Anda di halaman 1dari 7

REKAPITULASI

HARGA PERKIRAAN SENDIRI (HPS)

PEKERJAAN : PERENCANAAN RUMAH TINGGAL PERMANEN


INSTANSI : 99 M2
LOKASI : DISTRIK-MERAUKE, KABUPATEN-MERAUKE
T.A : 2019

JUMLAH HARGA
NO JENIS PEKERJAAN
(Rp)

#REF! PEKERJAAN PERSIAPAN 25,522,722.37


#REF! PEKERJAAN TANAH 6,507,815.88
#REF! PEKERJAAN STRUKTUR 181,248,559.64
#REF! PEKERJAAN ARSITEKTUR 232,818,071.18
V PEKERJAAN INSTALASI LISTRIK 6,381,784.00
VI PEKERJAAN SANITASI 22,889,160.80
VII PEKERJAAN FINISING 1,000,000.00
REAL COST = 476,368,113.87
DIBULATKAN = 476,300,000.00
Terbilang :
EMPAT RATUS TUJUH PULUH ENAM JUTA TIGA RATUS RIBU RUPIAH,-

MERAUKE, MEI 2020


DISIAPKAN OLEH :

……………………………………
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PERENCANAAN RUMAH TINGGAL PERMANEN
TYPE : 99 M2
LOKASI : DISTRIK-MERAUKE, KABUPATEN-MERAUKE
TA : 2019

HARGA
JUMLAH HARGA
No URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
I PEKERJAAN PERSIAPAN
2 Pengukuran dan Pas. Bouwplank 25.00 m1 84,530.00 2,113,250.00
3 Camp Darurat Kontsruksi Kayu 12.00 m2 567,019.00 6,804,228.00
5 Pek. Timbunan+ Pemadatan 94.72 m3 175,318.00 16,605,244.37
JUMLAH 25,522,722.37
SUB TOTAL I 25,522,722.37
II PEKERJAAN TANAH
1.1 Galian Tanah Pondasi 14.45 m3 126,000.00 1,820,070.00
1.2 Urugan Tanah Kembali 4.82 m3 35,000.00 168,525.00
1.3 Urugan Pasir Bawah Pondasi 4.09 m3 1,104,269.00 4,519,220.88
JUMLAH 6,507,815.88
SUB TOTAL I 6,507,815.88
III PEKERJAAN STRUKTUR
A PONDASI
1.1 Poer Plat (PR2) Uk. 1 X 1 M
1.7.1 Cor beton Camp. 1Pc:2Ps:3Kr 1.57 m3 2,954,457.00 4,645,883.63
1.7.2 Bekisting 2x Pakai 8.00 m2 239,523.00 1,916,184.00
1.7.3 Besi beton dia 14 247.85 kg 17,443.00 4,323,329.55
1.7.4 Besi beton dia 8 22.10 kg 17,389.00 384,216.22
JUMLAH 11,269,613.39

1.3 Pondasi Menerus 30/80/100 Camp. 1Pc:4Ps 46.48 m3 1,877,492.00 87,256,440.70


JUMLAH 87,256,440.70
B. SLOEF
1. Sloef type S1 (15X20)
1.1 Cor beton Camp. 1Pc:2Ps:3Kr 2.54 m3 2,954,457.00 7,489,548.50
1.2 Bekisting 3x pakai 8.45 m2 263,846.00 2,229,498.70
1.3 Besi beton dia 8 144.47 kg 17,434.00 2,518,772.27
1.4 Besi beton dia. 12 300.06 kg 17,571.00 5,272,404.86

