3. PEKERJAAN PENGUNCI PAVING Perhitungan Volume Pekerjaan + Acian Perhitungan Kebutuhan Volume Bahan/ Upah :
SNI 6.39 (7)
0.15 Sloof Beton , 1 PC : 2 PS : 3 Kr
Volume = 90 x 0.15 x 0.35 = 4.7 M³ Koral/Seplit = 0.78 x 4.73 = 3.69 M³
0.15
33
4. PEKERJAAN PAVING BLOCK
Pasir = 0.121 x 396 = 47.9 M³
= 48.000 M³
Luas = 33 x 12 = 396 m2 Paving = 50.00 x 396 = 19,800 Buah
= 19,800 Buah
12 = 396 m2 Pekerja = 0.248 x 396 .= 98.2 Hok
99.0 Hok
Tukang = 0.200 x 396 = 79.2 Hok
= 80.0 Hok
33 ###
###
5.
Dibuat oleh:
###
Tanggal survei :
RENCANA ANGGARAN BIAYA PRASARANA
Propinsi : No. RAB :
Kabupaten : Program :
Kecamatan : Jenis Kegiatan :
Desa : Ukuran/dimensi : 12 x 33
2. PERALATAN -
2.1.Tali spat 1 buah 10,000 10,000 10,000
Sub Total 2) 10,000 10,000
3. UPAH -
3.1. Pekerja 107 107 Oh 80,000 8,560,000 8,560,000
3.2. Tukang 103 103 Oh 100,000 10,300,000 10,300,000
- -
Sub Total 3) 18,860,000 18,860,000
5. LAIN -LAIN - -
5.1. Papan Proyek 1 1 Bh 100,000 100,000 100,000
Sub Total 5) 100,000 100,000
APBN
Sumber Dana PADes 74,007,730
TOTAL BIAYA 74,007,730