kept cold by spraying water.
Side forms can be removed after 24 hours to 36 hours. But it takes time while opening the
forms due to many reasons.
Regards

Check List for grade slab (floating slab @ plinth level) Concrete Pour.
Item # 9 previous (preparatory Works) / # 30 this (Concrete Pour)
Ensure that preparatory works have been approved & ITP signed off.
Plan for one go pouring operation.
Ensure that RMC delivery order is in place.
Ensure that RMC manager is instructed about grade slab pour being fast.
Ensure what type of concrete pump is required to cover whole pour area.
Make sure that a single pump is adequate or there may be needed more than one pump.
Have batching plant manager inspect site for assessment.
Decide frequency of supplies & pouring hours.
Decide workforce requirement strength for pouring period.
Make sure all other concrete pour requirements are available.
Make sure that access to concrete pump & trucks is clear.
QA engineer is required to care about testing of concrete.
Preferably, pour hours should match concrete temperature extremes.
In case, pour duration is long hours, rest pause to workers may be required which
necessitates standby teams.
Safety arrangements are to be looked into as well. Safety engineer should care about.
Check in case trucks have to arrive at a frequent interval of 10 to 15 minutes while one
truck carries say 8 to 10 cum concrete.
Workforce shall be required accordingly.
Surface finish shall also be required depending on the class of surface finish.
Check whether or not, power floating is demanded for thin tiling works.
In case, it is required, further post pour long hours shall be required for operating power
float.
Have the pour started & implement all checks.
Curing should be commenced with immediately after area is ready for that.
Curing compound should be sprayed immediately after or even during pouring is in
progress in case of unpleasant temperatures.
Cover surface with polythene sheet over curing compound temporarily.
After many hours, remove polythene sheet & cover with Hessian cloth watered &
recovered with polythene sheet.
Process of curing to continue for specified number of days.
Make sure that set concrete surface is ready to be applied with power float or demanded
manual finish whatever be the case.
Regards

Check List for RCC Columns Concrete Pour


Item # 10 previous (preparatory Works) / # 31 this (Concrete Pour)
Ensure that adequate number of columns are ready for pouring.
Make sure that all columns preparatory works are clear of all dust & dirt & well watered.
All nails, loose binding wires etc should be taken out.
Quantity of RMC should be enough for placing an order though tentative booking might
have been done in past but confirmation is required now.
Required boom length pump must be ordered.
Ensure that preparatory works have been approved & ITP signed off.
Make sure access working platform is ready to safety satisfaction duly tagged at all risky
droppable height areas.
Make sure that all supports are in place & all clamps & bolts are intact.
Make sure attendance of steel fixer & carpenters for responding during emergency of
sides opening or some other requirement.
Make sure competent pouring gang is deployed for required duration.
Make sure that vibrators are available & in working condition.
Make sure that standby vibrator too works in accordance to requirement.
Make sure all curing arrangement are in tact for immediate application.
Make sure that concrete pump & first transit truck mixer arrives as advised to plant.
Make sure that additional reducing size outlet of boom is attached if so required keeping
in view depth of pour & size of column section.
Arrange Quality assurance engineer for testing purpose.
Concrete has to be cleared after initial site tests are completed.
Ensure weather & concrete temperatures before allowing truck to stationed pump.
Make sure vibrator reaches to the lowest layer of concrete.
Make sure that layers are not poured at one time more than 400 to 500mm deep.
Make sure that vibrator needle does not touch formwork.
Make sure vibrator needle does not touch rebars.
Make sure that all columns are poured one after another only in layer.
It is advised that in no case, one time height should exceed one metre for preventing form
sides bulging.
Possibility is that concrete shall fall out of column forms & must be removed
immediately from ground.
Hammers can be used to tap the forms from exterior surfaces to ensure that all areas of
forms have received concrete to avoid any voids.
Concrete gang should be kept on rotating from one location of column to other location.
After completion of all pours, site should be clear of all debris & wet Hessian should be
kept on top of columns.
Form sides in case of high temperatures, should be kept wet by spraying water on exterior
surfaces.
Forms should not be removed from columns before 24 to 36 hours depending om the
weather temperature.
If there is no requirement of immediate reuse, form striking may be delayed. This
requires, keeping exterior surfaces wet with water spraying.
Immediately after, striking forms, urgent inspection has to be done for any defects & for
resorting to non compliance reporting as well as recommendation of remedial actions.
Curing has to be effectively continued first by applying curing compound of the wet RCC
surface using either water based compound or wax based compound as approved on
project.
Complete duration of curing has to be complied without either any slackening or
compromise.
Water curing can also be done on columns which shall be more effective & in fact cent
percent effective if carried out intensively though, quantity of water consumed shall be
considerable.
Curing compound based curing is effective only between 50 to 70 % depending on type
of curing compound.
Regards