JUMLAH 17,510,224.33
C. KOLOM
1. Pekerjaan Kolom Beton
1.1 Kolom KL2 (30X30)
1.1.1 Cor beton Camp. 1Pc:2Ps:3Kr 0.95 m3 2,954,457.00 2,791,961.87
1.1.2 Bekisting 2X pakai 4.20 m2 263,846.00 1,108,153.20
1.1.3 Besi beton dia. 8 63.52 kg 17,434.00 1,107,480.21
1.1.4 Besi beton dia.12 50.28 kg 17,571.00 883,517.79
JUMLAH 5,891,113.06
1.2 Kolom KL2 (25x25)
1.1.1 Cor beton Camp. 1Pc:2Ps:3Kr 0.44 m3 2,954,457.00 1,292,574.94
1.1.2 Bekisting 2X pakai 3.50 m2 263,846.00 923,461.00
1.1.3 Besi beton dia. 8 14.73 kg 17,434.00 256,807.00
1.1.4 Besi beton dia.12 37.29 kg 17,571.00 655,150.90
JUMLAH 3,127,993.84
1.3 Kolom KL2 (20x20)
1.1.1 Cor beton Camp. 1Pc:2Ps:3Kr 1.12 m3 2,954,457.00 3,308,991.84
1.1.2 Bekisting 2X pakai 11.20 m2 263,846.00 2,955,075.20
1.1.3 Besi beton dia. 8 58.92 kg 17,434.00 1,027,228.02
1.1.4 Besi beton dia.12 149.14 kg 17,571.00 2,620,603.60
JUMLAH 9,911,898.66
1.4 Kolom praktis type KP (13X13)
1.2.1 Cor beton Camp. 1Pc:2Ps:3Kr 1.35 m3 2,954,457.00 3,994,425.86
1.2.2 Bekisting 2X pakai 6.93 m2 263,846.00 1,829,332.27
1.2.3 Besi beton dia. 8 98.90 kg 17,434.00 1,724,275.60
1.2.4 Besi beton dia.10 197.28 kg 17,389.00 3,430,501.92
JUMLAH 10,978,535.65

D. RING BALOK RB(15x20)


1.1 Ring Balok 15/20
1.1.1 Cor beton Camp. 1Pc:2Ps:3Kr 1.97 m3 2,954,457.00 5,809,939.69
1.1.2 Bekisting 2X pakai 13.11 m2 263,846.00 3,459,021.06
1.1.3 Besi beton dia. 8 11.38 kg 17,434.00 198,397.17
1.1.4 Besi beton dia.12 161.65 kg 17,389.00 2,810,867.51
JUMLAH 12,278,225.43
D. RING BALOK RB(15x45)
1.1 Ring Balok 15/20
1.1.1 Cor beton Camp. 1Pc:2Ps:3Kr 0.61 m3 2,954,457.00 1,794,832.63
1.1.2 Bekisting 2X pakai 4.05 m2 263,846.00 1,068,576.30
1.1.3 Besi beton dia. 8 26.04 kg 17,434.00 453,998.10
1.1.4 Besi beton dia.12 63.92 kg 17,389.00 1,111,482.62
JUMLAH 4,428,889.65
D. RING BALOK RB(15x35)
1.1 Ring Balok 15/20
1.1.1 Cor beton Camp. 1Pc:2Ps:3Kr 0.47 m3 2,954,457.00 1,395,980.93
1.1.2 Bekisting 2X pakai 3.15 m2 263,846.00 831,114.90
1.1.3 Besi beton dia. 8 22.73 kg 17,434.00 396,216.52
1.1.4 Besi beton dia.12 47.94 kg 17,389.00 833,611.97
JUMLAH 3,456,924.32
D. BALOK B(20x40)
1.1 Balok 20/40
1.1.1 Cor beton Camp. 1Pc:2Ps:3Kr 0.80 m3 2,954,457.00 2,363,565.60
1.1.2 Bekisting 2X pakai 5.00 m2 263,846.00 1,319,230.00
1.1.3 Besi beton dia. 8 22.62 kg 17,434.00 394,382.18
1.1.4 Besi beton dia.12 79.90 kg 17,571.00 1,403,894.79
JUMLAH 5,481,072.57
D. PEKERJAAN PLAT BETON TALANG
1. Plat Dak
1.1 Bekisting 7.48 m2 263,846.00 1,972,248.85
1.2 Besi beton dia.10 61.44 kg 17,389.00 1,068,458.41
1.3 Cor Beton Pasir Import T=10 cm 0.52 m3 2,954,457.00 1,545,919.63
JUMLAH 4,586,626.89
D. PEKERJAAN PLAT DAK
1. Plat Dak
1.1 Bekisting 6.00 m2 263,846.00 1,583,076.00
1.2 Besi beton dia.10 98.64 kg 17,389.00 1,715,250.96
1.3 Cor Beton Pasir Import T=10 cm 0.60 m3 2,954,457.00 1,772,674.20
JUMLAH 5,071,001.16
SUB TOTAL II 181,248,559.64
IV PEKERJAAN ARSITEKTUR
A. PEKERJAAN LANTAI
1. Lantai
1.1 Pekerjaan Urugan Pasir, t = 5 cm 2.99 m3 1,104,269.00 3,302,868.58
1.2 Cor Lantai T=5 cm Pasir Import 4.99 m3 2,954,457.00 14,727,968.15
1.3 Pas. Keramik Uk. 60 x 60 83.00 m2 504,431.00 41,867,773.00
1.4 Pas. Keramik Uk. 40 x 40 16.70 m2 374,409.00 6,252,630.30
1.5 Pas. Dinding Keramik KM/WC Uk. 20x40 17.40 m2 305,440.00 5,314,656.00
JUMLAH 71,465,896.02
C. PEKERJAAN DINDING DAN PELAPIS DINDING

