DAFTAR HARGA DASAR

BAHAN

NO URAIAN SATUAN HARGA (RP) KETERANGAN


1 2 3 4 5

A. BAHAN LOKAL
1 Pasir urug M3 137,500.00 1 RET 500000
2 Pasir Beton M3 137,500.00 1 RET
3 Pasir Pasang M3 137,500.00 1 RET
1,3 ton/m3 = 1300 kg/m3 kg 105.77
4 Batu Gunung / Batu Kali M3 150,000.00 1 RET 600000
5 Koral Beton M3
6 Batu Krikil (sungai) M3 155,000.00 1 RET
7 Batu Pecah :
a. Batu Pecah 1 - 2 cm M3 312,500.00 1 RET 1250000
b. Batu Pecah 2 - 3 cm M3 250,000.00 1 RET 1000000
1,3 ton/m3 = 1300 kg/m3 kg 192.31
c. Batu Pecah 3 - 5 cm M3 250,000.00 1 RET
d. Batu Pecah 5 - 7 cm M3 250,000.00 1 RET
8 Sirtu M3 87,500.00 1 RET
9 Bahan Pilihan M3 112,500.00 1 RET
10 Filler Kg 2,500.00 1 RET
11 Grevel M3 262,500.00 1 RET
12 Bata Merah Bh 1,250.00
13 Tanah Urug M3 65,000.00 1 RET
14 Kayu Kelas I. a. Kayu Besi M3 10,000,000.00
b. Kayu Linggua M3 12,000,000.00
15 Kayu Kelas II :
a. Ky. Cempaka/Meranti (Balok/Papan/Tota M3 5,000,000.00
16 Kayu Kelas III :
a. Kayu Kananga (Papan Mal) M3 2,750,000.00
b. Kayu Nantu (Balok/Papan/Totara) M3 2,750,000.00
17 Bataco Bh 1,550.00
18 Hollobrik bh 3,000.00
19 Bambu (Dolken) Btg/4M 17,000.00
20 Dolken Kayu Btg/4M 56,000.00
21 Tanah Teras M3 137,500.00
22 Air ltr 100.00
23 Ijuk M2 112,500.00

C. BAHAN NON LOKAL / TOKO


1 Semen untuk Campuran (1 Kg) Kg 1,200.00
2 Semen untuk Campuran (50 Kg) Zak 60,000.00
3 Semen Warna Kg 3,375.00
4 Semen Warna (40 Kg) Zak 135,000.00
5 Seng Gelombang BJLS 20 Lembar 41,000.00
6 Seng alumunium gelombang BJLS 25 Lembar 55,000.00
7 Asbes Gelombang Lembar 37,000.00
8 Nok Asbes Lembar 40,000.00
9 Aluminium Gelombang Lembar 55,000.00
10 Genteng Metal
a. Genteng Metal Multiroof Lembar 95,000.00
b. Genteng Metal surya roof Lembar 72,500.00
c. Genteng Metal Sakura roof Lembar 33,000.00
11 Nok Genteng Metal Lembar 32,000.00
12 Baja Ringan (untuk atap)
a. Main Truss C.75-0,75 bh 80,000.00
b. Reng R 33-0,45 bh 40,000.00
c. Skrup Truss dia. 6-20 mm bh 400.00
d. Skrup reng dia 4-16 mm bh 400.00
e. Dynabol dia. 12-120 mm bh 850.00
13 Plat Aluminium Lembar 57,500.00
14 Seng Plat BJLS 20 Lembar 45,000.00
15 Seng Plat BJLS 25 Lembar 57,500.00
16 Superdek Lbr 65,000.00
17 Onduline Lbr 165,000.00
18 GRC board 6 mm x 30cm m1 25,000.00
19 Gypsum Board (122x244x0,40)cm lbr 85,000.00
20 Besi Beton Kg 11,000.00
21 Besi Profil Kg 17,000.00
22 Besi Plat t = 10 mm Lbr 1,250,000.00
23 Besi Plat t = 8mm Lbr 1,100,000.00
38 Kosen aluminium dark bown M' 110,000.00
39 Kosen aluminium silver M' 105,000.00
40 Pintu aluminium Bh 2,250,000.00
41 Profil aluminium pintu M' 165,000.00
42 Aluminium strip M' 60,000.00
43 Sekrup fixer bh 300.00
44 Sealant tube 45,000.00
45 Kawat Beton Kg 20,000.00
46 Kawat Anyam Kg 25,000.00
47 Kawat Harmonika Kg 27,000.00
48 Kawat Duri Kg 70,000.00
49 Kawat Ram Kg 25,000.00
50 Kawat Bronjong Kg 25,000.00
51 Kotak Bronjong 2,7 mm m3 450,000.00
52 Lem Kayu Kg 40,000.00
53 Paku Triplex Kg 20,000.00
54 Paku Seng Kg 25,000.00
55 Paku Biasa
Paku 1/2" Kg 18,000.00
Paku 3/5" Kg 18,000.00
Paku 1" Kg 18,000.00
Paku 1,5" Kg 18,000.00
Paku 2" Kg 15,000.00
Paku 2,5" Kg 15,000.00
Paku 3" Kg 15,000.00
Paku 4" Kg 15,000.00
Paku 5" Kg 15,000.00
Paku 6" Kg 15,000.00
56 Baut Genteng Kg 30,000.00
57 Ubin Abu-abu 20 x 20 Cm (antislip) M2 90,000.00 bh 3,600.00
58 Ubin Abu-abu 40 x 40 Cm (Polos) M2 85,000.00 bh 14,166.67
59 Plint Warna 10 x 40 Cm (Corak) M2 85,000.00 bh 14,166.67
60 Ubin Warna 20 x 25 Cm (Corak) M2 90,000.00 bh 4,500.00
61 Pasangan Batu Alam M2 125,000.00
62 Pasangan Batu Hias, palimanan M2 170,000.00
63 Ubin Marmer M2 175,000.00
64 Playwood 9 mm Lembar 115,000.00
65 Teakwood Besar Lembar 85,000.00
66 Teakwood Kecil Lembar 70,000.00
67 Triplex Tebal 4 mm Lembar 75,500.00
68 Triplex Tebal 2,7 mm Lembar 55,000.00
69 Triplex Tebal 9 mm Lembar 135,000.00
70 Triplex Tebal 12 mm Lembar 175,000.00
71 Gypsum board Lembar 85,000.00
72 Semen Gibsum kg 2,300.00
73 Lisplank GRC 20 cm Lembar 50,000.00
74 Lisplank GRC 30 cm Lembar 70,000.00
75 List Profil gibsum 8cm M1 20,000.00
76 Besi Hollow 20/20 M1 9,700.00
77 Besi Hollow 40/40 M1 17,000.00
78 Dumpul Kayu Kg 41,000.00
79 Spiritus Ltr 17,500.00
80 Minyak Cat Ltr 20,000.00
81 Politur Vernis Kg 60,000.00
82 Meni Kayu / Besi Kg 33,000.00
83 Cat Mengkilap Kg 58,000.00
84 Cat Minyak Kg 58,000.00
85 Marmerkalk Kg 10,000.00
86 Cat Tembok (Cat Dasar) Kg 45,000.00
87 Cat Tembok Kg 70,000.00
88 Cat Tembok Eksterior 2,5 ltr 244,500.00
89 Cat Tembok Interior 2,5 ltr 163,000.00
90 Cat Seng Mengkilap 5 Kg 195,000.00
91 Clear Cat Ltr 60,000.00
92 Thiner Ltr 20,000.00
93 Oker (Pewarna) Kg 40,000.00
94 Plamur Kg 45,000.00
95 cat waterproofing kg 60,000.00
96 Amplas lbr 15,000.00
97 Kaca Polos 2 mm M2 75,000.00
98 Kaca Polos 3 mm M2 100,000.00
99 Kaca Polos 5 mm M2 150,000.00
100 Kaca ES 3 MM (Buram) M2 230,000.00
101 Kaca Rayben 5 mm M2 175,000.00
102 Kaca Blok 20 x 20 Bh 23,000.00
103 Roster beton 20 x 20 Bh 12,500.00
104 Kunci Tanam 2 Slag Bh 120,000.00
105 handle jendela Bh 35,500.00
106 handle pintu stainless stell 60 cm Bh 225,000.00
107 Grendel Bh 15,000.00
108 Hak Angin Bh 17,500.00
109 Engsel Pintu 4" Bh 22,500.00
110 Engsel jendela 3" Bh 12,000.00
111 Engsel Kupu-Kupu Kecil (Nylon) Bh 5,000.00
112 Closet Jongkok Keramik (Warna) Bh 350,000.00
113 Closet Jongkok Keramik (Putih) Bh 325,000.00
114 Closet Duduk Keramik (Putih) Set 1,800,000.00
115 Wastafel Standart Set 400,000.00
116 Wastafel Keramik standart (Lengkap) Set 650,000.00
117 jet shower Bh 125,000.00
118 Floor drain stainless stell Unit 50,000.00
119 Bak Fiberglas (M3) Bh 3,250,000.00
120 Bak Vernikel Engkel Bh 185,000.00
121 Cermin set wastafel Bh 335,000.00
122 Mata Kran Vernekel 1/2 " Bh 50,000.00
123 Mata Kran Vernekel Angsa Bh 50,000.00
124 Lampu TL 2 x 20 Watt Set 135,000.00
125 Fitting lampu Down light dia 15cm Set 35,000.00
126 Lampu SL 18 Watt Set 82,000.00
127 Sakelar Engkel IB Bh 20,000.00
128 Sakelar Double IB Bh 25,000.00
129 Stop Kontak IB Bh 22,500.00
130 Panel Box (800x600x250) bh 2,750,000.00
131 kabel NYM 2 X 2,5 M1 11,750.00
132 Kabel NYM 3 X 2,5 M1 16,000.00
133 MCB 1P 6A Bh 85,000.00
134 MCB 1P 16A Bh 100,000.00
135 MCB 3P 6A Bh 285,000.00
136 Box Panel PVC - MCB 6grup set 150,000.00
137 Leis Profil SP3 Ujung 10,000.00
138 Leis Profil SP4 Ujung 12,000.00
139 Leis Profil SP5 Ujung 13,000.00
140 Pipa PVC Type AW 1/2 " Ujung 30,000.00
141 Pipa PVC Type AW 3/4 " Ujung 35,000.00
142 Pipa PVC Type AW 1 " Ujung 41,400.00
143 Pipa PVC Type AW 1 1/4 " Ujung 62,100.00
144 Pipa PVC Type AW 2 " Ujung 204,600.00
145 Pipa PVC Type AW 3 " Ujung 235,000.00
146 Pipa PVC Type AW 4" Ujung 350,000.00
147 Pipa PVC Type AW 6 " Ujung 675,000.00
148 Paving Stone Biasa Bh 2,200.00 m2 94,600.00
149 Paving Stone Warna Bh 2,500.00 m2 107,500.00
150 Besin Ltr 6,600.00
151 Solar Ltr 6,450.00
152 Pelumas/Olie Ltr 40,000.00
153 Thiner Ltr 25,000.00
154 Kawat Las Dos 40,000.00
155 Pipa Hollow (20x40x0,3)mm btng 28,000.00
156 Pipa Hollow (20x40x0,4)mm btng 38,500.00
157 Pipa Hollow (40x40x0,3)mm btng 36,000.00
158 Pipa Hollow (40x40x0,4)mm btng 55,000.00
550,000.00
550,000.00
550,000.00
423.08
600,000.00
0.00
620,000.00
0.00
1,250,000.00
1,000,000.00
275000
4.06
67734
DAFTAR HARGA DASAR
UPAH KERJA

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)
1 2 3 4

1 Pekerja / Buruh O.H. 120,000.00


2 M a n d o r O.H. 140,000.00
3 T u k a n g Kayu O.H. 160,000.00
4 Kepala Tukang Kayu O.H. 175,000.00
5 Tukang Batu O.H. 150,000.00

6 Kepala Tukang Batu O.H. 160,000.00

7 Tukang Besi O.H. 150,000.00

8 Kepala Tukang Besi O.H. 160,000.00

9 Tukang Cat O.H. 150,000.00

10 Kepala Tukang Cat O.H. 160,000.00

11 Tukang Las O.H. 160,000.00

12 Kepala Tukang Las O.H. 175,000.00

13 Tukang Plitur O.H. 150,000.00

14 Kepala Tukang Plitur O.H. 160,000.00

15 Tukang Listrik O.H. 160,000.00

16 Tukang Pipa Ledeng O.H. 175,000.00

17 Sopir O.H. 130,000.00

18 Kernet/Pembantu Sopir O.H. 100,000.00

19 Oprator Tak Terlatih O.H. 120,000.00

20 Oprator Terlatih O.H. 175,000.00

21 Oprator Semi Terlatih O.H. 150,000.00


DAFTAR HARGA DASAR
PERALATAN

NO URAIAN SATUAN
1 2 3

1 Mesin las jam


2 Alat penyambung pipa HDPE sd 24" (set) jam
3 Alat penyambung pipa HDPE sd 10" (set) jam
4 Alat penyambung pipa HDPE sd 5" (set) jam
5 Alat penyambung geomembran HDPE jam
0
1. Kepala Seksi Perencanaab Bidang Cipta Karya
2. Kepala seksi Perencanaan Bidang Bina Marga
3. Kepala Seksi Perencanaan Bidang Sumber Daya Air
4. Kepala Seksi Perencanaan Bidang Penataan Ruang dan Pertanahan

0
1. Kepala Bidang Cipta Karya
2. Kepala Bidang Bina Marga
3. Kepala Bidang Sumber Daya Air
4. Kepala Bidang Penataan Ruang dan Pertanahan

Mengetahui :
Kepala Dinas Pekerjaan Umum dan Penataan Ruang
ASAR

HARGA (RP) KETERANGAN


4 5

45,000.00
37,500.00
31,250.00
25,000.00
18,750.00
DAFTAR HARGA SATUAN PEKERJAAN
1 A.2.2.1.1. (K3) Pembuatan 1 m2 Pagar Sementara dari Kayu tinggi 2 meter
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA -
1 Pekerja L.01 OH 0.4000 120,000.00 48,000.00
2 Tukang Kayu L.02 OH 0.4000 160,000.00 64,000.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH 0.0200 140,000.00 2,800.00
JUMLAH TENAGA KERJA 118,300.00
B BAHAN
1 Dolken kayu dia 8-10; 400 cm Batang 1.2500 56,000.00 70,000.00
2 Semen Portland Kg 5.0000 1,200.00 6,000.00
3 Pasir Beton m3 0.0050 137,500.00 687.50
4 Koral Beton m3 0.0090 155,000.00 1,395.00
5 Kayu 5/7 m3 0.0720 2,750,000.00 198,000.00
6 Paku biasa 2"-5" Kg 0.0600 - -
7 Residu Liter 0.4000 40,000.00 16,000.00

JUMLAH HARGA BAHAN 292,082.50


C PERALATAN

-
-
JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 410,382.50


E OVERHEAD & PROFIT 10% X D 41,038.25
F HARGA SATUAN PEKERJAAN (D+E) 451,420.75

2 A.2.2.1.2 (K3) Pembuatan 1 m2 Pagar Sementara dari Seng Gelombang tinggi 2 meter

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA -
1 Pekerja L.01 OH 0.2000 120,000.00 24,000.00
2 Tukang Kayu L.02 OH 0.2000 160,000.00 32,000.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH 0.0200 140,000.00 2,800.00
JUMLAH TENAGA KERJA 62,300.00
B BAHAN
1 Dolken kayu 8/10; 400 cm Batang 1.2500 56,000.00 70,000.00
2 Semen Portland Kg 2.5000 1,200.00 3,000.00
3 Seng Gelombang Lbr 0.8333 41,000.00 34,166.67
4 Pasir Beton m3 0.0050 137,500.00 687.50
5 Koral Beton m3 0.0090 155,000.00 1,395.00
6 Kayu 5/7 m3 0.0320 2,750,000.00 88,000.00
7 Paku biasa 2"-5" Kg 0.0600 - -

JUMLAH HARGA BAHAN 197,249.17


C PERALATAN
-
-
JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 259,549.17


E OVERHEAD & PROFIT 10% X D 25,954.92
F HARGA SATUAN PEKERJAAN (D+E) 285,504.08

1 A.2.2.1.4 Pengukuran dan Pemasangan 1 m' Bouwplank


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA -
1 Pekerja L.01 OH 0.1000 120,000.00 12,000.00
2 Tukang Kayu L.02 OH 0.1000 160,000.00 16,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0500 140,000.00 7,000.00
JUMLAH TENAGA KERJA 36,750.00
B BAHAN
1 Balok Kayu 5/7 m3 0.0120 2,750,000.00 33,000.00
2 Paku biasa 2"- 3" Kg 0.0200 - -
3 Kayu papan 3/20 m3 0.0070 2,750,000.00 19,250.00

JUMLAH HARGA BAHAN 52,250.00


C PERALATAN
-
JUMLAH HARGA ALAT -
D JUMLAH )A+B+C) 89,000.00
E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 89,000.00

4 A.2.2.1.6 (K3) Pembuatan 1 m2 Rumah Jaga (Konstruksi Kayu)


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.0000 120,000.00 120,000.00
2 Tukang Kayu L.02 OH 1.5000 160,000.00 240,000.00
3 Kepala Tukang L.03 OH 0.1500 175,000.00 26,250.00
4 Mandor L.04 OH 0.0500 140,000.00 7,000.00
JUMLAH TENAGA KERJA 393,250.00
B BAHAN
1 Dolken kayu 8/10; 400 cm Batang 3.0000 56,000.00 168,000.00
2 Kayu m3 0.2760 2,750,000.00 759,000.00
3 Paku Biasa Kg 0.7000 - -
4 Seng Gelombang lbr 1.5000 41,000.00 61,500.00
JUMLAH HARGA BAHAN 988,500.00
C PERALATAN -
JUMLAH HARGA ALAT 1,381,750.00
D JUMLAH )A+B+C) 2,763,500.00
E OVERHEAD & PROFIT 10% X D 276,350.00
F HARGA SATUAN PEKERJAAN (D+E) 3,039,850.00