Check List for RCC Walls Concrete Pour


Item # 11 previous (preparatory Works) / # 32 this (Concrete Pour)
Make sure that wall works have been approved for pouring.
Check whether walls are to be poured whether by pump or by crane tower or else.
Since walls are not many in any building, pour quantity may be limited.
Check all working platforms are safe which may be installed from either side of walls.
Make sure that preparatory forms are cleaned properly leaving no unrequired dirt within.
Ensure that plenty of free access is available to reach either the concrete bucket chute or
pump boom to the level of first drop of concrete.
In certain cases of thin walls elements, reducer shall be attached to the end of initial
original pump boom.
Check all concrete pouring inventories as explained on other previous lists.
Make sure watering in to wall works as well as supports being intact.
Ensure availability of carpenters & steel fixers.
Check that plumbs & the wall line are in position to monitor any setting out alignment.
Receive concrete as usual checked through quality engineer for all site tests.
After approval, allow concrete to wall location.
Pour whole first layer in all walls & apply vibrator correctly so that concrete reaches all
corners & edges of first layer.
Pour other layers as usual in sequence gradually.
It would take hours for pouring a single wall.
Reach concrete to top of concrete marked line & give required roughness or demanded
finish.
Apply first instant curing on top by covering with polythene membrane or wet Hessian
cloth.
Make sure there is no opening of forms or bulging during concrete & if so observed, try
to reinstate back to true position using props or other supports.
Check that forms are not removed prior to at least 48 hours are lapsed.
Apply water on the forms exterior & on top for curing purpose after few hours of
concrete is over.
Clear all debris from around the wall areas of vicinity.
Regards

Check List for RCC Lift Well Walls Concrete Pour


Item # 12 previous (preparatory Works) / # 33 this (Concrete Pour)
Make sure that wall works have been approved for pouring.
Check all working platforms on both sides of lift well are safe which may be installed
from either side of walls.
Make sure access working platform is ready to safety engineer’s satisfaction duly tagged
at all risky droppable height areas.
Ensure that preparatory works have been approved & ITP signed off.
Make sure watering in to wall works as well as supports being intact.
Ensure availability of carpenters & steel fixers to control any displacement if preparatory
works.
Check that plumbs & the wall line are in position to monitor any setting out alignment
Make sure that all supports are in place & all clamps & bolts are intact.
Make sure attendance of steel fixer & carpenters for responding during emergency of
sides opening or some other requirement.
Make sure competent pouring gang is deployed for required duration.
Make sure that vibrators are available & in working condition.
Make sure that standby vibrator too, works in accordance to requirement.
Make sure all curing arrangements are intact for immediate application.
Make sure that concrete pump & first transit truck mixer arrives as advised to plant.
Make sure that additional reducing size outlet of boom is attached if so required, keeping
in view depth of pour & size of column section.
Arrange Quality assurance engineer for testing purpose.
Concrete has to be cleared after initial site tests are completed.
Ensure weather & concrete temperatures before allowing truck to stationed pump.
Make sure vibrator reaches to the lowest layer of concrete.
Make sure that layers are not poured at one time more than 400 to 500mm deep.
Make sure that vibrator needle does not touch formwork.
Make sure vibrator needle does not touch rebars.
Explain to concrete supervisor that pouring has to be started in such a way that corners
are poured first to have concrete move in all directions uniformly to certain extent.
Make sure that concrete layers are formed around the lift well forms & due care taken for
door position formwork.
Pump boom has to keep on moving around the preparatory works to allow uniform pour.
All layers have to be vibrated thoroughly gradually & concrete has to be kept on pouring
till 1 m height / depth is poured around.
Make sure that at least half an hour gap is allowed to the pour so that poured concrete sets
to certain extent but does not form cold joints.
Pour other layers till 2 m height / depth is completed & allow say another half an hour for
resting.
Continue whole height following specified sequences & start curing initially as explained
previously.
Make sure that top of concrete wall is roughened for making construction joint.
All walls outside forms have to be kept wet & top covered with polythene or wet
Hessian.
Check external forms as well as internal forms by strong hammer impact to find in case
some voids do exist during application of vibrator.
Make sure that repetition of forms would not be required soon which means that there
would be no earliest requirement to strike forms in specified duration.
In case of such non early requirement of striking, do not allow removal of forms after 48
hours but keep curing intact from top as well as from outside.
Allow removal of forms when it is to be repeated for higher level.
During monitoring of forms, make sure that lines do not go out of tolerance limits & if so
try to reinstate by tightening the supports.
After striking forms, make sure that defects are identified for raising non compliance
report & recommendation of remedial actions to close NCR.
Regards