1.1 Pas. dind. batu bata 1/2 bt camp.1:4 Pasir lokal 260.17 m2 158,930.00 41,348,818.10
1.2 Plesteran dinding 1 : 4 Pasir lokal 15 mm 520.34 m2 95,346.00 49,612,337.64
1.4 Pas. Batu Alam 4.88 m2 231,630.00 1,130,354.40
JUMLAH 92,091,510.14
D. PEKERJAAN KAYU, PINTU DAN VENTILASI
2 Ventilasi kayu Kls III 1.52 m2 639,778.00 972,462.56
3 Pintu Panel 14.41 m2 914,428.00 13,176,907.48
4 Jendela 6.00 m2 914,428.00 5,486,568.00
5 Kusen Pintu dan Jendela kayu Kls III 0.62 m3 7,747,093.00 4,819,311.61
6 Kunci Tanam 2 Sloot 8.00 Bh 69,500.00 556,000.00
7 Engsel Pintu 8.00 Bh 50,229.00 401,832.00
8 Engsel Jendela 9.00 Bh 39,454.00 355,086.00
9 Grendel Jendela 9.00 Bh 42,800.00 385,200.00
10 Kait Angin 9.00 Bh 25,999.00 233,991.00
JUMLAH 26,387,358.65
E. PEKERJAAN ATAP
1 Atap Almunium Gelombang 150.30 M2 110,864.00 16,663,358.09
2 Nok Atap Almunium 26.40 m1 78,978.00 2,085,019.20
3 Lisplank Ukuran (2 x 20) cm, Kayu Kelas III 44.30 m1 46,771.00 2,071,955.30
4 Kuda-kuda Kayu 4/8 (ky. Kls III) 1.20 m3 6,047,940.00 7,269,140.04
5 Gording Kayu 4/8 (ky. Kls III) 0.64 m3 4,832,095.00 3,095,633.34
7 Plafon tripek 3mm 93.20 m2 56,997.00 5,312,120.40
8 Rangka plafon 93.20 m2 114,855.00 10,704,486.00
JUMLAH 31,185,105.97
F. PEKERJAAN PENGECATAN

1 Pekerjan cat dinding 520.34 m2 20,894.00 10,871,983.96


2 Pekerjaan cat listplank 11.08 m2 73,699.00 816,216.43
JUMLAH 11,688,200.39
SUB TOTAL IV 232,818,071.18
V PEKERJAAN INSTALASI LISTRIK
1 MCB 1.00 bh 334,985.00 334,985.00
2 Lampu Down Light 18 watt 14.00 bh 204,241.00 2,859,374.00
3 Saklar Tunggal 6.00 bh 252,993.00 1,517,958.00
4 Saklar Ganda 3.00 bh 256,679.00 770,037.00
5 Stop Kontak 7.00 bh 128,490.00 899,430.00
JUMLAH 6,381,784.00
SUB TOTAL V 6,381,784.00
VI PEKERJAAN SANITASI
1 Septick Tank
1.1 Pengukuran dan Pemasangan Bowplang 8.00 m' 84,530.00 676,240.00
1.2 Galian Tanah 5.63 m3 126,000.00 708,750.00
1.3 Urugan Tanah Kembali 1.88 m3 35,000.00 65,625.00
1.4 Pasangan Batu Bata 14.25 m2 158,930.00 2,264,752.50
1.5 Cor Plat atas Tebal 10 cm Beton 1Pc:2Ps:3Kr 0.38 m3 2,954,457.00 1,107,921.38
1.6 Tulangan Plat Penutup 30.83 kg 17,389.00 536,015.93