5 A.2.2.1.7 (K3) Pembuatan 1 m2 gudang semen dan peralatan


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.0000 120,000.00 120,000.00
2 Tukang Kayu L.02 OH 2.0000 160,000.00 320,000.00
3 Kepala Tukang L.03 OH 0.2000 175,000.00 35,000.00
4 Mandor L.04 OH 0.0500 140,000.00 7,000.00
JUMLAH TENAGA KERJA 482,000.00
B BAHAN
1 Dolken kayu 8/10; 400 cm Batang 1.7000 56,000.00 95,200.00
2 Kayu m3 0.2100 2,750,000.00 577,500.00
3 Paku Biasa Kg 0.3000 - -
4 Semen Portland Kg 10.5000 1,200.00 12,600.00
5 Pasir Beton m3 0.0300 137,500.00 4,125.00
6 Koral Beton m3 0.0500 155,000.00 7,750.00
7 Seng Plat lbr 0.2500 45,000.00 11,250.00
8 Seng Gelombang lbr 1.5000 41,000.00 61,500.00
JUMLAH HARGA BAHAN 769,925.00
C PERALATAN -
JUMLAH HARGA ALAT 1,251,925.00
D JUMLAH )A+B+C) 2,503,850.00
E OVERHEAD & PROFIT 10% X D 250,385.00
F HARGA SATUAN PEKERJAAN (D+E) 2,754,235.00

6 A.2.2.1.11 Pembuatan 1 buah kotak adukan ukuran 40 cm x 50 cm x 25 cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Tukang Kayu L.02 OH 0.3000 160,000.00 48,000.00
2 Kepala Tukang L.03 OH 0.0300 175,000.00 5,250.00
JUMLAH TENAGA KERJA 53,250.00
B BAHAN
1 Papan Kayu Kelas III m3 0.0360 2,750,000.00 99,000.00
2 Paku Biasa Kg 0.0800 - -
3 Balok Kayu 5/7 Kelas III m3 0.0140 2,750,000.00 38,500.00
JUMLAH HARGA BAHAN 137,500.00
C PERALATAN
-
-
JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 190,750.00


E OVERHEAD & PROFIT 10% X D 19,075.00
F HARGA SATUAN PEKERJAAN (D+E) 209,825.00

7 A.2.2.1.13 Pembongkaran 1 m3 beton bertulang

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 13.3340 120,000.00 1,600,080.00
2 Mandor L.04 OH 0.6660 140,000.00 93,240.00
JUMLAH TENAGA KERJA 1,693,320.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH )A+B+C) 1,693,320.00
E OVERHEAD & PROFIT 10% X D 169,332.00
F HARGA SATUAN PEKERJAAN (D+E) 1,862,652.00

8 A.2.2.1.14 Pembongkaran 1 m3 dinding tembok bata

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 6.6670 120,000.00 800,040.00
2 Mandor L.04 OH 0.3330 140,000.00 46,620.00
JUMLAH TENAGA KERJA 846,660.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 846,660.00


E OVERHEAD & PROFIT 10% X D 84,666.00
F HARGA SATUAN PEKERJAAN (D+E) 931,326.00

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

2 A.2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 meter'

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.7500 120,000.00 90,000.00
2 Mandor L.04 OH 0.0250 140,000.00 3,500.00
JUMLAH TENAGA KERJA 93,500.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH )A+B+C) 93,500.00
E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 93,500.00
3 A.2.3.1.2 Penggalian 1 m3 tanah biasa sedalam 2 meter'

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.9000 120,000.00 108,000.00
2 Mandor L.04 OH 0.0450 140,000.00 6,300.00
JUMLAH TENAGA KERJA 114,300.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 114,300.00


E OVERHEAD & PROFIT 10% X D 11,430.00
F HARGA SATUAN PEKERJAAN (D+E) 125,730.00

11 A.2.3.1.3 Penggalian 1 m3 tanah biasa sedalam 3 meter'

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.0500 120,000.00 126,000.00
2 Mandor L.04 OH 0.0670 140,000.00 9,380.00
JUMLAH TENAGA KERJA 135,380.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 135,380.00


E OVERHEAD & PROFIT 10% X D 13,538.00
F HARGA SATUAN PEKERJAAN (D+E) 148,918.00

12 A.2.3.1.4 Menggali 1 m3 tanah keras sedalam 1 m

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.0000 120,000.00 120,000.00
2 Mandor L.04 OH 0.0320 140,000.00 4,480.00
JUMLAH TENAGA KERJA 124,480.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 124,480.00


E OVERHEAD & PROFIT 10% X D 12,448.00
F HARGA SATUAN PEKERJAAN (D+E) 136,928.00

13 A.2.3.1.6 Menggali 1 m3 tanah lumpur sedalam 1 m

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.2000 120,000.00 144,000.00
2 Mandor L.04 OH 0.0450 140,000.00 6,300.00
JUMLAH TENAGA KERJA 150,300.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 150,300.00


E OVERHEAD & PROFIT 10% X D 15,030.00
F HARGA SATUAN PEKERJAAN (D+E) 165,330.00

14 A.2.3.1.7 Pengerjaan stripping 1 m2 tanah tebing setinggi 1 meter

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0500 120,000.00 6,000.00
2 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 6,700.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 6,700.00


E OVERHEAD & PROFIT 10% X D 670.00
F HARGA SATUAN PEKERJAAN (D+E) 7,370.00

15 A.2.3.1.8 (K3) Pembuangan 1 m3 tanah sejauh 30 meter


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3300 120,000.00 39,600.00
2 Mandor L.04 OH 0.0100 140,000.00 1,400.00
JUMLAH TENAGA KERJA 41,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 41,000.00


E OVERHEAD & PROFIT 10% X D 4,100.00
F HARGA SATUAN PEKERJAAN (D+E) 45,100.00

4 A.2.3.1.9 Pengurugan kembali 1m3 galian tanah

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.5000 120,000.00 60,000.00
2 Mandor L.04 OH 0.0500 140,000.00 7,000.00
JUMLAH TENAGA KERJA 67,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH )A+B+C) 67,000.00
E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 67,000.00

17 A.2.3.1.10 (K3) Pemadatan tanah 1 m3 tanah (per 20 cm)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.5000 120,000.00 60,000.00
2 Mandor L.04 OH 0.0500 140,000.00 7,000.00
JUMLAH TENAGA KERJA 67,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 67,000.00


E OVERHEAD & PROFIT 10% X D 6,700.00
F HARGA SATUAN PEKERJAAN (D+E) 73,700.00

18 A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3000 120,000.00 36,000.00
2 Mandor L.04 OH 0.0100 140,000.00 1,400.00
JUMLAH TENAGA KERJA 37,400.00
B BAHAN
1 Pasir urug m3 1.2000 137,500.00 165,000.00

JUMLAH HARGA BAHAN 165,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 202,400.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 202,400.00

19 A.2.3.1.13 Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1500 120,000.00 18,000.00
2 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 20,100.00
B BAHAN
1 Ijuk m3 1.2000 112,500.00 135,000.00

JUMLAH HARGA BAHAN 135,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 155,100.00


E OVERHEAD & PROFIT 10% X D 15,510.00
F HARGA SATUAN PEKERJAAN (D+E) 170,610.00
5 A.2.3.1.14 Pengurugan 1 m3 tanah urug

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2500 120,000.00 30,000.00
2 Mandor L.04 OH 0.0250 140,000.00 3,500.00
JUMLAH TENAGA KERJA 33,500.00
B BAHAN
1 tanah urug m3 1.2000 65,000.00 78,000.00

JUMLAH HARGA BAHAN 78,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 111,500.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 111,500.00

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

21 A.3.2.1.1 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 3 PP

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.5000 120,000.00 180,000.00
2 Tukang Batu L.02 OH 0.7500 150,000.00 112,500.00
3 Kepala Tukang L.03 OH 0.0750 175,000.00 13,125.00
4 Mandor L.04 OH 0.0750 140,000.00 10,500.00
JUMLAH TENAGA KERJA 316,125.00
B BAHAN
1 Batu Belah m3 1.2000 150,000.00 180,000.00
2 Semen Portland kg 202.0000 1,200.00 242,400.00
3 Pasir Pasang m3 0.2850 137,500.00 39,187.50

JUMLAH HARGA BAHAN 461,587.50


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 777,712.50


E OVERHEAD & PROFIT 10% X D 77,771.25
F HARGA SATUAN PEKERJAAN (D+E) 855,483.75

6 A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 4 PP

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.5000 120,000.00 180,000.00
2 Tukang Batu L.02 OH 0.7500 150,000.00 112,500.00
3 Kepala Tukang L.03 OH 0.0750 175,000.00 13,125.00
4 Mandor L.04 OH 0.0750 140,000.00 10,500.00
JUMLAH TENAGA KERJA 316,125.00
B BAHAN
1 Batu Belah m3 1.2000 150,000.00 180,000.00
2 Semen Portland kg 163.0000 1,200.00 195,600.00
3 Pasir Pasang m3 0.5200 137,500.00 71,500.00

JUMLAH HARGA BAHAN 447,100.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 763,225.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 763,225.00
23 A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 5 PP

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.5000 120,000.00 180,000.00
2 Tukang Batu L.02 OH 0.7500 150,000.00 112,500.00
3 Kepala Tukang L.03 OH 0.0750 175,000.00 13,125.00
4 Mandor L.04 OH 0.0750 140,000.00 10,500.00
JUMLAH TENAGA KERJA 316,125.00
B BAHAN
1 Batu Belah m3 1.2000 150,000.00 180,000.00
2 Semen Portland kg 136.0000 1,200.00 163,200.00
3 Pasir Pasang m3 0.5440 137,500.00 74,800.00

JUMLAH HARGA BAHAN 418,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 734,125.00


E OVERHEAD & PROFIT 10% X D 73,412.50
F HARGA SATUAN PEKERJAAN (D+E) 807,537.50
7 A.3.2.1.9 (K3) Pemasangan 1 m3 batu kosong (aanstamping)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.7800 120,000.00 93,600.00
2 Tukang Batu L.02 OH 0.3900 150,000.00 58,500.00
3 Kepala Tukang L.03 OH 0.0390 175,000.00 6,825.00
4 Mandor L.04 OH 0.0390 140,000.00 5,460.00
JUMLAH TENAGA KERJA 164,385.00
B BAHAN
1 Batu Belah m3 1.2000 150,000.00 180,000.00
2 Pasir Urug m3 0.4320 137,500.00 59,400.00

JUMLAH HARGA BAHAN 239,400.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 403,785.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 403,785.00

25 A.3.2.1.9 Pemasangan 1 m3 pondasi sumuran diameter 100 cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 2.4000 120,000.00 288,000.00
2 Tukang Batu L.02 OH 0.8000 150,000.00 120,000.00
3 Kepala Tukang L.03 OH 0.0800 175,000.00 14,000.00
4 Mandor L.04 OH 0.1190 140,000.00 16,660.00
JUMLAH TENAGA KERJA 438,660.00
B BAHAN
1 Batu Belah m3 0.4500 150,000.00 67,500.00
2 Semen Portland kg 194.0000 1,200.00 232,800.00
3 Pasir Beton m3 0.3120 137,500.00 42,900.00
4 Kerikil m3 0.4680 155,000.00 72,540.00

JUMLAH HARGA BAHAN 415,740.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 854,400.00


E OVERHEAD & PROFIT 10% X D 85,440.00
F HARGA SATUAN PEKERJAAN (D+E) 939,840.00

A.4.1.1 HARGA SATUAN PEKERJAAN BETON

26 A.4.1.1.4 Membuat 1 m3 Lantai Kerja beton mutu f'c = 7,4 Mpa slump (3-6) cm, w/c = 0,87
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.2000 120,000.00 144,000.00
2 Tukang Batu L.02 OH 0.2000 150,000.00 30,000.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH 0.0600 140,000.00 8,400.00
JUMLAH TENAGA KERJA 185,900.00
B BAHAN
1 Semen Portland kg 230.0000 1,200.00 276,000.00
2 Pasir beton kg 893.0000 105.77 94,451.92
3 Kerikil (max 30 mm) kg 1,027.0000 192.31 197,500.00
4 Air ltr 200.0000 100.00 20,000.00
JUMLAH HARGA BAHAN 587,951.92
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 773,851.92


E OVERHEAD & PROFIT 10% X D 77,385.19
F HARGA SATUAN PEKERJAAN (D+E) 851,237.12

27 A.4.1.1.1 Membuat 1 m3 beton mutu f'c = 7,4 Mpa (K-100)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.6500 120,000.00 198,000.00
2 Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
3 Kepala Tukang L.03 OH 0.0280 175,000.00 4,900.00
4 Mandor L.04 OH 0.0830 140,000.00 11,620.00
JUMLAH TENAGA KERJA 255,770.00
B BAHAN
1 Semen Portland kg 247.0000 1,200.00 296,400.00
2 Pasir beton kg 869.0000 105.77 91,913.46
3 Kerikil (max 30 mm) kg 999.0000 192.31 192,115.38
4 Air ltr 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 601,928.85
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 857,698.85


E OVERHEAD & PROFIT 10% X D 85,769.88
F HARGA SATUAN PEKERJAAN (D+E) 943,468.73

8 A.4.1.1.2 Membuat 1 m3 beton mutu f'c = 9,8 MPa (K-125)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.6500 120,000.00 198,000.00
2 Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
3 Kepala Tukang L.03 OH 0.0280 175,000.00 4,900.00
4 Mandor L.04 OH 0.0830 140,000.00 11,620.00
JUMLAH TENAGA KERJA 255,770.00
B BAHAN
1 Semen Portland kg 276.0000 1,200.00 331,200.00
2 Pasir beton kg 828.0000 105.77 87,576.92
3 Kerikil (max 30 mm) kg 1,012.0000 192.31 194,615.38
4 Air ltr 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 634,892.31
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 890,662.31


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 890,662.31
29 A.4.1.1.3 Membuat 1 m3 beton mutu f'c = 12,2 Mpa (K-175)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.6500 120,000.00 198,000.00
2 Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
3 Kepala Tukang L.03 OH 0.0280 175,000.00 4,900.00
4 Mandor L.04 OH 0.0830 140,000.00 11,620.00
JUMLAH TENAGA KERJA 255,770.00
B BAHAN
1 Semen Portland kg 299.0000 1,200.00 358,800.00
2 Pasir beton kg 799.0000 105.77 84,509.62
3 Kerikil (max 30 mm) kg 1,017.0000 192.31 195,576.92
4 Air ltr 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 660,386.54
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 916,156.54


E OVERHEAD & PROFIT 10% X D 91,615.65
F HARGA SATUAN PEKERJAAN (D+E) 1,007,772.19

30 A.4.1.1.6 Membuat 1 m3 beton mutu f'c = 16,9 Mpa (K-175)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.6500 120,000.00 198,000.00
2 Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
3 Kepala Tukang L.03 OH 0.0280 175,000.00 4,900.00
4 Mandor L.04 OH 0.0830 140,000.00 11,620.00
JUMLAH TENAGA KERJA 255,770.00
B BAHAN
1 Semen Portland kg 352.0000 1,200.00 422,400.00
2 Pasir beton kg 731.0000 105.77 77,317.31
3 Kerikil (max 30 mm) kg 1,031.0000 192.31 198,269.23
4 Air ltr 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 719,486.54
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 975,256.54


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 975,256.54

31 A.4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K-250)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)
A TENAGA
1 Pekerja L.01 OH 1.6500 120,000.00 198,000.00
2 Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
3 Kepala Tukang L.03 OH 0.0280 175,000.00 4,900.00
4 Mandor L.04 OH 0.0830 140,000.00 11,620.00
JUMLAH TENAGA KERJA 255,770.00
B BAHAN
1 Semen Portland kg 371.0000 1,200.00 445,200.00
2 Pasir beton kg 698.0000 105.77 73,826.92
3 Kerikil (max 30 mm) kg 1,047.0000 192.31 201,346.15
4 Air ltr 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 741,873.08
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 997,643.08


E OVERHEAD & PROFIT 10% X D 99,764.31
F HARGA SATUAN PEKERJAAN (D+E) 1,097,407.38

32 A.4.1.1.8 Membuat 1 m3 beton mutu f'c = 21,7 Mpa (K-250)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.6500 120,000.00 198,000.00
2 Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
3 Kepala Tukang L.03 OH 0.0280 175,000.00 4,900.00
4 Mandor L.04 OH 0.0830 140,000.00 11,620.00
JUMLAH TENAGA KERJA 255,770.00
B BAHAN
1 Semen Portland kg 384.0000 1,200.00 460,800.00
2 Pasir beton kg 692.0000 105.77 73,192.31
3 Kerikil (max 30 mm) kg 1,039.0000 192.31 199,807.69
4 Air ltr 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 755,300.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 1,011,070.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 1,011,070.00

33 A.4.1.1.9 Membuat 1 m3 beton mutu f'c = 24 Mpa (K-300)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.6500 120,000.00 198,000.00
2 Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
3 Kepala Tukang L.03 OH 0.0280 175,000.00 4,900.00
4 Mandor L.04 OH 0.0830 140,000.00 11,620.00
JUMLAH TENAGA KERJA 255,770.00
B BAHAN
1 Semen Portland kg 406.0000 1,200.00 487,200.00
2 Pasir beton kg 684.0000 105.77 72,346.15
3 Kerikil (max 30 mm) kg 1,026.0000 192.31 197,307.69
4 Air ltr 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 778,353.85
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 1,034,123.85


