PENANGANAN REPLACEMENT MAIN ROAD (AREA TIMBUNAN)

PROYEK JALAN TOL PEKANBARU - DUMAI SEKSI-2D

PENANGANAN
LOKASI
TINGGI Replacement DASAR
NO PANJANG TIMBUNAN PANJANG GEOTEX GEOTEX PER COUNTER- PRE- KETERANGAN
TEBAL PASIR KEPUTUSAN
MAX DALAM TANAH PVD (m) DASAR 1m WEIGHT LOADING
AWAL ~ AKHIR GRANULAR
GALIAN (m) TIMBUNAN

1 12+953 ~ 13+307 354 10.24 0.50 WOVEN WOVEN 3 bln JUSTEK

2 13+200 ~ 13+307 107 10.24 0.50 WOVEN WOVEN JUSTEK

3 13+572 ~ 13+639 67 6.73 1.00 WOVEN WOVEN JUSTEK

4 14+047 ~ 14+128 81 7.46 1.00 WOVEN WOVEN 3.8 bln JUSTEK

14+809 ~ 15+000 191 8.98 1.00 WOVEN WOVEN 4.1 bln JUSTEK
REPLACEMENT DAN TIMBUNAN
5 15+000 ~ 15+125 125 8.39 1.00 9m jarak 1m 0.50 NON WOVEN WOVEN
UNTUK MERATAKAN EXISTING
5.4 bln JUSTEK
15+125 ~ 15+148 23 6.71 1.00 WOVEN WOVEN

6 15+189 ~ 15+268 79 9.20 1.00 WOVEN WOVEN 3 layer Konsultan

15+588 ~ 15+625 37 6.75 1.00 WOVEN WOVEN


REPLACEMENT DAN TIMBUNAN
7 15+625 ~ 15+650 25 7.68 1.00 12m jarak 1m 1.00 NON WOVEN WOVEN 4 bln JUSTEK
UNTUK MERATAKAN EXISTING
15+650 ~ 15+681 31 7.68 1.00 WOVEN WOVEN

8 15+986 ~ 16+113 127 7.80 2.00 WOVEN WOVEN 2.3 bln JUSTEK

9 16+400 ~ 16+525 125 12.31 2.50 NON WOVEN WOVEN 4.7 bln JUSTEK

10 16+629 ~ 16+679 50 4.54 0.70 WOVEN RTA

11 16+794 ~ 16+823 29 2.51 0.90 WOVEN RTA

12 16+921 ~ 16+938 17 1.87 0.90 WOVEN RTA

13 17+233 ~ 17+350 117 8.14 2.50 NON WOVEN WOVEN per 1.2m JUSTEK

14 17+350 ~ 17+562 212 8.14 2.50 NON WOVEN WOVEN JUSTEK

15 17+632 ~ 17+704 72 5.71 1.00 WOVEN WOVEN 3 layer Konsultan

16 17+787 ~ 17+810 23 3.59 0.60 WOVEN RTA

17 17+854 ~ 17+977 123 5.71 0.60 WOVEN RTA

18 18+432 ~ 18+492 60 6.99 0.50 WOVEN RTA

19 18+694 ~ 18+780 86 8.05 1.50 WOVEN WOVEN 3 layer Konsultan

20 19+206 ~ 19+479 273 6.39 1.00 WOVEN RTA

21 19+699 ~ 19+888 189 9.10 2.50 NON WOVEN WOVEN JUSTEK

22 20+046 ~ 20+149 103 5.97 1.00 WOVEN RTA


KONSULTAN SUPERVISI KONTRAKTOR DIAJUKAN OLEH, DIPERIKSA DAN DISETUJUI MENGETAHUI SHOP DRAWING NO. GAMBAR :
PEMBANGUNAN JALAN TOL
Digambar Basuki Rahmat JUDUL GAMBAR :
PEKANBARU - DUMAI
INOVASI UNTUK SOLUSI
TRANSSUMATERA SEKSI - 2
STA. 9+500 ~ STA. 33+600
egis INFRA STRUKTUR
Diperiksa R. Kresnoharijotejo

Tanggal
Anas Firmanto, ST
Project Manager
Ir. Rosihan Anwar, MT
Project Engineer
Bambang Hendrarto
Pimpinam Proyek
STRIPMAP PENANGANAN TIMBUNAN STA 12+950 ~ 16+600
SKALA : NTS

