1
12/22/2020 Erwin_Rommel (FT_Sipil_UMM) 3
PENDAHULUAN
2
PRINSIP SAMBUNGAN
ALAT SAMBUNG HARUS SAMA ATAU LEBIH
KUAT DARI BAHAN YANG DISAMBUNG
(DIMENSI, MUTU BAHAN, ....)
• BOLT CONNECTION
• WELD CONNECTION
• HIGH STRENGTH BOLT CONNECTION
CATATAN :
TIAP JENIS ALAT SAMBUNG MEMILIKI KEKAKUAN YANG
BERBEDA, SEHINGGA SEBAIKNYA DIGUNAKAN ALAT SAMBUNG
SATU TIPE SAJA PADA JOINT/SAMBUNGAN KONSTRUKSI BAJA
3
Rigidity of Connection Types
7
Erwin_Rommel (FT_Sipil_UMM) 12/22/2020
4
Kapan sambungan diperlukan ?
1. Panjang produksi elemen baja terbatas ;
produksi maks 12 meter, alat transportasi
terbatas ke lokasi site/workshop.
2. Menyalurkan beban-beban dari satu elemen ke
elemen lainnya ; joint balok-kolom, joint pada
rangka, sambungan girder (sambungan sama
kuat or tidak sama kuat).
3. Jika ada perubahan dimensi dan bentuk
penampang ; profil built-up, profil hybrid,
envelope change element
5
12/22/2020 Erwin_Rommel (FT_Sipil_UMM) 11
Required of connection
1. Strength and efficiency
2. Good dactility (jumlah alat sambung
dan jenis nya, stiffness berbeda)
3. Easy to install and work (fabrication
and on-site)
4. Easy to improvement and inspection
6
Bolt Connections
SNI 1729-2015 BAGIAN-J (HALAMAN 111-144)
J-1 & J-3 SAMBUNGAN BAUT
J-2 SAMBUNGAN LAS
7
12/22/2020 Erwin_Rommel (FT_Sipil_UMM) 15
8
12/22/2020 Erwin_Rommel (FT_Sipil_UMM) 17
9
Model kegagalan pada sambungan baut
• Bolt Shearing
• Tension Fracture
• Plate Bearing
• Block Shear
12/22/2020 Erwin_Rommel (FT_Sipil_UMM) 19
P P
P
P
Menumpu pada satu bidang geser
Lap Joint
P P
Bending
10
Sambungan geser pada baut
Possible failure modes
Failure of bolts: single or double shear
Single shear
PSingle Shear f v Abolt P P
Double shear
P/2
PDouble Shear 2 f v Abolt P
P/2
11
GAGAL KOMBINASI GESER DAN TARIK PADA BAUT
P P
P P
Pe
CG CG
Pe
e
e
Eccentricity in the plane of Eccentricity normal to the plane
the faying surface of the faying surface
Direct Shear + Additional Shear due to Direct Shear + Tension and Compression
moment Pe (above and below neutral axis)
12/22/2020 Erwin_Rommel (FT_Sipil_UMM) 24
12
GAGAL KRITIS-SLIP PADA BAUT MUTU TINGGI
13
GAGAL KRITIS-SLIP PADA BAUT MUTU TINGGI
14
GAGAL TUMPU PADA PELAT
SNI 1729;2015
Bagian J3 SPASI DAN JARAK TEPI BAUT
hal 123-133
15
JARAK ANTAR BAUT (s)
SNI 1729;2015
Bagian J3
hal 123-133
SPASI DAN JARAK TEPI BAUT
16
12/22/2020 Erwin_Rommel (FT_Sipil_UMM) 33