JUMLAH HARGA
NO JENIS PEKERJAAN
(Rp)
……………………………………
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PERENCANAAN RUMAH TINGGAL PERMANEN
TYPE : 99 M2
LOKASI : DISTRIK-MERAUKE, KABUPATEN-MERAUKE
TA : 2019
HARGA
JUMLAH HARGA
No URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
I PEKERJAAN PERSIAPAN
2 Pengukuran dan Pas. Bouwplank 25.00 m1 84,530.00 2,113,250.00
3 Camp Darurat Kontsruksi Kayu 12.00 m2 567,019.00 6,804,228.00
5 Pek. Timbunan+ Pemadatan 94.72 m3 175,318.00 16,605,244.37
JUMLAH 25,522,722.37
SUB TOTAL I 25,522,722.37
II PEKERJAAN TANAH
1.1 Galian Tanah Pondasi 14.45 m3 126,000.00 1,820,070.00
1.2 Urugan Tanah Kembali 4.82 m3 35,000.00 168,525.00
1.3 Urugan Pasir Bawah Pondasi 4.09 m3 1,104,269.00 4,519,220.88
JUMLAH 6,507,815.88
SUB TOTAL I 6,507,815.88
III PEKERJAAN STRUKTUR
A PONDASI
1.1 Poer Plat (PR2) Uk. 1 X 1 M
1.7.1 Cor beton Camp. 1Pc:2Ps:3Kr 1.57 m3 2,954,457.00 4,645,883.63
1.7.2 Bekisting 2x Pakai 8.00 m2 239,523.00 1,916,184.00
1.7.3 Besi beton dia 14 247.85 kg 17,443.00 4,323,329.55
1.7.4 Besi beton dia 8 22.10 kg 17,389.00 384,216.22
JUMLAH 11,269,613.39
JUMLAH 17,510,224.33
C. KOLOM
1. Pekerjaan Kolom Beton
1.1 Kolom KL2 (30X30)
1.1.1 Cor beton Camp. 1Pc:2Ps:3Kr 0.95 m3 2,954,457.00 2,791,961.87
1.1.2 Bekisting 2X pakai 4.20 m2 263,846.00 1,108,153.20
1.1.3 Besi beton dia. 8 63.52 kg 17,434.00 1,107,480.21
1.1.4 Besi beton dia.12 50.28 kg 17,571.00 883,517.79
JUMLAH 5,891,113.06
1.2 Kolom KL2 (25x25)
1.1.1 Cor beton Camp. 1Pc:2Ps:3Kr 0.44 m3 2,954,457.00 1,292,574.94
1.1.2 Bekisting 2X pakai 3.50 m2 263,846.00 923,461.00
1.1.3 Besi beton dia. 8 14.73 kg 17,434.00 256,807.00
1.1.4 Besi beton dia.12 37.29 kg 17,571.00 655,150.90
JUMLAH 3,127,993.84
1.3 Kolom KL2 (20x20)
1.1.1 Cor beton Camp. 1Pc:2Ps:3Kr 1.12 m3 2,954,457.00 3,308,991.84
1.1.2 Bekisting 2X pakai 11.20 m2 263,846.00 2,955,075.20
1.1.3 Besi beton dia. 8 58.92 kg 17,434.00 1,027,228.02
1.1.4 Besi beton dia.12 149.14 kg 17,571.00 2,620,603.60
JUMLAH 9,911,898.66
1.4 Kolom praktis type KP (13X13)
1.2.1 Cor beton Camp. 1Pc:2Ps:3Kr 1.35 m3 2,954,457.00 3,994,425.86
1.2.2 Bekisting 2X pakai 6.93 m2 263,846.00 1,829,332.27
1.2.3 Besi beton dia. 8 98.90 kg 17,434.00 1,724,275.60
1.2.4 Besi beton dia.10 197.28 kg 17,389.00 3,430,501.92