E OVERHEAD & PROFIT 10% X D 103,412.38
F HARGA SATUAN PEKERJAAN (D+E) 1,137,536.23

34 A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0700 120,000.00 8,400.00
2 Tukang Besi L.02 OH 0.0700 150,000.00 10,500.00
3 Kepala Tukang L.03 OH 0.0070 175,000.00 1,225.00
4 Mandor L.04 OH 0.0040 140,000.00 560.00
JUMLAH TENAGA KERJA 20,685.00
B BAHAN
1 Besi beton (polos/ulir) kg 10.5000 11,000.00 115,500.00
2 Kawat Beton kg 0.1500 20,000.00 3,000.00
JUMLAH HARGA BAHAN 118,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 139,185.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 139,185.00

35 A.4.1.1.20 (K3) Pemasangan 1m2 bekisting untuk pondasi

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.5200 120,000.00 62,400.00
2 Tukang Kayu L.02 OH 0.2600 160,000.00 41,600.00
3 Kepala Tukang L.03 OH 0.0260 175,000.00 4,550.00
4 Mandor L.04 OH 0.0260 140,000.00 3,640.00
JUMLAH TENAGA KERJA 112,190.00
B BAHAN
1 Kayu Kelas III m3 0.0400 2,750,000.00 110,000.00
2 Paku 5 - 10 cm kg 0.3000 - -
3 Minyak Bekisting liter 0.1000 40,000.00 4,000.00
JUMLAH HARGA BAHAN 114,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 226,190.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 226,190.00

36 A.4.1.1.21 (K3) Pemasangan 1m2 bekisting untuk sloof

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.5200 120,000.00 62,400.00
2 Tukang Kayu L.02 OH 0.2600 160,000.00 41,600.00
3 Kepala Tukang L.03 OH 0.0260 175,000.00 4,550.00
4 Mandor L.04 OH 0.0260 140,000.00 3,640.00
JUMLAH TENAGA KERJA 112,190.00
B BAHAN
1 Kayu Kelas III m3 0.0450 2,750,000.00 123,750.00
2 Paku 5 - 10 cm kg 0.3000 - -
3 Minyak Bekisting liter 0.1000 40,000.00 4,000.00
JUMLAH HARGA BAHAN 127,750.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 239,940.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 239,940.00

37 A.4.1.1.22 (K3) Pemasangan 1m2 bekisting untuk kolom

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.6600 120,000.00 79,200.00
2 Tukang Kayu L.02 OH 0.3300 160,000.00 52,800.00
3 Kepala Tukang L.03 OH 0.0330 175,000.00 5,775.00
4 Mandor L.04 OH 0.0330 140,000.00 4,620.00
JUMLAH TENAGA KERJA 142,395.00
B BAHAN
1 Kayu Kelas III m3 0.0200 2,750,000.00 55,000.00
2 Paku 5 - 10 cm kg 0.4000 - -
3 Minyak Bekisting liter 0.2000 40,000.00 8,000.00
4 Balok Kayu Kelas III m3 0.0150 2,750,000.00 41,250.00
5 Plywood tebal 9 mm lembar 0.3500 115,000.00 40,250.00

JUMLAH HARGA BAHAN 144,500.00


C PERALATAN
JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 286,895.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 286,895.00

38 A.4.1.1.23 (K3) Pemasangan 1m2 bekisting untuk balok

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.6600 120,000.00 79,200.00
2 Tukang Kayu L.02 OH 0.3300 160,000.00 52,800.00
3 Kepala Tukang L.03 OH 0.0330 175,000.00 5,775.00
4 Mandor L.04 OH 0.0330 140,000.00 4,620.00
JUMLAH TENAGA KERJA 142,395.00
B BAHAN
1 Kayu Kelas III m3 0.0200 2,750,000.00 55,000.00
2 Paku 5 - 10 cm kg 0.4000 - -
3 Minyak Bekisting liter 0.2000 40,000.00 8,000.00
4 Balok Kayu Kelas III m3 0.0180 2,750,000.00 49,500.00
5 Plywood tebal 9 mm lembar 0.3500 115,000.00 40,250.00

JUMLAH HARGA BAHAN 152,750.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 295,145.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 295,145.00

39 A.4.1.1.24 (K3) Pemasangan 1m2 bekisting untuk lantai

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.6600 120,000.00 79,200.00
2 Tukang Kayu L.02 OH 0.3300 160,000.00 52,800.00
3 Kepala Tukang L.03 OH 0.0330 175,000.00 5,775.00
4 Mandor L.04 OH 0.0330 140,000.00 4,620.00
JUMLAH TENAGA KERJA 142,395.00
B BAHAN
1 Kayu Kelas III m3 0.0250 2,750,000.00 68,750.00
2 Paku 5 - 10 cm kg 0.4000 15,000.00 6,000.00
3 Minyak Bekisting liter 0.2000 40,000.00 8,000.00
4 Balok Kayu Kelas III m3 0.0150 2,750,000.00 41,250.00
5 Plywood tebal 9 mm lembar 0.3000 115,000.00 34,500.00
6 Dolken kayu dia. 8-10 cm - pjng 4 m batang 4.0000 17,000.00 68,000.00

JUMLAH HARGA BAHAN 226,500.00


C PERALATAN
JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 368,895.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 368,895.00

40 A.4.1.1.25 (K3) Pemasangan 1m2 bekisting untuk dinding

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.6600 120,000.00 79,200.00
2 Tukang Kayu L.02 OH 0.3300 160,000.00 52,800.00
3 Kepala Tukang L.03 OH 0.0330 175,000.00 5,775.00
4 Mandor L.04 OH 0.0330 140,000.00 4,620.00
JUMLAH TENAGA KERJA 142,395.00
B BAHAN
1 Kayu Kelas III m3 0.0300 2,750,000.00 82,500.00
2 Paku 5 - 12 cm kg 0.4000 15,000.00 6,000.00
3 Minyak Bekisting liter 0.2000 40,000.00 8,000.00
4 Balok Kayu Kelas III m3 0.0200 2,750,000.00 55,000.00
5 Plywood tebal 9 mm lembar 0.3500 115,000.00 40,250.00
6 Dolken kayu dia. 8-10 cm - pjng 4 m batang 3.0000 17,000.00 51,000.00

JUMLAH HARGA BAHAN 242,750.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 385,145.00


E OVERHEAD & PROFIT 10% X D 38,514.50
F HARGA SATUAN PEKERJAAN (D+E) 423,659.50

41 A.4.1.1.26 (K3) Pemasangan 1m2 bekisting untuk tangga

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.6600 120,000.00 79,200.00
2 Tukang Kayu L.02 OH 0.3300 160,000.00 52,800.00
3 Kepala Tukang L.03 OH 0.0330 175,000.00 5,775.00
4 Mandor L.04 OH 0.0330 140,000.00 4,620.00
JUMLAH TENAGA KERJA 142,395.00
B BAHAN
1 Kayu Kelas III m3 0.0300 2,750,000.00 82,500.00
2 Paku 5 - 12 cm kg 0.4000 15,000.00 6,000.00
3 Minyak Bekisting liter 0.1500 40,000.00 6,000.00
4 Balok Kayu Kelas III m3 0.0150 2,750,000.00 41,250.00
5 Plywood tebal 9 mm lembar 0.3500 115,000.00 40,250.00
6 Dolken kayu dia. 8-10 cm - pjng 4 m batang 2.0000 17,000.00 34,000.00

JUMLAH HARGA BAHAN 210,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 352,395.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 352,395.00

9 A.4.1.1.35 Membuat 1 m' kolom praktis beton bertulang (11x11) cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1800 120,000.00 21,600.00
2 Tukang Batu L.02 OH 0.0200 150,000.00 3,000.00
3 Tukang Kayu L.02 OH 0.0200 160,000.00 3,200.00
4 Tukang Besi L.02 OH 0.0200 150,000.00 3,000.00
5 Kepala Tukang L.03 OH 0.0060 175,000.00 1,050.00
6 Mandor L.04 OH 0.0090 140,000.00 1,260.00
JUMLAH TENAGA KERJA 33,110.00
B BAHAN
1 Kayu Kelas III m3 0.0020 2,750,000.00 5,500.00
2 Paku 5 - 12 cm kg 0.0100 15,000.00 150.00
3 Minyak Bekisting liter - 40,000.00 -
4 Besi beton polos kg 3.0000 11,000.00 33,000.00
5 Kawat beton kg 0.4500 20,000.00 9,000.00
6 Semen Portland kg 4.0000 1,200.00 4,800.00
7 Pasir Beton m3 0.0060 137,500.00 825.00
8 Kerikil m3 0.0090 155,000.00 1,395.00
JUMLAH HARGA BAHAN 54,670.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 87,780.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 87,780.00

10 A.4.1.1.36 Membuat 1 m' ring balok beton bertulang (10x15) cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2970 120,000.00 35,640.00
2 Tukang Batu L.02 OH 0.0330 150,000.00 4,950.00
3 Tukang Kayu L.02 OH 0.0330 160,000.00 5,280.00
4 Tukang Besi L.02 OH 0.0330 150,000.00 4,950.00
5 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
6 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 54,670.00
B BAHAN
1 Kayu Kelas III m3 0.0030 2,750,000.00 8,250.00
2 Paku 5 - 12 cm kg 0.0200 15,000.00 300.00
3 Minyak Bekisting liter - 40,000.00 -
4 Besi beton polos kg 3.6000 11,000.00 39,600.00
5 Kawat beton kg 0.0500 20,000.00 1,000.00
6 Semen Portland kg 5.5000 1,200.00 6,600.00
7 Pasir Beton m3 0.0090 137,500.00 1,237.50
8 Kerikil m3 0.0150 155,000.00 2,325.00
JUMLAH HARGA BAHAN 59,312.50
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 113,982.50


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 113,982.50

A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

44 A.4.2.1.1 Pemasangan 1 kg besi profil

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0600 120,000.00 7,200.00
2 Tukang las konstruksi L.02 OH 0.0600 160,000.00 9,600.00
3 Kepala Tukang L.03 OH 0.0060 175,000.00 1,050.00
4 Mandor L.04 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 18,270.00
B BAHAN
1 Besi profil kg 1.1500 17,000.00 19,550.00
JUMLAH HARGA BAHAN 19,550.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 37,820.00


E OVERHEAD & PROFIT 10% X D 3,782.00
F HARGA SATUAN PEKERJAAN (D+E) 41,602.00

45 A1 1 m3 Pekerjaan Pondasi beton bertulang f'c=19,3Mpa (K-250) + Besi 180 kg + Bekisting

No Uraian Pekerjaan Volume/m3 Harga Satuan Jadi Jumlah Harga


A.4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K-250) 1 1,097,407.38 1,097,407.38
A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir 180 13,918.50 2,505,330.00
A.4.1.1.20 (K3) Pemasangan 1m2 bekisting untuk pondasi 4 226,190.00 904,760.00
Jumlah 1+2+3 4,507,497.38

46 A2 Pekerjaan Kolom beton bertulang f'c=19,3Mpa (K-250) + Besi 175 kg + Bekisting

No Uraian Pekerjaan Volume/m3 Harga Satuan Jadi Jumlah Harga


A.4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K-250) 1 1,097,407.38 1,097,407.38
A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir 175 13,918.50 2,435,737.50
A.4.1.1.22 (K3) Pemasangan 1m2 bekisting untuk kolom 8 286,895.00 2,295,160.00
Jumlah 1+2+3 5,828,304.88

47 A3 Pekerjaan Sloof bertulang f'c=19,3Mpa (K-250) + Besi 150 kg + Bekisting

No Uraian Pekerjaan Volume/m3 Harga Satuan Jadi Jumlah Harga


A.4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K-250) 1 1,097,407.38 1,097,407.38
A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir 150 13,918.50 2,087,775.00
A.4.1.1.21 (K3) Pemasangan 1m2 bekisting untuk sloof 10 239,940.00 2,399,400.00
Jumlah 1+2+3 5,584,582.38

48 A4 Pekerjaan balok beton bertulang f'c=19,3Mpa (K-250) + Besi 200 kg + Bekisting

No Uraian Pekerjaan Volume/m3 Harga Satuan Jadi Jumlah Harga


A.4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K-250) 1 1,097,407.38 1,097,407.38
A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir 175 13,918.50 2,435,737.50
A.4.1.1.23 (K3) Pemasangan 1m2 bekisting untuk balok 8 295,145.00 2,361,160.00
Jumlah 1+2+3 5,894,304.88

49 A5 Pekerjaan Plat Lantai/Dak atap beton bertulang f'c=19,3Mpa (K-250) + Besi 150 kg + Bekisting

No Uraian Pekerjaan Volume/m3 Harga Satuan Jadi Jumlah Harga


A.4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K-250) 1 1,097,407.38 1,097,407.38
A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir 150 13,918.50 2,087,775.00
A.4.1.1.24 (K3) Pemasangan 1m2 bekisting untuk lantai 8 368,895.00 2,951,160.00
Jumlah 1+2+3 6,136,342.38

50 A6 Pekerjaan Tangga beton bertulang f'c=19,3Mpa (K-250) + Besi 175 kg + Bekisting

No Uraian Pekerjaan Volume/m3 Harga Satuan Jadi Jumlah Harga


A.4.1.1.7 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K-250) 1 1,097,407.38 1,097,407.38
A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir 175 13,918.50 2,435,737.50
A.4.1.1.26 (K3) Pemasangan 1m2 bekisting untuk tangga 8 352,395.00 2,819,160.00
Jumlah 1+2+3 6,352,304.88
51 A.4.2.1.2 Pemasangan 1 kg rangka kuda-kuda baja

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0600 120,000.00 7,200.00
2 Tukang las konstruksi L.02 OH 0.0600 160,000.00 9,600.00
3 Kepala Tukang L.03 OH 0.0060 175,000.00 1,050.00
4 Mandor L.04 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 18,270.00
B BAHAN
1 Besi Baja IWF kg 1.1500 17,000.00 19,550.00
JUMLAH HARGA BAHAN 19,550.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 37,820.00


E OVERHEAD & PROFIT 10% X D 3,782.00
F HARGA SATUAN PEKERJAAN (D+E) 41,602.00

52 A.4.2.1.11 Pemasangan 1 m kusen pintu alumunium

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0430 120,000.00 5,160.00
2 Tukang Las L.02 OH 0.0430 160,000.00 6,880.00
3 Kepala Tukang L.03 OH 0.0043 175,000.00 752.50
4 Mandor L.04 OH 0.0021 140,000.00 294.00
JUMLAH TENAGA KERJA 13,086.50
B BAHAN
1 Profil alumunium kg 1.1000 110,000.00 121,000.00
2 Skrup fixer buah 2.0000 300.00 600.00
3 Sealant tube 0.0600 45,000.00 2,700.00
JUMLAH HARGA BAHAN 124,300.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 137,386.50


E OVERHEAD & PROFIT 10% X D 13,738.65
F HARGA SATUAN PEKERJAAN (D+E) 151,125.15

53 A.4.2.1.12 Pemasangan 1 m2 pintu alumunium strip lebar 8 cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0850 120,000.00 10,200.00
2 Tukang Las L.02 OH 0.0850 160,000.00 13,600.00
3 Kepala Tukang L.03 OH 0.0085 175,000.00 1,487.50
4 Mandor L.04 OH 0.0042 140,000.00 588.00
JUMLAH TENAGA KERJA 25,875.50
B BAHAN
1 Profil alumunium m 4.4000 165,000.00 726,000.00
2 Alumunium strip m 14.6000 60,000.00 876,000.00
JUMLAH HARGA BAHAN 1,602,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 1,627,875.50


E OVERHEAD & PROFIT 10% X D 162,787.55
F HARGA SATUAN PEKERJAAN (D+E) 1,790,663.05

54 A.4.2.1.13 Pemasangan 1 m2 pintu kaca rangka alumunium

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.8500 120,000.00 102,000.00
2 Tukang Las L.02 OH 0.8500 160,000.00 136,000.00
3 Kepala Tukang L.03 OH 0.0900 175,000.00 15,750.00
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 254,450.00
B BAHAN
1 Profil alumunium m 4.4000 165,000.00 726,000.00
2 Profil kaca 5mm m2 1.4000 150,000.00 210,000.00
3 Sealant tube 0.7700 45,000.00 34,650.00
JUMLAH HARGA BAHAN 970,650.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 1,225,100.00


E OVERHEAD & PROFIT 10% X D 122,510.00
F HARGA SATUAN PEKERJAAN (D+E) 1,347,610.00
55 A.4.2.1.14 Pemasangan 1 m2 venetions blinds dan vertical blinds

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3500 120,000.00 42,000.00
2 Tukang Las L.02 OH 0.3500 160,000.00 56,000.00
3 Kepala Tukang L.03 OH 0.0350 175,000.00 6,125.00
4 Mandor L.04 OH 0.0180 140,000.00 2,520.00
JUMLAH TENAGA KERJA 106,645.00
B BAHAN
1 Venetions Blinds dan Vertical m2 1.0000 200,000.00 200,000.00
Blinds

JUMLAH HARGA BAHAN 200,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 306,645.00


E OVERHEAD & PROFIT 10% X D 30,664.50
F HARGA SATUAN PEKERJAAN (D+E) 337,309.50

56 A.4.2.1.15 Pemasangan 1 m2 teralis besi strip (2x3)mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.6700 120,000.00 200,400.00
2 Tukang Las L.02 OH 1.6700 160,000.00 267,200.00
3 Kepala Tukang L.03 OH 0.1670 175,000.00 29,225.00
4 Mandor L.04 OH 0.0830 140,000.00 11,620.00
JUMLAH TENAGA KERJA 508,445.00
B BAHAN
1 Besi Strip m2 1.0000 11,000.00 11,000.00
9,026.67
2 Pengelasan cm 27.0800 333.33

JUMLAH HARGA BAHAN 20,026.67


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 528,471.67


E OVERHEAD & PROFIT 10% X D 52,847.17
F HARGA SATUAN PEKERJAAN (D+E) 581,318.83
A.4.4.1 HARGA SATUAN PEKERJAAN DINDING

57 A.4.4.1.2 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 bata campuran 1 SP : 3 PP

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.2000 120,000.00 144,000.00
2 Tukang Batu L.02 OH 0.2000 150,000.00 30,000.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH 0.0300 140,000.00 4,200.00
JUMLAH TENAGA KERJA 181,700.00
B BAHAN
1 Bata Merah buah 140.0000 1,250.00 175,000.00
2 Semen Portland kg 32.9500 1,200.00 39,540.00
3 Pasir Pasang m3 0.0910 137,500.00 12,512.50