2 Kloset Duduk 2.00 bh 1,325,480.00 2,650,960.00


3 Floor Drain 2.00 bh 15,000.00 30,000.00
4 Pipa 4" 12.00 m' 553,460.00 6,641,520.00
5 Pipa 3/4" 12.00 m' 164,066.00 1,968,792.00
6 Pek. Talang Air Hujan 24.00 m' 259,941.00 6,238,584.00

JUMLAH 22,889,160.80
SUB TOTAL VI 22,889,160.80
VII PEKERJAAN FINISING
1 Pembersihan 1.00 ls 1,000,000.00 1,000,000.00
JUMLAH 1,000,000.00
SUB TOTAL VII 1,000,000.00
DAFTAR HARGA SATUAN BAHAN
PEKERJAAN : PERENCANAAN RUMAH TINGGAL PERMANEN

LOKASI : DISTRIK-MERAUKE, KABUPATEN-MERAUKE


TAHUN ANGGARAN : 2019

Harga Satuan
No. Nama Bahan/Barang Satuan on Site Project
(Tanpa PPN)
1 2 4 13

A. BAHAN BAKAR DAN PENCAMPUR


1 Solar Industri Liter 12,238.00
2 Minyak Tanah Industri Liter 10,785.00
3 Minyak Pelumas / Olie Liter 34,885.00
4 Minyak Bekisting / Oli Bekas Buah 500.00
5 Residu / Teer Liter 25,043.00

B. BAHAN PASIR, BATU DAN SEMEN


1 Pasir semen (Import) M3 1,125,000.00
2 Pasir semen (Pasang-lokal) M3 500,000.00
3 Pasir semen ayakan/ halus (lokal) M3 500,000.00
4 Tanah timbun biasa/urug M3 125,000.00
5 Tanah pilihan (Selmat) M3 125,000.00
6 Batu kerikil/ koral beton (Import) M3 1,125,000.00
8 Batu bata merah Buah 800.00
11 Semen Portland (PC) @ 50 Kg Zak 95,000.00
12 Semen PC Putih / Warna Zak 136,666.00
13 Tepung Gypsum Zak 95,000.00

C. BAHAN KAYU, TRIPLEKS DLL


1 Balok Kayu Kelas III (Kayu Bus) M3 2,750,000.00
2 Balok Kayu Kelas II (Kayu Rahay) M3 4,000,000.00
3 Balok Kayu Kelas I (Kayu Besi) M3 7,000,000.00
4 Balok Kayu Kelas IV (Kayu Putih, Susu, dll) M3 2,500,000.00
5 Papan Kayu Kelas III (Kayu Bus) t = 2-5 cm M3 2,500,000.00
6 Papan Kayu Kelas II (Kayu Rahay) t = 2 cm M3 4,500,000.00
7 Papan Kayu Kelas II (Kayu Rahay) t = 3 cm M3 4,500,000.00
8 Papan Kayu Kelas I (Kayu Besi) t = 2 - 3 cm M3 7,500,000.00
9 Papan Kayu Kelas IV (tebal = 2-5 cm) M3 2,250,000.00
16 Tiang Kayu Bulat (Dia 20 cm, L=4-6 m) Batang 125,000.00
17 Kayu dolken Ø 8-10, L=4 M Kayu Bus Batang 12,500.00
18 Plywood - Multiplex Lembar 450,000.00
18 Tripleks (1,22 x 2,44) cm - tebal 3 mm Lmbr 60,687.00
19 Kaca Polos 5 mm M2 215,500.00
Harga Satuan
No. Nama Bahan/Barang Satuan on Site Project
(Tanpa PPN)
1 2 4 13
D. BAHAN BESI, PAKU DAN KAWAT
1 Besi Beton Dia.8 mm (SNI) Kg 13,967.00
2 Besi Beton Dia.10 mm (SNI) Kg 13,925.00
3 Besi Beton Dia.12 mm (SNI) Kg 14,098.00
4 Besi Beton Dia.14 mm (SNI) Kg 13,976.00
9 Kawat Beton Kg 27,500.00
10 Kawat beton / bindrat 4 mm KG 29,000.00
11 Paku Campur Kg 18,525.00
12 Paku 2" (5 cm) Kg 18,666.00
13 Paku 3" (7 cm) Kg 18,437.00
14 Paku 4" (10 cm) Kg 18,312.00
15 Paku Seng Kg 56,625.00
16 Paku Triplek Kg 19,344.00
17 Kawat Las 0.26 Dos 161,571.00
18 Baut Jembatan Dia. 19 mm Kg 15,000.00
19 Baut Dia, 3/8" - 17.5 + Mur - Ring Buah 4,075.00
20 Baut Dia, 3/8" - 12.0/15.0 + Mur - Ring Buah 3,150.00
21 Baut Dia, 3/8" - 20.0 + Mur - Ring Buah 4,625.00
22 Baut Dia, 3/8" - 35.0 + Mur - Ring Buah 6,000.00
23 Besi angkur dia. 8 mm Buah 10,000.00