JUMLAH 10,978,535.65
1.1 Pas. dind. batu bata 1/2 bt camp.1:4 Pasir lokal 260.17 m2 158,930.00 41,348,818.10
1.2 Plesteran dinding 1 : 4 Pasir lokal 15 mm 520.34 m2 95,346.00 49,612,337.64
1.4 Pas. Batu Alam 4.88 m2 231,630.00 1,130,354.40
JUMLAH 92,091,510.14
D. PEKERJAAN KAYU, PINTU DAN VENTILASI
2 Ventilasi kayu Kls III 1.52 m2 639,778.00 972,462.56
3 Pintu Panel 14.41 m2 914,428.00 13,176,907.48
4 Jendela 6.00 m2 914,428.00 5,486,568.00
5 Kusen Pintu dan Jendela kayu Kls III 0.62 m3 7,747,093.00 4,819,311.61
6 Kunci Tanam 2 Sloot 8.00 Bh 69,500.00 556,000.00
7 Engsel Pintu 8.00 Bh 50,229.00 401,832.00
8 Engsel Jendela 9.00 Bh 39,454.00 355,086.00
9 Grendel Jendela 9.00 Bh 42,800.00 385,200.00
10 Kait Angin 9.00 Bh 25,999.00 233,991.00
JUMLAH 26,387,358.65
E. PEKERJAAN ATAP
1 Atap Almunium Gelombang 150.30 M2 110,864.00 16,663,358.09
2 Nok Atap Almunium 26.40 m1 78,978.00 2,085,019.20
3 Lisplank Ukuran (2 x 20) cm, Kayu Kelas III 44.30 m1 46,771.00 2,071,955.30
4 Kuda-kuda Kayu 4/8 (ky. Kls III) 1.20 m3 6,047,940.00 7,269,140.04
5 Gording Kayu 4/8 (ky. Kls III) 0.64 m3 4,832,095.00 3,095,633.34
7 Plafon tripek 3mm 93.20 m2 56,997.00 5,312,120.40
8 Rangka plafon 93.20 m2 114,855.00 10,704,486.00
JUMLAH 31,185,105.97
F. PEKERJAAN PENGECATAN
JUMLAH 22,889,160.80
SUB TOTAL VI 22,889,160.80
VII PEKERJAAN FINISING
1 Pembersihan 1.00 ls 1,000,000.00 1,000,000.00
JUMLAH 1,000,000.00
SUB TOTAL VII 1,000,000.00
DAFTAR HARGA SATUAN BAHAN
PEKERJAAN : PERENCANAAN RUMAH TINGGAL PERMANEN
Harga Satuan
No. Nama Bahan/Barang Satuan on Site Project
(Tanpa PPN)
1 2 4 13
I. BAHAN CAT
1 Amplas Kertas (Amplas Kayu) Lembar 4,500.00
2 Amplas Besi Lembar 4,900.00
3 Kuas Roll Buah 15,000.00
4 Kuas Biasa Buah 10,000.00
5 Cat Meny Kayu Kg 31,320.00
6 Cat Meny Besi Kg 31,391.00
7 Cat Kayu Kg 56,445.00
8 Cat Besi Kg 62,695.00
9 Cat Kilat LN Kg 78,445.00
10 Minyak Cat / Thinner (Setara Lauguer) Kg 30,382.00
11 Palmur Tembok Zak 62,500.00
12 Cat Tembok (1 Klg @ 5 Kg) Kaleng 56,100.00
Lem Fox Kg 35,288.00
J BAHAN KERAMIK
1 Keramik Dinding 20x20 atau 20x25 cm M2 2,950.00
2 Ubin Granito Ukuran 30 x 30 cm BH 6,424.00
3 Keramik Lantai 40 x 40 cm BH 14,473.00
4 Keramik Lantai 60 x 60 cm BH 65,000.00
Batu Paras BH 22,727.00
Batu Tempel Hitam BH 22,727.00