REVISI :
Jalan Tol Pekanbaru - Dumai

13 307
12 953

13 572

13 639
247.34 106.89
67.34

(JUSTEK) 12+975 - 13+200 (JUSTEK) 13+200 - 13+300 (JUSTEK) 13+575 - 13+650


Replacement Tanah hasil galian 50cm Replacement Tanah hasil galian 50cm Replacement tanah 100-200cm
Dasar timbunan Geotex Woven Dasar timbunan Geotex Woven Dasar timbunan dgn Geotex Woven
Geotex woven per 1 m Geotex woven per 1 m Geotex woven per 1 m
Preloading 5m (U90=0.15m T90=9.8bln) 225.00m L = 100.00m Preloading (U90=0.11m T90=2.25 bln)

12+950 13+000 13+100 13+200 13+300 13+400 13+500 13+600 13+700 13+800 13+900

14 047

14 126

14 809
78.31

(JUSTEK) 14+050 - 14+150


Geotex Woven dasar timbunan
Replc Tanah hasil galian 1 m
Geotex Woven per 1 meter
Preloading 5,1m , T= 1 bln
Preloading 5,5m ; T= 1b
(U90=43cm, T90 = 3.84 thn)

13+900 14+000 14+100 14+200 14+300 14+400 14+500 14+600 14+700 14+800

15 189
14 809

15 148

15 268

15 588

15 681
191.13 125.00 23.31
78.74 36.88 25.00 30.72

(JUSTEK) 15+000 - 15+125


(JUSTEK) 14+825 - 15+000 Geotex non woven dasar timb
15+200 - 15+250
Replc Tanah hasil galian 1 m + Geotex woven dasar timbunan Sand Platform tebal 0,5m
Dasar timbunan dgn Geotex Woven Dasar timbunan dgn Geotex Woven
Timb dgn Geotex Woven per 1 meter PVD spasi 1m, panjang 9m, pola segi empat
Geotex woven per 1 m, 3 layer Geotex woven per 1 m + preloading
Preloading 5,5m ; T= 1bln (U90=0.31m, T90 =4.85 Bln) Geotex woven per 1m
Preloading 6,5m ; T= 2bln (U90=0.81 m, T90=5.4 bln) 1 layer
14+800 14+900 15+000 15+100 15+200 15+300 15+400 15+500 15+600 15+700
15+125 - 15+150 · (JUSTEK) 15+625 - 15650 PVD t=12m Dasar timbunan dgn Geotex Woven
Penggunaan Geotex 1 lapis
Dasar timbunan dgn Geotex Woven ,replacement tanah organik dengan tanah timbunan Geotex woven per 1 m + preloading
Geotex woven per 1 m agar dibackup dengan · geotex non woven pada dasar timbunan
justifikasi teknis konsultan · pasir 50cm, geotex woven per 1m + preloading

Granular 1m
15 681

15 986

16 113

16 400

16 525

16 629
30.72 127.14 125.32

(JUSTEK) 15+986 - 16+113 (JUSTEK) 16+400 - 16+525 (RTA)


Replcement Tanah hasil galian 2 m Replcement Granular 2.5 m Replacement Tanah hasil galian, 70
Geotex woven dasar timbunan Geotex non woven dasar timbunan sesuai DCP min 2 %
Geotex Woven per 1 meter Geotex Woven per 1 meter Geotex woven pada dasar Timbun
Preloading Preloading Preload 3 m , T= 2bln

15+700 15+800 15+900 16+000 16+100 16+200 16+300 16+400 16+500 16+600
Dasar timbunan dgn Geotex Woven
Geotex woven per 1 m + preloading
REVISI : 26 NOV 2019 UPDATE : 16 NOV 2019 ·
·
KONSULTAN SUPERVISI KONTRAKTOR DIAJUKAN OLEH, DIPERIKSA DAN DISETUJUI MENGETAHUI SHOP DRAWING NO. GAMBAR :
PEMBANGUNAN JALAN TOL
Digambar Basuki Rahmat JUDUL GAMBAR :
PEKANBARU - DUMAI
INOVASI UNTUK SOLUSI
TRANSSUMATERA SEKSI - 2
STA. 9+500 ~ STA. 33+600
egis INFRA STRUKTUR
Diperiksa R. Kresnoharijotejo