E. BAHAN PENUTUP ATAP


1 Genteng Metal - Multiroof Lembar 40,880.00
2 Nok Genteng Metal - Multiroof Lembar 37,213.00
3 Atap Allumunium Gelombang M2 66,380.00
4 Nok Atap Allumunium M 24,380.00

I. BAHAN CAT
1 Amplas Kertas (Amplas Kayu) Lembar 4,500.00
2 Amplas Besi Lembar 4,900.00
3 Kuas Roll Buah 15,000.00
4 Kuas Biasa Buah 10,000.00
5 Cat Meny Kayu Kg 31,320.00
6 Cat Meny Besi Kg 31,391.00
7 Cat Kayu Kg 56,445.00
8 Cat Besi Kg 62,695.00
9 Cat Kilat LN Kg 78,445.00
10 Minyak Cat / Thinner (Setara Lauguer) Kg 30,382.00
11 Palmur Tembok Zak 62,500.00
12 Cat Tembok (1 Klg @ 5 Kg) Kaleng 56,100.00
Lem Fox Kg 35,288.00

J BAHAN KERAMIK
1 Keramik Dinding 20x20 atau 20x25 cm M2 2,950.00
2 Ubin Granito Ukuran 30 x 30 cm BH 6,424.00
3 Keramik Lantai 40 x 40 cm BH 14,473.00
4 Keramik Lantai 60 x 60 cm BH 65,000.00
Batu Paras BH 22,727.00
Batu Tempel Hitam BH 22,727.00

K BAHAN PIPA DAN SANITAIR


1 Closet duduk / monoblok BH 556,714.00
2 Pipa PVC Dia. 4" - 4 Meter (AW) Batang 318,500.00
3 Pipa PVC Dia. 3/4" - 4 M Batang 30,375.00
4 Talang PVC Kotak 4" - 6 Meter Batang 127,125.00
Pipa PVC Dia. 3" - 4 Meter (D) Batang 136,875.00
5 Kran Air 3/4" BH 35,375.00

L BAHAN LISTRIK DAN ELEKTRONIKA


1 Kabel Listrik NYM/NYA 3x2.5 mm M' 1390000
2 Kabel Listrik NYM/NYA 2x1.5 mm M' 846250
3 Pipa Listrik dia, 5/8 Batang 8500
4 Saklar Double - Tempel Buah 18900
Harga Satuan
No. Nama Bahan/Barang Satuan on Site Project
(Tanpa PPN)
1 2 4 13
5 Saklar Tunggal / Engkel - Tempel Buah 15214
6 Stop Kontak 500 Watt - Tempel Buah 20000
7 Stop Kontak 1000 Watt - Tempel Buah 25000
8 Home Saklar 1 Fase Komplit Buah 400000
9 Lampu TL 1 x 40 Watt Komplit Buah 169333
10 Lampu TL 1 x 20 Watt Komplit Buah 102000
11 Lampu Pijar 40 Watt Komplit Buah 7375
12 Lampu Pijar 60 Watt Komplit Buah 7625
13 Lampu Pijar 100 Watt Komplit Buah 9500
14 Vitting Lampu Buah 14750
15 Lampu XL 40 Watt Set 95833
16 Lampu XL 20 Watt Set 50875
17 Lampu SL 23 Watt Set 48250
18 Lampu SL 14 Watt Set 39500
19 Sekring Kas 1 Group (Biasa) Buah 73000
20 Klem Kabel Dus 18833
21 Isolasi Listrik Buah 8571
22 Sekrup Dus 21666
23 Panil Distribusi Buah 12500000