JUMLAH HARGA BAHAN 227,052.50


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 408,752.50


E OVERHEAD & PROFIT 10% X D 40,875.25
F HARGA SATUAN PEKERJAAN (D+E) 449,627.75

58 A.4.4.1.3 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 bata campuran 1 SP : 4 PP

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.6000 120,000.00 72,000.00
2 Tukang Batu L.02 OH 0.2000 150,000.00 30,000.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH 0.0300 140,000.00 4,200.00
JUMLAH TENAGA KERJA 109,700.00
B BAHAN
1 Bata Merah buah 140.0000 1,250.00 175,000.00
2 Semen Portland kg 26.5500 1,200.00 31,860.00
3 Pasir Pasang m3 0.0930 137,500.00 12,787.50
JUMLAH HARGA BAHAN 219,647.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH )A+B+C) 329,347.50
E OVERHEAD & PROFIT 10% X D 32,934.75
F HARGA SATUAN PEKERJAAN (D+E) 362,282.25

59 A.4.4.1.8 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 bata campuran 1 SP : 3 PP

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3000 120,000.00 36,000.00
2 Tukang Batu L.02 OH 0.1000 150,000.00 15,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 54,850.00
B BAHAN
1 Bata Merah buah 70.0000 1,250.00 87,500.00
2 Semen Portland kg 14.3700 1,200.00 17,244.00
3 Pasir Pasang m3 0.0400 137,500.00 5,500.00
JUMLAH HARGA BAHAN 110,244.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH )A+B+C) 165,094.00
E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 165,094.00

60 A.4.4.1.8 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 bata campuran 1 SP : 4 PP

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3000 120,000.00 36,000.00
2 Tukang Batu L.02 OH 0.1000 150,000.00 15,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 54,850.00
B BAHAN
1 Bata Merah buah 70.0000 1,250.00 87,500.00
2 Semen Portland kg 11.5000 1,200.00 13,800.00
3 Pasir Pasang m3 0.0430 137,500.00 5,912.50
JUMLAH HARGA BAHAN 107,212.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH )A+B+C) 162,062.50
E OVERHEAD & PROFIT 10% X D 16,206.25
F HARGA SATUAN PEKERJAAN (D+E) 178,268.75

11 A.4.4.1.9 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 bata campuran 1 SP : 5 PP

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3000 120,000.00 36,000.00
2 Tukang Batu L.02 OH 0.1000 150,000.00 15,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 54,850.00
B BAHAN
1 Bata Merah buah 70.0000 1,250.00 87,500.00
2 Semen Portland kg 9.6800 1,200.00 11,616.00
3 Pasir Pasang m3 0.0450 137,500.00 6,187.50
JUMLAH HARGA BAHAN 105,303.50
C PERALATAN
JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 160,153.50


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 160,153.50

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

62 A.4.4.2.1 Pemasangan 1 m2 plesteran campuran 1 SP : 1 PP tebal 15 mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3000 120,000.00 36,000.00
2 Tukang Batu L.02 OH 0.1500 150,000.00 22,500.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 63,225.00
B BAHAN

1 Semen Portland kg 15.5040 1,200.00 18,604.80


2 Pasir Pasang m3 0.0160 137,500.00 2,200.00

JUMLAH HARGA BAHAN 20,804.80


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 84,029.80


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 84,029.80

63 A.4.4.2.2 Pemasangan 1 m2 plesteran campuran 1 SP : 2 PP tebal 15 mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3000 120,000.00 36,000.00
2 Tukang Batu L.02 OH 0.1500 150,000.00 22,500.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 63,225.00
B BAHAN

1 Semen Portland kg 10.2240 1,200.00 12,268.80


2 Pasir Pasang m3 0.0200 137,500.00 2,750.00

JUMLAH HARGA BAHAN 15,018.80


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH )A+B+C) 78,243.80
E OVERHEAD & PROFIT 10% X D 7,824.38
F HARGA SATUAN PEKERJAAN (D+E) 86,068.18

64 A.4.4.2.3 Pemasangan 1 m2 plesteran campuran 1 SP : 3 PP tebal 15 mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3000 120,000.00 36,000.00
2 Tukang Batu L.02 OH 0.1500 150,000.00 22,500.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 63,225.00
B BAHAN

1 Semen Portland kg 7.7760 1,200.00 9,331.20


2 Pasir Pasang m3 0.0230 137,500.00 3,162.50

JUMLAH HARGA BAHAN 12,493.70


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 75,718.70


E OVERHEAD & PROFIT 10% X D 7,571.87
F HARGA SATUAN PEKERJAAN (D+E) 83,290.57

65 A.4.4.2.4 Pemasangan 1 m2 plesteran campuran 1 SP : 4 PP tebal 15 mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3000 120,000.00 36,000.00
2 Tukang Batu L.02 OH 0.1500 150,000.00 22,500.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 63,225.00
B BAHAN
1 Semen Portland kg 6.2400 1,200.00 7,488.00
2 Pasir Pasang m3 0.0240 137,500.00 3,300.00
JUMLAH HARGA BAHAN 10,788.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 74,013.00


E OVERHEAD & PROFIT 10% X D 7,401.30
F HARGA SATUAN PEKERJAAN (D+E) 81,414.30

12 A.4.4.2.5 Pemasangan 1 m2 plesteran campuran 1 SP : 5 PP tebal 15 mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)
A TENAGA
1 Pekerja L.01 OH 0.3000 120,000.00 36,000.00
2 Tukang Batu L.02 OH 0.1500 150,000.00 22,500.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 63,225.00
B BAHAN
1 Semen Portland kg 5.1840 1,200.00 6,220.80
2 Pasir Pasang m3 0.0260 137,500.00 3,575.00
JUMLAH HARGA BAHAN 9,795.80
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 73,020.80


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 73,020.80

67 A.4.4.2.24 Pemasangan 1 m2 finishing siar pasangan bata merah

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1500 120,000.00 18,000.00
2 Tukang Batu L.02 OH 0.0750 150,000.00 11,250.00
3 Kepala Tukang L.03 OH 0.0080 175,000.00 1,400.00
4 Mandor L.04 OH 0.0080 140,000.00 1,120.00
JUMLAH TENAGA KERJA 31,770.00
B BAHAN
1 Semen Portland kg 3.1080 1,200.00 3,729.60
JUMLAH HARGA BAHAN 3,729.60
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 35,499.60


E OVERHEAD & PROFIT 10% X D 3,549.96
F HARGA SATUAN PEKERJAAN (D+E) 39,049.56

68 A.4.4.2.25 Pemasangan 1 m2 finishing siar pasangan batu kali

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3000 120,000.00 36,000.00
2 Tukang Batu L.02 OH 0.1500 150,000.00 22,500.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0150 140,000.00 2,100.00
JUMLAH TENAGA KERJA 63,225.00
B BAHAN
1 Semen Portland kg 6.3400 1,200.00 7,608.00
2 Pasir Pasang m3 0.0120 137,500.00 1,650.00

JUMLAH HARGA BAHAN 9,258.00


C PERALATAN
JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 72,483.00


E OVERHEAD & PROFIT 10% X D 7,248.30
F HARGA SATUAN PEKERJAAN (D+E) 79,731.30
13 A.4.4.2.26 Pemasangan 1 m2 acian

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2000 120,000.00 24,000.00
2 Tukang Batu L.02 OH 0.1000 150,000.00 15,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0100 140,000.00 1,400.00
JUMLAH TENAGA KERJA 42,150.00
B BAHAN

1 Semen Portland kg 3.2500 1,200.00 3,900.00

JUMLAH HARGA BAHAN 3,900.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 46,050.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 46,050.00

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

14 A.4.4.3.1 Pemasangan 1 m2 lantai Keramik PC Putih ukuran 40 cm x 40 cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2500 120,000.00 30,000.00
2 Tukang Batu L.02 OH 0.1250 150,000.00 18,750.00
3 Kepala Tukang L.03 OH 0.0130 175,000.00 2,275.00
4 Mandor L.04 OH 0.0130 140,000.00 1,820.00
JUMLAH TENAGA KERJA 52,845.00
B BAHAN

1 Ubin Abu-abu bh 6.6300 12,820.51 85,000.00


2 Semen Portland kg 9.8000 1,200.00 11,760.00
3 Pasir Pasang m3 0.0450 137,500.00 6,187.50

JUMLAH HARGA BAHAN 102,947.50


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 155,792.50


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 155,792.50
71 A.4.4.3.2 Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 30 cm x 30 cm antislip

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2500 120,000.00 30,000.00
2 Tukang Batu L.02 OH 0.1250 150,000.00 18,750.00
3 Kepala Tukang L.03 OH 0.0130 175,000.00 2,275.00
4 Mandor L.04 OH 0.0130 140,000.00 1,820.00
JUMLAH TENAGA KERJA 52,845.00
B BAHAN

1 Ubin Abu-abu bh 11.8700 7,160.91 85,000.00


2 Semen Portland kg 10.0000 1,200.00 12,000.00
3 Pasir Pasang m3 0.0450 137,500.00 6,187.50

JUMLAH HARGA BAHAN 103,187.50


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 156,032.50


E OVERHEAD & PROFIT 10% X D 15,603.25
F HARGA SATUAN PEKERJAAN (D+E) 171,635.75

15 A.4.4.3.3 Pemasangan 1 m2 lantai keramik ukuran 20 cm x 20 cm antislip

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2500 120,000.00 30,000.00
2 Tukang Batu L.02 OH 0.1250 150,000.00 18,750.00
3 Kepala Tukang L.03 OH 0.0130 175,000.00 2,275.00
4 Mandor L.04 OH 0.0130 140,000.00 1,820.00
JUMLAH TENAGA KERJA 52,845.00
B BAHAN

1 Ubin Abu-abu bh 26.5000 3,396.23 90,000.00


2 Semen Portland kg 10.4000 1,200.00 12,480.00
3 Pasir Pasang m3 0.0450 137,500.00 6,187.50

JUMLAH HARGA BAHAN 108,667.50


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 161,512.50


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 161,512.50

73 A.4.4.3.17 Pemasangan 1 m1 plint ubin PC abu-abu ukuran 10 cm x 30 cm


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0900 120,000.00 10,800.00
2 Tukang Batu L.02 OH 0.0900 150,000.00 13,500.00
3 Kepala Tukang L.03 OH 0.0090 175,000.00 1,575.00
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 26,575.00
B BAHAN

1 Plint Abu-abu PC bh 3.3500 1,347.94 4,515.59


2 Semen Portland kg 1.2400 1,200.00 1,488.00
3 Pasir Pasang m3 0.0030 137,500.00 412.50

JUMLAH HARGA BAHAN 6,416.09


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 32,991.09


E OVERHEAD & PROFIT 10% X D 3,299.11
F HARGA SATUAN PEKERJAAN (D+E) 36,290.19

16 A.4.4.3.18 Pemasangan 1 m1 plint ubin PC abu-abu ukuran 10 cm x 40 cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0900 120,000.00 10,800.00
2 Tukang Batu L.02 OH 0.0900 150,000.00 13,500.00
3 Kepala Tukang L.03 OH 0.0090 175,000.00 1,575.00
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 26,575.00
B BAHAN

1 Plint Abu-abu PC bh 2.6500 14,166.67 37,541.67


2 Semen Portland kg 1.2400 1,200.00 1,488.00
3 Pasir Pasang m3 0.0030 137,500.00 412.50

JUMLAH HARGA BAHAN 39,442.17


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 66,017.17


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 66,017.17
75 A.4.4.3.44 Pemasangan 1 m2 lantai karpet

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1700 120,000.00 20,400.00
2 Tukang Batu L.02 OH 0.1700 150,000.00 25,500.00
3 Kepala Tukang L.03 OH 0.0170 175,000.00 2,975.00
4 Mandor L.04 OH 0.0090 140,000.00 1,260.00
JUMLAH TENAGA KERJA 50,135.00
B BAHAN

1 Karpet m2 1.0500 170,000.00 178,500.00


2 Lam Kg 0.3500 25,000.00 8,750.00

JUMLAH HARGA BAHAN 187,250.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 237,385.00


E OVERHEAD & PROFIT 10% X D 23,738.50
F HARGA SATUAN PEKERJAAN (D+E) 261,123.50

76 A.4.4.3.46 Pemasangan 1 m2 lantai parquet kayu

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.7000 120,000.00 84,000.00
2 Tukang Kayu L.02 OH 0.3500 160,000.00 56,000.00
3 Kepala Tukang L.03 OH 0.0350 175,000.00 6,125.00
4 Mandor L.04 OH 0.0350 140,000.00 4,900.00
JUMLAH TENAGA KERJA 151,025.00
B BAHAN

1 Parquet m2 1.0500 165,662.65 173,945.78


2 Lam Kg 0.6000 32,500.00 19,500.00

JUMLAH HARGA BAHAN 193,445.78


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 344,470.78


E OVERHEAD & PROFIT 10% X D 34,447.08
F HARGA SATUAN PEKERJAAN (D+E) 378,917.86

17 A.4.4.3.53 Pemasangan 1 m2 Dinding Keramik 20 cm x 25 cm


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.4000 120,000.00 48,000.00
2 Tukang Batu L.02 OH 0.2000 150,000.00 30,000.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH 0.0200 140,000.00 2,800.00
JUMLAH TENAGA KERJA 84,300.00
B BAHAN

1 Keramik Artistik 20 x 25 bh 22.0000 3,600.00 79,200.00


2 Semen Portland kg 9.3000 1,200.00 11,160.00
3 Semen Warna kg 2.7500 3,375.00 9,281.25
4 Pasir Pasang m3 0.0180 137,500.00 2,475.00

JUMLAH HARGA BAHAN 102,116.25


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 186,416.25


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 186,416.25

78 A.4.4.3.54 Pemasangan 1 m2 Dinding Keramik 30 cm x 60 cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.9000 120,000.00 108,000.00
2 Tukang Batu L.02 OH 0.4500 150,000.00 67,500.00
3 Kepala Tukang L.03 OH 0.0450 175,000.00 7,875.00
4 Mandor L.04 OH 0.0450 140,000.00 6,300.00
JUMLAH TENAGA KERJA 189,675.00
B BAHAN

1 Keramik Artistik 30 x 60 bh 6.6000 20,833.33 137,500.00


2 Semen Portland kg 9.3000 1,200.00 11,160.00
3 Semen Warna kg 1.9400 3,375.00 6,547.50
4 Pasir Pasang m3 0.0180 137,500.00 2,475.00

JUMLAH HARGA BAHAN 157,682.50


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 347,357.50


E OVERHEAD & PROFIT 10% X D 34,735.75
F HARGA SATUAN PEKERJAAN (D+E) 382,093.25

18 A.4.4.3.64 Pemasangan 1 m2 paving block natural tebal 6 cm


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2500 120,000.00 30,000.00
2 Tukang Batu L.02 OH 0.5000 150,000.00 75,000.00
3 Kepala Tukang L.03 OH 0.0500 175,000.00 8,750.00
4 Mandor L.04 OH 0.0013 140,000.00 182.00
JUMLAH TENAGA KERJA 113,932.00
B BAHAN

1 Paving block 6 cm m2 1.0100 94,600.00 95,546.00


2 Pasir Beton m3 0.0500 137,500.00 6,875.00

JUMLAH HARGA BAHAN 102,421.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 216,353.00


E OVERHEAD & PROFIT 10% X D 21,635.30
F HARGA SATUAN PEKERJAAN (D+E) 237,988.30
19 A.4.4.3.66 Pemasangan 1 m2 paving block warna tebal 6 cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2500 120,000.00 30,000.00
2 Tukang Batu L.02 OH 0.5000 150,000.00 75,000.00
3 Kepala Tukang L.03 OH 0.0500 175,000.00 8,750.00
4 Mandor L.04 OH 0.0013 140,000.00 182.00
JUMLAH TENAGA KERJA 113,932.00
B BAHAN

1 Paving block 6 cm m2 1.0100 107,500.00 108,575.00


2 Pasir Beton m3 0.0500 137,500.00 6,875.00

JUMLAH HARGA BAHAN 115,450.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 229,382.00


E OVERHEAD & PROFIT 10% X D 22,938.20
F HARGA SATUAN PEKERJAAN (D+E) 252,320.20

A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

81 A.4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120X240) cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2500 120,000.00 30,000.00
2 Tukang kayu L.02 OH 0.5000 160,000.00 80,000.00
3 Kepala Tukang L.03 OH 0.0500 175,000.00 8,750.00
4 Mandor L.04 OH 0.0013 140,000.00 182.00
JUMLAH TENAGA KERJA 118,932.00
B BAHAN

1 Tripleks 2,7 mm lembar 0.3750 55,000.00 20,625.00


2 Paku tripleks kg 0.0300 20,000.00 600.00

JUMLAH HARGA BAHAN 21,225.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 140,157.00


E OVERHEAD & PROFIT 10% X D 14,015.70
F HARGA SATUAN PEKERJAAN (D+E) 154,172.70

82 A.4.5.1.6 Pemasangan 1 m2 langit-langit lambrisering kayu tebal 9 mm


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.8000 120,000.00 96,000.00
2 Tukang kayu L.02 OH 0.8000 160,000.00 128,000.00
3 Kepala Tukang L.03 OH 0.0800 175,000.00 14,000.00
4 Mandor L.04 OH 0.0400 140,000.00 5,600.00
JUMLAH TENAGA KERJA 243,600.00
B BAHAN

1 Kayu papan m3 0.0150 5,000,000.00 75,000.00


2 Paku tripleks kg 0.0100 20,000.00 200.00

JUMLAH HARGA BAHAN 75,200.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 318,800.00