Check List for RCC Longitudinal Stair Concrete Pour


Item # 13 previous (preparatory Works) / # 34 this (Concrete Pour)
Check whether single flight or complete flights have to be poured.
Make sure that stair flight works have been approved for pouring.
Single flight pour requires one portion along with landing to be poured.
Make sure all supports are intact below forms.
Make sure all rebars are intact & steps forms are correctly fixed & connected.
Make sure that all cleaning has been effected.
Make sure that inspection has been made & ITP signed off.
Make sure that side edge supports are well anchored.
In case complete stair flights have to be poured, make sure all supports & steps forms are
intact & well anchors.
All rebars are in correct positions. While walking on steps risers’ forms, these should not
twist in either direction.
Make sure that cleaning has been completed.
Make sure that pump or crane has been positioned rightly to cover the stair reach.
Quantity of concrete in stairs is not considerable one & it is slow in pouring.
Generally, upper flight is planned to be poured with the floor slab.
Make sure that all concrete tools are available in working order.
Make sure that curing arrangements are available on location.
Make sure that concrete starts being poured from lowest step area & continued to ascent
towards landing portion.
Vibrator is required to be applied at all steps location.
Portion of waist slab & steps sections have to be cast monolithic & accordingly, vibrator
is to be applied.
In case of single waist pour, a stop end has to be fixed at the possible lower level of upper
flight.
Landing has to be poured as small slab alongwith its downstand or upstand beam as case
may be.
Finish on vibrated surfaces have to be applied in such a fashion that a rough surface is
available to receive floor finishes.
Immediately after pouring is over, curing has to commence with.
For case of complete pouring with slab, work of pouring has to continue as explained.
Stair forms shall be in position until, all forms of slabs are opened with exception of
vertical sides of waist slabs.
Curing shall be an important activity as it is difficult to stagnate the water on steps.
Continuous water curing shall be required even after spraying curing compound.
Regards

Check List for RCC Suspended Slabs Concrete Pour


Item # 14 previous (Preparatory Works) / # 35 this (Concrete Pour)
Check that all preparatory works have been inspected in all respects.
Check that all temporary works have been inspected to meet safety requirements.
Check that supporting system of centering & shuttering has been inspected by probably
Third party if so required within contract.
Check that batching plant has been ordered for supplying RMC.
Make sure that correct quantity of RMC is ordered.
Make sure that pour plan has been finalized in method statement & plan details provided
to RMC supplier.
Make sure that type of pumping equipment required is well known to the RMC plant
manager.
Make sure all supervising personnel are available when concrete is delivered.
Make sure gang strength for concreting is available on site.
Concrete timings should match those hours when the temperature of weather as well as of
concrete shall be within limits.
RMC should supply concrete having defined temperature.
Concrete should be supplied with agreed frequency of transit truck mixers arrival.
A place should be selected for washing the trucks after empting so that environment is
not badly affected.
All equipment & tools to be used for concreting must be checked for their operations.
Vibrators & standby must be checked to be in order.
All curing arrangements should be made available on site to initiate timely curing.
For major slabs, construction joints must be prepared in advance & also stop ends for
emergency should be prepared to avoid any fabrication rush during odd hours.
Carpenters as well as steel fixers must be available on & below slabs.
Electricians should be available to check conduits displacements.
In case of additional disciplinary inserts, relevant technicians must also be available.
Positioning of pump locations should be clear of all obstructions.
Positioning of trucks should also be clear similarly.
Adequate electrical supply arrangements must be kept intact throughout.
In case of adverse weather, it may also be required to shade placing area but, it is not a
common practice.
All on site tests must be conducted before receiving concrete trucks leave test location for
reaching pump location for delivery.
Quality engineer has to conduct all on site tests & collect cube samples.
All defective trucks would be sent back after rejection but, it rarely happens.
Since, pouring slab is a fast activity, intense supervision & controls are required to be
affected in all respects.
Some sort of medical arrangement could be made to meet any accidental contingency.
Drinking waters or cold liquids for consumption must be made available on location for
the gang to drink to avoid dehydration or sun stroke.
For food time or tea time, a few minutes break would require standby replacement that
must be made available on site.
For workers passive moments, replacement should be made available.
Beams have to be poured first but not full.
Concrete should not be poured into the beams directly but received on the slab edges to
avoid impact on beams side forms to avoid opening or dislocation of forms.
Concreting should start from one end & go on completing after first stage beams are
completed.
Second stage should give concrete its level in right profile.
If temperature is high, immediate protection of surface has to be taken.
In case of two pumps or three pumps are installed, concrete can be started from as many
locations as are number of pumps available but, no cold joints are allowed.
Concrete pour plan should provide all details & site supervisor must be handed &
explained plan in details so that communication is made to all present on pour location.
Carpenters available must keep a watch from below that no support should yield or any
concrete comes out from forms or there is some other problem.
Similarly, steel fixers have to check that no bars are dislocated & if so, immediate
reinstatement of bar should be done.
In case of application is required by power float, it has to be made sure that concrete is
hard enough before applying power float.
In case, immediate cracks are seen, must be filled with cement & sand in the form of
grouting on the wet concrete.
Cover surface with polythene sheet or spray curing compound immediately.
Check that last truck does not reach immediately after last but one reaches but, wait till
all previous concrete is consumed. Make sure that whole truck quantity shall be
consumed. In case, there is small quantity requirement, order that much quantity only for
the last dispatch from RMC plant.
Procedural curing shall follow later as defined in method statement.
All rubbish should be removed from location & all concrete spill over upper rebars in
columns should be cleaned.
Concrete shall be leveled to fixed top profile & ensure that level of poured concrete is
fine & not above the fixed lines.
Do not allow any worker or person to walk on the finished surface until concrete sets
properly.
Regrds