Tanggal
Anas Firmanto, ST
Project Manager
Ir. Rosihan Anwar, MT
Project Engineer
Bambang Hendrarto
Pimpinam Proyek
STRIPMAP PENANGANAN TIMBUNAN STA 16+600 ~ 20+250
SKALA : NTS

REVISI :
Jalan Tol Pekanbaru - Dumai

16 629

16 679

16 794

16 823

16 921

16 938

17 233
166.94 166.70
49.52 29.81 17.41

(RTA) 16+650 - 16+700


(RTA) 16+800 (RTA) 16+945 (JUSTEK) 17+233 & 17+400 (JUSTEK) 17+450 & 17+525
Replacement Tanah hasil galian, 70cm
Replacement Tanah hasil galian, 90cm Replacement Tanah hasil galian, 90cm Replacement granular 250cm Replacement granular 250cm
sesuai DCP min 2 %
sesuai DCP min 2 % sesuai DCP min 2 % Geotextile non woven pada dasar Timbunan Geotextile non woven pada dasar Timbunan
Geotex woven pada dasar Timbunan
Geotex woven pada dasar Timbunan Geotex woven pada dasar Timbunan Geotextile woven per 1 meter Geotextile woven per 1 meter
Preload 3 m , T= 2bln
L = 32.7m L = 27.81m
L=33.2m

16+600 16+700 16+800 16+900 17+000 17+100 17+200 17+300 17+400 17+500
Sampai tanah Sampai tanah Sampai tanah
organik hilang organik hilang organik hilang
17 567

17 632

17 704

17 787

17 811

17 854

17 977

18 432
166.70
72.31 23.30 123.32

geotex per 1m

17+650
17+450 & 17+525 (RTA) 17+800 (RTA) 17+950 (RTA)
Replacement granular 100cm sesuai dcp 2%
Replacement granular 250cm Replacement Tanah hasil galian,60cm Replacement Tanah hasil galian, 60cm Replacement tanah hasil galian 50cm
Geotextile non woven pada dasar Timbunan
Geotextile non woven pada dasar Timbunan sesuai DCP min 2% sesuai dcp min 2% L=127.00m Geotextile non woven dasar Timbunan
Geotextile woven per 1 meter, 3 layer
Geotextile woven per 1 meter Geotex woven dasar Timbunan Geotex woven dasar Timbunan L=127.00m preload 3.50m, t=3bln
Counterweight

17+500 17+600 17+700 17+800 17+900 18+000 18+100 18+200 18+300 18+400
· Agar dilakukan DCP dengan kedalaman
Replacement tanah lebih dari 1m (±2.5m) Sampai tanah Sampai tanah
hasil galian 1-2m · Penggunaan Geotex agar dibackup dengan organik hilang organik hilang
justifikasi teknis konsultan
18 432

18 492

18 694

18 780

19 206
60.60 86.51 272.28

geotex per 1m geotex per 1m

(RTA) 18+425 18+700 ~ 18+800 (RTA) 19+225 ~ 19+500


Replacement tanah hasil galian 50cm Replacement granular 150cm Replacement tanah hasil galian 150cm Replacement Tanah hasil galian 100cm
Geotextile non woven dasar Timbunan Geotextile non woven dasar Timbunan (sampai tanah organik hilang) Geotex woven dasar Timbunan
preload 3.50m, t=3bln Geotextile woven per 1 meter, 3 layer Preloading h=2m T:2bln, 150.00m

18+400 18+500 18+600 18+700 18+800 18+900 19+000 19+100 19+200 19+300
Sampai tanah · DCP ulang
organik hilang · Penggunaan Geotex 3 layer agar dibackup
dengan justifikasi teknis konsultan

20 048

20 149
19 479

19 699

19 888
272.28 189.17 100.41

geotex per 1m

(RTA) 20+100
(RTA) 19+225 ~ 19+500 (JUSTEK) 19+775 Replacement Tanah hasil galian 100cm
Replacement Tanah hasil galian 100cm Replacement Granular 250cm sesuai dcp min 2%
Geotex woven dasar Timbunan Geotex non woven dasar Timbunan Geotex woven dasar Timbunan
Preloading h=2m T:2bln, 150.00m Geotex woven per 1 meter Preloading h:3m T:3.5bln
L =76.5m

19+300 19+400 19+500 19+600 19+700 19+800 19+900 20+000 20+100 20+200 20+250

REVISI : 26 NOV 2019 UPDATE : 16 NOV 2019 ·


·