E OVERHEAD & PROFIT 10% X D 31,880.00
F HARGA SATUAN PEKERJAAN (D+E) 350,680.00

20 A.4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120X240) cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1000 120,000.00 12,000.00
2 Tukang kayu L.02 OH 0.1000 160,000.00 16,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 30,450.00
B BAHAN

1 Tripleks 4 mm lembar 0.3750 75,500.00 28,312.50


2 Paku tripleks kg 0.0300 30,000.00 900.00

JUMLAH HARGA BAHAN 29,212.50


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 59,662.50


E OVERHEAD & PROFIT 10% X D 5,966.25
F HARGA SATUAN PEKERJAAN (D+E) 65,628.75
A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

84 A.4.5.2.32 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2000 120,000.00 24,000.00
2 Tukang kayu L.02 OH 0.1000 160,000.00 16,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0010 140,000.00 140.00
JUMLAH TENAGA KERJA 41,890.00
B BAHAN

1 Genteng Metal 3 mm buah 1.3000 33,000.00 42,900.00


2 Paku biasa kg 0.2000 18,000.00 3,600.00

JUMLAH HARGA BAHAN 46,500.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 88,390.00


E OVERHEAD & PROFIT 10% X D 8,839.00
F HARGA SATUAN PEKERJAAN (D+E) 97,229.00

85 A.4.5.2.33 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2000 120,000.00 24,000.00
2 Tukang kayu L.02 OH 0.1000 160,000.00 16,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0010 140,000.00 140.00
JUMLAH TENAGA KERJA 41,890.00
B BAHAN

1 Genteng Metal 3 mm buah 2.0000 33,000.00 66,000.00


2 Paku biasa kg 0.2000 18,000.00 3,600.00

JUMLAH HARGA BAHAN 69,600.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 111,490.00


E OVERHEAD & PROFIT 10% X D 11,149.00
F HARGA SATUAN PEKERJAAN (D+E) 122,639.00

86 A.4.5.2.37 Pemasangan 1 m1 nok genteng metal


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2500 120,000.00 30,000.00
2 Tukang kayu L.02 OH 0.1500 160,000.00 24,000.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0130 140,000.00 1,820.00
JUMLAH TENAGA KERJA 58,445.00
B BAHAN

1 Nok Genteng Metal buah 1.1000 32,000.00 35,200.00


2 Paku biasa kg 0.0500 18,000.00 900.00

JUMLAH HARGA BAHAN 36,100.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 94,545.00


E OVERHEAD & PROFIT 10% X D 9,454.50
F HARGA SATUAN PEKERJAAN (D+E) 103,999.50

21 A.4.5.2.39 Pemasangan 1 m2 atap seng Alumunium gelombang

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1200 120,000.00 14,400.00
2 Tukang kayu L.02 OH 0.0600 160,000.00 9,600.00
3 Kepala Tukang L.03 OH 0.0060 175,000.00 1,050.00
4 Mandor L.04 OH 0.0060 140,000.00 840.00
JUMLAH TENAGA KERJA 25,890.00
B BAHAN

1 Seng alumunium 3"x6" Lembar 0.7000 55,000.00 38,500.00


2 Paku biasa kg 0.0200 18,000.00 360.00

JUMLAH HARGA BAHAN 38,860.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 64,750.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 64,750.00

22 A.4.5.2.37 Pemasangan 1 m1 nok alumunium

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1500 120,000.00 18,000.00
2 Tukang kayu L.02 OH 0.0500 160,000.00 8,000.00
3 Kepala Tukang L.03 OH 0.0050 175,000.00 875.00
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 27,575.00
B BAHAN

1 alumunium lbr 0.3000 55,000.00 16,500.00


2 Paku biasa kg 0.0400 18,000.00 720.00

JUMLAH HARGA BAHAN 17,220.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 44,795.00


E OVERHEAD & PROFIT 10% X D 4,479.50
F HARGA SATUAN PEKERJAAN (D+E) 49,274.50
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU

22 A.4.6.1.1 Pembuatan dan Pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 6.5000 120,000.00 780,000.00
2 Tukang kayu L.02 OH 18.0000 160,000.00 2,880,000.00
3 Kepala Tukang L.03 OH 1.8000 175,000.00 315,000.00
4 Mandor L.04 OH 1.3000 140,000.00 182,000.00
JUMLAH TENAGA KERJA 4,157,000.00
B BAHAN

1 Balok Kayu m3 1.2000 5,000,000.00 6,000,000.00


2 Paku 10 cm kg 1.2500 15,000.00 18,750.00
3 Lem kayu kg 1.0000 40,000.00 40,000.00

JUMLAH HARGA BAHAN 6,058,750.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 10,215,750.00


E OVERHEAD & PROFIT 10% X D 1,021,575.00
F HARGA SATUAN PEKERJAAN (D+E) 11,237,325.00

90 A.4.6.1.2 Pembuatan dan Pemasangan 1 m2 pintu klamp standar, kayu kelas II

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.3500 120,000.00 42,000.00
2 Tukang kayu L.02 OH 1.0500 160,000.00 168,000.00
3 Kepala Tukang L.03 OH 0.1050 175,000.00 18,375.00
4 Mandor L.04 OH 0.0180 140,000.00 2,520.00
JUMLAH TENAGA KERJA 230,895.00
B BAHAN

1 Papan Kayu m3 0.0400 5,000,000.00 200,000.00


2 Paku 5-7 cm kg 0.0500 18,000.00 900.00

JUMLAH HARGA BAHAN 200,900.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 431,795.00


E OVERHEAD & PROFIT 10% X D 43,179.50
F HARGA SATUAN PEKERJAAN (D+E) 474,974.50
23 A.4.6.1.5 Pembuatan dan Pemasangan 1 m2 daun pintu panel, kayu kelas II

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.2000 120,000.00 144,000.00
2 Tukang kayu L.02 OH 3.0000 160,000.00 480,000.00
3 Kepala Tukang L.03 OH 0.3000 175,000.00 52,500.00
4 Mandor L.04 OH 0.0500 140,000.00 7,000.00
JUMLAH TENAGA KERJA 683,500.00
B BAHAN

1 Papan Kayu m3 0.0800 5,000,000.00 400,000.00


2 Paku 5-7 cm kg 0.0500 18,000.00 900.00
3 Lem kayu kg 0.5000 40,000.00 20,000.00

JUMLAH HARGA BAHAN 420,900.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 1,104,400.00


E OVERHEAD & PROFIT 10% X D 110,440.00
F HARGA SATUAN PEKERJAAN (D+E) 1,214,840.00
24 A.4.6.1.6 Pembuatan dan Pemasangan 1 m2 pintu dan jendela kaca, kayu kelas II

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.8000 120,000.00 96,000.00
2 Tukang kayu L.02 OH 2.4000 160,000.00 384,000.00
3 Kepala Tukang L.03 OH 0.2400 175,000.00 42,000.00
4 Mandor L.04 OH 0.0400 140,000.00 5,600.00
JUMLAH TENAGA KERJA 527,600.00
B BAHAN

1 Papan Kayu m3 0.0240 5,000,000.00 120,000.00


2 Lem kayu kg 0.3000 40,000.00 12,000.00

JUMLAH HARGA BAHAN 132,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 659,600.00


E OVERHEAD & PROFIT 10% X D 65,960.00
F HARGA SATUAN PEKERJAAN (D+E) 725,560.00

25 A.4.6.1.6 Pembuatan dan Pemasangan 1 m2 pintu double tripleks + alumunium ,rangka kayu kelas II

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.0000 120,000.00 120,000.00
2 Tukang kayu L.02 OH 2.5000 160,000.00 400,000.00
3 Kepala Tukang L.03 OH 0.2500 175,000.00 43,750.00
4 Mandor L.04 OH 0.0500 140,000.00 7,000.00
JUMLAH TENAGA KERJA 570,750.00
B BAHAN

1 Papan Kayu klas II m3 0.0240 5,000,000.00 120,000.00


2 Tripleks 4mm lembar 0.8330 75,500.00 62,891.50
3 seng plat lembar 0.8330 57,500.00 47,897.50
3 Lem kayu kg 0.3000 15,000.00 4,500.00

JUMLAH HARGA BAHAN 235,289.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 806,039.00


E OVERHEAD & PROFIT 10% X D 80,603.90
F HARGA SATUAN PEKERJAAN (D+E) 886,642.90

25 A.4.6.1.6 Pembuatan dan Pemasangan 1 m2 pintu double tripleks ,rangka kayu kelas II
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 TENAGA 0 OH 1.0000 120,000.00 120,000.00
2 Pekerja L.01 OH 2.5000 160,000.00 400,000.00
3 Tukang kayu L.02 OH 0.2500 175,000.00 43,750.00
4 Kepala Tukang L.03 OH 0.0500 140,000.00 7,000.00
JUMLAH TENAGA KERJA 570,750.00
B BAHAN

1 Papan Kayu klas II m3 0.0240 5,000,000.00 120,000.00


2 Tripleks 4mm lembar 0.8330 75,500.00 62,891.50
3 Lem kayu kg 0.3000 18,000.00 5,400.00

JUMLAH HARGA BAHAN 188,291.50


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 759,041.50


E OVERHEAD & PROFIT 10% X D 75,904.15
F HARGA SATUAN PEKERJAAN (D+E) 834,945.65
93 A.4.6.1.13 Pembuatan 1 m3 konstruksi kuda-kuda konvensional bentang 6 meter

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 4.0000 120,000.00 480,000.00
2 Tukang kayu L.02 OH 12.0000 160,000.00 1,920,000.00
3 Kepala Tukang L.03 OH 1.2000 175,000.00 210,000.00
4 Mandor L.04 OH 0.2000 140,000.00 28,000.00
JUMLAH TENAGA KERJA 2,638,000.00
B BAHAN

1 Balok kayu kelas II m3 1.1000 5,000,000.00 5,500,000.00


2 Besi Strip tebal 5 mm kg 15.0000 17,000.00 255,000.00
3 Paku 12 cm kg 5.6000 15,000.00 84,000.00

JUMLAH HARGA BAHAN 5,839,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 8,477,000.00


E OVERHEAD & PROFIT 10% X D 847,700.00
F HARGA SATUAN PEKERJAAN (D+E) 9,324,700.00

94 A.4.6.1.19 Pembuatan 1 m2 rangka langit-langit (50x100) cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1500 120,000.00 18,000.00
2 Tukang kayu L.02 OH 0.3000 160,000.00 48,000.00
3 Kepala Tukang L.03 OH 0.0300 175,000.00 5,250.00
4 Mandor L.04 OH 0.0750 140,000.00 10,500.00
JUMLAH TENAGA KERJA 81,750.00
B BAHAN

1 Kaso 5/7 kayu kelas III m3 0.0154 2,750,000.00 42,350.00


3 Paku 12 cm kg 0.2000 15,000.00 3,000.00

JUMLAH HARGA BAHAN 45,350.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 127,100.00


E OVERHEAD & PROFIT 10% X D 12,710.00
F HARGA SATUAN PEKERJAAN (D+E) 139,810.00

95 A.4.6.1.20 Pembuatan 1 m2 rangka langit-langit (60x60) cm


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2000 120,000.00 24,000.00
2 Tukang kayu L.02 OH 0.3000 160,000.00 48,000.00
3 Kepala Tukang L.03 OH 0.0300 175,000.00 5,250.00
4 Mandor L.04 OH 0.0100 140,000.00 1,400.00
JUMLAH TENAGA KERJA 78,650.00
B BAHAN

1 Kaso 5/7 kayu kelas III m3 0.0163 2,750,000.00 44,825.00


3 Paku 12 cm kg 0.2500 15,000.00 3,750.00

JUMLAH HARGA BAHAN 48,575.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 127,225.00


E OVERHEAD & PROFIT 10% X D 12,722.50
F HARGA SATUAN PEKERJAAN (D+E) 139,947.50

96 A.4.6.1.21 Pemasangan 1 m' lisplank uk (3 x 20 )cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1000 120,000.00 12,000.00
2 Tukang kayu L.02 OH 0.2000 160,000.00 32,000.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 48,200.00
B BAHAN

1 Papan Kayu Kls II m3 0.0108 5,000,000.00 54,000.00


3 Paku 5-7 cm kg 0.1000 18,000.00 1,800.00

JUMLAH HARGA BAHAN 55,800.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 104,000.00


E OVERHEAD & PROFIT 10% X D 10,400.00
F HARGA SATUAN PEKERJAAN (D+E) 114,400.00

26 A.4.6.1.22 Pemasangan 1 m' lisplank uk (3 x 30 )cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)
A TENAGA
1 Pekerja L.01 OH 0.1000 120,000.00 12,000.00
2 Tukang kayu L.02 OH 0.2000 160,000.00 32,000.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 48,200.00
B BAHAN

1 papan GRC 30 cm m1 1.1000 25,000.00 27,500.00


3 Baut kg 0.0500 18,000.00 900.00

JUMLAH HARGA BAHAN 28,400.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 76,600.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 76,600.00

98 A.4.6.1.23 Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1500 120,000.00 18,000.00
2 Tukang kayu L.02 OH 0.4500 160,000.00 72,000.00
3 Kepala Tukang L.03 OH 0.0450 175,000.00 7,875.00
4 Mandor L.04 OH 0.0080 140,000.00 1,120.00
JUMLAH TENAGA KERJA 98,995.00
B BAHAN

1 Balok Kayu Kelas II m3 0.0280 25,000.00 700.00


3 Paku 5-7 cm kg 0.1500 18,000.00 2,700.00

JUMLAH HARGA BAHAN 3,400.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 102,395.00


E OVERHEAD & PROFIT 10% X D 10,239.50
F HARGA SATUAN PEKERJAAN (D+E) 112,634.50

99 A.4.6.1.25 Pemasangan 1 m2 dinding pemisah plywood rangkap

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2000 120,000.00 24,000.00
2 Tukang kayu L.02 OH 0.6000 160,000.00 96,000.00
3 Kepala Tukang L.03 OH 0.0600 175,000.00 10,500.00
4 Mandor L.04 OH 0.0100 140,000.00 1,400.00
JUMLAH TENAGA KERJA 131,900.00
B BAHAN

1 Balok Kayu Kelas II m3 0.0280 25,000.00 700.00


2 Paku 5-10 cm kg 0.1500 18,000.00 2,700.00
3 Plywood 4 mm 120x240 lembar 0.8600 115,000.00 98,900.00
4 Lem Kayu kg 0.5600 40,000.00 22,400.00

JUMLAH HARGA BAHAN 124,700.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 256,600.00


E OVERHEAD & PROFIT 10% X D 25,660.00
F HARGA SATUAN PEKERJAAN (D+E) 282,260.00

100 A.4.6.1.26 Pemasangan 1 m2 dinding lambrisering

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.6000 120,000.00 72,000.00
2 Tukang kayu L.02 OH 1.8000 160,000.00 288,000.00
3 Kepala Tukang L.03 OH 0.1800 175,000.00 31,500.00
4 Mandor L.04 OH 0.0300 140,000.00 4,200.00
JUMLAH TENAGA KERJA 395,700.00
B BAHAN

1 Papan Kayu Kelas II m3 0.0070 25,000.00 175.00


2 Paku 5-10 cm kg 0.1000 18,000.00 1,800.00
3 Paku skrup kg 0.1500 30,000.00 4,500.00

JUMLAH HARGA BAHAN 6,475.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 402,175.00


E OVERHEAD & PROFIT 10% X D 40,217.50
F HARGA SATUAN PEKERJAAN (D+E) 442,392.50

A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

27 A.4.6.2.2 Pemasangan 1 buah kunci tanam biasa


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0100 120,000.00 1,200.00
2 Tukang kayu L.02 OH 0.5000 160,000.00 80,000.00
3 Kepala Tukang L.03 OH 0.0500 175,000.00 8,750.00
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 90,650.00
B BAHAN

1 Kunci tanam biasa 2 slag bh 1.0000 120,000.00 120,000.00

JUMLAH HARGA BAHAN 120,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 210,650.00


E OVERHEAD & PROFIT 10% X D 21,065.00
F HARGA SATUAN PEKERJAAN (D+E) 231,715.00
28 A.4.6.2.5 Pemasangan 1 buah engsel pintu

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0150 120,000.00 1,800.00
2 Tukang kayu L.02 OH 0.1500 160,000.00 24,000.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0008 140,000.00 112.00
JUMLAH TENAGA KERJA 28,537.00
B BAHAN

1 Engsel pintu bh 1.0000 22,500.00 22,500.00

JUMLAH HARGA BAHAN 22,500.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 51,037.00


E OVERHEAD & PROFIT 10% X D 5,103.70
F HARGA SATUAN PEKERJAAN (D+E) 56,140.70

29 A.4.6.2.6 Pemasangan 1 buah engsel Jendela Kupu-kupu besar

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0100 120,000.00 1,200.00
2 Tukang kayu L.02 OH 0.1000 160,000.00 16,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0005 140,000.00 70.00
JUMLAH TENAGA KERJA 19,020.00
B BAHAN

1 Engsel kupu-kupu besar bh 1.0000 12,000.00 12,000.00

JUMLAH HARGA BAHAN 12,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 31,020.00


E OVERHEAD & PROFIT 10% X D 3,102.00
F HARGA SATUAN PEKERJAAN (D+E) 34,122.00
30 A.4.6.2.7 Pemasangan 1 buah kait angin

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0150 120,000.00 1,800.00
2 Tukang kayu L.02 OH 0.1500 160,000.00 24,000.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0008 140,000.00 112.00
JUMLAH TENAGA KERJA 28,537.00
B BAHAN

1 Kait angin bh 1.0000 17,500.00 17,500.00

JUMLAH HARGA BAHAN 17,500.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 46,037.00


E OVERHEAD & PROFIT 10% X D 4,603.70
F HARGA SATUAN PEKERJAAN (D+E) 50,640.70

105 A.4.6.2.16 Pemasangan 1 m2 kaca tebal 3 mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0150 120,000.00 1,800.00
2 Tukang kayu L.02 OH 0.1500 160,000.00 24,000.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0008 140,000.00 112.00
JUMLAH TENAGA KERJA 28,537.00
B BAHAN