Check List for RCC Pedestal Footings Concrete Pour


Item # 15 previous (Preparatory Works) / # 36 this (Concrete Pour)
Used term pedestal for approximate cubical size of footing.
Ensure that a number of foundations have been approved for pouring.
Ensure concreting arrangements have been agreed with RMC plant manager.
Ensure acceptable temperature hours which may be either in early morning hours or night
hours.
Ensure access to the site for truck & pump is available.
Ensure block out pockets forms & anchorage for anchor bolts are intact.
Ensure all anchor bolts templates are in right locations when no block outs are allowed.
Ensure curing arrangement for immediate & post pour dealing.
Ensure concrete top level marks are rightly fixed by surveyor & clearly visible to
responsible masons.
Quality engineer must be available for quality control procedures.
Low slump is expected for such footing concrete.
Get delivery following all procedures.
Do not pour concrete in one go but, restrict layer to 450 mm.
Cold joints have to be avoided during pouring.
Keep eyes on sides of form & control in case sides try to open.
Vibrator should be applied adequately wherever concrete pouring is rotated.
After reaching top of concrete level, immediately cover with polythene sheet or spray
curing compound when finishing of surface of concrete is accomplished.
Keep side form also wet from external arrangements in hot hours.
Clear out all drop outs of concrete form surroundings as well as from top.

Regards,

Check List for RCC Footings Blocks For Concrete Pour Item # 16
Item # 16 previous (Preparatory Works) / # 37 this (Concrete Pour)

For footings of long span steel frames.


In plan it s rectangular shape with considerable depth block
Ensure that a number of foundations have been approved for pouring.
Ensure that right grade & type of mix is ordered since generally, these footings are thick
members & need low shrinkage concrete.
Ensure concreting arrangements have been agreed with RMC plant manager.
Ensure acceptable temperature hours which may be either in early morning hours or late
night hours.
Ensure access to the site for truck & pump is available.
Ensure block out pockets forms & anchorage for anchor bolts are intact.
Ensure all anchor bolts templates are in right locations when no block outs are allowed.
Ensure curing arrangement for immediate & post pour dealing.
Ensure concrete top level marks are rightly fixed by surveyor & clearly visible to
responsible masons.
Make sure pourable foundation space is clean from all dirt, dirt & debris.
Quality engineer must be available for quality control procedures.
Low slump is expected for such footing concrete.
Get RMC truck delivery following all QC procedures.
Do not pour footing concrete in one go but, restrict layer to 450 mm.
Cold joints have to be avoided during pouring.
Keep eyes on sides of forms & control, in case sides tend to open.
Vibrator should be applied adequately wherever concrete pouring is rotated.
After reaching top of concrete level, immediately cover with polythene sheet or spray
curing compound when finishing of surface of concrete is accomplished.
Finishing of concrete should be done using demanded finish tool.
Keep side forms also wet from external arrangements in hot hours.
Clear out all drop outs of concrete form surroundings as well as from top.
Make sure curing procedures are followed as defined on method statements.
Regards,