1 Kaca tebal 3 mm m2 1.1000 100,000.00 110,000.00


2 Sealant tube 0.0500 45,000.00 2,250.00

JUMLAH HARGA BAHAN 112,250.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 140,787.00


E OVERHEAD & PROFIT 10% X D 14,078.70
F HARGA SATUAN PEKERJAAN (D+E) 154,865.70

31 A.4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)
A TENAGA
1 Pekerja L.01 OH 0.0150 120,000.00 1,800.00
2 Tukang kayu L.02 OH 0.1500 160,000.00 24,000.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0008 140,000.00 112.00
JUMLAH TENAGA KERJA 28,537.00
B BAHAN

1 Kaca tebal 5 mm m2 1.1000 150,000.00 165,000.00


2 Sealant tube 0.0500 45,000.00 2,250.00

JUMLAH HARGA BAHAN 167,250.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 195,787.00


E OVERHEAD & PROFIT 10% X D 19,578.70
F HARGA SATUAN PEKERJAAN (D+E) 215,365.70
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

107 A.4.7.1.1 1 m2 pengikisan/pengerokan permukaan cat lama

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1500 120,000.00 18,000.00
2 Tukang kayu L.02 OH - 160,000.00 -
3 Kepala Tukang L.03 OH - 175,000.00 -
4 Mandor L.04 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 18,420.00
B BAHAN

1 Soda api kg 0.0500 35,000.00 1,750.00

JUMLAH HARGA BAHAN 1,750.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 20,170.00


E OVERHEAD & PROFIT 10% X D 2,017.00
F HARGA SATUAN PEKERJAAN (D+E) 22,187.00

32 A.4.7.1.4 1 m2 pengecatan bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0700 120,000.00 8,400.00
2 Tukang cat L.02 OH 0.0090 150,000.00 1,350.00
3 Kepala Tukang L.03 OH 0.0060 175,000.00 1,050.00
4 Mandor L.04 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 11,220.00
B BAHAN

1 Cat manie kg 0.2000 33,000.00 6,600.00


2 Plamuur kg 0.1500 45,000.00 6,750.00
3 Cat dasar kg 0.1700 58,000.00 9,860.00
4 Cat penutup kg 0.2600 58,000.00 15,080.00
5 Kuas bh 0.0100 60,000.00 600.00
6 Pengencer kg 0.0300 20,000.00 600.00
7 Ampelas lbr 0.2000 15,000.00 3,000.00

JUMLAH HARGA BAHAN 42,490.00


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH )A+B+C) 53,710.00
E OVERHEAD & PROFIT 10% X D 5,371.00
F HARGA SATUAN PEKERJAAN (D+E) 59,081.00

33 A.4.7.1.9 1 m2 Peleburan 1 m2 bidang kayu dengan vernis

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1600 120,000.00 19,200.00
2 Tukang cat L.02 OH 0.1600 150,000.00 24,000.00
3 Kepala Tukang L.03 OH 0.0160 175,000.00 2,800.00
4 Mandor L.04 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 46,420.00
B BAHAN

1 Vernis kg 0.1500 60,000.00 9,000.00


2 Dempul kg 0.0500 41,000.00 2,050.00
3 Ampelas lbr 0.1000 25,000.00 2,500.00

JUMLAH HARGA BAHAN 13,550.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 59,970.00


E OVERHEAD & PROFIT 10% X D 5,997.00
F HARGA SATUAN PEKERJAAN (D+E) 65,967.00
34 A.4.7.1.10 Pengecatan 1 m2 interior tembok baru ( 1 lapis cat dasar, 2 lapis cat penutup)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja 0 OH 0.0250 120,000.00 3,000.00
2 Tukang 0 OH 0.0750 150,000.00 11,250.00
3 Kepala Tukang 0 OH 0.0063 175,000.00 1,102.50
4 Mandor 0 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 15,772.50
B BAHAN
cat interior
1 Cat dasar kg 0.1500 45,000.00 6,750.00
2 Cat Penutup kg 0.2600 65,000.00 16,900.00

JUMLAH HARGA BAHAN 23,650.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 39,422.50


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 39,422.50

34 A.4.7.1.10 Pengecatan 1 m2 cat eksterior tembok baru ( 1 lapis cat dasar, 2 lapis cat penutup)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0500 120,000.00 6,000.00
2 Tukang cat L.02 OH 0.0750 150,000.00 11,250.00
3 Kepala Tukang L.03 OH 0.0063 175,000.00 1,102.50
4 Mandor L.04 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 18,772.50
B BAHAN
cat eksterior
1 Cat dasar kg 0.1500 65,000.00 9,750.00
2 Cat Penutup kg 0.2600 102,500.00 26,650.00

JUMLAH HARGA BAHAN 36,400.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 55,172.50


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 55,172.50

35 A.4.7.1.11 Pengecatan 1 m2 cat plafond ( 2 lapis cat penutup)


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0250 120,000.00 3,000.00
2 Tukang cat L.02 OH 0.0750 150,000.00 11,250.00
3 Kepala Tukang L.03 OH 0.0063 175,000.00 1,102.50
4 Mandor L.04 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 15,772.50
B BAHAN

cat interior
1 Cat dasar kg 0.1500 45,000.00 6,750.00
2 Cat Penutup kg 0.2600 65,000.00 16,900.00

JUMLAH HARGA BAHAN 23,650.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 39,422.50


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 39,422.50

112 A.4.7.1.15 Pemasangan 1 m2 wallpeper

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0200 120,000.00 2,400.00
2 Tukang cat L.02 OH 0.2000 150,000.00 30,000.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH 0.0025 140,000.00 350.00
JUMLAH TENAGA KERJA 36,250.00
B BAHAN

1 Wallpeper m2 1.2000 80,000.00 96,000.00


2 Lem kg 0.2000 32,500.00 6,500.00

JUMLAH HARGA BAHAN 102,500.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 138,750.00


E OVERHEAD & PROFIT 10% X D 13,875.00
F HARGA SATUAN PEKERJAAN (D+E) 152,625.00

113 A.4.7.1.18 Pengecatan 1 m2 permukaan baja galvanis secara manual 3 lapis


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.4000 120,000.00 48,000.00
2 Tukang cat L.02 OH 0.8000 150,000.00 120,000.00
3 Kepala Tukang L.03 OH 0.0800 175,000.00 14,000.00
4 Mandor L.04 OH 0.0200 140,000.00 2,800.00
JUMLAH TENAGA KERJA 184,800.00
B BAHAN
1 Cat dasar kg 0.1100 33,000.00 3,630.00
2 Cat antara kg 0.1700 60,000.00 10,200.00
3 Cat penutup kg 0.0800 58,000.00 4,640.00
4 Kuas bh 0.0100 60,000.00 600.00
5 Pengencer LTR 0.0100 20,000.00 200.00

JUMLAH HARGA BAHAN 19,270.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 204,070.00


E OVERHEAD & PROFIT 10% X D 20,407.00
F HARGA SATUAN PEKERJAAN (D+E) 224,477.00
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

114 A.5.1.1.1 (K3) Pemasangan Kloset Duduk / monoblock

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 3.3000 120,000.00 396,000.00
2 Tukang batu L.02 OH 1.1000 150,000.00 165,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.1600 140,000.00 22,400.00
JUMLAH TENAGA KERJA 585,150.00
B BAHAN

1 Closet duduk Unit 1.0000 1,800,000.00 1,800,000.00


2 Perlengkapan Ls 6%xcloset 108,000.00 108,000.00

JUMLAH HARGA BAHAN 1,908,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 2,493,150.00


E OVERHEAD & PROFIT 10% X D 249,315.00
F HARGA SATUAN PEKERJAAN (D+E) 2,742,465.00

36 A.5.1.1.2 Pemasangan 1 buah kloset duduk porselen

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.0000 120,000.00 120,000.00
2 Tukang batu L.02 OH 1.5000 150,000.00 225,000.00
3 Kepala Tukang L.03 OH 0.1500 175,000.00 26,250.00
4 Mandor L.04 OH 0.1600 140,000.00 22,400.00
JUMLAH TENAGA KERJA 393,650.00
B BAHAN

1 Closet duduk Unit 1.0000 1,800,000.00 1,800,000.00


2 Semen Portland Kg 6.0000 1,200.00 7,200.00
3 Pasir Pasang m3 0.0100 137,500.00 1,375.00

JUMLAH HARGA BAHAN 1,808,575.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 2,202,225.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 2,202,225.00

116 A.5.1.1.4 (K3) Pemasangan 1 buah jet shower


NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0100 120,000.00 1,200.00
2 Tukang batu L.02 OH 0.1000 150,000.00 15,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 18,650.00
B BAHAN

1 jet shower Unit 1.0000 125,000.00 125,000.00


2 Semen Portland Kg 6.0000 1,200.00 7,200.00
3 Pasir Pasang m3 0.0100 137,500.00 1,375.00
4 Perlengkapan % 30.0000 37,500.00 37,500.00

JUMLAH HARGA BAHAN 171,075.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 189,725.00


E OVERHEAD & PROFIT 10% X D 18,972.50
F HARGA SATUAN PEKERJAAN (D+E) 208,697.50
117 A.5.1.1.5 (K3) Pemasangan 1 buah wastafel

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 1.2000 120,000.00 144,000.00
2 Tukang batu L.02 OH 1.4500 150,000.00 217,500.00
3 Kepala Tukang L.03 OH 0.1500 175,000.00 26,250.00
4 Mandor L.04 OH 0.0600 140,000.00 8,400.00
JUMLAH TENAGA KERJA 396,150.00
B BAHAN

1 Wastafel Unit 1.0000 650,000.00 650,000.00


2 Semen Portland Kg 6.0000 1,200.00 7,200.00
3 Pasir Pasang m3 0.0100 137,500.00 1,375.00
4 Perlengkapan % 12.0000 78,000.00 78,000.00

JUMLAH HARGA BAHAN 736,575.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 1,132,725.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 1,132,725.00
37 A.5.1.1.14 Pemasangan 1 buah floor drain

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0100 120,000.00 1,200.00
2 Tukang batu L.02 OH 0.1000 150,000.00 15,000.00
3 Kepala Tukang L.03 OH 0.0100 175,000.00 1,750.00
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 18,650.00
B BAHAN

1 Floor drain stainless stell unit 1.0000 50,000.00 50,000.00

JUMLAH HARGA BAHAN 50,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 68,650.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 68,650.00

119 A.5.1.1.15 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 2.1600 120,000.00 259,200.00
2 Tukang batu L.02 OH 0.7200 150,000.00 108,000.00
3 Kepala Tukang L.03 OH 0.0720 175,000.00 12,600.00
4 Mandor L.04 OH 0.0110 140,000.00 1,540.00
JUMLAH TENAGA KERJA 381,340.00
B BAHAN

1 Bata merah bh 40.0000 1,250.00 50,000.00


2 Semen Portland kg 44.0000 1,200.00 52,800.00
3 Pasir Pasang m3 0.0700 137,500.00 9,625.00
4 Pasir Beton m3 0.0600 137,500.00 8,250.00
5 Kerikil m3 0.0700 155,000.00 10,850.00
6 Baja Tulangan kg 1.6000 11,000.00 17,600.00

JUMLAH HARGA BAHAN 149,125.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 530,465.00


E OVERHEAD & PROFIT 10% X D 53,046.50
F HARGA SATUAN PEKERJAAN (D+E) 583,511.50

120 A.5.1.1.16 Pemasangan 1 buah bak kontrol pasangan bata 45x45 tinggi 50 cm
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 3.2000 120,000.00 384,000.00
2 Tukang batu L.02 OH 1.1500 150,000.00 172,500.00
3 Kepala Tukang L.03 OH 0.0110 175,000.00 1,925.00
4 Mandor L.04 OH 0.0160 140,000.00 2,240.00
JUMLAH TENAGA KERJA 560,665.00
B BAHAN

1 Bata merah bh 70.0000 1,250.00 87,500.00


2 Semen Portland kg 77.0000 1,200.00 92,400.00
3 Pasir Pasang m3 0.1300 137,500.00 17,875.00
4 Pasir Beton m3 0.0900 137,500.00 12,375.00
5 Kerikil m3 0.0200 155,000.00 3,100.00
6 Baja Tulangan kg 2.6000 11,000.00 28,600.00

JUMLAH HARGA BAHAN 241,850.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 802,515.00


E OVERHEAD & PROFIT 10% X D 80,251.50
F HARGA SATUAN PEKERJAAN (D+E) 882,766.50

121 A.5.1.1.17 Pemasangan 1 buah bak kontrol pasangan bata 60x60 tinggi 65 cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 3.2000 120,000.00 384,000.00
2 Tukang batu L.02 OH 1.1500 150,000.00 172,500.00
3 Kepala Tukang L.03 OH 0.0110 175,000.00 1,925.00
4 Mandor L.04 OH 0.0160 140,000.00 2,240.00
JUMLAH TENAGA KERJA 560,665.00
B BAHAN

1 Bata merah bh 123.0000 1,250.00 153,750.00


2 Semen Portland kg 114.0000 1,200.00 136,800.00
3 Pasir Pasang m3 0.1840 137,500.00 25,300.00
4 Pasir Beton m3 0.1200 137,500.00 16,500.00
5 Kerikil m3 0.0330 155,000.00 5,115.00
6 Baja Tulangan kg 4.8500 11,000.00 53,350.00

JUMLAH HARGA BAHAN 390,815.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 951,480.00


E OVERHEAD & PROFIT 10% X D 95,148.00
F HARGA SATUAN PEKERJAAN (D+E) 1,046,628.00

122 A.5.1.1.18 Pemasangan 1 m' pipa galvanis diameter 1/2"

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0540 120,000.00 6,480.00
2 Tukang batu L.02 OH 0.0900 150,000.00 13,500.00
3 Kepala Tukang L.03 OH 0.0090 175,000.00 1,575.00
4 Mandor L.04 OH 0.0270 140,000.00 3,780.00
JUMLAH TENAGA KERJA 25,335.00
B BAHAN

1 Pipa Galvanis 1/2" m 1.2000 24,200.00 29,040.00


2 Perlengkapan Ls 35%xpipa 8,470.00 8,470.00

JUMLAH HARGA BAHAN 37,510.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 62,845.00


E OVERHEAD & PROFIT 10% X D 6,284.50
F HARGA SATUAN PEKERJAAN (D+E) 69,129.50

38 A.5.1.1.19 Pemasangan 1 m' pipa pvc diameter 1/2"

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0540 120,000.00 6,480.00
2 Tukang batu L.02 OH 0.0900 150,000.00 13,500.00
3 Kepala Tukang L.03 OH 0.0090 175,000.00 1,575.00
4 Mandor L.04 OH 0.0270 140,000.00 3,780.00
JUMLAH TENAGA KERJA 25,335.00
B BAHAN

1 Pipa PVC 1/2" m 1.2000 7,500.00 9,000.00


2 Perlengkapan Ls 35%xpipa 2,625.00 2,625.00

JUMLAH HARGA BAHAN 11,625.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 36,960.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 36,960.00
39 A.5.1.1.20 Pemasangan 1 m' pipa pvc diameter 2,5"

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0540 120,000.00 6,480.00
2 Tukang Batu L.02 OH 0.0900 150,000.00 13,500.00
3 Kepala Tukang L.03 OH 0.0090 175,000.00 1,575.00
4 Mandor L.04 OH 0.0270 140,000.00 3,780.00
JUMLAH TENAGA KERJA 25,335.00
B BAHAN

1 Pipa PVC 2,5" m 1.2000 51,150.00 61,380.00


2 Perlengkapan Ls 35%xpipa 17,902.50 17,902.50

JUMLAH HARGA BAHAN 79,282.50


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 104,617.50


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 104,617.50

40 A.5.1.1.20 Pemasangan 1 m' pipa pvc diameter 4"

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0540 120,000.00 6,480.00
2 Tukang Batu L.02 OH 0.0900 150,000.00 13,500.00
3 Kepala Tukang L.03 OH 0.0090 175,000.00 1,575.00
4 Mandor L.04 OH 0.0270 140,000.00 3,780.00
JUMLAH TENAGA KERJA 25,335.00
B BAHAN

1 Pipa PVC 4" m 1.2000 87,500.00 105,000.00


2 Perlengkapan Ls 35%xpipa 30,625.00 30,625.00

JUMLAH HARGA BAHAN 135,625.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 160,960.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 160,960.00
41 Pengecatan 1 m2 waterproffing ( 1 lapis dasar, 1 lapis penutup)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0200 120,000.00 2,400.00
2 Tukang cat L.02 OH 0.0630 150,000.00 9,450.00
3 Kepala Tukang L.03 OH 0.0063 175,000.00 1,102.50
4 Mandor L.04 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 13,372.50
B BAHAN

1 Cat WaterProffing kg 1.0000 60,000.00 60,000.00

JUMLAH HARGA BAHAN 60,000.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 73,372.50


E OVERHEAD & PROFIT 10% X D 7,337.25
F HARGA SATUAN PEKERJAAN (D+E) 80,709.75

127 Pekerjaan 1m2 Pintu Panel Rangka Alumunium + Kaca 5mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0850 120,000.00 10,200.00
2 Tukang besi L.02 OH 0.0850 150,000.00 12,750.00
3 Kepala Tukang L.03 OH 0.0085 175,000.00 1,487.50
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 25,137.50
B BAHAN
1 Alumunium Profil bingkai pintu m1 4.4000 165,000.00 726,000.00
2 Sekrup kg 8.0000 300.00 2,400.00
3 Kaca 5mm m2 1.2000 150,000.00 180,000.00
4 Sealant tube 1.5500 45,000.00 69,750.00
JUMLAH HARGA BAHAN 978,150.00
C PERALATAN
JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 1,003,287.50


E OVERHEAD & PROFIT 10% X D 100,328.75
F HARGA SATUAN PEKERJAAN (D+E) 1,103,616.25

128 Pekerjaan 1m2 Jendela Rangka Alumunium + Kaca 5mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0850 120,000.00 10,200.00
2 Tukang Besi L.02 OH 0.0850 150,000.00 12,750.00
3 Kepala Tukang L.03 OH 0.0085 175,000.00 1,487.50
4 Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 25,137.50
B BAHAN
1 Alumunium Profil bingkai jendela m1 4.4000 95,000.00 418,000.00
2 Sekrup kg 8.0000 300.00 2,400.00
3 Kaca 5mm m2 1.2000 150,000.00 180,000.00
4 Sealant tube 1.5500 45,000.00 69,750.00
JUMLAH HARGA BAHAN 670,150.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 695,287.50


E OVERHEAD & PROFIT 10% X D 69,528.75
F HARGA SATUAN PEKERJAAN (D+E) 764,816.25

42 Pekerjaan 1m2 Kaca 5mm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0150 120,000.00 1,800.00
2 Tukang Besi L.02 OH 0.1500 150,000.00 22,500.00
3 Kepala Tukang L.03 OH 0.0150 175,000.00 2,625.00
4 Mandor L.04 OH 0.0008 140,000.00 112.00
JUMLAH TENAGA KERJA 27,037.00
B BAHAN

1 Kaca 5mm m2 1.2000 150,000.00 180,000.00


2 Sealant tube 0.0400 45,000.00 1,800.00
JUMLAH HARGA BAHAN 181,800.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 208,837.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 208,837.00
43 Pekerjaan 1m2 rangka Plafond besi hollow 2 x 4 & 4x 4

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1500 120,000.00 18,000.00
2 Tukang Besi L.02 OH 0.2500 150,000.00 37,500.00
3 Kepala Tukang L.03 OH 0.0250 175,000.00 4,375.00
4 Mandor L.04 OH 0.0025 140,000.00 350.00
JUMLAH TENAGA KERJA 60,225.00
B BAHAN
1 Besi hollow galvanis 2x4 btg 0.5500 28,000.00 15,400.00
2 Besi hollow galvais 4x4 btg 0.5500 36,000.00 19,800.00
3 sekrup bh 4.0000 300.00 1,200.00
4 Kawat gantungan kg 0.0500 25,000.00 1,250.00
JUMLAH HARGA BAHAN 37,650.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 97,875.00


E OVERHEAD & PROFIT 10% X D 9,787.50
F HARGA SATUAN PEKERJAAN (D+E) 107,662.50

44 Pekerjaan 1m2 rangka atap baja ringan

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1500 120,000.00 18,000.00
2 Tukang Besi L.02 OH 0.2500 150,000.00 37,500.00
3 Kepala Tukang L.03 OH 0.0250 175,000.00 4,375.00
4 Mandor L.04 OH 0.0025 140,000.00 350.00
JUMLAH TENAGA KERJA 60,225.00
B BAHAN
1 a. Main Truss C.75-0,75 btg 0.8250 80,000.00 66,000.00
2 b. Reng R 33-0,45 btg 0.8250 40,000.00 33,000.00
3 c. Skrup Truss dia. 6-20 mm bh 8.0000 400.00 3,200.00
4 d. Skrup reng dia 4-16 mm bh 4.0000 400.00 1,600.00
5 e. Dynabol dia. 12-120 mm bh 0.5000 850.00 425.00
JUMLAH HARGA BAHAN 104,225.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 164,450.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 164,450.00
45 Pekerjaan 1 titik instalasi Listrik biasa

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.0450 120,000.00 5,400.00
2 Tukang Listrik L.02 OH 0.4500 160,000.00 72,000.00
3 Kepala Tukang L.03 OH 0.0450 175,000.00 7,875.00
4 Mandor L.04 OH - 140,000.00 -
JUMLAH TENAGA KERJA 85,275.00
B BAHAN
1 Kabel NYM 2 x 2,5 mm m1 8.0000 11,750.00 94,000.00
2 accecories ls 1.0000 7,500.00 7,500.00
-
JUMLAH HARGA BAHAN 101,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 186,775.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 186,775.00

46 Pekerjaan 1 titik lampu SL- 8 watt + Fitting Downlight Dia.15cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2000 120,000.00 24,000.00
2 Tukang Listrik L.02 OH 0.0200 160,000.00 3,200.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH - 140,000.00 -
JUMLAH TENAGA KERJA 30,700.00
B BAHAN
1 Lampu SL 8 Watt bh 1.0000 49,000.00 49,000.00
2 Fitting Downlight dia. 15cm bh 1.0000 35,000.00 35,000.00
-
JUMLAH HARGA BAHAN 84,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 114,700.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 114,700.00
47 Pekerjaan 1 titik lampu SL- 18 watt + Fitting Downlight Dia.15cm

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.2000 120,000.00 24,000.00
2 Tukang Listrik L.02 OH 0.0200 160,000.00 3,200.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH - 140,000.00 -
JUMLAH TENAGA KERJA 30,700.00
B BAHAN
1 Lampu SL 18 Watt bh 1.0000 82,000.00 82,000.00
2 Fitting Downlight dia. 15cm bh 1.0000 35,000.00 35,000.00
-
JUMLAH HARGA BAHAN 117,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 147,700.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 147,700.00

48 Pekerjaan 1 titik saklar tunggal/engkel

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1000 120,000.00 12,000.00
2 Tukang Listrik L.02 OH 0.0200 160,000.00 3,200.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH - 140,000.00 -
JUMLAH TENAGA KERJA 18,700.00
B BAHAN

1 Sakelar tunggal/engkel bh 1.0000 20,000.00 20,000.00


-
JUMLAH HARGA BAHAN 20,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 38,700.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 38,700.00
49 Pekerjaan 1 titik saklar seri/double

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1000 120,000.00 12,000.00
2 Tukang Listrik L.02 OH 0.0200 160,000.00 3,200.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH - 140,000.00 -
JUMLAH TENAGA KERJA 18,700.00
B BAHAN

1 Sakelar seri/double bh 1.0000 25,000.00 25,000.00


-
JUMLAH HARGA BAHAN 25,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 43,700.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 43,700.00

50 Pekerjaan 1 titik stop kontak

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1000 120,000.00 12,000.00
2 Tukang Listrik L.02 OH 0.0200 160,000.00 3,200.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH - 140,000.00 -
JUMLAH TENAGA KERJA 18,700.00
B BAHAN

1 stop kontak bh 1.0000 22,500.00 22,500.00


-
JUMLAH HARGA BAHAN 22,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 41,200.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 41,200.00
51 Pekerjaan 1 titik box panel pvc - mcb 4 grup

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1000 120,000.00 12,000.00
2 Tukang Listrik L.02 OH 0.0200 160,000.00 3,200.00
3 Kepala Tukang L.03 OH 0.0200 175,000.00 3,500.00
4 Mandor L.04 OH - 140,000.00 -
JUMLAH TENAGA KERJA 18,700.00
B BAHAN

1 box MCB 6 grup- panel PVC bh 1.0000 150,000.00 150,000.00


2 MCB 6A bh 2.0000 85,000.00 170,000.00
JUMLAH HARGA BAHAN 320,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 338,700.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 338,700.00

52 Pekerjaan 1m2 rangka Plafond besi hollow 2 x 4 & 4x 4

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 Pekerja L.01 OH 0.1500 120,000.00 18,000.00
2 Tukang Besi L.02 OH 0.2500 160,000.00 40,000.00
3 Kepala Tukang L.03 OH 0.0250 175,000.00 4,375.00
4 Mandor L.04 OH 0.0025 140,000.00 350.00
JUMLAH TENAGA KERJA 62,725.00
B BAHAN
1 Besi hollow galvanis 2x4 m 2.2000 9,700.00 21,340.00
2 Besi hollow galvais 4x4 m 2.2000 17,000.00 37,400.00
3 sekrup bh 4.0000 600.00 2,400.00
4 Kawat gantungan kg 0.0500 15,000.00 750.00
JUMLAH HARGA BAHAN 61,890.00
C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 124,615.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 124,615.00

53 A.4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (1200x2400x9mm)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 TENAGA 0 OH 0.100 120,000.00 12,000.00
2 Pekerja L.01 OH 0.050 160,000.00 8,000.00
3 Tukang Besi L.02 OH 0.005 175,000.00 875.00
4 Kepala Tukang L.03 OH 0.005 140,000.00 700.00
JUMLAH TENAGA KERJA 21,575.00
B BAHAN

1 Gypsumboard 9mm lembar 0.3630 85,000.00 30,855.00


2 Paku skrup kg 0.1100 25,000.00 2,750.00
3 Dempul semen kg 1.0000 2,300.00 2,300.00

JUMLAH HARGA BAHAN 35,905.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 57,480.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 57,480.00

54 A.4.5.1.7 Pemasangan 1 m2 langit-langitGRC board ukuran (1200x2400x4mm)

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (RP) JUMLAH HARGA (RP)

A TENAGA
1 TENAGA 0 OH 0.100 120,000.00 12,000.00
2 Pekerja L.01 OH 0.050 160,000.00 8,000.00
3 Tukang Besi L.02 OH 0.005 175,000.00 875.00
4 Kepala Tukang L.03 OH 0.005 140,000.00 700.00
JUMLAH TENAGA KERJA 21,575.00
B BAHAN

1 GRC 4mm lembar 0.3630 75,000.00 27,225.00


2 Paku skrup kg 0.1100 25,000.00 2,750.00
3 Dempul semen kg 1.0000 2,300.00 2,300.00

JUMLAH HARGA BAHAN 32,275.00


C PERALATAN

JUMLAH HARGA ALAT -

D JUMLAH )A+B+C) 53,850.00


E OVERHEAD & PROFIT 10% X D
F HARGA SATUAN PEKERJAAN (D+E) 53,850.00
DAFTAR HARGA SATUAN JADI
ENGINEERING ESTIMATE
REHABILITASI RUMAH DINAS
#NAME?

NO URAIAN PEKERJAAN UPAH BAHAN HARGA SATUAN

1 Pengukuran dan Pemasangan 1 m' Bouwplank 25,000.00 52,250.00 77,250.00


2 Penggalian 1 m3 tanah biasa sedalam 1 meter' 90,000.00 90,000.00
3 Penggalian 1 m3 tanah biasa sedalam 2 meter' 100,000.00 100,000.00
4 Pengurugan kembali 1m3 galian tanah 50,000.00 50,000.00
5 Pengurugan 1 m3 dengan pasir urug 50,000.00 165,000.00 215,000.00
7 Pengurugan 1 m3 Tanah Urug 50,000.00 78,000.00 128,000.00
8 (K3) Pemasangan 1 m3 batu kosong (aanstamping) 164,385.00 239,400.00 403,785.00
9 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 4 PP 316,125.00 447,100.00 763,225.00
12 Merangkai besi beton 10 kg 20,685.00 118,500.00 139,185.00
13 Merangkai besi beton 1 kg 2,068.50 11,850.00 13,918.50
Membuat 1 m3 beton mutu f'c = 9,8 MPa (K-125) 200,000.00 634,892.31 834,892.31
14 Membuat 1 m3 beton mutu f'c = 16,9 MPa (K-175) 200,000.00 719,486.54 919,486.54
34 Membuat 1 m3 beton mutu f'c = 21,7 MPa (K-250) 200,000.00 755,300.00 955,300.00
35 Membuat 1 m2 bekisting pondasi 100,000.00 114,000.00 214,000.00
36 Membuat 1 m2 bekisting sloof 100,000.00 127,750.00 227,750.00
37 Membuat 1 m2 bekisting kolom 115,000.00 144,500.00 259,500.00
38 Membuat 1 m2 bekisting balok 115,000.00 152,750.00 267,750.00
39 Membuat 1 m2 bekisting plat 115,000.00 226,500.00 341,500.00
40 Membuat 1 m2 bekisting tangga 115,000.00 210,000.00 325,000.00
41 Membuat 1 m' kolom praktis beton bertulang (11x11) cm 45,000.00 54,670.00 99,670.00
42 Membuat 1 m' ring balok beton bertulang (10x15) cm 45,000.00 59,312.50 104,312.50
54 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/ 50,000.00 110,244.00 160,244.00
55 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/ 50,000.00 105,303.50 155,303.50
60 Pemasangan 1 m2 plesteran campuran 1 SP : 5 PP tebal 15 30,000.00 9,795.80 39,795.80
63 Pemasangan 1 m2 acian 20,000.00 3,900.00 23,900.00
64 Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 40 cm x 40 50,000.00 102,947.50 152,947.50
66 Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20 cm x 20 50,000.00 108,667.50 158,667.50
68 Pemasangan 1 m1 plint ubin PC abu-abu ukuran 10 cm x 40 26,575.00 39,442.17 66,017.17
71 Pemasangan 1 m2 Dinding Keramik 20 cm x 25 cm 75,000.00 102,116.25 177,116.25
82 Pemasangan 1 m2 rangka plafond hollow 4 x 4 35,000.00 61,890.00 96,890.00
83 Pemasangan 1 m2 plafond gibsum 9mm 15,000.00 35,905.00 50,905.00
84 Pemasangan 1 m2 plafond GRC 4mm 15,000.00 32,275.00 47,275.00
86 Pemasangan 1 m2 atap seng Alumunium gelombang 20,000.00 38,860.00 58,860.00
95 Pemasangan 1 m' lisplank GRC uk (6 mm x 30 cm) 25,000.00 28,400.00 53,400.00
106 Pengecatan interior 1 m2 tembok 15,000.00 23,650.00 38,650.00
111 Pengecatan eksterior 1 m2 tembok 17,000.00 36,400.00 53,400.00
112 Pengecatan plafond 1 m2 tembok 15,000.00 23,650.00 38,650.00
111 Pemasangan 1 buah kloset duduk porselen 200,000.00 1,808,575.00 2,008,575.00
114 Pemasangan 1 buah floor drain 10,000.00 50,000.00 60,000.00
118 Pemasangan 1bh Wasatafel set 200,000.00 736,575.00 936,575.00
119 Pemasangan 1 m' pipa pvc diameter 1/2" 15,000.00 11,625.00 26,625.00
120 Pemasangan 1 m' pipa pvc diameter 2" 15,000.00 79,282.50 94,282.50
121 Pemasangan 1 m' pipa pvc diameter 4" 20,000.00 135,625.00 155,625.00
125 Pekerjaan 1m2 Kaca 5mm 25,000.00 181,800.00 206,800.00
126 Pekerjaan 1m2 rangka Plafond besi hollow 2 x 4 & 4x 4 35,000.00 61,890.00 96,890.00
127 Pekerjaan 1m2 penutup plafond gibsum 9mm 15,000.00 35,905.00 50,905.00
128 Pekerjaan rangka + plafond gibsum 9mm 50,000.00 97,795.00 147,795.00
129 Pekerjaan 1m2 penutup plafond grc 9mm 15,000.00 32,275.00 47,275.00
130 Pekerjaan rangka + plafond GRC 4mm 50,000.00 94,165.00 144,165.00
129 Pekerjaan 1m2 rangka atap baja ringan 45,000.00 104,225.00 149,225.00
130 Pekerjaan 1 titik instalasi Listrik biasa 75,000.00 101,500.00 176,500.00
131 Pekerjaan 1 titik lampu SL- 18 watt + Fitting Downlight Dia.15cm 10,000.00 117,000.00 127,000.00
132 Pekerjaan 1 titik lampu SL- 8 watt + Fitting Downlight Dia.15cm 10,000.00 84,000.00 94,000.00
133 Pekerjaan 1 titik saklar tunggal/engkel 10,000.00 20,000.00 30,000.00
134 Pekerjaan 1 titik saklar seri/double 10,000.00 25,000.00 35,000.00
135 Pekerjaan 1 titik stop kontak 10,000.00 22,500.00 32,500.00
136 Pekerjaan 1 titik box panel pvc - mcb 4 grup 10,000.00 320,000.00 330,000.00
KOP
PERHITUNGAN VOLUME PEKERJAAN
ENGINEERING ESTIMATE
REHABILITASI RUMAH DINAS
#NAME?

NO URAIAN PEKERJAAN PANJANG LEBAR


I 2 3 4

1 Pekerjaan Rangka Atap baja Ringan


a (rangka atap ruangan dapur belakang) 8.14 2.75
1.35 3.6

2 Pekerjaan Penutup Atap Seng Gelombang


a ( atap ruangan dapur belakang) 8.14 2.75
1.35 3.6
b ( atap bagian depan) 1.8 9.14

3 Pekerjaan Talang Pipa PVC 2,5 inci

4 Rangka Plafond
(plafond dapur belakang) 8.14 2.75
1.35 3.6

5 Pekerjaan Penutup Plafond


a (plafond dapur belakang) 8.14 2.75
1.35 3.6
b bangunan utama interior
rg.tamu 1 2.61
4.86 2.86
kamar 1 3.86 2.86
kamar 2 3.86 2.86
rg antara 1.86 1.86
km/wc 1.86 1.86

c bagian eksterior
teras 2.86 1.75
depan 5.14 1
kiri 9.5 1
kanan 9.5 1

6 PekerjaanProfil Kayu SP4


rg. Tamu
kamar 1
kamar 2
rg. Antara
km/wc
dapur
ekterior depan
eksterior kiri
eksterior kanan

7 Pekerjaan Kusen Kayu Klas II


PVJ 16.25 1
PV1 6.9 3
PV2 6.9 1
PB
P1 5.1 2
P2 5 1
JVR
VR
JV1 5.9 4
V1 7.95 1

90.600 0.13
39 Pekerjaan Pengecatan Kusen,pintu,jendela dan ventilasi
KUSEN
PVJ 16.250
PV1 20.700
PV2 6.900
P1 10.200
P2 5.000
JV1 23.600
V1 7.950
90.600 0.295

PINTU
PVJ 3.78
PV1 10.08
PV2 3.36
P1 6.72
P2 1.47

JENDELA
PVJ 0.56
JV1 2.24

VENTILASI
PVJ 2.6
PV1 2.4
PV2 0.8
JV1 2.8
V1 2.6
11.2 0.36

JUMLAH

40 Pekerjaan Keramik Lantai 40 x 40 cm


Rg. Antara 3.4596
dapur 28.125
jumlah

41 Pekerjaan keramik Lantai 20 x 20 cm


42 Pekerjaan Keramik Dinding 20 x 25 cm
43 Pekerjaan keramik Meja beton 40 x 40
44 Pekerjaan Pas. Closed jongkok set
45 Pekerjaan Pas. Wastafel + mata kran wastafel
46 Pekerjaan Pas. mata kran
47 Pekerjaan Floor drain
48 Pekerjaan Cermin uk. 100 x 60 cm
49 Pekerjaan instalasi air kotor Pipa PVC 2 inci
OP
OLUME PEKERJAAN
NG ESTIMATE
RUMAH DINAS
AME?