Check List for RCC For DC Generator & Alternator Concrete Pour
Item # 17 previous (Preparatory Works) / # 38 this (Concrete Pour)
Components Involved are raft, alternator foundation in thick column form, isolation
between generator foundation & raft & generator foundation on isolation on raft.
Pouring concrete & suring activities for defined period.
Generator foundation
Activity of pouring & curing
This pour of being a massive concrete block.
Make sure that a coordinated instruction has been issued to RMC plant.
Make sure that plant operator knows type of mix & its grade.
Make sure that temperature range is known to the plant operator / manager.
Make sure that all arrangements for the workers access are well secured.
Make sure required water is available on site.
All concrete pouring list requirements are available.
Make sure quality engineer’s availability.
This pour could require a concrete temperature range from 20 deg C to 24 deg C for
which chilled water may be required to be used for concrete mixing.
Make sure the all preparatory works are clean & ready to receive concrete that would be
carried out in line to agree method statement of specific pouring & not general.
Depth of body could be between 1.5 m to 2 m that require stepping arrangement for
layered pour. Stepping means pouring concrete in stepping sequence only & no
formwork in steps as such.
Concrete pour to start from one corner moving to other corner of the strip & then other
step in sequence.
All strips would be vibrated properly.
Make sure that block out pockets for grooves are not disturbed during pouring &
vibration.
Between steps or layers, no cold joints would be permitted.
Top surface exposed to be finished using wooden float or could be specified as power
float. Generally, it is specified as good finish to receive epoxy grouting layer later.
Curing has to be care with due care since, in updated specifications, thermal curing could
be specified that may not required any water flooring or spraying.
Surrounding of the massive block has to be maintained within specified temperature
range so that no thermal; transfer can occur through formwork.
Thermal curing has been specified in other posts.

Alternator foundation Concrete Pour.


Follow all operations as are required for a column with addition of provision of pockets
for block outs. This column is monolithically connected to the combined raft for
equipment.
Height of this column could be somewhat 3.5 m or more.
Since, size of this foundation may also be more than 800 mm, it would be considered as a
thick element & worked accordingly for casting as well as for curing.
Care would be exercise to make sure that construction joint with theraft is properly
produced without causing any voids or honeycombing.
Concrete shall be poured maintaining temperature no more than 24 deg C.
Concrete shall be poured in layers not exceeding 450 mm deep duly vibrated.
Make sure that block out pockets for grooves are not disturbed during pouring &
vibration.
Between steps or layers, no cold joints would be permitted.
Top surface exposed to be finished using wooden float or could be specified as power
float. Generally, it is specified as good finish to receive epoxy grouting layer later.
Curing has to be care with due care since, in updated specifications, thermal curing could
be specified that may not required any water flooring or spraying.
Surrounding of the massive block has to be maintained within specified temperature
range so that no thermal; transfer can occur through formwork.
Thermal curing has been specified in other posts
Regards,

Check List for RCC Fair Face Concrete Pour


Item # 18 previous (Preparatory Works) / # 39 this (Concrete Pour)

Fairface does not require any plastering on the formed surfaces.


Checks for all items should be made for various vertical members as described earlier.
Ensure that the plumb does not exceed out of line by 1 mm in 1000 mm.
No opening of sides is allowed in fair face forms.
No unrequired joints are allowed.
Make sure all supports are well anchored.
Make proper concreting pouring arrangements.
During concreting, no voids or honeycombing are acceptable.
Make proper pouring plan for wall as fair face is generally applicable to vertical members
including elevation columns.
No opening of sides or bulging would be permitted.
No voids would be accepted.
No honeycombing would be accepted.
Texture of concrete surface preferably should be uniform.
Concrete would be poured in layers of uniform thickness allowing no seen curves on
surface.
Concrete should be of pourable consistency using plasticizer.
Better if self leveling concrete is applicable & allowed.
Over vibration has to be avoided.
Drop height of pump has to be maintained.
High level of supervision is required.
Pouring gang has to be trained for such type of elevation structural works.
During preparatory works of form, oil must be applied on ply to strike it easily.
Curing has to follow as specified for defined duration.
During pouring lines & plumbs have to be kept on monitoring constantly & any minor
bulging seen should be corrected immediately.
Regards