TINGGI BANYAKNYA JUMLAH


5 6 7.000

22.385
4.86
jumlah 27.245

22.385
4.86
16.452
jumlah 43.697

10
3
3
jumlah 16.000

104.1
22.385
4.86
jumlah 27.245

22.385
4.86 4
6.468
2.61 5
13.8996
11.0396 6.468
11.0396 228
3.4596
3.4596 30
jumlah 72.753 5
5.005
5.14
9.5
9.5
jumlah 29.145

17.44
13.44
13.44
7.44
7.44
26.17
16
20.6
20.6
jumlah 142.570

16.250
20.700
6.900
5.1 1 0.000
10.200
5.000
1.44 2 0.000
0.32 2 0.000
23.600
7.950
90.600
0.05 0.5889 m3

26.727 m2
25.41 m2

2.8 m2

4.032 m2

58.969 m2

31.5846
2.85
2.85
0.9

0.9
7.5
RENCANA ANGGARAN BIAYA
PEMBANGUNAN RUKO RING ROAD
NO PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH

UPAH BAHAN JUMLAH UPAH BAHAN JUMLAH


1 2 3 4 5 6 7 8=3X5 9=3X6 10 = 3 X 7

A PEKERJAAN PERSIAPAN 8,171,500


1 Pembersihan Lokasi 1 ls 1,000,000 1,000,000 1,000,000 - 1,000,000
2 Pemasangan Papan Proyek/IMB 1 ls 500,000 500,000 500,000 - 500,000
3 Pemasangan pagar penutup area proyek 1 ls 750,000 1,750,000 2,500,000 750,000 1,750,000 2,500,000
4 Pekerjaan Pemasangan Bouplank 54 m1 25,000 52,250 77,250 1,350,000 2,821,500 4,171,500

B PEKERJAAN GALIAN DAN URUGAN 8,463,150


1 Galian Tanah Pondasi Telapak 28.125 m3 100,000 100,000 2,812,500 - 2,812,500
2 Galian Tanah Pondasi jalur 29.68 m3 90,000 90,000 2,671,200 - 2,671,200
3 Urugan Tanah Kembali 17.3415 m3 50,000 50,000 867,075 - 867,075
4 Urugan Pasir Bawah Pondasi 2.7 m3 50,000 165,000 215,000 135,000 445,500 580,500
5 Urugan Pasir Bawah Lantai 7.125 m3 50,000 165,000 215,000 356,250 1,175,625 1,531,875

C PEKERJAAN PONDASI DAN BETON BERTULANG 340,808,238


1 Pekerjaan Pasangan Batu Kosong 9.66 m3 164,385 239,400 403,785 1,587,959 2,312,604 3,900,563
2 Pekerjaan Pasangan Pondasi batu kali 24.84 m3 316,125 447,100 763,225 7,852,545 11,105,964 18,958,509
3 Pekerjaan Pondasi Telapak -
a Pekerjaan Bekisting 48 m2 100,000 114,000 214,000 4,800,000 5,472,000 10,272,000
b Pekerjaan Pembesian 538.272 kg 2,069 11,850 13,919 1,113,416 6,378,523 7,491,939
c Pekerjaan Cor Beton mutu K 250 8.5875 m3 200,000 755,300 955,300 1,717,500 6,486,139 8,203,639
4 Pekerjaan Sloof -
a Pekerjaan Bekisting 46.2 m2 100,000 127,750 227,750 4,620,000 5,902,050 10,522,050
b Pekerjaan Pembesian 555.324 kg 2,069 11,850 13,919 1,148,688 6,580,589 7,729,277
c Pekerjaan Cor Beton mutu K 250 4.62 m3 200,000 755,300 955,300 924,000 3,489,486 4,413,486
5 Pekerjaan Kolom lantai 1 -
a Pekerjaan Bekisting 71.68 M2 115,000 144,500 259,500 8,243,200 10,357,760 18,600,960
b Pekerjaan Pembesian 1316.412 KG 2,069 11,850 13,919 2,722,998 15,599,482 18,322,480
c Pekerjaan Cor Beton mutu K 250 4.704 m3 200,000 755,300 955,300 940,800 3,552,931 4,493,731
6 Pekerjaan Balok Lantai 2 -
a Pekerjaan Bekisting 78.28 m2 115,000 152,750 267,750 9,002,200 11,957,270 20,959,470
b Pekerjaan Pembesian 1427.58 kg 2,069 11,850 13,919 2,952,949 16,916,823 19,869,772
c Pekerjaan Cor Beton mutu K 250 7.21 m3 200,000 755,300 955,300 1,442,000 5,445,713 6,887,713
7 Pekerjaan Plat Lantai 2 -
a Pekerjaan Bekisting 126 m2 115,000 226,500 341,500 14,490,000 28,539,000 43,029,000
b Pekerjaan Pembesian 2473.8 kg 2,069 11,850 13,919 5,117,055 29,314,530 34,431,585
c Pekerjaan Cor Beton mutu K 250 17.1 m3 200,000 755,300 955,300 3,420,000 12,915,630 16,335,630
8 Pekerjaan Tangga -
a Pekerjaan Bekisting 11.39 m2 115,000 210,000 325,000 1,309,850 2,391,900 3,701,750
b Pekerjaan Pembesian 197.7304 kg 2,069 11,850 13,919 409,005 2,343,105 2,752,111
c Pekerjaan Cor Beton mutu K 250 2.0502 m3 200,000 755,300 955,300 410,040 1,548,516 1,958,556
9 Pekerjaan Balok Latei atas kusen 30 m1 45,000 59,313 104,313 1,350,000 1,779,375 3,129,375
10 Pekerjaan Kolom Praktis Lantai 1 25.6 m1 45,000 54,670 99,670 1,152,000 1,399,552 2,551,552
11 Pekerjaan Kolom Praktis Lantai 2 57.6 m1 45,000 54,670 99,670 2,592,000 3,148,992 5,740,992
12 Pekerjaan Kolom Lantai 2 -
a Pekerjaan Bekisting 49.5 m2 115,000 144,500 259,500 5,692,500 7,152,750 12,845,250
b Pekerjaan Pembesian 468.747 kg 2,069 11,850 13,919 969,603 5,554,652 6,524,255
c Pekerjaan Cor Beton mutu K 250 2.4 m3 200,000 755,300 955,300 480,000 1,812,720 2,292,720
13 Pekerjaan Balok atap -
a Pekerjaan Bekisting 58.4 m2 115,000 152,750 267,750 6,716,000 8,920,600 15,636,600
b Pekerjaan Pembesian 589.11 kg 2,069 11,850 13,919 1,218,574 6,980,954 8,199,528
c Pekerjaan Cor Beton mutu K 250 1.971 m3 200,000 755,300 955,300 394,200 1,488,696 1,882,896
14 Pekerjaan Plat atap -
a Pekerjaan Bekisting 20 m2 115,000 226,500 341,500 2,300,000 4,530,000 6,830,000
b Pekerjaan Pembesian 347.2 kg 2,069 11,850 13,919 718,183 4,114,320 4,832,503
c Pekerjaan Cor Beton mutu K 250 2.4 m3 200,000 755,300 955,300 480,000 1,812,720 2,292,720
14 Pekerjaan ring balok atap 50 m1 45,000 59,313 104,313 2,250,000 2,965,625 5,215,625

D PEKERJAAN DINDING 124,748,257


1 Pekerjaan pasangan dinding bata 306.3 m2 50,000 105,304 155,304 15,315,000 32,254,462 47,569,462
2 Pekerjaan Plesteran 612.6 m2 30,000 9,796 39,796 18,378,000 6,000,907 24,378,907
3 Pekerjaan Acian 612.6 m2 20,000 3,900 23,900 12,252,000 2,389,140 14,641,140
4 Pekerjaan Pengecatan interior 336.93 m2 15,000 23,650 38,650 5,053,950 7,968,395 13,022,345
5 Pekerjaan Pengecatan exterior 275.67 m2 17,000 36,400 53,400 4,686,390 10,034,388 14,720,778
6 Pekerjaan Pengecatan Plafond 142.5 m2 15,000 23,650 38,650 2,137,500 3,370,125 5,507,625
7 Pekerjaan Waterprofing 20 m2 17,000 36,400 53,400 340,000 728,000 1,068,000
8 Pekerjaan Pasangan batu alam 12.8 m2 75,000 225,000 300,000 960,000 2,880,000 3,840,000

E PEKERJAAN PLAFOND 27,990,300


1 Pekerjaan Rangka & plafond akustik 120 m2 - - - -
2 Pekerjaan Rangka Plafond Gibsum 165 m2 50,000 97,795 147,795 8,250,000 16,136,175 24,386,175
3 Pekerjaan Rangka Plafond GRC 25 m2 50,000 94,165 144,165 1,250,000 2,354,125 3,604,125

F PEKERJAAN ATAP 39,293,563


1 Pekerjaan Rangka atap baja ringan 157.5 m2 45,000 104,225 149,225 7,087,500 16,415,438 23,502,938
2 Pekerjaan Penutup atap 157.5 m2 15,000 68,750 83,750 2,362,500 10,828,125 13,190,625
3 Pekerjaan Lisplank GRC 30 cm 52 m1 15,000 35,000 50,000 780,000 1,820,000 2,600,000
G PEKERJAAN PINTU DAN JENDELA 71,431,500
1 Pekerjaan kusen alumunium 102.5 m1 35,000 85,000 120,000 3,587,500 8,712,500 12,300,000
2 Pekerjaan Pintu alumunium 3 bh 250,000 2,250,000 2,500,000 750,000 6,750,000 7,500,000
3 Pekerjaan Jendela alumunium 8 unit 50,000 350,000 400,000 400,000 2,800,000 3,200,000
4 Pekerjaan Kaca mati 32.5 m2 25,000 181,800 206,800 812,500 5,908,500 6,721,000
5 Pekerjaan pintu Harmonika 36.27 m2 250,000 900,000 1,150,000 9,067,500 32,643,000 41,710,500

H PEKERJAAN LANTAI 55,830,458


1 Pekerjaan Pengecoran Lantai dasar K-175 9.975 m3 200,000 719,487 919,487 1,995,000 7,176,878 9,171,878
2 Pekerjaan Pasangan Lantai keramik 40 x 40 285 m2 50,000 102,948 152,948 14,250,000 29,340,038 43,590,038
3 Pekerjaan Pasangan keramik lantai wc 20x20 3.6 m2 50,000 108,668 158,668 180,000 391,203 571,203
4 Pekerjaan Pasangan keramik dinding wc 20 x 25 14.1 m2 75,000 102,116 177,116 1,057,500 1,439,839 2,497,339

I PEKERJAAN KAMAR MANDI DAN INSTALASI AIR 26,767,080


1 Pekerjaan Pas. Closed duduk 2 bh 200,000 1,808,575 2,008,575 400,000 3,617,150 4,017,150
2 Pekerjaan Pas. Wastafel 2 bh 200,000 736,575 936,575 400,000 1,473,150 1,873,150
3 Pekerjaan floor drain 2 titik 10,000 50,000 60,000 20,000 100,000 120,000
4 Pekerjaan mata kran 5 titik 10,000 65,000 75,000 50,000 325,000 375,000
5 Pekerjaan Roof drain 1 titik 10,000 50,000 60,000 10,000 50,000 60,000
6 Pekerjaan instalasi air 1/2 inci 20 m1 15,000 11,625 26,625 300,000 232,500 532,500
7 Pekerjaan instalasi air limbah 4 inci 12 m1 15,000 79,283 94,283 180,000 951,390 1,131,390
8 Pekerjaan instalasi air limbah 2 inci 22 m1 20,000 135,625 155,625 440,000 2,983,750 3,423,750
9 Pekerjaan Penampungan air fiber 1 unit 150,000 1,500,000 1,650,000 150,000 1,500,000 1,650,000
10 Pekerjaan instalasi pompa set 1 unit 250,000 2,500,000 2,750,000 250,000 2,500,000 2,750,000
11 Pekerjaan septik tank dan resapan - - - -
a Pekerjaan Galian 12.5 m3 100,000 100,000 1,250,000 - 1,250,000
b pengecoran lantai kerja 0.4 m3 255,770 634,892 890,662 102,308 253,957 356,265
c Pekerjaan biofil 1 unit 350,000 5,750,000 6,100,000 350,000 5,750,000 6,100,000
d Pekerjaan Pasangan dinding bata 10.5 m2 50,000 110,244 160,244 525,000 1,157,562 1,682,562
e Pekerjaan batu dasar 1.8 m3 164,385 239,400 403,785 295,893 430,920 726,813
f Pekerjaan urugan pasir 0.9 m3 50,000 165,000 215,000 45,000 148,500 193,500
g Pekerjaan lapisan ijuk 0.45 m3 250,000 500,000 750,000 112,500 225,000 337,500
h pekerjaan urugan kembali tanah 3.75 m3 50,000 50,000 187,500 - 187,500

J PEKERJAAN INSTALASI LISTRIK 17,075,000


1 Pekerjaan Panel Listrik 1 unit 500,000 2,500,000 3,000,000 500,000 2,500,000 3,000,000
2 Pekerjaan instalasi listrik 38 titik 75,000 101,500 176,500 2,850,000 3,857,000 6,707,000
3 Pekerjaan Stop kontak 6 bh 10,000 22,500 32,500 60,000 135,000 195,000
4 Pekerjaan saklar 5 bh 10,000 25,000 35,000 50,000 125,000 175,000
5 Pekerjaaan lampu led 15 watt 30 titik 10,000 117,000 127,000 300,000 3,510,000 3,810,000
6 Pekerjaan Lampu led 5 watt 2 titik 10,000 84,000 94,000 20,000 168,000 188,000
7 Pekerjaan Lampu backdrop plafond 2 titik - - - -
8 Pekerjaan lampu sorot exterior 3 titik - - - -
9 Pekerjaan Penangkal Petir 1 titik 500,000 2,500,000 3,000,000 500,000 2,500,000 3,000,000

K PEKERJAAN AKHIR 1,000,000


1 Pekerjaan Pembersihan 1 ls 1,000,000 1,000,000 1,000,000 - 1,000,000
- - -

232,280,332 489,298,713 721,579,045


REKAPITULASI RENCANA ANGGARAN BIAYA (R-RAB)
ENGINEERING ESTIMATE
#NAME?
#NAME?

NO URAIAN PEKERJAAN JUMLAH


I 2 6
A PEKERJAAN PERSIAPAN Rp 8,171,500.00
B PEKERJAAN GALIAN DAN URUGAN Rp 8,463,150.00
C PEKERJAAN PONDASI DAN BETON BERTULANG Rp 340,808,237.71
D PEKERJAAN DINDING Rp 124,748,256.63
E PEKERJAAN PLAFOND Rp 27,990,300.00
F PEKERJAAN ATAP Rp 39,293,562.50
G PEKERJAAN PINTU DAN JENDELA Rp 71,431,500.00
H PEKERJAAN LANTAI Rp 55,830,457.85
I PEKERJAAN KAMAR MANDI DAN INSTALASI AIR Rp 26,767,079.92
J PEKERJAAN INSTALASI LISTRIK Rp 17,075,000.00
K PEKERJAAN AKHIR Rp 1,000,000.00

JUMLAH Rp 721,579,044.61
PPN 10 %
JUMLAH TOTAL Rp 721,579,044.61
DIBULATKAN Rp 721,579,044.61
TERBILANG
LUAS LT 1 135 M2
LT 2 142.5 M2
JUMLAH 277.5 M2 Rp 2,600,284.85
HARGA/M2
MANADO, 8 MARET 2018
CV. L'COMER CONSULTANT

Rp 14.29
Rp 142.50
Rp 50,000.00
JEMMY V. ROGI,ST Rp 7,125,000.00
DIREKTUR
GALIAN TELAPAK Rp 250,000 TITIK
GALIAN PONDASI Rp 150,000 M1
TIMBUNAN TANAH Rp 25,000 M2
COR LANTAI DASAR Rp 50,000 M2
COR SLOOF BESI MAL Rp 75,000 M1
COR KOLOM BESI MAL Rp 150,000 M1
COR KOLOM PRAKTIS Rp 50,000 M1
COR BALOK PLAT BESI MAL Rp 150,000 M1
PASANG MAL UNTUK PLAT Rp 200,000 M2 125000 150000
PASANG BATA Rp 60,000 M2 45000
PLESTER Rp 30,000 M2 25000
ACI Rp 20,000 M2 15000
PLESTER ACI DINDING LUAR Rp 75,000 M2
PASANG ATAP Rp 45,000 M2

KOLOM 35 35 0.1225 M2
0.001608
1.312392

BALOK 25 40 0.1
0.001407
1.40672

SLOOF 20 X 30 0.06
0.000678
1.1304

KOLOM 25 X 25 0.0625
0.000904
1.446912

BALOK 20 X 30 0.06
0.000804
1.339733

BALOK PRAKTIS 0.015


0.000251
1.674667

11.34 57000
14
0.62 8.68
98.4312
10000 86800
984312