Check List for RCC Architectural Finish works Item # 19


Item # 19 previous (Preparatory Works) / # 40 this (Concrete Pour)
Architectural finish means a selected texture to be embossed on concrete vertical surface.
No unrequired joints are allowed.
Make sure all supports are well anchored.
Make proper concreting pouring arrangements.
During concreting, no voids or honeycombing are acceptable.
Make proper pouring plan for wall as fexture face is generally applicable to vertical
members.
No opening of sides or bulging would be permitted. Actually, when thick timber planks
are used, chances of bulging are not common but exempting certain negligence.
No voids would be accepted.
No honeycombing would be accepted.
Texture of concrete surface preferably should be uniform. Even after texture finish,
concrete cover must be as defined.
Concrete would be poured in layers of uniform thickness allowing no seen curves on
surface.
Concrete should be of pourable consistency using plasticizer.
Better, if self leveling concrete is applicable & allowed.
Over vibration has to be avoided.
Drop height of pump pipe chute has to be maintained.
High level of supervision is required.
Pouring gang has to be trained for such type of textural structural works.
During preparatory works of form, oil must be applied on ply to strike it easily.
Curing has to follow as specified for defined duration.
During pouring lines & plumbs have to be kept on monitoring constantly & any minor
bulging seen should be corrected immediately.
Regards
.
Check List for RCC Hourdy Slab Concrete Pour
Item # 20 previous (Preparatory Works) / # 41 this (Concrete Pour)
Hourdy precast concrete trapezoidal blocks are used at low spacing.
Check all services embeds that run through the beams as well as through the Hourdy
block void cavities. Hourdy special blocks would be required to have fixing compatibility
allowing services inserts to pass through.
It is to be noted that slab is too thin say about 60 mm & therefore, services embeds may
not find any room through or within slab portion.
A bigger area of hourdy slab should be planned to pour since thickness is relatively
lesser.
Make sure all top levels are well earmarked & all concrete spacers in positions.
Make sure rebar touch up paint is continuously applied for epoxy coated bars if so
provided.
Make sure whole portion to receive concrete is clean.
Make sure no dirt is seen in the beams between hourdy.
Make sure damaged blocks are replaced well.
Make sure again formwork supporting system is intact.
Order concrete using pump & check all arrangements for pouring are available.
Plant operator should be instructed correctly about requirements.
Make ready available concrete curing arrangement.
Make sure for MS concrete, excellent vibration shall be applied & in certain cases, setting
time would start delayed by many hours.
Receive concrete after site testing & start from one corner of beams & suggested is that
pour beams first & follow think slab.
Use wooden / timber float to finish the unformed surfaces.
Adopt curing procedures immediately after finishing depending on weather conditions
Regards

Check List for RCC Sloping Portion Floor Concrete Pour Item # 21
Item # 21 previous (Preparatory Works) / # 42 this (Concrete Pour)
Check that all operations have been done as defined within other operations of grade
slabs.
Ensure that cleaning has been done to requirement.
Ensure curing arrangements being intact.
Ensure that concrete pour to be laid from low end to up end.
Generally, slope concrete quantity is not much in comparison to other elements.
Concrete may be done slowly in comparison to unformed surfaces concrete.
Make sure that after the concrete is poured & compacted, the opening is closed as
required & hollow soundness does not occur when tested by tamping hammer.
Practically, slope concrete is cast monolithic with the lower & higher slab concrete that
does not necessitate making of construction joints.

Regards

Check List for RCC Sloping Portion Suspended Slab Concrete Pour
Item # 22
Item # 22 previous (Preparatory Works) / # 43 this (Concrete Pour)
Ensure that supporting system is well carried out to scaffolding effective fitness.
For slope exceeding 30 to 45 degrees, special formwork requirement is made.
Ensure that the sloping supports are well anchored & if so required, well braced.
Make sure again that temporary platforms are available for the sloping portion as well.
Ensure again that these forms do have square shaped openings at suitable spacing in both
directions of sloping surface forms.
These openings should cover whole area of the slope to avoid any honeycombing or any
voids in the hardened concrete.
Make sure plugs to cover these openings are available prior to commence with pouring.
Make sure again that required services inserts are duly embedded in the prepared sloping
forms.
Ensure that the sloping form is strong enough to be accessed & working.
Check these openings do allow cleaning & concreting pouring operations easily.
Make sure that vibrator would be applicable easily.
Make sure that slope would be cast monolithic with upper & lower flat concrete.
Make sure that curing arrangements are ready.
Make sure adequate number of carpenters are available below the slab forms to check
about any yielding supporting system &b to correct in case it miss happens.
Apply good cleaning & to remove out all rubbish or dirt.
Plug all dust holes before watering in.
Water in all volume of proposed concrete to maintain temperature so that, flash setting is
avoided.
Receive concrete following all standard QA procedures & pour,
Cure accordingly in line with approved method statements.
Regards

Check List for RCC Heavy Compressor Concrete Pour Item # 23


Item # 23 previous (Preparatory Works) / # 44 this (Concrete Pour)
May apply to Cracked Gas / Propane / Ethane etc. gas compressors foundation to be
installed within process areas of plants. Dimension of foundation could be 25 m long x 8
to 10 m wide x 2 m deep or as sketch attached.

Ensure again that all precaution required for such area for ingress & egress & other safety
measures are adopted.
Ensure again that heavy columns or walls if so designed, are well placed intact into the
foundation portion. Mind that these bars are always heavy as well. Sometimes bending of
these rebars is not permitted. It requires special positioning of these rebars.
Ensure that workers do work safely within space available.
Ensure again that forms are erected in sequence & well supported.
Ensure sequential panel edges are well secured.
Ensure corner panels are well secured.
Ensure the access to the inside of forms being safe.
Ensure alignment & plumb for the forms.
Ensure inclined supports are fixed to necessary requirement.
Ensure concrete spacers are installed to meet rebars requirement.
Ensure certain bars on top are allowed to be fixed later so that entry is allowed to descend
to the lower bars.
Ensure that the sacrificial anodes are arranged & their interface connections to the
foundation rebars are tied up using the galvanized wires or cables clamped with SS C
clamps,
Check Plan for the pouring method that has to be approved.
Check Plan for the concrete ordering sequence.
Check Plan for pouring working hours.
Check Plan for curing arrangements.
Check Plan for the workers deployment.
Check Plan for stepping management of pouring.
Check Plan for thermal controls.
Check Plan for working access on to the top area.
Check Plan for a stand by construction joint formwork or stop arrangement to meet any
damn emergency.
Concrete has to be poured in exact practical sequence as planned without producing cold
joints.
Curing is of utmost importance & therefore, requires intelligent & efficient attention.
Only specialized concrete pouring gang must be utilized in such massive concrete pour.
Pouring would be faster & probably one truck load of concrete would be vacated in 5 to
10 minutes therefore, all arrangements require good management.
Follow temperatures as specified that is not more than 24 degree C.
Ice could be used.
Differential thermometers could be used for recording thermal gradient.
Regards

Check List for RCC Tabletop Concrete Pour Item # 24


Item # 24 previous (Preparatory Works) / # 45 this (Concrete Pour)
Check out concrete pouring levels to the requirement.
Check form supporting arrangements be intact.
Make sure a temporary platform is available for casting.
Suggested pour in full height if feasible.
Two stages of pour can also be allowed depending on column height limits.
Since generally, such members are in category of thick members or even massive
members, relevant concrete should be ordered.
Temperature of concrete should be between range of 24 to 30 degrees C.
Concrete shall be placed in layers & in rotations without allowing cold joints formation.
During concreting, plumb values shall be monitored.
Application of vibration must be applied rightly so that no voids are formed in concrete.
All arrangements must be ready for immediate & post pouring curing.
Curing could be applied from external forms by spraying water until the forms are in
place.
Regards

Check List for RCC Tabletop Slab Concrete Pour Item # 25


Item # 25 previous (Preparatory Works) / # 46 this (Concrete Pour)
It is an elevated pour depending on the height of the equipment to be mounted though it
is named as foundation.
All supporting systems must be perfectly checked for heavy element.
CJ on the previous concrete pour of columns must be properly scabbled.
Flash setting must be avoided by spraying water prior to pouring.
It is a massive block of concrete that is quiet wide, deep & thick.
It contains many block outs & other openings.
It is not easy to be accessible to all parts of area within concrete pour.
Rebars are also provided in many layers that require higher degree of pouring supervision
so that concrete is vibrated correctly.
Adequate access to all areas of pour is made sure.
It is suggested to pour the whole concrete in one unit. It is commented that one design
showed the table top to be poured in two units with deep construction joint in the middle
that was objected by me & later the whole unit of concrete was poured in one go. It was
too tedious to formulate the CJ in the middle due to continuous rebars in many layers.
Make sure all arrangements required for workers standing & working.
Make sure all areas are well guarded.
Make sure all ladders are tagged as safe.
Make sure that curing arrangements are made in advance.
All arrangements must be ready for immediate & post pouring curing.
Curing could be applied from external forms by spraying water until the forms are in
place.
Make sure that the site engineer or foreman understands the concrete pour plan without
any ambiguity.
Check station locations of pumps & delivery locations of transit mixers.
Temperature of concrete should be between range of 24 degrees C.
During concreting, plumb values shall be monitored.
Concrete has to be poured in steps not exceeding 450 mm thick while concreting to be
done from both ends for easy convenience.
It is a fast pour & adequate strength of personnel as well as workers must be available.
Regards

Check List for Below Ground RCC Swimming Pool Concrete Pour Item
# 26
Item # 26 previous (Preparatory Works) / # 47 this (Concrete Pour)
Pool size 25 x 13 M say & meant for local competition. Shallow end depth 1M. Deep end
depth 2.5 M. RCC base. RCC walls. Construction Joints. Open surface drains.
Submerged pool lights. Internal tiling on shelf surface. Pool carpet. Changing room.
Pergola.

Structural Items pours are defined herein.


Base Slab
Check coordinated services drawings duly approved or approve it to ensure the embeds
for first fix.
Check again all coordination for all such minor structures for services meeting purpose.
Make sure slope portion between the shallow & deep end is done rightly causing no
difficulty while pouring.
Make sure that water bars are available as well as fixed properly duly heat welded for the
CJ for both vertical & horizontal locations.
Make sure that these joints are correctly welded fixed at locations to produce watertight
CJ extending to horizontal & vertical profiles.
Or Check welded piece of PVC CJ ring is available & fixed correctly being kept half in
the raft & half in the walls portion Check all raft rebars to be true to design requirements
& well placed.
Check for CJ are correctly produced rough during concrete pour.
Check all side forms are erected rightly with good supports.
Check for electrical first fix conduits are inserted to shop drawings within the raft work.
Plan for raft pouring in one go. Pour lower end concrete first starting from corners &
move towards the sloping slab.
After doing this part, rise to the higher slab pout.
Make sure that CJ is correctly formed after the concrete for CJ kicker portion is complete.
CJ requires roughened surface of concrete at new concrete surface,
Extra concrete or laitance from water bar should be cleaned out immediately after
concreting.
Make sure that finishing is given such that tiles are laid properly later.
Proceed for curing of base slab

Walls
Check again that walls are carried out in alternate bays of CJ.
Check relevant wall again for all services first fix are inserted for walls.
Check again that bolts & supports would not slacken during pour.
Check again from safety angle working platforms are ready & erected.
Check pour can be done rightly.
Check relevant wall preparatory works are completed.
Plan four pour relevant wall after inspection.
Probably reducer shall be required for this pour at pump boom chute.
Follow concrete procedures so that it is poured in layers.
Check concrete is well vibrated & no voids are formed.
Make sure voids are avoided by taming hammers on sides of shutters.
Check curing procedures are complied with.
Balance Tank
Follow all procedures for base slab, walls & roof of balance tank are carried out
according to drawings with all inserts placed in.
All repetitive operations’ checks are required as defined on other check lists.
Comply with all QA requirements
Regards

Check List for Firing or Shooting Range Concrete Pour Item # 27


Item # 27 previous (Preparatory Works) / # 48 this (Concrete Pour)
300 M long, 25 M wide Range.
Components
Main building. RCC Framed structure.
General RCC Construction Procedures such as foundation, framing (beams & columns
wit suspended diaphragm slabs)
Previous quality procedures to follow with for all such elements.

Indoor Pistol Range. RCC Framed structure.


General RCC Construction Procedures such as foundation, framing (beams & columns
with suspended diaphragm slabs)
Previous quality procedures to follow with for all such elements.

Outdoor Shooting Range. RCC Framed structure & RCC walls.


General RCC Construction Procedures such as foundation, framing (beams & columns
with suspended diaphragm slabs)
Previous quality procedures to follow with for all such elements.

Bullet Trap Chamber. RCC Framed structure with inclined slabs.


General RCC Construction Procedures such as foundation, framing (beams & columns
with suspended inclined slabs given consideration of all safety inputs)
Previous quality procedures to follow with for all such elements.

Target Pits every 100 M. RCC Framed structure.


General RCC Construction Procedures such as foundation, framing (beams & columns
with suspended inclined slabs given consideration of all safety inputs)
Previous quality procedures to follow with for all such elements.

Underground passages Pits every 100 M. RCC Framed structure.


General RCC Construction Procedures such as foundation, framing (beams & columns
with suspended inclined slabs given consideration of all safety inputs) (tunneling)

Baffle walls. RCC ordinary thick walls 6 to 4 m high.


All procedures for RCC walls & architectural finishes to follow with.
Gantries supported on PTFE bearing mounted on Corbels.. Structural Steel armoured
plate with water proof board covering.
Regards

ITPs Inspection & Test Plans


Foregoing postings do provide to understand to some extent various quality controls
procedures in the form of check list. The check lists have been little explained for young
engineers. In field, experienced engineers produce such list point wise & that are
approved after incorporating required points of inspections.

ITPs would be required for the final check up of all items essential for inspections &
approvals. These plans shall carry relevant tests & inspections rows or columns
depending on defined or included activities.

These plans shall also contain hold & release points as well as test checks & surveillance
points. All activities shall be dealt in accordingly.

These ITPs projections of requirements shall also be projected on the construction


method statements in the part of QA mix in.
Regards,

Number if ITPs?
It is big issue to decide how many inspections should be planned for any project?
Based on experience & works interests’ it has been seen that excessive inspections do not
cater for a good quality requirement controls.
Inspections should be conducted in a proposing manner by the construction site
personnel.
Inspections should be conducted in a decisive manner by the construction quality
personnel.
Inspections should be conducted in a supervising manner by the consulting quality
personnel.
Inspections should be conducted in a surveillance manner by the consulting quality
personnel.
All relevant personnel must be given procedural opportunities to share responsibilities at
various levels.
It may not be necessary to create hundreds of work items for thorough technical
inspection when all method statements have been approved.
Excessive scheme for inspections may allow hold points that would jeopardize the
progress on works while simultaneously, minimum level of inspections may jeopardize
work qualities.
Moderation must be calculated to keep inspections in such an optimum style that least
paperwork is required with maximum level of quality achievement.
Work input should build a degree of confidence in the construction personnel while the
engineer end must enjoy trust of all personnel involved with project.
ITPs should be approved & sequenced in such a way that progress should move smoothly
with minimum hold points while surveillance should keep overall inspection eyes.
Regards
P Eng Suraj Singh